JUNE 2011 DHV, The Netherlands In association with DevCon Bangladesh Kranti Bangladesh DPM Bangladesh Institutional Strengthening and Project Management Technical Report No. 30 Subunit implementation plan SWC-17+18; NOAGRAM-GAZARIA CHENCHURI BEEL SUB-PROJECT AREA ADB Loan 2200-BAN(SF) / GON Grant 0036 BAN SOUTHWEST AREA Integrated Water Resources Planning and Management Project Bangladesh Water Development Board SOUTHWEST AREA Integrated Water Resources Planning and Management Project Bangladesh Water Development Board

Transcript of CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the...

Page 1: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

JUNE 2011

DHV, The Netherlands

In association with DevCon Bangladesh Kranti Bangladesh DPM Bangladesh

Institutional Strengthening and Project Management

Technical Report No. 30

Subunit implementation plan SWC-17+18; NOAGRAM-GAZARIA

CHENCHURI BEEL SUB-PROJECT AREA ADB Loan 2200-BAN(SF) / GON Grant 0036 BAN

SOUTHWEST AREAIntegrated Water Resources Planning and Management Project

Bangladesh Water Development Board

SOUTHWEST AREAIntegrated Water Resources Planning and Management Project

Bangladesh Water Development Board

Page 2: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

SSWRDSP Small Scale Water Resources Development Sector Project

SWAIWRMP South West Area Integrated Water Resource Management Project

TL Team Leader

TNA Training Need Assessment

UNO Upazila Nirbahi Officer

UP Union Parishad

UNDP United Nations Development Programme

WMCA Water Management Cooperative Association

WMG Water Management Group

WMO Water Management Organization

WMF Water Management Federation

WRMF Water Recourse Management Families

XEN Executive Engineer (BWDB or LGED)

GLOSSARY Beel Low-lying depression on the floodplain that generally retains

water throughout the year Baor Water body similar to an ox bow lake Jalmahal Water bodies leased only by Government – a “water estate” Khal Canal Kharif Summer season or summer crop Rabi Winter season or winter crop Union Parishad Lowest level of administrative organization

Page 3: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Acronyms and Abbreviations ADB Asian Development Bank

BRAC Bangladesh Rural Advancement Committee

BRDB Bangladesh Rural Development Board

BWDB Bangladesh Water Development Board

CDSP Char1 Development and Settlement Project of BWDB

DAE Department of Agricultural Extension

DWA Department of Women Affairs

XEN Executive Engineer (BWDB or LGED)

FAP Flood Action Plan

FCD Flood Control and Drainage

FCDI Flood Control, Drainage and Irrigation

DFID Department for International Development

GB Grameen Bank

BISCIC Bangladesh Small and Cottage Industries Corporation

GOB Government of Bangladesh

GPWM Guideline for Participatory Water Management

IGA Income Generating Activities

IWMP Integrated Water Management Implementation Plan

LEP Livelihood Enhancement Perspectives

LGED Local Government Engineering Department

MPE Marketing Promotional Enterprises

MOWR Ministry of Water Resources

NGO Non Government Organization

NWP National Water Policy

NWMP National Water Management Plan

PMO Project Management Office

PPTA Project Preparatory Technical Assistance

PRRA Participatory Rapid Rural Appraisal

PRS Poverty Reduction Strategy

RF Resettlement Framework

RP Resettlement Plan

RRP Report and Recommendations of the President to the Board of Directors, ADB

SIP Sub-unit Implementation Plan

SMO Sub-project Management Office

Page 4: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project BWDB

SWC-17+18; Noagram-Gazaria Page - i

TABLE OF CONTENTS

SUMMARY Page

1.0 INTRODUCTION …………………………………………………………………….………1

2.0 PROJECT HISTORY ……………………………………………………………………1-4

3.0 SUB PROJECT OVERVIEW ………………..…………………………………………..4-5

3.1 SIP Formulation …………………………………………………………………………………4

3.2 Location ………...……………………………………………………………………………….4

3.3 Topographic Data ……………………………………………………………………………….4

3.4 Climate …………………………………………………………………………………………..5

3.5 Communications / Road …………………………………………………………………………5

4.0 IMPACT ASSESSMENT ………………………………………….………………...……5-14

4.1 Proposed Interventions ……………………………..…………..……………….……….............5

4.2 Land Types………………….…………..…………………………….……….…………………6

4.3 Hydrologic Characteristics…………………………………………………………..…...........6-7

4.4 Agriculture…………………………………………………………………….………………...7

4.5 Fisheries…….……………………………………………………………….…………..…....10

4.6 Environment …………………………………………………..……………………..……….10

4.7 Surface Water……..…………………………………………..……………………..……….10

4.8 Socio Economy ……………………………………………….………………………….11-14

4.8.1 Stakeholders ………………………………………..…………………………..….11

4.8.2 Peoples Participation ……………………………………….…………………..…11

4.8.3 Training ……………………………………………………………………..………13

4.8.4 Gender and Livelihood ………………………………………..……………..……13

4.8.5 Collective Action Plan (CAP)………………………………………………….13-14

5.0 O & M ISSUES ……………………….………………………..……….……..………..14-15

6.0 FINDINGS, RECOMMENDATIONS AND CONCLUSIONS……….…………….…….15

7.0 MULTI - CRITERIA ANALYSIS ………………………………….……...…………….…16

8.0 TABLES ……………………………………………………………………....……..….17-30

Table - 1 : Land type analysis ……………………………………………………….……………..17

Table - 2 : Land use changes ……………………………………………………………………....18

Table - 3 : Household farm size distribution and occupation distribution ……….….…..……...19

Table - 4 : Production by land type impacts on SIP Agriculture ………………….…….……….20

Table - 5 : Total, Cereal and high value crop production Impacts on project area.......……… 21

Table -6 : Financial and Economic Impacts on SIP Agriculture ……………….…….………….22

Table -7 : Financial and Economic Impacts on SIP Fisheries ……………..……………..…… 23

Table - 8 : Cost Estimates of Proposed Works ………………………………..….………………24

Table - 9 :Annual O & M Cost ………………………………………………………………………24

Table -10: Crop Production Summary ……………………………………………………….…….25

Table -11: Fish Production Summary ……………………………………………………….……..25

Page 5: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project BWDB

SWC-17+18; Noagram-Gazaria Page - ii

Table -12: Economic Sensitivity ……………………………………………………………..……..25

Table -13: Financial Cash Flow ……………………………………………..…………….…..…...26

Table -14: Economic Cash Flow …………………………………………………...…..….……….27

Table -15: Multi-Criteria Analysis ……………………………………………………………..…....28

Table -16: Elevation, Area & Storage on SIP Area ………………………………..……..………29

Table -17 : Observed data river water salinity impact…….…………………...……………....…30

9.0 CHARTS ………………………………………………………………………………...18-30

Chart - 1 : Land use changes ……………………………………………………….………...18

Chart - 2 : Farm size distribution …………………………………...…………….………….19

Chart - 3 : Occupational distribution of households ………………………………..………..19

Chart - 4 : Total, Cereal and high value crop production Impacts on project area……………21

Chart - 5 : Potential open water fish production gross impacts ………………………..…….23

Chart - 6 : Area-Elevation-Storage Curve ………………………………………..…………..29

Chart -7 : Observed data river water salinity impact curve.………………………..…………30

10.0 FIGURES

Figure – 1: Chenchuri beel Sub Project Map……………………………….…..……………..2

Figure – 2: SWC-16 Map……………………………………………..……………...………….3

Figure – 3: Crop Calendar……………………………………………………….……………8-9

Figure – 4: SWC-16 WMG Map…………………………………….……………..…………..12

11.0 ANNEXES

Annex-A: Agriculture

Annex-B: Fisheries

Annex-C: Environment

Annex-D: Socio Economy, Gender and Livelihood

Annex-E: Water Management Organization (WMO)

Annex-F: O & M

Annex-G: Hydrology

Annex-H: Training

Page 6: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 1

SWC-17+18, Noagram-Gazaria Scheme

1. INTRODUCTION Chenchuri Beel Sub-project (SP), located in Narail, Lohagora and Kalia Upazila of Narail District is bounded by the Chitra River to the west and the Nabagonga River to the north,east and south. Covering a gross area of about 25,560 ha and net area of about 17,900 ha. In the north-west corner of the sub-project there exists a pumped irrigation scheme of about 1,100 ha implemented by BWDB. Two inclined irrigation pumps one at Kamapur and the other at Gandarbakhali are there in the scheme with a capacity of about 0.60 cumec each to draw water from the Chitra river. The pre-feasibility study of the SP was done in 1993 under FAP-4, South-west Area Water Resources Management Project. The study proposed compartmentalization as water management strategies. During feasibility study of the SP under Feasibility Study of South-West Area Water Resources Development Project in 1998, it was felt that integrated development of agriculture, Fisheries and navigation are needed as per desire of the people of the SP area. These objectives can be met through engineering works including rehabilitation and limited construction of embankment, improvement of irrigation and drainage channels, bank protection works and rehabilitation and limited construction of structures. To reduce poverty through increasing food production and creating employment generation South-west Area Integrated Water Resources Planning and Management Project (SAIWRPMP) has been taken up by BWDB in 2005, where people’s participation shall be ensured in planning, design, implementation, monitoring and O&M of the project. The total area under the project (SAIWRPMP) covers an area of 100,000 ha. Two sub-projects (i) Chenchuri Beel sub-project and (ii) Narail sub-project covering 57,000 ha of land has been taken up for immediate implementation. This was prepared through a Project Preparatory Technical Assistance (PPTA). The rest 43,000 ha area of the project will be implemented after feasibility studies from amongst 11 Nos candidate sub-projects preliminary identified in the PPTA study. Considering the hydrological boundary, the Chenchuri Beel Sub-Project has been divided in to 18 Nos Sub-unit Implementation Plan (SIP) ( Figure-1) for better Operation and Maintenance of the Sub-Project SWC-17+18 ( Figure-2) is within Chenchuri Beel sub-project, having a gross area of about 1301 ha and net cultivable area of about 911 ha ( 70% of gross area ). 2. PROJECT HISTORY

Following the consecutive disastrous floods of 1987 and 1988, the Government of

Bangladesh initiated a five-year study programme namely Flood Action Plan (FAP)

comprising 26 components that included five regional studies.The South West Area Water

Resources Management Project (SWAWRMP) was one of the regional studies, namely FAP-

4, carried out at pre-feasibility level between 1991 and 1993 with ADB and UNDP assistance.

The study identified 30 sub-projects (SP) and prioritized them in terms of need,

implementation period, rate of return and social and environmental impacts. As a result of the

analysis, seven SPs covering about 250,000 ha, were recommended for carrying forward to

feasibility level study and detailed design. The recommendation included the Narail and the

Chenchuri Beel sub-projects.

Subsequently, the South West Area Water Resources Development Project (SWAWRDP)

was initiated as a follow up to conduct feasibility studies of the recommended seven SPs in

order to select the best alternatives for detailed design and implementation. The study,

carried out during 1996-1997 with ADB assistance, showed that the Narail and the Chenchuri

Beel sub-projects stood out as first and second respectively in priority ranking.

Page 7: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 2

Figure – 1 : Chenchuri Beel sub-projects Map

Page 8: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 3

Figure – 2 : SIP SWC-17+18, Noagram-Gazaria Scheme Map

Page 9: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 4

The present South West Area Integrated Water Resources Planning and Management

Project (SWAIWRPMP) is the ultimate outcome of a Project Preparatory Technical Assistance

(PPTA) of ADB executed during 2003-2004.It was decided to divide the selected Sub Projects

into smaller hydrological units for IWMP formulation and efficient implementation as

independent schemes. In the process the Narail Sub Project was broken down to 25 smaller

sub-units.

However, after detailed scrutiny it was found that the scheme boundaries were often

geographical borders defined by roads with open culvert/bridge requiring modification to

define the sub-unit as a hydrological entity as far as practicable.

3. SUB PROJECT OVERVIEW 3.1 SIP Formulation

For the purpose of sound and effective implementation and management system, each sub-project area (FCD/I scheme) will be divided into independent hydrological sub-units (as far as possible) as a unit of implementation. The Consultant Team are now reviewing these and in consultation with the BWDB, beneficiary and LGED (if required) are revising/ modifying the plan and design as necessary. The IWMPs will be implemented on the basis of individual Sub-unit Implementation Plans (SIPs) and will follow the steps described below with the engagement of NGOs, Community Based Organizations (CBOs) and private service providers. To assure a manageable implementation of the various stages, the individual sub-units in any sub-project will be grouped in batches ( Batch-1, 2 & 3). The Consultants, in consultation with the relevant stakeholders, will prepare 4 (four) sample SIPs from Narail sub-project. The preparation of the remaining SIPs will be outsourced to a Firm, to be procured by the BWDB, PMO and trained for the purpose by the ISPMC. Related documents (especially the EIA, EMP and RP) would be prepared by the Firm/NGO staff under the guidance and supervision of PMO/SMO/Consultant. The same procedure will be followed for the implementation of IWMPs for the additional sub-project areas to be selected. The original concept of preparing the balance SIPs were by NGO / Firms, now have been changed and being implemented through ISPM Consultants / PMO with the help of Facilitators, Research Assistants and Planning Engineers.Batch-3 contents 5 SIPs ( 3 in NSP & 2 in CSP, both cluster ) are being prepared jointly by ISPM/PMO. Now previous draft SIP report ( 8 nos ) will be revised new style as batch-3, SWC-17+18 is one of them. 3.2 Location

The Sub-unit SWC-17+18 (titled Noagram-Gazaria Scheme in the PPTA) with a gross area of about 1,471 ha is contained within Compartment # 8 of the Chenchuri Beel Sub-Project.The Sub-unit is bounded by Baje Babra-Chandropur road on the north, Nahaganga river embankment to the east and south east, Chitra river embankment on southwest and Liner khal on the west.Located partly in Peruli and Purulia unions of Kalia Upazila, the area comprises 13 villages (3 in Peruli, 10 in Purulia) and are shown in (Figure -1).

3.3 Topographic Data

The topography ranges from about 2 m PWD in the south to about 3 m PWD along the northern and eastern boundaries forming a gently slope from north to south. The area between the Liner khal and the Chanchuri khal has nearly flat topography dominated by lands with elevations between 2 m PWD and 2.5 m PWD. The area between the Chanchuri khal and the Nabaganga dike has an exactly similar feature dominated by lands with elevation between lass than 1.5 m PWD to over 2 m PWD thus forming a mild lateral slope from west to east and are shown in ( Figure-2).

3.4 Climate

Page 10: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 5

The project area belongs to the coastal zone with extreme tidal influence. The nearest climatic stations of the sub-project, are Jessore (E-17) and Khulna (E-20) and the nearest rainfall station to the project area is located at Narail (R-461). Project area experiences two distinct seasons such as, Monsoon season and Dry season. Monsoon season, lasting during July to September, is characterized by high temperature, heavy rainfall and high humidity. Dry season during November to March has moderate cool dry weather with little or no rainfall. Pre-monsoon period and Post monsoon period are two truncation periods (comparatively of shorter duration) that separate the monsoon and the winter seasons. The pre-monsoon period is again associated with nor-wester and cyclone storms while post monsoon period is fairly smooth with declining temperature, humidity and storms frequency. It may be added that the project area occasionally suffers from the devastation of severe cyclone storms accompanied by high tidal surges generally during the beginning and the end of monsoon season in the month of May and October. The pre-monsoon rainfall, Annual maximum water level are furnished in Annex – G.

3.5 Communications / Road

The area is accessible by the metalled regional road (Narail-Kalia) down to Baje Babra village in the east and then by metalled Nabaganga embankment towards southwest down to the southern tip near confluence of Nabaganga and Chitra rivers and then northwestwards over the metalled Chitra embankment upto Pateswari (Figure-2). All the villages are located on the relatively higher peripheral lands along the northern road and the eastern and southern embankments along the two rivers.

The main transport on these roads is generally by motorized vehicle, rickshaw and rickshaw van or on foot. Small country boats are also used for communication on the internal khals or canal, particularly in the beel areas during the monsoon season. River transport forms an important link to the peripheral parts of the Sub Project area and its surroundings.

4. IMPACT ASSESSMENT 4.1 Proposed Interventions

The existing infrastructures in the sub-project have been implemented in 1985-86 under programme of DFC-I project. The sub-project area is protected from annual flooding by embankment around most of its periphery. The Regulators are located on the peripheral embankments along Chitra and Nabaganga rivers. Most of the existing drainage channels and khals have been silted up thus reducing the hydraulic capacity of the drainage system as a whole. It is necessary to Re excavation. Due to better performance of this sub project repair and rehabilitation of the facilities, some new construction / rehabilitation works are proposed as shown below:

New Construction of Takimara Ragulator1 Ragulator….……2 Vent - 1.52m X 1.82m

Thorough rehabilitation of Pateswari Ragulator….……….…10 Vent - 1.52m X 1.82m

Thorough rehabilitation of Takimara Ragulator….……...….…2 Vent - 1.52m X 1.82m

Thorough rehabilitation of Noagram Ragulator….………….…1 Vent - 1.52m X 1.82m

Re-Sectioning of Existing Embankment……………………….9.291 km earthwork Ch: Km 70.05 to km 70.95=0.90 km Ch: Km 71.015 to km 71.82=0.805 km Ch: Km 73.61 to km 75.51=1.90 km Ch: Km 76.00 to km 78.656=2.66 km Ch: Km 78.38 to km 80.61=2.23 km Ch: Km 81.930 to km 82.73=0.80 km

Re excavation of khal ……………………………………..…….23.80 km earthwork Liner khal =5.00 km Takimara-Mora khal =4.60 km Noagram khal =1.80 km Naridanga khal = 2.60 km Sourar khal =1.80 km

Page 11: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 6

Majalir khal =3.40 km Gozaria khal =1.80 km Kumarer khal = 1.80 km At Aterhat New cut = 1.00 km

1mx1m Box sluice …..…….………………………………….….3 Nos

Foot Bridge over Mora, Majalir khal & Noagram khal……...…3 Nos

WMG Office ……………….………………………………..…….2 Nos

Supply of Deep Tubewells (DTW)………………………...…...10 Nos Location of Box culvert /1mx1m Box sluice/ WMG Office and Deep Tubewells (DTW). Will be selected as per WMG/WMA advice. The above Interventions cost is shown in table- 8.

4.2 Land Types

Land Classification in planning of BWDB projects is carried out in relation to average flooding for three conditions:

i) pre-project when interventions to modify the flood regime are yet to be put in place;

ii) post-project when facilities are installed and are in operation. The post-project scenario depicts the modified condition of the area for future planning.

iii) without FCD, when the system deteriorates to the extent that there will be free flow between the river and the beel areas.

The sub unit area SWC-17+18 put down (i) & (ii) condition. The basin or sub unit area water level does not depend only river water level. It depends on the internal water level and also proposed & existing interventions. Inadequate internal water level data we had putted gauge inside the SIP area, 20 years (1987 to 2007) rainfall data analysis have done, calculate drainage modulus and also checked the size of regulator. Considering all circumstances the internal water level at monsoon govern 2.81 mPWD which is shown annex-G, hydrology part.

The Pre-Project water level with in the project is 2.81 mPWD, then the land type pattern

would be :

Fo land (0-.3 m flood) -el. 2.81 m and above;

F1 land (0.3 -.6 m flood) -el. 2.81 m down to 2.51 m;

F2 land (0.9-.1.80 m flood) -el. 2.51 m down to 1.91 below

F3 land (>1.8 m flood) -el. 1.01 m and below

After rehabilitation of all required intervention the internal water level will be 2.51 mPWD, then

the land type pattern would be :

Fo land (0-.3 m flood) -el. 2.51 m and above;

F1 land (0.3 -.6 m flood) -el. 2.51 m down to 2.21 m;

F2 land (0.9-.1.80 m flood) -el. 2.21 m down to 1.61 below

F3 land (>1.8 m flood) -el. 0.71 m and below

The Pre-Project & Post-Project land type and percentage of land change are shown in Table-1 & chart-1 and also are presented in Annex-G. 4.3 Hydrologic Characteristics

A close look of Figure -1 reveals that the Liner khal carries most of the drainage of the SP from way up in north including areas around the Narail-Lohagora road. The huge flow was

Page 12: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 7

designed to be discharged into the Chitra partly through the 10-vent Pateswari regulator and partly by Chenchuri khal (taking off from Liner khal near northern boundary) through the 2-vent Takimara regulator. According to thumb-rule (1,000 to 1,500 ha per 1.52 m x 1.83 m vent) the Pateswari regulator should be able to evacuate about 60 percent of the entire SP. Presumably, the remainder was designed to be drained through the relatively smaller peripheral Baghbaria, Modina, Noagram, Jadavpur and Bagdanga (1+2) regulators. Any failure of the smaller structures would affect only their localized command areas but malfunctioning of Pateswari and Takimara would be disastrous for a large area. However, for the Pateswari dependent northern part the congestion problem would be less pronounced because of relatively steeper gradient than the flatter south where all the water is likely to accumulate. And this is exactly what has happened over the last decade when all the regulators, excepting those at Bagdanga in the western part of the SP, have become dysfunctional. Now it has become rather difficult to distinguish Compartment 7 (SWC 16) and Compartment 8 (SWC-17+18) as independent entities because of coverage under one sheet of water during peak monsoon. In other words, the area has suffered a regression almost to a pre-project scenario.

As for the Sub-unit SWC-17+18, it can be seen from Table 1 that about 22% of the area belongs to F2 and F3 categories of land implying susceptibility to flooding from .9 m to over 1.8 m while 77% belongs to F0 and F1 categories that may suffer none or shallower flooding. Figure -2 shows that a thin strip of F0 land (about 42%) is located along the northern boundary with 1 more isolated spot on the western boundary below which a strip of F1 land (about 36%) occurs along northern and western fringes. Rest of the Sub-unit is covered by F2 lands (about 21%) all around and F3 lands in the middle. Such occurrence of different types of lands has rendered the terrain saucer-shaped.

4.4 Agriculture Assessment of the existing situation of agriculture in the project area has been based on production, yield and other data collected from the respective Upazila Agriculture Offices, supplemented by participatory appraisal surveys, through Focus Group Discussion ( FGD ) in the field and interviews with farmers, village leaders and other knowledgeable persons about agricultural activities in their areas. Developments in agriculture expected to result from the implementation of the proposed project are based on the present situation in the area and a careful consideration of the expected impact of the proposed engineering works on physical conditions in the project areas. The major impact of these works will be on the basis of lands, benefiting from irrigation, flood control and drainage and ensuring safety of land and homestead from erosion and inundation. By Focus Group Discussion (FGD) the river water of the areas become saline which creates problem for irrigating during pre monsoon cropping. Thus test of river water was carried out from Dec. ’09 to Jun. ‘10 at various locations of existing regulator. The observed river water salinity are shown Table – 17 & Chart- 7.The salinity of this area is controlled by the Jadavpur, Takimara and Pateswari regulator. Needs a action plan through WMG / WMA for appropriate O & M of the regulators according to threshold (tolerance) value. Threshold (tolerance) value for rice is => 2.0 PPT.In Figure-4 shown pre-project and post-project Crop Calendar according to land type and cropping pattern, Sub project area hydrograph and also show this area observed salinity impact. Cropping pattern, production etc are furnished in Annex – A. The main sub-project benefit (positive impact) is increased agriculture production (Table 4 & Table 5), specially an overall increase of 5798 MT, 3491 MT for cereals; production of non-cereal will increase by 2340 MT and cash crop (Aromatic rice, Maize, Winter Vegetables and Soybeans ) will be increase by 5115 MT in future and are presented in Table-5. Crop intensity Pre-Project is 212% and Post-Project will be achieved 250 %.The Table-10 shows the crop production summary, Table 6 illustrates crop area, yield, production, and value of production by land type under both pre and post project conditions.

Page 13: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 8

Figure-3 : Pre Project and Post Project Crop Calendar & Cropping pattern Carry on

Page 14: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 9

Figure-3 : Pre Project and Post Project Crop Calendar & Cropping pattern

Page 15: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 10

4.5 Fisheries Fisheries are an important sub-sector contributing to the socio-economic activities of the Narail Sub project area. Table 7 and Chart 5 show the estimated potential open water fisheries impacts, in terms of habitat, yield and production changes. As FCD sub-project the structure will remain closed during monsoon and open water fisheries will be reduced. There is negative impact on fish production. Capture fish product is decreases and culture fish product is increases due to sub-project intervention. From Table-7 & chart-5 and Table-11 it is seen that culture fisheries will be increased from 185 MT to 332 MT ie. by 147 MT however capture fisheries will be decreased from 34 MT to 19 MT ie. by 15 MT, after rehabilitation of this Sub Project Area. Some habitat expansion / improvement will be achieved through water retention in the beel and khal. Training program for culture fish practices will be provided to WMG / WMA. Also, improvements in fish production will depend substantially on efforts directed towards stocking and expanding pond aquaculture and cooperative aquaculture in the khal and in the beel. Residual impacts on subsistence fisheries (primarily landless and small / marginal farmers) are expected to be partially or entirely compensated by positive employment and nutritional impacts associated with increased agricultural activity and production. Fishing / navigation as a primary occupation is reported to be insignificant of sub-project residents. There may be a need for the WMG / WMA to address the need for rehabilitation of this group. 4.6 Environment The sub-unit reflects the typical scenario of rural areas near coastal zone where lack of rapid industrialization including brick-fields and salt water shrimp cultivation is yet to cause any pronounced degradation of environment. Of course, some downslide has occurred but that is comparable to the general pattern and the observed changes are indeed, less alarming than those found in many other locations of the coastal belt. For example, siltation of khals and creeks under tidal influence is a common phenomenon near the coast which has been exacerbated by the reduction of upland flow in the Ganges. It has also caused migration of some aquatic animals while in fishery and forestry sectors many exotic varieties have replaced the indigenous species purely for commercial reasons. The environmental study has examined the following environmental components:

physical;

biological;

human and economic; and

quality of life. The study has been carried out in three phases as below and are presented in Annex-C.

initial environmental assessment (IEE);

environmental impact assessment (EIA); and

environmental management plan (EMP). 4.7 Surface Water The availability of surface and ground water was assessed from TR-15 of MPO and FAP 4 reports. Annex-G of Hydrology are presented the availability of surface water in the area. Moreover invert level of the regulators in peripheral embankment are quite low (-0.60 mPWD), allowing 0.64 m to 2.27m depth of water during dry season. Water can be made available in the khals through the regulators during each high tide, which can be stored in the khal for dry season irrigation by closing the C/S lift gate.

Page 16: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 11

4.8 Socio Economy 4.8.1 Stakeholders Located in Purulia and Peruli Unions under the Kalia Upazila, the sub-unit area is spread, partly or wholly, over 13 villages of Narail District. The population is estimated as 16730 with a sex-ratio of 152 males per 148 females as against the national average of 106.6.The proportion of functionally landless people (owning < 0.2 ha) stands at 40% of the population. The number of households (HH) stands at 3179 with agricultural farming as the predominant means of income. The number of female headed households is about 8% and they are mostly poor. The Farm-size distribution and the occupational pattern are presented in both Tabular form and Graphics in Table 3, Chart 2 and Chart 3 and also are presented in Annex-D.

Fifteen (15) nos traditional fishermen households exists in this sub–unit area since about 8th generation, all are of Hindu religion and social order is in the name of Rajbongshi and also fifty two (52) nos non-traditional Muslim fishermen households exists in this area. Now most of the fishermen have changed their profession in course of time due to lack of open water fish in the river, beel and khals having less availability of fish due to over fishing. Some fishermen are now engaged in agriculture, catching fish in the beel during monsoon, some time caching fish in Gher (Close water fishing inland) on hire and fish trading. Most of the fishermen families are becoming affluent day by day; they are taking education and trying to live a better life. As per field data about 12% of traditional & non-traditional fishermen are connected with agriculture, they catch fish in the beel during monsoon and also catch fish in Gher (Close water fishing) on hire; about 45 % of traditional & non-traditional fishermen are engaged in culture fish production, fish trading and labour and about 42% of traditional & non-traditional fishermen are fishing in khal and river, fishing in beel during monsoon and fishing in Gher (Close water fishing) on hire. In this area some Muslim and Hindu fishermen ( Total=114 nos) are also catching fish in beel area during monsoon period, actually they are farmer, daily labourers, Rickshaw Pooler etc. They have been shown as part time fishermen. So there have no adverse impact in the traditional Hindu fishermen community.

Sustained lack of O & M has led to deterioration of FCD projects to such an extent that those have been rendered dysfunctional and need thorough rehabilitation with the inclusion of IWRM. One of the fundamental objectives of the SWAIWRM project is, therefore, to formulate restoration plans for the under performing schemes through participatory process with the ultimate aim of gradual transfer of O & M responsibilities to the Stakeholders/Beneficiaries. Associated with this is the important aspect of the beneficiaries' contribution to O & M in order to induce the sense of belonging and ownership of the scheme among the stakeholders. 4.8.2 Peoples Participation In order to involve stakeholders, public consultations would be held from grassroots at village upto Union, Upazila and District level involving stakeholders, local elites, LGIs, line agency and government representative. Instead of making a presentation, problem identification and the perceived solution there to would be extracted from the stakeholders through extensive and intensive dialogue. It ultimately leads to the realization of the need to form WMOs for sustainability of implemented schemes. The entire process would follow guidelines provided in the GPWM. This sub unit area is located in Purulia & Peruli (2) Unions under Kalia Upazilas, the sub-unit area is spread, partly or wholly, over 13 villages of Narail District. So far, consultation meetings are to be held in all villages and ultimately at the union level. Proceedings of all the meetings will be duly minuted along with the list of participants. Meanwhile, training needs for WMO members have been identified, training modules formulated and annual training plan prepared. All relevant detail about villages and procedures for WMO forming to ensure participatory planning, implementation through O & M and monitoring in the long-run. 10 Nos WMG will be formed and are presented in Figure-4; they will be registered in WMG with the Doc (with MOU) and look after future O & M of the water infrastructure and are presented in Annex-E.

Page 17: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 12

Figure – 4 : SIP SWC-17+18, Noagram-Gazaria Scheme WMG Map

Page 18: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 13

4.8.3 Training It needs to be stressed that rehabilitation of dilapidated project facilities is not the only means to an end; training of the stakeholders (EAs) and beneficiaries) in all domains is an equally essential project component in order to realize the stipulated benefits as well as to ensure sustainability. Therefore, provision has been made to cater to the needs of training and demonstration including necessary physical works in the spheres of Agriculture, Fisheries, Environment, Gender and Livelihood and WMO. Detailed training plan on each subject has been prepared spanning 2009-2010, 2010-11, 2011-12 and 2012-13 with the expectation of continuity beyond and are presented in Annex-H. 4.8.4 Gender and Livelihood Gender and livelihood are two complementary aspects of the SWAIWRPM project. The gender aspect relates to involvement of women in water management organizations. At least 30 per cent of the seats of the managing committee of the WMG and WMA shall be allocated for women as per the Guideline for Participatory Water Management (GPWM). This project got a chance for livelihood enhancement. Crop and fish cultivation through better water resource management are the important and major livelihood enhancement activities for the poor which can only be ensured after the successful implementation of proposed scheme. Especially the poor are interested to participate in construction and maintenance of water structure through LCS. It will increase their income. Women members of the poor household are interested to have skills on home based jute works, duck rearing and puffed rice making, sweet rice ball (Moa), sesame toffee, pressed rice etc to undertake IGA and are presented in Annex-D. 4.8.5 Collective Action Plan (CAP)

Collective Action Plan (CAP) of the Sub-unit Implementation Plan (SIP) will be prepared after formation of Water Management Group (WMG) and Water Management Association (WMA) with consultation with WMG members. The related (Agriculture, Fishery, O & M and Gender & Livelihood etc.) information for the CAP will be collected by the Facilitators through Focus Group Discussion (FGD) from the WMG members. Farther additional information will be collected through “Walk Through” jointly by the Project Management Office (PMO), ISPMC, Facilitators and the WMG members. After collection and analyzing the data the CAP of the SIP will be prepared. The CAP may be on the following fields:

(A) Agriculture:

i) Soil test for acidity, Alkalinity and PH and water test for Salinity are needed. These tests can be done by WMG through DAE or other sources. A kit for Water Salinity test may be provided to each WMG.

ii) Procurement of quality seeds and fertilizers may be done by WMG from the dealers and distribute the same to the beneficiaries centrally.

iii) In order to minimize the organic matter in soil, demonstration on compost preparation could be practices at the farmer’s field.

iv) Infrastructures development needs to be planned to minimize the scarcity irrigation water.

v) Training Farmers need training on modern methods of crop production, cultivation of High value crops (HVC), Training on IPM / ICM and practical training through establishment of demonstration plots on different crops and varieties.

vi) Marketing WMG can take initiatives to sell their products collectively to a big business centre.

Page 19: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 14

(B) Fisheries:

i) To enhance fisheries production each WMG may be provided with a kit for water quality test and Fisheries Sub-committee of WMG can take initiatives for soil testing from BFRI, Jessore.

ii) WMG can procure quality fry / fingerling from the reputed hatchery and distribute the same to the beneficiaries.

iii) To minimize the shortage of organic fertilizer in pond for increasing productivity, cow dung / compost to pond can be practiced. Additional amount of compost need to be provided to fish pond.

iv) Use of high doses of pesticides to be discouraged through practicing IPM / ICM.

v) Training Rigorous training need to be imparted to enhance knowledge on modern methods of production and also high value fish, establishment of demonstration pond would help the farmers for increasing fish production and dissemination of technology.

vi) Marketing WMG can take initiatives to sell their fish collectively to a big business centre.

(C) O & M

i) New Construction of Takimara Ragulator1 Ragulator….……2 Vent - 1.52m X 1.82m

ii) Thorough rehabilitation of Pateswari Ragulator….……….…10 Vent - 1.52m X 1.82m

iii) Thorough rehabilitation of Takimara Ragulator….…….….…2 Vent - 1.52m X 1.82m

iv) Thorough rehabilitation of Noagram Ragulator….…….….…1 Vent - 1.52m X 1.82m

v) Re-Sectioning of Existing Embankment……………….9.291 km earthwork vi) Re excavation of khal ………………………..…..…….23.80 km earthwork vii) 1mx1m Box sluice …..…….………………………………….….3 Nos viii) Foot Bridge over Mora, Majalir khal & Noagram khal……...…3 Nos ix) WMG Office ……………….………………………………..…….2 Nos x) Supply of Deep Tubewells (DTW)………………………...…...10 Nos

Training a) WMA members shall have to be trained for operation of the structures for

proper Water Management. b) BWDB officials should also be given the same training. c) Training on maintenance is also be imparted to both WMG and BWDB

officials. d) Gate operators should be trained regarding gate operation including practical

training at their respective gate sides. e) The topics of training may be (i) maintenance need assessment (ii) type of

maintenance work (iii) role and responsibility of each party (iv) maintenance schedule (v) budgeting and (vi) monitoring.

The identified Collective actions will be transformed into implementation plans to be supported under the project. The names of the facilities to be managed by WMG/WMA will be specified in the CAP

Page 20: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 15

5. O & M ISSUES Inadequate budgetary allocation is a major factor for the lack of upkeep of FCD projects ultimately rendering them dysfunctional to such as extent that necessitates thorough rehabilitation. It is, indeed, time that concerned parties (Beneficiary, PAP, BVVDB, Donors etc.) adopt a policy that this shall be the major rehabilitation. Another major factor behind this is lack of stakeholder-participation in project activities. It is well established that active stakeholder-participation is a 'must' for sustainability of FCD projects and now stakeholder-involvement in entire life cycle of any water development project from identification through O&M has been made mandatory in the National Water Policy (NWPo). The ultimate objective is to gradually transfer the O&M responsibilities to the stakeholders reducing pressure on the government exchequer where the line agencies of the government would play the role of facilitators. However, their services would still be needed in case of major works requiring capital investment.With this end in view, the rehabilitation of the sub-unit has been planned by incorporating the concepts of IVVRM and stakeholder participation in order to ensure last rehabilitation and sustainability.To that end, the Project requires formation of VVMOs by beneficiaries on the basis of villages or clusters thereof with at least 70% enrolment of whom about 30% are to be women. To demonstrate their willingness each VVMO is required to make on upfront contribution to the capital investment equivalent to one year O&M costs. Maintenance requirement of FCD schemes are generally classified as: Preventive : Undertaken throughout the year that includes minor repairs of embankments, removal of weeds, water hyacinths etc. from khals and greasing, painting, minor repairs of and removal of debris from hydraulic structures; Periodic : Requiring greater resources than preventive maintenance based on checklist prepared at the end of each monsoon that includes resection of dykes, re-excavation of khals and larger repair of structures such as partial or full replacement of gates, hoist, rubber seals etc. ; and Emergency Repair: Unforeseen and unpredictable caused by sudden massive floods or events like cyclone leading to breach or overtopping of embankment and/or severe damage to structures. The preventive/routine maintenance, in its entirety, appears the responsibility of-the V\/MGs while the periodic maintenance might see a mix of involvement and cost-sharing. On the other hand, in case of emergency the VVMGs might be conveniently engaged with their physical labour as part of the contribution in kind / borne by BWDB. However, a Maintenance Plan for the Sub-unit (SWC-17+18) has been formulated where responsibilities have been delineated and costs for periodic maintenance worked out as shown in Table 9.The total cost of preventive and periodic maintenance for SWC-17+18 has been estimated as Tk.17.387 lac per annum of which WMA share would be Tk. 4.158 lac with BWDB bearing Tk.13.229 lac. The WMA / WMG share comes to Tk. 404/ha/year and are presented in Annex-F. 6. FINDINGS, RECOMMENDATIONS AND CONCLUSIONS The PRA examined three questions related to sub-project (here SWN 9) viability and sustainability: (i) Is there broad popular support for this sub-project, (ii) Is there any opposition to the sub-project, (iii) Is the sub-project socially acceptable, (iv) Is there any negative environmental impact and (v) Are the beneficiaries willing to form in to a WMG / WMA, pay O

Page 21: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB

SWC-17+18; Noagram-Gazaria Scheme 16

& M contribution, assist with land acquisition and take full responsibility for the operation and maintenance. In relation to these questions, the findings of the CAP and work through (One Go) are: People activity supported the sub-project. There is no opposition. Socially acceptable No adverse impact on environment. The beneficiaries expressed willingness to form WMG / WMA, pay O & M contribution, assist with land acquisition and to take full responsibility for O & M after the sub-project is complete. This sub-project (SIP-9) passed each of the standard social, environment and economic viability tests used for SAIWRPMP sub-projects. The relevant financial and economic information is presented in tables 10 through 14. The status of the sub-project relative to the SAR sub-project selection / acceptability criteria is shown in Table 15. As such the sub-project is socially acceptable, technically economically viable and economically feasible. Considering people demand and lower development cost (Benefit-Cost ratio 0.78, Table-14) and economic ( 9.00%, Table-14 ) and financial (7.00 %, Table-13) rate of return, it is recommended to implement the SIP. The economic sensibility has been shown in Table-12. All residual adverse environmental impacts of the sub-project are expected to be either not significant, or acceptable under the circumstances except reduction of capture fisheries. There is also no adverse impact on the eco-system. 7. MULTI - CRITERIA ANALYSIS In addition to the economic sensitivity tests, a preliminary exercise of Multi-Criteria Analysis has been performed with available data an insight gained through PRAs. The result is presented as a matrix in Table 15 which shows the proposed scheme is technically feasible, economically viable and socially acceptable.

Page 22: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

APPRAISAL

TABLES & CHARTS

Page 23: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

ANNEX – A

AGRICULTURE

Page 24: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 1

Noagram-Gajaria Scheme (SWC-17 + 18)

Agriculture Summary

The gross area of SWC-17 + 18 is 1471 ha. According to PPTA net cultivable area (NCA) has

been estimated at 70% of the gross area for Chenchuri Beel Sub-Project. Thus, the NCA of the

SIP is calculated at 1029 ha with a present cropped area of 2178 ha yielding a cropping

intensity of 212%. Future total cropped area has been estimated at 2569 ha with a cropping

intensity of 250%.Annual production of Cereal crops will be increased by 3286 MT after

rehabilitation. In the future Cropping Pattern, 18 % of the cropped area will be covered by High

Value Crops (HVCs).

