2C11 Business economics and entrepreneurship Claudiu Albulescu Lecture 3: Financial management in construction companies (30/04/2014) European Erasmus Mundus Master Course Sustainable Constructions under Natural Hazards and Catastrophic Events 520121-1-2011-1-CZ-ERA MUNDUS-EMMC

Transcript of Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of...

Page 1: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

2C11

Business economics and entrepreneurship

Claudiu Albulescu

Lecture 3: Financial management in construction companies (30/04/2014)

European Erasmus Mundus Master Course

Sustainable Constructions

under Natural Hazards and Catastrophic Events 520121-1-2011-1-CZ-ERA MUNDUS-EMMC

Page 2: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Lectures

L1 Trends and challenges for the construction industry

L2 Business strategies and business development in construction companies

L3 Financial management in construction companies

L4 Project management – generalities

L5 Project management – support activities

L6 Project management systems applied in constructions

L7 Entrepreneurship issues

L8 Standard contracts in civil engineering

L9 Risk management in construction company

L10 Summary and discussion of the exam questions

Applications

A1 General presentation of the case study (WTP – Hunedoara)

A2 Financial analysis and management in construction company (WTP – Hunedoara)

A3 Cash flow analysis (WTP – Hunedoara)

A4 Visit – WTP Hunedoara

A5 Project’s presentation

LIST OF LECTURES

Lecture 3: Financial management in construction companies

Page 3: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

OBJECTIVES

- Student is familiar with the basic economic concept used in the construction

industry

- Student understands the role and the structure of the main financial

statements

- Student can use common financial ratios and interpret them

- Student can make a cash flow analysis based on projected expenditures and

revenues

- Student is familiar with the tasks performed by a financial manager

L3 FINANCIAL MANAGEMENT IN

CONSTRUCTION COMPANIES

Lecture 3: Financial management in construction companies

Page 4: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

I. BASIC ECONOMIC CONCEPTS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

II. FINANCIAL STATEMENTS

• Income statement

• Balance sheet

III. FINANCIAL RATIOS

• Activity ratios (Sales dynamics, Inventories dynamics, Total asset turnover ratio)

• Debt ratios (Total Liabilities/Total Assets)

• Profitability ratios (ROE, ROA)

• Liquidity ratios (Quick ratio, Current ratio)

• Investment ratios (IRR, NPV, ROI)

IV. CASH FLOW ANALYIS

V. FINANCIAL MANAGEMENT: TASKS

L3 FINANCIAL MANAGEMENT IN

CONSTRUCTION COMPANIES

Lecture 3: Financial management in construction companies

Page 5: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Page 6: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Expenditures

- Represent the amounts of money that support the activity of a company. Are the

monetary expression of the production factors consumption.

- Examples:

• Operating expenses: Staff costs (wages, social contributions, taxes, etc.),

Capital costs (equipment, plants, technologies, materials etc.), Land,

Administration, Rent.

• Financial expenses (interests, provisions, etc.)

• Unexpected expenses (penalties, loses due to natural causes).

- Their inclusion in one or another category depends on the accounting system

(European continental, Anglo-Saxon system, etc.).

- A complete list with expenditures is found in the Income statement

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Page 7: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Page 8: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Costs

- Accountants use the term of expenditures, economists employ the term costs

- The production cost include only those expenses items generated by the production (Q)

process

- Categories of costs:

• Fixed (indirect) and variables (direct) costs

A. Indirect costs are independent of output. These remain constant throughout the

relevant range, on short-term (depreciation, rent, managers wages, administration,

interests)

B. Direct costs vary with output. Generally variable costs increase at a constant rate

relative to labor and capital. Variable costs may include employees wages, utilities,

materials used in production, etc.

• Total and unit costs (each of them are fixed and variables)

A. Total costs, including direct and indirect components are the costs related to the entire

production volume (i.e. for 10 steel beams)

B. Unit costs (direct and indirect component) are the costs per unit (i.e. for 1 steel beam)

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Page 9: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Costs

Total costs (C) and output volume (Q)

C = FC + VC (Total costs = Fixed costs + Variable costs)

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Q

C

0

FC

VC

C

Page 10: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Page 11: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Page 12: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Page 13: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Page 14: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies

Page 15: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Break-even point

??? What volume of production or of the turnover is necessary in order to obtain

profit?

