CNRA International Workshop on - oecd-nea.org · CNRA International Workshop on ... IEEE, ACI,...
Transcript of CNRA International Workshop on - oecd-nea.org · CNRA International Workshop on ... IEEE, ACI,...
CNRA International Workshop on CNRA International Workshop on “New Reactor Siting, Licensing and Construction Experience”“New Reactor Siting, Licensing and Construction Experience”
Licensing Experience of New Reactor (APR1400) in KoreaLicensing Experience of New Reactor (APR1400) in Korea
Woo-Ho Lee, Seon Ho Song, Yong Lak Paek
Nuclear Regulation Division
Korea Institute of Nuclear Safety (KINS)
15 September 2010
Slide - 2-
Table of ContentsTable of Contents
Introduction
Licensing Process • Pre-application Safety Review • Standard Design Approval • Construction Permit (CP) for Nuclear Installation • Operating License (OL) for Nuclear Installation • Pre-Operational Inspection
Design Features of APR1400
Safety Review
• Standard Design Approval
• Shin-Kori unit 3&4
Conclusion
Slide - 3-
IntroductionIntroduction
Current status of NPPs in Korea
Korea has achieved a remarkable growth in nuclear power since commercial operation of Kori Unit 1 in 1978
Korea has now 20 operating NPPs : 16 PWRs and 4 PHWRs
Total licensed output of 20 units is 17,716MW
- generation capacity : 32.9%
- actual production : over 40 %
6 PWRs are now under construction and 2 additional units are planned
4 PWRs (1,000MW) and 2 PWRs (1,400MW) are under const.
2 PWRs (1,400MW) are under docket review for CP
Total units in operation by 2016 : 28 units
Slide - 4-
IntroductionIntroduction
Location of NPPs in Korea
Ulchin 1,2,3,4,5,6
Shin-Ulchin 1,2
Wolsong 1,2,3,4
Shin-Wolsong 1,2
Kori 1,2,3,4
Shin-Kori 1,2 and 3,4
Yonggwang
1,2,3,4,5,6
KINS
PWR PWR
PHWR & PWR
PWR
Slide - 5-
IntroductionIntroduction
Plant Type MW Commercial
Operation
Commercial
Operation Type
Shin-Kori #1 #1
#2
PWR PWR
PWR
1,000 1,000
1,000
Dec. 2010 Dec. 2010
Dec. 2011
OPR1000
OPR1000
OPR1000
Shin-
Wolsong
#1
#2
PWR
PWR
1,000
1,000
Mar. 2012
Jan. 2013
Shin-Kori #3 #3
#4
PWR PWR
PWR
1,400 1,400
1,400
Sep. 2013 Sep. 2013
Sep. 2014
OPR1000
OPR1000
APR1400 APR1400
APR1400
Shin-Shin-
Ulchin
#1 #1
#2
PWR PWR
PWR
1,400 1,400
1,400
Dec. 2015 Dec. 2015
Dec. 2016
APR1400 APR1400
APR1400
: Under Construction, : Under Docket Review, : Under Construction & DR for OL
OPR 1000 : Improved KSNP (Korea Standard Nuclear Power Plant, 1000MW PWR)
APR 1400 : Advanced Power Reactor (1400MW PWR)
Current Status of New Reactor
Slide - 6-
IntroductionIntroduction
Background & Current status of APR1400
• Launch of a 10-year National Project : 1992
To develop technologies involved in the design of an advanced
reactor
Application for Pre-application Safety Review (PSR) : 2000
Application for Standard Design Approval (SDA) : 2001
• The SDA was issued in 2002 after two years of safety review
• Shin-Kori units 3&4(APR1400)
KHNP applied a Construction Permit *(CP) in 2003 , CP was
granted in 2008
Structure & Installation inspection are undergoing
• Shin-Uljin units 1&2 (APR1400)
KHNP applied a CP in October 2008, Review for CP are undergoing
Slide - 7-
IntroductionIntroduction
Shin-Kori Units 3 and 4 (APR 1400)
• May 2002: DC issued , April 2008: CP granted
• Structure inspection are undergoing
Slide - 8-
IntroductionIntroduction
Shin-Uljin units 1&2
• PWR-type reactor (1,400 MWe APR)
Almost same design as Shin-Kori units 3&4
• Docket Review & Safety Review for CP are undergoing since Oct. 2008
• Scheduled to begin commercial operation in Dec. 2015 and Dec. 2016, respectively.