Based on the hydrological analysis ,the land area under the SIP have been figured out as

F0,F!,F2 & F3 as per present & future governing water levels on which total cropped area,

cropping pattern, cropping intensity and total production have been estimated.

Data furnished in the report are based on the agricultural information collected from the field

(SIP area) through Focus Group Discussions (FGDs) by the Facilitators and compiled by the

Research Assistants. Moreover, for authentication, secondary data from the local DAE office

has been consulted.

A total of 10- Water Management Groups (WMGs) have already been organized & formed in

the Sub-Unit. Data for Collective Action Plan (CAP) have been collected from the WMG-

members by the Facilitators by ‘Walkthroughs’ and Focus Group Discussions (FGDs).

Present Agriculture

The present agriculture in the sub-unit is hampered by poor drainage, resulting in water logging in the lower areas during the wet season. Conversely, the higher areas suffer from water shortage especially during the pre-monsoon season. From the gathered data, it is known that 60% of the land are being irrigated through STWs and LLPs.

Present cropping pattern and production have been provided in Tables 3 and 4. Agriculture in

the sub-unit is dominated by rice cultivation covering over 50% of the total cropped area

followed by jute (19%), wheat(12%), mustard (11%) and pulses (8%)

Present production of major crops (cereals) have been calculated as 3581 metric tonnes of

which rice is 3057 MT and 524 MT of wheat is produced annually.

Page 25: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 2

Future Agriculture

Future cropping pattern and production have been provided in Tables 5 and 6. Future

agriculture under changed scenario, shows that cereal crops (rice, maize and wheat)will cover

72% of the total cropped area followed by Jute (9%),Vegetables(7%), Soybean (7%), and

Oilseeds (5%) with an estimated cropping intensity of 250% and total cropped area of 2569 ha.

In the future Cropping Pattern, 18 % of the cropped area will be covered by High Value Crops

(HVCs).

Annual production of major crops (cereals) have been estimated as 6867 MT of which rice will

be 5761 MT ,Maize will be 666 MT and wheat will be 440 MT. Thus, annual Cereal production

of the Sub-Unit has been estimated to be increased by 3286 MT after rehabilitation.

To facilitate this shift the DAE,NGOs and the Project will provide extension support to the

farmers in the form of improved agricultural techniques, integrated pest/crop management,

home gardening (for women), etc. Detailed agricultural activities for the SIP have been

furnished along with the estimated budget provisions in the form of training, demonstrations,

agricultural fairs, motivational tours, nursery development, etc . Further, a Bar diagram has

been shown to spell out various activities for agricultural development in the Sub-Unit area

throughout the entire Project period.

A budget has been reserved for an amount of BDT 60.55 million for the agricultural program for

total project under implementation. The agricultural development (enhancement) activities of

the SIP have been estimated at BDT 14 lacs for the entire Project period.

Page 26: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 3

1.0 Description

The gross area of SWC 17 +18 is 1471 ha. According to PPTA net cultivable area (NCA) has

been estimated at 70% of the gross area for Chenchur beel Sub-Project. Thus, the NCA is

calculated at 1029 ha with a present cropped area of 2178 ha yielding a cropping intensity of

212%.Future total cropped area has been estimated at 2569 ha with a cropping intensity of

250%. Production of Cereal crops will be increased by 3286 MT after rehabilitation. . In the

future Cropping Pattern, 18 % of the cropped area will be covered by High Value Crops

(HVCs).

Based on the hydrological analysis, the land area under the SIP have been figured out as

F0,F!,F2 & F3 as per present & future governing water levels on which total cropped area,

cropping pattern, cropping intensity and total production have been estimated.

Data furnished in the report are based on the agriculture information collected from the field

through Focus Group Discussions (FGDs) by the Facilitators and compiled by the Research

Assistants. Moreover, for authentication, the secondary data from the local DAE office have

been consulted.

A total of 10-Water Management Groups (WMGs) have already been organized & formed in

the Sub- Unit. Data for Collective Action Plan (CAP) have been collected by the Facilitators

from the WMG-members during FGDs.

1.1 Present Agriculture

The Tables and items below are the compiled information on the agricultural data of the SIP,

which to be considered as Present Agriculture:

Table-1: Crops & Varieties cultivated during various seasons

Seasons Crops Crops & Varieties

Rabi Kharif-1 Kharif-II

Paddy Wheat Pulse Mustard Paddy Jute Paddy

Boro: HYV – BRRI dhan 28, BRRI dhan 29. Hybrid – Hira, ,ACI, ,Laltir, ,etc. Aus: Ratul, Ratna, Buri ,Gambhur--local varieties. HYV Aman: BR-11 Aman: Jabra, Hori, ,,Manohar,Sona Digha, Lal Digha-- Local varieties.

Page 27: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 4

Table-2: Yield of Major crops/ha.

Crops Variety Average Yield per ha(MT)

Paddy Aus (Local) 1.2

Aman (Local) 1.5

HYV Boro 5.0

Hybrid Boro 5.5

Pulse 2.8

Mustard 1.5

Wheat 2.0

Jute 2.5

The present agriculture in the sub-unit is hampered by poor drainage, resulting in water logging in the lower areas during the wet season. Conversely, the higher areas suffer from water shortage especially during the pre-monsoon season. From the gathered data, it is known that 60% of the land are being irrigated through STWs and LLPs.

Present cropping pattern and production have been provided in Tables 3 and 4. Agriculture in

the sub-unit is dominated by rice cultivation covering over 50% of the total cropped area

followed by jute(19%), wheat(12%), mustard (11%) and pulses (8%)

Present production of major crops (cereals) have been calculated as 3581 metric tonnes of

which rice is 3057 and 524 metric tonnes of wheat is produced annually.

Table - 3 : Present Cropping Pattern by Land Type

Land type and flood

depth

Cropping Pattern No. of Crop

Net area (ha)

Cropped area (ha) Rabi Kharif - I Kharif - II

FO (0 - 30 cm)

Pulses B.Aus HYV T. Aman 3 70 210

HYV Boro Jute 2 153 306

Wheat Jute 2 162 324

Mustard B.Aus LT.Aman 3 50 150

Sub-total 435 990

F1 (31 - 90 cm)

Wheat Jute 2 100 200

Pulses B.Aus 2 113 226

Hybrid Boro

LT. Aman 2 69 138

Mustard B.Aus 2 92 184

Page 28: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 5

Sub-total 374 748

F2 (91 - 180 cm)

HYV Boro B.Aman Cont’d 2 120 240

Mustard B.Aman Cont’d 2 100 200

Sub-total 220 440

Grand Total 1029 2178

Cropping Intensity - 212%

Table - 4 furnishes the existing crop wise area, yield and total production which need to be improved

through the required development of infrastructures, re-excavation of khals etc. through which

agricultural production will obviously by increased.

Table - 4: Present Position : Crops with their production by Land Type

Total Cropped

area

Net cultivated

area

Cropping intensity Land type and

flood depth Name of

Crop Area (ha)

Average Yield

Total productio

n

(ha) (ha) (%) (mt/ha) (mt)

2178 1029 212

FO (0 - 30 cm)

Pulses 70 2.8 196

Jute 315 2.5 787.5

HYV Boro 153 5.0 765

HYV T. Aman

120 3.5 420

B.Aus 120 1.2 144

Wheat 162 2 324

Mustard 50 1.5 75

Sub-total 990 2711.5

F1 (31 - 90cm)

Wheat 100 2 200

Pulses 113 2.8 316.4

Jute 100 2.5 250

B.Aus 205 1.2 246

Hybrid Boro 69 5.5 379.5

LT.Aman 69 2.5 172.5

Mustard 92 1.5 138

Sub-total 748 1702.4

F2 B.Aman 220 1.5 330

Page 29: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 6

(91 - 180 cm)

HYV Boro 120 5.0 600

Mustard 100 1.5 150

Sub-total 440 1080

2178 1029 212 Grand Total 2178 5493.9

Present annual rice production has been calculated as 3057 MT and wheat as 524 MT. Thus, annual Cereal production is 3581 MT.

Extracts from the collected Data: Regarding availability of seeds, most of the farmers have opined that the condition is good. Following steps could be taken for better availability of seeds.

1.1.1 Steps for seed availability

1. Own collection.

2. Farmers should get directly from the Government.

3. Supplying of good seed by BADC.

4. To arrange training on production and preservation of seed.

1.1.2 Irrigation Facilities From the gathered data, it is known that 60% of the land are being irrigated through STWs and LLPs.

1.1.2.a Problems of using irrigation facilities

1. Water scarcity in the khals during draught period. 2. Saline water enter into the field during Mid-March to April and damages Boro rice. 3. Inactive regulator/Sluice gates in the khals. 4. Excessive siltation in the khals. 5. Poor drainage facilities. 6. Number of STWs is inadequate as per requirement. 7. Low water discharge through Swallow Tube Well during dry season.

For further expansion of irrigation facilities, following points may be taken into consideration.

1.1.2.b Steps to improve irrigation facilities

1. Immediate repairing of existing regulator or reinstallation of new regulator. 2. Re-excavation of existing khals to easy and quick drain out of water from the field. 3. Excavation of new khals. 4. Supply of electricity for irrigation. 5. Deposition of pure water for irrigation.

Page 30: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 7

1.1.3.a Water Salinity

In the SIP- area, there exists some amount of water salinity but within permissible limit upto end of February.

1.1.3.b Ways to mitigate Water Salinity

To check the entrance of saline water from the river into the khals by repairing or installing regulators.

Use of saline tolerant rice varieties.

Embankment need to be repaired.

To test water salinity regularly.

Use of zypsum fertilizer.

.1.4.a Soil salinity

Soil of the SIP-area are quite fertile and responsive to addition of fertilizers as per characteristics of Gangetic alluvium. There is a complain of soil salinity problem at the lower areas- beel areas.

1.1.4.b Ways to mitigate soil salinity

Awareness raising among the farmers

Soil testing in field as per farmers’ demand

Cultivation of salinity tolerant rice varieties

Check the entrance of saline water from the river into the khals by repairing or installing regulators

Embankment to be repaired

Use of zypsum fertilizer.

1.1.5.a Extent of Fertilizer Use

Farmers are generally using over and imbalanced doses of chemical Fertilizers because of lack of adequate knowledge about proper doses of Fertilizers requiring training on crop-wise Fertilizers application.

Farmers are not also using Compost/Organic Fertilizers.

1.1.5.b Reasons for not using Compost/Organic Fertilizers

Lack of domestic animals/cows.

Cow dung is used as fuel due to scarcity of firewood.

Less awareness and lack of knowledge of Compost preparation

Farmers have no ideas about Green manure.

1.1.6.a Use of Insecticides

Farmers are using moderate doses of insecticides. They do not possess adequate knowledge on the required doses of insecticides application.

Page 31: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 8

1.1.6.b Practice of IPM/ICM by the Farmers

Farmers have little knowledge on IPM/ICM .Extension activities in this regard needs to be geared up.:

1.1.7.a Training topics for the Farmers

1. Compost Preparation & Green manuring 2. Fertilizer and Water Management. 3. Cultivation of HYV Rice

4. IPM/ICM

5. Soil testing

6. Water salinity testing

7. Nursery development

8. Vegetables Production

1.1.7.b Training topics for Women

1. Homestead Gardening

2. Poultry rearing

3. Seed preservation

4. Goat & Cow rearing.

The following problems are being identified which hamper better crop production. If these

problems could be solved, more production could be achieved.

1.1.8.a Problems of crop production

1. Water logging.

2. Soil salinity

3. Water salinity

4. Lack of awareness on modern technology of agriculture development

5. High price of inputs

6. Lack of good quality of seeds

7. Proper Water management

8. Marketing facilities.

Following points need to be considered to mitigate the production problems through the project

activities and regular programme of DAE.

1.1.8.b Steps to mitigate those problems

1. Re-excavation of canal to prevent water logging.

2. Improving the irrigation system and water management.

3. Reducing the price of diesel.

4. Reducing the price of Fertilizer.

5. Using the improved technology in agriculture development.

Page 32: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 9

6. Perform the duties of agricultural officers/staffs through close contact with the farmers

to make aware of soil quality, uses of seeds and fertilizers, techniques of pest control

etc. i.e. technology dissemination.

People are expecting better production and livelihood from this project. Project intervention will

hopefully fulfil their aspirations through their active participation.

1.2 Future Scenario

Future cropping pattern and production have been provided in Tables 5 and 6. Future

agriculture under changed scenario, shows that cereal crops (rice,maize and wheat) cover 72%

of total cropped area followed by Jute (9%),Vegetables(7%), Soybean (7%), and Oilseeds

(5%) with an estimated cropping intensity of 250% and total cropped area of 2569 ha. In the

future Cropping Pattern, 18 % of the cropped area will be covered by High Value Crops

(HVCs).

Annual production of major crops (cereals) have been estimated as 6867 MT of which rice will

be 5761 MT, maize will be 666 MT and wheat will be 440 MT. Thus, annual Cereal production

of the Sub-Unit has been estimated to be increased by 3286 MT after rehabilitation.

Table - 5: Future after Rehabilitation: Cropping Pattern by Land Type

Land type and flood depth

Cropping Pattern No. of Crop

Net Area (ha)

Cropped area (ha) Rabi Kharif - I Kharif - II

FO (0 - 30 cm)

Winter Vegetables

T.Aus 2 185 370

Wheat Jute HYV T. Aman 3 110 330

Soybean Maize HYV T. Aman 3 121 363

Aromatic Rice

HYV T. Aman 2 175 350

Sub-total 591 1413

F1 (31 - 90 cm)

Wheat Jute HYV T. Aman 3 110 330

HYV Boro Sesame HYV T. Aman 3 120 360

Soybean T.Aus HYV T. Aman 3 50 150

Hybrid Boro HYV T. Aman 2 100 200

Sub-total 380 1040

F2

(91-180cm) HYV Boro B.Aman Cont'd 2 58 116

Sub-total 58 116

Grand total 1029 2569

Page 33: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 10

Cropping Intensity =250% Table - 6 : Future with Project Position : Crops with their Production by Land Type

Total Cropped

area

Net cultivated

area

Cropping intensity Land type and

flood depth Name of Crops

Area (ha)

Average Yield

Total production

(ha) (ha) (%) (mt/ha) (mt)

Winter Vegetables

185 17 3145

2569 1029 250

FO (0 - 30 cm)

T.Aus 185 3 370

Wheat 110 2 220

Soybean 121 2 242

Maize 121 5.5 665.5

Jute 110 2.5 270

HYV T. Aman

406 3.5 1421

Aromatic Rice

175 5.5 962.5

Sub-total 1413 7296

Wheat 110 2 220

F1 Jute 110 2.5 275

(31-90 cm) HYV T. Aman

380 3.5 1330

Hybrid Boro 100 5.5 550

Sesame 120 1.5 180

Soybean 50 2 100

T.Aus 50 3 150

HYV Boro 120 5.0 600

Sub-total 1040 3405

(91-180 cm) B.Aman 58 1.5 87

HYV Boro 58 5.0 290

Sub-total 116 377

2569 1029 250 Grand total 2569 1178

Future cereal production has been estimated as 6867 MT of which rice will be 5761MT,Maize will be 666 MT and wheat will be 440 MT. Present cereal production has been calculated at 3581 MT. Thus, annual cereal production will be increased by 3286 MT.

Page 34: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 11

2.0 Future Agricultural Development Programs

After collecting, compiling and analysing the data based on existing agriculture conditions and

discussions with the farmers of the sub-unit; Following agricultural development programs have

been planned for implementation by the project.

2.1 Demonstration Programs

Demonstration is an important method for rapid extension of improved agro-technology of

various crops. Major objective of the demonstration is to introduce new crops and improved

technology with a view to increasing productivity and thereby income generation of farmers.

Modern varieties of crops and other technologies developed by various National Agricultural

Researches(NARs)Institutes are disseminated to farmers through demonstration. The

extension of Agricultural Services should be widely facilitated so that farmers can obtain advice

and support when they want to try new crops to increase cropping intensity and production.

Demonstration farms/trials plots will be established in sub-project area.

Following detailed Demonstration Programs have been formulated for the SIP for the

entire Project period.

Page 35: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 12

echnology Demonstrations for FY, 2010-11, 2011-2012,2012-13 (for 3- years):

Technology

Units Farmers Number Unit Cost Demo.

Cost (Tk.) Cost for field

day (Tk.)

Remuneration for the

Supervising Officer (Tk.)*

Total Cost (Tk.)

No. Area Male Female (Tk.)

1. Demo. on compost preparation 3 Nos. 1 dcm. each 2 1 3000 9000 5000 each for 100 farmers

3000 per demo.

33000

3. Demonstration of Urea Super Granules (GUTI’ Urea) to Boro

10 Nos. 33 dcm. each

10 - 2500 25000 5000 each for 100 farmers

3000 per demo.

105000

5. Demonstration on Sex Pheromones 10 Nos. 33 dcm. each

7 3 3000 30000 5000 each for 100 farmers

3,000 per demo

110000

FY 2009-10

TOTAL 23 Nos. 19 4 64000 248000

2. Varietal Demo. of Wheat (BR-42, Bijoy, Prodip)

5 Nos. 33 dcm. each

5 - 3000 15000 5000 each for 100 farmers

3000 per demo 55000

3. Demonstration of Maize Production 12 Nos. 33 dcm. each

12 - 5000 60000 5000 each for 100 farmers

3000 per demo 156000

4. Demonstration of Mustard (BARI-6) 10 Nos. 33 dcm. each

10 - 2500 25000 5000 each for 100 farmers

3000 per demo 105000

FY 2010-11

TOTAL 27 Nos. 27 100000 316000

1. Varietal Demo. of Boro (BR-47) 4 Nos. 33 dcm. each

4 - 2500 10000 5000 each for 100 farmers

3000 per demo 42000

2. Demonstration of Soybean Production 10 Nos. 33 dcm. each

5 5 2000 20000 5000 each for 100 farmers

3000 per demo 100000

FY 2011-12

TOTAL 14 Nos. 9 5 30,000 142,000

* One field level officer will supervise each demonstration intensively throughout the whole crop season (approx. 3-months). Summery of cost for Demonstration : 1. Cost for the FY 2010-11=Tk.2,48,,000/- 2. Cost for the FY 2011-12= Tk 3,16,500/- 3. Cost for the FY 2012-13 =Tk. 1,42000/-

Page 36: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 13

Total Tk. 7,06,500/-( Total Taka Seven lacs six thousand five hundred only).

Page 37: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 14

2.2 Training programs for farmers

Human resources development through training of farmers, officials and trainers will be

provided under the Agricultural Extension Component.

The farmers will be trained by DAE/Livestock/Fishery staff after getting TOT from the Project.

Training will be provided to the farmers for integrated pest management to minimize the

negative impact of agro-chemicals on the environment. The use of compost will also reduce the

possible negative impacts agro-chemicals on the environment. Agricultural extension focusing

on home gardens and livestock to women for increased production of vegetables will be

provided.

A detailed Training Plan along with the cost estimates have been formulated for

the beneficiaries of the SIP is presented as follows:

Page 38: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 15

Detailed Costing of Training for FY, 2010-11, 2011-2012,2012-13 (for 3- years):

Sl. No.

Topic of Training Participants Number of

Participants

Tra

inin

g A

llo

wan

ce/

da

y (

A)

No

.of

tra

ine

e (

B)

No

. o

f d

ay (

C)

Tra

inin

g A

llo

wan

ce

(to

tal)

(A

XB

XC

) =

D

No

. o

f sessio

n

(E

)

Ho

no

rari

um

rate

/ sessio

n (

H)

No

. o

f g

rou

ps

(G

)

To

tal

h

on

or

raru

im

(EX

FX

G)

= H

Tra

ns

po

rt

su

pp

ort

(I)

To

tal

Tra

ns

po

rt

(BxI)

= J

Ven

ue

ch

arg

e (

K)

Mis

c. (L

)

GR

AN

D

TO

TA

L=

(D+

H+

J+

K+

L)

(Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.)

1. Training on Plantation Activities Water Management Group (WMG) Members

40 =(M 30 + F 10) 200 40 2 16000 10 400 2 8000 100 4000 300 500 28800

2. Vegetables Gardening -ditto- 50 =(M 0 + F 50) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

3. Fruit Trees (Quick growing) Plantation

-ditto- 50 =(M 0 + F5 0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

4. Seed Production Technology Water Management Group (WMG) Members

50 =(M 40 + F 10) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

6. Compost Preparation -ditto- 50 =(M 40 + F 10) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

FY 2010-11

TOTAL 240 10 96000 10 40000 24000 1500 2500 164000

1. Fertilizer Management Water Management Group (WMG) Members

50 =(M5 0 + F 0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

2. Winter Vegetables Production -ditto- 50 =(M 40 + F1 0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

3. Integrated Crop Management (ICM)

Water Management Group (WMG) Members

50 =(M5 0 + F 0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

Page 39: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 16

4. Compost Preparation -ditto- 40 =(M 40 + F 10) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

FY 2011-12

TOTAL 200 8 80000 8 32000 20000 1200 2000 135200

1. Fruit Trees Management WMG Committee Members and other Beneficiaries

50=(M50+F0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

2. Fertilizer Management -ditto- 50=(M50+F0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

3. Water Management for Boro -ditto- 50=(M50+F0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

4. Pest Control for Winter Vegetables

-ditto- 50=(M50+F0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

5. Post-harvest Technology of Rice

-ditto- 50=(M0+F50) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

FY 2012-13

TOTAL 250 10 100000 10 40000 25000 1500 2500 169000

Summery of cost for Training :

1. Cost for the FY 2010-11 =Tk. 1,64,000/-

2. Cost for the FY 2011-12 =Tk 1,35,200/-

3. Cost for the FY 2012-13 =Tk. 1,69,000/-

Total Tk.4,68,200/-(Total Taka Four lacks sixty eitht thousand two hundred only)

Page 40: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 17

2.3 Agricultural Fairs

Agricultural fair is one of the most important and effective method which disseminate modern

technology at the shortest possible time. It helps the people as well as farmers to know the

latest agricultural technologies. Agricultural fair also creates a liaison with other development

organizations. The objectives of the fair is to disseminate agricultural technologies of the

farmers in a short time.

At least one agricultural fair will be arranged annually at the Sub-unit area during winter season.

- Budget for one agricultural fair will be Tk 80,000/-

- One agricultural fair will be organized in each SIP area where the farmers will be able

to show and see different products

2.4 Farmers’ Motivational Tours

Motivational Tour is another aspect to enrich the farmers knowledge by sharing their

experiences with other successful farmers and visits to renowned agricultural research

and development institutes

Budget for one batch of Motivational Tour will be Tk. 75,000/-(approx)

- Motivational Tour will be conducted in batch of 30 farmers .

- One batch of farmers (30) will be selected from each SIP area.

2.5 Nursery Development

Agriculture Nursery is another tool for dissemination of different extension messages. Major

objectives of the nursery will be to enhance production of vegetables, spices and fruits, and

thereby reduce malnutrition problem of people. Farmers will be able to purchase seed, saplings

and seedlings of the above noted items from the nursery at reasonable price. They will be also

able to receive free advice from the DAE staff for establishment of nursery.

At least one nursery need to be established in each SIP. A complete guideline will have to be

prepared for management of the nursery by the Resource persons. The cost of all inputs will

be borne by the project.

The total cost per nursery may be estimated at Tk.75,000/-(approx).

2.6 Total cost

Total cost of expenditures for Agricultural activities in the SIP for the entire Project period will be

as per following break-up:

a. Total Demonstration cos = Tk. 7,06,500/-

b. Total Training cost = Tk. 4,68,200/-

c. Cost for Motivational Tour = Tk. 75,000/-

d. Cost for Agricultural Fair = Tk. 80,000/-

e. Cost for Nursery Development = Tk. 75,000/-

--------------------------------------------------------------------------

TOTAL = Tk.14,04,700/-

(Total Taka Fourteen lacs four thousand seven hundred will be spent for

different agricultural activities at the SIP area)

Page 41: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 18

2.7 Summary of Future Agricultural Activities:

For undertaking the agricultural development activities for SIP # 16, a schedule has been

prepared to implement those activities in the form of Bar diagram.

Items 2010-11 2011-12 2012-13

a) 1. Farmers’ Training b)

2.Demonstrations of crops & varieties

3.Farmers’ Motivational Tours

4.Agricultural Fair

5.Seed production activities

6 Nursery Development

7. Devt. of Marketing Facilities

Page 42: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 19

3.0 Collective Action Plan (CAP) During FGDs, following initiatives were recorded from the WMG-members and they are agreed

to work collectively under the supervision of the Senior Facilitators and Community Facilitators

which can be summarized by the following Table:

WMG Name/No./

Village.

List of Initiatives Training topics Remarks

Chameli/

S-18/1/

Dariaghata,

Fuldah

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

7. Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

Management

c. Vegetables production

d.IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development,

Beli /

S-18/2/

Amtola

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

a. Compost preparation

b. Fertilizer and Water

management

c. Vegetables

production

d.IPM/ICM

e. Soybean production

Keya/

S-18/3

Kalamonkhali,

Bajebabra

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6. Vegetables Production.

a. Vegetables production

b.IPM/ICM

c. Soybean production

d. Seed preservation

e. Nursery development,

Nabaganga/

S-18/4

Noagram

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

7.Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development,

Page 43: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 20

Ekata/

S-18/5

Diadanga

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

7.Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development,

Suravi/

S-18/5A

Perbishnupur

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6. Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Seed preservation

Hasnahena/

S-18/6

Burikhali

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development,

Rajanigandha/

S-18/6A

Pervumbag

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

7. Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Nursery development,

Kanakchapa/

S-18/7

Perulistan

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

Page 44: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 21

6.Cultivation of High Value

Crops

(HVCs).

7.Collective Marketing.

f. Seed preservation

g. Nursery development,

Gandharaj/

S-18/8

Satbaria,Pateswari

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Nursery development,

N0tes:

‘CAP’ Opportunities explored by WMG –members: After organizing Focus Group

Discussions (FGD) with the Water Management Group (WMG) members, following activities

have been identified in order to implement with the initiatives of the WMG-members

collectively.

1. Soil testing:- WMG- members given the responsibilities to the Agriculture sub-

committee to test their soil in order to have ideas about acidity, alkalinity, soil PH. and

other nutritional status of soil.

Agriculture sub-committee of the WMG will collect soil samples from the interested

farmers’ field with the assistance of the Facilitator and take necessary measures to test

the soil by the Department of Agricultural Extension(DAE) or Soil survey Resources

Institute(SRDI).

In doing so, Farmers will be able to select different crops and varieties suitable for their

land. They will discuss the results of soil testing In WMG-meetings and plan their crops

to be cultivated during the next season.

Further, through soil testing, the nutritional condition of the soil especially the macro-

nutrients (N,P,K,Zn) status can be measured and Farmers will be able to plan for

recommended fertilizer doses for different crops.

2. Water salinity test:- Each WMA will be provided with a water salinity test kit by which

WMG-members will be able to test water of their locality in order to know the salinity

level. After knowing the salinity level during the pick-time of the season ,they can decide

to cultivate some saline –tolerant varieties of rice. Thus Farmers can mitigate the crop

losses.

3. Procurement of quality Seeds and Fertilizers:-Agriculture sub-committee of the WMG

will explore the seasonal requirements of seeds and fertilizers for a season and communicate

with the respective organizations (like BADC, DAE, commercial seeds and fertilizer

agencies, etc.) by providing indent ahead of time. They will take delivery of the materials

centrally on behalf of the WMG and distribute the same to the WMG-beneficiaries according

to their requirement. Thus individual carrying costs can be minimized and less chance of

adulteration of inputs could be ensured.

Through discussions and decisions at WMG-meetings, they can use the WMG –fund for

Page 45: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 22

the procurement of required inputs. Thus, Farmers can get the inputs timely and with the

reasonable prices at their door-steps.

Further, some of the WMG will try to allocate Seeds and Fertilizer sub-dealership from the

Govt. organizations.

4.Establish demonstration plots: Project will conduct some demonstrations at the Farmers’

field in introducing new crops and varieties. WMG will adopt those with the technical

assistance from DAE and Project. WMG decide in the meeting to materialize the program

through sub-groups by taking lease of land and sharing the benefits by the WMG –

members. In this way, farmers will be able to know the technology jointly and economic

benefits. Through demonstrations, new technology will be adopted and practiced in the area.

Collective demonstrations by the WMG-members will be encouraged.

5.Practice Integrated Pest/Crop Management ( IPM/ICM):-WMG-members will decide

collectively for not using any pesticides in their crop field. It is rarely impossible to practice

IPM/ICM individually ,it must be a collective effort. WMG-members will decide at which

area and which crop field will be taken for IPM/ICM. By practicing IPM/ICM, Farmers can

reduce the cost of cultivation without using insecticides in the crop field. Thus, the produced

crops will be considered as non-hazardous for human consumption.

6. Cultivation of High Value Crops (HVCs): Some vegetables, Maize, Soybean are being

considered as HVCs which can be introduced at the WMG-areas. As these are somewhat

new crops in the area, there might be little risk for cultivation. So, it is decided at the WMG-

meetings to cultivate some HVCs collectively on the part of WMG.

WMG can take a piece of land on lease and cultivate some HVCs and take the benefits to

WMG-fund.

7. Collective Marketing: Farmers normally sale their products individually at the nearest

markets where they generally sale at lower prices. But if the WMG take the initiatives to

collect seasonal agricultural commodities and store at the custody of the Executive

Committee and communicate with the wholesale/retail markets and bargain with them

for higher prices. Thus, by collective marketing, individual farmers can get better prices

at a time and can plan for next season’s cropping practices.

Topics of Training asked by the WMG-members: The following training topics were

selected by the WMG –members thr4ough which they can be equipped with knowledge and

techniques for better agr4icultural production:-

a. Compost preparation

b. Fertilizer and Water management

c. Vegetables production

d. IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development, etc.

Training modules will be developed and supplied to the participants during the training

programs.

Page 46: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 23

List of topics for Training Modules: 1. Integrated Pest/Crop Management (IPM/ICM).

2. Soybean Production.

3. Maize Production.

4. Aromatic Rice(BRRI dhan-50- Banglamoti).

5. Summer Tomato.

6. Saline tolerant Rice (BRRI dhan-47).

7. Methods of Agricultural Extension and Communication with Farmers.

8. Winter Vegetables Cultivation.

9. Fruit Trees Nursery Development.

10. Rice-cum-Fish Culture.

Page 47: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 1

Noagram-Gajaria Scheme (SWC-17 + 18)

Agriculture Summary

The gross area of SWC-17 + 18 is 1471 ha. According to PPTA net cultivable area (NCA) has

been estimated at 70% of the gross area for Chenchuri Beel Sub-Project. Thus, the NCA of the

SIP is calculated at 1029 ha with a present cropped area of 2178 ha yielding a cropping

intensity of 212%. Future total cropped area has been estimated at 2569 ha with a cropping

intensity of 250%.Annual production of Cereal crops will be increased by 3286 MT after

rehabilitation. In the future Cropping Pattern, 18 % of the cropped area will be covered by High

Value Crops (HVCs).

Based on the hydrological analysis ,the land area under the SIP have been figured out as

F0,F!,F2 & F3 as per present & future governing water levels on which total cropped area,

cropping pattern, cropping intensity and total production have been estimated.

Data furnished in the report are based on the agricultural information collected from the field

(SIP area) through Focus Group Discussions (FGDs) by the Facilitators and compiled by the

Research Assistants. Moreover, for authentication, secondary data from the local DAE office

has been consulted.

A total of 10- Water Management Groups (WMGs) have already been organized & formed in

the Sub-Unit. Data for Collective Action Plan (CAP) have been collected from the WMG-

members by the Facilitators by ‘Walkthroughs’ and Focus Group Discussions (FGDs).

Present Agriculture

The present agriculture in the sub-unit is hampered by poor drainage, resulting in water logging in the lower areas during the wet season. Conversely, the higher areas suffer from water shortage especially during the pre-monsoon season. From the gathered data, it is known that 60% of the land are being irrigated through STWs and LLPs.

Present cropping pattern and production have been provided in Tables 3 and 4. Agriculture in

the sub-unit is dominated by rice cultivation covering over 50% of the total cropped area

followed by jute (19%), wheat(12%), mustard (11%) and pulses (8%)

Present production of major crops (cereals) have been calculated as 3581 metric tonnes of

which rice is 3057 MT and 524 MT of wheat is produced annually.

Page 48: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 2

Future Agriculture

Future cropping pattern and production have been provided in Tables 5 and 6. Future

agriculture under changed scenario, shows that cereal crops (rice, maize and wheat)will cover

72% of the total cropped area followed by Jute (9%),Vegetables(7%), Soybean (7%), and

Oilseeds (5%) with an estimated cropping intensity of 250% and total cropped area of 2569 ha.

In the future Cropping Pattern, 18 % of the cropped area will be covered by High Value Crops

(HVCs).

Annual production of major crops (cereals) have been estimated as 6867 MT of which rice will

be 5761 MT ,Maize will be 666 MT and wheat will be 440 MT. Thus, annual Cereal production

of the Sub-Unit has been estimated to be increased by 3286 MT after rehabilitation.

To facilitate this shift the DAE,NGOs and the Project will provide extension support to the

farmers in the form of improved agricultural techniques, integrated pest/crop management,

home gardening (for women), etc. Detailed agricultural activities for the SIP have been

furnished along with the estimated budget provisions in the form of training, demonstrations,

agricultural fairs, motivational tours, nursery development, etc . Further, a Bar diagram has

been shown to spell out various activities for agricultural development in the Sub-Unit area

throughout the entire Project period.

A budget has been reserved for an amount of BDT 60.55 million for the agricultural program for

total project under implementation. The agricultural development (enhancement) activities of

the SIP have been estimated at BDT 14 lacs for the entire Project period.

Page 49: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 3

1.0 Description

The gross area of SWC 17 +18 is 1471 ha. According to PPTA net cultivable area (NCA) has

been estimated at 70% of the gross area for Chenchur beel Sub-Project. Thus, the NCA is

calculated at 1029 ha with a present cropped area of 2178 ha yielding a cropping intensity of

212%.Future total cropped area has been estimated at 2569 ha with a cropping intensity of

250%. Production of Cereal crops will be increased by 3286 MT after rehabilitation. . In the

future Cropping Pattern, 18 % of the cropped area will be covered by High Value Crops

(HVCs).

Based on the hydrological analysis, the land area under the SIP have been figured out as

F0,F!,F2 & F3 as per present & future governing water levels on which total cropped area,

cropping pattern, cropping intensity and total production have been estimated.

Data furnished in the report are based on the agriculture information collected from the field

through Focus Group Discussions (FGDs) by the Facilitators and compiled by the Research

Assistants. Moreover, for authentication, the secondary data from the local DAE office have

been consulted.

A total of 10-Water Management Groups (WMGs) have already been organized & formed in

the Sub- Unit. Data for Collective Action Plan (CAP) have been collected by the Facilitators

from the WMG-members during FGDs.

1.1 Present Agriculture

The Tables and items below are the compiled information on the agricultural data of the SIP,

which to be considered as Present Agriculture:

Table-1: Crops & Varieties cultivated during various seasons

Seasons Crops Crops & Varieties

Rabi Kharif-1 Kharif-II

Paddy Wheat Pulse Mustard Paddy Jute Paddy

Boro: HYV – BRRI dhan 28, BRRI dhan 29. Hybrid – Hira, ,ACI, ,Laltir, ,etc. Aus: Ratul, Ratna, Buri ,Gambhur--local varieties. HYV Aman: BR-11 Aman: Jabra, Hori, ,,Manohar,Sona Digha, Lal Digha-- Local varieties.

Page 50: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 4

Table-2: Yield of Major crops/ha.

Crops Variety Average Yield per ha(MT)

Paddy Aus (Local) 1.2

Aman (Local) 1.5

HYV Boro 5.0

Hybrid Boro 5.5

Pulse 2.8

Mustard 1.5

Wheat 2.0

Jute 2.5

The present agriculture in the sub-unit is hampered by poor drainage, resulting in water logging in the lower areas during the wet season. Conversely, the higher areas suffer from water shortage especially during the pre-monsoon season. From the gathered data, it is known that 60% of the land are being irrigated through STWs and LLPs.

Present cropping pattern and production have been provided in Tables 3 and 4. Agriculture in

the sub-unit is dominated by rice cultivation covering over 50% of the total cropped area

followed by jute(19%), wheat(12%), mustard (11%) and pulses (8%)

Present production of major crops (cereals) have been calculated as 3581 metric tonnes of

which rice is 3057 and 524 metric tonnes of wheat is produced annually.

Table - 3 : Present Cropping Pattern by Land Type

Land type and flood

depth

Cropping Pattern No. of Crop

Net area (ha)

Cropped area (ha) Rabi Kharif - I Kharif - II

FO (0 - 30 cm)

Pulses B.Aus HYV T. Aman 3 70 210

HYV Boro Jute 2 153 306

Wheat Jute 2 162 324

Mustard B.Aus LT.Aman 3 50 150

Sub-total 435 990

F1 (31 - 90 cm)

Wheat Jute 2 100 200

Pulses B.Aus 2 113 226

Hybrid Boro

LT. Aman 2 69 138

Mustard B.Aus 2 92 184

Page 51: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 5

Sub-total 374 748

F2 (91 - 180 cm)

HYV Boro B.Aman Cont’d 2 120 240

Mustard B.Aman Cont’d 2 100 200

Sub-total 220 440

Grand Total 1029 2178

Cropping Intensity - 212%

Table - 4 furnishes the existing crop wise area, yield and total production which need to be improved

through the required development of infrastructures, re-excavation of khals etc. through which

agricultural production will obviously by increased.

Table - 4: Present Position : Crops with their production by Land Type

Total Cropped

area

Net cultivated

area

Cropping intensity Land type and

flood depth Name of

Crop Area (ha)

Average Yield

Total productio

n

(ha) (ha) (%) (mt/ha) (mt)

2178 1029 212

FO (0 - 30 cm)

Pulses 70 2.8 196

Jute 315 2.5 787.5

HYV Boro 153 5.0 765

HYV T. Aman

120 3.5 420

B.Aus 120 1.2 144

Wheat 162 2 324

Mustard 50 1.5 75

Sub-total 990 2711.5

F1 (31 - 90cm)

Wheat 100 2 200

Pulses 113 2.8 316.4

Jute 100 2.5 250

B.Aus 205 1.2 246

Hybrid Boro 69 5.5 379.5

LT.Aman 69 2.5 172.5

Mustard 92 1.5 138

Sub-total 748 1702.4

F2 B.Aman 220 1.5 330

Page 52: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 6

(91 - 180 cm)

HYV Boro 120 5.0 600

Mustard 100 1.5 150

Sub-total 440 1080

2178 1029 212 Grand Total 2178 5493.9

Present annual rice production has been calculated as 3057 MT and wheat as 524 MT. Thus, annual Cereal production is 3581 MT.

Extracts from the collected Data: Regarding availability of seeds, most of the farmers have opined that the condition is good. Following steps could be taken for better availability of seeds.

1.1.1 Steps for seed availability

1. Own collection.

2. Farmers should get directly from the Government.

3. Supplying of good seed by BADC.

4. To arrange training on production and preservation of seed.

1.1.2 Irrigation Facilities From the gathered data, it is known that 60% of the land are being irrigated through STWs and LLPs.

1.1.2.a Problems of using irrigation facilities

1. Water scarcity in the khals during draught period. 2. Saline water enter into the field during Mid-March to April and damages Boro rice. 3. Inactive regulator/Sluice gates in the khals. 4. Excessive siltation in the khals. 5. Poor drainage facilities. 6. Number of STWs is inadequate as per requirement. 7. Low water discharge through Swallow Tube Well during dry season.

For further expansion of irrigation facilities, following points may be taken into consideration.

1.1.2.b Steps to improve irrigation facilities

1. Immediate repairing of existing regulator or reinstallation of new regulator. 2. Re-excavation of existing khals to easy and quick drain out of water from the field. 3. Excavation of new khals. 4. Supply of electricity for irrigation. 5. Deposition of pure water for irrigation.

Page 53: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 7

1.1.3.a Water Salinity

In the SIP- area, there exists some amount of water salinity but within permissible limit upto end of February.

1.1.3.b Ways to mitigate Water Salinity

To check the entrance of saline water from the river into the khals by repairing or installing regulators.

Use of saline tolerant rice varieties.

Embankment need to be repaired.

To test water salinity regularly.

