Chhattisgarh State Electricity Regulatory Commission · M/s API Ispat & Powertech Pvt. Ltd and 52...
Transcript of Chhattisgarh State Electricity Regulatory Commission · M/s API Ispat & Powertech Pvt. Ltd and 52...
Page 1 of 42
Suo-Motu Petition No. 55 of 2016(M)
In the Matter of, "miscellaneous petition under section 142 read with
section 86(1)(k) of the Electricity Act, 2003, for non-compliance of
Renewable Purchase Obligation (RPO) by the respondents, for the Finance
Year 2014-15".
Chhattisgarh State Renewable Energy
Development Agency (CREDA) … Petitioner
Versus
M/s API Ispat & Powertech Pvt. Ltd
and 52 others …Respondent
PRESENT : Narayan Singh, Chairman Arun Kumar Sharma, Member
ORDER (Passed on 27th April, 2018)
The petitioner Chhattisgarh State Renewable Energy Development
Agency (CREDA), the nodal agency as per clause 6 of the
Chhattisgarh State Electricity Regulatory Commission (Renewable
Purchase Obligation and REC framework Implementation)
Regulations, 2013 (in short, the Regulations, 2013) for Renewable
Purchase Obligation (RPO) in the State, has filed the present
petition under section 142 read with section 86(1)(k) of the
Electricity Act, 2003 (the Act) for non-compliance of RPO by the
respondents for the Financial Year 2014-15.
2. The nodal agency is entrusted with the job of accreditation and to
recommend the renewable energy projects for registration in the
State. The CREDA is also responsible for monitoring of RPO.
3. The respondents, who are 53 in numbers, are the companies
registered under the Companies Act and are captive users. They are
“obligated entities” as defined in Regulations 2 (XIII) of the
Regulations, 2013 and have to comply mandatorily with the RPO for
relevant year 2014-15 under the Regulations.
Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur - 492 001 (C.G.)
Ph.0771-4048788, Fax: 4073553
www.cserc.gov.in, e-mail: [email protected]
Page 2 of 42
4. The petitioner, in compliance of Regulation 6.3 of the Regulations,
2013, collects information from the obligated entities, Chief
Electrical Inspector (CEI), generating companies etc. to compute the
compliance of RPO target by the obligated entities.
5. The petitioner received detailed reports from CEI regarding captive
consumption and non captive consumption by the obligated entities.
These reports submitted by the CEI through letter dated 12.06.2015
for 41 consumers, through letter dated 18.09.2015 for 15
consumers and through letter dated 03.11.2015 for M/s Monnet
Ispat & Energy Ltd, Naharpali, Raigarh. Thus the CEI submitted
report related to 57 captive users.
6. The petitioner has further sent notices to all obligated entities who
failed to submit the compliance report for the FY 2014-15, for
submission of their RPO compliances. Put a large number of
respondents again failed to submit the RPO compliance report for
the year 2014-15.
7. The petitioner submits that there were total 62 obligated entities
existing in the year 2014-15, out of which 09 obligated entities have
complied with the RPO and the rest 53 have been made respondents
in this case for their non-compliance.
8. The Electricity Act, 2003 (the Act) entrusts a duty upon the State
Commission to promote co-generation and generation of electricity
from renewable sources. Section 86(1)(e) the Act provides that:-
“Promote co-generation and generation of electricity from
renewable sources of energy by providing suitable measures
for connectivity with the grid and sale of electricity to any
person, and also specify, for purchase of electricity from such
sources, a percentage of the total consumption of electricity
in the area of a distribution licensee.”
9. According to the mandate of the Act, the Commission notified
Chhattisgarh State Electricity Regulatory Commission (Renewable
Purchase Obligation and REC framework Implementation)
Regulations, 2013 (in short, Regulations, 2013) for a period starting
from 1st April 2013 and ending on 31st March 2016.
10. Under clause 4.3 of the Regulations, 2013, the obligated entities
are required to procure renewable power to meet out their
Renewable Purchase Obligation (RPO) as specified below:-
Page 3 of 42
Minimum quantum of electricity to be procured by Obligated Entity
as percentage of total consumption
Year Solar Non solar Total
Biomass/renewable energy based co-generation
Other RE (hydel, Wind etc.)
2013-14 0.50% 3.75% 2.00% 6.25%
2014-15 0.75% 3.75% 2.25% 6.75%
2015-16 1.00% 3.75% 2.50% 7.25%
11. The respondents failed to fulfill their solar and non solar RPO in
prescribed percentage for the year and therefore, this petition was
initiated by the petitioner.
12. After filing of the petition by CREDA, the Commission issued notices
to the respondents with copy of this petition to the respondents with
direction to file their replies within four weeks. Some of the
respondents have replied the notice of the Commission and the
others have still not filed their replies.
13. Looking to the large numbers of respondents, we think it appropriate
to discuss the case of non-compliance of RPO by the respondents
separately for each of the respondents.
i. M/s API Ispat & Powertech Pvt. Ltd.:-
(A) The respondent no. 1 M/s API Ispat & Powertech Pvt. Ltd.
submits that according to the provisions of clause 8.1 of the
RPO Regulations, 2013, a captive user or open access
customers may fulfill it's RPO through Renewable Energy
Certificates (RECs) as provided in clause 4 of the Regulations,
2013. However, captive user or open access customers
consuming power in any year to the extent of RPO specified
under regulation 4.3 from fossil fuel based co-generation power
plant shall be exempted from RPO. Quoting this provision, the
respondent says that they have consumed 25.78 MUs from
their fossil fuel based co-generation plant as against their RPO
of 1.803 MUs. The respondent prays, looking to the facts for
dismissal of the petition against the respondent.
(B) After receiving reply, the petitioner CREDA was directed for
verification. The CREDA submits that though the respondent
M/s API Ispat & Powertech Pvt. Ltd. is claiming consumption of
25.78 MUs from the fossil fuel based co-generation plant
against required RPO, which is much more than the RPO, the
Page 4 of 42
respondent failed to furnish certified details of steam
generation and power generation from the Waste Heat along
with the certificate issued by the Boiler Inspector and
therefore, the information provided by the respondent no. 1 is
not complete.
(C) We considered the submissions of both the parties. Though
there is no reason to reject the plea of respondent that they
have consumed much more power than their RPO from their
fossil fuel based co-generation power plant and they are
exempted from RPO for the year, but CREDA's contention is
also right that the respondent has to submit the details with
the certificate issued by Boiler Inspector. We therefore, direct
the respondent no. 1 M/s API Ispat & Powertech Pvt. Ltd. to get
certificate, if not got earlier, from the Boiler Inspector that the
boiler was run from the waste heat of their steel plant and used
in generation of power. This certificate must be obtained within
30 days and submit the details with the certified documents to
the CREDA. The CREDA is directed to verify the same and issue
RPO compliance report accordingly.
ii. M/s Bhagwati Power & Steel Limited :-
(A) The respondent no. 2 M/s Bhagwati Power & Steel Ltd. submits
that they have already submitted RPO compliance report for FY
2014-15 with the petitioner on 17.06.2015. The respondent
no.2 submits that the company is having 6 MW capacity Waste
Heat Recovery Based (WHRB) and having capacity of 4 MW
Atmospheric Fluidized Based Combustion Boiler (AFBCB), thus
total 10 MW installed capacity power plant. According to the
respondent they have consumed more than 11.901 MU's out of
total generation of 41.59 MU's from their fossil fuel based co-
generation plant, against their RPO of 0.7141 MU's. Quoting
the provisions of clause 8.1 of the RPO Regulations, 2013, by
which, captive user or open access customers consuming
power in any year to the extent of RPO specified under
regulation 4.3 from fossil fuel based co-generation power plant
shall be exempted from RPO. The respondent prays, looking to
the facts for dismissal of the petition against the respondent.
Page 5 of 42
(B) After receiving reply, the petitioner CREDA was directed for
verification. The CREDA submits that though the respondent is
claiming fulfillment of it's RPO, the details submitted by the
respondent is incomplete as it is not in accordance with the
prescribed format approved by the Commission. Further the
respondent has failed to submit certificate issued by the Boiler
Inspector, regarding WHRB operating during the compliance
period to prove that they have generated and consumed power
from fossil fuel based co-generation power plant. Thus,
according to the petitioner the respondent has failed to comply
it's RPO for the FY 2014-15.
(C) We considered the submissions of both the parties. Though
there is no reason to reject the plea of respondent that they
have consumed much more power than their RPO from their
fossil fuel based co-generation power plant and they are
exempted from RPO for the year, but CREDA's contention is
also right that the respondent has to submit the details with
the certificate issued by Boiler Inspector. We therefore, direct
the respondent to get certificate, if not got earlier, from the
Boiler Inspector that the boiler was run from the waste heat of
their steel plant and used in generation of power. This
certificate must be obtained within 30 days and submit the
details with the certified documents to the CREDA. The CREDA
is directed to verify the same and issue RPO compliance report
accordingly.
iii. M/s Mahendra Sponge & Power Ltd. :-
(A) The respondent no. 3 M/s Mahendra Sponge & Power Ltd.
submits that RPO in their case, on gross energy consumption
as per the prescribed format amounts to 0.430 MU's in case of
solar RPO and 3.447 MU's in case of non-solar RPO. It is clear
from the compliance report for FY 2014-15 submitted by them
that the company has sold only 1.208 MU's infirm power to
CSPDCL. The power generated through the respondent's co-
generation plant i.e. WHRB amount to 27.980 MU's which is
higher than the actual RPO obligations. Referring Commission's
order dated 06.09.2016 in petition no. 72 of 2015(M), the
respondent submits that it has been decided that obligated
entities who have consumed power from their own co-
Page 6 of 42
generation plant to the extent of RPO have duly complied with
the RPO, the respondent no.3 claims it's fulfillment of RPO and
request the Commission to quash the notice issued to them.
