City of London Corporation Case Study Embedding and sustaining portfolio management Rebecca Kearney Corporate Programme Manager

description

Presentation by Rebecca Kearney, Corporate Programme Managager at APM Conference Creating and sustaining an environment for success on 6th March 2014.

Transcript of City of London Corporation case study

Page 1: City of London Corporation case study

City of London Corporation Case Study

Embedding and sustaining portfolio

management

Rebecca KearneyCorporate Programme Manager

Page 2: City of London Corporation case study

City of London Corporation

Page 3: City of London Corporation case study

Where did we start?

Constrained capital resources

A project process failure

Member-led review 2009-

2010

New project arrangements

introduced October 2011

Page 4: City of London Corporation case study

What did we do?

Page 5: City of London Corporation case study

Where were we? 2011/12

Implementation(2011/12)

Refinement &Improvement (2014)

Consolidation &Compliance (2013)

Time

Change

• Improved communication about projects, especially problems• Corporate overview of all projects within scope • Monthly programme reports to Projects Sub-Committee• Better consistency in decision-making about projects• Greater scrutiny of individual projects is leading to savings• Learning lessons from projects and celebrating success

Page 6: City of London Corporation case study

Where were we? 2013

Implementation(2011/12)

Refinement &Improvement (2014)

Consolidation &Compliance (2013)

Time

Change

• Following gateway process and using corporate templates• Completing key information on project management system• Lessons learnt – systems for institutionalising lessons• Gateway 0s – business plans• Resource allocation – prioritisation based on categories • Staff changes

Page 7: City of London Corporation case study

Where are we now?2014

Implementation(2011/12)

Refinement &Improvement (2014)

Consolidation &Compliance (2013)

Time

Change

• Improvements to gateway process and corporate templates• Review of project management system• Changing role of Corporate Programme Office• Training and development

Page 8: City of London Corporation case study

Lessons

• Drive from the top is critical

• Terminology is not important

• Departmental diversity is ok?

• Talk to people, particularly the difficult ones!

• Articulate clear benefits for all involved

• Embedding and sustaining involves different skills to initiating and implementing

Page 9: City of London Corporation case study

Any Questions?

Page 10: City of London Corporation case study

Contact Details

Rebecca Kearney

Corporate Programme Manager

Email: [email protected]