Use of zypsum fertilizer.

.1.4.a Soil salinity

Soil of the SIP-area are quite fertile and responsive to addition of fertilizers as per characteristics of Gangetic alluvium. There is a complain of soil salinity problem at the lower areas- beel areas.

1.1.4.b Ways to mitigate soil salinity

Awareness raising among the farmers

Soil testing in field as per farmers’ demand

Cultivation of salinity tolerant rice varieties

Check the entrance of saline water from the river into the khals by repairing or installing regulators

Embankment to be repaired

Use of zypsum fertilizer.

1.1.5.a Extent of Fertilizer Use

Farmers are generally using over and imbalanced doses of chemical Fertilizers because of lack of adequate knowledge about proper doses of Fertilizers requiring training on crop-wise Fertilizers application.

Farmers are not also using Compost/Organic Fertilizers.

1.1.5.b Reasons for not using Compost/Organic Fertilizers

Lack of domestic animals/cows.

Cow dung is used as fuel due to scarcity of firewood.

Less awareness and lack of knowledge of Compost preparation

Farmers have no ideas about Green manure.

1.1.6.a Use of Insecticides

Farmers are using moderate doses of insecticides. They do not possess adequate knowledge on the required doses of insecticides application.

Page 54: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 8

1.1.6.b Practice of IPM/ICM by the Farmers

Farmers have little knowledge on IPM/ICM .Extension activities in this regard needs to be geared up.:

1.1.7.a Training topics for the Farmers

1. Compost Preparation & Green manuring 2. Fertilizer and Water Management. 3. Cultivation of HYV Rice

4. IPM/ICM

5. Soil testing

6. Water salinity testing

7. Nursery development

8. Vegetables Production

1.1.7.b Training topics for Women

1. Homestead Gardening

2. Poultry rearing

3. Seed preservation

4. Goat & Cow rearing.

The following problems are being identified which hamper better crop production. If these

problems could be solved, more production could be achieved.

1.1.8.a Problems of crop production

1. Water logging.

2. Soil salinity

3. Water salinity

4. Lack of awareness on modern technology of agriculture development

5. High price of inputs

6. Lack of good quality of seeds

7. Proper Water management

8. Marketing facilities.

Following points need to be considered to mitigate the production problems through the project

activities and regular programme of DAE.

1.1.8.b Steps to mitigate those problems

1. Re-excavation of canal to prevent water logging.

2. Improving the irrigation system and water management.

3. Reducing the price of diesel.

4. Reducing the price of Fertilizer.

5. Using the improved technology in agriculture development.

Page 55: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 9

6. Perform the duties of agricultural officers/staffs through close contact with the farmers

to make aware of soil quality, uses of seeds and fertilizers, techniques of pest control

etc. i.e. technology dissemination.

People are expecting better production and livelihood from this project. Project intervention will

hopefully fulfil their aspirations through their active participation.

1.2 Future Scenario

Future cropping pattern and production have been provided in Tables 5 and 6. Future

agriculture under changed scenario, shows that cereal crops (rice,maize and wheat) cover 72%

of total cropped area followed by Jute (9%),Vegetables(7%), Soybean (7%), and Oilseeds

(5%) with an estimated cropping intensity of 250% and total cropped area of 2569 ha. In the

future Cropping Pattern, 18 % of the cropped area will be covered by High Value Crops

(HVCs).

Annual production of major crops (cereals) have been estimated as 6867 MT of which rice will

be 5761 MT, maize will be 666 MT and wheat will be 440 MT. Thus, annual Cereal production

of the Sub-Unit has been estimated to be increased by 3286 MT after rehabilitation.

Table - 5: Future after Rehabilitation: Cropping Pattern by Land Type

Land type and flood depth

Cropping Pattern No. of Crop

Net Area (ha)

Cropped area (ha) Rabi Kharif - I Kharif - II

FO (0 - 30 cm)

Winter Vegetables

T.Aus 2 185 370

Wheat Jute HYV T. Aman 3 110 330

Soybean Maize HYV T. Aman 3 121 363

Aromatic Rice

HYV T. Aman 2 175 350

Sub-total 591 1413

F1 (31 - 90 cm)

Wheat Jute HYV T. Aman 3 110 330

HYV Boro Sesame HYV T. Aman 3 120 360

Soybean T.Aus HYV T. Aman 3 50 150

Hybrid Boro HYV T. Aman 2 100 200

Sub-total 380 1040

F2

(91-180cm) HYV Boro B.Aman Cont'd 2 58 116

Sub-total 58 116

Grand total 1029 2569

Page 56: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 10

Cropping Intensity =250% Table - 6 : Future with Project Position : Crops with their Production by Land Type

Total Cropped

area

Net cultivated

area

Cropping intensity Land type and

flood depth Name of Crops

Area (ha)

Average Yield

Total production

(ha) (ha) (%) (mt/ha) (mt)

Winter Vegetables

185 17 3145

2569 1029 250

FO (0 - 30 cm)

T.Aus 185 3 370

Wheat 110 2 220

Soybean 121 2 242

Maize 121 5.5 665.5

Jute 110 2.5 270

HYV T. Aman

406 3.5 1421

Aromatic Rice

175 5.5 962.5

Sub-total 1413 7296

Wheat 110 2 220

F1 Jute 110 2.5 275

(31-90 cm) HYV T. Aman

380 3.5 1330

Hybrid Boro 100 5.5 550

Sesame 120 1.5 180

Soybean 50 2 100

T.Aus 50 3 150

HYV Boro 120 5.0 600

Sub-total 1040 3405

(91-180 cm) B.Aman 58 1.5 87

HYV Boro 58 5.0 290

Sub-total 116 377

2569 1029 250 Grand total 2569 1178

Future cereal production has been estimated as 6867 MT of which rice will be 5761MT,Maize will be 666 MT and wheat will be 440 MT. Present cereal production has been calculated at 3581 MT. Thus, annual cereal production will be increased by 3286 MT.

Page 57: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 11

2.0 Future Agricultural Development Programs

After collecting, compiling and analysing the data based on existing agriculture conditions and

discussions with the farmers of the sub-unit; Following agricultural development programs have

been planned for implementation by the project.

2.1 Demonstration Programs

Demonstration is an important method for rapid extension of improved agro-technology of

various crops. Major objective of the demonstration is to introduce new crops and improved

technology with a view to increasing productivity and thereby income generation of farmers.

Modern varieties of crops and other technologies developed by various National Agricultural

Researches(NARs)Institutes are disseminated to farmers through demonstration. The

extension of Agricultural Services should be widely facilitated so that farmers can obtain advice

and support when they want to try new crops to increase cropping intensity and production.

Demonstration farms/trials plots will be established in sub-project area.

Following detailed Demonstration Programs have been formulated for the SIP for the

entire Project period.

Page 58: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 12

echnology Demonstrations for FY, 2010-11, 2011-2012,2012-13 (for 3- years):

Technology

Units Farmers Number Unit Cost Demo.

Cost (Tk.) Cost for field

day (Tk.)

Remuneration for the

Supervising Officer (Tk.)*

Total Cost (Tk.)

No. Area Male Female (Tk.)

1. Demo. on compost preparation 3 Nos. 1 dcm. each 2 1 3000 9000 5000 each for 100 farmers

3000 per demo.

33000

3. Demonstration of Urea Super Granules (GUTI’ Urea) to Boro

10 Nos. 33 dcm. each

10 - 2500 25000 5000 each for 100 farmers

3000 per demo.

105000

5. Demonstration on Sex Pheromones 10 Nos. 33 dcm. each

7 3 3000 30000 5000 each for 100 farmers

3,000 per demo

110000

FY 2009-10

TOTAL 23 Nos. 19 4 64000 248000

2. Varietal Demo. of Wheat (BR-42, Bijoy, Prodip)

5 Nos. 33 dcm. each

5 - 3000 15000 5000 each for 100 farmers

3000 per demo 55000

3. Demonstration of Maize Production 12 Nos. 33 dcm. each

12 - 5000 60000 5000 each for 100 farmers

3000 per demo 156000

4. Demonstration of Mustard (BARI-6) 10 Nos. 33 dcm. each

10 - 2500 25000 5000 each for 100 farmers

3000 per demo 105000

FY 2010-11

TOTAL 27 Nos. 27 100000 316000

1. Varietal Demo. of Boro (BR-47) 4 Nos. 33 dcm. each

4 - 2500 10000 5000 each for 100 farmers

3000 per demo 42000

2. Demonstration of Soybean Production 10 Nos. 33 dcm. each

5 5 2000 20000 5000 each for 100 farmers

3000 per demo 100000

FY 2011-12

TOTAL 14 Nos. 9 5 30,000 142,000

* One field level officer will supervise each demonstration intensively throughout the whole crop season (approx. 3-months). Summery of cost for Demonstration : 1. Cost for the FY 2010-11=Tk.2,48,,000/- 2. Cost for the FY 2011-12= Tk 3,16,500/- 3. Cost for the FY 2012-13 =Tk. 1,42000/-

Page 59: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 13

Total Tk. 7,06,500/-( Total Taka Seven lacs six thousand five hundred only).

Page 60: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 14

2.2 Training programs for farmers

Human resources development through training of farmers, officials and trainers will be

provided under the Agricultural Extension Component.

The farmers will be trained by DAE/Livestock/Fishery staff after getting TOT from the Project.

Training will be provided to the farmers for integrated pest management to minimize the

negative impact of agro-chemicals on the environment. The use of compost will also reduce the

possible negative impacts agro-chemicals on the environment. Agricultural extension focusing

on home gardens and livestock to women for increased production of vegetables will be

provided.

A detailed Training Plan along with the cost estimates have been formulated for

the beneficiaries of the SIP is presented as follows:

Page 61: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 15

Detailed Costing of Training for FY, 2010-11, 2011-2012,2012-13 (for 3- years):

Sl. No.

Topic of Training Participants Number of

Participants

Tra

inin

g A

llo

wan

ce/

da

y (

A)

No

.of

tra

ine

e (

B)

No

. o

f d

ay (

C)

Tra

inin

g A

llo

wan

ce

(to

tal)

(A

XB

XC

) =

D

No

. o

f sessio

n

(E

)

Ho

no

rari

um

rate

/ sessio

n (

H)

No

. o

f g

rou

ps

(G

)

To

tal

h

on

or

raru

im

(EX

FX

G)

= H

Tra

ns

po

rt

su

pp

ort

(I)

To

tal

Tra

ns

po

rt

(BxI)

= J

Ven

ue

ch

arg

e (

K)

Mis

c. (L

)

GR

AN

D

TO

TA

L=

(D+

H+

J+

K+

L)

(Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.)

1. Training on Plantation Activities Water Management Group (WMG) Members

40 =(M 30 + F 10) 200 40 2 16000 10 400 2 8000 100 4000 300 500 28800

2. Vegetables Gardening -ditto- 50 =(M 0 + F 50) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

3. Fruit Trees (Quick growing) Plantation

-ditto- 50 =(M 0 + F5 0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

4. Seed Production Technology Water Management Group (WMG) Members

50 =(M 40 + F 10) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

6. Compost Preparation -ditto- 50 =(M 40 + F 10) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

FY 2010-11

TOTAL 240 10 96000 10 40000 24000 1500 2500 164000

1. Fertilizer Management Water Management Group (WMG) Members

50 =(M5 0 + F 0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

2. Winter Vegetables Production -ditto- 50 =(M 40 + F1 0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

3. Integrated Crop Management (ICM)

Water Management Group (WMG) Members

50 =(M5 0 + F 0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

Page 62: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 16

4. Compost Preparation -ditto- 40 =(M 40 + F 10) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

FY 2011-12

TOTAL 200 8 80000 8 32000 20000 1200 2000 135200

1. Fruit Trees Management WMG Committee Members and other Beneficiaries

50=(M50+F0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

2. Fertilizer Management -ditto- 50=(M50+F0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

3. Water Management for Boro -ditto- 50=(M50+F0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

4. Pest Control for Winter Vegetables

-ditto- 50=(M50+F0) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

5. Post-harvest Technology of Rice

-ditto- 50=(M0+F50) 200 50 2 20000 10 400 2 8000 100 5000 300 500 33800

FY 2012-13

TOTAL 250 10 100000 10 40000 25000 1500 2500 169000

Summery of cost for Training :

1. Cost for the FY 2010-11 =Tk. 1,64,000/-

2. Cost for the FY 2011-12 =Tk 1,35,200/-

3. Cost for the FY 2012-13 =Tk. 1,69,000/-

Total Tk.4,68,200/-(Total Taka Four lacks sixty eitht thousand two hundred only)

Page 63: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 17

2.3 Agricultural Fairs

Agricultural fair is one of the most important and effective method which disseminate modern

technology at the shortest possible time. It helps the people as well as farmers to know the

latest agricultural technologies. Agricultural fair also creates a liaison with other development

organizations. The objectives of the fair is to disseminate agricultural technologies of the

farmers in a short time.

At least one agricultural fair will be arranged annually at the Sub-unit area during winter season.

- Budget for one agricultural fair will be Tk 80,000/-

- One agricultural fair will be organized in each SIP area where the farmers will be able

to show and see different products

2.4 Farmers’ Motivational Tours

Motivational Tour is another aspect to enrich the farmers knowledge by sharing their

experiences with other successful farmers and visits to renowned agricultural research

and development institutes

Budget for one batch of Motivational Tour will be Tk. 75,000/-(approx)

- Motivational Tour will be conducted in batch of 30 farmers .

- One batch of farmers (30) will be selected from each SIP area.

2.5 Nursery Development

Agriculture Nursery is another tool for dissemination of different extension messages. Major

objectives of the nursery will be to enhance production of vegetables, spices and fruits, and

thereby reduce malnutrition problem of people. Farmers will be able to purchase seed, saplings

and seedlings of the above noted items from the nursery at reasonable price. They will be also

able to receive free advice from the DAE staff for establishment of nursery.

At least one nursery need to be established in each SIP. A complete guideline will have to be

prepared for management of the nursery by the Resource persons. The cost of all inputs will

be borne by the project.

The total cost per nursery may be estimated at Tk.75,000/-(approx).

2.6 Total cost

Total cost of expenditures for Agricultural activities in the SIP for the entire Project period will be

as per following break-up:

a. Total Demonstration cos = Tk. 7,06,500/-

b. Total Training cost = Tk. 4,68,200/-

c. Cost for Motivational Tour = Tk. 75,000/-

d. Cost for Agricultural Fair = Tk. 80,000/-

e. Cost for Nursery Development = Tk. 75,000/-

--------------------------------------------------------------------------

TOTAL = Tk.14,04,700/-

(Total Taka Fourteen lacs four thousand seven hundred will be spent for

different agricultural activities at the SIP area)

Page 64: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 18

2.7 Summary of Future Agricultural Activities:

For undertaking the agricultural development activities for SIP # 16, a schedule has been

prepared to implement those activities in the form of Bar diagram.

Items 2010-11 2011-12 2012-13

a) 1. Farmers’ Training b)

2.Demonstrations of crops & varieties

3.Farmers’ Motivational Tours

4.Agricultural Fair

5.Seed production activities

6 Nursery Development

7. Devt. of Marketing Facilities

Page 65: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 19

3.0 Collective Action Plan (CAP) During FGDs, following initiatives were recorded from the WMG-members and they are agreed

to work collectively under the supervision of the Senior Facilitators and Community Facilitators

which can be summarized by the following Table:

WMG Name/No./

Village.

List of Initiatives Training topics Remarks

Chameli/

S-18/1/

Dariaghata,

Fuldah

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

7. Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

Management

c. Vegetables production

d.IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development,

Beli /

S-18/2/

Amtola

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

a. Compost preparation

b. Fertilizer and Water

management

c. Vegetables

production

d.IPM/ICM

e. Soybean production

Keya/

S-18/3

Kalamonkhali,

Bajebabra

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6. Vegetables Production.

a. Vegetables production

b.IPM/ICM

c. Soybean production

d. Seed preservation

e. Nursery development,

Nabaganga/

S-18/4

Noagram

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

7.Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development,

Page 66: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 20

Ekata/

S-18/5

Diadanga

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

7.Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development,

Suravi/

S-18/5A

Perbishnupur

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6. Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Seed preservation

Hasnahena/

S-18/6

Burikhali

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development,

Rajanigandha/

S-18/6A

Pervumbag

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Cultivation of High Value

Crops

(HVCs).

7. Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Nursery development,

Kanakchapa/

S-18/7

Perulistan

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

Page 67: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 21

6.Cultivation of High Value

Crops

(HVCs).

7.Collective Marketing.

f. Seed preservation

g. Nursery development,

Gandharaj/

S-18/8

Satbaria,Pateswari

1.Soil testing

2.Water salinity test

3.Procurement of quality Seeds

and Fertilizers

4.Establish demonstration plots

5.Practice Integrated Pest/Crop

Management ( IPM/ICM)

6.Collective Marketing.

a. Compost preparation

b. Fertilizer and Water

management

c.. Vegetables

production

d.IPM/ICM

e. Soybean production

f. Nursery development,

N0tes:

‘CAP’ Opportunities explored by WMG –members: After organizing Focus Group

Discussions (FGD) with the Water Management Group (WMG) members, following activities

have been identified in order to implement with the initiatives of the WMG-members

collectively.

1. Soil testing:- WMG- members given the responsibilities to the Agriculture sub-

committee to test their soil in order to have ideas about acidity, alkalinity, soil PH. and

other nutritional status of soil.

Agriculture sub-committee of the WMG will collect soil samples from the interested

farmers’ field with the assistance of the Facilitator and take necessary measures to test

the soil by the Department of Agricultural Extension(DAE) or Soil survey Resources

Institute(SRDI).

In doing so, Farmers will be able to select different crops and varieties suitable for their

land. They will discuss the results of soil testing In WMG-meetings and plan their crops

to be cultivated during the next season.

Further, through soil testing, the nutritional condition of the soil especially the macro-

nutrients (N,P,K,Zn) status can be measured and Farmers will be able to plan for

recommended fertilizer doses for different crops.

2. Water salinity test:- Each WMA will be provided with a water salinity test kit by which

WMG-members will be able to test water of their locality in order to know the salinity

level. After knowing the salinity level during the pick-time of the season ,they can decide

to cultivate some saline –tolerant varieties of rice. Thus Farmers can mitigate the crop

losses.

3. Procurement of quality Seeds and Fertilizers:-Agriculture sub-committee of the WMG

will explore the seasonal requirements of seeds and fertilizers for a season and communicate

with the respective organizations (like BADC, DAE, commercial seeds and fertilizer

agencies, etc.) by providing indent ahead of time. They will take delivery of the materials

centrally on behalf of the WMG and distribute the same to the WMG-beneficiaries according

to their requirement. Thus individual carrying costs can be minimized and less chance of

adulteration of inputs could be ensured.

Through discussions and decisions at WMG-meetings, they can use the WMG –fund for

Page 68: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 22

the procurement of required inputs. Thus, Farmers can get the inputs timely and with the

reasonable prices at their door-steps.

Further, some of the WMG will try to allocate Seeds and Fertilizer sub-dealership from the

Govt. organizations.

4.Establish demonstration plots: Project will conduct some demonstrations at the Farmers’

field in introducing new crops and varieties. WMG will adopt those with the technical

assistance from DAE and Project. WMG decide in the meeting to materialize the program

through sub-groups by taking lease of land and sharing the benefits by the WMG –

members. In this way, farmers will be able to know the technology jointly and economic

benefits. Through demonstrations, new technology will be adopted and practiced in the area.

Collective demonstrations by the WMG-members will be encouraged.

5.Practice Integrated Pest/Crop Management ( IPM/ICM):-WMG-members will decide

collectively for not using any pesticides in their crop field. It is rarely impossible to practice

IPM/ICM individually ,it must be a collective effort. WMG-members will decide at which

area and which crop field will be taken for IPM/ICM. By practicing IPM/ICM, Farmers can

reduce the cost of cultivation without using insecticides in the crop field. Thus, the produced

crops will be considered as non-hazardous for human consumption.

6. Cultivation of High Value Crops (HVCs): Some vegetables, Maize, Soybean are being

considered as HVCs which can be introduced at the WMG-areas. As these are somewhat

new crops in the area, there might be little risk for cultivation. So, it is decided at the WMG-

meetings to cultivate some HVCs collectively on the part of WMG.

WMG can take a piece of land on lease and cultivate some HVCs and take the benefits to

WMG-fund.

7. Collective Marketing: Farmers normally sale their products individually at the nearest

markets where they generally sale at lower prices. But if the WMG take the initiatives to

collect seasonal agricultural commodities and store at the custody of the Executive

Committee and communicate with the wholesale/retail markets and bargain with them

for higher prices. Thus, by collective marketing, individual farmers can get better prices

at a time and can plan for next season’s cropping practices.

Topics of Training asked by the WMG-members: The following training topics were

selected by the WMG –members thr4ough which they can be equipped with knowledge and

techniques for better agr4icultural production:-

a. Compost preparation

b. Fertilizer and Water management

c. Vegetables production

d. IPM/ICM

e. Soybean production

f. Seed preservation

g. Nursery development, etc.

Training modules will be developed and supplied to the participants during the training

programs.

Page 69: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-A

SWC-17+18; Noagram-Gazaria Scheme 23

List of topics for Training Modules: 1. Integrated Pest/Crop Management (IPM/ICM).

2. Soybean Production.

3. Maize Production.

4. Aromatic Rice(BRRI dhan-50- Banglamoti).

5. Summer Tomato.

6. Saline tolerant Rice (BRRI dhan-47).

7. Methods of Agricultural Extension and Communication with Farmers.

8. Winter Vegetables Cultivation.

9. Fruit Trees Nursery Development.

10. Rice-cum-Fish Culture.

Page 70: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

ANNEX – B

FISHERIES

Page 71: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 1

SWC-17+18, Noagram-Gazaria Scheme

FISHERIES

Summary

Traditionally FCD schemes have been designed on the basis of mainly agricultural considerations and thereby often clashed with the interests of fishermen. Beels are important breeding ground for river fish and regulators that check the flood waters entering the beel also block the way of spawning fish. To mitigate the negative effect, the gate of the regulator often used to be left ajar or intermittently opened and closed. This was at times a source of tension within/between the communities. That is why the fisheries interest are now better incorporated in the sub-unit implementation plan, and consent of concerned parties is a strict condition for implementation of the plan. The present fish production in the SIP area SWC- 17-18 can be distinguished in fish capture in (large) open water bodies, and fish culture in (smaller) ponds and gher. Captured fisheries covers about 2 fold larger area than cultured fisheries but yield is less than 5.88 times lower (Table-1). There is also a scope for Daudkandi-styled community based fisheries management practice which can significantly increase the production per unit beel area. The productivity of cultured fish in ponds in the area is only 51% of the national average, mainly because of absence of improved aquaculture know-how as evidenced by the very poor number of trained farmers. Inadequate supply of quality inputs (fertilizers, fingerlings, etc.) is another reason. Bringing the production to the national average level would require training (to be provided by DoF targeting about 10% of the farmers in the area) and quality inputs like seed fertilizer and feed (to be provided by the farmers). Presently rice-fish (gher) cultivation is being practiced but has scope for improvement, especially for the poor when introduced in the sharecroppers fields. Relatively novel is the proposal for stocking of fingerlings by poor fishermen/land less in order to sustain fishing in the beels and khals. The approach can also be used to mitigate the bio-diversity concerns by stocking endangered species, if any, in the sanctuaries and/or dug-out water bodies thereby increasing the possibility of their survival and propagation. A comprehensive conservation effort for bio-diversity is, however, above the scope of the SIP and should be taken up by DoF at the national level. Due to project intervention, area of floodplain will be reduced but production through floodplain,/ beel fish culture, canal fish culture and fry stocking in beel will be increased gradually. Economic return is mainly attributable to the big floodplain / beel area, where production cost is almost nil. Increase production (about 79 %) from culture fishery (184.91 MT in 2010-11 to 331.86 MT in 2013-14) can only be attained if the inputs given are optimal and proper training imparted.

Page 72: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 2

Present and Future Fisheries Current Situation The sub unit command area has both culture and capture fisheries firmly rooted in the local socio- economic life style. As apparent from table below (Table 1), culture fishery is the dominating one as far as production rate and total production are concerned although area wise capture fishery occupies more area than culture fisheries. Culture fisheries areas are relatively very small here. But rice- fish (gher) production areas are mentionable and its production is also remarkable. Local people also started fish culture in borrow pit. About 14 ha areas of borrow pits are now under culture and its production level is good sign . 75 ha areas of rice fish are also under culture and its production level is encouraging. Present total annual fish production (2010-2011) in the sub unit is estimated as 218.74 MT. In the capture fishery, only the floodplain fishery is significant as far as area and productivity are concerned.

Table 1: Present fisheries situation in the Sub-Unit SWC-17-18 command area

Fisheries

Present (July 2010-June 2011)

Area (ha)

Prod. Rate

Prodn. Value*

(kg/ha) (MT) (Lac Tk.)

A. Culture

1. Pond 70.00 1523 106.61 111.94

2. Nursery 0.00 0.00 0.00 0.00

3. Rice-Fish (gher)** 75.00 862.00 64.65 67.88

4. FP beel 0.00 0.00 0.00 0.00

5. Baor 0.00 0.00 0.00 0.00

6. Borrow pit 14.00 975 13.65 14.33

7. Canal 0.00 0.00 0.00 0.00

8. Pen 0.00 0.00 0.00 0.00

9. Cage 0.00 0.00 0.00 0.00

10.Khas pond 0.00 0.00 0.00 0.00

Total: A 159.00 184.91 194.15

B. Capture

1. Public low land 0.00 0.00 0.00

2. Canal 8.50 92 0.78 0.98

3. Floodplain/Beel 305.00 106 32.33 40.41

4. Baor 0.00 0.00 0.00 0.00

5. Borrow Pit 4.00 180 0.72 0.76

6. Sanctuary 0.00 0.00 0.00 0.00

7. Beel stocking 0.00 0.00 0.00 0.00

Total: B 317.50 33.83 42.15

Total: (A+B) 476.50 218.74 236.30

* Fish Tk. 105.00/kg, Fingerling Tk.130/kg and floodplain / beel and sanctuary Tk.125 /kg , as they contain shing, magur,koi etc.(at 2010 price) ** Only fish MT: Metric ton

Page 73: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 3

Culture fishery In the culture fisheries, pond fishery is always considered to be one of the most important fisheries for significant increase in total fish production and also to offset any adverse effect of FCD/I activities on natural floodplain fish production. Here, in the pond fishery, the average fish production rate, 1523 kg/ha, is very low compared to the national average (FRSS, DoF 2008-2009) which is 2,991 kg/ha, with no apparent reason to be so when one considers the water quality of the area. Either the farmers are lacking adequate technical knowledge or they are unable to use quality inputs, or may be both. No formal Beel culture is practiced although with individual initiatives pockets of low areas in the beels have completely been transformed into small ‘ghers’ or impounded water bodies. As such, these impounded water bodies have been included under culture fishery. Development of an array of local nurseries catering to the needs of local demand for quality (healthy and of required size) fingerlings is now becoming a pre-requisite for the local culture fisheries to have a strong footing. Supply of fingerlings from the local sources is not adequate. After pond, rice-fish (gher) aquaculture is the next important culture fishery in the SIP area as far as culture area is concerned. Production rate is good with scope for further improvement. This fishery can be a pro-poor activity if introduced in the share croppers’ rice field.

Capture fishery In the capture fisheries, area-wise as well as production-wise, the most important fishery is floodplain where production rate (106.32 kg/ha) is much lower than the national average (271kg/ha). Area is also considerable for increasing fish production. Canals are there with some productivity. Most of the canals are silted and require rehabilitation support not only as a measure to facilitate irrigation but also to allow natural fish to grow. The only other capture fishery presently in use in the sub-unit is in borrow pits. Borrow pits are officially supposed to belong to the BWDB/ LGED as they have constructed the embankment/ roads. Without getting any information from them, eye estimation was made and through FGD discussion present borrow pit areas and uses have been figured out. Most of the areas appeared to be under some sort of private control although these are some being used for aquaculture purpose.

Future fisheries To free the local people of the curse of mal-nourishment, they need more fish in their diet which can be made possible only by producing more fish in a sustainable way and making it affordable to poor including the fishermen and the disadvantaged people, especially the womenfolk. Considering the prevailing local situation and the potential opportunities that the project can create, a number of measures have been proposed for the production increase both in culture and capture fisheries (Table 2 below). An overall annual increase of 146.95 MT of fish from culture fishery, worth Tk. 154.30 lac, is achievable once the proposed fisheries activities are in place, at the end of the project period. The production and value increases may look insignificant. However, if one considers the fact that estimated floodplain area will become reduced, due to project interventions, by more than about 231 ha, the result is encouraging as the culture efforts not only compensate for the production loss but also result in surplus production. This production increase is largely dependent on supply of quality inputs in appropriate quantities, following the project training guideline, into the production systems. Sudden exorbitant increase of some of the inputs may significantly deter the process thereby affecting the production rate. Future annual production (2012-2013) is estimated as 350.43 MT .

Page 74: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 4

Table 2: Future fisheries production scenario after the implementation of fisheries

development programme

Fisheries

Future (July 2012-June 2013)

Area (ha)

Prod. Rate

Prodn. Value*

kg/h (MT) (Lac Tk.)

A. Culture

1. Pond 72.00 2600 187.20 196.56

2. Nursery 1.70 2800 4.76 6.19

3. Rice-Fish** 75.00 1300 97.50 102.38

4. FP beel 5.00 1400 7.00 7.35

5. Baor 0.00 0.00 0.00 0.00

6. Borrow pit 15.00 2200 33.00 34.65

7. Canal 2.00 1200 2.40 2.52

8. Pen 0.00 0.00 0.00 0.00

9. Cage 0.00 0..00 0.00 0.00

10. Khas pond 0.00 0.00 0.00 0.00

Total: A 170.70 331.86 349.65

B. Capture

1. Public low land 0.00 0.00 0.00 0.00

2. Canal 6.50 92 0.60 0.75

3. Floodplain/Beel 62.00 106 6.57 8.21

4. Baor 0.00 0.00 0.00 0.00

5. Borrow Pit 1.50 600 0.90 0.95

6. Sanctuary 3.00 700 2.10 2.63

7. Beel stocking 7.00 1200 8.40 8.82

Total: B 80.00 18.57 21.36

Total: (A+B) 250.70 350.43 371.01

* Fish Tk 105.00/kg, Fingerling Tk.130/kg and floodplain / beel and sanctuary Tk.125/kg , as they contain shing, magur,koi etc.(at 2010 price)

** Only fish *** Floodplain will be reduced due to project intervention and this land will be used for agriculture production especially for rice MT: Metric ton

Culture fishery If the ponds presently ‘not under culture’ (mostly new ponds) are brought under aquaculture then there is

a possibility of slight area increase (horizontal expansion of aquaculture) although some area again will

go to increased nursery. The major boost is expected from a possible significant gradual increase in pond

productivity rate – from 1523 kg/ha to 2600 kg/ha. The quality of water and soil can easily support this

increase. To achieve this feat, it will require adequate training and use of quality physical inputs including

seed, fertilizer and feed. While the project will provide the training, the farmers are required to take care of

other inputs. Participants of some of the Union Level Consultation Meetings (ULCMs) have expressed

their strong demand for required amount of inorganic fertilizers to be collected for aquaculture from the

Page 75: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 5

appropriate sources and then to be distributed among the WMG members first. Training on compost

manufacture can greatly reduce the pressure on cow dung an organic fertilizer as well as the inorganic

fertilizers. This can also ensure better and maximum use of some locally available natural raw materials

while providing employment to a few poor. Another important issue is ensuring dissemination of

technological knowledge to all the local farmers including the farmers not directly trained by the project

through the trained farmers as well as the WMO.

Nursery area would be increased with a view to producing more quality fingerlings locally. And it would be

done by developing more efficient nursery operators.

An increase in rice-fish (gher) aquaculture has been proposed. A clear picture of rice field areas currently

under IPM (Integrated Pest Management) control, or would be in near future, could not be ascertained

from the local agricultural offices. But potentiality is there to increase the present production rate also to

some extent.

Some parts of the beel area can be used for the introduction of Daudkandi styled community based

fisheries management (CBFM) practices in the area which can significantly increase fish production by

organizing local people into an effective fish producing team. If properly organized, this can also be

turned into an enterprise sort of effort where even a poor man can have his/her share. Both the

Department of Fisheries and the NGOs have to take good initiatives for this to happen. But this is a

proven, time-tested practice, production can reach as high as 1400 kg/ha.

Areas under borrow pits should be brought under culture and in the process poor people, especially the

WMG Fisheries Members, should be given the borrow pits on lease. This was also a demand of the local

people expressed during the ULCMs. Project may support this effort by extending support in the form of

physical development (earthwork) and training.

Capture fishery

River fishery can hardly be benefited by the present project activities. Scope is very limited. However, fishermen and their community members need support as they constitute the bulk of hard-core poor people in the rural society. Income generating activities (IGAs) and/or alternative IGAs have been proposed for the fishermen and their family members that will include activities like net making, fish processing, etc.

Canal productivity is expected to increase as a result of canal rehabilitation processes. Participants in all the ULCMs have demanded re-excavation of various canals criss-crossing their unions. An increase in canal productivity is also expected to help floodplain production further which is very low at the moment.

Recently, fish sanctuary has established itself as an important fishery activity contributing significantly both to the fish bio-diversity and fish production. Development of an effective community management system is the key to success of this potential effort. Department of Fisheries has consolidated its techniques. Therefore, Upazila Fisheries Office coupled with the NGO presence in the project is bound to help develop the system in a sustainable manner. One sanctuary areas has been proposed which will require support in the forms of physical development and management training. The project will support the local fishermen by providing financial support for development of the sanctuary and by providing management and maintenance trainings. It will be the responsibility of the fishermen to bear maintenance costs once it is fully developed and put into operation.

Beel stocking is meant to support subsistence fishing of many local poor people which also ensures their access to natural water body and fish therein. Production is boost and sustained by fingerling stocking. No such effort was made earlier in the area and in the project a modest proposal has been included to introduce this type of fisheries activity. Experience of Fourth Fisheries Project (DoF) would be immensely useful here. Compared to the total beel area, the beel stocking area under the project may look very small.

Due to project intervention, flood land will be reduced to a great extent. And flood land will be used for agriculture production especially for HYV rice this land might have played a great role for fish production. Flood land areas also decreasing due to expansion of nursery development and rice fish culture.

Table 3 provides the total fisheries scenario in the 4 implementing years: areas, productivity and costs.

Page 76: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 6

Economics Economic premises

Costs and benefits calculated at December 2010 market prices.

Period covered is from July 2009 /June 2010 (the present financial year) to July 2012 / June 2013 (the concluding financial year of the project).

Financing of the fisheries activities would entail both beneficiary and project contributions. Beneficiaries will be responsible for all direct inputs cost required for fisheries production, both culture and capture.

Project contributions will cover trainings, demonstrations, exchange visits and investment supports. Training costs exclude Training Module preparation cost.

Project investment supports are all one-time offer and will cover costs for earthworks for borrow pits and beel culture, and construction of sanctuaries. All the maintenance and operational costs are to be borne by the beneficiaries.

Table 3 .: The 4-year fisheries scenario – area, productivity, value and costs involved

Fisheries

Future (July 2010-June 2011) Future (July 2012-June 2013)

Area (ha)

Prod. Prodn. Value* Cost

Area (ha)

Prod. Prodn. Value* Cost

Rate Rate

kg/ha

(MT) (Lac Tk.)

(Lac Tk.)

kg/ha (MT) (Lac Tk.)

(Lac Tk.)

A. Culture

1. Pond 70.00 1523 106.61 111.94 33.60 72.00 2600 187.20 196.56 64.80

2. Nursery 0.00 0.00 0.00 0.00

0.00 1.70 2800 4.76 6.19 1.63

3. Rice-Fish (gher) **

75.00 862.00

64.65 67.88 3 4.50

75.00 1300 97.50 102.38 39.22

4. FP beel 0.00 0.00 0.00 0.00

0.00 5.00 1400 7.00 7.35 3.10

5. Baor 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6. Borrow pit 14.00 975 13.65 14.33 5.60 15.00 2200 33.00 34.65 9.30

7. Canal 0.00 0.00 0.00 0.00 0.00 2.00 1200 2.40 2.52 1.22

8. Pen 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9. Cage 0.00 0.00 0.00 0.00 0.00 0.00 0..00 0.00 0.00 0.00

10. Khas pond

0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total: A 159.0

0 184.91 194.15

73.70 170.70 331.86 349.65 119.27

B. Capture

1. Public low land

0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00

2. Canal 8.50 92 0.78 0.98

0.00 6.50 92 0.60 0.75 0.00

3. Floodplain/Beel

305.0

0

106 32.33 40.41 0.00 62.00 106 6.57 8.21 0.00

4. Baor 0.00 0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00 0.00

Page 77: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 7

5. Borrow Pit 4.00 180 0.72 0.76 0.00 1.50 600 0.90 0.95 0.38

6. Sanctuary 0.00 0.00 0.00 0.00 0.00 3.00 700 2.10 2.63 1.05

7. Beel stocking

0.00 0.00 0.00 0.00 0.00 7.00 1200 8.40 8.82 2.52

Total: B 317.5

0 33.83 42.15 0.00 80.00 18.57 21.36 3.95

Total: (A+B) 476.5

0 218.74 236.30 73.70 250.70 350.43 371.01 123.22

* Fish Tk.105.00/kg, Fingerling Tk.130 /kg and beel and sanctuary Tk.125/kg, as they contain shing, magur,koi etc.(at 2010 price) ** Only fish MT: Metric ton

Costs-Benefits: At a glance Table 4 provides information on costs to be incurred and the benefits to be gained from the fisheries activities in 2 implementing financial years. Fisheries activities are divided under two broad categories: CULTURE and CAPTURE. Cost estimates Table 5 provides all cost estimates of the sub-unit – 17-18 for the project period ( FY 2010-11 and 2012-13) Notes on these estimates:

Fisheries Production: Production costs are mentioned in Table 4. Detailed costs involved in unit productions are appended at the end of the report. Full production is expected from final year, i.e., July 2012 – June 2013 FYs.

Foundation Training: The most important and the biggest contribution of the project to increase fish production in a sustainable manner is training of the farmers and fishers. Production increase will result in two ways: firstly by horizontal means whereby new water areas are to be brought under different types of aquaculture requiring training for the new to-be farmers or entrants. Secondly, fish production increase is also possible by vertical means where the production rates of the used water bodies will increase. This will be achieved by providing training to the farmers in more effective and profitable technologies.

Besides farmers, fishermen and their family members will also be trained. Fishermen play an important role not only in harvesting but also in post harvest activities. Since they constitute a part of the ultra-poor people in the society, specially the ethnic ones, wherever available khas ponds/beel areas, borrow pits/sanctuaries, etc., will be used to accommodate them. They will receive training from the project to do all these and also to maintain them. Female family members will be trained in income generating activities including net making, fish processing and compost preparation.

A total of 166 farmers, fishers and others will be trained (Foundation training for 145 and Advanced training for 21). There are a good number of female pond owners who do not take active part in aquaculture as they are not trained. They are willing to take training and many of their family members are in favour of this move. Also there are scopes, other than aquaculture, where women can and should take part as those are very suitable for them considering their socio-economic situations. As many as 65 women (44% of the total foundation trainees) will take part in the overall training programme in different useful subjects.

There are some activities that will specifically suit the very poor people in providing them with special employment opportunities. To name a few are borrow pit aquaculture, compost preparation, fish processing, beel stocking, sanctuary, etc. These are going to add effective and sustainable dimension to the overall livelihoods aspect.

Page 78: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 8

Suitable training modules will be prepared as and where necessary for the purpose.

Table 4 : Productive Values, Productive Costs and Benefits of fisheries activities at a glance

Fisheries

Present year (July 2010-June ,2011) Final year (July 2012-June

2013) Incremental

Value Cost Benefits Value Cost Benefits Benefit/final

yr.

(Lac Tk.) (Lac Tk.) (Lac Tk.) (Lac Tk.) (Lac Tk.) (Lac Tk.) (Lac Tk.)