(B) After receiving reply, the petitioner CREDA was directed for
verification. The CREDA submits that though the respondent
M/s Mahendra Sponge and Power Ltd. is claiming fulfillment of
it's RPO, the details submitted by the respondent is incomplete
as it is not in accordance with the prescribed format approved
by the Commission. Further the respondent has failed to
submit certificate issued by the Boiler Inspector, regarding
WHRB operating during the compliance period to prove that
they have generated and consumed power from fossil fuel
based co-generation power plant. Thus, according to the
petitioner the respondent has failed to comply it's RPO for the
FY 2014-15.
(C) We considered the submissions of both the parties. Though
there is no reason to reject the plea of respondent that they
have consumed much more power than their RPO from their
fossil fuel based co-generation power plant and they are
exempted from RPO for the year, but CREDA's contention is
also right that the respondent has to submit the details with
the certificate issued by Boiler Inspector. We therefore, direct
the respondent to get certificate, if not got earlier, from the
Boiler Inspector that the boiler was run from the waste heat of
their steel plant and used in generation of power. This
certificate must be obtained within 30 days and submit the
details with the certified documents to the CREDA. The CREDA
is directed to verify the same and issue RPO compliance report
accordingly.
iv. M/s Real Ispat & Power Ltd. :-
(A) The respondent no. 4 M/s Real Ispat and Power Ltd. submits
that they have consumed 67.99 MU's from their fossil fuel
based co-generation plant against their RPO of 8.74 MU's. It is
clear from the compliance report for FY 2014-15, the
respondent fulfills RPO and requests the Commission to dismiss
the petition against them.
(B) After receiving reply, the petitioner CREDA was directed for
verification. The CREDA submits that though the respondent
Page 7 of 42
M/s Real Ispat and Power Ltd. is claiming fulfillment of it's RPO,
the details submitted by the respondent is incomplete as it is
not in accordance with the prescribed format approved by the
Commission. Further the respondent has failed to submit
certificate issued by the Boiler Inspector, regarding WHRB
operating during the compliance period to prove that they have
generated and consumed power from fossil fuel based co-
generation power plant. Thus, according to the petitioner the
respondent has failed to comply it's RPO for the FY 2014-15.
(C) We considered the submissions of both the parties. Though
there is no reason to reject the plea of respondent that they
have consumed much more power than their RPO from their
fossil fuel based co-generation power plant and they are
exempted from RPO for the year, but CREDA's contention is
also right that the respondent has to submit the details with
the certificate issued by Boiler Inspector. We therefore, direct
the respondent M/s Real Ispat and Power Ltd. to get certificate,
if not got earlier, from the Boiler Inspector that the boiler was
run from the waste heat of their steel plant and used in
generation of power. This certificate must be obtained within
30 days and submit the details with the certified documents to
the CREDA. The CREDA is directed to verify the same and issue
RPO compliance report accordingly.
v. M/s Lafarge India Ltd.(Sonadih Cement Plant) :-
(A) The respondent no. 5 M/s Lafarge India Ltd. has filed reply,
according to which the respondent has already complied with
the statutory requirement of procuring REC for the year 2014-
15 and reported the petitioner through communicated dated
04.07.2015. The respondent has wrongly arrayed in this
petition. The petition is not maintainable against the
respondent. The respondent has submitted the details, certified
by a Chartered Accountant firm, regarding gross annual energy
consumption and RPO compliance report. According to data
given solar RPO was 0.0012 MU against which solar certificate
of 0.0020 MU procured and the non-solar RPO was 0.0100 MU
against which non-solar REC of 0.010 procured.
Page 8 of 42
(B) According to the petitioner's data the respondent was required
to fulfill solar obligation of 0.0013 MU, but the respondent has
procured 0.0020 MU solar power and thus the solar RPO is
compiled by the respondent. The respondent was needed to
procure 0.0102 MU non-solar renewable power but respondent
has procured only 0.0100 MU non-solar power. Thus, the
respondent complied the solar obligation and there is a short
fall in non-solar compliance.
(C) We considered the data submitted before us by both the
parties. We observe that there is a negligible difference
between the data submitted by the petitioner and respondent
before us. It is also pertinent to note here that the petitioner's
data is also based on data submitted by the respondent either
before them or the Chief Electrical Inspector. Hence, there is
no reason to disbelieve the data, verified by a Chartered
Accountant, submitted by the respondent before us, with his
reply supported by an affidavit. Therefore, we conclude that
the respondent has fulfilled his RPO for the year 2014-15.
vi. M/s Lafarge India Ltd.(Arasmeta) :-
(A) The respondent no. 6 M/s Lafarge India Ltd has filed reply,
according to which the respondent has already complied with
the statutory requirement of procuring REC for the year 2014-
15 and reported the petitioner through communication dated
21st September 2016. The respondent has wrongly arrayed in
this petition. The petition is not maintainable against the
respondent. However the data submitted by the respondent
with reply supported by affidavit, are related to the year 2015-
16 and 2016-17, while the petition is concerned with the year
2014-15.
(B) According to the petitioner's data, captive consumption of the
respondent is 0.00 and solar and non-solar obligation are also
0.00. The non-solar REC procured as mentioned by the
petitioner is carry forward from previous year.
(C) We are unable to understand; when the respondent's captive
consumption was 0.00 in the year 2014-15 then why they are
made respondent in this petition. After considering the data
available on records, we conclude that the respondent no. 6 is
Page 9 of 42
not required to fulfill RPO for year 2014-15 because their
captive consumption was nil in that year.
The petitioner CREDA shall take care in future that in
this type of cases the captive consumers need not be
impleaded as respondent, because it is unnecessary
harassment to a party which is not an obligated entity for a
certain moment of time.
vii. M/s S.K. Sarawagi & Co. Pvt. Ltd. :-
(A) The respondent no. 7 M/s S.K. Sarawagi & Co. Pvt. Ltd. denied
all the averments made in petition in totality. According to this
respondent the averments are baseless and untenable in law.
According to the respondent no. 7 the company is having 5 MW
capacity Waste Heat Recovery Boiler (WHRB) based co-
generation power plant which uses waste gas produced from
it's sponge iron plant to generate electricity. This respondent
do not have any Coal Fed Boiler nor Biomass fed Boiler. The
respondent generate electricity solely through it's 5 MW WHRB
based co-generation captive power plant with the use of fossil
fuels. The respondent submits that they have consumed 15.41
MU's of power only from their WHRB co-generation plant,
hence he is exempted from RPO obligation as per the
provisions of the Regultions. The respondent prays, looking to
the facts for dismissal of the petition against the respondent.
(B) After receiving reply, the petitioner CREDA was directed for
verification. The CREDA submits that the details provided by
the respondent M/s S.K. Sarawagi & Co. Pvt. Ltd. is incomplete
as it is not in accordance with the prescribed format approved
by the Commission. The respondent has failed to furnish any
proof that they have generated and consumed power from
fossil fuel based co-generation power plant. Thus, according to
the petitioner, the respondent has failed to comply it's RPO for
the FY 2014-15.
(C) We considered the submissions of both the parties. Though
there is no reason to reject the plea of respondent that they
have consumed power only from their fossil fuel based co-
generation power plant and they are exempted from RPO for
the year, but CREDA's contention is also right that the
Page 10 of 42
respondent has to submit the details with the certificate issued
by Boiler Inspector. We therefore, direct the respondent M/s
S.K. Sarawagi & Co. Pvt. Ltd. to get certificate, if not got
earlier, from the Boiler Inspector that the boiler was run from
the waste heat of their steel plant and used in generation of
power. This certificate must be obtained within 30 days and
submit the details with the certified documents to the CREDA.
The CREDA is directed to verify the same and issue RPO
compliance report accordingly.
viii. M/s Sunil Sponge Pvt. Ltd. :-
(A) The respondent no. 8 M/s Sunil Sponge Pvt. Ltd. was not
present on the day i.e. 05.01.2017 when the matter was
heard. Due to non appearance, we have ordered that in
relation to this respondent, the case may be decided on the
basis of data available on records. As per data available, the
captive consumption of this respondent was 16.4911 MU's in
the year 2014-15 and therefore, the respondent was under
obligation to procure either 0.1237 MU's solar power or
certificate and 0.9895 MU non-solar renewable power or
certificate to fulfill RPO. Thus, this respondent was under
obligation to procure total 1.1132 MU renewable power
including solar and non-solar power.
The respondent no. 8 has filed reply to the notice on
23.01.2017 with affidavit of Shri Sanjay Nachrani a Director
and authorized signatory of the respondent company, with
request, by stating reasons for not filing the reply earlier, to
consider the reply before passing orders on merit. Though the
reasons given in the request letter for non filing of reply earlier
are not satisfactory, we take the reply for consideration looking
to the injustice that may be caused to the respondent, if the
reply is not considered.
(B) After receiving reply, the petitioner CREDA was directed for
verification. The CREDA submits that though the respondent is
claiming fulfillment of it's RPO, the details submitted by the
respondent is incomplete as it is not in accordance with the
prescribed format approved by the Commission. Further the
respondent has failed to submit certificate issued by the Boiler
Page 11 of 42
Inspector, regarding WHRB operating during the compliance
period to prove that they have generated and consumed power
from fossil based co-generation power plant. Thus, according to
the petitioner the respondent has failed to comply it's RPO for
the FY 2014-15.
