Collaborative Planning on 5 London Underground Projects
Mr Daniel Agutter, A2B Excellence
![Page 2: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/2.jpg)
2
1. Set the Scene
2. Collaborative Planning
3. Summary
4. Questions and Answers
Agenda
![Page 3: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/3.jpg)
3
How often do we complete the things we plan to do?
![Page 4: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/4.jpg)
4
100% of the time?90% of the time?
75% of the time?
50% of the time?
![Page 5: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/5.jpg)
5
In Feb 2013, achieved Authority for:
• £350m
•7 year Programme
•Upgrade 72 Underground stations
•Savings Target of 12% to 20%
1. Set the Scene
![Page 6: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/6.jpg)
So, what did we do?
![Page 7: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/7.jpg)
Developed a new delivery strategy: ‘STAKE’
• Went down supply chain
• Supply chain - Continuity of work
• Capable workforce – Quality & Productivity
• Simplified non-adversarial contracts
![Page 8: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/8.jpg)
8
• 1st time LU to perform Client and Principal Contractor role
• Collaborative working and relationships
• …Collaborative Planning
STAKE Delivery Model
![Page 9: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/9.jpg)
9
2. Collaborative Planning
STAGE 1 - Planning in Design
![Page 10: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/10.jpg)
10
STAGE 1 -
Planning in Design
![Page 11: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/11.jpg)
11
STAGE 1 – Planning in Design
![Page 12: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/12.jpg)
12
STAGE 2 – Production Management
![Page 13: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/13.jpg)
13
STAGE 2 – Production Management
![Page 14: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/14.jpg)
14
STAGE 2 – Production Management
• Daily Pre and Post-Shift Meetings
• Weekly Progress Review
• Periodically Review Stage 1
- Divergence
![Page 15: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/15.jpg)
15
STAGE 3 – Process Improvement
• Unachieved activities
• Issue cards recorded
• Contractor Performance - PPC
• Lessons Learned
![Page 16: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/16.jpg)
16
3. Summary – Costs
• Early Contractor Involvement
• Contractor’s time to complete cards
• Planning cards, boards, frames
• Daily, weekly, periodical meeting attendance
![Page 17: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/17.jpg)
17
3. Summary – Benefits
• One Team Approach
• Early Contractor Involvement
• Standardised site management
• PPC increases from 55-60% to 80-90%
![Page 18: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/18.jpg)
18
3. Summary – Benefits
• Highways England: 10-40% improvements in Time and Cost
• Work-site clashes mitigated & maximise opportunities
• Issues identified early
• Transparency of progress, process and interfaces
![Page 19: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/19.jpg)
19
CPTP & ICE
![Page 20: Collaborative Planning on 5 London Underground Projects Mr Daniel Agutter, A2B Excellence.](https://reader035.fdocuments.net/reader035/viewer/2022062217/5697c02d1a28abf838cd9892/html5/thumbnails/20.jpg)
20
4. Questions and Answers