A. Culture

1. Pond 111.94 33.60

78.34 196.56 64.80 131.76 53.42

2. Nursery 0.00 0.00

0.00 6.19 1.63 4.56 4.56

3. Rice-Fish(gher) **

67.88 34.50

33.38 102.38 39.22 63.16 29.78

4. FP beel 0.00 0.00 0.00 7.35 3.10 4.25 4.25

5. Baor 0.00 0.00 0.00 0.00 0.00 0.00 0.00

6. Borrow pit 14.33 5.60 8.73 34.65 9.30 25.35 16.62

7. Canal 0.00 0.00 0.00 2.52 1.22 1.30 1.30

8. Pen 0.00 0.00 0.00 0.00 0.00 0.00 0.00

9. Cage 0.00 0.00 0.00 0.00 0.00 0.00 0.00

10. Khas pond

0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total: A 194.15 73.70

120.45 349.65 119.27 230.38 109.93

Table 4 Cont.: Production Values, Productive Costs and benefits of fisheries activities at a glance

Fisheries

Present year (July 2010-June ,11) Final year (July 2012-June 2013) Incremental

Value Cost Benefit

Value Cost Benefit Benefit/final

yr.

(Lac Tk.) (Lac Tk.)

(Lac Tk.) (Lac Tk.) (Lac Tk.) (Lac Tk.)

B.Capture

1. Khas low land 0.00

0.00 0.00 0.00 0.00 0.00 0.00

2. Canal 0.98

0.00 0.98 0.75 0.00 0.75 (-)0.23

3. Floodplain/Beel 40.41 0.00 40.41 8.21 0.00 8.21 (-)32.20

4. Baor 0.00 0.00 0.00

0.00 0.00

0.00 0.00

5. Borrow Pit 0.76 0.00 0.76 0.95 0.38 0.57 (-)0.19

6. Sanctuary 0.00 0.00 0.00 2.63 1.05 1.58 1.58

7. Beel stocking 0.00 0.00 0.00 8.82 2.52 6.30 6.30

Total: B 42.15 0.00 42.15 21.36 3.95 17.41 (-) 24.74

Total: (A+B) 236.30 73.70 162.60 371.01 123.22 247.79 85.19

Page 79: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 9

Table 5: Year Wise detailed Cost estimates for enhancement of production which will be supplied by the Project

Cost item FY July 10 - June 11 (lac)

FY July 11 - June 12(lac)

FY July 12- June 13(lac)

TOTAL(lac)

1. Trainings

1.1 Foundation training 1.30 1.10 2.40

1.2 Advanced training

0.80 0.80

1.3 Demonstration 1.90 1.10 3.00

1.4. Motivational tour 1.20 1.20

Sub-Total 1 3.20 3.00 1.20 7.40

2. Investment costs

2.1 Borrow pit development

1.40

1.40

2.2 Beel stocking 1.20 0.80 2.00

2.3 Sanctuary 0.60 0.30 0.90

2.4 Water test kit

Sub-Total 2 0.60 2.90 0.80 4.30

TOTAL (1+2) 3.80 5.90 2.00 11.70

Table 6: Foundation Training details

Trainee Topic Number Duration

A. Farmer Male Female Total

1. Fish Farmer Carp-Golda mixed culture 25 05 30 2 days

2. Fish Farmer Nursery operations 15 5 20 2 days

3. Fish farmer Mono-sex GIFT Tilapia culture

00 30 30 2 days

4. Fishers/ farmer Beel stocking 25 00 25 2 days

5.Fish Farmer Thai koi 00 25 25 2 days

6. Fishers/ farmer Sanctuary dev. 15 00 15 2 days

Total (6 topics)

80 65 145

Advanced training: This will form a strong part of exit strategy. Once the project duration comes to an end, fisheries activities are supposed to continue as useful economic activities. However, technology keeps on changing, new farmers come in, geo-physical conditions of the water bodies keep changing and nature of consumer demand varies. All these require even more effort to keep fisheries activities going on to meet the ever changing challenges. To meet the challenges one most important factor would be to develop enough of quality farmers who can also act as local extension agents for the local new and old farmers maintaining close liaison with the Upazila Fisheries Offices (DoF). With an aim to developing

Page 80: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 10

such local supporting hands, the project is going to provide further training (advanced training) in some of the more useful subjects to the best farmers/fishers. It is expected that they will carry the advanced/up-to-date knowledge to the fellow farmers as well as apply to their own water bodies. This way, even after the completion of the project period, there will be some competent persons (18 nos.) to carry on the task of knowledge dissemination. Table 7 provides detailed information on this.

Table 7: Advanced training details

Trainee Topic Nos. Duration

1. Best performers Carp-Galda mixed culture 4 2 days

2. Best performers GIFT farming 5 2 days

3. Best performers Thai Koi farming 4 2 days

4. Best performers Nursery management farming 3 2 days 5. Best performers Beel stocking 3 2 days 6. Best performers Sanctuary 2 2 days TOTAL 21

Demonstration: As the motto goes ‘seeing is believing’, demonstration has always been regarded as one of the most effective tools in disseminating practical knowledge, especially the new ones. The fisheries programme, therefore, include some demonstrations of fisheries technologies with the expectation that the messages will reach not only to the direct project beneficiaries, but indirectly to many more. Following table (Table 8 below) provides a list of demonstrations. Project will bear all the inputs cost while the farmer will provide the suitable water body and do the field works.

Table 8: Details of technology demonstrations

Technology Units Farmer number Remarks

1. Major carp nursery 1 nos.

40 dcm each

1 M 0 F 1 Best in trainings and having suitable water bodies

2. Mono-sex GIFT Tilapia

5 nos.

25 dcm each

0 M 5 F 5 Best in trainings and having suitable water bodies

3. Thai koi culture 4 nos

20 dcm each

0 M 4 F 4 Best in trainings and having suitable water bodies

4. Beel stocking 2 nos 3 ha 5 M 0 F 2 Best in trainings and having suitable water bodies

5. Carp-polyculture 4nos 45 ha 3 M 0 F 4

Total: 16 demonstrations on 5 topics

Motivational tour: Sharing of experiences can be a good means of getting better ideas and confirming the used ones. Exchange visits by the best performers to other places can enrich and consolidate their knowledge base. It also works as good and positive incentive for the better and hard workers. Project has therefore included exchange visits in its programme in the final implementation year. Motivational tour will take place involving other sub-projects areas beyond the present sub-unit area. Not only the farmers and fishers but also the concerned officials will get the opportunity of such types of motivational tour. Programme is as follows (Table 9). Both males and females will participate in the visits :

Table 9: Details of motivational tour

Participants Number Places of visits

1. Carp-Galda farmers 2 best farmers TBC (to be confirmed)

2. Thai koi 3 best farmers TBC

3. Nursery operators - Carp 2 best operators TBC

4.GIFT 4 best operators TBC

Page 81: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 11

5.Beel stocking/ sanctuary 5 best operators TBC Total 16 persons

Mode of implementation

Activities: In order to support increased fish production activities through environment-friendly and peoples’ participation, especially the poor fisherfolk of the locality, a number fisheries activities have been proposed and explained above. These are listed below for a quick look: 1. Fish production. It includes both culture and capture fisheries. There are traditional activities like

pond aquaculture and then there are new introductions like beel culture (community based fisheries management). These are meant to bring in more waters under aquaculture as well as to increase productivity. Targets are set by the project. However, under favourable conditions (local demand, profitability, no major natural disaster, etc.) motivated local people may go for higher targets, horizontally and vertically as well.

Pond aquaculture – In the final year productivity rate is expected to reach 2600kg/ha/yr from present production of 1523 kg/ha/yr .New species introduction will also be tried during this period. There are some Khas (govt. owned) ponds in the sub-unit area. Attempts will be made to recover this water area from the present occupiers, influential moneyed man, and give this to poor fishers.

Nursery – Efforts will be made to increase nursery area by 1.70 ha in 2011-12 FY . This is important to cope up with the increasing demand for quality seeds.

Rice-fish (Gher) aquaculture – A significant increase in area is to happen from present position. Present production rate is moderate with the scope of future production rate.

Borrow pit – It will be a big challenge to bring in local poor, disadvantaged women and /or fishers into the use of borrow pits as a means of aquaculture. Properly constituted WMGs have to play a big and strong role here. Culture practice will start from the next year. However, most important issue here is to get access to borrow pits presently under control of local influential persons.

Canal fishery – Actual rehabilitation/re-excavation works are expected to start in the next FY. Following the rehabilitation works the water is expected to support much more natural fish than before benefiting the local fishers. There is possibility that if canals are allowed for aquaculture the production within the canal will no doubt increase. More importantly, aquaculture is more prone to be captured by the local influential people. Better to leave it for natural production which will benefit not only the surrounding floodplains, especially during the flood season, also the poor fishers by ensuring their access to the natural water bodies. But some area may be arranged for genuine fisher and poor peoples of WMG members to sustain their livelihood.

{{

Beel stocking – Again local fishermen will be identified and organized into a team for the purpose. They will fence an area for about 7 days for the fingerlings to acclimatize with the local situations and to allow them to grow a little bigger to avoid immediate predation. Then the fence will be taken off and used elsewhere. Once they are dispersed in the adjacent waters, organized fisher group will monitor and have the right to fish according to their own management rules. The project proposed 8 ha to be stocked in the 3rd FY (2011-12) and additional 5 ha from 4th yr the fisher groups will take care of stocking and overall management.

2. Trainings

Foundation trainings will start immediately after the preparation of SIP report and it is planned to start in the year (January, 2011) FY of project implementation and will continue up to 2012-13 FY.

Advanced trainings, on the other hand, will be conducted in the concluding year or before the concluding year.

Demonstrations will be conducted, after the foundation trainings, mostly in this year.

Motivational tour will be conducted in the concluding year of the project implementation period.

Page 82: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 12

3. Investment activities. These will follow the time of use of particular water body. These are all one time support to develop the bases so that the poor fishers and women can carry on from there. An Endowment Fund/Revolving Fund for Tk. 4.30 lac (except water test kit) may be created for the purpose. WMO has to play an important role in administering the fund to ensure efficient use and transparency of the fund management.

Floodplain beel stocking (CBFM) in 2011-12 FY 5 ha and 2012-13 FY another 2 ha. The investment worth is Tk. 15,000 per ha, on an average, and will be used for the required earth works and fry purchasing only.

Borrow pit development. Average per hectare earth work support is Tk 15,000 and the works will start from 2011-12 FY ending in 2012-13 FY.

4. Monitoring and Evaluation, and Reporting of fisheries activities. As expected, this activity will stretch over the entire implementation period. To make it a participatory a well as more effective concerned officials will be trained on how to involve the farmers/fishers in the process. Table -10 below summarizes the incremental production, implementation period, responsible personnel

and trainings. Culture fisheries will contribute the lion share of increasing fish production (146.95 MT) in

the concluding year of the project completion. With an aim to developing such local supporting hands, the

project is going to provide further training (advance training) in some of the more useful subjects to the

best farmers/ fishers. Training will be provided through the DoF staff and specialists from their research

institutes, but may also be provided by the local private experts and NGO staff to the extent that existing

public institution staff resources are insufficient.

Table 10: The mode of implementation of fisheries related major activities

Activity Expected output Responsibility Timing

1. Fisheries programme

1.1 CULTURE Incremental production total: 146.95 MT

Beneficiaries and project fisheries personnel

Final Year of the project

1.2. CAPTURE Incremental production total: ( -) 15.26

Beneficiaries and project fisheries personnel

Final Year of the project

Total Incremental production total: 131.69 MT

Beneficiaries and project fisheries personnel

Final Year of the project

2. Trainings

2.1 Foundation training 145 (M 80and F 65) project beneficiaries capable of practicing modern fisheries technologies

Project fisheries personnel

In 2010-11 and 2011-12 FY

2.2 Advanced training 21selected (best performers) farmers/fishers and others capable of carrying out task of technology dissemination beyond project period

Project fisheries personnel

Concluding year

2.3 Demonstrations

16 demonstrations on new and improved technologies making fellow farmers, other than the direct project beneficiaries), capable of handling new technologies

Project fisheries personnel

In 2010-11 and 2011-12 FY

2.4 Motivational tour 16 best performers capable of sharing experiences with their counterparts within and without the project area

Project fisheries personnel

Concluding year

Page 83: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 13

Activity Expected output Responsibility Timing

facilitating exchange of ideas for even better results

3. Investment supports

3.1 Floodplain beel 7 ha floodplain beel area developed for aquaculture

Concerned beneficiaries and the project fisheries personnel

In 1st half of 2011-12 & 1st half of 2012-13 FYs.

3.2 Borrow pits 3.00 ha of borrow pit developed for aquaculture

Concerned beneficiaries and the project fisheries personnel

In 1st half of 2011- 12 FY .

4. M&E and Reporting Project implementation activities monitored, evaluated and reports prepared as when necessary

Project fisheries personnel

The whole implementation period

Following the MOU signed between the BWDB and the Department of Fisheries, a meaningful cooperation between these two organizations, especially in providing technological support to the project fisheries personnel as well as to the beneficiaries, is expected. Project NGOs as well as other NGOs operating in the region can provide useful suggestions and guidance in the way of consultation meetings with the project personnel regarding mainly the social aspects of the project objectives. Properly developed WMO will always be the key body for the effective and transparent implementation of the activities. Fishing Community / Dependable Community in SIP area

There are three types of fishermen like-full time fishers (professional fisher), part-time fishers and subsistence fishers. The professional fisher of the project area is mostly poor and deprived community. They are generally landless and have no alternative income source. There is less practice of family planning and sanitation system due to lack of awareness, financial capability that are very common for other poor peoples. The full time fishers catch fish for their livelihood round the year in surrounding rivers, khals and beels. A total of 90 numbers of professional fishermen which are fully depend on fishing but from recent few years they catch fish from khal and beels only from July to mid January, when water is available in these areas, rest of the time they harvest fish from pond as a daily labour (tk.165-190 per day) or harvesting fish by share basis. But they are harvesting the fish from river round the year. Part time fisher catch the fish to maintain their family only September to December each year when fish are available in beels and floodplain and no work in their surrounding areas. A total of 111 numbers of part time fishermen are found during the FGD program and their present average income per year tk. 22,000.00- 27,000.00 from fisheries. During FGD program, an opinion was passed from local peoples for professional fishermen to ensure their involvement in fishery enhancement program like sanctuary fishing, fry stocking in beel, leased out public low land water bodies to fisher. Also give them the top priority in alternative livelihood program and trainings to earn more money and employment opportunity. Mitigation measures for Professional fishermen:

Capture fisheries is declining due to decreasing water areas, destroying of the mother stock because of dewatering of the whole low land water bodies, obstacle of migration route, destruction of breeding and feeding grounds and over fishing etc. Professional fishermen will be affected no doubt, does not mean that all fishermen will be vulnerable, because river fishery is always open to all for fishing. But culture fisheries is increasing from last decades. Fishermen have also started changing their life pattern gradually for their necessities and survivability. The following measures should be taken for their survival under enhancement of project activities.

By Khas water bodies : The fishermen can excess easily into Khas water bodies ( low land area). This land will be leased out for fishermen/ landless peoples under Fishery Sub Committee for a long term basis for fish culture. But only few water bodies are found during survey.

Page 84: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 14

By fry rearing : Under Fishery Sub Committee, fishermen will take the private small water bodies for rearing fry. It is very profitable business and earn more money within 3-5 months. Because project will provide nursery management training for fry rearing to WMG members.

By beel stocking : Under the enhance plan, some low land area will be transferred into deep area to save mother fish as a mother stock to breed more fish and save the local variety of fishes. Some condition to be applied for land owners, such as, at least 10 years of those deep part and surrounding low land area must be under Fishery Sub Committee with involvement of fishermen. And land owners will take share or lease money per year of their lands for leasing out their land.

By Marketing Channel : Marketing is more profitable business than other work either in Fisheries or Agriculture products and others. A marketing channel will be developed especially for fishermen under fishery section or IGAs to create employment opportunity and earning more money.

By demonstration pond : Under enhancement program, a lot of demonstration pond will be implemented to increase fish production through group wise approach and benefit will be shared among group members. Fishermen should take initiatives under this program.

By IGAs program: Through IGAs , fishermen will take initiative to create employment opportunity like net making and other related activities for their livelihood.

Wet - Land Management : Wet land conservation is very important for aquatic flora and fauna, and to enrich the bio-diversity. It is also important to landless and genuine fishermen for their livelihood and animal protein supply. During FGD program a discussions was made about the importance of Wet Land Conservation. All members realized it but most of the members prefer the crop production than bio-diversity and fish production. They also pass their opinion which is only possible in govt. khas land but only 0.95 ha khas low land is occurred in SIP. Before making a final decision especially for private wet land management, a detailed discussions will be needed with WMG members and local peoples (high/ medium /low land owners) to clear and concrete decision about inundation areas. A demarcation should be established in all low land areas, when, where and how much areas will be inundated or not. WMG members and local people will take proper concrete decision about wet land management.

Value addition The per capita consumption rate has shown in declining trend in recent years due to high population growth which is faster than the growth rate of fish production. It is becoming increasingly impossible to maintain the stable of foods, especially the animal protein. The prospects of adding value to by catch largely depend on the demand. Good quality raw material supplies are an essential pre requisite for any value added processing activity. Once the quality of raw materials get deterioration, there is no way to improve it by any means of preservation and processing. Improvement of handling of by catch can be done by sorting, de-heading and gutting during the catching. Although storage life inside ice, varies from species to species. Iced fish was found fairly good for 8-10 days. All the species are not equally suitable for processing of various value added products. Difference flesh characteristics in a product may influence the quality and make the product unattractive to the consumers, in terms of appearance, flavor and odour. Training will be provided to WMG members through the DoF staff and specialists from Research Institutes. Marketing Much of the catch, particularly from fresh water both from culture and capture, is consumed locally by the local peoples or with in same thana or district. However there are areas which consume less than they produce and therefore have a surplus which can be exported to other areas of the country. Almost all fish traded internally passes through private channels. The market structure varies from area to area. Marketing Channels divides into four stages; primary market, secondary market, higher secondary market and final consuming market. The primary market: Here the fisherman sells to a mobile assembler, who may be known as a mahajan, a jogandar or a faria The Secondary Market:

Page 85: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 15

The assembler sells the fish in a wholesale market to local retailers {nickaries}. Local wholesale {Paikers}, or distributors who transport the fish to other districts {beparis or chalans}. The sale is normally carried out through the medium of a commission agent {arotdar} who conducts public auctions The higher secondary market: Fish consumed at a distance from the secondary market is transported by distributors {bepari or chalan} to other distribution markets, usually whole sale markets in districts towns. Here they sell to local retailers {nickaries} and whole sellers {paikers} through local aratdars. Training and extension program will be organized for WMG members to develop the marketing channel to get more price from their own products and to create employment opportunity. Summarized activities on strength and weakness of Directorate of Fisheries (DoF)

Sl.

No.

Issues Activities of DoF Activities of SW project

with line agencies

Remarks

01. Soil test of

pond

DoF generally do not go for

soil testing for fish culture in

pond, only they do the

some special cases.

WMG members will take

initiatives for soil testing for

increased production &

prevention of fish diseases

in ponds.

Mainly for intensive

fish culture and

prevention of

diseases.

02. Water quality

test of pond

DoF do water quality test in

problematic ponds (fish

diseases affected pond)

WMG members will take

initiatives for water testing

for applying the lime,

organic and inorganic

fertilizer, and prevention of

diseases

Kit box of water

quality test need to

be provided to each

WMA level from

project

03. Quality fry /

fingerlings

Procurement

Farmers purchase

fry/fingerlings individually

from open market without

maintaining quality. DoF do

not involve in such type of

activities

WMG members will procure

quality fry / fingerlings from

the reputed hatchery / firm

by taking advice from

fisheries specialists (

project or DoF) collectively.

WMG members

collectively will

procure quality fry /

fingerlings with

cheap rate.

04. Establish

demonstration

ponds

Learning by doing is more

effective-which is not

always practiced in DoF.

During 4th fisheries project

some demonstration ponds

were established in Narail

areas but within SIP area.

Some demonstration ponds

will be established on

different aspects under the

project among from WMG

members pond.

Dissemination of

technology in the

project area for

increasing fish

production.

05. Shortage of

organic

fertilizer in

pond for

DoF do not take initiative

for such type of activities.

Project will introduce

adequate amount of

compost preparation to be

provided to fish pond for

To apply organic

fertilizer in pond for

increasing

productivity.

Page 86: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 16

increasing

productivity.

increased fish production

06. Massive use

of pesticides

in rice cum

fish culture/

surrounding

beels saving

the HYV rice

crop.

Farmers normally use

pesticides during pest

attacks without caring of

doses and quantity. DoF is

not involve in such types of

activities.

Use of high doses of

pesticides need to be

discouraged through

practicing IPM/ICM.

07. Training

No training is going on at

present on modern

methods of fish culture .

Rigorous training will be

provided to WMG members

on different aspects of

fisheries production by the

project with the help of line

agencies.

WMG members

will be skilled up

about modern fish

culture.

08. Cultivation of

High Value

fish like Sing,

Koi , Magur,

Pabda etc

Farmers have shallow

knowledge of valued fish.

DoF do not take initiative

about high value fish

culture in this area.

Project will take initiative

with help of DoF & BFRI to

introduce high value fish

culture in this area through

WMG members for

increased production and

benefit.

WMG members

will know about

high value fish and

its culture

technique.

09. Fish

production

Present fish production of

pond is an average of 1235

kg/ha/yr

Production will be

increased up to 2500

kg/ha/yr through

enhancement program

under the project.

Fish production will

be increased due to

enhancement

program.

10. Marketing

facilities

Farmers sell their fish at

nearby markets individually.

No initiative is taken by

DoF about the

development of marketing

system.

WMG members will take

initiatives with the help of

project to sell their fish

collectively to big business

centres to get more

benefit.

Marketing system

will be established

through WMG

members

collectively.

11. Fry stocking

in beel

No such types of activities

are being taken up by DOF

Project will take initiative for

stocking through WMG

members to increase

production and more

To create a

employment

opportunity and

income generating

Page 87: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 17

income. activities.

12. Sanctuary

development

Few fish sanctuaries were

established in Narai district

during 4th Fisheries Project

but not in this SIP area. At

present no such types of

activities are found.

Project will established fish

sanctuary to conserve

threatened fish and to

increase production

through WMG members

activities.

To enrich the

biodiversity

13. Manpower No sufficient manpower to

conduct extension program

and other fisheries related

activities.

Project will supply the

sufficient manpower to

conduct extension and

fisheries related activities of

WMG/ WMA members.

14.

Monitoring &

Evaluation

At present there is no

monitoring system of DoF

on their fisheries activities

SW project will establish

monitoring system with

MIS data base to know the

project achievement .

WMG

members/Local

people / authority of

the project will

know the

achievement of the

objectives.

Monitoring and Evaluation

Monitoring tools:

1. Farmer and Fisher Record Books. These would constitute the major backbone of the M&E drive. These will not only help the beneficiaries in assessing their achievements but also to improve next year activity plan. Not all but representative samples of these books would also help the project management including WMO to evaluate performance. It is difficult but not impossible to put a significant number of the beneficiaries, if not all, into the habit of keeping records regularly. Making them adequately aware of the immediate as well far reaching benefits is the key.

2. Project Record Books and Report Cards. Project will also maintain quarterly implementation records adequately reporting the progress made, qualitative as well quantitative, and identifying issues that needs to be resolved for better performance in the next quarter. Project personnel, especially the Senior Fisheries Facilitators, will be the responsible persons.

3. MIS-based monitoring. Project management in their MIS-based overall M&E system will include fisheries activities as an important and indispensable component. Fisheries personnel will assist in developing this system so that an effective mechanism is developed with which quality of implementation and progress made can be properly assessed and the project impact can also be assessed some times after the end of the project period. Among others, special attention should be made to include issues like women participation and empowerment, inclusion of poor fisher folk and their family members into the mainstream of fisheries activities, and the salinity issue to guard against Bagda shrimp culture, etc., in the MIS format.

Performance indicators:

Area increase and utilization under different culture and capture systems as outlined in this sub-unit implementation plan above.

Production increase, where applicable, as outlined in this sub-unit implementation plan above.

Page 88: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 18

Beneficiary count: trainee and participants in the various activities considering the gender and livelihoods aspects.

Effective check of saline water intrusion: proper handling of water regulators/structures.

Page 89: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-B

SWC-17+18; Noagram-Gazaria Scheme 19

Activities at a glance, SWC – 17&18

SL.No

Activities 2010-2011

2011-2012 2012-2013

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

1 Fish production

1.1 Pond aquaculture (extension)

1.2 Nursery

1.3 Demonstration pond

1.4 Rice-fish

1.5 Floodplain beel

1.6 Borrow pit

1.7 Canal

1.8 Beel stocking

2 Training

2.1 Foundation training

2.2 Advance training

2.3 Motivational tour

3

Development of Marketing Facilities

4 Investment activities

4.1 Floodplain fish culture

4.2 Borrow pit repair

5 Monitoring & evaluation

5.1 Data collection

5.2 Data analysis

6 Reporting

Page 90: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

SWC-17+18; Noagram-Gazaria Scheme 20

Collective Action Activities (CAP) Fisheries Section, SWC-17&18 During FGD, the following initiatives are recorded from the WMG members who expressed to work collectively. The list of planned initiatives and training required opted by the WMG / Members are listed below.

Name of WMG/

no./village

List of planned initiatives by groups

Training topics Remarks

Chemieli S-18/1

Dariagata

1. Demonstration ponds (1no.) 2. Pond (extension) (4 no.) 3. Rice –fish (1 no.) 4. Gher extension (6 no.) 5. Fry procurement ( by 1group.) 6 .Marketing activities( by 1group.)

1.Carp-polyculture 2.GIFT culture in small size pond 3. Marketing 4. Valued fish culture in pond (Thai koi, Sing, Magur & Pabda

They are interest in training and demos activities

Beli S- 18/ 2 Amtola

1. Demonstration ponds (1no.) 2. Pond (extension) (4 no.) 3. Nursery (1 no) 4. Rice –fish (2 no.) 5. Gher extension (4 no.) 6. Fish culture in borrow pit (1place by 1group.).

1. Marketing chain 2. Valued fish culture in pond (Thai koi, Sing, Magur &

Pabda 3. Poly culture

Keya S-18/3 Bajebabra

1.Demonstration ponds (1no.) 2.Pond (extension) (4 no.) 3. Sanctuary (1place by 1group.) 4.Fry procurement (1group.) 5.Marketing activities(1group.)

1.Carp-Golda mix culture 2.GIFT culture in small size pond 3. Sanctuary development 4. Valued fish culture in pond (Thai koi, Sing, Magur & Pabda

Most of the WMG members are interested in training especially in carp-golda culture.

Nabagonga S-17&18/4 Noagram

1. Demonstration ponds (1no.) 2. Pond (extension) (4 no.) 3. Rice –fish (1 no.) 4. Gher extension (5 no.) 5. Fry procurement ( by 1group.) 6 .Marketing activities( by 1group.)

1.Fish culture in rice fish 2.GIFT culture in small size pond 3. Fry management 4. Valued fish culture in pond (Thai koi, Sing, Magur & Pabda

They are interest in training and demos activities

Ekota S-17&18/5 Diadanga

1..Demonstration ponds (1no.) 2. Pond (extension) (5 no.) 3. Rice –fish (2 no.) 4. Gher extension (6 no.) 5. Sanctuary (1place by 1group.) 6. Fry procurement ( by 1 group.) 7. Water and soil quality test: 8. Fry procurement ( by 1group.)

1.Carp-polyculture 2.GIFT culture in small size pond

3. Sanctuary development 4. Sanctuary development 5. Value chain

Suruvi S-18/5A Parbisnopur

1. Demonstration ponds (1 no.) 2. Pond (extension) (4 no.) 3.Nursery (1 no) 4. Beel stocking (1place by 1group) 5. Marketing activities( by 1group)

1. GIFT culture in small size pond 2. Nursery management 3.Valued fish culture in pond (Thai koi, Sing, Magur) 4. Marketing activities

A few members interest in nursery management

Hasnehena S-18/6

1.Demonstration ponds (2 no.) 2.Pond (extension) (5 no.) 3.Rice –fish (2 no.)

1.Carp-polyculture 2.GIFT culture in small size pond

They are interest in training and demos activities

Page 91: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

SWC-17+18; Noagram-Gazaria Scheme 21

Burikhali 4. Gher extension (6 no.) 5. Sanctuary (1place by 1group.) 6. Fry procurement (1group.) 7.Marketing activities(1group.) 8.Water and soil quality test

3.Valued fish culture in pond (Thai koi, Sing, Magur

Rajanigandha S-18/6A Pervumbag

1. Demonstration ponds (1 no.) 2. Pond (extension) (4 no.) 3.Nursery (1 no) 4. Beel stocking (1place by 1group) 5. Marketing activities( by 1group)

1. GIFT culture in small size pond 2. Nursery management 3.Valued fish culture in pond (Thai koi, Sing, Magur) 4. Marketing activities

A few members interest in nursery management

Konokchapa S-18/7 Perulistan

1.Demonstration ponds(1 no.) 2.Pond (extension) (3 no.) 3.Nursery (1 no) 4.Rice –fish (1 no.) 5. Gher extension (5 no.) 6. Fish culture in canal (1place by 1group.) 7. Water and soil quality test: 8. Fry procurement ( by 1group.) 9. Marketing activities ( by 1group.)

1.GIFT culture in small size pond 2. Nursery management 3.Valued fish culture in pond (Thai koi, Sing, Magur & Pabda 4. Marketing activities

Some member interested in marketing activities.

Gondaraj S-18/8 Pateshori

1. Demonstration ponds (1no.) 2.Pond (extension) (3 no.) 3.Nursery (1 no) 4.Rice –fish (2 no.) 5. Gher extension (4 no.) 6. Fish culture in borrow pit (1place by 1group.). 7.Sanctuary (1place by 1group.) 8.Fish culture in beel (1place by 1group.) 9. Fry procurement ( by 1 group.)

1.Carp-polyculture 2.GIFT culture in small size pond

3. Sanctuary development 4.Fish culture beel through Community Based Management. 5. Value chain

All members are interested in demos activities

Notes

Demonstration ponds: Some demos will be conducted through WMG members collectively to introduce new technology on carp – polyculture, carp-golda mix culture, GIFT and valued fish like Thai koi and Sing fish. Learning by Doing process will be adopted and at the last harvesting day, a field day will be arranged for all WMG members and surrounding pond owners to observed the fish directly and hearing culture technology from pond operator directly. Such type of program will create a awareness and confidence among pond owners.

Nursery pond: A few water area will be arranged for nursery management. Most of the members do not know how to rearing / culture fish fry. But huge demand the quality of fingerling in this area for fish culture in their ponds. After receiving the training on nursery management from the project, WMG members will start fry culture through “Learning by Doing” having facilitation from SF/ ISPMC Fishery consultant . These activities will be able to meet shortage of quality fry/ finger ling and ultimately will enhance the production of fish.

Extension Pond: Most of the WMG members culture their ponds without proper technical knowledge, only they release fry without maintaining numbers and ratio and culture fish with out proper management. So production rate is very low. But after receiving training from project, members of WMG will be skilled on fish culture and production would be increased ultimately.

Fry procurement : Sub committee members of WMG are agreed to procure the fry/ fingerlings collectively to safe time and money. They will supply fry/fingerlings with in WMG members and surrounding pond owners. They will do the work with the help of concern SF and CF through guidance of ISPMC.

Page 92: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

SWC-17+18; Noagram-Gazaria Scheme 22

Fish culture in Canal: Sub committee of WMG members are agreed to fish culture in canal through group based to boost up production and create an employment opportunity with the direct involvement of dependable community. The concern SF and CF will facilitata the committee to perform their activities.

Fish culture in Rice field: Surrounding members of beel are agreed to fish culture in monsoon period through community based management including dependable community to increase fish production in beel areas and create employment opportunity with facilitation from ISPMC/SF/ PMO.

.Beel stocking: Some WMG members are agreed to stock the fingerlings in the beel through community management to increase fish production and employment opportunity. At some part of Bangladesh, community based management fingerling stocking in beel has been successful in increasing (from 500 kg to 1200 to1800 kg/ha) fish production and employment opportunities. Water and soil quality test: Members of sub committee of WMG are interested to test water quality test of their ponds to increase production up to optimum level and minimize the production cost and prevent fish diseases. SF will facilitate concern WMG members to test their soil and water quality from BFRI or DOF. Or each WMA level will be provided a test kit by which each members will be able to know their test report with the help of SF/Consultant, After getting results which will be discussed among the members and advised them what to do. Thus by this collective initiatives, farmer will be benefited.

Marketing activities: Under this SIP some WMG members are interested to develop the marketing channel to get an appropriate price from their commodities with the help of technical support of the project. Normally sale the fish in pond side or the nearest market where they get the low prices. But if WMG members and keep the harvested fish in store under own custody of marketing committee of WMG and communicate with whole sellers (Narail / Khulna or even Dhaka) and will be able to bargain with them for appropriate prices and marketing channel will be created.

Trainings The above training topics were selected by WMG members through which they can equipped with knowledge and techniques for more fish production.

Page 93: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

ANNEX – C

ENVIRONMENTAL

Page 94: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-C

SWC-17+18; Noagram-Gazaria 1

Monitoring Report-1: Environmental Impact and Safeguard Monitoring

For SIP- 17-18 (SWC): Baseline

Environment

FCD projects are implemented with the objectives of controlling flood and improving drainage of an

area, which bring some changes in water related ecology in the area mainly. Moreover, many efforts

have been planned to fulfill the project goal, some of which may also affect the environmental quality

of the area.

Southwest Area Integrated Water Resources Planning and Management project SAIRPMP) presently

composed of rehabilitation of 2 FCD sub-projects (with minor support to surface irrigation) namely

Narail sub-project NSP) and Chenchuri sub-project (CSP), which have been subjected to further

segmentation into sub unit implementation planning (SIP) areas, based on hydrological unit mainly.

Presently a report on the environmental situation of SIP- 17-18 of SWC areas is under considerations

(Map enclosed).

A survey on the present environmental conditions of the SIP area has been undertaken that will be

used as base data, and the required measures have to be undertaken to safeguard the environmental

standards throughout project life and beyond.

The present data collection and monitoring plan is based on environmental issues that are found

during the preparation of EIA. Main Environmental Impacts include

Possible increase in agricultural pollution of soil/waste due to increased agriculture.

Reduce the natural grazing areas, likely to contribute to reduction of number of bovines.

Increase dependence on fuel wood (rather than cow-dung) for cooking.

Reduce the jungle area contributing to reduction of terrestrial biodiversity

Lowering the ground water table by increased use of tube well water for irrigation and

reduced recharge potentiality.

Reduce the number and size of perennial and seasonal wetland areas affecting livelihood of

fisher folks, protein intake of poor people, aquatic flora and fauna, ground water recharge etc.

Page 95: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-C

SWC-17+18; Noagram-Gazaria 2

Figure: Map of the SWC 17-18

Page 96: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-C

SWC-17+18; Noagram-Gazaria 3

1. Drinking Water

It is found that test of arsenic contamination of HTWs of all the sampled villages of SIP-17 and 18 has

been carried out by DPHE between 2004 and 2008; total number of HTWs is being about 550, there

is report of arsenic-contamination of about 80 HTW in the area.

An NGO, namely Ulashi Sreejoni Songha , imparted awareness training on adverse affects of

drinking arsenic contaminated drinking water during 2007, in addition to DPHE’s routine activities

since 2004. The sampled three villages namely Satbaria, Kalamonkhali and Perbishnopur that

SAIWRPMP carried out the study. The local people of that villages commented HTWs water are

arsenic free and no iron content but little amount of saline content.

Table-1: Status of Arsenic-content of HTW Water in SIP 17-18

No of Tubewells Arsenic contaminated % of Arsenic contaminated

550 80 14.54

Source: Field Survey

2. Sanitation Facility

There exists different types of latrines in the total areas of two sampled area; their extents are given

in the following table (Table-9):

Table- 2: Types of latrines in use in the area

Types of latrines Nos. Per cent

Pucca 87 5.02

Ring slab 1150 66.32

Open/kutcha 395 22.78

Wild 102 5.88

Total 1,734 100.00

Source: Field data of survey villages

It is found that the NGO Ulashi Sreejoni Songho started some motivational training of the local people from 2007 on general health issues, which is still continued.

Page 97: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-C

SWC-17+18; Noagram-Gazaria 4

It is found that wild defecation practice still exists among the male, especially when they go outside for field work, although their number has reduced due to training and motivational activities of DPHE and NGOs. It needs further motivation through training.

Most of the HHs (91%) has hygienic sanitation facility in three sampled villages, overwhelmed by ring

slab latrines. But all ring slab latrines may not qualify for hygienic one.

Table 3: Situation of Sanitation Facility

Village No of HHs No. of sanitation facility Comments

Satbaria 20 18(90%) Sanitation facilities include ring slab latrines* mainly, with about 20% pucca latrines. The remaining unhygienic latrines are composed of open latrines.

Kalamonkhali 14 13 (93%)

Perbishnupur 19 17 (89%)

Total 53 48 (91%)

Source: Field Survey; *All the ring slab latrines are not hygienic, as many of them have their goose-

neck broken, due to lack of awareness.

3. Water Quality

Laboratory analyses of surface water (ponds and khals) have been carried out recently based on

requirements of fishery production and the results are furnished below:

Page 98: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-C

SWC-17+18; Noagram-Gazaria 5

Table 4: Results of laboratory analyses of water samples

Sample

no.

Date of

collection Location

Dissolved

Oxygen

(DO)

Biochemical

Oxygen

Demand

(BOD)

Chemical

Oxygen

Demand

(COD)

pH

Electrical

Conductivity

(EC)

Turbidity Sulphate TDS

mg/l mg/l mg/l µs/m JTU ppm mg/l

1. 06.5.09 Pond in village Purulia,

U/C- Purulia, Upazila - Kalia

1.3 14.0 23.0 7.73 470 7.78 004 288

2. 06.5.09 Pond in village Dariaghata,

U/C- Purulia, Upazila - Kalia

1.2 16.0 28.0 7.06 520 3.28 055 218

3. 06.5.09 Liner khal in village -Chandpur,

U/C- Purulia, Upazila - Kalia

2.4 13.2 22.0 7.03 9600 8.33 264 3720

4. 06.5.09 Pond in village Raghunathpur

U/C- Peruli, Upazila- Kalia

2.2 13.4 20.3 7.13 462 5.53 044 397

5. 07.5.09 Matiary khal in village -Jadavpur,

U/C- Purulia, Upazila - Kalia

2.8 12.0 18.3 7.27 10,400 7.59 135 4670

6. 07.5.09 Pond in the beel centre, village -

Jadavpur,

U/C- Purulia, Upazila - Kalia

2.3 14.0 16.2 7.33 10,800 6.50 223 5020

7. 07.5.09 Pond in village Jadavpur

U/C- Peruli, Upazila- Kalia

2.6 13.4 17.3 7.38 80015 16.22 192 2310

8. 07.5.09 Jadavpur khal in village Jadavpur,

U/C- Purulia, Upazila - Kalia

1.5 15.1 18.0 7.11 13504 36.91 206 4990

9. 07.5.09 Pond (gher) in village Jadavpur

U/C- Peruli, Upazila- Kalia

2.7 12.3 16.3 7.09 3000 032 1640

10. 07.5.09 River Chitra, village Mohishkhola

U/C- Peruli, Upazila- Kalia

3.7 12.6 16.4 7.49 12800 16.73 285 5920

11. 07.5.09 Pateshwari khal (country side) in village

Mohishkhola, U/C- Peruli, Upazila -

Kalia

3.5 13.2 15.0 7.58 9805 42.03 212 5400

12. 07.5.09 Pond in village Pateshwari

U/C- Peruli, Upazila- Kalia

3.4 13.4 13.3 7.50 1500 7.44 225 1110

13 07.5.09 Pond in village Noagram,

U/C- Purulia,, Upazila- Kalia

1.4 17.1 16.2 7.45 522 106.0 006 394

14 07.5.09 River Nabaganga village Noagram

U/C- Purulia, Upazila- Kalia

2.0 16.2 16.2 7.51 13750 10.06 235 4520

15 07.5.09 Pond in village Amtola

U/C- Purulia , Upazila- Kalia

1.6 17.0 20.00 7.42 800 70.0 25 397

Permissible limit >5 For fish- <6.0

and

for irrigation

<10

6.5-8.5 Up to 10 upto 400

ppm

Source: Water samples were analyzed at site and in the laboratory of Department of Soil, Water and

Environment, Dhaka University.