(C) We considered the data available on records as well as the
reply of the respondent. It is observed that in reply the
respondent submits that their own generation from WHRB
boiler was 10.30 MUs in the year 2014-15 and in total the
respondent generated 6.85 MUs more power than required for
compliance of RPO. Certificate of Boiler Inspector is also
enclosed. From the above data, it appears that the respondent
has complied with the RPO obligation for the year 2014-15.
ix. M/s Hi-tech Power and Steel Ltd. :-
(A) The respondent no. 9 M/s Hi-tech Power & Steel Ltd. has not
made any specific statement regarding their RPO. However, the
respondent has submitted gross annual energy consumption
and RPO compliance report. According to the report the solar
RPO @ 0.75% of GEC was 0.52592 MU's and out of which they
have procured solar power 0.22406 MU's from their own
generation. Non-solar RPO @ 6% of GEC was 4.2033 MU's
against which the respondent procured 23.74694 MU's from
their own WHRB plant. The respondent has also submitted
certificate issued by Boiler Inspectorate.
(B) The CREDA has not filed any further submission on the data.
(C) From the above data, it appears that the respondent has
complied with the RPO obligation for the year 2014-15.
x. M/s Drolia Electro steel Pvt. Ltd. :-
(A) The respondent no. 10 M/s Drolia Electro steel Pvt. Ltd.
submits that the respondent is operating 11 MW captive power
plant from which 5 MW through WHRB and 6 MW through AFBC
Boiler. The respondent is also operating 0.2 MW solar power
plants. According to the respondent, it's solar RPO was 0.355
MU's against which 0.225 MU's was generated by their own
solar plant. Their non solar RPO was 2.843 MU's and their
WHRB boiler generated 23.364 MU's in the year 2014-15. In
Page 12 of 42
total, the respondent has generated 20.391 MU's more power
than required for compliance of RPO.
(B) After receiving reply, the petitioner CREDA was directed for
verification. The CREDA submits that though the respondent is
claiming fulfillment of it's RPO, the details submitted by the
respondent is incomplete as it is not in accordance with the
prescribed format approved by the Commission. Further, the
respondent has failed to submit certificate issued by the Boiler
Inspector regarding WHRB operating during the compliance
period to prove that they have generated and consumed power
from fossil based co-generation power plant. Thus, according to
the petitioner, the respondent has failed to comply it's RPO for
the FY 2014-15.
(C) We considered the submissions of both the parties. Though
there is no reason to reject the plea of respondent that they
have consumed much more power than their RPO from their
WHRB power plant and they are exempted from RPO for the
year, but CREDA's contention is also right that the respondent
has to submit the details with the certificate issued by Boiler
Inspector. We therefore, direct the respondent to get
certificate, if not got earlier, from the Boiler Inspector that the
boiler was run from the waste heat of their steel plant and used
in generation of power. This certificate must be obtained within
30 days and submit the details with the certified documents to
the CREDA. The CREDA is directed to verify the same and issue
RPO compliance report accordingly.
xi. M/s Shivalay Ispat & Power Pvt. Ltd. :-
(A) The respondent no. 11 M/s Shivalay Ispat & Power Pvt. Ltd.
submit, that according to the provisions of clause 8.1 of the
RPO Regulations, 2013, a captive user or open access
customers may fulfill it's RPO through Renewable Energy
Certificates (RECs) as provided in clause 4 of the Regulations,
2013. However, captive user or open access customers
consuming power in any year to the extent of RPO specified
under regulation 4.3 from fossil fuel based co-generation
power plant shall be exempted from RPO. Quoting this
provision, the respondent says that they have consumed
Page 13 of 42
11.267 MUs from their fossil fuel based co-generation plant as
against their RPO of 0.676 MUs. The respondent is generating
power only from WHRB and the entire power is utilized by
itself. The respondent prays, looking to the facts, for dismissal
of the petition against the respondent.
(B) After receiving reply, the petitioner CREDA was directed for
verification. The CREDA submits that the respondent failed to
furnish certified details of steam generation and power
generation from the Waste Heat alongwith the certificate
issued by the Boiler Inspector and therefore, the information
provided by the respondent is not complete.
(C) We considered the submissions of both the parties. Though
there is no reason to reject the plea of respondent that they
have consumed much more power than their RPO from their
fossil fuel based co-generation power plant and they are
exempted from RPO for the year, but CREDA's contention is
also right that the respondent has to submit the details with
the certificate issued by Boiler Inspector. We therefore, direct
the respondent to get certificate, if not got earlier, from the
Boiler Inspector that the boiler was run from the waste heat of
their steel plant and used in generation of power. This
certificate must be obtained within 30 days and submit the
details with the certified documents to the CREDA. The CREDA
is directed to verify the same and issue RPO compliance report
accordingly.
xii. M/s ACB India Limited :-
(A) The respondent no. 12 M/s ACB India Ltd. submits that their
solar obligation was 200.45 MWH and non-solar RPO was
1603.57 MWH, total RPO was 1804.02 MWH for the year
2014-15 against which the respondent purchased RE
certificates from Power Exchange India Limited. For solar RPO
201 and non-solar RPO 1610, total 1811 certificates have been
purchased. Total 1804.02 certificates are required to be
purchased against which 1811 certificates purchased by the
respondent. Additional 6.98 RE certificates shall be adjusted in
next financial year.
Page 14 of 42
(B) The petitioner CREDA verifies that the respondent has
complied with the RPO obligations for the year 2014-15.
(C) As the petitioner has verified, we conclude that the respondent
has fulfilled his RPO for year 2014-15.
xiii. M/s Spectrum Coal and Power Pvt. Limited :-
(A) The respondent no. 13 M/s spectrum Coal and Power Pvt. Ltd.
submits that their solar obligation was 73.27 MWH and non-
solar RPO was 586.20 MWH, total RPO was 659.47 MWH for
the year 2014-15 against which the respondent purchased RE
certificates from Power Exchange India Limited. For solar RPO
72 and non-solar RPO 582 total 654 certificates have been
purchased. Total 659.47 certificates are required to be
purchased against which 654 certificates purchased by the
respondent. The respondent assures that shortfall 5.47 REC
will be completed in the next financial year. The respondent
has submitted that they have complied 99.17% RPO.
(B) The petitioner CREDA verifies that the respondent has
completed 99.17% of it's RPO for the year 2014-15.
(C) As the petitioner has verified, we conclude that the respondent
has fulfilled it's 99.17% RPO for year 2014-15 and direct the
respondent to complete it's RPO for the year, if not completed
till the date, in next financial year 2018-19.
xiv. M/s Madhya Bharat Paper Limited :-
(A) The respondent no. 14 M/s Madhya Bharat Paper Ltd.
submits that they are abiding industry since inception, but
due to past three years market condition the respondent has
become presently a sick company under the Sick Industrial
Companies (Special Provisions) Act, 1985 and an application
for the same is under process to BIFR. It is submitted by the
respondent that the unit has almost remained closed due to
change of raw material from Paddy Straw to Waste Paper
w.e.f. from 01.04.2015.
(B) The petitioner CREDA submits that no proof has been
submitted by the respondent to prove it's contentions. The
respondent has failed to submit any information regarding
RPO compliance for the year 2014-15.
Page 15 of 42
(C) Considering the submissions of both the parties we direct the
respondent to comply it's obligation for the year 2014-15, if
not complied till the date, in the next financial year 2018-19.
xv. M/s Ultratech Cement Ltd. Hirmi Cement works :-
(A) The respondent no. 15 M/s Ultratech Cement Ltd. (Hirmi
Cement works) submits that they have fully complied RPO. It
is submitted that the CREDA has not considered carry forward
surplus solar and non-solar power of previous year 2013-14
for the current year. It is also submitted that non-solar REC
procured in May 2015 against shortfall of the year 2014-15
and thus the RPO for the year was complied.
(B) The petitioner CREDA submits that the compliance report as
filed by the respondent does not have the seal and signature
of a Chartered Accountant. The CREDA therefore, concluded
the respondent has failed to fulfill RPO for the year.
(C) We are of the view in this matter that report submitted by the
respondent cannot be rejected or disbelieved only on the
ground that it is not certified by a Chartered Accountant, if
could be verified otherwise. From the documents available in
record it appears that the respondent has fulfilled it's RPO
obligation for the year 2014-15. Hence, we conclude that the
respondent has complied with RPO.
xvi. M/s Ambuja Cements Ltd. :-
(A) The respondent no. 16 M/s Ambuja Cement Ltd. has neither
filed reply nor present at the time of hearings despite given
opportunities, hence we are constrained to decide the matter
on the basis of data available on records.
(B) According to the petitioner's data, the respondent's
consumption was 233.02 MU and accordingly, the solar
obligation was 1.7477 MU and non-solar obligation was
13.9812 MU's. Against the obligation the respondent procured
0.3497 MU solar power and solar REC 2.844 MU for non-solar
obligation, no power procured by the respondent. However,
non solar REC procured for 12.536 MU's and thus there is
shortfall of 1.4452 for non-solar REC. According to CREDA the
Page 16 of 42
respondent complied the solar obligation and there is a short
fall in non-solar compliance.
