Closure plan: a tool for mine management and cost · PDF fileA.A.S. Pena Golder Associates,...

19
Closure plan: a tool for mine management and cost savings A.M. Pulino Golder Associates, Brazil E. Chapadeiro Golder Associates, Brazil A.A.S. Pena Golder Associates, Brazil A.P.M. Saliba Golder Associates, Brazil

Transcript of Closure plan: a tool for mine management and cost · PDF fileA.A.S. Pena Golder Associates,...

Closure plan: a tool for mine management and cost savings

A.M. Pulino Golder Associates, BrazilE. Chapadeiro Golder Associates, BrazilA.A.S. Pena Golder Associates, BrazilA.P.M. Saliba Golder Associates, Brazil

Summary

• Introduction

• Methodology

– Mine Closure Plan

– Identification of Critical Closure Costs

– Assessment of alternative closure approaches

• Results - Case Study

– Mine Closure Plan and Critical Costs

– Alternative closure approaches and potential savings

• Conclusion

2

Introduction

• Mining should be managed using a life cycle approach the way you conceive and operate the mine has huge impact on closure (costs)!

• Mining is a dynamic activity Mine closure planning must be a dynamic process.

• Knowing closure costs in advance is crucial.

• Mine Closure Plans can be a powerful tool for mine planning and management.

• Decisions made in the early stages of mine planning can significantly impact closure costs.

3

Introduction

• Objective: to demonstrate how the mine closure plan can be used as a tool for mine management.

• Focus of presentation:

– Methodology for identifying critical closure costs Planning and financing closure.

• Technical aspects of closure solutions proposed on the case study are not the focus.

• Social aspects of mine closure are not the focus also.

• Case study presented to exemplify the methodology.

4

Methodology

Conceptual mine closure

plan

Identification of critical

closure costs

Assessment of alternative

closure approaches

Simple but powerful

Dynamic process

Focus on main issues

5

Methodology• Mine Closure Plan Guidelines:

– Must be prepared as early as possible;

– Updated throughout the mine life cycle;

– Level of information increase uncertainties and risks decrease

6

Methodology

• Conceptual mine closure plan:

– Define life of mine: ROM, waste rock and tailings production schedule;

– Define domains (ex: open pit, waste pile, tailings dam, process plant);

– Describe future condition of each domain (physical and chemical characterization) propose closure concept estimate cost (quantities x unit costs) risk assessment;

– Put all domains together in the closure plan prepare physical-financial closure schedule;

7

Methodology

• Identification of critical closure costs:

– Find out what are the costs that contribute the most to the overall closure costs.

– Critical closure costs can be of two kinds:

• Domains ; and

• Activities.

– Critical Domains: direct comparison.

– Critical Activities: add up costs of similar activities for all domains and compare.

8

Methodology

• Assessment of alternative closure approaches:

– Why is it a critical cost (quantity or unit costs)?

– Quantity:• Large structures

• Usually hard to reduce

– Unit costs: • The more complex the closure concept, the higher costs

– Is it possible to reduce these costs? How?• Alternative closure approaches

9

Case Study - Mine Description

• Open pit mine with both oxide and sulphide ore types.

• Process includes crushing, milling, flotation and acid leaching.

• Mine domains: open pit, waste rock pile (sulphide material), two dams for the flotation tailings and ponds for the leaching tailings.

• Confidentiality:

– Site name, owner and values will not be disclosed.

– Closure costs and potential savings will be disclosed as percentages only.

10

Case Study - Closure PlanDomain Closure Measures Closure Cost

GeneralAdditional studies, decommissioning management, socioeconomicactions, water quality monitoring for the whole site.

8%

Open PitPump water to accelerate lake formation, cover exposed sulphideareas, treat pit lake water until it reaches a stable geochemicalcondition.

4%

Waste PileCover with soil layer (mine overburden), implement surfacedrainage system and revegetate.

14%

Process Plant Complete demolition and removal. Revegetate the whole area. 3%

Flotation Tailings Dam AImplement multilayer cover over the whole dam reservoir:trafficability layer (soil), capillary break (crushed rock), store andrelease (soil). Revegetate the whole area.

