City of Olathe - PNWS-AWWA Ses… · 20 City of Olathe •Developed a standardized Utilities CIP...

29
City of Olathe Adopting a Holistic Approach to Asset Management

Transcript of City of Olathe - PNWS-AWWA Ses… · 20 City of Olathe •Developed a standardized Utilities CIP...

City of Olathe Adopting a Holistic Approach to Asset Management

The City of Olathe

City of Olathe 2

Area of 61 square miles

4th largest City in Kansas

Population of 130,045

Full Service City

More than Water & Sewer

City of Olathe 3

300 Employees

6 Divisions

6 Funds

o Central Garage

o General Fund

o Solid Waste

o Stormwater

o System Development Fund

o Water & Sewer

32 Programs

Infrastructure Inventory

City of Olathe 5

Description of Inventory

Streets and Sidewalks Includes streets (arterials, collectors, local; curb and gutter), sidewalks, bridges and auxiliary structures (such as gates, streetscape and others).

Utility Drainage Includes sanitary sewer, stormwater and wastewater treatments.

Solid Waste Includes operation and administration facilities, customer accounts, transfer station, household hazardous waste facility and compost facility.

Water Services Includes water distribution, water metering and water production.

Traffic Control Includes traffic signals, signs, markings, street lighting and school beacons.

Buildings Includes public works and operation facilities (e.g. administrative and maintenance), laboratory services

Fleet Includes city vehicles and shop equipment.

Technology Equipment Includes servers, network, all communication equipment.

In the Beginning

City of Olathe 6

Asset Management done in silos

Gaps in processes

Unorganized and inaccurate asset inventory

Asset condition information was inconsistent or non-existent

Various “homegrown” asset management systems

What We Knew

City of Olathe 7

Assets were aging faster than we could replace them

Investments in infrastructure had been on the decline since „08

We were not adequately planning for the wave of needed

infrastructure replacement

Continued growth required new infrastructure development

Regulations made infrastructure improvements even more

costly

But…..Leadership was committed to and supported a

comprehensive approach to Asset Management

Our Current State

City of Olathe 8

We are “doing” Asset Management

Designing a Comprehensive Asset Management (CAM)

System o Shared consensus and goals that include:

Creating cross-divisional collaboration “matrix”

Developing champions within all levels of the organization

(Re)defining coordinated business process

(Re)Defining the Organization

City of Olathe 9

2010 Reorganization o Consolidation of three Departments

2013 APWA Reaccreditation

Creation of Asset Management Team

Department wide process review o Documentation and analysis of Standard Operating Procedures (SOPs)

o Development of in-house Procedure Management System (OPro)

Stewardship of Infrastructure

City of Olathe 11

Strategies:

o Maximize value of existing and future infrastructure

o Developing a comprehensive asset management inventory and system

o Developing sustainable levels of service and performance targets

o Identify priorities and optimize infrastructure investments

o Comply with current regulatory demands and help shape future

regulations

Developing the Culture

City of Olathe 12

Charting the course

o Program development, objectives, goals, levels of service

Putting the “right” people in the “right job”

Communication

Assessing performance

o Reinforce and reward organizational values

o Make directional change when needed

Setting Direction

Creating Alignment

Developing the Plan

Strengthening Processes, Systems, and Data

Data Collection, Inventory and

Management

City of Olathe 13

Conducting asset inventory and condition assessment

o Mobile Data Collection (MDC)

Baseline Inventory Sub-project (BIS)

Field Data Collection Sub-project (FDCS)

the Pipeline Sub-project (tPS)

Utilization of Information System

Tools Consolidation of work order and asset management systems to develop a better

understanding of current infrastructure

In Use • Bridge Inspections Data

• Pavement Management

• Street Maintenance

• Sewer Manhole

• Sewer Gravity Mains

• Signs

• Street Light Supports

• Circuits

• Junction Boxes

• Power Supplies

• Cabinets

• Water Valves

• Water Hydrants

• Water Mains

• Sewer ARVs

• Sewer Vaults

• Water Asset Failures

City of Olathe 14

• Stormwater Inlets

• Stormwater Outlets

• Stormwater Pipes

• Stormwater Basins

• Streets

• Parking Lots

• Snow Zones

• Stormwater Channels

• Stormwater Junctions

In the Works • Bridge Inspections Data

• Pavement Management

• Street Maintenance

• Sewer Manhole

• Sewer Gravity Mains

• Signs

• Street Light Supports

• Circuits

• Junction Boxes

• Power Supplies

• Cabinets

• Water Valves

• Water Hydrants

• Water Mains

• Sewer ARVs

• Sewer Vaults

• Water Asset Failures

Interfaces • Eone-Labor, Equipment

• Billing System-Sewer & Water Work Requests

• WinCan CCTV inspection system (future)

• Olathe Connect (future)-Work Requests

Other Systems • MaintStar

• ERPortal

• Mission Control

Implementation Objectives : Centralized Asset Inventory

Overall Condition Index (OCI) by Asset

Type

So Now What?

