Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-AIA members are available upon request.
This course is registered with AIA CES for continuing professional education. As such, it does not include
content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner ofhandling, using, distributing, or dealing in any material or product.
___________________________________________
Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
@Jana_Owens@brielights@LEDucationNYC
Jana Owens, PEHenderson EngineersKansas City, MO
Brienne Willcock, LCIlluminartDetroit, MI
In this presentation, we will investigate the specification of LED luminaires and ways to communicate design intent through initial concern to construction administration. We will cover how much information is necessary in specs and drawings to facilitate accurate bids and installation, reduce RFI's and maintain design integrity. We will also cover areas of concern where coordination is paramount to a successful project.
ABSTRACT
• Apply specific documenting techniques of LED systems to assist with bidding and construction administration.
• Interpret warranty information to improve owner understanding and advocacy.
• Plan for a specific controls outcome through coordination with design team, manufacturers, and owners.
• Evaluate alternate LED luminaires with specific attention to coordinating compatibility with controls and design.
• Identify potential installation & commissioning pitfalls and steps to overcome them during the design phase.
OUTLINE
IF…The drawings clearly note project controls and design
intent
THEN… I can prove how my LED system should work together
So this should be easy, right?
DocumentEducateResearch
DOCUMENTRESEARCH EDUCATEOwner Comfort
Expectations
Compatibility
Design Collaboration
Luminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Owner Understandingof LED
Contractor Awareness
Warranty
Future
RESEARCHOwner Comfort
Expectations
Compatibility
Design Collaboration
DOCUMENT EDUCATELuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Owner Understandingof LED
Contractor Awareness
Warranty
Future
– Understanding of LED and accessibilityRESEARCH
Owner Comfort
Expectations
Compatibility
Design Collaboration
What do you have at your house? Do you like it? What would you change about it?
– Dimming with LED, color, and the basics
RESEARCHOwner Comfort
Expectations
Compatibility
Design Collaboration
Do we need Architectural Dimming everywhere?
Are we dimming for energy code compliance?
Would our owner be satisfied with ‘Lighting Management Dimming’?
Source: IESNA Lighting Handbook, 9th Edition, (New York; IESNA, 2000), 27-4Perceived Light
Mea
sure
d Lig
ht
– Design for compatibility, not against it
RESEARCHOwner Comfort
Expectations
Compatibility
Design Collaboration
Research dimming compatibility
• Low voltage, 0-10V, DMX, DALI • Discuss with manufacturer’s dimming compatibility • Look for common denominators, build a spec accordingly• Narratives discussed with the owner
RESEARCH
– Scope Creep and LED
RESEARCHOwner Comfort
Expectations
Compatibility
Design Collaboration
Research warranties:
1. Owner expectation of labor coverage 2. Labor costs 3. Catastrophic-failure labor agreement 4. Extended warranty
65%
26%
9%
Extended Warranty27 High Bay manufacturer’s response
Yes No Negotiable
45%
30%
25%
Labor Agreement 27 High Bay manufacturer’s response
Yes No Negotiable
RESEARCH
How do we avoid wasting time during Construction Administration because we have to revisit our intent of dimming and design?
DOCUMENTRESEARCH EDUCATEOwner Comfort
Expectations
Compatibility
Design Collaboration
Luminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Owner Understandingof LED
Contractor Awareness
Warranty
Future
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCH EDUCATEOwner Comfort
Expectations
Compatibility
Design Collaboration
Owner Understandingof LED
Contractor Awareness
Warranty
Document the luminaires you intend to use
• Compatibility with control systems – manufacturer’s approval • Design intent met with luminaire differences (beyond
qualities of light):• Dimensions• Remote vs. integral• Ambient temperature rating
• Warranty review for alternates
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCH EDUCATEOwner Comfort
Expectations
Compatibility
Design Collaboration
Owner Understandingof LED
Contractor Awareness
Warranty
Document your dimming strategy
• List your dimming technology & type• Document common denominators in your sequence of
operations• Include driver types for all luminaires• Dimming requirements should go in your schedule
Clearly indicate dimming type
List dimming intent
If 1% isn’t required: • Consider waiting to verify dimming curves.• Put the responsibility in the contract documents to verify
after the project has bid.