Slide - 9-
IntroductionIntroduction
Development of Regulatory Requirements of APR1400
KINS developed a set of
regulatory requirements
• To achieve a higher level
of safety for APR1400
• Based on the existing
requirements and
international safety
standards
legislated as a Ministerial
Ordinance on Technical
Standards for Nuclear
Facilities in July 2001
Reg. Guide, Criteria, SRGs
Industrial Codes and Standards
(ASME, IEEE, ACI, KEPIC, etc.)
Atomic
Energy Act
Enforcement
Decree of the Act
(Presidential Decree)
Enforcement
Regulations of the Act
(Ministerial Ordinances)
Notice of the Minister of
Education, Science and Technology
The Act provides the bases and
fundamental matters concerning the
development and utilization of atomic
energy and safety regulations
The Decree provides particulars
entrusted by the Act and necessary for
the enforcement of the Act
The Notice provides detailed
particulars for the technical standards
and guidelines
Codes and Standards for materials,
design, test, and inspection of
components and equipment
The Regulation provides the technical
standards and particulars entrusted by the Act
and the Decree such as detailed procedures and
format of documents
Industrial Codes and Standards
(ASME, IEEE, ACI, KEPIC, etc.)
Atomic
Energy Act
Enforcement
Decree of the Act
(Presidential Decree)
Enforcement
Regulations of the Act
(Ministerial Ordinances)
Notice of the Minister of
Education, Science and Technology
The Act provides the bases and
fundamental matters concerning the
development and utilization of atomic
energy and safety regulations
The Act provides the bases and
fundamental matters concerning the
development and utilization of atomic
energy and safety regulations
The Decree provides particulars
entrusted by the Act and necessary for
the enforcement of the Act
The Decree provides particulars
entrusted by the Act and necessary for
the enforcement of the Act
The Notice provides detailed
particulars for the technical standards
and guidelines
The Notice provides detailed
particulars for the technical standards
and guidelines
Codes and Standards for materials,
design, test, and inspection of
components and equipment
Codes and Standards for materials,
design, test, and inspection of
components and equipment
The Regulation provides the technical
standards and particulars entrusted by the Act
and the Decree such as detailed procedures and
format of documents
The Regulation provides the technical
standards and particulars entrusted by the Act
and the Decree such as detailed procedures and
format of documents
Legal System of Nuclear Safety RegulationLegal System of Nuclear Safety Regulation
Slide - 10-
Licensing ProcessLicensing Process
Structure of Licensing Process
Slide - 11-
Licensing ProcessLicensing Process
New Licensing Process
Slide - 12-
PrePre--application Safety Review (PSR)application Safety Review (PSR)
Licensing Process Licensing Process
Prepare Preliminary Safety
Information Documents (PSIDs)PSR Approach Safety Evaluation Results
- Prepare PSIDs In the design
development stage - The applicable current regulations,
and codes & standards are applied
first
- When necessary, enquired
regulatory requirements for the new
design features will be developed as
appropriate
- Major information including in the
PSIDs
. Accident Calculation
. Containment performance
. Calculation of source-term
. Probabilistic Safety Assessment
. Safety test Program, etc.
- Not official licensing review
in accordance with formal
licensing process
- Reflected to the preparation of
application Documents (SARs,
SSARs) for formal licensing
process
Slide - 13-
Standard Design Approval (SDA)Standard Design Approval (SDA)
Licensing Process Licensing Process
Purpose
• Encourage the use of standard plant designs to enhance plant
safety, to improve the efficiency, and to reduce the complexity of
the regulatory process
• Improve the efficiency of licensing review by early resolution of
safety issues for the timely construction of nuclear power plants
Documents submitted for SDA
• Standard Design Safety Analysis Report (SSAR)
• Description on the technical capability for the design of the reactor
• Preparation plan for the Emergency Operating Procedure (EOP)
Slide - 14-
Construction Permit (CP)Construction Permit (CP)
Purpose
to ensure that the technical standards for the location, structure,
facility, and performance of NPP are met
Documents submitted for CP
Radiation Environmental Report (RER)
Preliminary Safety Analysis Report (PSAR)
Quality Assurance Program (QAP) for construction
Description on the Technical Capability (DTC) for nuclear plant
installation, etc.
Licensing Process Licensing Process
Slide - 15-
Construction Permit (CP)Construction Permit (CP)
Processing Period of CP
New reactor is 24 months
15 months for the reactors that have similar type and size in design to the previously licensed ones,
Review method
KINS’ Safety Review Guides (SRGs)
Provide not only the regulatory requirements but also review procedures to keep the consistence in the review results
Safety review
The principle and concept of reactor facility design
The implementation of the regulatory criteria
The evaluation of the environmental effects resulting from the construction, etc.