It is observed that Dissolved Oxygen (DO) of all the water samples are below the permissible limit

requiring some measures and water turbidity in samples 1 &2 is high probably due to washing of soil

particles by erosion or due to excessive human uses.

4. Use of Chemical Fertilizers

It is observed that most of the farmers apply different doses of chemical fertilizers mainly on their

experience (some farmers learn from surrounding farmers) and crop responses, although a few of

them receive some training from DAE. In doing so, farmers fail to maintain balance of fertilizers in

most occasions. According to field survey various chemical fertilizers used for different crops mainly

grown in the area are given in the following table:

Page 99: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-C

SWC-17+18; Noagram-Gazaria 6

Table-4: Average Use of Chemical Fertilizers (kg/ha)

Crops Fertilizers (kg/hectare)

Urea TSP MP Zinc Sulphate Gypsum

B. Aus - - - -

T.Aus 80 44 12 - -

B. Aman 55 30 - - -

Lt Aman 75 32 - - -

HYV T. Aman 200 75 42 10 5

Boro(HYV/Hybrid) 280 120 75 45 8

Jute 90 70 25

Wheat 120 80 30

Onion 80 40

Sesame 40 40 16

Source: Field survey

5. Use of Pesticides/Insecticides

It is found that farmers usually use pesticides/ insecticides for Boro crops mainly. Main types and

quantity used are given below (based on field data):

Table-5: Average use of pesticides/insecticides

Village Crops Type of pesticide/insecticide

Average Quantity(kg) /ha

Remarks

Satbaria Boro (HYV/Hybrid)

Furadan/Basudin 10 Some farmers use sunfuran, Brifer and Kartap for Boro crops in addition to Thiovit/Dimecron. The farmers use no kind of insecticides/ pesticides for other crops.

Kalamonkhali Boro (HYV/Hybrid)

Furadan/Basudin 7.5

Boro (HYV) Thiovit/Kurater 10

Perbishnopur Boro (HYV/Hybrid)

Thiovit/Sumithion/ Dimecron

3.5

Vegetable Thiovit/Sumithion 3.0

Source: Field Survey

Application of insecticides/pesticides is carried out by DAE-trained local people on payment. The total

quantities applied by the people will be collected on use per hectare in various crops.

6. Wetlands/Beels

There is no perennial wetland/beel in the SIP area. The existing beels remain inundated for 6-7

months from June to December. Data/ information on the beels are furnished in the following table:

Table-6: Beel situation

Village Beel name Depth of beel during monsoon

No. of HHs of affected livelihood

No. of HHs of partly affected livelihood

Remarks

Satbaria Takimara beel (60.73 ha)

1.2-2.0m but dries out seasonally

5 13 All the beels are seasonally inundated.

Kalamonkhali Pateshwar beel 6 10

Perbishnupur Pateshwar beel 4 11

Source: Field survey

Page 100: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-C

SWC-17+18; Noagram-Gazaria 7

The potentially affected HHs have, who are mainly fishermen, to be provided with alternative suitable

means of livelihood.

7. Irrigation Facility

Ground water is the major source of irrigation water, as shown in the following table:

Table-7: Status of Irrigation Water

Village Per cent irrigated by

surface water

Per cent irrigated by

Ground water

Problems of irrigation

Satbaria 10 90 Lowering of GWT creates problem in lifting of irrigation water;

Salinity of river water;

Siltation and early drying of khal;

Non-functional regulator (gates broken).

Kalamonkhali 5 95

Perbishnupur 8 92

Total 7.66% 92.34%

Source: Field Survey

8. Bovine animals and cow dung

Data on number of bovine animals and different uses of cow dung of the sampled villages of SIP

areas are given in the following table:

Table-8: No. of Bovine animals and cow-dung

Village Total nos.

Total cow-dung (kg/day)

Quantity (in kg/day) of cow-dung for different uses

Remarks

For fuel For manure Others

Satbaria 62 (20*)

459 395 44 20 Other uses of cow-dung include smearing of court yard and earthen house floor mainly.

Kalamonkhali 35 (11*)

200 145 40 15

Perbishnupur 35 (13*)

190 140 37 13

Total 132 (44*)

849 680 (80.10%)

121 (14.25%)

48 (5.65%)

Source: Field Survey; * Figures in the parenthesis indicate number of HHs.

Page 101: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-C

SWC-17+18; Noagram-Gazaria 8

Currently most HHs is using cow-dung as the main source of fuel (approx. 80.10%). Potential

increase in agricultural crop lands following improvements to flooding a changed situation is expected.

This may reduce the grazing land and livestock population that will reduce the amount of cow dung

available for energy needs. This may lead to increase demand of fuel wood.

9. Fuel wood situation

Fuel wood is available round the year in the area, although its price goes up during monsoon, when

dry fuel wood is scarce. Information on fuel wood has been furnished given in the following table:

Table-9: Availability and use of fuel wood

Village Availability Average consumption/HH

(kg/day)

Remarks

Satbaria Available round the year 6 The availability of fuel wood becomes difficult during the rainy season (during mid-June to mid- October).

Kalamonkhali 7

Perbishnupur 9

Total 7.3 kg

Source: Field Survey

10. Renewable Energy

Cow dung, crop residues, leaves and twigs and fuel wood are main energy sources used for cooking

(major) and crop processing in the area. The extent of different sources is shown as follows:

Table-8: Extent of use of bio-mass sources

Bio-mass sources Extent of uses (per cent)

Cow dung 42.20

Leaves and twigs 18.75

Crop residues 25.50

Fuel wood 13.55

Total 100.00

Source: Data on field survey

Availability of bio-mass sources is not satisfactory to the people of the sample villages for the

following reason.

Page 102: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-C

SWC-17+18; Noagram-Gazaria 9

Shortage of livestock (production of reduced cowdung)

Shortage of crop residues (for crop damage)

Reduced availability of fuel wood.

The potential solution of fuel shortage can be solved as opined by the respondents are as follows, as

opined by the respondents:

Checking crop damage and production of better crops will ensure more crop by-products

More livestock animals should be reared

Jute cultivation should be increased

Increase of plantation activities.

Consumption of renewable energy is mostly utilized for cooking purposes ( 74.50 per cent) whereas

crop processing consume a small extent (25.50 per cent) in SIP-17 and 18 areas.

11. Grazing/Fodder Situation

The study area SWC-17-18 no significant grazing area is present. The situation is worsening day by

day. That’s why number of bovines is decreasing in the area, which ultimately enhanced use of power

tiller for cultivation. Due to lack of fodder the bovine animals’ production capacity is also hampered.

Moreover, reduction of grazing areas farmer’s cost of protecting cattle is increased (shed, guarding).

As a consequence the availability of manure is dwindling resulting in increased use of fertilizers and

less fuel for cooking. Since there is no exclusive area for grazing of bovine animals; they graze the

livestock in the paddy fields (for a short period) after harvest of Boro crops. There is no practice of

growing fodder crops in the area.

12. Biodiversity

According to the local people biodiversity of the study area was rich once upon a time. Due to the

different types of anthropogenic factors the trend of aquatic flora and fauna are decreasing. Some

endangered and threatened species name of SIP-17-18 areas are given in the following table.

Table 11: Biodiversity of SIP-17-18, some threatened and endangered species uses local name

Biodiversity Threatened species Endangered species

Terrestrial fauna kokka, bhuban chil and Shonkha chil bon biral,/bagdasha, ghulo,

badur and kathbirali

Wood species chambal, chatka, lombu, gab and tentul somrail and uri aam

Fruit trees bel, koramcha, kamranga, jalpai, chalita and

dalim

Aesthetic plants ashok and kamini

Herb kumari lata

Reptiles species kanon and ghormoni ghorial

Amphibians kola beng, gecho beng,

mecho beng

Source: Field Survey

Page 103: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

ANNEX – D

SOCIO ECONOMY, GENDER AND LIVELIHOOD

Page 104: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

1

Asian Development Bank Government of the Government of the People’s Republic of Bangladesh Kingdom of The Netherlands

_________________________________________________________________________

Gender and Livelihood Enhanced Perspective (GLEP)

SIP # SWC – 18 (Noagram - Gajaria Scheme)

SOUTHWEST AREAIntegrated Water Resources Planning and Management Project

Bangladesh Water Development Board

SOUTHWEST AREAIntegrated Water Resources Planning and Management Project

Bangladesh Water Development Board

Page 105: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

2

Summary Gender and Livelihood are two complementary aspects of the SAIWRPMP project. The gender aspect relates to involvement of women in water management organizations. As women are socially suppressed by men, in order to protect their rights, at least 30% of the seats of the managing committee of the WMG and WMA shall be allocated for women as per the guideline for participatory water management (GPWM). In these seats only women candidates are allowed to compete in the election. The project should make it their regular activity to empower women in water management sector. The Project will support WMGs / project beneficiaries through PMO / SMO / Line Agencies / NGOs / LGIs with institutional strengthening gender concerns to ensure sustainability as gender is a cross-cutting issue. In these aspects, the situation of poverty, gender & livelihood enhancement and other related social issues were studied through primary data enumeration & FGD for the Noagram-Gajaria Scheme (SIP # SWC – 18) with the newly recruitment facilitator & fine tuned through Research Assistant, during the project between the periods 2008 and April-May, 2011. The objectives of the study is to asses the current poverty & livelihood status, gender & livelihood and Socio-economic situation of the targeted beneficiaries, specially those families and vulnerable women who will be directly or indirectly involved or influenced by the water resource management program of the project. The study was carried out using Participatory Rapid Rural Appraisal (PRRA) method and house to house Households survey under the overall supervision of the concerned persons of the projects Gender & Livelihood Component. The study techniques applied were HHs Survey and Focus Group Discussion (FGD) with marginal farmers, Landless, Share croppers and farm workers group, women’s group and occupational group like fishermen; Key Informant Interviews (KIIs) specially interviewing the formal / informal leaders of community and Local Governments Institutes (LGI), large farmers, businessmen and concerned officials of the governments and non-governments organizations (NGOs). A household survey was also carried out to identity poor and non-poor population per house holds by collecting data on income and expenditure and other basic socio-economic condition. The appraisal on gender & social issues and livelihood look after the demand of the poor and vulnerable women. To get a picture of real socio-economic situation an inventory of households was made in the subunit area on their land ownership, occupational activities, approximate income and expenditure, other family assets (cattle, households farming, non framing equipment etc.), and gender concerns. HHs survey shows that there are 2929 (92%) male headed and 250 (8%) female headed house holds in the area. Out of total HHs also shows the following Landless (1424) 45%, Marginal (732) 23%, Small (522) 16%, Medium (368) 12% and Large (133) 4% HHs in the area. Basically Farmers dimension of land indicate in the area. It was found that about (6602) 39 % of the HHs population lives below poverty line (National average as per BBS 2005 40%). They belong to landless and some of them marginal & small farmers including sharecroppers who cannot meet the required expenditure on food, clothing, healthcare, child education etc. Their main constraints appeared to be very small size of land holding, less job opportunity and low wages (for women less job opportunity and 30% less earnings than men in the same job), and absence of private and public investments (SME or any industry) in the SIP area. The present government safety net programs (VGD, VGF, Old Age, and Widow Allowances) are perceived as inadequate. In the SIP there were 54 poor Female headed HHs who are vulnerable and destitute. All vulnerable women and approximately 30% poor HHs are covered by VGF, VGD, Old age and Widow allowances (Tk. 300.00 - 350.00 per month) under safety net support. The amounts they get are not sufficient to maintain expense of livelihood. Household survey shows that 16730 household’s members including 8557 (51%) male and 8173 (49%) female population live in 13 villages within the subunit area. However, final selection to involve the poor in livelihood enhancement activities (Gender awareness training, technical skill and business training and follow-up training) will be finalized by the selection committees (Representative of WMG, LGI, NGO, PMO / SMO) after formation of the WMG. The final decision will be as per the Managing Committee and project authority’s decision. It is expected that finally selected beneficiaries by the project could be minimum 30% if this total number of poor or approx. Minimum 990 poor women beneficiaries including poor women as target group for their livelihood enhancement (allocation based

Page 106: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

3

on DPP budget and other probable reason is that the committee may not find beneficiaries among the poor who will be able to fulfill the criteria such as interest for training, give time for training, limit of working age 18-50 years, pregnant and lactating mother, ability to invest in business by taking loan etc). It is expected that the proposed livelihood enhancement activities will be undertaken by the remaining beneficiaries through social induced method (adopting some new idea / activity / technology by following the others). Poor Households including vulnerable women living under the poverty line will be able to participate in a variety of income generating activities. A number of such activities are homestead vegetables gardening, seed production, quick growing fruit tree plantation at homestead and timber tree plantation by the roadside and embankment, mini nursery, agri-business, food processing specially rice based food processing (puffed rice, rice ball, toffee, pressed rice), fish cum duck farming including mini hatchery, home based bamboo work, home based jute work and pottery etc. A selection of them will be offered to the beneficiaries, after selection, skill training will be provided to them on relevant activities along with post training support including market linkages. This part of the program will ensure sufficient income for the poor and vulnerable women to reduce their poverty. It was identified that on the two sides of the embankment there are some khash land. This khas land is proposed to be distributed / leasing out to the vulnerable poor women and hard core poor families through establishing linkages with Department of land, local UNO / Upazila parishad, DC and LGIs. Another scope to benefit the hardcore poor and vulnerable women is to involve them in project construction works like canal digging, earth works in connection with embankment through Labour Contracting Society (LCS). The project should take advantage of utilizing local resources and institutions to assist poor for poverty reduction, Facilitating links with other organizations and institutions, such as DAE, DWA, DOF, DOLA, DOC, DSS, DOFT, LGED, DOYD and concerned NGO for specialized skill training and micro credit / SME loan from local banks (10% quota for women entrepreneur, policy imposed by Bangladesh Bank for all Banks), is a part of this effort. One tool has been development to facilitate this process: The Venn diagram analyzes the role of different micro finance institutes. Especially the poor and the vulnerable members of the committees will be monitored in order to see if they benefit from new opportunities under the project, or become marginalized further and would need especial supporting measures by targeting individuals.

Objectives The objectives of the study are: To asses the livelihood status of the targeted beneficiaries specially water resources management

families and vulnerable women; To support project targeted beneficiaries specially the poor to enhance their livelihood and poverty

reduction;

Methodology As mentioned earlier the methodology followed to conduct the study is House holds Survey and participatory Rural Appraisal (PRA). The most important techniques of PRA are Focus Group Discussion (FGD); Key Informant Interviews (KIIs), survey and case study have been chosen and applied to conduct this study.

Page 107: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

4

1. Location SIP # SWC - 18 (Noagram-Gajaria Scheme) of Chenchuri Beel sub-project is located in 2 Unions (Purulia and Peruli) of Kalia Upazila under Narail District. 13 villages from these Two Unions are associated (fully or partly) within this SIP # SWC - 18. SIP # SWC - 18 is popularly known as Liner khal (canal) area and bounded by the river Chitra to the east and the Afra to the west.

2. Introduction Bangladesh Water Development Board has given highest priority to poverty reduction in its development efforts. SAIWRPM project is fully aware of the presence of all pervasive and endemic gender based discriminations and depravations in all social and economic levels, among all castes, religions, and ethnic groups in both poor and non poor beneficiaries of the project area. Bangladesh Water Development Board (BWDB) under the Ministry of Water Resource (MoWR) started the implementation the project “Southwest Area Integrated Water Resources Planning and Management Project (SAIWRPMP)” from 2007 with financial and technical assistance from Asian Development Bank and Royal Netherlands Government. The overall objective of the project is to reduce poverty by increasing agricultural and fish production and employment creation through integrated water management (Flood Control, Drainage and Irrigation) with active participation of the local people. The project focuses need based issues of engineering and technical matters of water management, environment, water management institution/group and association, agriculture and fishery, gender, poverty and livelihood enhancement to achieve its objectives.

One of the objectives of the project is to enhance the livelihood of the poor living within the project area. Provision has therefore been kept within the project frame work to utilize project resources for implementing activities needed to achieve this objective. For this purpose the project felt the need to carry out a study on poverty and livelihood in the selected project area as a preparatory activity for gathering information on key issues of poverty and livelihood. This is extremely needed to make plan and formulate strategies for the implementation of livelihood enhancement activities for the poor. This study is the outcome of project’s primary step to start implementation process on livelihood enhancement for the poor. While in all implementation stage the project decided to ensure people’s participation as a key implementation strategy, this study followed the method of participatory Rural Appraisal (PRA). At the first stage the study has been undertaken at Kalia Upazila of Narail District. The projected present population is 16730 part of which male 8557 (51%) and female 8173 (49%) based line based on enumeration of 2008 and April-May, 2011. According to survey data the total population of the surveyed households is 3179 part of which male headed HHs 2929 and female headed HHs 250. The average household size of the SIP area is 5.26, which is much greater than the national average of 4.8. So, field survey showed a positive link of family size with income; landless, marginal, small, medium and large farmer category identification on quantity of land. The section deals primarily with the clientele or the stakeholders of different classes in the project area and its main socio-economic characteristics.

2.1 List of villages in SIP SIP # SWC – 18 of Chenchuri Beel Sub-project comprises 13 Villages are fully or partly at 2 Unions of Kalia Upazila under Narail districts. Total area is 1471 ha; figure as showing is table 2.1.1.

Page 108: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

5

Table – 2.1.1 : List of Villages in SIP

Sl. No.

Name of Village Union Upazilla District Remarks

1 Dariaghata Purulia Kalia Narail

2 Fuldah Purulia Kalia Narail

3 Amtola Purulia Kalia Narail

4 Kalamonkhali Purulia Kalia Narail

5 Bajebabra Purulia Kalia Narail

6 Noagram Purulia Kalia Narail

7 Diadanga Purulia Kalia Narail

8 Perbishnupur Purulia Kalia Narail

9 Burikhali Purulia Kalia Narail

10 Pervumbhag Purulia Kalia Narail

11 Perulicstan Peruli Kalia Narail

12 Sathbaria Peruli Kalia Narail

13 Patesswari Peruli Kalia Narail

Total 13 2 1 1 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

2.2 Population The projected total population according to HHs survey is 16730 of which male 8557 (51%) and 8173 (49%) female. Showing is table 2.2.1 and pie.

Table – 2.2.1 : Population and Sex Ratio

HHs Categories

Population No of HHs Male Female Total

Landless 3429 3314 6743 1424

Marginal 1955 1964 3919 732

Small 1488 1335 2823 522

Medium 1229 1098 2327 368

Large 456 462 918 133

Total 8557 8173 16730 3179 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Sex Ratio of Population

Male

51%

Female

49%

Male Female

2.3 Adult population The projected total adult population according to HHs survey depicts that among the eligible (18 years & above) is 9737 of which male 5021 (52%) and 4716 (48%) female. Showing is table 2.3.1 and pie.

Table – 2.3.1 : Adult Population and Sex Ratio (18 years & above)

HHs Categories

Population No of HHs Male Female Total

Landless 1924 1881 3805 1424

Marginal 1202 1077 2279 732

Small 954 846 1800 522

Medium 658 644 1302 368

Large 283 268 551 133

Total 5021 4716 9737 3179 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Sex Ratio of Adult Population

Male

52%

Femal

e

48%

Male Female

Page 109: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

6

2.4 House holds The Present situation of projected that total HHs / Family according to HHs survey is 3179 of which male headed HHs 2929 (92%) and 250 (8%) female headed HHs. Maximum HHs are male headed showing is table 2.4.1 and pie.

Table – 2.4.1 : Male and Female headed HHs and Population

Name of Village

Population HHs

Male Female Total Male Headed

HHs Female Headed

HHs Total HHs

Dariaghata 396 374 770 139 3 142

Fuldah 644 606 1250 234 8 242

Amtola 767 758 1525 261 21 282

Kalamonkhali 546 506 1052 199 6 205

Bajebabra 476 459 935 134 29 163

Noagram 1388 1345 2733 475 63 538

Diadanga 654 657 1311 214 24 238

Perbishnupur 1447 1356 2803 500 50 550

Burikhali 395 394 789 135 14 149

Pervumbhag 362 327 689 110 17 127

Perulicstan 481 482 963 179 6 185

Sathbaria 540 515 1055 192 3 195

Patesswari 461 394 855 157 6 163 Total 8557 8173 16730 2929 250 3179

Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Male & Female Headed HHs Status

Male

Headed

HHs

92%

Female

Headed

HHs

8%

Male Headed HHs Female Headed HHs

2.5 Population of HHs Size Ratio The Present situation confirmed is observation that the average size of large farmer HHs is also bigger than that of the landless and marginal farmer’s families. Showing is table 2.5.1 and figure of column.

Table – 2.5.1 : Population of HHs Size Ratio

Page 110: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

7

Land owner Categories

Population No of HHs

HHs Size

Male Female Total

Landless 3429 3314 6743 1424 4.74

Marginal 1955 1964 3919 732 5.35

Small 1488 1335 2823 522 5.41

Medium 1229 1098 2327 368 6.32

Large 456 462 918 133 6.90

Total / Avg. 8557 8173 16730 3179 5.26 Source: HHs Survey, 2009 & 2011, SAIWRPMP, BWDB.

Status of HHs Size

5.266.906.325.415.354.74

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

Landless M arginal Small M edium Large Total /

Avg.

2.6 Age Structure Presents the age structure of the population in the house holds survey and this data is perhaps more intriguing. Available age status information showing is table 2.6.1 and pie.

Table – 2.6.1 : Age Structure of HHs Member

Age

Group

Population

Male Female Total

1 - 17 3304 3145 6449

18 - 45 3593 3488 7081

46 - 60 1182 1047 2229

61 + 478 493 971

Total 8557 8173 16730 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Age Structure of Population

0 - 17

39%

18 - 45

42%

46 - 60

13%

61 +

6%

0 - 17

18 - 45

46 - 60

61 +

2.7 HHs category of Land Land man relationships are immensely important in agriculture. The tenure arrangement influences the whole production system significantly. Main socio-economic condition dimension category of per farmer land identity. 5 kinds of farmer / Family / HHs are very clearly showing at table 2.7.1 and pie. Maximum HHs is landless (45%) and marginal (23%). Basically this overview is very strong and respectively.

Table – 2.7.1 : HHs category of Land owner basis under the village

Page 111: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

8

Name of Village HHs Category of Land

Total Landless Marginal Small Medium Large

Dariaghata 78 15 18 15 16 142

Fuldah 85 60 45 41 11 242

Amtola 129 59 41 38 15 282

Kalamonkhali 89 46 35 22 13 205

Bajebabra 45 49 39 19 11 163

Noagram 228 118 87 72 33 538

Diadanga 116 44 55 18 5 238

Perbishnupur 258 128 88 63 13 550

Burikhali 71 47 17 12 2 149

Pervumbhag 63 30 16 12 6 127

Perulicstan 110 37 16 19 3 185

Sathbaria 96 48 28 20 3 195

Patesswari 56 51 37 17 2 163

Total 1424 732 522 368 133 3179 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

HHs Category of Land Large

4%

Medium

12%

Small

16%

Marginal

23%

Landless

45%

Landless Marginal Small Medium Large

2.8 Male & Female headed HHs category of Land The survey data shows that some landless and marginal female headed HHs is stated in the area. Basically in attendance are poor female families. Obtainable figure is show at table - 2.8.1 and pie.

Table – 2.8.1 : HHs Category of Land owner basis in Male & Female headed HHs in the area

Name of

Village

Category of Land Owner Total Total

HHs

Landless Farmer (0-49

Dec)

Marginal Farmer (50-

120 Dec)

Small Farmer (121-247 Dec)

Medium Farmer (248-

500 Dec)

Large Farmer ( > 501)

No. of HHs

Male Female Male Female Male Female Male Female Male Female Male Female

Dariaghata 76 2 15 0 17 1 15 0 16 0 139 3 142

Fuldah 79 6 58 2 45 0 41 0 11 0 234 8 242

Amtola 124 5 53 6 35 6 34 4 15 0 261 21 282

Kalamonkhali 86 3 44 2 34 1 22 0 13 0 199 6 205

Bajebabra 35 10 42 7 33 6 15 4 9 2 134 29 163

Noagram 203 25 96 22 75 12 68 4 33 0 475 63 538

Diadanga 98 18 39 5 54 1 18 0 5 0 214 24 238

Perbishnupur 228 30 116 12 82 6 61 2 13 0 500 50 550

Burikhali 65 6 42 5 15 2 11 1 2 0 135 14 149

Pervumbhag 51 12 28 2 14 2 11 1 6 0 110 17 127

Perulicstan 105 5 37 0 16 0 18 1 3 0 179 6 185

Sathbaria 93 3 48 0 28 0 20 0 3 0 192 3 195

Patesswari 53 3 51 0 37 0 14 3 2 0 157 6 163

Page 112: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

9

Total 1296 128 669 63 485 37 348 20 131 2 2929 250 3179 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Category of Land Owner

4%1%

11%

15%

2% 21% 4%

41%

0.07%

1.17%

Landless Farmer (0-49 Dec) M ale

Landless Farmer (0-49 Dec) Female

M arginal Farmer (50-120 Dec) M ale

M arginal Farmer (50-120 Dec) Female

Small Farmer (121-247 Dec) M ale

Small Farmer (121-247 Dec) Female

M edium Farmer (248-500 Dec) M ale

M edium Farmer (248-500 Dec) Female

Large Farmer ( > 501) M ale

Large Farmer ( > 501) Female

2.9 Occupation Status Occupation indicates sources of income from work, time spent in work as well as social status. Table shows the main households occupation. Agriculture farming is the main occupation of all categories of farmers. Wage / Daily labourers are mostly found in landless, marginal and small farm families. Trade and business as family occupation is found in all level farmer. IGA is very importance of livelihood development. But IGA is very atypical of found in all level farmer. Also actual fisherman is very exceptional. Maximum populations are being used HHs work and students. The table - 2.9.1 and pie shows in all occupational figures.

Table – 2.9.1 : Occupation of Respondent population in the area

Occupation Categories HHs Category

Total Landless Marginal Small Medium Large

Agri. Farmer 1811 1104 532 349 162 3958

Fisherman 35 24 17 7 1 84

Partial Fisherman 19 29 35 19 12 114

Day Labour 618 312 274 214 12 1430

Transport Worker 247 138 73 82 14 554

Service Holder 214 197 154 161 147 873

Traders / Businessmen 104 48 46 67 44 309

Student 1354 972 576 512 207 3621

HHs Works 1795 833 747 695 180 4250

IGA 15 9 8 5 4 41

Destitute / Vulnerable Women 48 4 2 0 0 54

Others 483 249 359 216 135 1442

Total 6743 3919 2823 2327 918 16730 NB : IGA = (Handicrafts, Embroidery, Poultry, B. fattening, V. Gardening, Cow rearing, Duck farming, Livestock, Nursery, Hatchery etc.)

NB : Day Labour =(Daily Wage labour, Rajmistri, Daily Agri. Farmer, Carpenters, Blacksmith, Barber, Tailor, Potterman, Hawker, Electrician etc.)

NB : Transport Worker = ( Ricksaw, Van, Bus, Track, Boat, Launch, Tempu, Grambangla & others Driver etc.)

NB : Others = ( Infant, Unemployed, Beggar & Old etc.)

NB.: Service Holder = (GOB, NGO & Private etc.)

Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Page 113: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

10

Main Occupational Status Agri Farmer

24%

Fisherman

0.50% Partial Fisherman

1%

Day Labour

9% Transport

Worker

3%

Service Holder

5% Traders /

Businessmen

2%

Student

22%

HHs Works

24%

IGA

0.24%

Destitute /

Vulnerable

Women

0.33%

Others

9%

Agri Farmer Fisherman Partial FishermanDay Labour Transport Worker Service Holder Traders / Businessmen Student HHs WorksIGA Destitute / Vulnerable Women Others

Table – 2.9.2 : Assessment of fishing community

Fishermen social position Present profession

Hose Hold Type

HHs Nos

Caste Nos of

member Fishermen Farmer

Fish trading/ Gher/Labour

Full time

fishing

Part time

fishing

Traditional Hindu

fishermen HH 15 Hindu 45 30 6 9

84 114 Non Traditional

Muslim fishermen HH

52 Muslim 156 54 18 81

Fifteen (15) nos traditional fishermen households exists in this sub–unit area since about 8th generation, all are of Hindu religion and social order is in the name of Rajbongshi and also fifty two (52) nos non-traditional Muslim fishermen households exists in this area. Now most of the fishermen have changed their profession in course of time due to lack of open water fish in the river, beel and khals having less availability of fish due to over fishing. Some fishermen are now engaged in agriculture, catching fish in the beel during monsoon, some time caching fish in Gher (Close water fishing inland) on hire and fish trading. Most of the fishermen families are becoming affluent day by day; they are taking education and trying to live a better life. As per field data about 12% of professional fisher men are connected with agriculture, they catch fish in the beel during monsoon and also catch fish in Gher (Close water fishing) on hire; about 45 % of traditional & non-traditional fishermen are engaged in culture fish production, fish trading and labour and about 42% of traditional fishermen are fishing in khal and river, fishing in beel during monsoon and fishing in Gher (Close water fishing) on hire. In this area some Muslim and Hindu fishermen ( Total=114 nos) are also catching fish in beel area during monsoon period, actually they are farmer, daily labourers, Rickshaw Pooler etc. They have been shown as part time fishermen. So there have no adverse impact in the traditional Hindu fishermen community.

2.10 Poor / Non Poor population

Page 114: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

11

Figure at table – 2.10.1 and pie summarize the monthly per capita income for the various groups of farmers families in the project area. Maximum Small, Large, medium and marginal farming HHs population income is normally indication of Non poor but landless HHs population 67% is poor. Table – 2.10.1 : Poor/Non poor population identification Per Capita Income/ monthly in the area

Type HHs Category

Total Landless % Marginal % Small % Medium % Large %

Poor 4522 67.06 1081 27.58 508 18.00 403 17.32 88 9.59 6602

Non Poor

2221 32.94 2838 72.42 2315 82.00 1924 82.68 830 90.41 10128

Total 6743 100 3919 100 2823 100 2327 100 918 100 16730

NB : Poor = ( Per capita monthly Tk. 742 < ) and Non Poor = ( Per capita monthly Tk. 742 > ) . Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Poor and Non Poor Status

Poor

39%

Non

Poor

61%

Poor

Non

Poor

2.11 Educational Status

In the project area the literacy rate is 76% which part of the male literacy rate is 40% and the female literacy rate is 36% against the national average of 65%. Figure showing the table 2.11.1 and pie of primary level, junior secondary, Secondary, Higher Secondary, Graduate, Self taught and Illiterates data & % figure are presented.

Table – 2.11.1 : Educational Attainment

Education Status

Literacy Rate (%)

Total Male Female

No % No %

Primary (Class I - V) 2718 31.8 2534 31.0 5252

Junior Secondary (Class VI - VIII) 1154 13.5 1247 15.3 2401

Secondary and Equivalent 793 9.3 776 9.5 1569

Higher Secondary and Equivalent 482 5.6 427 5.2 909

Graduate / Post Graduate and Equivalent 172 2.0 83 1.0 255

Literacy Course / Self taught 1386 16.2 1022 12.5 2408

Illiterate 1852 21.6 2084 25.5 3936

Total 8557 100% 8173 100% 16730 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Page 115: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

12

Literacy Rate

Fema

le

36%

Illiter

ate

24%

Male

40%

Male

Female

Illiterate

Educational Status

32%

14%

9%5%

2%

14%

24%

Primary (Class I - V)

Junior Secondary (Class

VI - VIII)

Secondary and

Equivalent

Higher Secondary and

Equivalent

Graduate / Post Graduate

and Equivalent

Literacy Course / Self

taught

Illiterate

2.12 Housing Characteristics In earlier days the roof of a house most prominently depicted the socio-economic status of household in society. But with the paucity of availability of straw / bamboo / katcha and difficulty in maintenance, the poor and non poor also have gone for tin / CI sheet / semi brick wall roofing of the main house. The data shows that figure in the table – 2.12.1 and pie are offered in the present situation at the SIP area.

Table – 2.12.1 : Main Housing Characteristics of HHs

Type of Roof HHs Category

Total Landless Marginal Small Medium Large

Pucca 32 41 47 37 33 190

Semi Pucca 172 145 158 92 34 601

Tin + Bamboo 936 398 263 221 66 1884

Jute Stick + Straw 158 84 24 3 0 269

Kacha 55 30 12 7 0 104

Others 71 34 18 8 0 131

Total 1424 732 522 368 133 3179 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Housing Characteristics status

Others

4%Kacha

3%

Jute Stick +

Straw

8%

Tin + Bamboo

60%

Semi Pucca

19%

Pucca

6%

Pucca Semi Pucca Tin + Bamboo Jute Stick + Straw Kacha Others

2.13 Sanitation Status

Page 116: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

13

The toilet facilities for discharging of human waste are important element for healthy and hygienic environment of households. The use of sanitary latrine has improved tremendously over the last decades. The present important Figure showing the table – 2.13.1 and pie.

Table – 2.13.1 : Access to Sanitation of the HHs in the SIP area

Type of Latrine HHs Category

Total Landless Marginal Small Medium Large

Sanitary / Pucca 71 72 74 115 38 370

Ring Slub 1153 529 382 200 81 2345

Katcha / Hanging 144 86 45 38 11 324

Open 56 45 21 15 3 140

Total 1424 732 522 368 133 3179 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Sanitation Status

Sanitary /

Pucca

12%

Ring Slub

74%

Katcha /

Hanging

10%

Open

4%

Sanitary / Pucca Ring Slub Katcha / Hanging Open

2.14 Drinking Water Status Due to acute scarcity of drinking Water the local people use more than one source for drinking purpose. Table – 2.14.1 and figure of pie shows that in the project area. 95% people are drinking of tube well water, but it is not tested.

Table – 2.14.1 : Sources of drinking water of the HHs within the SIP area

Type HHs Category

Total Landless Marginal Small Medium Large

Tube well 1367 701 486 346 128 3028

Pond / khals / rivers 41 14 11 4 0 70

Others 16 17 25 18 5 81

Total 1424 732 522 368 133 3179 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Sources of Drinking Water

Tube

well

95%

Pond /

khals /

rivers

2%

Others

3%

Tube w ell Pond / khals / rivers Others

2.14.2 Arsenic Contamination circumstances

Page 117: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

14

It is found that test of arsenic contamination of HTWs of both the sampled villages of SIP-18 has been carried out by DPHE between 2003 and 2006, total number of HTWs are being about 500, although there is no report of arsenic-contaminated HTW in the area. An NGO, namely Ullashi, Sreejoni, imparted awareness training on adverse affects of drinking arsenic contaminated water during 2007. The study area people commented that the water contain fewer quantity saline and iron component in the HTW. In order to mitigate SAIWRPMP will provide some deep tube well to the arsenic affected villages according to their agreement. SAIWRPM project will be provided a deep tube well per WMG to mitigate arsenic for drinking water.

2.15 Present Health Status Table – 2.15.1 shows the common disease of the SIP area. Modern medical facilities are not available to large population. For many people the medical facilities are far away and difficult to reach. The health condition of the people in the project area is generally poor. It is found from the sample households that the landless and marginal farmer mostly suffer from water borne disease. The common disease are Gastric, Diarrhea / Dysentery, Influenza / Cough, Jaundice, Pain in Hip / Back etc. figure and % showing the pie.

Table – 2.15.1 : Most common Diseases mentioned by Respondents

Type of Disease HHs Category Total

Landless Marginal Small Medium Large No

Gastric 332 209 175 86 38 840

Diarrhea / Dysentery 268 56 46 23 6 399

Influenza / Cough 401 162 167 120 41 891

Pain in Hip / Back 212 143 52 87 31 525

Jaundice 31 13 8 12 3 67

Others 142 92 42 31 13 320

Diseases Free 38 57 32 9 1 137

Total 1424 732 522 368 133 3179 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Main Disease of Respondent

Gastric

26%

Diarrhea /

Dysentery

13%

Influenza /

Cough

28%

Pain in Hip /

Back

17%

Jaundice

2%

Others

10%

Disease Free

4%

Gastric Diarrhea / Dysentery Influenza / Cough Pain in Hip / Back Jaundice OthersDisease Free

2.16 Electricity Coverage Status Out of total house holds maximum respondents answered to the question. Among them 39% HHs mentioned they have electricity connection in their houses. And 61% HHs they have no electricity connection in their houses. Show the table – 2.16.1 and pie.

Page 118: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

15

Table – 2.16.1 : Electricity coverage according to per HHs

Electricity Status

HHs Category Total No Landless Marginal Small Medium Large

Yes 416 319 254 174 75 1238

No 1008 413 268 194 58 1941

Total 1424 732 522 368 133 3179 Source: HHs Survey, 2008 & 2011, SAIWRPMP, BWDB.

Electricity Coverage

No

61%

Yes

39% Yes

No

3. Findings of the Study Some of the Key findings followed House Holds survey study analyzed below:

The area is connected by a semi paved and unpaved road through which only light transport vehicle (rickshaw/ van/ bicycle) and occasionally light motor van move. Due to constraints in resources and time only the household heads / members were interview on their quantity of land, education, occupation, income and assets etc. owned by them. In the synthesized socio economic data of 13 villages of the SIP has been presented. This gives some insight on general socio economic conditions of the people living under the Hydrological Unit or SIP # SWC – 18. Analysis of these data was supported by Households Survey, field observation report and FGDs. Both data and its analysis were made gender disaggregated. The table shows that 42% populations are within the age 18-45. This demographic situation indicates the existence of a very good number of working age population within the SIP area. Their labour and skills may be utilized for the socio economic development of people living within the SIP area. The average literacy rate although 76% its distribution is more within self taught to post graduate, primary (32%) followed by 14% within VI-VIII / Junior secondary, 9% Secondary, 14% Self taught and illiterate is 24%. This indicates also a large percentage of school dropouts especially among poor community. Probably it is the personal initiative that they themselves took this skill training from Government and Non Government Organizations. But this is not a sufficient number to build human capital for socio economic and livelihood development. The project cans intervene in this area at least with a program of skill and business training. Such intervention will contribute to develop socio economic condition and livelihoods of people. The project should also undertake advocacy and awareness creation program to give most basic education under adult no formal education program in collaboration with local elected bodies or through WMA to its beneficiaries. The same is with other social indicators. For example occupation of highest number of people is Agri farming (24%) followed by small trade/ business (2%), actual + partial fishermen (1.24%), day labour (9%), Transport worker (3%) Service holder in GOB, NGO and private organization (5%), Student (22%), IGA (0.24%), HHs / family works (25%) and Destitute / Vulnerable (0.33%) are also included. The encouraging fact is that the others (infant, old and unemployment) rate is 9% and maximum women are involved in HHs or family work. So, it is big fact of development in the area. Various IGA training is very essential in the area. The project should address this issue by creating alternative employment.

Page 119: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

16

The income shows that more than 39% of families population monthly income less than Tk. 742, to meet their basic requirement (food, cloth etc) which indicate that they are living below poverty line And 61% families population monthly income more then Tk. 742 which indicate that they are living upper poverty line. As per study the House Hold Survey mentioned by gender and livelihood disaggregated. This means medium poverty exists in the SIP area. Poverty reduction measure is therefore a justified intervention by the project. This figure is secure to national average (44.3% as per BBS 2005 sample survey) which justifies the validity of data and also justifies the fact that one of the causes of poverty is landlessness. The project should therefore undertake alternative livelihood enhancement activities to reduce the poverty of landless poor. Indicators on household structure show a little bit better living condition both for poor and non poor including female headed households. 60% of households have houses with Tin + Bamboo and 8% of HHs they have houses in Jute stick & straw roofing. Maximum poor / non poor are included in this figure. 19% of HHs has houses with semi pucca (Brick wall + Tin) roofing. Maximum large and medium non poor HHs is included in this figure. On drinking water it is encouraging. Almost 95% including poor and non poor have access to safe drinking water / tube well. In case of sanitation it is worst. 74% HHs have water sealed Ring slub latrine, 12% sanitary latrine, 10% Katcha / hanging and 4% open latrine. The project through WMG should address this issue with technical support from district public health engineering department. Temporary Migration for Employment and Income: This is both a social and an economic problem a large number of families / HHs, approximately 50% FGD members thinkable 0.5% people of out migrate to Bombay, India, UAE, Saudi Arab, Qatar, Quet, Malaysia, Singapore, Korea illegally for hard work (men find work in construction and women in rich men’s house as maid) for a year or two and return with Tk. 30000-35000. They invest this money to construct a house or to buy other asset or to repay loan. 30% of them are harassed by broker, police etc and return with penniless. Some time they remain in jail for several months. Cases of trafficking are reported but not significantly (even less than 1%). The men of these poor families work as illegal worker in construction site and the women work as house maid. Some women also work as construction worker. Such illegal migration is not acceptable. This could only be reduced if the project creates alternative employment opportunities for them. In spite of low illiteracy rate and poor base of physical and human capital / assets, existing natural resources / Beel / canal / river / water may be utilized through better management to improve livelihood of poor community. Intervention by this project through construction / rehabilitation of water structure for an efficient water resource management along with other alternative opportunities will definitely contribute to create more employment and improve livelihood through increased cropping intensity and its yield and an increased fish production which ultimately improve the social and economic condition of people in the SIP area.