!!! The profit is not generated automatically after the start of a business (the fixed costs are high

while the output volume is reduced)!

- The break-even point corresponds to the output level (Qbep) where the firm starts to

obtein profit (in this point, the profit is zero).

I. BASIC ECONOMIC CONCEPTS

Lecture 3: Financial management in construction companies Q

C

0

FC

VC

C

T

bep

Qbep

Loss

Profit

Page 16: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

I. BASIC ECONOMIC CONCEPTS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

II. FINANCIAL STATEMENTS

• Income statement

• Balance sheet

III. FINANCIAL RATIOS

• Activity ratios (Sales dynamics, Inventories dynamics, Total asset turnover ratio)

• Debt ratios (Total Liabilities/Total Assets)

• Profitability ratios (ROE, ROA)

• Liquidity ratios (Quick ratio, Current ratio)

• Investment ratios (IRR, NPV, ROI)

IV. CASH FLOW ANALYIS

V. FINANCIAL MANAGEMENT: TASKS

L3 FINANCIAL MANAGEMENT IN

CONSTRUCTION COMPANIES

Lecture 3: Financial management in construction companies

Page 17: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

II. FINANCIAL STATEMENTS

• Income statement

• Balance sheet

II. FINANCIAL STATEMENTS

Lecture 3: Financial management in construction companies

Page 18: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Income statement

DEF: An income statement (profit

and loss account) shows the

company’s revenues and expenses

during a particular period.

II. FINANCIAL STATEMENTS

Lecture 3: Financial management in construction companies

Page 19: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Income statement

Resume

II. FINANCIAL STATEMENTS

Lecture 3: Financial management in construction companies

Revenues

Expenses

PROFIT

Revenues

Expenses

LOSS

Page 20: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

II. FINANCIAL STATEMENTS

• Income statement

• Balance sheet

II. FINANCIAL STATEMENTS

Lecture 3: Financial management in construction companies

Page 21: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Balance sheet

DEF: A balance sheet

summarizes an organization or

individual's assets, equity and

liabilities at a specific point in

time.

II. FINANCIAL STATEMENTS

Lecture 3: Financial management in construction companies

Page 22: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Balance sheet

II. FINANCIAL STATEMENTS

Lecture 3: Financial management in construction companies

Balance sheet

2011 2012 2013

Gross fixed assets 1,330,832 1,244,003 1,127,678

Depreciation 0 10,198 58,834

NET FIXED ASSETS 1,330,832 1,233,804 1,068,844

Inventories 24,069 12,018 30,659

Accounts receivable 799,092 945,112 1,079,979

Other current assets 38 33 510

Cash in hand 24,757 21,320 23,563

CURRENT ASSETS 847,956 978,483 1,134,711

TOTAL ASSETS 2,178,788 2,212,287 2,203,554

Fixed Assets & Contributions 756,036 740,381 855,748

Retained earnings 538,999 409,664 -62,520

EQUITY 1,295,035 1,150,045 793,228

Investment grants 0 0 210,073

Loans 0 0 0

Bank overdraft 0 0 0

Accounts payable 883,753 1,062,242 1,200,252

Other current liabilities 0 0 0

LIABILITIES 883,753 1,062,242 1,410,325

TOTAL EQUITY AND LIABILITIES 2,178,788 2,212,287 2,203,554

Page 23: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Balance sheet

Resume

II. FINANCIAL STATEMENTS

Lecture 3: Financial management in construction companies

Balance sheet

Assets Liabilities and Owners' Equity

Show which is the wealth of the company (the patrimony, the value).

Represents a snapshot of a company's technical condition.

Show where the money came from (owners or loans).

Represents a snapshot of a company's financial condition.