C. We considered the data available on records and observed
that the respondent could not fulfill the non-solar RPO for the
year 2014-15. However, the respondent has procured more
solar power/REC for it's obligation. The respondent has
procured 1.4461 MUs more solar power/REC against it's
obligation and there is a shortfall of 1.4452 MU in non-solar
obligation. The excess of solar obligation is approximately
equal to the shortfall in non-solar obligation. Looking to the
circumstances, it would be appropriate in our view to offset
the excess power/REC for solar obligation with the shortfall in
non-solar obligation. We therefore, conclude that the
respondent has fulfilled it's obligation for the year 2014-15.
However, at this moment we want to express our displeasure
towards the attitude of the respondent M/s Ambuja Cement
Ltd. and hope that they will improve their attitude in future.
xvii. M/s Ultratech Cement Ltd. Rawan Cement works :-
(A) The respondent no. 17 M/s Ultratech Cement Ltd. (Rawan
Cement works) submits that for the year 2014-15 they have
to require solar RPO 1.826 MU against which their solar
generation was 0.84 MU, the shortfall in solar RPO was 0.986
MU's. After adjustment of excess RPO 0.0955 MU in previous
year 2013-14, the net shortfall was 0.8905 MU, which will be
met in FY 2015-16 as per Gadget notification no. 49/RPO-
REC/2013 dated 21.05.2013 clause no. 2. Non-solar RPO for
the year was 14.611 MU; they have not procured non-solar
power, but procured non-solar REC for 14.665 MU. Thus
excess REC 0.054 will be adjusted against meet shortfall of
0.20 of FY 2013-14. Balance shortfall of 0.146 will be met in
FY 2015-16.
(B) The petitioner CREDA submits that the compliance report as
filed by the respondent does not have the seal and signature
of a Chartered Accountant. The respondent rectified the short
coming and filed duly verified by Chartered Accountant and
duly notarized document.
Page 17 of 42
(C) We hold that the respondent has given proper data verified by
a Chartered Accountant. There is a shortfall of 0.146 MU's in
non-solar RPO. We direct the respondent to fulfill the RPO for
the shortfall by the end of June 2018, if not fulfilled earlier as
per assurance.
xviii. M/s Nalwa Steel & Power. :-
(A) The respondent no. 18 M/s Nalwa Steel & Power submits that
their solar RPO was 1.006 MU and non-solar RPO was 8.049
MUs for the year. WHRB own generation of the respondent was
62.271 MUs for the year and thus their WHRB consumption
62.271 MUs is much more than the total RPO 9.055 MU
(8.049+1.006). In support of WHRB power generation the
respondent submitted certificates from Boiler Inspectorate.
(B) The petitioner CREDA has affirmed the data given by the
respondent and submits that the respondent has complied with
it's RPO obligations.
(C) We conclude that the petitioner has fulfilled it's RPO for the
year 2014-15.
xix. M/s Uniworth Limited:-
(A) The respondent no. 19 M/s Uniworth Ltd. submits that the
respondent has electricity generator sets as stand-by for
emergency backup only to it's industry and the DG sets are not
connected to grid. The need of DG sets arises because of power
failure from the CSEB grid to cater the emergency load of the
plant. The Commission has exempted the respondent to fulfill
RPO for FY 2012-13 through order dated 20.10.2015 in petition
No. 88 of 2014(M).
(B) The petitioner CREDA submits that according to respondents
own admission it could not fulfill the RPO.
(C) We considered the submissions of both the parties. There is no
reason to disbelieve the pleadings of the respondent. If the
respondent uses DG sets in emergencies and these are not
connected with the grid, the respondent is not required to fulfill
the RPO. The Commission has already ordered in a similar
matter in petition No. 88 of 2014(M) on 20.10.2015.
Page 18 of 42
xx. M/s Jindal Steel & Power Limited :-
(A) The respondent no. 20 M/s Jindal Steel & power Ltd. submits
that according to the provisions of clause 8.1 of the RPO
Regulations, 2013, a captive user or open access customers
may fulfill it's RPO through Renewable Energy Certificates
(RECs) as provided in clause 4 of the Regulations, 2013.
However, captive user or open access customers consuming
power in any year to the extent of RPO specified under
regulation 4.3 from fossil fuel based co-generation power plant
shall be exempted from RPO. Quoting this provision, the
respondent says that they have consumed their own generation
by WHRB 1203.37 MUs while their solar RPO was 19.19 and
non-solar RPO was 153.54 MU total RPO was 172.3 MUs. Thus
the respondent has fulfilled it's obligation. The respondent
through affidavit affirmed the data given.
(B) The petitioner CREDA submits that the data given by the
respondent does not have the seal and signature of a Charted
Accountant.
(C) We considered the submissions of both the parties. There is no
reason to reject the plea of respondent, which is supported by
affidavit that they have consumed more power than their RPO
from their fossil fuel based co-generation power plant and they
have fulfilled their obligation according to the provisions of the
Regulations. If the data verified by Charted Accountant has not
been produced before the CREDA, the respondent is directed to
submit the same within a month before the nodal agency
CREDA for their satisfaction.
xxi. M/s Arasmeta Captive Power Plant (Sai Lilagar power):-
(A) The respondent no. 21 M/s Arasmeta Captive Power Plant (Sai
Lilagar Power Generation Limited) submits that they are
presently supplying power to Chhattisgarh State Power Trading
Company Limited. The RPO obligation applies to only
distribution licensee captive users and open access customers.
The respondent is a generating company having 86 MW
(2x43MW) coal based generating station. The question of RPO
Regulations being applicable on the supply by the respondent
to Chhattisgarh State Power Trading Company Limited does not
Page 19 of 42
arise. The respondent does not procure electricity from open
access. The only consumption of the respondent is auxiliary
consumption which forms part of generation itself and is not
counted separately.
(B) The petitioner CREDA verified the above statement of the
respondent and observed that the respondent does not need to
comply with the RPO for year 2014-15.
(C) As the respondent stated and the petitioner verified, we
conclude that the RPO obligations do not apply to the
respondent's case. The CREDA is advised to take care in such
type of cases to avoid unnecessary prosecution.
xxii. M/s Anjani Steels Limited :-
(A) The respondent no. 22 M/s Anjani Steels Ltd. submits that their
solar obligation was 0.619 MUs and non-solar obligation was
4.955 MUs. They are consuming their WHRB power about
26.264 MUs from their WHRB power generation. Thus they are
not required to fulfill the RPO from purchasing power or
procuring certificates as per provisions of Regulations.
(B) The petitioner CREDA affirms the data submitted by the
respondent and confirmed that the respondent has complied
with it's RPO for the year 2014-15.
(C) We considered the submissions of both the parties. We
conclude that the respondent fulfills it's RPO obligation.
xxiii. M/s Bharat Alluminium Company Limited (BALCO) :-
(A) The respondent no. 23 M/s Bharat Alluminium Company
Limited submits that they have complied 100% solar RPO by
purchase of 37,336 solar RECs. The respondent had also
purchased 33,333 non-solar REC certificates from Power
Exchange India Limited on 25.10.2017. After purchase of these
certificates, the respondent has fulfilled 12.5% of it's non-solar
RPO. The balance obligation for non-solar obligation is
2,65,358, which is to be fulfilled by the respondent. The
respondent describing it's financial status, requests to grant
time upto end of 1st quarter of financial year 2018-19.
Page 20 of 42
(B) The petitioner CREDA submitted that the respondent has
complied with it's RPO for the year 2014-15.
(C) The petitioner's contention is not clear as to whether the
respondent has fulfilled it's both solar and non-solar RPO or it
fulfills solar RPO only. We observed that the respondent has
submitted that they have fulfilled solar RPO but non-solar RPO
is to be completed by the end of 1st Quarter of financial year
2018-19. Looking to the circumstances, we accept the
respondent's plea and direct him to fulfill it's RPO according to
the promise made by it in it's reply within the period asked by
them. We also hope that the CREDA will take care in future
before making submissions to the Commission, so that the
mistake occurred in this case is not repeated again in any other
case.
xxiv. M/s Shri Bajrang Metalics and Power Ltd, (TMT Division)
xxv. M/s Shri Bajrang Metalics and Power Ltd, (Tilda Division):-
(A) The respondent No. 24 & 25 M/s Shri Bajrang Metalics and
Power Ltd., TMT Division & Tilda Division both have filed their
reply separately but the contents of the reply are same in
nature. According to these respondents, the Commission
through orders in P.No. 98 of 2015 and P.No. 76 & 77 of 2015
already recognized the three units of these respondent
company as one entity and therefore after accumulation of data
of the respondent companies i.e. the single entity, both are
exempted from RPO as their own generation and consumption
from waste heat recovery based power generation was 160.527
MUs, which was much more than the RPO compliance (solar
RPO 2.106 + non solar RPO 16.845 total 18.951 MUs) of the
entity i.e. 3 units of the respondents.
(B) The petitioner CREDA submits that both the respondents failed
to furnish the certified details of steam generation and power
generation from waste heat along with the certificate issued by
the Boiler inspector regarding waste heat recovery boiler
operating during the compliance period to prove that they have
generated and consumed from fossil fuel based co-generation
power plant. The petitioner submits that both the respondents
failed to comply their RPO obligations for the year 2014-15.