Licensing Process Licensing Process
Slide - 16-
Operating License (OL)Operating License (OL)
Purpose to confirm whether the components, systems, structures are installed and
their performances are assured as designed. In addition, to perform safety review on the operating capability and accident
management
Licensing documents for OL
Final Safety Analysis Report (FSAR)
Quality Assurance Program (QAP) for operation
Technical Specifications (TS) for Operation
Radiation Environmental Report (RER)
Radiation Emergency Plan (REP)
Description on the Technical Capability (DTC) for the reactor operation
Description on nuclear fuel loading plan
Description of the technical background and verification method to be for the Emergency Operating Procedure, etc.
Licensing Process Licensing Process
Slide - 17-
PrePre--Operational Inspection (POI)Operational Inspection (POI)
Purpose to confirm that the structures, systems, components (SSCs) of plants
are manufactured, installed, and tested in compliance with the SAR and QAP
to ensure that the completed nuclear reactor can be operated as expected throughout the design life
Inspection Items
Structure Inspection (19 items)
Installation Inspection (52 items)
Cold Functional Test (CFT) Inspection (77 items)
Cold Hydro Test (CHT) & Hot Functional Test (HFT) Inspection (23 items)
Initial Fuel Loading & Start-up Test Inspection (33 items)
Licensing Process Licensing Process
Slide - 18-
PrePre--Operational Inspection (POI)Operational Inspection (POI)
Inspection schedule for each stage (Shin-Kori unit 3)
Licensing Process Licensing Process
2008 2009 2010 2011 2012 2013
Structure Inspection
Installation Inspection
CFT Inspection
CHT&HFT Inspection
Start-up Test Inspection
CP April 2008
R/V Install
OL (Initial Fuel Loading)
Remark : CFT (Cold Functional Test), CHT (Cold Hydrostatic Test), HFT (Hot Functional Test)
SIT/ILRT
First Con’t
Slide - 19-
Design Features of APR1400Design Features of APR1400
Design Features
based upon the design, construction and operation experiences of KSNP
Overall design concept
very similar to that of KSNP and System80+
Major design differences between APR1400, System80+ and KSNP
Design Features APR1400 System80+ KSNP
1. Capacity (Mwe) 1,400 1,300 1,000
2. Safety Goal - CDF(/RY) - Cont. Failure Fre. (/RY)
<10-5 <10-6
<10-5 <10-6
10-4 10-5
3. Design Life (yr) 60 60 40
4. Containment Cylindrical Spherical Cylindrical
Slide - 20-
Design Features of APR1400Design Features of APR1400
Design Major design differences between APR1400 and KSNP
Design Features APR1400 System80+ KSNP
5.ECCS - No. of Trains - Safety Injection - RWST location
4
DVI Inside Cont.
4
Cold Leg Injection Inside Cont.
2
Cold Leg Injection Outside Cont.
6.Seismic Design (g) 0.3 0.3 0.2
7.Thermal Margin(%) 10-15 15 8
8.Operator Action (min) 30 30 10
9.Radiation Source Term Realistic Realistic Deterministic
10.Hot Leg Temp. (oF) 615 615 621.2
11.Radiation Exposure 20 20 50
Slide - 21-
Safety Review of APR1400Safety Review of APR1400
Standard Design Approval (SDA)
Licensing issues during the safety review Thermal-hydraulic loads and pool temperature of In-containment Refueling
Water Storage Tank (IRWST)
Performance Evaluation of ECCS
Consideration of Environmental Effect in Fatigue Evaluations of ASME Code Class 1 Components
Soft Control Application for Digital I&C System
Human Factors Engineering for the Advanced Control Room
Alternative Accident Source Term
In-Vessel Core Debris Retention through External Reactor Vessel Cooling
Steam Generator Tube Integrity
Supplementary actions
Uncertainty analysis for the core cooling capability at late reflood phase
Verification of design suitability for soft control and safety console
Submission of design report concerning steam generator tube integrity
Slide - 22-
Safety Review of APR1400Safety Review of APR1400
Shin-Kori units 3&4
Schedule of Shin-Kori units 3&4
Design certification of APR1400 : May, 2002
Application for CP : October, 2003
Safety review for CP : October, 2003 ~ April, 2008
Issuance of CP : April, 2008
Safety review focused on
Implementation of the follow-up actions for SDA
Comparison with the previous units and the standard design of APR1400
Major design features of Shin-Kori units 3&4
Domestic and overseas experience in nuclear power plant operation
Other matters
Slide - 23-
Safety Review of APR1400Safety Review of APR1400
Shin-Kori units 3&4 Assessment of Implementation of the Follow-up
Actions for SDA Safety Injection System Performance Evaluation during Late Reflood
of a LBLOCA
Evaluation of Design Adequacy of the Soft controller, Safety Control Panel and Remote Shutdown Room (RSR)
