CIP Report of RO
-
Upload
m-uzair-shaikh -
Category
Documents
-
view
216 -
download
0
Transcript of CIP Report of RO
-
8/17/2019 CIP Report of RO
1/15
1
CIP REPORT OF RO PLANT AT EEAP
Engro Eximp Agriproducts Utilities Department March 02, 2016
Prepared by: Reviewed by:
Adeel Ahmed Muhammad Uzair
AM Utilities Manager Utilities
M.Uzair Sha
-
8/17/2019 CIP Report of RO
2/15
2
The Team
Adeel Ahmed AM (Lead) Khalid Javed FC
-
8/17/2019 CIP Report of RO
3/15
3
Table of Contents
Topic Page• Team 2
• Why we need CIP 4
• P & ID of RO Plant 5
• CIP Procedure 6
• CIP Activity 7
• Data Comparison 9
• Conclusion 9
• Recommendation 10
• Preservation 10
• Preservation Procedure 11
• Annexures (A) 12
• Annexures (B) 14
• Annexures (C) 15
-
8/17/2019 CIP Report of RO
4/15
4
Why We Need CIP
This report contains the CIP for the RO plant at EEAP. The RO plant
CIP required when the surface of RO membrane is subjected to
fouling by foreign materials which may be present in the field water
such as Hydrates of metal oxides, Calcium precipitates, Organic and
biological matters. (The term” fouling” here includes the buildup of all
kinds of layers on the membrane surface, including scaling.
CIP of RO plant mostly required on the Basis of following 3 points:
• When the ∆p across the membranes increases 10%
• Permeate flow decreases 10%
• TDS increases abnormally.
In normal operation, the membrane in reverse osmosis elements can
become fouled by suspended solids, microorganisms, and mineral scale.
These deposits build up during operation and cause loss in water output or
salt rejection, or both. Regular cleaning of the membrane elements
minimizes the loss of performance and extends membrane life.
Membrane cleaning systems are designed to be used with any RO system
to clean membranes without removing them from the system. Our cleaning
systems are provided with hoses and quick disconnect fittings to allow easy
connection to the membrane system.
Background
-
-
8/17/2019 CIP Report of RO
5/15
5
P & ID of RO Plant
CIP Procedure
-
8/17/2019 CIP Report of RO
6/15
6
CIP Procedure
Genesol 703 (Alkaline cleaning) first bath for Reverse Osmosis plant
Genesol 703 quantity required: 10 Kg
Total Time Required 02 Hrs
Soaking time: 15 min
Recirculation time: 15 min
Genesol 703 (Alkaline cleaning) second bath for Reverse Osmosis
plant
Genesol 703 quantity required: 15 Kg
Total Time Required 04 Hrs
Soaking time: 30 min
Recirculation time: 15 min
Genesol 30 (Biocide) bath for Reverse Osmosis plant
Genesol 30 quantity required: 01 Kg
Total Time Required 50 min
Soaking time: 20 min
Recirculation time: 05 min
Genesol 37 (Acid cleaning) bath for Reverse Osmosis plant
Genesol 37 quantity required: 30 Kg
Total Time Required 05 Hrs
Soaking time: 40 min
Recirculation time: 30 min
Chemicals Used : ListCIP Regime
-
8/17/2019 CIP Report of RO
7/15
7
CIP Activity
• RO plant CIP activity started at 0900 hrs. at 1st March
• First of we fill the cleaning tank with permeate water.
• Chemical used for CIP are Genesol 703, Genesol 37, Genesol 30
• Take samples for Analysis before the CIP
• Before CIP starts note down all the parameters of RO plant. • After that starts the first bath with Gensol 703 for 02 hours by adding
10 kg.
• In this bath 15 minutes are for circulation and fifteen minutes for
soaking.
• After that starts the 2nd batch by adding 15 kg chemical time required
for that bath was 4 hrs.
• During this cleaning we frequently note down the ph. of solution, that
was alkaline solution and PH remains from 10.5 to 12
• After this complete flushing of system take place.
• After that we started the acidic cleaning with Genesol 37.
• Total time required for this activity was 05 hrs.
• 30 minutes for circulation and 40 minutes for soaking.
• After that bath with acidic chemical complete flushing was done,
• The RO plant cleaning activity was end at 00:30 hrs.
• Then we take RO back in service and note down its parameters after
cleaning.
• Took the sample for lab analysis after cleaning.
Procedure
-
8/17/2019 CIP Report of RO
8/15
8
RO Cleaning Tank
Alkaline Cleaner Acid Cleaner
-
8/17/2019 CIP Report of RO
9/15
9
Data Comparison before and after CIP
Data and LAB Results
Conclusion
• After CIP the completion it was observed that the permeate flow is
increased from 10 GPM to 20 GPM.