City of Olathe 15

• Asset Management Road Map

o Purpose:

Provide an assessment of the current state of the Olathe‟s Asset Management

program

Recommend (prioritized) initiatives for further implementation

o Objectives:

Identify strengths and opportunities for improvement

Develop a longer term Roadmap to improve management and performance

City of Olathe 16

Comprehensive Asset

Management

Strategy

Process

People

Technology

The Roadmap Process

City of Olathe 17

The Roadmap Process • Contracted with CH2MHILL

• CH2MHILL’s team conducted an exhaustive review of Asset

Management related documents, processes and procedures

• CH2MHILL interviewed over 20 of Olathe’s senior leaders through out the organization to validate conclusions from document review and to gather staff opinions on opportunities for improvements

City of Olathe 18

The Roadmap Process

• CH2MHILL facilitated a self

assessment workshop attended by

over 20 Olathe‟s senior leaders

o Attendees assessed the organization‟s

maturity (capabilities), on a 1 to 5

scale, related to 36 different AM

processes

o CH2MHILL used its Comprehensive

Asset Management Review and

Assessment (CAMRA) tool to

structure the discussion

• CH2HMILL prepared a report and Roadmap reflecting its findings

and results of the self assessment workshop, and a recommended

list of initiatives

Strategic Roadmap

City of Olathe 19

Initiatives and Actions

City of Olathe 20

• Developed a standardized Utilities CIP prioritization framework that considers risk and consequence of failure

• Developed a Hydrant AMP

• Developed a draft IT Master Plan

• Developed plans to retain skilled employees and reduce costly turnover

• Formalized Levels of Service (LOS) and corresponding Key Performance Indicators (KPIs)

• Piloted BCE process

• Created Maintenance Manager position in Utilities Maintenance

CIP Prioritization Process

City of Olathe 21

Objectives

City of Olathe 22

• Develop a consistent approach to the justification and

prioritization of competing projects

• Develop a CIP that was driven by a rigorous

understanding of asset need including risk measurements

and root cause analysis

• Adjust funding requirements to suit the assets needs

CIP Prioritization Process

City of Olathe 23

• Projects were selected from three categories –

o Renewal and Replacement Projects

o Level of Service Projects

o Capacity Projects

Likelihood of Failure

City of Olathe 24

LOF Category Wt Negligible = 1 Unlikely = 3 Possible = 5 Likely = 7 Very Likely = 10

Capacity (Hydraulic or

Treatment)30%

Adequate capacity for

next 25 years or as

designed and/or 200%

backup redundancy

available.

Adequate capacity for next

10 years or as designed

and/or 100% backup

redundancy available.

Demand strategies are

mostly adequate to ensure

adequate capacity or are

not needed.

Adequate capacity for next

5 years or as designed

and/or 50% backup

redundancy available.

Currently overloaded under

peak conditions 1 - 2 times

per year and/or 25% backup

redundancy available.

Voluntary demand

management strategies can

only address 50% of

potential water shortages.

Chronically overloaded

under existing

conditions (3 or more

times per year) and no

backup available.

Structural Condition 30%Existing infrastructure is

in: Good conditionModerate condition Fair condition Poor condition Deteriorated

Operational

Maintenance20%

Little or no maintenance

required to keep

operational.

Moderate maintenance

required.

Moderate plus maintenance

required (between 25 -50%

of moderate costs/effort).

Excessive maintenance

required (more than 50% of

moderate costs/effort).

High level of

maintenance required

that stretches O&M

capability and is costly

(more than 100% of

moderate costs/effort).

Reliability/

Performance Indicator20%

No corrective work order

events within 12 months.

<2 corrective work order

events within 12 months.

2-5 corrective work order

events within 12 months.

6-8 corrective work order

events within 12 months.

>8 corrective work order

events within 12

months.

Likelihood of Failure (LOF)by Category Olathe

LOF Category Wt Negligible = 1 Unlikely = 3 Possible = 5 Likely = 7 Very Likely = 10

Capacity (Hydraulic or

Treatment)100%

Adequate capacity for

next 25 years or as

designed and/or 200%

backup redundancy

available.

Adequate capacity for next

10 years or as designed

and/or 100% backup

redundancy available.

Demand strategies are

mostly adequate to ensure

adequate capacity or are

not needed.

Adequate capacity for next

5 years or as designed

and/or 50% backup

redundancy available.