Scheme for Suppressing Wear Damage of the Steam Generator Tube and Flow Induced Vibration Assessment
Safety Injection System Performance Evaluation during Late Reflood of a LBLOCA
The maximum clad temperature in a LBLOCA : 987.2℃ Acceptance criteria (1,204℃)
The reflood model and code which were conservatively set in the
current method
Slide - 24-
Safety Review of APR1400Safety Review of APR1400
Assessment of Implementation of the Follow-up Actions for SDA
Evaluation of Design Adequacy of the Soft controller, Safety
Control Panel and Remote Shutdown Room (RSR)
Design class categorization and the detailed design plan
Human factors engineering program implementation plan
Physical and electrical isolation of RSR from MCR and ICCR (Instrumentation and Component Control Room)
Scheme for Suppressing Wear Damage of the Steam Generator Tube
and Flow Induced Vibration Assessment
Material, capacity, number of the steam generator tube and the design of the top steam generator tube support structure were changed
Wear resistance of the steam generator tube : 62% improved
Hydraulic expansion method : Contact strength & Remaining stress
Heat treated Alloy 690 : No flaws caused by corrosion in the steam generator tube expansion transition areas
Standardization of expansion pressure
Slide - 25-
Safety Review of APR1400Safety Review of APR1400
Shin-Kori units 3&4 Licensing issues for major design features
Evaluation of the Hydrogen Control System Design Evaluation of the Design of the Reactor Cavity Flooding System Fatigue Design of the Safety Class 1 System Considering Environmental
Impact Design Excluding Operating Basis Earthquake Loads in Seismic Design Adequacy of the Reactor Coolant System Overpressure Protection Facilities Evaluation of the Design of the Human-System Interface of the Main
Control Room The Integrity of the Structure of Engineering Safety Feature Actuating
System Adequacy of the Integrated Design of the Soft Controller and Engineering
Safety Feature-Component Control System Analysis of Human Reliability for Establishing the Human Error Mechanism Application of Human Factors Engineering Activity to Local Control Panel
Design Redundancy Design of the Digital Protection Relay System Design Change of the Off-Site (Preferred) Power Supply System Classification of Underwater Intake and Discharge Facilities
Slide - 26-
Safety Review of APR1400Safety Review of APR1400
Review of Major Design Features
Evaluation of the Design of the Reactor Cavity Flooding
System(CFS)
The basic design of the reactor cavity
flooding system
The flooding time of the reactor
cavity
CFS series 1 : 50 minutes
CFS series 2 : 25 minutes
The schematic diagram of the reactor cavity flooding system of Shin-Kori Units 3 & 4
Slide - 27-
Safety Review of APR1400Safety Review of APR1400
Shin-Kori units 3&4
Evaluation of Reflection of Experience in NPP operation
Review of Ductility Dip Cracking (DDC) Resistance of Alloy 690
Design Change Reflecting Experience of Swedish Forsmark-1 Accident
Review of Ductility Dip Cracking (DDC) Resistance of Alloy 690
Ductility Dip Cracking (DDC) between the welded layers or in the root of
Alloy 690.
Inconel 52M filler material (AWS Classification, ERNiCrFe-7A) for the
buttering areas of Alloy 690
Non-destructive tests (PT, UT and RT) for all Alloy 690 welds
A test for qualifying the ductility dip cracking resistance of Alloy 690
Slide - 28-
Safety Review of APR1400Safety Review of APR1400
Shin-Kori units 3&4
Review of Other Matters operation
Survey of Faults in the Site
Design Standard of Gas Effluent Sampling Facilities
Inclusion of the Screw Fixture Control Program in the Preliminary Safety Analysis Report
Delta-Ferrite Content Requirement for Austenite Series Stainless Steel
Slide - 29-
ConclusionConclusion
PSR and SDA
Improved the efficiency of licensing review by early resolution of safety issues for the timely construction of new reactor (APR 1400)
APR 1400 (Shin-Kori units 3&4)
The location, structure and equipment of the nuclear reactor and related facilities for Shin-Kori units 3&4 satisfied the current safety requirements
APR 1400 can protect the public health and the environment from the impact of the radioactive materials generated from the construction of the facilities
Relatively recent experience accumulated in Korea can be utilized
effectively to facilitate mutual cooperation in the area of new reactor regulation.
KINS has a willingness to cooperate actively with other regulatory authority if the KINS have abilities to give a hand.
Thank you for your attention !Thank you for your attention !