Cloud-Based GIS Success: Collaborative Effort Produces
Efficient Development in Eagle Ford
Angela Remer, de maximis Data Management Solutions
Travis Faul, EDGE Engineering and Science
Outline
• Introduction • Project Components
– Background – Needs – Desktop Components – Field Components – Cloud Components
• Measured Success • Lessons Learned • Questions
2
2013 – ESRI PUG CONFERENCE
Project Components
• Background – Eagle Ford Shale Play – 500 proposed oil and gas well locations – 200 miles of pipe
• Environmental Review – Opportunity of significant E&P assets – No program in place – compliant for environmental – Programmatic Approach – evaluating all criteria – Documentation
• Manage Regulatory Issues –Total Compliance
3 2013 – ESRI PUG CONFERENCE
The Players
• EDGE Engineering & Science (EDGE)
• de maximis Data Management Solutions, Inc. (ddms)
• Confidential E&P Client
4 2013 – ESRI PUG CONFERENCE
Needs
• Evaluate Rig Locations – Regulatory Needs
• Section 10 • Section 404 • EPA Driver – Floodplain • Cultural Driver – NHPA • Threatened & Endangered Species • Building ID for DOT Pipeline Classification & Air Permitting
– Aggressive Drilling and Development – Documentation and Data Creation – Management of Documents/Data Web-Secure
Environment 5
2013 – ESRI PUG CONFERENCE
Smart people can waste resources without access to the right information.
6 2013 – ESRI PUG CONFERENCE
Good Information = Better Decisions
Workflow
8 2013 – ESRI PUG CONFERENCE
Workflow
9 2013 – ESRI PUG CONFERENCE
Desktop Components • Critical Assessment Layers
– National Data Sets • FEMA • NHD • NWI • Soils • Land Cover
– State & Local • T&E • LiDAR
– Client Specific • Residential • Archeological • Existing Facilities
10 2013 – ESRI PUG CONFERENCE
Desktop Components
• 24 hour turn around • Identify major issues • Desktop assessment allows
client to make adjustments before too much time has passed
• Distribute on web platform for group viewing
11 2013 – ESRI PUG CONFERENCE
Field Components • Field Delineations
– Trimble GPS Unit – Desktop review
components – Staking adjustment in field – Discuss permitting
implications for efficiency – Collaborative staking – GPS Trimble w/ current
Data Sets – iPad w/ GIS layers outside
of Trimble
12 2013 – ESRI PUG CONFERENCE
Cloud Components
• Project Portal Interface – Secure Tiered User Structure – Ability to Manage and Visualize Project Data – Ability to Inform Team of Schedule, Modifications,
and Alerts – iPad Compatible – Document Management – GIS Webmap Module
13 2013 – ESRI PUG CONFERENCE
Cloud Components
https://www.projectportal.net/
14 2013 – ESRI PUG CONFERENCE
Project Portal
• Modular: Documents, Calendar, Database, GIS, Project Tables, Field Data Logger
• Secure –Tiered User Access (SAS 70 Type II Hosting) • Project Management Tool – Manage, Analyze and
Visualize • Ability to Search Across All Modules Simultaneously
15 2013 – ESRI PUG CONFERENCE
Project Portal
• Document Management
16 2013 – ESRI PUG CONFERENCE
Project Portal
• GIS
17 2013 – ESRI PUG CONFERENCE
Project Portal
• Data Analytics
18 2013 – ESRI PUG CONFERENCE
Project Portal
• Project Tables
19 2013 – ESRI PUG CONFERENCE
Project Portal
• Project Calendar
20 2013 – ESRI PUG CONFERENCE
Project Portal
• Environmental Database
21 2013 – ESRI PUG CONFERENCE
Success and Lessons Learned
• Client incorporation of Project Portal in Emergency Management Plan
• Secure Document Management system to hold reports, permits to support any regulatory compliance follow up
• Reduced staking efforts by at least half saving time and money (Week vs Month)
• Regulatory plan in place - NO VIOLATIONS to date • Stormwater recommendations using LiDAR
22 2013 – ESRI PUG CONFERENCE
Summary
• Client had need for regulatory compliance program • Created critical layers for desktop review (1-3 days) • Reduced time and overhead cost by providing
adjustments before staking • Cloud components allowed for review and document
storage
23 2013 – ESRI PUG CONFERENCE