Perfect equality

Page 24: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

I. BASIC ECONOMIC CONCEPTS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

II. FINANCIAL STATEMENTS

• Income statement

• Balance sheet

III. FINANCIAL RATIOS

• Activity ratios (Sales dynamics, Inventories dynamics, Total asset turnover ratio)

• Debt ratios (Total Liabilities/Total Assets)

• Profitability ratios (ROE, ROA)

• Liquidity ratios (Quick ratio, Current ratio)

• Investment ratios (IRR, NPV, ROI)

IV. CASH FLOW ANALYIS

V. FINANCIAL MANAGEMENT: TASKS

L3 FINANCIAL MANAGEMENT IN

CONSTRUCTION COMPANIES

Lecture 3: Financial management in construction companies

Page 25: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

FINANCIAL RATIOS

• Activity ratios (Sales dynamics, Inventories dynamics, Total asset turnover

ratio)

• Debt ratios (Total Liabilities/Total Assets)

• Profitability ratios (ROE, ROA)

• Liquidity ratios (Quick ratio, Current ratio)

• Investment ratios (IRR, NPV, ROI)

III. FINANCIAL RATIOS

Lecture 3: Financial management in construction companies

Page 26: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

III. FINANCIAL RATIOS

Lecture 3: Financial management in construction companies

Page 27: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

III. FINANCIAL RATIOS

Lecture 3: Financial management in construction companies

Page 28: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

FINANCIAL RATIOS

• Investment ratios – used in business plans, feasibility studies,

etc.(investment opportunities)

!!! The feasibility study would be completed prior to the business plan. The feasibility study helps

determine whether an idea or business is a viable option and is usually made when we have a

construction objective (economic and technical parts).

IRR - internal rate of return (measure and compare the profitability of

investments). IRR the discount rate (interest rate – 5%) at which the present

value of all future cash flow is equal to the initial investment (NPV=0)

III. FINANCIAL RATIOS

Lecture 3: Financial management in construction companies

Page 29: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

FINANCIAL RATIOS

• Investment ratios

NPV – Net present value of a time series of cash flows, both incoming and

outgoing, is defined as the sum of the present values of the individual cash flows

of the same entity (NPV is an indicator of how much value an investment or

project adds to the firm; value added in NPV >0)

ROI - Return on investment - is used to measure, per period, rates of return on

money invested in an economic entity in order to decide whether or not to

undertake an investment. It is also used as indicator to compare different project

investments within a project portfolio.

III. FINANCIAL RATIOS

Lecture 3: Financial management in construction companies

Page 30: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

I. BASIC ECONOMIC CONCEPTS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

II. FINANCIAL STATEMENTS

• Income statement

• Balance sheet

III. FINANCIAL RATIOS

• Activity ratios (Sales dynamics, Inventories dynamics, Total asset turnover ratio)

• Debt ratios (Total Liabilities/Total Assets)

• Profitability ratios (ROE, ROA)

• Liquidity ratios (Quick ratio, Current ratio)

• Investment ratios (IRR, NPV, ROI)

IV. CASH FLOW ANALYIS

V. FINANCIAL MANAGEMENT: TASKS

L3 FINANCIAL MANAGEMENT IN

CONSTRUCTION COMPANIES

Lecture 3: Financial management in construction companies

Page 31: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

CASH FLOW

DEF: Is the movement of money into or out of a business or investment project.

Purpose: to determine problems with a business's liquidity (risk) and to determine a

project's rate of return or value.

Importance of cash management in construction

- Construction projects have inherent cash management problems

- One of the major problems is the range in the cost of projects, which can vary

- Large cash outflows take place during periods when cash inflows do not

- Cash management problems are often multiplied by other factors like: Sensitivity to

current economic trends; Lack of sufficient bank credit facilities; Low industry

profitability; Inadequate tax planning; Wrong pricing strategy.

IV. CASH FLOW ANALYIS

Lecture 3: Financial management in construction companies

Page 32: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

CASH FLOW

Cash Flow Analysis:

- The goal in measuring project cash flow is to accelerate receipts so that there is a

positive cash flow from each contract (receive payments from the owner before the

cash payments to subcontractors, material suppliers, employees, and others)

- The cash flow analysis should be based on time periods (e.g., monthly, yearly) for

each contract or for each segment or activity of each contract in process (the

purpose is to identify the cash needs).

- To complete the cash-forecasting function, the projected cash flow from jobs in

process should be combined with non-job-related cash flows (general and

administrative expenses, interest, fixed assets expenditures, taxes, etc.).

- Cash flow analysis include all components which generate cash movements

(inwards and outwards).