Page 21 of 42
(C) We considered the submissions of both the parties. Though
there is no reason to reject the plea of the respondents that
they have consumed much more power than their RPO from
their fossil fuel based co-generation power plant and they are
exempted from RPO for the year, but CREDA's contention is
also right that the respondent has to submit the details with
the certificate issued by Boiler Inspector. We therefore, direct
the respondent No. 24 & 25 M/s Shri Bajrang Metalics and
Power Ltd., TMT Division & Tilda Division to get certificate, if
not got earlier, from the Boiler Inspector that the boiler was
run from the waste heat of their steel plant and used in
generation of power. This certificate must be obtained within
30 days and submit the details with the certified documents to
the CREDA. The CREDA is directed to verify the same and issue
RPO compliance report accordingly.
xxvi. M/s Crest Steel & Power Pvt. Ltd. :-
(A) The respondent No. 26 M/s Crest Steel & Power Pvt. Ltd.
submits that the power in respondent's plant is generated
through waste heat recovery boilers and Fluidized Bed
Combustion for its own consumption. The respondent has
already installed 100x3 KW solar power units. Such units or
such source of energy has been considered as renewable
source of energy by the Hon'ble APTEL in Appeal no. 57 and
54 of 2012. It is also pleaded by the respondent that as per
the judgment of APTEL, the definition of obligated entity would
not cover a case where a person is consuming power from co-
generation plant. So the respondent is not an obligated entity
and it is not obligated to fulfill RPO.
(B) The petitioner CREDA submits that the respondent failed to
furnish the certified details of steam generation and power
generation from waste heat along with the certificate issued by
the Boiler inspector regarding waste heat recovery boiler
operating during the compliance period to prove that they
have generated and consumed power from fossil fuel based
co-generation power plant. The petitioner submits that the
respondent failed to comply their RPO obligations for the year
2014-15.
Page 22 of 42
(C) We considered the submissions of both the parties. Though
there is no reason to reject the plea of respondent that they
have consumed much more power than their RPO from their
fossil fuel based co-generation power plant and they are
exempted from RPO for the year, but CREDA's contention is
also right that the respondent has to submit the details with
the certificate issued by Boiler Inspector. We therefore, direct
the respondent No. 26 M/s Crest Steel & Power Pvt. Ltd. to
provide necessary and relevant information to the petitioner
CREDA and also to get certificate, if not got earlier, from the
Boiler Inspector that the boiler was run from the waste heat of
their steel plant and used in generation of power. This
certificate must be obtained within 30 days and submit the
details with the certified documents to the CREDA. The CREDA
is directed to verify the same and issue RPO compliance report
accordingly.
xxvii. M/s Gopal Sponge & Power Pvt. Limited:-
(A) The respondent No. 27 M/s Gopal Sponge & Power Pvt. Ltd.
submits that the respondent is engaged in production of
sponge iron, MS Ingot and generation of power through WHRB
based power plant. The captive generation plant produces
electricity for respondent own use in the process of
manufacturer of sponge iron and MS ingot from the waste heat
recovery boilers. The generation in the relevant year was
20.75 MUs and their own consumption was 10.04 MUs. As the
respondent generates electricity as co-generation, they are
exempted from the requirement of RPO, under provision of 8.1
of the Regulations 2013.
(B) The petitioner CREDA submits that the respondent failed to
furnish the certified details of steam generation and power
generation from waste heat along with the certificate issued by
the Boiler inspector regarding Waste Heat Recovery Boiler
operating during the compliance period to prove that they
have generated and consumed from fossil fuel based co-
generation power plant. The petitioner submits that the
respondent failed to comply their RPO obligations for the year
2014-15.
Page 23 of 42
(c) We considered the submissions of both the parties. Though
there is no reason to reject the plea of respondent that they
have consumed much more power than their RPO from their
fossil fuel based co-generation power plant and they are
exempted from RPO for the year. Later, the respondent has
also filed the certificate issued by Boiler Inspector. We
therefore, decide that the respondent has complied with it's
RPO.
xxviii. M/s Vaswani Industries Limited:-
(A) The respondent no. 28 M/s Vaswani Industries Limited submits
that they are generating power by using steam from Waste
Heat Recovery Boilers. Their total power generation in the
year 2014-15 was 65.302 MUs out of which their own
consumption was 60.1824. Their solar RPO was 0.451368 and
non-solar RPO was 3.610944 MUs in the year. They have
procured 40.59148 MUs from WHRB which is 36.980536 MUs
more than their RPO.
(B) The petitioner CREDA submits that the respondent failed to
furnish the certified details of steam generation and power
generation from waste heat along with the certificate issued by
the Boiler inspector regarding waste heat recovery boiler
operating during the compliance period to prove that they
have generated and consumed power from fossil fuel based
co-generation power plant. The petitioner submits that the
respondent failed to comply their RPO obligations for the year
2014-15.
(C) We considered the submissions of both the parties. The
respondent has pleaded that they have consumed 40.59148
MUs from WHRB, which is equal to the total generation from
WHRB, which is possible. Though, there is no reason to reject
the plea of respondent that they have consumed much more
power than their RPO from their fossil fuel based co-
generation power plant and they are exempted from RPO for
the year, but CREDA's contention is also right that, the
respondent has to submit the details with the certificate issued
by Boiler Inspector. We therefore, direct the respondent No.
28 M/s Vaswani Industries Limited to provide necessary and
Page 24 of 42
relevant information to the petitioner CREDA and also to get
certificate, if not got earlier, from the Boiler Inspector that the
boiler was run from the waste heat of their steel plant and
used in generation of power. This certificate must be obtained
within 30 days and submit the details with the certified
documents to the CREDA. The CREDA is directed to verify the
same and issue RPO compliance report accordingly.
xxix. M/s Vandana Global Limited:-
(A) The Respondent No. 29 M/s Vandana Global Limited submits
that they generated 95.23 MU from WHRB and as per the
CSERC order dated 21.05.2013 in petition No. 28 of 2012 and
P. No. 07 of 2013, WHRB power is considered as co-generation
and no RPO obligation is required.
(B) The petitioner CREDA, in reply, verifies the documents
submitted by the respondent and concluded that the
respondent has complied with it's RPO obligations for the year
2014-15.
(C) We, looking to the submissions of both the parties, arrive at
the conclusion that the respondent has completed with it's
RPO obligations for the year 2014-15.
xxx. M/s Topworth Steel Pvt. Ltd. :-
(A) The respondent no. 30 M/s Topworth Steel Pvt. Ltd. submits
quoting various provisions of the Act, Rules and also Orders
and judgments of the Commission and the APTEL, that the
power in respondent's plant is generated through WHRB and
Fluidized Bed Combustion for it's own consumption. It is also
submitted that the respondent has already installed 100x3 KW
solar power units. Such units and such sources of energy have
been considered as renewable sources of energy by the Hon'ble
APTEL in appeal No. 57 and 54 of 2012.
Despite the above submissions, the respondent has not given
detailed data and required documents in support of the
statement made above. It is pertinent to mention here that the
petitioner has filed petition against the respondent on the basis
of non submission of RPO compliance report for the year 2014-
15.
Page 25 of 42
(B) The petitioner CREDA, in reply, submits that though the
respondent claims exemption from RPO obligations in it's reply
dated 04.11.2016, the respondent has failed to furnish the
certified details of steam generation and power generation from
waste heat along with the certificate issued by the Boiler
inspector regarding Waste Heat Recovery Boiler operating
during the compliance period to prove that they have
generated and consumed from fossil fuel based co-generation
power plant. The petitioner submits that the respondent failed
to comply their RPO obligations for the year 2014-15.
(C) Considering the submissions of both the parties, we decide that
the respondent has failed to provide details as required to the
nodal agency as well as the Commission during the proceeding
of this petition. Hence, we direct the respondent to submit the
details with affidavit to the petitioner nodal agency within 30
days stating the reasons for non-filing the details earlier. Any
shortfall in RPO compliance must be fulfilled by purchasing RE
certificates by the end of June 2018. We also warn the
respondent if they fail in future in compliance of the RPO
including the submission of proper data and certificates to the
nodal agency, we will take strict action and impose penalty
upon him for such non-compliance.
xxxi. M/s Singhal Enterprises (P) Ltd. :-
(A) The respondent no. 31 M/s Singhal Enterprises (P) Ltd. has
neither filed reply nor was present at the time of hearings
despite given opportunities, hence we are constrained to
decide the matter on the basis of data available on records.
It is pertinent to mention here that the petitioner has filed
petition against the respondent on the basis of non
submission of RPO compliance report for the year 2014-15.
(B) The petitioner CREDA submits that the respondent has not
filed reply till date and therefore the petitioner is not in a
position to verify the data of the respondent. The petitioner
prays to declare that the respondent has failed to fulfill it's
RPO obligation for the year 2014-15.
(C) Looking to the respondent's attitude and petitioner's
submissions, we have gone through the file. We observe that
Page 26 of 42
a letter No. 1244 dated 03.11.2015 of the Chief Electrical
Inspector is on record. Through this letter, CEI has given
details available with them regarding captive consumption of
the respondent to the petitioner. From there details, it is
observed that the respondent owns 2 MW capacity solar
power plant. The plant generated 3.30 MU power in the year
2014-15 out of which 0.03 MU was their auxiliary
consumption and 3.27 was their net generation and the total
power of net generation was sold to the distribution licensee.
As there was no captive consumption observed, the
respondent is not liable for fulfillment of RPO.
From the above observation it appears that the petitioner has
not properly scrutinized the details submitted by the CEI to it
and therefore, this position emerges. We direct the CREDA to
ensure, before filing petition in future, whether the entity has
consumed power either from CPP or taken power through
open access and thereafter, keeping in view the quantum of
captive consumption or power taken from open access,
enquire against the entity and thereafter, if required initiate
proceedings against the entity.
