CLLS Construction Law Committee Foundation Level Training – Day 1

Transcript of CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP)...

Page 1: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

CLLS Construction Law Committee Foundation Level Training – Day 1

Page 2: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Programme

Session One: Construction Procurement

Topic Speakers Time Programme

Registration/ Introduction 9.00 – 9.10

Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett

(CMS)

9.10 – 10.10 Explanation of various

procurement routes including

traditional, design and build,

management forms and two

stage contracting

Availability of standard forms

Letters of Intent – uses and

abuses – the CLLS form

Consultancy Appointments Alistair McGrigor (CMS)

Gillian Thomas (Hogan Lovells)

10.10 – 11.10 Key provisions of consultancy

appointments

Standard forms

COFFEE BREAK 11.10 – 11.30

Warranties and Third Party

Rights

Angus Dawson (Macfarlanes)

11.30 – 12.30 Key provisions and standard

forms

Page 2

Page 3: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Marc Hanson (BCLP) & Victoria Peckett (CMS) City of London Law Society – Foundation Level Training

1 November 2019

Page 4: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Page 4

Procuring Global House

Page 5: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Procuring Global House

Developer Marc CEO Global House Developments Limited Quantity Vince Surveyor: Counter & Partners Funder: Gulf Development Bank Tenant: Flood and Fire Assurance Limited (FFA) Construction Victoria lawyer:

Page 5

Page 6: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Traditional Procurement

Page 6

Developer

Main Contractor

Quantity Surveyor

Engineers Architect

Supplier Sub

Contractor Sub

Contractor

Page 7: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Design and Build

Page 7

Developer

Main Contractor

Employer’s Agent/ Quantity Surveyor

Supplier Sub

Contractor Engineers Architect

Sub Contractor

Page 8: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Construction Management

www.bclplaw.com Page 8 © Bryan Cave Leighton Paisner

Developer

Construction Manager

Trade Contractor

Trade Contractor

Quantity Surveyor

Engineers Architect

Supplier Trade

Contractor Trade

Contractor Trade

Contractor Trade

Contractor Supplier

Page 9: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Standard Form Contracts

• JCT 2016

• Standard Form (Traditional)

• Design and Build

• Intermediate

• Minor Works

• Management Contract

• Construction Management

• Prime Cost

• Measured Term

Page 9

Page 10: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Standard Form Contracts

• NEC 04

• Option A – Priced Contract with Activity Schedule

• Option B – Priced Contract with Bill of Quantities

• Option C – Target Contract with Activity Schedule

• Option D – Target Contract with Bill of Quantities

• Option E – Cost Reimbursable

• Option F – Management Contract

Page 10

Page 11: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Standard Form Contracts

• ICC

• Measurement

• Design and Construct

• Minor Works

• Ground Investigation

• Target Cost

• “Partnering Forms”

• PPC 2000

• JCT Constructing Excellence

Page 11

Page 12: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Page 12

LETTERS OF INTENT

Page 13: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Consultancy Appointments

City of London Law Society Construction foundation level training

Page 14: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 14 Hogan Lovells

• Alistair McGrigor – CMS

• Gillian Thomas – Hogan Lovells International LLP

Introductions

Page 15: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 15 Hogan Lovells

• Key provisions of Consultancy Appointments

• Standard Form Consultancy Appointments

• Common points of negotiation

Format of Talk

Page 16: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 16 Hogan Lovells

• Common Law duty

• Reasonable skill and care

• Standard at Common Law

• Ordinary skilled and competent practitioner

• Standard normally sought

• Skill, care and diligence to be expected of a properly qualified [insert discipline] experienced in carrying out work of a similar size, scope and complexity to the Project

• Fitness for Purpose

Key provisions – Duty of Care

Page 17: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 17 Hogan Lovells

• Fees and payment

• Lump Sum Fees

• Ad Valorem Fees

• Time based Fees

• Expenses

• Housing Grants, Construction and Regeneration Act provisions

• Interest on Late payment

Key provisions – Fees and payment

Page 18: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 18 Hogan Lovells

• Obligation to maintain

• Period to maintain

• Level of Insurance

• Aggregate/each and every claim cover

• Exclusions and restrictions

Key provisions – Professional Indemnity Insurance

Page 19: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 19 Hogan Lovells

• Assignment

• Novation

• Sub-contracting

Key provisions – Assignment, Novation and Sub-contracting

Page 20: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 20 Hogan Lovells

• Collateral Warranties

• Third party rights – Contracts (Rights of Third Parties) Act 1999

• Which Third Parties?

Key provisions – Duties to Third Parties

Page 21: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 21 Hogan Lovells

• Ownership of Copyright in Materials

• Licence in copyright materials

• Rights to use document

• Reproduction of design

• Liability for use of document

Key provisions – Copyright licence

Page 22: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 22 Hogan Lovells

• Suspension by the Client

• Termination at will by the Client

• Termination for default by the Client

• Termination for default by the Consultant

• Consequences of Termination

Key provisions – Suspension and Termination

Page 23: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 23 Hogan Lovells

• Adjudication

• Arbitration

• Courts

Key provisions – Dispute Resolution

Page 24: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 24 Hogan Lovells

• Bespoke -v- Standard?

• Royal Institution of British Architects

• Association of Consulting Engineers

• Construction Industry Council

• NEC Professional Services Contract

• GC/Works 5

• International Federation of Consulting Engineers (FIDIC)(White Book)

• Partnering forms – ACA PPC 2000

Standard Forms

Page 25: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

| 25 Hogan Lovells

• Absolute obligations -v- reasonable skill and care

• Obligations regarding breach of third party agreements

• Copyright

• Net Contribution

• Limitation and exclusion of liability

Points for negotiation

Page 26: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

macfarlanes.com

CLLS Construction Committee foundation course

Warranties and third party rights

Angus Dawson

1 November 2019

Page 27: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Warranties and third party rights

• Background

• Why are they needed?

• What is a warranty?

• What are third party rights?

Page 28: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Warranties and third party rights

Who should give / receive them?

Tenant

Tenant

own fit out consultants/ contractor

own fit out consultants/ contractor

own monitoring

team

Client

Project Manager

M&E Engineer

Structural Engineer

Quantity Surveyor

Contractor

Cladding

M&E Sub-Contractor

Piling Sub-Contractor

Purchaser

Funder

own monitoring

team

Architect

Page 29: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Warranties and third party rights

• Form and enabling provisions

• Standard form or bespoke?

• Enabling provisions

• Sanctions for non-compliance

• Are warranties and third party rights an either/or option?

Page 30: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Warranties and third party rights

• Differences

• Boilerplate drafting

• Consideration

• Defences

• Benefit not burden and step in rights

• ‘Excluding’ the Contracts (Rights of Third Parties) Act 1999

Page 31: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Warranties and third party rights

• Substantive provisions

• Primary covenant/duty of care clause

• Prohibited materials

• Insurance provisions

• Assignment

• No ‘no loss’ clause

• Copyright

Page 32: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Warranties and third party rights

• Substantive provisions (part II)

• Step in rights

• Right to call for further warranties/third party rights

• Inspection/approval not to negate duties of warrantor

• Notices

• Limitation period

• Adjudication?

Page 33: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

Warranties and third party rights

• Caps and limitations on liability

• Various forms/types

• No greater liability provisions

• Net contribution clauses

Page 34: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes
Page 35: CLLS Construction Law Committee - Citysolicitors · Procurement Route Options Marc Hanson (BCLP) and Victoria Peckett (CMS) 9.10 – 10.10 Explanation of various procurement routes

CLLS Construction Law Committee Foundation Level Training – Day 1