IV. CASH FLOW ANALYIS

Lecture 3: Financial management in construction companies

Page 33: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

CASH FLOW

IV. CASH FLOW ANALYIS

Lecture 3: Financial management in construction companies

Page 34: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

CASH FLOW – construction (1)

IV. CASH FLOW ANALYIS

Lecture 3: Financial management in construction companies

Page 35: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

CASH FLOW – construction (2)

IV. CASH FLOW ANALYIS

Lecture 3: Financial management in construction companies

Page 36: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

CASH FLOW - general

IV. CASH FLOW ANALYIS

Lecture 3: Financial management in construction companies

Page 37: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

CASH FLOW – tips

- Billing practices and the controlling of job expenditures are two important areas

that further enhance a contractor's cash flow

- Billing practices are related to: (1) comparison between number of days until

paying the suppliers and number of days until receiving payments from customers;

(2) retention by the owner, which is usually 10% of the progress billing of a portion

of the cash due on the contract (performance security)

- Factors that should be considered by the contractor when negotiating billing terms

in the contract with the owner include the following:

• Payment schedule

• Weekly billing procedures (when contracts are field-labor intensive)

• Payment for materials stored on-site prior to installation

• Contract closeout and punch-list procedures

• Rights to submit claims (approved and unapproved)

• Eliminating or minimizing retention provisions

IV. CASH FLOW ANALYIS

Lecture 3: Financial management in construction companies

Page 38: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

I. BASIC ECONOMIC CONCEPTS

• Expenditures

• Costs

• Prices & Revenues

• Profit

• Break-even point

II. FINANCIAL STATEMENTS

• Income statement

• Balance sheet

III. FINANCIAL RATIOS

• Activity ratios (Sales dynamics, Inventories dynamics, Total asset turnover ratio)

• Debt ratios (Total Liabilities/Total Assets)

• Profitability ratios (ROE, ROA)

• Liquidity ratios (Quick ratio, Current ratio)

• Investment ratios (IRR, NPV, ROI)

IV. CASH FLOW ANALYIS

V. FINANCIAL MANAGEMENT: TASKS

L3 FINANCIAL MANAGEMENT IN

CONSTRUCTION COMPANIES

Lecture 3: Financial management in construction companies

Page 39: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

TOPICS

Goals

Financial Manager Tasks

Key balance sheet accounts

V. FINANCIAL MANAGEMENT: TASKS

Lecture 3: Financial management in construction companies

Page 40: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Goals

- DEF: Financial management is the process of planning decisions in order to

maximize the owners' wealth.

- Financial managers have a major role in:

• cash management,

• in the acquisition of funds ,

• in all aspects of raising and allocating financial capital, taking into account the

trade-off between risk and return.

- Company goals usually include:

• stockholder wealth maximization

• profit maximization

• managerial reward maximization

• social responsibility

!!! The traditional goal frequently stressed by economists-profit maximization is

not sufficient for most construction companies today.

V. FINANCIAL MANAGEMENT: TASKS

Lecture 3: Financial management in construction companies

Page 41: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Goals

V. FINANCIAL MANAGEMENT: TASKS

Lecture 3: Financial management in construction companies

Page 42: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Financial Manager Tasks

- Financial managers need accounting and financial information to carry out their

responsibilities.

- Tasks

V. FINANCIAL MANAGEMENT: TASKS

Lecture 3: Financial management in construction companies

Accounting Payroll

Reporting financial information Maintaining banking relationships

Interpreting financial data Investing funds

Budgeting Obtain financing

Controlling operations Investor relations

Preparing taxes Managing cash

Managing assets Disbursing dividends

Internal auditing Deciding on the financing mix

Reporting to authorities Managing pension funds

Page 43: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Financial Manager Tasks

V. FINANCIAL MANAGEMENT: TASKS

Lecture 3: Financial management in construction companies

Page 44: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Financial Manager Tasks (!!! In large companies, the tasks are split)

V. FINANCIAL MANAGEMENT: TASKS

Lecture 3: Financial management in construction companies

Page 45: Claudiu Albulescu - UPT 2C11_Financial management in... · Break-even point ??? What volume of production or of the turnover is necessary in order to obtain profit? !!! The profit

L10 – B.2 – Mechanical properties of cast iron, mild iron and steel at historical structures

European Erasmus Mundus Master Course

Sustainable Constructions under Natural

Hazards and Catastrophic Events

Key balance sheet accounts (necessary to manage the cash)

V. FINANCIAL MANAGEMENT: TASKS

Lecture 3: Financial management in construction companies