We also express our displeasure towards the attitude of the
respondent M/s Singhal Enterprises (P) Ltd. They have to
reply to the notice issued by the Commission and put the
factual position before the Commission, as the Commission is
a quasi judicial authority.
xxxii. M/s Monnet Ispat & Energy Limited :-
(A) The respondent no. 32 M/s Monnet Ispat & Energy Limited
submits that for the year 2014-15 their RPO obligation was
19.1163 MUs including 2.1240 solar RPO and 16.9923 MU non-
solar RPO. The respondent consumed 131.8836 MUs through
it's co-generation plant i.e. WHRB plant, which is more than the
required actual RPO obligation.
(B) The petitioner CREDA submitted in reply that claim of
exemption of respondent vide Commission's order dated
22.10.2016 is not proper as the said exemption has been
granted only to the Raigarh plant. It is further submitted that
the respondent has failed to furnish any proof that they have
Page 27 of 42
consumed power from fossil based co-generation power plant.
The information submitted by the respondent is not complete.
(C) Considering arguments of both the parties, we could not agree
with the petitioner contentions that through order dated
22.10.2016 the Commission exempted only the Raigarh plant
of the respondent company. The data submitted with the reply
shows that the respondent has fulfilled it's RPO in the year
2014-15. We conclude accordingly.
xxxiii. M/s M.S.P. Steel & Power Ltd. :-
(A) The respondent no. 33 M/s M.S.P. Steel & Power Limited
submits that for the year 2014-15 their RPO obligation of
solar energy was 1.70 MU and non-solar RPO was 17.83 MUs.
The WHRB generation from their own plant was 124.40 MUs.
From this WHRB generation some powers they have supplied to
their sister concern M/s MSP Sponge Iron Limited. According to
the data submitted they consumed more 89.63 MUs after
fulfillment of their solar and non-solar RPO.
(B) The petitioner CREDA, in reply, submits though the respondent
claims exemption from RPO obligations in it's reply dated
25.11.2016, the respondent has failed to furnish the certified
details of steam generation and power generation from waste
heat along with the certificate issued by the Boiler inspector
regarding Waste Heat Recovery Boiler operating during the
compliance period to prove that they have generated and
consumed from fossil fuel based co-generation power plant.
The petitioner submits that the respondent failed to comply
their RPO obligations for the year 2014-15.
(C) Considering the submissions of both the parties, we observe
some mismatch in data given with reply; however, it is prima
facie apparent that the company is not obligated entity under
RPO. It appears from the record that the respondent has failed
to provide details as required to the nodal agency as well as
the Commission during the proceedings of this petition. Hence,
we direct the respondent to submit the details with affidavit to
the petitioner nodal agency within 30 days stating the reasons
for non-filing the details earlier. Any shortfall in RPO
compliance must be fulfilled by purchasing RE certificates by
Page 28 of 42
the end of June 2018. We also warn the respondent if they fail
in future in compliance of the RPO including the submission of
proper data and certificates to the nodal agency, we will take
strict action and impose penalty upon him for such non-
compliance.
xxxiv. M/s M.S.P. Sponge Iron Pvt. Ltd. :-
(A) The respondent no. 34 M/s M.S.P. Sponge Iron Pvt. Limited
submits that for the year 2014-15 their RPO obligation of
solar energy was 1.163 MU and non-solar RPO was 8.144 MUs.
They have procured 21.10 MUs WHRB power and 4.87 MUs
biomass based power total 25.97 MUs RE power from their
sister concern M/s MSP Steel & Power Ltd. According to the
data submitted they consumed 17.83 MUs more after
fulfillment of their solar and non-solar RPO.
(B) The petitioner CREDA, in reply, submits though the respondent
claims exemption from RPO obligations in it's reply dated
25.11.2016, the respondent has failed to furnish the certified
details of steam generation and power generation from waste
heat along with the certificate issued by the Boiler inspector
regarding Waste Heat Recovery Boiler operating during the
compliance period to prove that they have generated and
consumed from fossil fuel based co-generation power plant.
The petitioner submits that the respondent failed to comply
their RPO obligations for the year 2014-15.
(C) Considering the submissions of both the parties, we observe
prima facie that the respondent has procured more RE power
then his RPO. However, it appears from the record that the
respondent has failed to provide details, as required, to the
nodal agency as well as the Commission during the
proceedings of this petition. Hence, we direct the respondent to
submit the details with affidavit to the petitioner nodal agency
within 30 days stating the reasons for non-filing the details
earlier. Any shortfall in RPO compliance must be fulfilled by
purchasing RE certificates by the end of June 2018. We also
warn the respondent if they fail in future in compliance of the
RPO including the submission of proper data and certificates to
Page 29 of 42
the nodal agency, we will take strict action and impose penalty
on them for such non-compliance.
xxxv. M/s Rashmi Sponge Iron & Power Industries Ltd. :-
(A) The respondent no. 35 M/s Rashmi Sponge Iron & Power
Industries Ltd. submits that they have capacity of about 4 MW
WHRB and 4 MW AFBC captive power plant. During the
relevant financial year 2014-15 they have generated the power
only from their 4 MW WHRB boiler and not from 4 MW AFBC
boiler and same was used in their home consumption i.e.
captive use. It is pleaded that according to the Hon'ble APTEL's
judgments in appeal No. 57 of 2009, 54 of 2012 and 59 of
2012, the definition of the obligated entity would not cover a
case where a person is consuming power from co-generation
plant. Hence the respondent prays to declare that the RPO is
not applicable in the respondent case.
(B) The petitioner CREDA, in reply, submits though the respondent
claims exemption from RPO obligations in it's reply dated
10.11.2016, the respondent has failed to furnish the certified
details of steam generation and power generation from waste
heat along with the certificate issued by the Boiler inspector
regarding Waste Heat Recovery Boiler operating during the
compliance period to prove that they have generated and
consumed from fossil fuel based co-generation power plant.
The petitioner submits that the respondent failed to comply
their RPO obligations for the year 2014-15.
(C) Considering the submissions of both the parties, we do not
disbelieve the submission made by the respondent however, it
is apparent from the record that the respondent has failed to
provide details as required to the nodal agency as well as the
Commission during the proceedings of this petition. Hence, we
direct the respondent to submit the details with affidavit to the
petitioner nodal agency within 30 days stating the reasons for
non-filing the details earlier. Any shortfall in RPO compliance
must be fulfilled by purchasing RE certificates by the end of
June 2018. We also warn the respondent if they fail in future in
compliance of the RPO including the submission of proper data
Page 30 of 42
and certificates to the nodal agency, we will take strict action
and impose penalty upon him for such non-compliance.
xxxvi. M/s Jayaswal Neco Limited:-
(A) The respondent No. 36 M/s Jayaswal Neco Ltd. submits that
the respondent is operating a co-generation captive power
plant based on waste heat generated by the blast furnace
plant of respondent with the use of fossil fuel (coal). According
to the respondent, their gross consumption of power from CGP
based on WHRB was 51.41 MUs in the year 2014-15. The solar
RPO in that year was 2.6321 MUs and non-solar RPO was
16.451 MUs. After adjustment of the RPO from their WHRB
generation they have consumed 34.959 MUs more renewable
power than their RPO compliance. The respondent requests
that they have no conventional generating plant, but it is a co-
generation plant and consumes power generated from co-
generation captive power plant and therefore the respondent
shall be exempted from RPO for the year 2014-15. The
respondent has also submitted certificate for the use of a
boiler from the Boiler Inspection Department.
(B) The petitioner CREDA submits that the respondent failed to
furnish the certified details of steam generation and power
generation from waste heat along with the certificate issued by
the Boiler inspector regarding Waste Heat Recovery Boiler
operating during the compliance period to prove that they
have generated and consumed from fossil fuel based co-
generation power plant.
(C) We considered the submissions of both the parties. We
observe that there is no reason to reject the plea of
respondent that they have consumed much more power than
their RPO from their fossil fuel based co-generation power
plant and they are exempted from RPO for the year. We
decide that the respondent fulfilled RPO for the year 2014-15.
xxxvii. M/s Sarda Energy & Minerals Ltd. :-
(A) The respondent no. 37 M/s Sarda Energy & Minerals Limited
submits that for the year 2014-15 they are exempted from the
RPO under Regulation 3(ii) para 3. The details submitted shows
Page 31 of 42
that the respondent's generation from co-generation plant was
13,67,06,360 MUs. After deduction of auxiliary consumption
1,42,25,658 MUs the net generation was 12,24,80,702 MUs all
the power of net generation was consumed by the respondent
itself.
(B) The petitioner CREDA submits that the respondent failed to
furnish the certified details of steam generation and power
generation from waste heat along with the certificate issued by
the Boiler inspector regarding Waste Heat Recovery Boiler
operating during the compliance period to prove that they have
generated and consumed from fossil fuel based co-generation
power plant.
(C) Considering the submissions of both the parties, we do not
disbelieve the submission made by the respondent, however, it
is apparent from the record that the respondent has failed to
provide details as required to the nodal agency as well as the
Commission during the proceedings of this petition. Hence, we
direct the respondent to submit the details with affidavit to the
petitioner nodal agency within 30 days stating the reasons for
none filing the details earlier. Any shortfall in RPO compliance
must be fulfilled by purchasing RE certificates by the end of
June 2018. We also warn the respondent if they fail in future in
compliance of the RPO including the submission of proper data
and certificates to the nodal agency, we will take strict action
and impose penalty upon him for such non-compliance.
xxxviii. M/s Prakash Industries Limited:-
(A) The respondent No. 38 M/s Prakash Industries Limited submits
that the power in plant of the respondent is generated through
waste heat recovery boilers for it's own consumption. Such
units or such source of energy has been considered as
renewable sources of energy by the Hon'ble APTEL in appeal
Nos. 57 and 54 of 2012. According to the respondent, their
own generation from WHRB was 258.78 MUs and their solar
RPO was 6.21 MUs and non-solar RPO was 49.66 MUs. Thus
the respondent has consumed excess 202.91 MUs power than
their RPO compliance for the year 2014-15. The respondent
Page 32 of 42
has also submitted certificate for the use of boiler from the
Boiler Inspection Department.
