Transcript of City of Willmar's capital improvement plan
-
7/27/2019 City of Willmar's capital improvement plan
1/18
Proposed
Capital Improvement Plan
2014-2018
Presented September 30, 2013
Charlene Stevens, City Administrator
City of Willmar
-
7/27/2019 City of Willmar's capital improvement plan
2/18
Capital Planning 2014-2018
Followed same process as 2013
Criteria for consideration
Legal Mandates
Maintenance of Existing Assets
Sustainability
Reduce or Offset Costs
Critical Public Safety Needs or Concern
Meeting City Council Priorities
Goal of establishing a five (5) year planning horizon
2
-
7/27/2019 City of Willmar's capital improvement plan
3/18
-
7/27/2019 City of Willmar's capital improvement plan
4/18
Capital Improvement Funding
Bonding (Debt)
Cash
Unspent Reserves Unspent Previous Capital Allocations
Special Revenues
WWTF LOST
4
-
7/27/2019 City of Willmar's capital improvement plan
5/18
Proposed Capital Expenditures
5
2014 2015 2016 2017 2018
Cash 1,050,450 1,677,500 1,475,500 1,368,000 1,443,500
DebtService
9,183,000 3,570,000 3,354,000 2,883,000 2,710,000
WWTP 120,000 953,500 140,000 258,500 300,000
LOST 4,605,00 170,000 0 0 0
Stormwater 200,000 100,000 300,000 0 0
State Aid 647,625 714,000 238,000 224,000 1,190,000
Totals $15,735,300 $3,615,000 $5,507,500 $4,733,500 $5,643,500
-
7/27/2019 City of Willmar's capital improvement plan
6/18
2014 Projects
51 projects
Fourteen different categories
Threshold over $5,000
6
-
7/27/2019 City of Willmar's capital improvement plan
7/18
Airport
$236,125 in Cash Funded projects (20%)
$647,625 in State Funded (80%)
Projects Include Overlay Taxi Lanes (East Hanger)
Master Plan Update
Crack Repair/Seal Taxilanes & Parking lots
Airfield Electrical Back-Up Generator
Tiling & Drainage; Fencing; Terminal Irrigation System
Free Standing Sign & MnDOT Sign
Environmental Assessment 13/31 Ext
7
-
7/27/2019 City of Willmar's capital improvement plan
8/18
Fire Department
Emergency Outdoor Sirens, $5,000
Voice Amplifiers, $20,000
West Bay Garage Door Adjustment, $10,000
Copy Machine/Printer, $9,600
All cash funded.
8
-
7/27/2019 City of Willmar's capital improvement plan
9/18
Engineering
Sidewalk/Bike Path Reconstruction, $15,000
Sidewalk/Path New Construction, $35,000
Color Plotter Replacement, $10,000
Signal Loop Detector Replacement, $10,000
Signal Cabinet Replacement, $30,000
Ariel Photography, $15,000
9
-
7/27/2019 City of Willmar's capital improvement plan
10/18
Industrial Park
Phase 2A Construction
$3,500,000 from Local Option Sales Tax
10
-
7/27/2019 City of Willmar's capital improvement plan
11/18
Information Technology
Server Replacement, $25,000
Video Cameras, $17,000
Agenda Software, $27,000
11
-
7/27/2019 City of Willmar's capital improvement plan
12/18
Leisure Services
Civic Center (Local Option Sales Tax) HVAC, $1,000,000
Door Replacement, $30,000
North Driveway Repair, $40,000
WCAC (Cash)
WCAC Signage, $12,000
Mechanical Work (kitchen), $7,500
Building Exterior, $50,000 City Auditorium Gun Range, $30,000 (Cash)
Fence Repair North Swanson, $20,000 (Cash)
12
-
7/27/2019 City of Willmar's capital improvement plan
13/18
Public Works
Street Reconstruction
$2,500,000 Bonded, Annual Program
$140,000 Cash Funded, Overlay
Sign Reflectivity Replacement $25,000 cash funded
PW Facility Siding and Painting
$100,000 cash funded
Play Equipment $30,000 Cash Funded
13
-
7/27/2019 City of Willmar's capital improvement plan
14/18
Public Works
Path Lighting 15th Ave to 19th Ave, $15,000.
Path Lighting Willmar Ave to 15th Ave, $5,000.
Public Works Garage Door Replacement, $10,000.
All Cash funded projects.
14
-
7/27/2019 City of Willmar's capital improvement plan
15/18
Stormwater
Improvements at former WWTP
$100,000 Stormwater Funds
Area West of Menards (Phase 1)
$100,000 Stormwater Funds
15
-
7/27/2019 City of Willmar's capital improvement plan
16/18
Wastewater Treatment
Lakeland Drive Interceptor/MinnWest LS
$6,611,000 (Debt)
Sewer Replacement (annual)
$50,000 Utility fee
Sewer Line under BNSF by Sperryville,
$60,000
Diesel Particulate Filters, $120,000
16
-
7/27/2019 City of Willmar's capital improvement plan
17/18
Other Projects
Downtown Gateways, $200,000
Highway 12 Corridor Study, $50,000
Facilities Study, $50,000
Police Canine Unit, $6,000
17
-
7/27/2019 City of Willmar's capital improvement plan
18/18
Questions?