4. Focus Group Discussion for the Need Assessment of Gender and Livelihood Enhancement Activities The objectives of the study is to asses the current poverty & livelihood status, gender & livelihood and Socio-economic situation of the targeted beneficiaries, specially those families and vulnerable women who will be directly or indirectly involved or influenced by the water resource management program of the project. The study was carried out using Participatory Rapid Rural Appraisal (PRRA) method under the overall supervision of the concerned persons of the projects Gender & Livelihood Component. The study techniques applied were Focus Group Discussion (FGD) with marginal farmers, Landless, Share croppers and farm workers group, women’s group and occupational group like fishermen; Key Informant Interviews (KIIs) specially interviewing the formal / informal leaders of community and Local Governments Institutes (LGI), large farmers, businessmen and concerned officials of the governments and non-governments organizations (NGOs).

5. Location of FGD

Page 120: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

17

Eight Focus Group Discussion (FGD) were held in the project area and a number of Key Informants Interviews (KIIs) were carried under the study. These provided perception of the communities about the existing water resources with regard to irrigation, drainage condition and flood hazards, and their ideas and priorities about the improvements needs.

At village level, discussion were held with different categories of people, ranging from farmers, fishermen, boatman, small traders, landless, destitute & vulnerable women, union level LGI, UP Chairman & Members, Religious leader, school teacher and others people.

Table – 5.1 : Place of Focus Group Discussion (FGD) SWC – 18

District Upazila Union Village Date Place Participants

Narail Kalia Purulia fuldah 19.11.2008 Fuldah Village 37

Narail Kalia Purulia Amtola 01.12.2008 Amtola Village 41

Narail Kalia Purulia Diadanga 16.12.2008 Diadanga Village 34

Narail Kalia Peruli Perulicstan 27.12.2008 Perulicstan Village 42

Narail Kalia Purulia Bajebabra 18.12.2008 Bajebabra Village 28

Narail Kalia Purulia Kalamonkhali 12.05.2011 Kalamonkhali Village 48

Narail Kalia Peruli Patesswari 23.05.2011 Exist. Regulator 35

Narail Kalia Purulia Noagram 24.05.2011 Noagram Village 38

1 1 2 8 Total 8 FGD 303

6. Poverty Poverty has been assessed in this study by making a monthly expenditure for basic need (food, clothing, children education and health care) survey for each individual HHs of villages within the SIP area. The number of poor or incidence of poverty is further validated by comparing with poverty information from Key Informants (Kls), FGDs and literature. 85 Kls or 218 FGD members are comments on poverty situation in this area. According to maximum KIs the incidence of poverty therefore is Acceptable ranges in this area. But according to maximum FGD member’s comments on the incidence of poverty therefore is very highly a range of acceptable in the area. The number of poor or incidence of poverty is further validated by comparing with poverty information from Key Informants (Kls), FGDs and literature. The information of poverty given by Kls and FGDs is given in following table.

Table 6.1 : Present Poverty Situation Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls or FGD members

No of Kls or FGD

members commented

Total No of Kls or FGD members

% Ranking

KIs : How is the poverty situation in the area?

Very high or above 75% 25 85 30% 3 or not

acceptable

High or within the range of 51% - 75% 51 85 60% 4 or

acceptable

Moderate or within the range of 35-49% 9 85 10% 3 or not

acceptable

FGDs : How is the poverty situation in the area?

Very high or above 75% 153 218 70% 4 or

acceptable

High or within the range of 51% - 75% 44 218 20% 3 or not

acceptable

Moderate or within the range 35-49% 22 218 10% 3 or not

acceptable

7. Causes of Poverty

Page 121: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

18

These causes of high poverty as expressed by the majority participants of FGD and Kls 80% of Kls and 80% of FGD participants are very common, logical and justified. They are lack of employment, Decrease of cultivable land, low literacy rate and no facilities for skill development, lack of communication network, Marketing problem, Lack of Credit facilitates, Low wage rate of women and lack of seed & fertilizers problem.

These causes are logical and justified. However, the project has limitation to address all the causes. Project’s gender and poverty component may address the employment issues by undertaking tailored made skills training to promote income generating activities for the poor. The projects do not have approved resources allocation or provision to address the other causes directly. However increased fishery and crop production due to project intervention will create employment opportunities as a whole which will contribute to reduce poverty. The causes of poverty are relevant to local situation. Most interesting is that the people are aware of it. Their opinion is summarized in the following table:

Table- 7.1 : Causes of Poverty

Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls or FGD members No of Kls or

FGD members commented

Total No of Kls or FGD members

% Ranking

KIs : What do you think what could be the possible causes of so high or high poverty?

Decrease the cultivable land, Lack of employment, low wage, irrigation problem, agriculture seed & fertilizers problem, low literacy rate, Training & skill problem, inadequate credit facilities, lack of communication network.

68 85 80% 5 or highly acceptable

FGDs : What do you think what could be the possible causes of so high or high poverty?

Decrease the cultivable land, Lack of employment, low wage, irrigation problem, agriculture seed & fertilizers problem, low literacy rate, Training & skill problem, inadequate credit facilities, no industry. Marketing problem.

175 218 80% 5 or highly acceptable

8. Poverty Reduction According to most FGD participants and key informant skill training, VGD, Old age and Pregnant women allowances, awareness raising and road construction (road, bridge, canal etc.). Under took by the government, although in limited scale, contributed to increase employment opportunity for the people. Maximum number of KIs and FGD participants told that immunization and safe drinking water program implemented by the government agencies made an impact on poverty reduction. The team enquire these facts further by observation and discussing it informally with local people in market place and union parishad / local Govt. body and a few district level and Upazila level government officers like District Women affairs, Rural Development officer, Block Supervisor of DAE etc. who informed the team that government budget is extremely poor compare to need, size of area and number of people and therefore whatever development activities they implement, its impact are forgotten by the people quickly and its visibility disappear although it creates some impact at least on a few poor families

Government Organizations and its Impact Different agencies / department of government and NGOs implement development program aimed at reducing poverty directly or indirectly. The issue was discussed with the Key informants as they are

Page 122: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

19

most aware of it and even involved with it. The following table summarizes their comment / opinion and also result.

Table – 8.1 : Poverty Reduction Program undertaken by the Government and non- Government Organizations and its impacts

Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls or FGD members

Comment on Impact

No of Kls / FGD

Participants

Total No of Kls or FGD members

% Ranking

KIs : Development Program undertaken by the government and NGOs in this SIP aimed at reducing poverty directly or indirectly.

Skill Training, VGD, Old age and pregnant women allowance, awareness raising and road construction (road, bridge, canal etc.)

Employment Increased

56 85 65% 4 or

acceptable

VGD, Old age and maternity allowances

Impact insignificant on poverty

60 85 70% 4 or

acceptable

Immunization and supply of safe drinking water

Contribute poverty

reduction 72 85 85%

5 or highly acceptable

FGDs : Development Program undertaken by the government and NGOs in this SIP aimed at reducing poverty directly or indirectly.

Skill Training, VGD, Old age and pregnant women allowance, awareness raising and road construction (road, bridge, canal etc.)

Employment Increased

131 218 60% 4 or

acceptable

VGD, Old age and maternity allowances

Impact insignificant on poverty

153 218 70% 4 or

acceptable

Immunization and supply of safe drinking water

Contribute poverty

reduction 185 218 85%

5 or highly acceptable

Government development program especially Skill training, VGD, Old age and pregnant women allowances, awareness raising and road construction (road, bridge, canal etc.). Although compare to the need it is inadequate it contribute to increase employment and reduce poverty. Immunization, supply of safe drinking water by tube well and family planning service did not contribute to reduce poverty directly, a one third of KIs and FGD participants made opinion that immunization and safe drinking water contribute to poverty reduction process by saving cost of health care and keeping the family size smaller. Transfer or adaptation of new improved agriculture technology and construction of new road linking to city town market place etc. can create tremendous impact on poverty reduction.

9. Gender Participation of situation Demand for Family / HHs Regarding the community level local people to present overall scenario about the participation of male and female members of different issues influencing the livelihood and position of different decision making on the area. The table on present scenario, indicates that the major components to dependent of men are very highly influencing, Participation at the HHs decision making to men and women are medium influencing, Participation at the community level decision to dependent of men are very highly influencing and Knowledge & awareness to men and women are low influencing of the area.

Table - 9.1 : Major Gender Dimension and Participation

Sl. No

Components / Factors Women Men

No L M H No L M H

1 Control over HHs resources (Land, Crop, Cow etc.) √ √

2 Mobility inside the community (relative, shop, group meeting etc.)

√ √

3 Mobility outside the community (market, labour, crop field, hospital, bank, fair, movie etc.)

√ √

Page 123: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

20

4 Participation at the HHs Decision :

a. Decision to have new children √ √

b. Decision to undertake new economic activity √ √

c. Decision to purchase / sell of property √ √

d. Decision to children schooling √ √

e. Decision to children marriage √ √

f. Decision to buy inputs and daily essentials √ √

5 Participation at the Community Decision :

a. Participation in the Mosque / mondir committee √ √

b. Participation in village development activity √ √

c. Participation in school management committee √ √

d. Participation in village salish √ √

e. participation in union parishad √ √

6 Knowledge and Awareness :

a. Law related to marriage and divorce √ √

b. Law related to inheritance rights √ √

c. Legal process to torture and inhuman treatment √ √

NB : L = Low ; M = Medium ; H = High

10. Present Livelihood Situation in the area Livelihood is maintaining life with its basic means or food, shelter, clothing, health care, safe drinking water etc for which assets are required as described earlier in methodology. The issues on present livelihood situation were discussed with randomly by field facilitators especially with families appeared to be poor, landless and marginal and farmers. Poverty and livelihood relates closely in the way that if poverty reduce livelihood improves proportionately. Some assets like cattle, chicken etc. can be acquired by taking loan from NGOs which are now available. Land is expensive and acquiring it is difficult. Skills can be acquired by training and physical ability to work can be better utilized by creating employment opportunities against wage. It was also examined through Kls (FGD participants declined to comment on this issue) that for what purpose micro credit are being used. These are summarized as follows:

10.1 Impact of Micro Credit It was also examined through FGD and Kls whether micro credit creates an impact on livelihood enhancement and poverty reduction. Majorities of Kls (30%) and FGD participants (50%) who are users of micro credit gave opinion that micro credit help to increase income and improve livelihood. It is summarized as follows:

Table – 10.1.1 : Impact of Micro Credit on Livelihood Enhancement and Poverty Reduction Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls or FGD members No of Kls or

FGD commented

Total No of Kls or FGD members

% Ranking

Kls : How is micro credit helping in poverty alleviation?

Increasing income, improving livelihood, developing housing, increasing facilities of education and health care. Fish Farm, Beef fattening, Agri farming, Investment of small cottage & handicrafts.

26 85 30% 3 or not

acceptable

FGDs : How is micro credit helping in

Increasing income, improving livelihood, developing housing, increasing facilities of education and health care. Agriculture

109 218 50% 4 or

acceptable

Page 124: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

21

poverty alleviation?

Investment.

10.2 Use of Micro Credit Majorities of Kls told that micro credit are being used for small business, crop cultivation, beef fattening and van purchase. 100% Kls and FGD participants told that NGOs are the biggest providers of micro credit. It is in fact true. Grameen Bank, BRAC, Proddipan, Banchte Shekha, Palli Dardro Foundation, Kalia Daridro Foundation, Gram Bangla, Sabuj Samity, Jagoroni Chakro Foundation, ASHA, and BRDB, Krishi Bank, Sonali Bank are also providing credit. The team however could not find its evidence in the area. Thus the role of micro credit can not be ignored for livelihood enhancement. According to most Kls its demand is high and continues to increase. The project should take this advantage. Through WMG they should take collective loan from the bank with low interest and distribute to marginal farmers, landless share croppers and other poor members of WMGs. Such provision now exists in all nationalized banks.

Table – 10.2.1 : Use of Micro Credit Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls No of Kls or

FGD commented

Total No of Kls or FGD members

% Ranking

Kls : what purpose are used of micro credit?

Small business, crop production, cow rearing, beef fattening, Poultry farming, livelihood expenditure, payment of loan, marriage of daughter, house preparation or repair.

67 85 80% 5 or highly acceptable

FGDs : what purpose are used of micro credit?

Small business, crop production, cow rearing, beef fattening, Poultry farming, livelihood expenditure, payment of loan, marriage of daughter, house preparation or repair.

196 218 90% 5 or highly acceptable

Key Findings of the Micro credit study Present livelihood is inadequate for most people of SIP area due to the possession of little amount of assets / land, cattle, chicken, skills, low wage etc and under utilization of health asset or physical ability to work. Land being an expensive asset is difficult to acquire by them or though external assistance. However, its productivity can be increased for more income by applying improved technology. Other assets like cattle, chicken, skills etc. can be acquired through generation of additional income, saving and external assistance (micro credit, grant etc.) for a better livelihood. The role of micro credit can not be ignored for livelihood enhancement. According to most Kls, demand of micro credit is high and continues to increase. The project should take this advantage. Through WMG they should take collective loan from the bank with low interest and distribute to marginal farmers, landless share croppers and other poor members of WMGs. Such provision now exists in all nationalized banks. The occupational group or fishermen and potters are facing difficulties to maintain livelihood due to reduction of fish population and increased price of potter’s raw materials. They need assistance through alternative employment creation. Inadequate livelihood created social problem like trafficking of women and children. Especially the poor women need alternative employment to improve their livelihood. Underutilized physical ability of most women may be utilized for income by creasing alternative employment opportunities (non farm).

11. Options for Livelihood Enhancement Activity

Page 125: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

22

Identifying options to support the Livelihood enhancement of poor beneficiaries is one of the major objectives of this study. Related issues on different options of livelihood enhancement were discussed with FGD participants and KIs and the result is summarized in the following tables:

Income Generating Activity Present livelihood is Agricultural Income Generating Activities is small relevant but non farm income generating activities is not relevant of the area. Although the study team took opinion from KIs and FGD participants on possible IGAs, they verify these recommendations with local realities (resource owned by communities, capital supply, available land, market and credit facilities and institutional support). The team found that the following IGA are technically and economically feasible for the poor families. The team therefore recommended the following livelihoods enhancement for the identified poor families of the area.

Table – 11.1 : Income Generating Activities Situation Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls or FGD No of

Kls / FGD commented

Total No of Kls or FGD members

% Ranking

KIs : what are the agricultural Income Generating Activities of the Area?

Early HYV / Hybrid rice, pulse crop, Vegetables, Integrated Rice and Fish culture, Duck farming, Poultry, Cow & Goat rearing, Beef fattening, Seed processing, Food processing, Oil seeds,

17 85 20% 3 or not

acceptable

FGD : what are the agricultural Income Generating Activities of the Area?

Early HYV / Hybrid rice, pulse crop, Vegetables, Integrated Rice and Fish culture, Duck farming, Poultry, Cow & Goat rearing, Beef fattening, Seed processing, Food processing Oil seeds,

65 218 30% 3 or not

acceptable

Page 126: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

23

KIs : what is the probable non farm Income Generating Activities in the area?

Home based jute industry, small business, case culture, organic fertilizer, food processing, masonry, Handicraft,

17 85 20% 3 or not

acceptable

FGDs : what is the probable non farm Income Generating Activities in the area?

Home based jute industry, small business, case culture, organic fertilizer, food processing, masonry, Handicraft; Home based bamboo work, Pottery.

44 218 20% 3 or not

acceptable

12. Expectation of the Project The team also carried out FGDs and KIs survey whether the proposed project may create options for their expectation of the project for livelihood enhancement. These are summarized below:

Table – 12.1 : Expectation / Support / Demand of the Local Area Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls or FGD No of Kls/

FGD commented

Total No of Kls or FGD members

% Ranking

Kls : What is your Expectation / support / demand?

Increase Income per capita & development

68 85 80% 4 or

acceptable

Increase Agriculture production

Increase small cottage & business Poverty reduction & social development

Education & Health sector development Infrastructure & Communication development Agriculture & Others Marketing

FGDs : What is your Expectation / support / demand?

Increase Income per capita & development

185 218 85% 4 or

acceptable

Increase Agriculture production

Increase small cottage & business Poverty reduction & social development

Education & Health sector development Infrastructure & financial development Agriculture & Others Marketing

Although the study team took opinion from KIs and FGD participants on possible for local beneficiary members demand of acceptable on Increase Income per capita, Agriculture production, small cottage & business, Poverty reduction & social mobilization, Education & Health sector development, Infrastructure & communication, and marketing of the area.

13. Services of GOB & NGO Structure Although the study team took opinion from KIs and FGD participants on present situation on services of GOB is very low (15%) and lack of demand of the area. But NGO supported is comparably is good because 35% - 45% people are involved any other NGO and others private credit organization.

Table – 13.1 : Present Services of GOB & NGO Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls No of

Kls / FGD commented

Total No of Kls or FGD members

% Ranking

Page 127: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

24

Kls : what are the Service of GOB?

Bank, DAE, DOF, DWA, DOL, PWDB, BWDB, BRDB, BBS, LGI, UP, Upazila & District level all officials, Institutional, Educational & Health , IT services etc.

13 85 15% 3 or not

acceptable

FGDs : what are the Service of GOB?

Bank, DAE, DOF, DWA, DOL, PWDB, BWDB, BRDB, BBS, LGI, UP, Upazila & District level all officials, Institutional, Educational & Health, IT services etc.

44 218 20% 3 or not

acceptable

Kls : what are the Service of NGO?

Credit, Institutional service, Educational Service, Information Technology, Health & sanitation etc. services

30 85 35% 3 or not

acceptable

FGDs : what are the Service of NGO?

Credit, Institutional service, Educational Service, Information Technology, Health & sanitation etc. services

98 218 45% 3 or not

acceptable

14. Present Marketing Situation Although the study team took opinion from KIs and FGD participants on present situation on marketing of various product of demand for production status problem is acceptable and highly acceptable. Agriculture product Value of Price is very differential of all market of the area.

Table – 14.1 : Marketing Status Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls No of

Kls / FGD commented

Total No of Kls or FGD members

% Ranking

Kls : Do you have any problem to sale your Product & where ?

Value of Price level difference between another market, Agricultural goods, Fishery production, Vegetable marketing, Paddy marketing, Handicrafts marketing, Jute product, Bamboo product, other Crop product marketing.

64 85 75% 4 or

acceptable

FGDs : Do you have any problem to sale your Product & where ?

Value of Price level difference between another market, Agricultural goods, Fishery production, Vegetable marketing, Paddy marketing, Handicrafts marketing, Jute product, Bamboo product, Crop product marketing & Others crop.

174 218 80% 5 or highly acceptable

15. Gender and Women’s Empowerment Although the study team took opinion from KIs and FGD participants for regarding usually the major family / HHs decision are taken from Men and Women both, but maximum people opinion that, major family decision taken from Men.

Table – 15.1 : Decision Making of your Family & any situation Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls Impact No of

Kls / FGD commented

Total No of Kls or FGD members

% Ranking

Kls : Who and usually the major

Regarding HHs income Decision taken from

51 85 60% 4 or

acceptable Regarding HHs Expenditure

Regarding buying HHs assets

Page 128: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

25

family decision are taken?

Regarding selling HHs assets Male & Female

Regarding children assets Regarding children marriage Regarding birth control Regarding Election / voting / other

FGDs : Who and usually the major family decision are taken?

Regarding HHs income

Decision taken from

Male & Female

110 218 50% 4 or

acceptable

Regarding HHs Expenditure

Regarding buying HHs assets Regarding selling HHs assets Regarding children assets Regarding children marriage Regarding birth control Regarding Election / voting / other

16. Present Migration Situation Although the study team took opinion from KIs and FGD participants of Out Migration status is very low (0.5%), Out of migration people at outside of country level various type of jobs. Because out of migration are Available job, Higher wages, big family, Debt ness, Social conflict and NGO loan of the major criteria in the area.

Table – 16.1 : Out Migration Status Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters

Comments of Kls No of

Kls / FGD commented

Total No of Kls or FGD members

% Ranking

Kls : What is your Out Migration Situation in area?

Out of migration People 5% in the area

43 85 50% 4 or

acceptable Available job, Higher wages, big family

Debt ness, Social conflict

FGDs : What is your Out Migration Situation in area?

Out of migration People 5% in the area

112 218 50% 4 or

acceptable Available job, Higher wages, big family

Debt ness, Social conflict

17. Future Scenario of the Project Although the study team took opinion from KIs and FGD participants Everymen are well-disposed that the proposed project will be helpful for improvement of livelihood of poor and poverty alleviation.

Table – 17.1 : Livelihood Enhancement to be created by Proposed Project Ranking : More than 80% = 5 highly acceptable, 50-80% = 4 or acceptable, below 50% = 3 not acceptable)

Discussion matters Comments of Kls or FGD

members

No of Kls / FGD

commented

Total No of Kls or FGD members

% Ranking

Kls: Do you agree that the proposed project will be helpful for improvement of livelihood of poor and poverty alleviation? (If yes then what?)

Yield of crop and fish will be increased and new employment will be generated.

72 85 85% 5 or highly acceptable

Income will be increased

Food supply will be increased

Food price will be increased

others

Page 129: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

26

FGDs: Do you agree that the proposed project will be helpful for improvement of livelihood of poor and poverty alleviation? (If yes then what?)

Yield of crop and fish will be increased and new employment will be generated.

196 218 90% 5 or highly acceptable Income will be increased

Food supply will be increased

Key Findings All FGD participants including the participants from potters and fishermen community and Kls suggested the implementation of proposed project to promote livelihood enhancement activities through increased income, more food supply at reduced price and more employment. All however shows similar conditions which are: People live in cluster (village) around the elevated side of beel using the beel for crop cultivation and fishing as major livelihood activities. A paved road on eastern side of beel and other connecting road leading to beel area provide facilities to bring the beel products to home and market. Which also support the crop and fish farming? Schools, religious centers / Mosque / Temple, local government offices, market provide ample social evidence that people are involved in managing the existing resource / land, water, river, canal etc for their livelihood. It justifies that crop and fish farming is two major and potential livelihood enhancement activities. The FGD report shows that the NGOs are directly providing most micro finance service to the people of SIP. The NGOs are Grameen Bank, BRAC, Proddipan, Banchte Shekha, Palli Dardro Foundation, Kalia Daridro Foundation, Gram Bangla, Sabuj Samity, Jagoroni Chakro Foundation and ASHA. Only a few participants are provided by Government institution (BRDB, Krishi Bank, Sonali Bank etc). For livelihood enhancement credit is needed. The FGD report provides important information that NGOs are the major sources of credit and their cooperation and assistance are required for livelihood enhancement of the poor. Finally project is exceptionally necessitated in the area.

18. Objective of the Gender & Livelihood Enhancement Perspectives (GLEP) Asses the existing gender and livelihood demand identify the local resources and recommended the possible interventions to be incorporated in the SIP # SWC – 18 (Noagram - Gajaria Scheme) of the Southwest Area integrated Water Resources Planning and Management Plan (SAIWRPMP).

For attaining the project objectives earmarked as the enhanced livelihood and livelihood opportunities impacted by integrated water resources management as result of increased user participation and improved decentralized service delivery.

In order to asses the present socio-economic condition, a Participatory Rapid Rural Appraisal (PRRA) was conducted. Based on the PRRA findings, following information was analyzed and possible means for livelihood enhancement strategy were identified.

From the analysis of options for livelihood enhancement and the study team’s observations and discussion with business and other relevant people a list of feasible livelihood activities is prepared which is as follows:

19. Feasible Livelihood enhancement Activities

Sl. No

Name of the livelihood

enhancement activities

Justification / Feasibility

Page 130: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

27

Sl. No

Name of the livelihood

enhancement activities

Justification / Feasibility

1. Homestead vegetable gardening, fruit tree at homestead and timber tree plantation by the roadside and embankment

Suitable for poor and marginal farmers and landless share croppers because they do not sufficient land accept homestead by at the same time interested to increase their income. The products have a guaranteed market in the area and the profit margins are high (estimated 60-70%).

2. Food processing specially rice based food processing (puffed rice, rice ball, till toffee, pressed rice etc.)

A profitable activity where women from landless poor households will be employed, their income will increase and their livelihood will be enhanced. The product has demand in local market.

3. Duck farming including mini hatchery

There is no problem of marketing duck and eggs. Profit margin is high / almost 70%. The area has good natural condition / river, canal, water body etc. for duck rearing

4. Poultry farming including mini hatchery

There is no problem of marketing Meat and eggs. Profit margin is high / almost 60%. The area has good natural condition / river, canal and green level ground area for poultry farm.

5. Cow Rearing farm There is no problem of marketing Meat and eggs. Profit margin is high / almost 50%. The area has good natural condition / river, canal and green level ground area for Cow Rearing farm.

6. Beef fattening farm There is no problem of marketing Meat and eggs. Profit margin is high / almost 50%. The area has good natural condition / river, canal and green level ground area for Beef fattening farm.

7. Home based bamboo work

This activity is getting popular in the area. Already some poor and marginal farmer families undertook this activity. Others are interested but capital and skill limits the promotion of this activity. There is already adequate market for bamboo products / basket / sieve / winnower etc. The profit margin is estimated to be 60-80% which is very reasonable.

8. Home based Jute work

The area is Jute growing area. It is available at low cost during season. Many useful items like rope, mat, bag etc. can be making with it at home using appropriate technology. The product has good market in local area and also at Narail & Jessore town.

9. Pottery There is some professional potters group. They need to support by the project. Potters product is used in rice storage and processing. The product has good market and the profit margin is 70-80%.

10. Tailoring & Handicrafts This activity is getting popular in the area. Already some poor and marginal farmer families undertook this activity. Others are interested but capital and skill limits the promotion of this activity. There is already adequate market for Handicrafts goods. The profit margin is estimated to be 50-60% which is very reasonable.

11. Packet / Box / Shopping Bag Making & Marketing

This activity is getting popular in the area. Already some poor and marginal farmer families undertook this activity. Others are interested but capital and skill limits the promotion of this activity. There is already adequate market for paper box / packet. The profit margin is estimated to be 60-80% which is very reasonable.

12. Social Forestry This activity is getting popular in the area. Already some poor and marginal farmer families undertook this activity. Others are interested but capital and skill limits the promotion of this future activity. The profit margin is estimated to be 50-60% which is very reasonable.

13. Marketing Development / Value Chain Development

This activity is not getting popular in the area. Already some group of poor and marginal farmer families undertook this activity, but this activity is unusual. Others group and WMG are interested but capital and skill limit

Page 131: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

28

Sl. No

Name of the livelihood

enhancement activities

Justification / Feasibility

the promotion of this activity. But it is practical; The profit margin is estimated to be 40-50% which is very sensible.

20. Strategies for Implementation of Livelihood Enhancement Program

The findings on important issues studied through Households Survey, PRRA / Focus Group Discussion under this project provide the basis and justification to formulate strategies for implementation of program for livelihood enhancement, these are follows:

20.1 Targeting the number of Poor Beneficiaries for Project Assistance

Under the section incidence of poverty the number of poor households has been estimated 39%. All of them may not be able to participate in livelihood enhancement program due to engagement in housework, field work, pregnancy, lactation of children etc. On the other hand resource is also a constraint to address all the poor. Therefore, one fifth of the poor which is approx. Gender are targeted for project intervention. Once their capacity building is completed they undertake income generating activities and the others will adopt these through social induced method. Budget allocation per WMO in DPP was also considered to make the target for livelihood enhancement activities.

Gender Dimension of Targeting: On the basis of the findings in section incidence of poverty and causes of poverty that, “women faces difficulties of poverty more than men, they have little opportunities to work outside against wage, they are the victims of trafficking and a few women who work outside their wages are less than men”, the target number need to be split out equally for both women and men.

20.2 Transparency to be maintained in selection process to have right kind of

Beneficiaries

Livelihood program implementation needs beneficiary selection ahead. An unplanned selection will lead to chaotic situation. Transparency is too maintained to have right kind and deserving beneficiaries. This can achieved if selection is made by a well established selection board following a set of well chosen criteria.

A selection board consisting of a representative of WMG, relevant UP member, and a representative sub project is being proposed here. This should be reviewed and finalized. Based on findings that skills, credit, orientation on improved technology and undertaken IGA are required for livelihood enhancement, the following criteria are being proposed here for discussion, review and finalization:

The beneficiary must be a member of a poor family whose monthly expenditure per family member is below Tk. 742 (upper poverty line).

He or she must be within working age preferably below 50 and above 18. He or she must be permanent resident of project area. He or she must below interest to join skill, business and marketing training for livelihood

enhancement. He or she should guarantee that after the training business / IGA will be undertaken by herself

or himself He or she must join as member in the local WMG.

20.3 Ensuring Appropriate Institutional Arrangement for Implementation of GLEP Livelihood enhancement program targeting the poor involve activities at the grass root level. Identifying the poor families, selecting the poor beneficiaries, aware and motivate them to acquire skills and undertaken IGA, organizing training and orientation for them, linking them with the market,

Page 132: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

29

arranging for them required financial capital etc. need local expertise and organizational and financial capacity. Government agency including BWDB may have technical expertise for implementing technical activities like design, construction, technology, demonstration etc. But they do not have capacity and expertise to handle the poor directly at the grassroots level as required for livelihood enhancement of poor people. Some XO of SMO, PMO Facilitators and NGOs are implementing similar livelihood activities at Narail & Jessore area. They have required capacities to handle the poor at the grass root level for livelihood enhancement. Livelihood enhancement program, specially identifying and selecting poor beneficiaries, creating awareness, financing, organizing and involve the poor in livelihood enhancement activities, locally are therefore proposed to be implemented by outsourcing through appropriate NGOs working in the relevant project area under the supervision of this project.

21. Gender Dimension of the Livelihood Enhancement Some of the gender issues are related to livelihood. These are the cases of divorce, violence against women, women headed households, marriage registration, birth registration and child marriage. The issues were discussed with women participants openly and some times privately on individual basis to maintain privacy. The marriage and birth registration have improved. More than 75% marriage and 80% birth were registered through Union Council. As reported by the women participants of FGD and women key informants, this contributed the decline of divorce and child marriage. Of course awareness raising by NGOs and Government program / radio / television etc. also contributed to the decline of it. Due to government incentive (food or cash incentive to poor children) primary school enrollment of girls is almost more than 80%. VGD and VGF program are currently implemented by the government. The program has contributed to enhance livelihood of poor households to very limited extent. Employing women in operation and maintenance of water structure; there is another gender dimension to enhance the livelihood of vulnerable women (FHH). Generally men are employed in operation and maintenance of the water structure and they get financial benefit. It is here suggested that along with men equal number of women must also be given opportunity for this activity.

In the construction of embankment and canal digging vulnerable women must be involved, minimum 50%, through LCS.

21.1 Recommendation After analyzing the HHs Survey data analysis, FGD study reports and other related documents comprehensive mitigation measures are suggested:

Gender and Livelihood Enhancement Awareness raising campaign among WMGs members/ community leaders / UP members / Line Agencies (DWA / DAE / DOF / DOF / concerned NGOs.

Legal Aid support for ensuring good governance, gender balanced family, women trafficking, polygamy and working environment.

Organize skills development training of the target group beneficiaries.

Facilitate linkage development activities with the resources organizations for the livelihood enhancement programs promotion/credit support/technologies of the target group beneficiaries.

Promote gender awareness programs to ensuring women’s rights and their entailment.

Ensure women involvement, especially vulnerable women in water management organization as executive committee member (as per GPWM-minimum one third) and general committee 50%.

Poor fishing community / landless member of the community will be involved in WMGs.

Vulnerable women will be form groups as LCs for canal digging, construction of embankment.

Disadvantage poor community / vulnerable women will get access in khash land / canal side tree plantation / nursery rising.

Fishing community/poor families will access for fish culture in borrow pit.

Page 133: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

30

Training on organizational management / leadership development / participatory planning/ resource mobilization and linkages / business development & marketing / banking transaction / poverty alleviation & management / women’s empowerment / LCS formation and poverty alleviation & management.

Gender awareness training for both male and female in target level;

Motivational and communicational skill development training for WMGs representatives

Monitoring, supervision and follow up training for WMGs representatives,

Mobilization of youth group to protect violence;

Ensure extension services to the WMGs / target beneficiaries for getting information / technology at regular basis (when require).

Legal Aid support for ensuring good governance and gender balanced family and working environment.

The GLEP will be in line with and complementary to the Gender Action Plan (GAP).

21.2 In brief GLEP will have the following special features

Increase involvement of the line agencies.

Capacity building of the beneficiaries on identified potential IGAs including business promotion and marketing linkages.

Awareness rising on gender issue legal rights, women violence etc.

Utilization of local resources & poverty & management.

Facilitation for linkage & communication skill.

Assistance for empowering women and poor people / fishing community.

22. Guideline for Selection of IGA a. WMG member with the support of NGO facilitators first identify the local level potential IGA

activities which are profitable and easily marketable in the local market. b. Market assessment involving the selected member needed for finalization of the IGA. c. The candidate member / group of members must apply to Managing Committee (MC) for having

support from the project / or other sources: other GO (DAE / DOFi / DOF (Social Forestry) / DOL / DOL (Land) / DOYD / BRDB /DWA / DSS etc) NGOs / Private sectors etc. and fill up a prescribed from prepared by WMG with the support of PMO / NGO facilitator.

22.1 Following are the possible steps for facilitating the organization of IGA for

the target Groups’ members :

a. After assessment by the committee (Representative from the Managing Committee / NGO facilitators / GFP, PMO / SMO) minimum 15 of thus selected poor members of the WMG (per village 50% members) will be selected where 50 percent at least will be vulnerable women for support by the project.

b. The identified participants will get skill training through local level organizations / NGOs / private sector first.

c. In some cases resource person in the training could be engaged from outside as per skill need for the identified IGA.

d. Participants could be sent to other concerned organizations / for be required skills e. Trained targeted poor WMG members who will be involved in the IGA, if needed, they will be

supported to link to the concerned financial institutes (Govt. banks / commercial banks / NGOs) for micro credit / SME loans [10% quota kept for women (Ref. Bangladesh Bank)]

f. Marketing linkages will be supported by the G&L PMO & NGO facilitators g. LCS will be organized by the poor beneficiaries (minimum 50% vulnerable women), supported by

WMG / PMO / SMO / ASG to carry out earthwork as “D” class contractor h. Targeted poor WMG members will be linked to the concerned authority of the Department of Land

(DOLA) /Deputy Commissioner to have Khash Land / Borrow pit (for the tree plantation beside the embankment and LGED paved & unpaved road/ nursery raising / fish culture etc) for involving poor / vulnerable women members of WMG.

Page 134: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

31

23. Gender & Livelihood enhancement Training Plan

The project generally progress of sustainable WMO formation and various training and others IGA programs in light of the Gender Action Plan implementation. PMO will maintain the project training to be provided following the principles of ‘’ Demand driven’’, ‘’ field based’’, and group oriented approach.

Detail Estimate Annex - 1

Page 135: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

32

Sl. N

o.

Topic of Training

Participants

Number of

Participants

(Female)

Tra

inin

g

All

ow

an

ce

/ D

ay

N

o.

of

Tra

ine

e

No

. o

f D

ay

Tra

inin

g

All

ow

an

ce

(To

tal)

(axbxc)

=

d

No

. o

f S

ess

ion

H

on

ora

riu

m

Ra

te/

Se

ss

ion

No

. o

f G

rou

ps

To

tal

Ho

no

rari

um

(exfx

g)

= h

Sn

ac

ks

&

La

un

ch

To

tal

Fo

od

(bxi)

= j

Mis

ce

lla

ne

ou

s

(k)

Gra

nd

To

tal

L =

(d

+h+

j+k)

a b c d e f g h i j k l (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.)

1.

Homestead vegetable gardening, fruit tree at homestead and timber tree plantation by the roadside and embankment

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

2.

Rice based food processing / puffed rice, rice ball, rice cake etc

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

3.

Duck / Koile bird farming along with mini hatchery

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

4.

Home based bamboo work / storage and processing basket, and marketing

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

5. Home based jute works

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

6.

Pottery / improved design for rice storage and processing pot etc

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

7.

Gender Awareness / Capacity Building

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

8. Tailoring / Handicrafts / Embroidery

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

9. Packet / Box / Shopping Bag

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

10. Cow Rearing / Beef fattening

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

11. Mashrum Cultivation & Marketing

WMG Member

60 (30) 350 60 2 42000 8 600 3 14400 200 12000 10000 78400

12. Motivational Tour

WMG Member

200 (100)

350 200 2 140000 8 600 3 14400 200 40000 30000 254400

Training costing for 2 WMG 1116800

Tentative 10 WMG for SWC – 18, (5 x 1116800) 5584000

Total cost for Gender & Livelihood Enhancement Plan; SWC – 18 ; 5584000

Program implementation cost (Follow-up on post training activities, linkage with resources, marketing promotional activities, demonstration / piloting in sample basis (initial capital for destitute women only) etc.

Page 136: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

33

24. Monitoring & Evaluation Monitoring and evaluation will be carried out side by side: GFP / PMO / SMO / ASG / project personnel / MC of WMG & WMA will form a monitoring committee and will provide a quarterly report to the PMO / Project authority, copy to Gender and Poverty Component (GPC). The ADB Mission recalled the MTR agreement to retain RAs as experts to provide training to the concerned WMGs as well as monitoring and evaluation after SIP preparation. ISPMCs will explore the possibility of engaging an NGO or group of experts to provide facilitation, training and advisory support to value chain development. PMO will maintain the project training to be provided following the principles of ‘’ Demand driven’’, ‘’ field based’’, and group oriented approach.

25. Goals / G&L Enhanced Policy of SAIWRPMP The major goals of are as follows:

To establish participation of water resources operation and maintenance for women capacity

building.

To minimum 70% poor / non poor women are always contribution of any water related program.

To minimum 50% poor / non poor women are targeted of any other IGA participation.

To minimum 50% poor / non poor women are targeted of various IGA / Skill / WMG / leader ship empowering / capacity building / Agri based / Fish farm / O&M of water structures training.

To minimum 50% poor / non poor women are always contribution of WMG program.

To establish equality between men and women in all spheres of livelihood.

To ensure women’s security in all sphere of state, society and family.

To ensure empowerment of women in the fields of politics, administration and the economy.

To financial / credit facility as per WMG activity for IGA.

To the 100% poverty / impoverished reduced for women participation require is always of any water resource program.

To establish Women’s human rights.

To develop women as educated and efficient human resources.

To free women from the curse of poverty.

To eliminate existing discrimination against men and women.

To acknowledge women’s contribution in social and economic sphere.

To eradicate all forms of oppression on women and girls.

To establish equality between men and women in administration, politics, education, culture, sports and all other economic activities.

To devise and import technology congenial to the interest of women and ban use of technology harmful to women.

To take adequate measures to ensure women’s health and nutrition.

To ensure priority of women in the arrangement of hoisting and providing suitable shelter for women.

To meet the needs of women especially in difficult circumstances.

To ensure security for widows, divorced, unmarried and childless women.

To reflect gender perspective in mass-media by projection positive image of women.

To provide assistance on flourishing creativity of meritorious and talented women.

To provide support services in the advancement of women.