(B) The petitioner CREDA submits that the respondent failed to
furnish the certified details of steam generation and power
generation from waste heat along with the certificate issued by
the Boiler inspector regarding Waste Heat Recovery Boiler
operating during the compliance period to prove that they
have generated and consumed from fossil fuel based co-
generation power plant.
(C) We considered the submissions of both the parties. We
observe that there is no reason to reject the plea of
respondent that they have consumed much more power than
their RPO from their fossil fuel based co-generation power
plant and they are exempted from RPO for the year. We
decide that the respondent fulfilled RPO for the year 2014-15.
xxxix. M/s Nav Durga Fuels Pvt. Ltd. :-
(A) The respondent no. 39 M/s Nav Durga Fuels Pvt. Ltd. has
neither filed reply nor present at the time of hearings despite
given opportunities, hence we are constrained to decide the
matter on the basis of available records.
It is pertinent to mention here that the petitioner has filed
petition against the respondent on the basis of non submission
of RPO compliance report for the year 2014-15.
(B) The petitioner CREDA submits that the respondent has not
filed reply till date and therefore the petitioner is not in a
position to verify the data of the respondent. The petitioner
prays to declare that the respondent has failed to fulfill it's
RPO obligation for the year 2014-15.
(C) Looking to the respondent's attitude and petitioner's
submissions, we have gone through the file. We observe that
there is no data in the file regarding the power generation and
consumption by the respondent. We are surprised that without
any data how the respondent is included in the petition.
We direct CREDA to ensure before filing petition in future
whether, the entity has consumed power either from CPP or
taken power through open access and thereafter, keeping in
Page 33 of 42
view the quantum of captive consumption or power taken from
open access, enquire against the entity and thereafter, if
required initiate proceedings against the entity.
(D) We also express our displeasure towards the attitude of the
respondent. They have to honour the notices issued by the
Commission as a quasi judicial body and issued by the CREDA
as a nodal agency and put the factual position before them.
xl. M/s S.V. Power Pvt. Ltd. :-
(A) The respondent no. 40 M/s S.V. Power Pvt. Ltd. submits that
the unit of the respondent was under shut down for want of
raw material (coal and coal washery rejects) during the period
of FY 2014-15. The power plant of the respondent was re-
commissioned in the month of September 2015 and started
generation in the month of October 2015.
(B) The petitioner CREDA submits as the respondent has
informed that unit was shut down in the year, it can be
concluded that the respondent has not complied with the RPO
obligation in the year 2014-15.
(C) We have seen the submissions of both the parties. It appears
from the record that M/s S.V. Power was shut down in the
relevant period and neither generated nor consumed any
power from it's CPP. Hence we conclude that the respondent
was not obligated for RPO for the year 2014-15 as the plant
was shut down during the period.
xli. M/s Alok Ferro Alloys Limied :-
(A) The respondent No. 41 M/s Alok Ferro Alloys Ltd. admits that
they could not meet out RPO obligation for the year 2014-15,
but this condition emerged due to market condition as existing
during that time. It is also submitted that it was extremely
difficult to procure costly solar power. The respondent contrary
to the above submissions informed that the respondent has
set up 100 KW solar power generating station for itself to
meet it's solar RPO. The solar generating plant has already
been started in the month of March 2013. According to the
respondent, due to cash shortage RECs could not be
purchased and assured that in future on availability of cash
Page 34 of 42
the respondent will purchase the RECs, in case solar purchase
obligations remain unfulfilled. The respondent prays to
discharge him from the present suo-motu proceedings and
exempt the respondent from RPO-REC obligations for the year
2014-15.
(B) The petitioner CREDA submits that no relevant documents
have been provided by the respondent in accordance with the
format prescribed; hence the respondent has failed to comply
RPO obligations for the year 2014-15.
(C) We considered the submissions of both the parties. The
respondent has admitted that it could not fulfill RPO, but it is
explained that due to market condition and financial difficulty,
they could not fulfill RPO. We do not agree with reasons
submitted by the respondent for non fulfillment of RPO. We
direct the respondent to fulfill the RPO for year 2014-15 by the
end of June 2018.
xlii. M/s Shri Bajrang Power & Ispat Ltd, (Borjhara):-
(A) The respondent No. 42 M/s Shri Bajrang Power & Ispat Ltd.,
Borjhara Division has filed their reply separately but the
contents of the reply are same in nature. According to these
respondents, the Commission through orders in P. No. 98 of
2015 and P. No. 76 & 77 of 2015 already recognized the three
units of these respondent companies, as one entity. After
accumulation of data of the respondent companies, this
respondent is exempted from RPO as their own generation and
consumption from waste heat recovery based power generation
was 160.527 MUs, which was much more than the RPO
compliance (solar RPO 2.106 + non solar RPO 16.845 total
18.951 MUs) of the entity i.e. 3 units of the respondents.
(B) The petitioner CREDA submits that the respondent has not filed
reply and therefore, the petitioner is not in a position to verify
the data of the respondent. The petitioner submits that the
respondent failed to comply their RPO obligations for the year
2014-15.
(C) We considered the submissions of both the parties. There is no
reason to reject the plea of respondent that they have
Page 35 of 42
consumed much more power than their RPO from their fossil
fuel based co-generation power plant. We have gone through
the data submitted by the respondent with reply and conclude
that they have consumed much more power than their RPO
from their fossil fuel based co-generation power plant and they
are exempted from RPO for the year. We decide that the
respondent fulfilled RPO for the year 2014-15.
xliii. M/s Ind Synergy and Power Limited :-
(A) The respondent no. 43 M/s Ind Synergy and Power Limited
has neither filed reply nor present at the time of hearings
despite given opportunities; hence we have to see the data
available on records.
It is pertinent to mention here that the petitioner has filed
petition against the respondent on the basis of non submission
of RPO compliance report for the year 2014-15.
(B) The petitioner CREDA submits that the respondent has not filed
reply till date and therefore the petitioner is not in a position to
verify the data of the respondent. The petitioner prays to
declare that the respondent has failed to fulfill it's RPO
obligation for the year 2014-15.
(C) Looking to the respondent's attitude and petitioner's
submissions, we have gone through the file. We observe that
there is no data in the file regarding the power generation and
consumption by the respondent. We are surprised that without
any data how the respondent is included the petition.
We direct the CREDA to ensure before filing petition in future
whether, the entity has consumed power either from CPP or
taken power through open access and thereafter, keeping in
view the quantum of captive consumption or power taken from
open access, enquire against the entity and thereafter, if
required initiate proceedings against the entity.
We also express our displeasure towards the attitude of the
respondent. They have to honour the notices issued by the
Commission as a quasi judicial body and issued by the CREDA
as a nodal agency and put the factual position before them. We
Page 36 of 42
direct the respondent to take care in future and reply the
notices issued by the competitive authorities.
However, as per records available to us, the respondent's
plant was shut down in the relevant year for some reasons.
xliv. M/s Indsil Energy & Electrochemicals Ltd. :-
(A) The respondent no. 44 M/s Indsil Energy & Electrochemical
Limited submits that in the year 2014-15 their solar RPO was
0.343 MU and non-solar RPO was 2.742 MUs. Neither
certificates nor the power was procured hence, the shortfall of
2.742 MUs remain at the end of the year. It is also submitted
that due to global recession and highly competitive market
especially in the Steel and stainless steel industries, the
demand for company's core product has drastically reduced, as
a result the company suffered huge loss in the business. The
respondent requests to grant exemption from RPO-REC
obligation as an obligated entity for the year 2014-15.
(B) The petitioner CREDA submits that the respondent does not
have WHRB co-generation power and neither has bought RE
Certificate/ RE Power. The CREDA prays that the respondent
failed to comply RPO obligation for the year 2014-15 and
accordingly, suitable action may be taken against the
respondent.
(C) Considering the submissions of both the parties, we dismiss the
submission of the respondent that due to global recession and
highly competitive market especially in the Steel and stainless
steel industries, the company suffered huge loss in the
business and therefore, the respondent may be exempted from
the RPO. We direct the respondent to meet out the RPO
obligation for the year 2014-15 by purchasing RE certificates or
RE power by the end of June 2018.
xlv. M/s Hira Ferro Alloys Ltd.:-
xlvi. M/s Hira Power & Steel Ltd.:-
(A) The respondent No. 45 M/s Hira Ferro Alloys Ltd. and
respondent No. 46 M/s Hira Power and Steel Ltd. admit that
they could not meet out RPO obligation for the year 2014-15,
but this condition emerged due to market condition as existing
during that time. It is also submitted that it was extremely
Page 37 of 42
difficult to procure costly solar power. The respondents
contrary to the above submissions informed that they have set
up 100 KW solar power generating station for themselves to
meet their solar RPO. The solar generating plant has already
been started in the month of March 2013. According to the
respondents, due to cash shortage RECs could not be
purchased and assured that in future on availability of cash
they will purchase the RECs to meet out their RPO. The
respondents pray to discharge them from the present suo-
motu proceedings and exempt them from RPO-REC obligations
for the year 2014-15.