• ∆p across the membrane is decreased from 105 psi to 95 psi.
• Permeate TDS are also decreased.
Parameters Unit Before CIP After CIP
Membrane inlet
Pressure psi 120 120
∆p across the
membrane psi 105 95
Permeate flow GPM 10 20
Reject flow GPM 74 64
TDS mg/L 15.4 11
-
8/17/2019 CIP Report of RO
10/15
10
Recommendation
It is recommended that when a RO machine is going to shutdown,
carefully consideration must be paid. And For the membrane storage
procedure in order to minimize the potential for micro biological growth in
the system.
Preservation
Short term shut down of an RO system (24-48 hours) generally does not
require special membrane storage procedures. The RO should be cycled
(run in operational mode) for at least 15 minutes every 24-48 hours to
reduce the potential for bio-growth and stagnation within the system. Some
systems use a permeate flush during shutdown. This type of cycling will
allow the system to remain “operationally” ready, and it will allow for a
slightly longer time between flush cycles.
For prolonged storage (i.e. several days to several months), the following
procedures are recommended. These procedures will help protect and
preserve the elements from bacterial growth. The elements can be left in
their housings or unloaded and stored separately.
Typically, one of the following lay-up solutions is used depending upon
application
Regulatory limitations, preference, and chemical availability:
1. 0.5 to 1.0% sodium bisulfite or Biocide.
-
8/17/2019 CIP Report of RO
11/15
11
Preservation procedure
The following procedure is recommended for RO storage with biocide
solution.
• Prepare the appropriate strength sodium bisulfite or biocide solution
in the Cleaning tank by diluting with permeates water.
• Circulate the solution through the RO system for 15 to 20 minutes.
• When the RO system is filled with this solution, close the valves to
retain the solution in the RO.
• Repeat Steps 2 and 3 with fresh solution every 15 days
• When the RO system is ready to be returned to service, flush the
system to drain until the
• Permeate water meets quality specifications, then return the machine
to service
-
8/17/2019 CIP Report of RO
12/15
12
Annexures
Annexures (A)
Mail Endorsement
From: t_Adeel Ahmed [mailto:[email protected]]
Sent: Tuesday, March 01, 2016 11:47 AM
Cc: Mohammad Uzair Shaikh; Muhammad Munir Ahmed; Muhammad Asim Zeb
Subject: RO cleaning and preservation.
Dear Faisal Farooq
As per our telephonic conversation I have sent you the procedure for RO
cleaning and Ro preservation, kindly review these and reply me if you want to add
some points or any suggestion .we are using Gensol membrane cleaner chemicals
for RO CIP.
Also please confirm your visit at plant sight tomorrow for ROpreservation activity.
Regards
Adeel Ahmed
AM utilities.
EEAP Muridke.
https://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]
-
8/17/2019 CIP Report of RO
13/15
13
From: Faisal [mailto:[email protected]]
Sent: Tuesday, March 01, 2016 2:22 PM To: t_Adeel Ahmed
Cc: Mohammad Uzair Shaikh; Muhammad Munir Ahmed; Muhammad Asim
Zeb; [email protected]; 'Sajid Khan'
Subject: RE: RO cleaning and preservation.
Dear Mr. Adeel
Reference to your given below email, please find the attached file for RO CIP and
RO preservation procedure. Furthermore charges for the visit would be 5000 Rs.
Kindly confirm us by return email.
With Best Regards.
Engr. Faisal Farooq
Product Engineer
Voice +92-301-8461341
Email [email protected]
Water Regime Pvt Ltd
130/R-3, Johar Town,
Lahore, Pakistan
Tel: 0092-42-35955584-5
Fax: 0092-42-35955586
www.waterregime.com
https://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://www.google.com/url?q=http://www.waterregime.com/&sa=D&sntz=1&usg=AFQjCNGjTwmJ-6TZ3uOCp0XH13loZnkchAhttp://www.google.com/url?q=http://www.waterregime.com/&sa=D&sntz=1&usg=AFQjCNGjTwmJ-6TZ3uOCp0XH13loZnkchAhttp://www.google.com/url?q=http://www.waterregime.com/&sa=D&sntz=1&usg=AFQjCNGjTwmJ-6TZ3uOCp0XH13loZnkchAhttps://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]://mail.google.com/mail/u/0/h/1kybxp84vgumh/?&cs=wh&v=b&[email protected]
-
8/17/2019 CIP Report of RO
14/15
14
Annexures (B)
RO Log Sheet
-
8/17/2019 CIP Report of RO
15/15
15
Annexures (C)
LAB Results