26. Conclusion

Many thanks for the cooperation of the PMO & SMO official’s staff of the BWDB, ISPM Consultants of BWDB such as Research Assistant, Senior Facilitator, Community Facilitator, XO of SMO, NGO Facilitator, and Project Beneficiaries local members in collecting data, checking the filled-in questionnaires, data entry, data cleaning, and editing the entered data in the computer database. Without their help it would have not been possible to complete the Baseline House holds survey Report.

Page 137: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB. Annex - D

SWC-17+18; Noagram-Gazaria

34

We also convey our thanks to all our colleagues of Socio-economy Division and Research Cell of Gender & Livelihood, BWDB for their tireless efforts at all stages of conducting the survey and to all who contributed in producing and improving the report. Whatever is found useful in this report is all due to these inputs from various colleagues. However, the production of this report itself has been a valuable experience for the Report Writing Team. This report is a one-hundred percent BWDB product and that is very much in line with the objectives of Gender & Livelihood enhancement plan of SAIWRPMP: women empowering, capacity building and poverty reduced integrated institutional strengthening competence upsurge.

One of the important issues of the project objective is to enhanced livelihood through created IGA opportunities in collaboration with Government and Non-Government organizations. The feature of the gender & livelihood of SIP # SWC – 18 (Noagram-Gajaria Scheme) already mentioned in this report which are come across by the study. May wish the project will take initiative for better livelihood situation to alleviate of poverty reduction.

Finally, we are thankful to the All.

Page 138: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

ANNEX – E

WATER MANAGEMENT ORGANIZATIONS

Page 139: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 1

WMO Plan for SIP # SWC- 17+18 Chenchuri Beel Sub- Project

Summary FCD/I Projects may either enhance the community integration or it may make the people

quarrel. This became ironically true for most of FCD/I projects of the erstwhile WAPDA installed

in the early sixties. Planners during the time nursed the theory that as soon as water is made

available to farmers, farmers will utilize irrigation water and food production will be doubled. But

in reality, farmers felt reluctant to use irrigation water in different parts of the country. Although

irrigation canals were completed in record period with an excellent level of engineering skills, an

integrated approach with farmers participation was totally missing. So in many areas farmers

strongly oppose the FCD/ I systems.

Participatory management has received a lot of attention in recent years as a result of

commercialization and privatization of Government agencies in many parts of the world. It is

recognized that participation of the farmers plays an important role in increasing agriculture

production and performance improvement of FCD/I systems. One of the ways of

institutionalizing participatory Water Management in public sector FCD/I system is to establish a

formal mechanism for interaction between beneficiaries and agency personnel. From the survey

it reveals that 8 local NGOs are working in the SIP area. About 90% of them are involved in

credit & the rests are working with health, education etc. But none is involved is water

management sectors. For SIP # 18 proposed 10 WMG and one WMA will enable beneficiaries

to discuss, negotiate and participate in decision making with the agency on various issues of

water managements.

Introduction

The Southwest Area Integrated Water Resources Planning & Management Project

(SAIWRPMP), with the assistance of Asho Samaj Gori (ASG) an NGO contracted by the

project, will utilize a clear, step-by- step and participatory process in the formation,

strengthening and mobilization of WMOs. ASG through its cadre of facilitators will be primarily

responsible for developing the capacity of WMOs to manage their water-related resources on

their own.

This process of WMO Development is guided by the provisions of the Guidelines for

Participatory Water Management (GPWM) and will be adopted in the formation of WMOs in the

Narail and Chenchuri Beel sub-projects then reviewed, adjusted and fine tuned based on the

actual field experiences from these 2 sub-projects to make it more responsive to the needs and

requirements of the other sub-projects under SAIWRPMP. As proposed in the inception report,

the process of WMO development has 6 phases as illustrated below:

Page 140: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 2

Phases Involved in WMO Development

Phase Description of Each Phase Time frame

1 Rapport and knowledge building phase Months 1 & 2

2 Problem analysis and service identification phase Months 3 – 9

3 Organization building phase Months 3 – 9

4 Capacity building phase Months 10 -12

5 SIP Implementation 1 Year

6 Management transfer phase After completion of rehabilitation works

Location SIP # 17+18 of Chenchuri Beel sub-project is located in 2 Unions (Purulia and Peruli) of Kalia Upazila under Narail District. 13 villages from these two Unions are associated (fully or partly) within this SIP # 17+18 (Table-1 , 2 & Fig-1). SIP # 17+18 is popularly known as Liner khal (canal) area and bounded by the river Chitra to the west and Nabaganga to the south & east and ridges of other SIPs northwards & westwards.

Page 141: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 3

Table – 1: Villages of SIP # SWC-17+18 on GPS Study

Sl. No. Name of Village GPS Remarks

1 Diadanga N-2300121.9

E-8903535.6 Small Village

2 Noagram N-2300150.8

E-8903539.3 Big Village

3 Bajababra N-2300241.0

E-8903554.7 Small Village

4 Kalamonkhali N-2300258.5

E-8903543.3 Small Village

5 Amtola N-2300302.0

E-8903520.1 Small Village

6 Fuldhaho N-2300321.0

E-8903447.1 Small Village

7 Dariaghata N-2300337.8

E-8903439.5 Small Village

8 Burikhili N-2205941.7

E-8903350.1 Small Village

9 Per-Vhombag N-2300011.8

E-8903419.3 Small Village

10 Perbeshnopur N-2300046.4

E-8903439.1 Medium Village

11 Pateswari N-2300108.8

E-8903347.0 Medium Village

12 Satbaria N-2300037.3

E-8903358.7 Medium Village

13 Perulistan N-2205945.9

E-8903329.9 Medium Village

Page 142: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 4

Table- 2: Planned Formulation and Activities for Organizing WMOs in SIP # SWC – 17+18

Sl No

Name of WMG

(with cl. villages)

Date of WMG

Formation

Regd No/ Date

Area (Ha)

Planned Members (1 from each HHs)

Potential # of Members

(70%)

Members enrolled

Date of monthly meeting

Date of Members enrollment

meeting

Date of Executive committee meeting

Capital formation general meeting

Capital formation (Tk)

Bank A/c Responsi

bility

Last month Total

(Female)

This month

This month Total

(Female) Last month

This month

Total

1

Chameli WMG S-18/1 Dariaghata Fuldah

-- -- 188 384 270 -- -- -- -- -- -- -- -- -- -- -- Afroza

2 Beli WMG S-18/2 Amtola 5.5.10

8/Klaia 24.2.11

158 282 197 144 (42)

-- 144 (42)

25 of Every month

-- 6/611 8/6/11 43580 1000 44580 SB/

6313 Afroza

3

Keya WMG S-18/3 Kalamonkhali Bajebabra

3.5.10 4/Kakia/ 24.01.11

174 368 258 175 (62)

-- 175 (62)

28 of Every month

-- 10/6/11 10/6/1

1 45590 2960 48550

SB/ 6312

Afroza

4 Nabaganga WMG S-18/4 Noagram 18.5.10

3/Kakia/ 24.01.11

195 538 377 205 (64)

7 (4)

212 (68)

30 of Every month

-- 11/6/11 11/6/1

1 50420 1980 52400

SB/ 6323

Suvankar

5 Ekata WMG S-18/5 Diadanga

1.5.10 7/ kalia/ 1.02.11

64 238 167 134 (31)

-- 134 (31)

23 of Every month

17/6/11 -- 17/6/1

1 35320 1500 36820

SB/ 6303

Shyamol

6 Suravi WMG S-18/5A Perbishnupur

14.5.10 12/Kalia 3/3/11

107 550 385 422 (71)

-- 422 (71)

25 of Every month

-- 8/6/11 8/6/11 47700 -- 47700 SB/

6318 Mamun

7 Hasnahena WMG S-18/6 Burikhali 22.5.10

14/Kalia 28/3/11

100 149 104 114 (33

-- 114 (33)

28 of Every month

-- 9/6/11 9/6/11 30000 -- 30000 SB/ Pe 5318

Mamun

8 Rajanigandha WMG S-18/6A Pervumbag

27.5.10 -- 83 127 89 52 (7)

-- 52 (7)

17 of Every month

-- -- -- -- -- -- -- Shaymol

9 Kanakchapa WMG S-18/7 perulistan

23.5.10 1/Kalia 10.1.11

155 185 130 147 (45)

-- 147 (45)

29 of Every month

-- 10/6/11 10/6/1

1 36370 510 36880

SB/ 5274

Tukarem

10

Gandharaj WMG S-18/8 Satbaria Pateswari

1.5.10 2/Kalia 10.1.11

247 358 251 257 (105)

2 (2)

259 (107)

30 of Every month

-- 9/6/11 9/6/11 67260 -- 67260 SB/

5252

Tukarem

10 9 8 1471 3179 2228 1650 (442)

3 (0)

1659 (442)

356240

7950 36419

0

Page 143: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 5

Fig- 1

Page 144: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 6

Levels of Water Management Organization in the SIP # 17+18 1. Water Management Group (WMG) The Southwest project intends to establish Water Management Organizations (WMOs) that will in future be able to take care of O&M of the water infrastructure in their area. The areas are defined on hydrological basis, called subunits of the subproject area. Further subdivision is based on “sub-schemes” basis within the sub-units, that are defined as the command area (CA) of the main regulator discharging to the river. The GPWM distinguishes three tiers of WMO for projects of 5000 hectares or more:

Water Management Group (WMG) at the lowest level for each smallest hydrological unit or Social Unit (Para or Village).

Water Management Association (WMA) at the mid level for each project or system.

Water Management Federation (WMF) at the apex level of the project/scheme.

Principles followed to form WMG and to identify potential WMG members within DBA: In SWAIWRPMP, following this 3- tires model the principle followed is that a hydrologically delineated DBA based WMG shall be formed within each SIP area. SIP # 18 covers 4 regulators (1 is proposed), 6 WM structures, 13 Villages in 2 Unions. 13 Villages are clustered into 10 groups for organizing 10 WMGs. In clustering the villages following factors are considered:

a) Future O & M of water infrastructure in their area b) Social complexity c) Maintaining minimum distance to facilitate WMG members to attend meeting place. d) Maintaining (as per as possible) administrative boundaries (Village or Union

boundaries) for each WMG. e) Common and acceptable nomenclatures of each WMG. f) Overall, technically feasible & socially acceptable Section of the water infrastructure

are the basis of WMG formation. Nomenclatures of each WMG is proposed on popular artistic names of Flowers in consultation with stakeholders (Table- 2).To identify potential WMG members mouza maps are used. Mouza maps of the Directorate of Lands are overlaid in DBA map developed by the SW project to identify the related villages (fully or partly). The villages are then screened to identify plot numbers. Superimposed DBA thus obtained are then further verified through ‘Google Earth’. Next task is to identify the names of plot owners. Normally Upazila Sub- Register’s office (Land Registry office) is the source where names of actual land owners are available. This ownership record are in huge quantity which contains both minor and adults. But for WMG formation only adult land owners (above 18 years) of small area is needed. To prepare a reliable & actual land ownership list for each WMG, one or two senior resource persons were picked- up as volunteers from the local Community to supply the names of plot owners in one sitting organized in any meeting place near the DBA. This list is more accurate & accepted by the stakeholders. The WMG is the grass root and core WM organization for O & M of which all (>70%) of the people of the DBA in the community (farmers, fishermen, aqua-culturists, small traders, boatmen, craftsmen, landless people, destitute women, PAPs etc) shall become member

Page 145: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 7

The process of organizing the local stakeholders into WMOs is implemented by an NGO (ASG) under guidance of the ISPM-consultants and supervised by the Project Director (PMO). General members of the WMG will elect representatives for WMG and WMA. They will hold two elections; 1st Election for the Executive Committee of the WMG consisting 12, (at least 30% women) that will decide on how to spend the budget for O&M which needs approval from the general members. The second election is to elect 5 representatives (male1, female-1, landless-1, fisherman-1, destitute woman-1) of the WMG to the WMA as in Annex-1. A member of WMG Executive Committee can not be a general member of the WMA, meaning they will not be allowed to compete for two posts simultaneously in two tiers (one in the WMG Executive Committee and the other in the WMA neither member or EC). This is different from the public administration and the Co-operative Societies where dual posts can be held. 2. Water Management Association (WMA): One (1) WMA will be formed to manage the water management activities in SIP # 18. Representatives of General Members of each WMG will become General Members of WMA who in turn will form WMA Executive Committee consisting 12 members through election.

Key Activities involved in developing WMO in SIP # 18 The following summarizes the key steps those are being undertaken by the ASG NGO facilitators in the process of organizing the Water Management Association in SIP # 18. 1. Prepare list of beneficiaries: The NGO Asho Samaj Gori (ASG) has been contracted for social mobilization works during September, 2008. They have fielded 14 Facilitators and 1 NGO Supervisor. Facilitators are now in the stage of WMO formation with their entry in the local community. The aim is to establish rapport with the Community by conducting house to house visits to meet potential beneficiaries’ families and participating in the Community activities. Before fielding, the Facilitators were imparted 2-days training (1 day class room and 1 day field test) on the preparation of beneficiaries list. Their performances were tested before they are actually fielded on the 10th of September’ 2008. The ASG completed their initial report for WMO formation during November 2008. After fine tuning of the DBA, number of villages have been increased. Further beneficiaries survey was made during 1-5 March 2009 through the NGO Facilitators, 2. Organizing the WMO: At the initial stage of WMO formation, series of discussion meetings were held and is continuing with local stakeholders, UP Chairman, LGI members before and after Union Level Orientation workshop (12.06.08) at Purulia Union Parishad. After synthessing the stakeholders recommendations, SIP was cleared in the DLIAPEC meeting on 18.02.09. SMO Narail confirms the implementability of works. Process for formation of WMO is in progress. 3. Formation of Water Management Group (WMG) and Water Management Association (WMA):

Page 146: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 8

3 water management groups (WMG) and 1 Water Management Association will be formed in SIP # 17+18. (Table-2 and Annex-1). 4. Registration of the WMO with the Department of Cooperatives: The WMG, through its elected executive committee, registers with the DoC after completing all the required documentations and complying with all the requirements for registration. WMA the mid tier will supervise & monitor WMG and will participate O & M activities under management agreements. Afterwards attempts will be made for registering WMA. 5. WMO Proceeds with its O & M Activities: The WMO makes plan/program of activities so that it is able to actively participate in the

discussion, finalization and implementation of the SIP and in undertaking its O & M activities.

(The process of WMO formation is illustrated in the flowchart (Annex-2) 6. Training program for WMO members in SIP # 18 Training of WMG/WMA Executive Committee members on organizational management. This training intervention is designed to enhance the existing basic leadership skills of WMA leaders. It is geared towards the provision of adequate knowledge and leadership skills to enable the WMA leaders to improve their performance as they carry out their O & M tasks. This training provides learning opportunities to WMA leaders for more effective and efficient job performance. The curriculum includes a discussion of the WMA’s operations and its composition, the roles and functions of the WMA leaders, sessions which explore the WMA leaders’ skills in communication and problem solving as well as management of WMA records. This training also introduces the WMG/WMA leaders to the concept of saving and the operation and maintenance of water management infrastructures. This organizational management training (Training Plan) will be given to each WMG and WMA executive committee members. Each training will last for 3 days and will be facilitated by the NGO facilitator assigned in SIP # 18. Bar chart of WMO development activities in SIP # 18 (Annex-3) 7. Monitoring Indicators for WMO development in SIP # 18 The progress of the WMO development activities in SIP # 18 needs to be regularly monitored and evaluated to assess the viability status of the WMO during the various phases of WMO development. This will determine the key areas where the WMO needs to be strengthened and to guide the NGO facilitators in redirecting organizing efforts geared towards developing the capability of the WMO to manage its water resources efficiently and effectively. The monitoring indicators listed below focus on the capacity of the various committees to carry out committee work effectively; the organizational and leadership skills of the WMO officers and leaders; and, the functionality of the WMO as a whole. Evaluation of the WMO in SIP # 18 based on the monitoring indicators below will be conducted jointly by the Executive Engineer/Narail SMO, JMC subcommittee and representatives from the SIP # 18 WMOs. Organizational Phase

1) Leaders/officers demonstrate organizational leadership skills in: a) preparing and organizing meetings properly b) presiding meetings in an orderly manner c) keeping records of minutes of meetings

Page 147: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 9

d) maintaining financial books and other financial reports

2) Leaders/officers demonstrate good problem solving capability in: a) identifying and analyzing the problems affecting them; b) setting priorities, general objectives and plan action strategies, c) implementing action/strategies and monitoring and evaluating outcome of

implementation.

3) Committee level. The ad hoc committees carry out committee work effectively when:

a) members participate actively in committee activities and meetings; b) the committee regularly conducts meetings to assess accomplishments vs.

targets; c) the committee regularly reports to the officers and members; d) planned activities are implemented at a given time;

4) WMO level. The WMO is able to assess existing organizational structure to suit

the changing needs. The members also actively participate in the affairs of the WMO.

a) The WMO is legally registered; b) 70% of the potential beneficiaries( 30% women) are registered members of the

WMO; c) The necessary positions to be created determined by the leaders and members.

Functions of the positions to be created are well defined by the officers and members; d) Qualifications criteria for the positions to be created are set by the officers and

members; e) Mechanics for filling up the position set up by the officers and members; f) The proposed organizational set up discussed with the members before

finalization; g) Members regularly attend WMO meetings; h) Members actively participate by voicing out their ideas, opinions, suggestions and

concerns regarding conflicts, problems, issues, activities , accomplishments and plans of the WMO;

i) The members carry out their duties and responsibilities expected of them by the WMO e.g. involvement in committee work, payment of dues, etc.

Operation and Maintenance Phase

5) Leaders/officers demonstrate organizational leadership skills in: a) preparing and organizing meetings properly b) presiding meetings in an orderly manner c) keeping records of minutes of meetings d) maintaining financial books and other financial reports 6) Leaders/officers demonstrate good problem solving capability in: a) identifying and analyzing the problems affecting them; b) setting priorities, general objectives and plan action strategies, c) implementing action/strategies and monitoring and evaluating outcome of

implementation.

7) Committee level. The committees carry out committee work effectively when: a) members participate actively in committee activities and meetings; b) the committee regularly conducts meetings to assess accomplishments vs.

targets;

Page 148: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 10

c) the committee regularly reports to the officers and members; d) planned activities are implemented at a given time; 8) WMO level: a) regular executive committee meetings held to assess status of operation and

maintenance b) in the WMO and issues and problems encountered in the implementation of O &

M policies; c) executive committee members attend committee meetings d) regular general assembly meetings are held to assess status of WMO operation

and maintenance and issues/problems encountered in the implementation of O & M policies e) members attend general assembly meetings; f) regular maintenance work is undertaken; g) members actively participate in regular maintenance work; h) fees and dues required are collected; i) A financial report is regularly presented to the general assembly; j) Issues/ conflicts are resolved by the WMO in a timely fashion; k) WMO is up-to-date in keeping its records and documents e.g. financial records, membership books, minutes of meetings, etc.; l) standing committee members actively participate in the committee activities; m) executive committee members of the WMO actively perform their duties and responsibilities; n) O & M personnel actively perform their duties and responsibilities.

Page 149: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 11

Annex-1

Page 150: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 12

Annex-2

WMO FORMATION AT A GLANCE

SMO confirms Implementability of SIP

Approval of Internal Rules & Regulations by the General

Members of WMG

Elected representatives of WMG form WMA E.C

Registration of WMO with DoC

SIP clearance by Union

SIP Approved in DLIAPEC

Prepare list of Beneficiary from DB Areas

Stakeholders form WMO Foundation Committee

Drafting Internal Rules & Regulations of the WMG

Hold 2 Elections: WMG E.C. & WMA Representatives

WMA

General Members of the WMG

WMO proceeds with its O&M activities

Page 151: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 13

WMO Development Main Activities in SIP # SWC – 17+18

Annex-3

Sl. No

Activities 2009 - 2010 2010 - 2011 2011 - 2012 2012 - 2013

1. SIP clearance by Union

2. SIP approved in DLIAPEC

3. SMO Confirms implement ability of SIP

4. Prepare list of beneficiaries

5. Formation of WMO Foundation Committee

6. WMO Foundation Committee submit project request to SMO

7. Formation of WMG

Creation of Committee to develop draft internal Rules

Drafting bye – laws

Election of Executive Committee

8. Formation of WMA

Creation of Committee to develop draft internal Rules

Drafting bye – laws

Election of Executive Committee

9. Registration by DoC

10. Training on Organizational Management

WMG Executive Committee

WMA Executive Committee

Capacity Development

11. SIP IA Signing by WMA & BWDB

12. Regular Organizational Strengthening

13. Awareness building and Motivational Campaign

14. WMG members registration

15. Collection of Savings, Shares, Admission fees etc.

16. Monitoring

17. WMA Proceeds O & M

Page 152: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 14

SIP wise WMO Training Plan Annex - 4

Detailed Costing of Training 1st Phase

Sl.

No.

Topic of Training

Participants

Number of

Participants

(Female) Tra

inin

g

All

ow

an

ce/

Day

(A)

No

. o

f T

rain

ee

(B)

No

. o

f D

ay

(C)

Tra

inin

g

All

ow

an

ce (

To

tal)

(AX

BX

C)

= D

N

o.

of

Ses

sio

n

(E)

Ho

no

rari

um

Ra

te/

Ses

sio

n

(F)

No

. o

f G

rou

ps

(G)

To

tal

Ho

no

rari

um

(EX

FX

G)

= H

Tra

nsp

ort

Su

pp

ort

(I)

To

tal

Tra

nsp

ort

(BX

I) =

J

V

enu

e C

ha

rge

(K)

Gra

nd

To

tal

= (

D+

H+

J+

K)

(Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.)

1. Concepts of IWM

& objects of WMO

WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 1500 41100

2. GPWM & Formation

of WMG / Tasks &

Responsibility

WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 1500 41100

3. Preparation List of

Beneficiaries WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 1500 41100

4. Procedures of WMG

By-law drafting WMG

Members

30 (10) 200 30 2 12000 8 400 1 3200 100 3000 1500 19700

5. Election Procedures

of WMO WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 1500 41100

6. Registration

Procedures of WMO WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 1500 41100

7. Book Keeping

WMG

Members

30 (10) 200 30 2 12000 8 400 1 3200 100 3000 1500 19700

8. Meetings &

Maintaining meeting

proceedings

WMG

Members

30 (10) 200 30 2 12000 8 400 1 3200 100 3000 1500 19700

9. Motivational Tour

WMG

Members

50 (15) 5 Members from each WMG X 10 WMG = 50 LS 50000

FY 2009- 10

Total

314600

Page 153: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 15

SIP wise WMO Training Plan

Detailed Costing of Training 2nd Phase

Sl.

No.

Topic of Training

Participants

Number of

Participants

(Female)

Tra

inin

g

All

ow

an

ce/

Day

(A)

No

. o

f T

rain

ee

(B)

No

. o

f D

ay

(C)

Tra

inin

g

All

ow

an

ce

(To

tal)

(AX

BX

C)

= D

No

. o

f S

essi

on

(E)

Ho

no

rari

um

Ra

te/

Ses

sio

n

(F)

No

. o

f G

rou

ps

(G)

To

tal

Ho

no

rari

um

(EX

FX

G)

= H

Tra

nsp

ort

Su

pp

ort

(I)

To

tal

Tra

nsp

ort

(BX

I) =

J

V

enu

e C

ha

rge

(K)

Gra

nd

To

tal

= (

D+

H+

J+

K)

(Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.)

1. Formation of

WMA & Task

&

Responsibilities

WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 150

0 41100

2. WMA By-law

drafting WMG

Members

30 (10) 200 30 2 12000 8 400 1 3200 100 3000 150

0 19700

3. Management

transfer

WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 150

0 41100

4. Conflict

Management

WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 150

0 41100

5. Formation JMC

its composition

tasks &

responsibilities

WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 150

0 41100

6. Operation &

Maintenance

WMG

Members

60 (20) 200 60 2 24000 8 400 3 9600 100 6000 150

0 41100

7. Motivational

Tour WMG

Members

50 (15) 5 Members from each WMG X 10 WMG = 50 LS 50000

FY 2010- 11

Total

275200

Page 154: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 16

SIP wise WMO Training Plan

Detailed Costing of Training 3rd Phase

Sl.

No.

Topic of Training

Participants

Number of

Participants

(Female) Tra

inin

g

All

ow

an

ce/

Day

(A)

No

. o

f T

rain

ee

(B)

No

. o

f D

ay

(C)

Tra

inin

g

All

ow

an

ce (

To

tal)

(AX

BX

C)

= D

N

o.

of

Ses

sio

n

(E)

Ho

no

rari

um

Ra

te/

Ses

sio

n

(F)

No

. o

f G

rou

ps

(G)

To

tal

Ho

no

rari

um

(EX

FX

G)

= H

Tra

nsp

ort

Su

pp

ort

(I)

To

tal

Tra

nsp

ort

(BX

I) =

J

V

enu

e C

ha

rge

(K)

Gra

nd

To

tal

= (

D+

H+

J+

K)

(Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.) (Tk.)

1. O & M

WMG Members 60 (20) 200 60 2 24000 8 400 3 9600 100 6000 1500 41100

2. Capacity Building

WMG Members 60 (20) 200 60 2 24000 8 400 3 9600 100 6000 1500 41100

3. Monitoring &

Evaluation

WMG Members 60 (20) 200 60 2 24000 8 400 3 9600 100 6000 1500 41100

4. Audit &

Inspection

WMG Members 30 (10) 200 30 2 12000 8 400 1 3200 100 3000 1500 19700

5. Motivational

Tour

WMG Members

50 (15) 5 Members from each WMG X 10 WMG = 50 LS 50000

FY 2011- 12

Total

193000

Page 155: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-E

SWC-17+18; Noagram-Gazaria 17

Page 156: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

ANNEX – F

O & M PLAN

Page 157: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 1

Noagram-Gajaria Scheme (SWC-17 + 18)

O & M Plan

1. Introduction

The Chenchuri Beel is a Sub-Project under South West Area Integrated Water Resources

Management Project (SWAIWRMP).This sub project area is bounded by the Chitra river in the east

and Naboganga river in the southeast & north.The rivers are tidally influenced. On the basis of the

Hydrological boundary the sub project was divided into 18 SWCs units during the feasibility study

(PPTA). After detail hydrological studies the SIP boundary of SWC 17-18 has been finalized as one

unit after combining both 17 & 18. The total gross area under SIP 17-18 is about 1471 ha of which

1030 ha is benefitted area..The SIP area is located in two unions namely Perulia and Purulia under

Kalia Upazila of Narail District. There are 13 ( seaven) villages partly or fully within the SIP area. The

area has been sub-divided into sub-catchments considering formation of WMOs. There are as many

as 10 ( ten) number of WMGs formed within the SIP The topography of the SIP area varies from 3.50

m PWD in the north to 1,5 m PWD at the south .The rivers are tidally influenced.

2. Methodology :

The SIP area has been delineated and the WMG have also been formed. At the very outset

discussion meetings were held for awareness development about the concept & activities of the

project with the Chairman,Ward Members & the beneficiaries of the area. In view of the suggestions

made in the awareness building meetings walkthrough were held for physical verification of the need

placed by the participants in all the tentative WMG areas. After taking into account of the beneficiaries

demand the total no of infrastructure within the SIP SWC 17-18 are as follows:

i) Pateswari Regulator: 10-Vents (1.82m x 1.52m )

ii) Takimara Regulator: 2-Vents (1.82m x 1.52m )

iii) Takimara Regulator ( proposed) : 1-Vent (1.82m x 1.52m )

iv) Satbaria Regulator (proposed) : 1-Vent (1.82m x 1.52m )

v) Noagram Regulator : 1-Vent (1.82m x 1.52m )

vi) Diadanga Bishnapur Regulator : 1-Vent (1.82m x 1.52m )

vii) Dakhin Burikhali Regulator : 1-Vent (1.82m x 1.52m )

viii) Bridge/Culverts (proposed) : 2 nos

ix) WMG Office Building (Proposed) : 2 nos

x) Tube Well (Proposed) : 10 nos

xi) Re-excavation of Liner Khal: 8/2 = 4.00 km

xii) Re-excavation of Chachuri Khal : 3.25 km.

xiii) Re-excavation of Maridanga Khal : 2.00 km

xiv) Re-excavation of Noagram Khal :1.6 km

xv) Re-excavation of Suorer Khal: 1.80 km

xvi) Re-excavation of Majhalir Khal: 3.40 km

xvii) Re-excavation of Mora Khal: 2.80 km

xviii) Re-excavation of Amtola Khal: 1.25 km

xix) Re-excavation of Kumarer Khal: 1.80 km

xx) Re-excavation of Takimara Khal: 1.50 km

xxi) Re-excavation of Satbaria/Gajaria Khal: 1.50 km

xxii) Re-excavation of Diadanga-Bishnapur Khal: 1.75 km

xxiii) Embankment from Urushi to Pateswari: 12.00 km.

Page 158: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 2

3. Data Collection:

A draft O & M Plan for this SIP SWC 17-18 has been prepared on the basis of data received from the

research assistants. There were senior facilitators, community facilitators in the field to collect data for

this SIP and these data were sent to the research assistants working under the PMO. After analyzing

by the research assistants the data were submitted to the O & M specialist for this Project. The O & M

specialist after getting the infrastructure data of the SIP have examined and incorporated in the O & M

Plan for the SIP. During discussion with the beneficiaries it was found that the beneficiaries have

suggested for all types of earthwork within the SIP are to be executed through the WMG members.

The beneficiaries also opined that they are ready to share the O & M cost for the SIP.

4. Annual Maintenance Cost:

Summary of Annual Maintenance Cost of Infrastructure under CSP 17-18 (Sub-Unit Action Plan) is

given in Table: 1.

Table: 1 (Tk. in Lac)

Item of Works Type of Maintenance Cost Total Cost

Reference

Preventive Periodic

Drainage

Channel/Khal

0.133 4.105 4.138 Table :4

Structures 0.431 4.924 5.355 Table :5

Embankment 1.680 6.144 7.824 Table :6

Total 2.244 15.173 17.417

5. Cost Sharing between WMG & BWDB

The total O & M cost for this SIP,SWC 17-18 comes to Tk 17,41,700.00 per year. For sustainable

operation & maintenance of the scheme, all peripheral infrastructure & the khals connecting to the

peripheral structures and infrastructure within the SIP having command area more than 1000 ha are

considered as public goods. The periodic maintenance of the public goods will be borne by BWDB

under the JMC. The preventive maintenance of the public goods plus the preventive & periodic

maintenance of other infrastructure within the SIP are to be borne by WMGs. It is to be noted here

that the structures ( serial i to serial v) in the infrastructure list under methodology Section 2 serves

SIP SWC 16, (17-18) & (4+6+8+9+14 ) for which the maintenance cost of these structures ( sl i to sl v

) are distributed on the basis of their respective benefitted areas.The share for this SIP comes to

11%.. Here for this SIP, the shared structures and Diadanga Bishnapur, Daskhin Burikhali regulators

2 nos Bridge/Culverts, 1no Inlet/Outlet, Liner , Noagram , Takimara, Satbaria/Gajaria khals and 12.00

km of embankment are considered as public goods. The operation & maintenance cost sharing for

SWC 16 is given below in Table2

Page 159: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 3

a) Khals/Canals Table : 2/1

Sl.No Name of Khal Length (Km) Cost Sharing

1 Liner Khal ( 1/2 of 8 km) 4 Pre:WMA Per; WDB

2 Chenchuri Khal 3.25 Pre & Per WMA

3 Maridanga 2 Pre & Per WMA

4 Noagram 1.6 Pre:WMA Per; WDB

5 Suorer 1.8 Pre & Per WMA

6 Majhair 3.4 Pre & Per WMA

7 Mora 2.8 Pre & Per WMA

8 Amtola 1.25 Pre & Per WMA

9 Kumarer 1.8 Pre & Per WMA

10 Takimara 1.5 Pre:WMA Per; WDB

11 Satbaria/Gajaria 1.5 Pre:WMA Per; WDB

12 Diadanga Bishnapur 1.75 Pre & Per WMA

Total 26.65

b) Structures Table : 2/2

Sl. No Name of

Structures Vent Size No. Vents

Cost Sharing

1 Pateswari Reg 1.52m X 1.8 2 m 10

As the structures Sl.1 to Sl.5 will

serve the SIPs SWC 16,17-

18,7-14.the O & M cost will

also shared among the SIPs.As

these are peripheral structures

,preventive by WMA/WMG &

periodic by BWDB

2 Takimara Reg 1.52 m X 1.82m 2

3 Takimara Reg

(Proposed) 1.52 m X 1.82 m

1`

4 Satbaria Reg

(Proposed) 1.52 m X 1.82 m

1

5 Noagram

Reg 1.52 m X 1.82 m

1

Share for SWC:17-18 for the maintenance of structures from Sl. 1 Sl. 5 is 11 %

6 Diadanga Bishnapur

1.52 m X 1.82 m 1 Preventive:WMA Periodic:BWDB

Page 160: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 4

Sl. No Name of

Structures Vent Size No. Vents

Cost Sharing

7 Daskhin Burikhali

1.52 m X 1.82 m 1 Preventive:WMA Periodic:BWDB

8 Inlet/Outlet Strs 1 No Preventive:WMA Periodic:BWDB

7 WMG office (proposed)

2 Nos Preventive & Periodic by WMA

8 Bridge/ Culverts

(proposed) 2 Nos

Preventive:WMA Periodic:BWDB

9 Tube Well (proposed)

10 Nos Preventive & Periodic by WMA

c) Brick reference Sections Table : 2/3

Sl. No.

Name of Canal Length

of Canal (Km)

Bed Width

(m)

No of 2m Brick

Masonry Cost sharing

1 Liner 4 7.5 8 Pre-WMA

Per-WDB

2 Chachuri 3.25 1.5 6 Pre & Per WMA

3 Maridanga 2 1 4 Pre & Per WMA

4 Noagram 1.6 3.25

3 Pre-WMA

Per-WDB

5 Suorer 1.8 1.25 3 Pre & Per WMA

6 Majhalir 3.4 1 7 Pre & Per WMA

7 Mora 2.8 1 6 Pre & Per WMA

8 Amtola 1.25 1 2 Pre & Per WMA

9 Kumarer 1.8 1.5 2 Pre & Per WMA

10 Takimara 1.5 2

3 Pre-WMA

Per-WDB

11 Satbaria /Gajaria 1.5 2

3 Pre-WMA

Per-WDB

12 Diadanga-Bishnapur 1.75 2 3 Pre & Per WMA

d) Embankment Table : 2/4

Page 161: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 5

Length of

Embankment Location Owned by

Type of

Embankment Cost sharing

12.00 From Urushi to

Pateswari

Regulator

BWDB Top earthen Preventive :WMA

& Periodic: WDB

The total operation & maintenance cost and sharing of the cost between BWDB and WMA/WMG for

the SIP SWC 17-18 is given below in Table : 3

Table: 3.

O & M Cost

Borne By

Of Works (Lac Tk)

Embankment Structures Khals/Canals Total

WMA 1.68 0.806 1.672 4.158

BWDB 6.144 4.549 2.566 13.259

Total 7.824 5.355 4.238 17.417

The WMA/WMG share comes to Tk 163 /acre/year and on the other hand the share for BWDB under

JMC comes to Tk 522 /acre/year The O & M Cost sharing is given in Appendix 1.

Maintenance responsibilities and cost sharing between the parties will be finalised during the

negotiations between the WMO and the BWDB.

6 Operational Plan of all Regulators in consultation with the concerned WMG and

WMA

Hydrological analysis were made separately for all the SIPs under NSP & CSP. Basin water levels

have been calculated after matching with the river water levels & rainfall. The basin water levels & the

opening and closing of gates at different time of the year have been shown below for each of the

SIPs. As a start in the first year the gates of the regulators around each SIP may be operated as per

the schedule shown below. The WMG/WMA may be informed that the level has been fixed on

hydrological analysis and as the first year let the run on this basis. On the second year the operation

will be fine tuned on the basis of the recommendations of the WMG/WMA and also on the experience

from the first year’s operation. While preparing the recommendations the WMA / WMG will have

threadbare discussion with the all the stake holders of the SIP. Accumulated basin storage, water

level and probable date of gate opening of SIP SWC :17-18 is given in Table : 4

Table : 4

Page 162: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 6

Date River WL Runoff Vol. Gate

Position

Basin condition

(M.PWD) Vol. (ha-m) Storage PWL

11th July 1.69 105.50 Closed 105.50 1.69

31st July 2.56 301.64 Closed 407.14 2.06

15th August 2.52 252.90 Closed 660.04 2.25

31st August 2.79 269.77 Closed 929.81 2.41

16th Sept. 3.12 114.55 Closed 1044.36 2.48

24th Sept. 2.50 57.27 Opened 1101.63 2.51

7. Maintenance Schedule

A yearly maintenance schedule is to be prepared at the beginning of the each financial year which

should be strictly followed to achieve regular and effective maintenance. Maintenance schedule is to

be prepared by BWDB in consultation with the WMOs. Draft maintenance program is to be prepared

by BWDB before 30th June for the works of the next year. Necessary steps like budget allocation,

design drawings for the maintenance work, work authorization, tendering processes are to be initiated

at proper time by the BWDB.

8. Training on Maintenance Issue

Water Management Group (WMG) members shall have to be trained on operation of structure for

proper water management of the project. BWDB officials should be given training on the same issue.

For proper implementation of the maintenance plan, training on maintenance is also to be imparted to

water management groups as well as to the BWDB officials. The training should cover maintenance

needs assessment, types of maintenance work, roles and responsibilities of each party, maintenance

schedule, budgeting and monitoring. Training is also required to be imparted to the gate operators of

all the infrastructure (regulators, sluices and water control structures) the project. Such type of training

should be imparted to the individual gate operator at his concerned gate site showing the practical

operation of the gate by BWDB experts.

9. Rates For Maintenance (Canals/Khals) :

i) Preventive maintenance work on khals and canals includes:

(a) removal of floating debris and water hyacinth and water hyacinth and

(b) cutting grass/weeds prior to the starting of the monsoon.

Preventive maintenance of canals has been taken as Tk.500.00 per Km.

ii) Periodic maintenance work on khals and canals includes mainly desalting and re-excavation of

khals

Average siltation per year has been taken as 10 cm.

Side slope of khals has been taken as 1:!.5 both sides

Silt clearance at the rate of Tk 60.40/cum (BWDB Jessore Circle rate)

The annual maintenance cost of these khals are given Appendix-2

10. Rates For Maintenance (Structures) :

Page 163: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 7

a) Preventive Cost: i) Painting area has been taken as vent size area plus 10% more for the angles & others.

ii) Painting @ Tk.225. 44 per sq.m. ( as per schedule of rates of Jessore O&M Circle).

iii) Greasing cost for greasing gearbox Tk 644.02 (as per schedule of rates of Jessore O & M

Circle).

iv) Devris clearance : L.S. Tk.300.00 per structure per year.

v) Gauge painting : L.S Tk.150.00 per meter.

Average 7 meter per structure i.e. Tk. 1,050.00 per structure.

b) Periodic Cost.

Periodic maintenance cost per structure per year has been taken as the 1.5% of total Investment cost.

Investment cost of the existing old structures have been taken as the present cost for the type design

of similar structure in PPTA. The bill of quantities of the type design of same size & vent (1.5 m X 1.8

m) has been updated with the present schedule of rates of Jessore O & M Circle. For example the

PPTA cost for 1 vent (1.5 m X 1.8 m) structure was Tk.53.76 lac which has been updated to Tk

88.49 lac at present schedule of rates.

Periodic cost will include the following :

Replacing of rubber seals ( 1 in 3 years )

Repairing of structures ( 1 in 10 years )

Replacement of gates ( 1 in 15 years)

Replacing wire ropes for pinion gear gate ( 1 in 5 years )

Annual maintenance cost of structure are given in Appendix-3

10. Rates For Maintenance (Embankments) :

a) Preventive maintenance per km of Embankment

During monsoon , 5 months on an average every alternate week ( 6 days a week) : 60 days

During Off-monsoon, 7 months , on an average one week a month ( 6 days a week ) : 42

days

Total 102 days @ Tk. 150 per day = 15300.00

Contingency @ 10 % = 1530.00

!6,830.00

Say,Tk 17,000.00

Assume a fifth of embankment is under some sort repair/maintenance activities hence effective

length of Preventive Maintenance is 0.8 X L ( L= actual length of embankment). Therefore, weighted

average cost per km of embankment is

Tk 17000 X 0.8 = Tk 13,600.00.