28%

Flotation Tailings Dam B

Keep a lake on the upstream part of the dam reservoir; implementmultilayer cover over exposed tailings beaches: trafficability layer(soil), capillary break (crushed rock), store and release (soil).Revegetate the covered area.

32%

Leaching Tailings PondsImplement multilayer cover over the whole area: trafficability layer(soil), capillary break (crushed rock), HDPE membrane, store andrelease (soil). Revegetate the whole area.

11%

TOTAL 100%

11

Case Study - Critical Costs

• Soil covers will use all mine overburden material mass balance to ensure there will be enough cover material

• Critical Domains: – Waste Pile (14%), Tailings Dam A (28%) and B (32%) 74% of total

closure costs.

• Critical activities:– Excavation of cover material: 14% of total closure costs.

– Transport of cover material: 29% of total closure costs.

– Crushed rock for covers (capillary breaks): 15% of total closure costs.

– Together those activities represent 58% of total closure costs.

12

Case Study - Alternatives

• Waste Pile:– Cover: 80% of domain cost

– Quantity issue: Large volumes of cover material

– Recommendation: optimize cover design (modest savings)

• Alternative: – Reduce unit costs by using mine equipment

– Cost of third party equipment is 5 times higher than mine costs

– Recommendation use a progressive rehabilitation approach to reclaim the pile with large mine equipment

– Potential savings: 57% of domain closure costs

– Issues: change the pile design (allow traffic of large equipment) + integrate pile reclamation with mine planning

13

Case Study - Alternatives

• Flotation tailings dam A:– Receives oxide + sulphide tailings complex cover to avoid ARD

– Cover: 91% of domain cost

– Quantity issue: Large volumes of cover material

– Unit Cost issue: crushed rock (capillary break) cost

• Alternative: – Make a “cover” with oxide tailings during operation (enough material

to dispose a 4 m thick oxide tailing top layer) minimize ARD risk

– Change to a simple soil cover (reduce unit costs)

– Potential savings: 60% of domain closure costs

– Issue: change mine operation and production schedule

14

Case Study - Alternatives

• Flotation tailings dam B:– Will receive sulphide tailings only complex cover to avoid ARD

– Cover: 90% of domain cost

– Quantity issue: Large volumes of cover material

– Unit Cost issue: crushed rock (capillary break) cost

• Alternative: – Improve flotation recovery desulphurization minimize ARD risk

– Desulphurization plat is currently under feasibility study focus on process recovery, not closure

– Potential savings: 64% of domain closure costs

– Dam closure cost great impact on desulphurization plant feasibility

– Design for closure approach

15

Case Study - Alternatives

• Soil Covers:– Critical costs activities are all related to cover construction.

– Most part of this material is overburden that will come from the mine

– Alternative: improve overburden management allow direct hauling from the mine to the other areas

– Issue: timing overburden is mined before waste rock need to identify areas that can be covered throughout the mine life

– Requires integration between mine planning and closure planning.

• Crushed Rock (capillary break layers):– Segregate oxide and sulphide waste rock

– Reduce unit costs of crushed rock in 80%

– Requires waste rock management changes mine operation

16

Case Study - Alternatives

DomainClosure Cost –

Base Case

Alternative Closure

Approach

Potential Saving Closure Cost –Alternative

Scenario

General 8% None - 8%

Open Pit 4% None - 4%

Waste Rock Pile 14%Progressive

rehabilitation57% 6%

Process Plant 3% None - 3%

Dam A 28%Oxide Tailing

Cover60% 11%

Dam B 32% Desulphurization 64% 12%

Leaching Tailings Ponds

11% None - 11%

TOTAL 100% 55%

17

Conclusion

• Methodology for assessing critical closure costs was shown to be simple but very useful allowed focusing on the key issues in order to improve the economic effectiveness of closure solutions.

• Alternative closure approaches identified directions to further studies rather than final closure solutions additional engineering design will be necessary to assess technical and economical feasibility.

• Alternative closure solutions proposed will require changes on mine design, planning and operation, but might result in a great reduction of closure costs.

• Need to integrate mine closure on mine planning mine closure plan can be an important tool for mine management and cost savings.

18

Thanks!Alexandre Pulino [email protected]

55-31-2121-9837

19