Currently overloaded under

peak conditions 1 - 2 times

per year and/or 25% backup

redundancy available.

Voluntary demand

management strategies can

only address 50% of

potential water shortages.

Chronically overloaded

under existing

conditions (3 or more

times per year) and no

backup available.

Structural Condition 0%Existing Infrastructure is

in: Good conditionModerate condition Fair condition Poor condition Deteriorated

Operational

Maintenance0%

Little or no maintenance

required to keep

operational.

Moderate maintenance

required.

Moderate plus maintenance

required (between 25 -50%

of moderate costs/effort).

Excessive maintenance

required (more than 50% of

moderate costs/effort).

High level of

maintenance required

that stretches O&M

capability and is costly

(more than 100% of

moderate costs/effort).

Reliability/

Performance Indicator0%

No corrective work order

events within 12 months.

<2 corrective work order

events within 12 months.

2-5 corrective work order

events within 12 months.

6-8 corrective work order

events within 12 months.

>8 corrective work order

events within 12

months.

Likelihood of Failure (LOF) by Category Olathe

Likelihood of Failure - Capacity

City of Olathe 25

Consequence of Failure

City of Olathe 26

COF Category Wt. Negligible = 1 Unlikely = 3 Possible = 5 Likely = 7 Very Likely = 10

Impact on the

Safety of Public

and Employees

30% No impact. Minimal impact. Moderate impact. Significant impact.Significant and immediate impact on

injuries or off site health issues.

Impact on

Regulatory

Compliance

25%No state or local permit

violations. No SSOs.

Notice of Violation (NOV), no

enforcement action, fines or

surcharge.

Notice of Violation (NOV),

regulatory inquiry but fines or

surcharge unlikely.

Notice of Violation (NOV), probable

enforcement action, but fines or

surcharge unlikely.

Notice of Violation (NOV), enforcement

action with fines or surcharge.

Impact on Service

Delivery20% No impact.

Minor impact; conservation

messages may need to be

emphasized more than usual.

System overload will occur once

per year with potential for small

SSO and number of backups.

Moderate impact; conservation

messages may need to be

accelerated and some

measures, such as volunteer

lawn watering bans, may need

to be implemented for short

periods. System overloads will

occur 2 times per year and less

than 3 backups.

Major impact; some mandatory

water conservation measures need

to be implemented; new

development permits and new

construction restricted until a new

source is online. Chronic system

overloads - 4 times per year.

Severe impact; major mandatory water

conservation measures need to be

implemented; new development permits

and new construction needs to be placed

on hold until a new source is online.

Chronic system overloads, large SSO

volumes and more than 5 backups.

Impact to

Community 15%

No social or economic impact

on the community. No

reactive media coverage. Any

media coverage is a result of

proactive announcements by

utility. No complaints.

Minor disruption. No adverse

media coverage. Some

complaints.

Moderate disruption. Some

adverse media coverage.

Substantial but short-term

disruption. Adverse media coverage

due to public impact. Localized

media coverage.

Long-term impact. Area-wide disruption.

Regional media coverage.

Impact on O&M 10% No impact on O&M.Minor impact on O&M (5%

increase over typical)

Moderate impact on O&M (10%

increase over typical).

Significant increase in O&M (20%

increase over typical).

Severe increase in O&M and disruption to

other operations needed.

Consequence of Failure (COF) by Level of Service

CategoryOlathe

0

10

20

30

40

50

60

70

80

90

Ha

rold

Str

ee

t W

WTP

Ha

rold

an

d V

an

Ma

r Lif

t S

tati

on

Re

pla

ce

me

nt

WTP

2: R

eh

ab

ilit

ati

on

WTP

2: E

lectr

ica

l/B

ack

up

Po

we

r

WTP

2: C

he

mic

al

Fe

ed

Mo

dif

ica

tio

ns

Co

lle

cto

r W

ell 5

Ra

w W

ate

r Tra

nsm

issio

n M

ain

, C

W5

to

WTP

2

WTP

2: L

ime

Fe

ed

Bu

ild

ing

an

d P

lan

t

Mo

dif

ica

tio

ns

Ha

rris

on

Str

ee

t W

ate

rlin

e

Lif

t S

tati

on

Re

pla

ce

me

nts

Wa

terl

ine

Re

ha

bilit

ati

on

I&I

Re

ha

bilit

ati

on

Sta

nd

pip

e R

eco

ati

ng

s

Fa

cilit

ies R

eh

ab

ilit

ati

on

Re

mo

te F

acilit

ies I

mp

rove

me

nts

Ele

vate

d S

tora

ge

Ta

nk

, 1

51

st

& M

ur-

Le

n

WP

T 2

: A

lte

rna

tive

Dis

infe

cti

on

36

" Tra

nsm

issio

n M

ain

11

9th

Str

ee

t W

ate

r Tra

nsm

issio

n M

ain

Imp

rove

me

nts

Ne

igh

bo

rho

od

Sa

nit

ary

Se

we

r

Imp

rove

me

nts

WTP

2: M

em

bra

ne

Mo

du

le A

dd

itio

ns

Lo

ne

Elm

Bo

oste

r P

um

p S

tati

on

an

d 1

2"