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCH EDUCATEOwner Comfort
Expectations
Compatibility
Design Collaboration
Owner Understandingof LED
Contractor Awareness
Warranty
LED dimming has significant commissioning standards/requirements.
DOCUMENT
Document commissioning requirements in specifications.
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCH EDUCATEOwner Comfort
Expectations
Compatibility
Design Collaboration
Owner Understandingof LED
Contractor Awareness
Warranty
Document through the Contract Drawings
• Remote and integral drivers notated on plans• Ventilation, max distances, dimensions
• Consider a separate luminaire type designation for dimmable luminaires
Sequence of Operations
• Easier for owner to read and understand• Function is for end users, not engineers• Notes should include all assumptions and outcomes in
detail• Focus on If/THEN statements
Vital information is not buried in a schedule.
Sequences can be read and understood by your owner.
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCH EDUCATEOwner Comfort
Expectations
Compatibility
Design Collaboration
Owner Understandingof LED
Contractor Awareness
Warranty
Documentation is critical to make the Construction Administration process successful
luminaires selectedduring conceptualdesign.
luminaires reselectedduring final design.
luminaires ordered and installed.
Are my luminaire selections still valid?
1. Lumen outputs change rapidly2. Optics change3. Model numbers get updated4. Wattage or VA values will change5. Driver technology will innovate
Pay attention to the minutiae:• Check new bins/tolerances• Did your drivers or chip manufacturer change? • What about phosphor? Did you have chip on
board? Remote Phosphor?
Clearly identify in your luminaire schedule what is important to you.
• List details of everything
DOCUMENT
Consider the application. • Is remote a necessity? • Is there a temperature controlled driver location?
Conversely, did you spec an integral driver because there was no place to mount it?
Coordinate your drawings across your basis of design.
If driver changes (remote vs. integral) during CA: • Require contractor to suggest an applicable driver location• Ask manufacturer for voltage drop and wire size chart• Verify ventilation and ambient temperatures• Verify aesthetics with architect• Verify driver quantity for field-cuttable luminaires
DOCUMENT
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCH EDUCATEOwner Comfort
Expectations
Compatibility
Design Collaboration
Owner Understandingof LED
Contractor Awareness
Warranty
Document for the future
• Maintenance materials• Control interface and commissioning• Overview of LED system • Review the WARRANTY!
DOCUMENT
EDUCATEOwner Understanding
of LED
Contractor Awareness
Warranty
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCHOwner Comfort
Expectations
Compatibility
Design Collaboration
EDUCATEOwner Understanding
of LED
Contractor Awareness
Warranty
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCHOwner Comfort
Expectations
Compatibility
Design Collaboration
Educate owners about their investment
…time, maintenance, monetary commitment.
EDUCATE
Educate on the differences between traditional technologies and LEDs.
1. Relamping mindset2. Define end of life3. Replacement time frame
SOURCE: DOE Building Technologies Program, Solid State Lighting Technology Fact Sheet
SOURCE: DOE Building Technologies Program, Solid State Lighting Technology Fact Sheet
EDUCATEOwner Understanding
of LED
Contractor Awareness
Warranty
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCHOwner Comfort
Expectations
Compatibility
Design Collaboration
Educate about the warranty and focus on common denominator information if there are several manufacturers.
EDUCATE
Warranty fine print is rarely conveyed to the owner. They could violate their warranty without the correct information.
Seriously, would you read this?
1. Warranty duration 2. Environmental Condition (In-situ)
1. Moisture2. Maximum rated temperature3. Electrical (control compatibility, surge protection)4. Ventilation
3. What’s the first step in pursuing a warranty?
EDUCATE
EDUCATEOwner Understanding
of LED
Contractor Awareness
Warranty
DOCUMENTLuminaire Performance
Dimming Strategy
Commissioning
Contract Drawings
ConstructionAdministration
Future
RESEARCHOwner Comfort
Expectations
Compatibility
Design Collaboration
Submittals
Lead times (4 weeks? 12 weeks?)
Commissioning and final focus (1 day? 1 week?)
Opening date
Alternates create delays
Commissioning duration and accuracy impacted by documentation
EDUCATE
DocumentEducateResearch
This concludes The American Institute of ArchitectsContinuing Education Systems Course