(B) The petitioner CREDA submits that no relevant documents
have been provided by the respondents in accordance with the
format prescribed; hence the respondents have failed to
comply RPO obligations for the year 2014-15.
(C) We considered the submissions of both the parties. The
respondents have admitted that they could not fulfill RPO, but
it is explained that due to market condition and financial
difficulty, they could not fulfill RPO. We do not agree with
reasons submitted by the respondents for non fulfillment of
RPO. We direct them to fulfill the RPO either through procuring
renewable power or REC for year 2014-15 by the end of June
2018.
xlvii. M/s Jai Balaji Industries Limited:-
(A) The respondent No. 47 M/s Jai Balaji Industries Ltd. submits
that their plant is completely closed since last few months and
so records related to the subject matter is not available so
they are not able to furnish the details as required.
(B) The petitioner CREDA submits as the respondent is unable to
produce any details, it can be concluded that the respondent
has not complied with the RPO obligations for the year 2014-
15.
(C) We considered the submissions of both the parties. It is not
clear from the reply of the respondent that from which day or
month the plant is closed. It is also not made clear by the
respondent that during the relevant year i.e. 2014-15 the
plant was closed or not. Hence, we are constrained to presume
Page 38 of 42
that during the relevant year 2014-15 the respondent has not
complied with the RPO and we direct the respondent to comply
the obligation either by purchasing RE certificate or RE power
by the end of June 2018.
xlviii. M/s Devi Iron & Steel Power Limited:-
(A) The respondent No. 48 M/s Devi Iron & Steel Power Limited
submits that they are exempt from RPO as their net co-
generation was 4.435 MUs from their co-located WHRB based
7.5 MW power generating plant. They have consumed 1.425
MUs as captive consumption and rest power was exported to
CSPDCL grid.
(B) The petitioner CREDA, in reply, submits though the respondent
claims exemption from RPO obligations in it's reply dated
06.10.2017, the respondent has failed to furnish the certified
details of steam generation and power generation from waste
heat along with the certificate issued by the Boiler inspector
regarding Waste Heat Recovery Boiler operating during the
compliance period to prove that they have generated and
consumed from fossil fuel based co-generation power plant.
The petitioner submits that the respondent failed to comply
their RPO obligations for the year 2014-15.
(C) Considering the submissions of both the parties, we do not
disbelieve the submission made by the respondent, however,
it is apparent from the record that the respondent has failed to
provide details as required to the nodal agency as well as the
Commission during the proceedings of this petition. Hence, we
direct the respondent to submit the details with affidavit to the
petitioner nodal agency within 15 days stating the reasons for
non-filing the details in earlier. Any shortfall in RPO
compliance must be fulfilled by purchasing RE certificates by
the end of June 2018. We also warn the respondent if they fail
in future in compliance of the RPO including the submission of
proper data and certificates to the nodal agency, we will take
strict action and impose penalty upon him for such non-
compliance.
Page 39 of 42
xlix. M/s National Thermal Power Corporation, Seepat
l. M/s National Thermal Power Corporation, Korba :-
(A) The respondent No. 49 M/s National Thermal Power
Corporation, Seepat and respondent No. 50 M/s National
Thermal Power Corporation, Korba have filed joint reply and
submit that they are neither distribution licensee, open access
consumer nor captive generating plant and therefore, do not
qualify as obligated entity as per the definition provided under
the RPO Regulations, 2013. It is further submitted that the
respondents being Central Generating Station are to be
regulated by the Central Electricity Regulatory Commission
(CERC) and not by the State Electricity Regulatory
Commission. Any dispute concerning these respondents has to
be adjudicated by the CERC.
(B) The petitioner CREDA, in reply, submits that no compliance
report has been submitted by these respondents and
therefore, requested to conclude that these respondents have
failed to fulfill their RPO for the year 2014-15.
(C) We have considered the submissions of both the parties.
These respondents submitted that they are generating stations
established by a Central Govt. under taking and they have no
captive consumption. They are neither distribution licensee nor
open access consumer and therefore, they are not covered
under the definition of obligated entity under the RPO
regulation, 2013.
There is no reason to disbelieve the submission by these
respondents. We hold that these respondents do not come
under the purview of definition of obligated entity. The CREDA
shall take care in future when it scrutinizes the list of obligated
entities.
li. M/s NTPC- Sail Power Company Limited :-
(A) The respondent No. 51 M/s NTPC- Sail Power Company
Limited has filed reply and submited that they are neither
distribution licensee, open access consumer nor captive
generating plant and therefore, do not qualify as obligated
entity as per the definition provided under the RPO
Regulations, 2013.
Page 40 of 42
(B) The petitioner CREDA, in reply, submits that no compliance
report has been submitted by the respondent and therefore,
requested to conclude that the respondent has failed to fulfill
their RPO for the year 2014-15.
(C) We have considered the submissions of both the parties. The
respondent submitted that they are generating station
established by a joint venture of NTPC and SAIL. Both NTPC
and SAIL are Central Govt. undertakings and they have no
captive consumption. The respondent is neither distribution
licensee nor open access consumer and therefore, the
respondent is not covered under the definition of obligated
entity under the RPO regulation, 2013.
There is no reason to disbelieve the submission by the
respondent. We hold that the respondent does not come under
the purview of definition of obligated entity. The CREDA shall
take care in future when it scrutinizes the list of obligated
entities.
lii. M/s Maa Kali Alloys Udyog Pvt. Limited:-
(A) The respondent No. 52 M/s Maa Kali Alloys Udyog Pvt. Limited
submits that their own generation from WHRB was 11.65 MUs
and their solar RPO was 0.39 MU and non-solar RPO was 3.08
MUs. Thus the respondent has consumed excess 8.57 MUs
power than their RPO compliance for the year 2014-15. The
respondent has also submitted certificate for the use of boiler
from the Boiler Inspection Department.
(B) The petitioner CREDA submits that the respondent failed to
furnish the affidavit and the certified details of steam and
power generation from waste heat along with the RPO
compliance report with the seal and signature of a Chartered
Accountant. Therefore, the information provided by the
respondent is not complete and in accordance with the format
prescribed and approved by the Commission.
(C) We considered the submissions of both the parties. We
observe that there is no reason to reject the plea of
respondent, which is supported by an affidavit and also a
certificate in form-v issued by the Boiler Inspectorate. We
Page 41 of 42
observe that the respondent has consumed much more power
than their RPO from their fossil fuel based co-generation
power plant and the respondent is exempted from RPO for the
year. We decide that the respondent fulfilled RPO for the year
2014-15.
liii. M/s Baldev Alloys Pvt. Limited:-
(A) The respondent No. 53 M/s Baldev Alloys Pvt. Limited submits
that the respondent is operating an 8 MW captive power plant
out of which 6 MW through WHRB and 2 MW through AFBC
boiler. The captive generation plant of the respondent
produces electricity for it's own use in the process of
manufacture of steel, sponge iron from WHRB. The respondent
power plant does not fall under the definition of "obligated
entity" as per the Regulations, 2013.
(B) The petitioner CREDA, in reply, submits though the respondent
claims exemption from RPO obligations in it's reply dated
28.11.2016, the respondent has failed to furnish the certified
details of steam generation and power generation from waste
heat along with the certificate issued by the Boiler inspector
regarding Waste Heat Recovery Boiler operating during the
compliance period to prove that they have generated and
consumed from fossil fuel based co-generation power plant.
The petitioner submits that the respondent failed to comply
their RPO obligations for the year 2014-15.
(C) Considering the submissions of both the parties, we do not
disbelieve the submission made by the respondent; however,
it is apparent from the record that the respondent has failed to
provide details as required to the nodal agency as well as the
Commission during the proceedings of this petition. Hence, we
direct the respondent to submit the details with affidavit to the
petitioner nodal agency within 15 days stating the reasons for
non-filing the details earlier. Any shortfall in RPO compliance
must be fulfilled by purchasing RE certificates by the end of
June 2018. We also warn the respondent if they fail in future
in compliance of the RPO including the submission of proper
data and certificates to the nodal agency, we will take strict
action and impose penalty on them for such non-compliance.
Page 42 of 42
14. During the hearing many of the respondents have raised issue
regarding the prescribed format for data collection. We advise the
respondents, if they feel any difficulty regarding the format to
resolve the issue through mutual meeting with the petitioner
CREDA.
15. In some cases we observe that the petitioner CREDA has not
analyzed the data available with due care, which resulted in
unnecessary prosecution of the parties. We direct CREDA to
scrutinize and analyze the data carefully and ensure that the entities
have consumed power either from CPP or through open access. The
entities selling power to the licensees without any self consumption
is not the obligated entities and, therefore, such entities need not be
prosecuted.
16. We also observe negligent attitude of some of the respondents
regarding compliance of notices issued by the Commission as well as
by the nodal agency CREDA. All the respondents are directed to
comply properly the notices issued to them by the competent
authorities; otherwise the Commission will be constrained to take
strict action against them.
17. Each of the respondents and the petitioner CREDA are directed to
keep in mind the directions given in relevant paragraphs of this
order and honour the directions appropriately.
18. The case is accordingly disposed off. Copies of order may be
communicated to the respondents and the petitioner nodal agency
CREDA.
Sd/-
(ARUN KUMAR SHARMA) MEMBER
Sd/-
(NARAYAN SINGH) CHAIRMAN