CMRP exam passing tips?

6
Pass CMRP - Certified Maintenance & Reliability Professional exam in just 24 HOURS! 100% REAL EXAM QUESTIONS ANSWERS CMRP - Certified Maintenance & Reliability Professional Exam Buy Complete Questions Answers File from http://www.certs4you.com/smrp/cmrp- dumps.html 100% Exam Passing Guarantee & Money Back Assurance

Transcript of CMRP exam passing tips?

Page 1: CMRP exam passing tips?

Pass CMRP - Certified Maintenance & Reliability Professional

exam in just 24 HOURS!

100% REAL EXAM QUESTIONS ANSWERS

CMRP - Certified Maintenance & Reliability

Professional Exam Buy Complete Questions Answers File from

http://www.certs4you.com/smrp/cmrp-

dumps.html

100% Exam Passing Guarantee & Money Back Assurance

Page 2: CMRP exam passing tips?

Sample Questions

Question # 1: When initiating change to an existing process or program, die best practice is to:

A. Involve key personnel in planning, development of new process or program

directives), train affected personnel, and then implement before a specified

compliance date.

B. Issue a directive on the revised process or program, start it and require

compliance by a specific date, then begin training as soon as possible

thereafter.

C. Announce the new process or program, issue a draft directive for review

and comment then issue the final with a specific compliance date, and

employee review comments and recommendations incorporated to the

maximum extent possible to get "buy-in."

D. Make organizational meetings to plan, train for, and implement change

mandatory, but make participation voluntary to avoid alienating employees

who dislike change.

Answer: C

Question # 2: The maintenance manager of a bearing manufacturer has asked you to calculate the reorder point of a spare part item. She has provided you with the following information to facilitate your calculations. The cost of the spare parties S100. The cost of earning inventory is 20% of the cost of the part. The cost of placing an order is S40 for which the annual demand is 100,000 units. The average tad-time for replenishment is two weeks and the buffer stock of 500 units S desired and the average inventory is 100 units per week. What is the reorder point in units for this spare part?

A. 350 units

B. 600 units

C. 700 units

Page 3: CMRP exam passing tips?

D. 707 units

E. 1200 units

Answer: B

Question # 3: When forming teams to address reliability issues, four stages of team development should be recognized and managed by the reliability professional. These stages in order are:

A. Warming/Absorbing/Performing/Norming.

B. Forming/Absorbing/Storming/Performing.

C. Forming/Storming/Norming/Performing.

D. Warming/Swarming/Absorbing/Norming.

Answer: C

Question # 4: Using predictive technologies, approximately what percent of failures in rotating equipment can be found?

A. Measure the number of safety slogans and bulletins posted

B. Periodic safety audits of work processes in the field

C. Review health and safety performance as required

D. Solicit feedback about safety performance from employees

Answer: B

Question # 5: When measuring the temperature of an object using a radiometric imager, which two parameters have the greatest effect on accuracy of the temperature reading on the instrument?

A. Relative humidity and ambient air temperature

Page 4: CMRP exam passing tips?

B. Emissivity and background temperature

C. Aperture and brightness

D. Range and span

Answer: A

Question # 6: On Monday, the maintenance manager sent an e-mail memo to the production manager saying that the date and time of the next planned outage would be on the third shift of the coming Friday. When the maintenance manager arrived at the unit on Friday third shift, the equipment was still operating at full capacity. The operator said he knew nothing of a planned outage and he had to make up production on this shift. Which of the following is the most likely reason the equipment was still running?

A. The maintenance manager did not know if the production manager had

communicated the plan to the shift leader.

B. The maintenance manager did not know if the production manager

received his e-mail communication.

C. The maintenance manager made a unilateral decision it was time to do the

outage.

D. The maintenance manager did not know if the production schedule allowed

for the planned downtime.

Answer: C

Question # 7: Of the choices below, which is the best way to evaluate the effectiveness of a Safety Program?

A. Measure the number of safety slogans and bulletins posted

B. Periodic safety audits of work processes in the field

C. Review health and safety performance as required

D. Solicit feedback about safety performance from employees

Page 5: CMRP exam passing tips?

Answer: B

Question # 8: Percent overtime maintenance labor hours is:

A. Overtime maintenance labor hours used to maintain assets, divided by the

total maintenance labor hours to maintain assets, expressed as a

percentage.

B. Total overtime labor hours, divided by the total scheduled maintenance

labor hours, expressed as a percentage.

C. Total overtime labor hours, divided by the total maintenance labor hours to

maintain assets, expressed as a percentage.

D. Scheduled overtime maintenance labor hours used to maintain assets,

divided by scheduled maintenance labor hours to maintain assets,

expressed as a percentage.

Answer: B

Buy Complete Questions Answers File from

http://www.certs4you.com/smrp/cmrp-

dumps.html

100% Exam Passing Guarantee & Money Back Assurance

PDF Version + Test Engine Software Version

90 Days Free Updates Service

Valid For All Countries