Ma

in

Ris

k S

co

re-I

mp

lem

en

t

5-year Capital Improvement Projects -

Total Risk Score

Do Nothing

After Implementation

Risk Reduction

2015-2019 5-Year CIP

City of Olathe 27

2016-2025 10-Year CIP

0.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

40.00

Ha

rris

on

Str

ee

t W

ate

rlin

e (

20

15

)

Ha

rold

an

d V

an

Ma

r Lif

t S

tati

on

(2

01

5)

WTP

2: C

he

mic

al F

ee

d M

od

ific

ati

on

s (

20

18

)

JCW

Me

teri

ng

Va

ult

Im

pro

ve

me

nts

(N

EW

) (2

01

6)

I&I

Re

ha

bilit

ati

on

(O

n-g

oin

g)

Ne

igh

bo

rho

od

Sa

nit

ary

Se

we

r Im

pro

v. (O

n-g

oin

g)

Lif

t S

tati

on

Im

pro

ve

me

nts

(O

n-g

oin

g)

WTP

2: A

lte

rna

tive

Dis

infe

cti

on

(2

01

6)

WTP

2: E

lectr

ic/B

ack

up

Po

we

r (2

01

8)

Wa

terl

ine

Re

ha

bilit

ati

on

(O

n-g

oin

g)

Bla

ck

Bo

b W

ate

rlin

e R

ep

lace

me

nt

(NE

W)

(2

02

0)

En

vir

on

me

nta

l La

b (

20

16

)

Bla

ck

Bo

b W

ate

rlin

e U

psiz

ing

(2

02

0)

Co

lle

cto

r W

ell 5

(2

01

8)

Dre

sse

r H

ydra

nt

Re

pla

ce

me

nt

(NE

W)

(20

16

)

Lo

ne

Elm

Bo

oste

r P

um

p S

tati

on

an

d 1

2"

Ma

in (

20

15

)

Re

mo

te F

acilit

ies I

mp

rove

me

nts

(2

02

0)

Ele

vate

d S

tora

ge

Ta

nk

(2

02

0)

Ce

da

r C

ree

k W

WTP

: M

ain

ten

an

ce

Bu

ild

ing

(2

01

6)

Ra

w W

ate

r Tra

nsm

issio

n M

ain

, C

W5

to

WTP

2 (

20

18

)

Sta

nd

pip

e R

eco

ati

ng

s (

20

17

)

Ra

w W

ate

rlin

e C

W5

to

CW

6 (

20

25

)

WTP

2: Lim

e F

ee

d B

uild

ing

an

d P

lan

t M

od

ific

ati

on

(2

01

5)

Co

lle

cto

r W

ell 6

(2

02

5)

No

rth

Pa

rke

r S

an

ita

ry S

ew

er

(N

EW

) (2

01

6)

11

9th

St.

Wa

ter

Tra

nsm

issio

n M

ain

Im

pro

v. (2

02

0)

WTP

2: M

em

bra

ne

Mo

du

le A

dd

itio

ns (

20

19

)

WTP

2: B

asin

Exp

an

sio

n (2

02

0)

Ris

k S

co

re-I

mp

lem

en

t

10-Year Capital Improvement Projects -

Total Risk Score

Do Nothing

After Implementation

Risk Reduction

City of Olathe 28

Results

City of Olathe 29

• Developed Standardize Utilities CIP prioritization framework and tools

• Advanced Asset Management principles

• Improved data management and utilization of tools for real results

• Adjusted resource allocation to asset needs

• Delayed $38.9M in capacity projects

• Maintained signal digit rate increases

• Advanced our analytical expertise

• Improved communication and information sharing between work groups

Next Steps

City of Olathe 30

• Develop AMPs for all major classes of assets in all lines of

business

• Develop Management Team team charter that establishes

shared values and commitments

• Enhance communication through a Communication Plan

and training

Questions?

Contact information:

Sarah Doherty

Olathe Public Works, Asset Manager

[email protected]

Phone: 913-971-9034

Nick Pealy

Senior Consultant, CH2MHILL

[email protected]

Cell: 206-852-9790

City of Olathe 31