Say, Tk 14000.00 per km/year.

b) Periodic Maintenance per km of embankment.

I. Considering Section :

Page 164: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 8

Earth Work

4.27m

Considering subsistence @ . 05 m/year

Av. Ht. 2.5 m X- sectional area = 4.27*0.05 + 1/2 0.10*2.5

1:2 1:3 + 1/2 0.15*2.5

= 0.213 + 0.125 + 0.1875

= 0.53 sq.m.

Therefore, per Km. volume of earthwork = 0.53 * 1000 = 530 m3

Cost @ Tk 65.12 per m3 earthwork = Tk.34,513.00

II. Turfing :

Turfing area i.e slope area = { ( 2.5 2 + 7.5 2 ) 1/2 + ( 2.5 2 + 5 2 ) ½ } 1000

= { 7.9 + 5.6 } 1000

= 13.5 * 1000

= 13500 sq. m.

So yearly requirement as per assumption : 10 % of 13500 = 1350 sq. m .

Therefore, per km turfing

Cost @ Tk. 12.37 per sq. m = Tk. 16,699.50

Say, Tk 16,700.00 per km.

As the top of the embankment is carpeted for which periodic Maintenance = Tk 16,700.00

Annual maintenance cost embankment is given in Appendix 4

11. Rates for Maintenance of 2-meter Width Reference Sections on Khals :

As per suggestion of ADB, a 2 (two) meter width brick the masonry reference section have been

provided across each canal at every 500 meter intervals of the length of the canal. This will be

provided at the design bed level of the canal so that while silt clearance is necessary in future it will

act as a reference datum.

a) Preventive Cost:

Considered on a lump sum basis of Tk.500.00 per brick masonry.

b) Periodic Cost:

Considered 0.075 m cement concrete over 0 .075 m brick soling, As per the bed width,height and

side slopes of the canal the estimated cost of the respective 2 meter width reference sections

were calculated on the basis of the schedule of rates of Jessore O & M Circle of BWDB. 1.5 % of

the cost has been taken as the periodic costs of the brick sections.

Annual maintenance cost of structure are given in Appendix-5

Page 165: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 9

Cost Sharing in SIP SWC 17-18 Appendix 1

Command

Area ( ha) 1471

Benefitted

Area ( ha) 1030

O & M Cost

O & M Cost

Payable by

WMA

( Tk/Acre/Year )

O & M Cost payable by

BWDB

(Tk/Acre/Year)

Total Cost

(Tk/Acre/Year) Borne By

Of Works (Lac Tk)

Embankment Khals/Canals Structures Total

WMA 1.68 1.672 0.806 4.158 163

BWDB 6.144 2.566 4.549 13.259 522

Total 7.824 4.238 5.355 17.417 685

Page 166: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 10

Preventive and Periodic maintenance Cost of Khals / Canals

SWC ; 17-18

Appendix 2

Sl. No

Name of Khal Length of

Khals (Km)

Canal Size Annual Siltation

(m )

Volume of

Siltation m3/Year

Unit Rate of Maintainance

Costs (Tk)

Cost sharing Av. Bottom

Width (m)

Avg. Side

Slopes

Preventive (Tk./Km)

Periodic (Tk./ m3 )

Preventive Periodic Total

1 Liner Khal (1/2 of 8 km)

4 7.5 ! : 1.5 0.1 3060 500 60.4 2000 184824 186824 Pre: WMA Per; WDB

2 Chenchuri Khal 3.25 1.5 ! : 1.5 0.1 536.25 500 60.4 1625 32389.5 34014.5 Pre & Per WMA

3 Maridanga 2 1 ! : 1.5 0.1 230 500 60.4 1000 13892 14892 Pre & Per WMA

4 Noagram 1.6 3.25 ! : 1.5 0.1 544 500 60.4 800 32857.6 33657.6 Pre:WMA Per; WDB

5 Suorer 1.8 1.25 ! : 1.5 0.1 252 500 60.4 900 15220.8 16120.8 Pre & Per WMA

6 Majhair 3.4 1 ! : 1.5 0.1 391 500 60.4 1700 23616.4 25316.4 Pre & Per WMA

7 Mora 2.8 1 ! : 1.5 0.1 322 500 60.4 1400 19448.8 20848.8 Pre & Per WMA

8 Amtola 1.25 1 ! : 1.5 0.1 143.75 500 60.4 625 8682.5 9307.5 Pre & Per WMA

9 Kumarer 1.8 1.5 ! : 1.5 0.1 297 500 60.4 900 17938.8 18838.8 Pre & Per WMA

10 Takimara 1.5 2 ! : 1.5 0.1 322.5 500 60.4 750 19479 20229 Pre:WMA Per; WDB

11 Satbaria/Gajaria 1.5 2 ! : 1.5 0.1 322.5 500 60.4 750 19479 20229 Pre:WMA Per; WDB

12 Diadanga Bishnapur

1.75 2 ! : 1.5 0.1 376.25 500 60.4 875 22725.5 23600.5 Pre & Per WMA

Total 26.65 13325 410553.9 423878.9

In Lac Tk

Canal Maintenance Sharing

Preventive Periodic Total

WMA 0.133 1.539 1.672

BWDB 0 2.566 2.566

Total 0.133 4.105 4.238

Preventive & Periodic Maintenance Costs of Structures

Page 167: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 11

Appendix 3

Sl. No.

Name of Structures

Vent Size No.

Vents

Approx Cost of

Structures (lac Tk)

Preventive Cost Periodic Costs=1.5%

of Investment

Costs (Lac Tk.)

Cost Sharing

Painting of Gates Painting Gauge

(Tk)

Greasing of Gates

Others

(Tk.) Total (Tk.) Area

(Sq.m) Cost

(Tk/Sq.m) Costs (Tk)

Cost/ Gate

Costs (Tk.)

1 Pateswari Reg 1.52m X 1.8 2 m

10 327 121.72 225.44 27440.56

1050 644.02 6440.2 300 35230.76 4.91 As the

structures Sl.1 to Sl.5 will

serve the SIPs SWC 16,17-

18,4-6,8,9,14.the O & M cost will also shared among the

SIPs.As these are peripheral

structures ,preventive by WMA/WMG &

periodic by BWDB

2 Takimara Reg 1.52 m X

1.82m 2 117 24.34 225.44

5487.21

1050 644.02 1288.04 300 8125.25 1.76

3 Takimara Reg

(Proposed) 1.52 m X 1.82

m 1 88.49 12.17 225.44

2743.60

1050 644.02 644.02 300 4737.62 1.33

4 Satbaria Reg (Proposed)

1.52 m X 1.82 m

1 88.49 12.17 225.44 2743.6

0 1050 644.02 644.02 300 4737.62 1.33

5 Noagram Reg 1.52 m X 1.82

m 1 88.49 12.17 225.44

2743.60

1050 644.02 644.02 300 4737.62 1.33

Sub-total 57568.88 10.64

Share for SWC:17-18 for the maintenance of structures from Sl. 1 Sl. 5 is 11 % 6332.00 1.17 Preventive:

WMG Periodic: BWDB

6 Diadanga-Bishnapur 1.52 m X 1.82 m

1 88.49 6.08 225.44 1370.68 1050 644.02 644.02 300 3364.70 1.33 Pre: WMG Per:

BWDB

7 Daskhin Burikhali 1.52 m X 1.82 m

1 88.49 6.08 225.44 1370.68 1050 644.02 644.02 300 3364.70 1.33 Pre: WMG Per:

BWDB

8 Inlet/Outlet Strs 1 no 17.14 Lump Sum

500.00 0.26 Pre: WMG Per:

BWDB

9 Bridge/Cul 2 Nos (Pro) 28.6 Lump Sum 1000 0.43

Pre:WMA Per:WDB

10 WMG Offi 2 No ( Pro) 14 Lump Sum 1000 0.21 Pre & Per WMA

11 Tube Well 10 Nos ( Pro) 7 Lump Sum 2500 0.11 Pre & Per WMA

Maintenance cost of structures inSWC 16 18061.39 4.83

Cost sharing among WMA

& BWDB

WMA 18061.39 0.32

BWDB 0 4.51

Total 18061.39 4.83

Page 168: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 12

Preventive & Periodic maintenance costs of Embankments

Appendix 4

Length of

Embt(km) Location

Owned

by

Type of

Embt

Avg.Dimensions of Embt Prev.Cost (Lac Tk) Per.Cost (Lac Tk)

Total

(Lac Tk)

Cost

Sharing

Slopes Ht(m)

Top

Width(m)

Unit Rate

per

Km(Lac

Tk)

Total

(Lac Tk)

Unit Rate

per

Km(Lac

Tk)

Total

(Lac Tk)

12

From

Urushi to

Pateswari

BWDB Earthen C[S:1:2

R/S:1:3 2.5 4.27 0.14 1.680 0.512 6.144 7.824

Pre:WMA

Per:WDB

Total 1.680 6.144 7.824

WMA 1.680 0

WDB 0 6.144

Brick Masonry Reference Sections on Khals

Page 169: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F Annex-A

SWC-17+18; Noagram-Gazaria 13

Preventive & Periodic Maintenance cost of 2m Wide Brick Masonry on Khals in SWC 17-18 Appendix 5

Sl. No.

Name of Canal

Length of

Canal (Km)

Bed Width

(m)

No of 2m Brick

Masonry Unit Cost of one Khal Brick Masonry (Lac Tk)

App.Cost Masonry (Lac Tk)

Preventive Cost Tk 500 per brick

Masonry (Lac Tk)

Periodic Costs=1.5% of

Investment Costs (Lac Tk)

Cost sharing

1 Liner 4 7.5 8 0.193 1.544 0.04 0.023 Pre-WMA Per-WDB

2 Chachuri 3.25 1.5 6 0.113 0.678 0.030 0.010 Pre & Per WMA

3 Maridanga 2 1 4 0.107 0.428 0.020 0.006 Pre & Per WMA

4 Noagram 1.6 3.25 3

0.137 0.411 0.015

0.006 Pre-WMA Per-WDB

5 Suorer 1.8 1.25 3 0.11 0.33 0.015 0.005 Pre & Per WMA

6 Majhalir 3.4 1 7 0.107 0.749 0.035 0.011 Pre & Per WMA

7 Mora 2.8 1 6 0.102 0.612 0.030 0.009 Pre & Per WMA

8 Amtola 1.25 1 2 0.107 0.214 0.010 0.003 Pre & Per WMA

9 Kumarer 1.8 1.5 2 0.113 0.226 0.010 0.003 Pre & Per WMA

10 Takimara 1.5 2 3

0.12 0.36 0.015

0.005 Pre-WMA Per-WDB

11 Satbaria /Gajaria 1.5 2

3 0.12

0.36 0.015 0.005

Pre-WMA Per-WDB

12 Diadanga-Bishnapur 1.75 2

3 0.12

0.36 0.015 0.005

Pre & Per WMA

Total 0.250 0.094

Total A + B Preventive (Lac Tk) Periodic(Lac

Tk) Total

WMA 0.431 0.375 0.806 WMA 0.250 0.055

BWDB 0 4.549 4.549 WDB 0.000 0.039

Total 0.431 4.924 5.355

Page 170: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-F

Annex-A

SWC-17+18; Noagram-Gazaria 14

Map of SWC : 17-18

Page 171: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

ANNEX – G

HYDROLOGY

Page 172: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 1

HYDROLOGY

SWC-17+18; Noagram-Gazaria Scheme 1. INTRODUCTION 1.1 Background The proposed study area is located in the Southwest Coastal Region of Bangladesh. The project area is bounded by the Chitra river on the West and by the Nabaganga river on the North, South and East. Both the rivers tidal and thus the drainage of the study area are governed by the tidal fluctuation of these rivers. In variably the entire southwest region has been suffering from tidal intrusion and monsoon drainage congestion over the years. In order to prevent the salinity intrusion and tidal flooding the study area is enclosed by constructing coastal embankment with water control structures for drainage of the polder areas. But at present most of the controlling structures are not full functioning and some of the internal drainage khals have been severely silted up as well, which prevents the people to get full benefit out of the existing project condition. In view of the above fact, the hydrological analysis has been carried out to provide a justification of decision making for planning, design and improved O&M of the controlling structures. 1.2 Objective of the Study The main objective of this hydrological study is to review and improve the existing drainage plan and to generate data for assessing the inundation patterns with and without project situations. 1.3 Study Area The study area is mainly concentrated in the SIP SWC-17+18 areas of Chenchury Beel Sub-project under SWAIWRPMP. The area is located in the two unions namely Perulia and Purulia under Kalia Upazila of Narail District. The whole area of Chenchuri Beel Sub-project has been divided into a number of sub-catchments considering formation of Water Management Organisations (WMO) and existing drainage patterns. The proposed study area (SIP SWC-17+18) is located at the most downstream part of the Chenchuri Beel Sub-project which seems to be the lowest part of the project in terms of land elevation. The total area of SWC-17+18 is about 1470 ha. The average land elevation is about 2.15 m, PWD. Maximum land of the area is within the elevation of 1.75 m PWD and 3.0 m PWD covering about 95% of these SIP areas. Agriculture is the main earning source of income of the people of the project area which is most frequently affected by tidal intrusion through the existing structures and monsoon drainage congestion. The entire project area is criss-crossed by numerous drainage channels which are mostly silted up as mentioned earlier. The location map of the study area is shown in the Figure 1.1. & Figure 1.2.

Page 173: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 2

Figure 1.1: Map of Chenchuri Beel Sub-Project showing Study Area 2. Data Collection and Analysis The study has been carried out mainly based on the secondary data collected from BWDB and previous study reports. 2.1 Water Level Data

Figure 1.1: Map of Chenchuri Beel Sub-Project showing Study Area

Chenchuri-Beel Sub-Project

SIP 16

SIP 17 & 18

Study Area

Page 174: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 3

Figure 1.2: Map of Proposed SIP, SWC-17+18; Noagram-Gazaria Scheme

Page 175: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 4

2. HYDROLOGICAL ANALYSIS 2.1 Rainfall Data The nearest rainfall station to the study area is located at Narail (R-461) maintained by BWDB. The rainfall data is available from 1965 to 2007.Monthly Maximum, Mean & Minimum rainfall table, Annual & Monthly rainfall and 5-Day rainfall analysis (Maximum Rainfall Depth-Duration Data) table are shown below. That table is computed from 1987 to 2007 (20 years) data.

Table 2.1.1: Monthly Maximum, Mean & Minimum rainfall ( mm )

Rainfall station : R- 461 ( Narail )

Year Parameter January February March April May June July August September October November December

1987 Max= 0.00 0.00 10.20 81.30 33.00 99.10 105.40 259.10 39.40 14.00 84.30 7.60

Mean= 0.00 0.00 0.98 5.72 2.37 12.99 18.66 21.08 5.88 1.07 3.33 0.33

Min= 0 0 2.5 5.1 2.5 5.1 2 1.3 1.3 9.1 1.5 2.5

1988 Max= 0.00 0.00 39.90 122.40 55.90 78.70 76.20 62.00 25.90 27.20 50.80 0.00

Mean= 0.00 0.00 3.17 5.21 9.23 14.51 12.10 14.53 3.65 3.43 3.62 0.00

Min= 0 7.6 5.1 7.6 2.5 1 1.5 0.8 0.5 5.1 27.2 0

1989 Max= 0.00 28.40 2.00 50.80 106.70 40.10 41.10 31.80 48.80 90.70 0.00 1.30

Mean= 0.00 1.12 0.08 1.70 10.50 8.98 8.95 4.27 5.70 7.44 0.00 0.04

Min= 0 3 0.5 0.3 0.3 7.9 2.3 2.3 1.5 5.1 0 1.3

1990 Max= 0.00 31.80 56.60 31.80 63.50 38.10 60.20 46.20 101.60 44.50 22.10 5.10

Mean= 0.00 2.94 4.50 1.86 8.97 6.38 10.48 4.47 9.54 5.96 1.33 0.16

Min= 0 2.5 2.5 7.6 2.5 2.5 1.3 2.3 5.1 5.1 2.5 5.1

1991 Max= 31.50 15.20 31.80 40.60 69.90 66.00 33.50 137.20 147.80 63.50 0.00 59.70

Mean= 1.22 0.54 1.35 3.26 4.96 13.32 7.35 10.38 15.78 6.12 0.00 2.50

Min= 6.4 15.2 10.2 20.3 5.1 1.3 5.1 4.6 7.1 2.5 0 17.8

1992 Max= 20.30 20.30 0.00 12.70 96.50 238.30 120.70 71.10 37.00 3.00 0.00 0.00

Mean= 0.65 2.28 0.00 0.42 8.77 16.07 22.09 8.03 5.58 0.19 0.00 0.00

Min= 20.3 5.1 0 12.7 7.6 2.5 15.2 5.1 9 1.4 0 0

1993 Max= 0.00 54.00 45.00 45.00 74.00 90.00 69.00 60.00 71.00 67.00 10.00 0.00

Mean= 0.00 1.93 2.97 3.70 9.55 16.97 9.87 11.26 10.47 4.10 0.33 0.00

Min= 0 54 15 7 5 4 4 4 4 6 10 0

1994 Max= 0.00 45.00 25.00 50.00 69.00 120.00 100.00 75.00 30.00 9.00 0.00 0.00

Mean= 0.00 2.29 0.81 3.27 6.97 11.20 11.87 10.03 2.57 0.29 0.00 0.00

Min= 0 19 25 15 10 4 5 5 10 9 0 0

1995 Max= 0.00 23.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 110.00 0.00

Mean= 0.00 1.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.57 0.00

Min= 0 10 0 0 0 0 0 0 0 0 40 0

1996 Max= 35.00 9.00 20.00 45.00 67.00 150.00 33.00 71.00 52.00 210.00 75.00 0.00

Mean= 1.13 0.55 0.65 1.73 4.74 17.53 4.45 10.19 3.67 9.90 2.50 0.00

Min= 35 7 20 2 25 10 4 9 4 22 75 0

1997 Max= 0.00 30.00 23.00 23.00 35.00 55.00 40.00 60.00 76.00 40.00 20.00 15.00

Mean= 0.00 2.50 0.74 2.77 3.71 8.33 11.77 7.06 16.67 1.29 0.67 0.87

Min= 0 10 23 10 15 5 5 5 10 40 20 12

1998 Max= 20.00 17.00 95.00 36.00 75.00 15.00 60.00 38.00 45.00 50.00 55.00 0.00

Mean= 1.00 0.93 4.52 2.97 5.16 2.33 10.71 6.03 7.50 4.81 4.00 0.00

Min= 11 9 12 8 10 5 6 5 6 10 25 0

1999 Max= 0.00 0.00 0.00 22.00 70.00 43.00 60.00 86.00 70.00 52.00 0.00 0.00

Mean= 0.00 0.00 0.00 1.07 4.35 4.40 10.06 12.32 10.87 8.03 0.00 0.00

Min= 0 0 0 10 5 3 3 8 6 5 0 0

2000 Max= 0.00 0.00 0.00 50.00 48.00 100.80 98.00 120.00 180.00 105.00 0.00 0.00

Mean= 0.00 0.00 0.00 4.40 6.61 11.83 12.58 10.87 15.90 5.19 0.00 0.00

Min= 0 0 0 15 5 10 10 5 4 8 0 0

2001 Max= 0.00 20.00 14.00 20.00 14.00 15.00 60.00 65.00 45.00 35.00 30.00 0.00

Mean= 0.00 1.25 0.45 2.17 2.00 5.97 6.71 4.10 3.13 4.58 66.32 0.00

Min= 0 15 14 5 8 4 4 10 7 10 10 0

2002 Max= 15.00 0.00 30.00 60.00 75.00 75.00 75.00 80.00 45.00 0.00 0.00 0.00

Mean= 0.81 0.00 1.19 3.33 8.90 18.20 8.42 16.19 8.70 0.00 0.00 0.00

Min= 10 0 7 15 5 5 7 5 5 0 0 0

2003 Max= 0.00 0.00 42.00 40.00 28.00 80.00 58.00 32.00 0.00 73.00 0.00 7.00

Mean= 0.00 0.00 3.68 3.37 2.29 12.63 10.74 4.42 0.00 8.45 0.00 0.52

Min= 0 0 15 15 10 10 10 5 0 5 0 4

2004 Max= 0.00 0.00 0.00 25.00 54.00 36.00 30.00 67.00 122.00 44.00 10.00 0.00

Mean= 0.00 0.00 0.00 0.83 5.26 9.47 4.06 6.52 19.73 4.77 64.97 0.00

Min= 0 0 0 25 6 10 8 10 12 10 10 0

Page 176: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 5

Table 2.1.2 : Monthly & Annual rainfall Rainfall station : R-461 ( Narail )

Year Annual

rainfall (mm) January

(mm) February

(mm) March (mm)

April (mm)

May (mm)

June (mm)

July (mm)

August (mm)

September (mm)

October (mm)

November (mm)

December (mm)

1987 2217 0 0 31 172 74 390 579 653 177 33 100 10

1988 2176 0 50 98 156 286 435 375 451 110 106 109 0

1989 1493 0 31 3 51 326 269 278 132 171 231 0 1

1990 1727 0 82 140 56 278 191 325 139 286 185 40 5

1991 1999 38 15 42 98 154 400 228 322 474 190 0 78

1992 1940 20 66 0 13 272 482 685 249 168 6 0 0

1993 2168 0 54 92 111 296 509 306 349 314 127 10 0

1994 1504 0 64 25 98 216 336 368 311 77 9 0 0

1995 230 0 33 0 0 0 0 0 0 0 0 197 0

1996 1707 35 16 20 52 147 526 138 316 110 307 75 0

1997 1712 0 70 23 83 115 250 365 219 500 40 20 27

1998 1498 31 26 140 89 160 70 332 187 225 149 120 0

1999 1568 0 0 0 32 135 132 312 382 326 249 0 0

2000 2057 0 0 0 132 205 355 390 337 477 161 0 0

2001 981 0 35 14 65 62 179 208 127 94 142 55 0

2002 1983 25 0 37 100 276 546 261 502 261 0 0 0

2003 1413 0 0 114 101 71 379 333 137 0 262 0 16

2004 1550 0 0 0 25 163 284 126 202 592 148 10 0

2005 1493 12 0 144 66 72 120 449 110 86 446 0 0

2006 1151 0 0 0 26 221 255 0 148 447 54 0 0

2007 1969 0 0 0 0 228 0 562 252 325 359 243 0

Page 177: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 6

Table 2.1.3 : 5-Day rainfall analysis ( Maximum Rainfall Depth-Duration Data) Rainfall station : 461 ( Narail )

Year Premonsoon Monsoon

1-DAY 2-Day 3-DAY 4-Day 5-DAY 1-DAY 2-Day 3-DAY 4-Day 5-DAY

1987 99.1 160.1 231.5 245.5 245.5 259.1 309.9 386.1 395.5 395.5

1988 78.7 108.2 159 179.3 197.1 62 62.8 62.8 62.8 63.6

1989 40.1 40.1 40.1 40.1 40.1 31.8 31.8 31.8 31.8 31.8

1990 38.1 38.1 38.1 38.1 38.1 46.2 77.4 77.4 77.4 77.4

1991 66 66 66 101.6 111.8 137.2 149.9 149.9 149.9 149.9

1992 238.3 238.3 238.3 268.8 269 71.1 86.3 86.3 86.3 86.3

1993 90 90 90 165 186 60 60 105 130 130

1994 120 165 169 169 169 75 75 105 135 167

1995 0 0 0 0 0 0 0 0 0 0

1996 150 175 175 175 258 71 80 80 80 80

1997 55 55 55 78 78 60 72 72 72 72

1998 15 25 40 55 60 38 47 57 69 74

1999 43 43 43 43 43 86 108 164 164 164

2000 100.8 100.8 122.8 132.8 165.8 120 157 197 197 197

2001 15 29 29 39 39 65 94 117 127 127

2002 75 75 110 180 215 80 130 130 130 130

2003 80 112 144 154 154 32 37 37 37 37

2004 36 36 36 36 36 67 97 97 97 97

2005 45 53 61 76 81 30 30 30 30 30

2006 180 194 194 194 194 31 61 61 61 61

2007 0 0 0 0 0 45 50 50 50 58

No. of Data 21.0 21.0 21.0 21.0 21.0 21.0 21.0 21.0 21.0 21.0

Mean(mm) 74.5 85.9 97.2 112.9 122.9 69.9 86.5 99.8 103.9 106.1 Std Dev 59.9 66.7 74.1 80.0 88.2 53.2 64.3 81.2 83.2 83.7

Max(mm) 238.3 238.3 238.3 268.8 269.0 259.1 309.9 386.1 395.5 395.5

Min(mm) 15 25 29 36 36 31 30 30 31.8 30

Frequency Analysis of Individual Month using Extreme Value Distribution

1 in 2 17 76 87 103 113 60 77 90 94 96

1 in 5 126 137 148 164 174 121 138 151 155 157

1 in 10 178 189 200 216 226 173 189 203 207 209

1 in 20 233 244 255 271 281 228 245 258 262 264

1 in 25 268 279 290 306 316 263 280 293 297 299

1 in 30 188 199 211 226 236 183 200 213 217 220

1 in 50 243 255 266 282 292 239 255 269 273 275

80% dep.

1.25 17 29 40 56 66 13 29 43 47 49

Page 178: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 7

2.2 Topographic Data Topographic data is so basic and very important for the assessment of inundation patterns during monsoon in the various SIP areas. Accurate topographic data is also needed for assessment of benefited areas with project conditions in terms of land classification coverage. The topographic data that has been used in this study are collected from the secondary sources. The Project Map of the Chenchuri Beel Sub-project available from PPTA has been updated by incorporating contour lines taken from the topographical maps prepared by SOB with the help of CEGIS. The map has been updated incorporating other features such as alignment of the khals, location of the beels etc. The contour lines are at an interval of 0.25m. Area-Elevation & Storage-Elevation curves have been prepared using the updated contour map by planimetering for the use in hydrological analysis and land classification. The topographic map showing contour lines is presented in Figure 2.3.

Figure 2.3: Topographic map of the study area (SIP 16, 17 &18) showing contour lines

SIP-16

SIP-17 & 18

Page 179: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 8

2.3 Water Level Data Daily water level data (Station: Gazirhat-SW219, Nabaganga river) of the peripheral rivers of the project area has been analysed to determine the monthly maximum water level, monthly mean water level and frequency analysis of water level and also are presented hydrograph Table 2.3.1 : Monthly Maximum water level (mPWD)

Year Parameter January February March April May June July August September October November December

1984 Max (H.Tide)= 1.94 2.04 2.14 2.34 2.49 3.17 3.58 3.58 3.59 3.28 2.18 1.91

Max (L.tide)= 0.49 0.34 0.24 0.44 0.79 1.89 2.58 2.98 3.08 2.55 1.18 0.71

1985 Max (H.Tide)= 1.79 1.94 2.11 2.16 2.44 2.44 3.27 3.50 3.47 3.39 2.85 2.12

Max (L.tide)= 0.36 0.21 0.29 0.34 0.74 1.14 2.10 2.51 2.64 2.61 1.81 0.87

1986 Max (H.Tide)= 1.80 1.79 2.09 2.31 2.39 2.44 3.08 3.54 3.46 3.33 2.66 2.06

Max (L.tide)= 0.36 0.18 0.19 0.49 0.64 0.99 2.15 2.58 3.06 2.46 1.31 0.61

1987 Max (H.Tide)= 1.85 1.85 1.92 2.18 2.18 2.51 3.24 3.87 3.84 3.37 2.55 2.02

Max (L.tide)= 0.25 0.20 0.10 0.38 0.42 1.09 1.94 3.17 3.19 2.87 1.32 0.77

1988 Max (H.Tide)= 1.85 2.11 2.20 2.38 2.49 2.76 3.43 3.93 3.92 2.96 2.44 2.24

Max (L.tide)= 0.48 0.36 0.38 0.43 1.04 1.36 2.40 3.03 3.36 1.96 1.14 1.14

1989 Max (H.Tide)= 1.80 2.10 2.25 2.30 2.50 2.72 3.37 3.38 3.38 3.15 2.43 1.94

Max (L.tide)= 0.28 0.30 0.20 0.47 1.10 1.42 2.42 2.40 2.32 1.95 1.07 0.47

1990 Max (H.Tide)= 1.91 2.14 2.37 2.52 2.44 2.74 3.53 3.60 3.23 3.33 2.70 2.10

Max (L.tide)= 0.12 0.12 0.30 0.62 0.77 1.42 2.53 2.81 2.30 2.43 1.20 0.48

1991 Max (H.Tide)= 2.01 1.91 2.19 2.36 2.51 2.78 3.17 3.51 3.86 3.09 2.37 2.13

Max (L.tide)= 0.36 0.13 0.11 0.34 0.76 1.29 1.84 2.48 2.96 1.81 1.05 0.53

1992 Max (H.Tide)= 2.11 2.30 2.39 2.33 2.45 2.66 3.06 3.43 3.36 2.86 2.40 2.06

Max (L.tide)= 0.29 0.21 0.24 0.30 0.76 1.16 1.64 2.01 2.15 1.45 1.09 0.60

1993 Max (H.Tide)= 2.02 2.20 2.24 2.32 2.97 2.85 3.20 3.60 3.65 3.40 2.54 2.28

Max (L.tide)= 0.25 0.27 0.30 0.45 0.82 1.25 1.90 2.25 2.45 2.22 1.47 0.62

1994 Max (H.Tide)= 2.17 2.37 2.67 2.69 2.60 2.85 3.23 3.65 3.40 2.93 2.42 2.17

Max (L.tide)= 0.42 0.24 0.35 0.45 0.60 1.30 1.81 2.30 2.08 1.23 0.52 0.22

1995 Max (H.Tide)= 1.92 2.12 2.22 2.16 2.44 2.44 3.27 3.50 3.47 3.39 2.85 2.12

Max (L.tide)= 0.12 0.12 0.22 0.34 0.74 1.14 2.10 2.51 2.64 2.61 1.81 0.87

1996 Max (H.Tide)= 1.93 2.31 2.33 2.53 2.58 2.73 3.65 3.90 3.82 3.22 2.94 2.38

Max (L.tide)= 0.20 0.20 0.28 0.38 0.73 1.01 2.30 2.55 2.74 1.52 1.36 0.66

1997 Max (H.Tide)= 2.38 2.52 2.62 2.63 2.82 2.88 3.68 3.79 3.53 3.25 2.53 2.13

Max (L.tide)= 0.40 0.26 0.41 0.55 0.76 1.16 2.30 2.15 2.37 1.54 0.83 0.38

1998 Max (H.Tide)= 2.18 2.46 2.61 2.78 3.37 3.47 4.23 4.40 4.02 3.35 2.97 2.47

Max (L.tide)= 0.83 0.48 0.36 0.53 1.39 1.67 3.03 3.35 3.28 1.61 1.28 0.78

1999 Max (H.Tide)= 2.36 2.45 2.58 2.82 2.93 3.06 3.65 4.01 4.02 3.88 3.03 2.56

Max (L.tide)= 0.56 0.46 0.38 0.68 0.83 1.08 2.25 2.65 2.75 2.65 1.62 0.71

2000 Max (H.Tide)= 2.36 2.45 2.58 2.79 2.84 3.50 3.62 3.85 3.69 3.56 2.83 2.40

Max (L.tide)= 0.61 0.49 0.48 0.85 1.11 1.90 2.05 2.57 2.44 1.88 1.12 0.78

2001 Max (H.Tide)= 2.24 2.24 2.33 2.58 2.44 2.96 3.10 1.57 1.70 1.34 3.12 2.71

Max (L.tide)= 0.44 0.34 0.62 0.27 0.77 1.17 1.27 0.14 0.20 -0.32 1.24 0.86

2002 Max (H.Tide)= 2.46 2.75 3.02 3.09 3.37 3.62 4.02 4.25 4.07 3.92 3.21 1.88

Max (L.tide)= 0.39 0.42 0.49 0.62 1.22 1.82 2.57 2.87 2.63 2.14 1.52 0.08

2003

Max (H.Tide)= 2.76 2.87 3.10 3.46 3.56 3.43 4.30 4.44 4.46 4.24 3.50 3.10

Max (L.tide)= 0.76 0.71 0.71 0.91 1.36 1.46 2.81 2.83 2.96 2.77 2.11 1.36

Max (L.tide)= 1.00 0.87 1.13 1.07 1.56 2.07 3.47 2.82 3.08 3.05 1.87 1.72

Page 180: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 9

Table 2.3.2 : Monthly Mean water level (mPWD)

Year Parameter January February March April May June July August September October November December

1984 Max (H.Tide)= 1.61 1.48 1.69 1.92 2.25 2.72 3.15 3.38 3.48 2.79 2.03 1.73

Max (L.tide)= 0.39 0.10 0.17 0.30 0.63 1.43 2.09 2.61 2.89 1.78 0.78 0.51

1985 Max (H.Tide)= 1.52 1.51 1.76 1.78 2.00 2.29 2.81 3.29 3.27 3.12 2.42 1.90

Max (L.tide)= 0.24 0.14 0.22 0.21 0.47 0.87 1.58 2.30 2.34 2.21 1.23 0.64

1986 Max (H.Tide)= 1.50 0.99 1.45 1.85 1.97 2.09 2.77 3.22 3.18 2.95 2.29 1.69

Max (L.tide)= 0.22 -0.36 -0.04 0.28 0.43 0.61 1.52 2.22 2.22 1.95 1.08 0.42

1987 Max (H.Tide)= 1.34 1.24 0.56 1.73 1.87 2.19 2.86 3.56 3.70 2.73 2.24 1.82

Max (L.tide)= 0.03 -0.17 -0.98 0.15 0.28 0.74 1.57 2.78 3.07 1.73 1.04 0.55

1988 Max (H.Tide)= 1.51 1.57 1.62 1.87 2.15 2.54 3.00 3.54 3.55 2.63 2.08 1.83

Max (L.tide)= 0.20 0.21 0.15 0.30 0.67 1.16 1.84 2.66 2.73 1.41 0.77 0.53

1989 Max (H.Tide)= 1.32 1.62 1.59 1.86 2.14 2.42 2.84 3.17 3.15 2.84 2.10 1.68

Max (L.tide)= -0.03 0.11 0.03 0.24 0.55 1.00 1.66 2.07 2.06 1.65 0.79 0.28

1990 Max (H.Tide)= 1.38 1.59 1.55 2.02 2.10 2.50 3.14 3.40 3.00 2.79 2.19 1.78

Max (L.tide)= -0.07 0.06 -0.12 0.34 0.47 1.03 1.95 2.56 1.94 1.74 0.87 0.34

1991 Max (H.Tide)= 1.44 1.34 1.49 1.83 2.19 2.50 2.89 3.24 3.45 2.69 2.08 1.80

Max (L.tide)= 0.00 -0.22 -0.19 0.12 0.51 0.95 1.52 2.15 2.48 1.34 0.69 0.34

1992 Max (H.Tide)= 1.59 1.57 1.80 1.91 2.15 2.26 2.55 3.03 3.05 2.67 2.17 1.81

Max (L.tide)= 0.15 -0.01 0.12 0.21 0.43 0.66 0.98 1.60 1.77 1.21 0.76 0.35

1993 Max (H.Tide)= 1.02 1.41 1.28 1.88 2.21 2.50 2.86 3.23 3.38 2.93 2.26 2.02

Max (L.tide)= -0.45 -0.23 -0.42 0.12 0.53 0.92 1.37 1.96 2.31 1.51 0.78 0.47

1994 Max (H.Tide)= 1.86 1.82 2.03 2.17 2.25 2.46 2.94 3.31 3.06 2.49 1.97 1.80

Max (L.tide)= 0.29 0.19 0.21 0.32 0.45 0.74 1.34 2.07 1.64 0.81 0.31 0.14

1995 Max (H.Tide)= 0.64 1.10 0.92 1.78 2.00 2.29 2.81 3.29 3.27 3.12 2.42 1.90

Max (L.tide)= -0.93 -0.56 -0.89 0.21 0.47 0.87 1.58 2.30 2.34 2.21 1.23 0.64

1996 Max (H.Tide)= 1.65 1.75 1.81 2.03 2.39 2.46 3.14 3.46 3.41 2.88 2.51 2.09

Max (L.tide)= 0.04 0.02 0.06 0.16 0.50 0.65 1.47 2.15 2.16 1.33 0.98 0.47

1997 Max (H.Tide)= 1.93 1.99 2.15 2.17 2.36 2.60 3.08 3.29 3.21 2.57 2.22 1.90

Max (L.tide)= 0.20 0.17 0.26 0.23 0.50 0.73 1.45 1.84 1.81 0.88 0.54 0.28

1998 Max (H.Tide)= 1.76 1.82 2.01 2.20 2.58 3.25 3.87 4.12 3.57 2.92 2.60 2.16

Max (L.tide)= 0.08 0.09 0.09 0.27 0.63 1.40 2.42 2.98 2.54 1.39 0.99 0.50

1999 Max (H.Tide)= 2.11 2.12 2.08 2.34 2.55 2.73 3.34 3.62 3.70 3.28 2.65 2.28

Max (L.tide)= 0.31 0.22 0.21 0.43 0.63 0.86 1.79 2.31 2.52 1.87 0.99 0.63

2000 Max (H.Tide)= 2.08 2.04 2.20 2.40 2.55 2.97 3.41 3.55 3.46 2.94 2.47 2.13

Max (L.tide)= 0.43 0.29 0.31 0.46 0.68 1.20 1.90 2.18 2.18 1.33 0.78 0.51

2001 Max (H.Tide)= 1.92 2.00 2.05 2.08 2.10 2.68 1.70 1.30 1.31 1.03 2.65 2.35

Max (L.tide)= 0.29 0.19 0.15 0.04 0.47 0.84 0.02 -0.17 -0.16 -0.60 0.98 0.62

2002 Max (H.Tide)= 2.04 2.20 2.40 2.58 2.89 3.20 3.73 4.02 3.80 3.42 2.00 1.60

Max (L.tide)= 0.30 0.32 0.33 0.44 0.85 1.41 1.97 2.59 2.18 1.68 0.22 -0.18

2003 Max (H.Tide)= 2.25 2.35 2.57 2.82 3.05 3.21 3.88 4.09 4.16 3.83 3.32 2.95

Max (L.tide)= 0.50 0.58 0.59 0.71 1.02 1.24 2.34 2.54 2.78 2.27 1.61 1.20

2004 Max (H.Tide)= 2.61 2.27 2.52 2.94 3.22 3.44 4.03 4.27 4.35 4.01 3.30 3.10

Max (L.tide)= 0.89 0.48 0.58 0.82 1.19 1.40 2.33 2.60 2.65 2.34 1.59 1.38

Average monthly H.Tide 1.67 1.70 1.79 2.10 2.33 2.63 3.08 3.40 3.36 2.89 2.38 2.01

Average monthly L.Tide 0.15 0.08 0.04 0.30 0.59 0.99 1.65 2.21 2.21 1.53 0.90 0.51

Page 181: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 10

Table 2.3.3 : Frequency Analysis of River Water Level

River : Nabaganga Flow Type : Tidal

Station : SW219, Gazirhat, Narail Period : 1984 to 2004

Year Monthly Maximum & Minimum Water Level (m, PWD)

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

HWL LWL HWL LWL HWL LWL HWL LWL HWL LWL HWL LWL HWL LWL HWL LWL HWL LWL HWL LWL HWL LWL HWL LWL

1984 1.94 0.49 2.04 0.34 2.14 0.24 2.34 0.44 2.49 0.79 3.17 1.89 3.58 2.58 3.58 2.98 3.59 3.08 3.28 2.55 2.18 1.18 1.91 0.71

1985 1.79 0.36 1.94 0.21 2.11 0.29 2.16 0.34 2.44 0.74 2.44 1.14 3.27 2.10 3.50 2.51 3.47 2.64 3.39 2.61 2.85 1.81 2.12 0.87

1986 1.80 0.36 1.79 0.18 2.09 0.19 2.31 0.49 2.39 0.64 2.44 0.99 3.08 2.15 3.54 2.58 3.46 3.06 3.33 2.46 2.66 1.31 2.06 0.61

1987 1.85 0.25 1.85 0.20 1.92 0.10 2.18 0.38 2.18 0.42 2.51 1.09 3.24 1.94 3.87 3.17 3.84 3.19 3.37 2.87 2.55 1.32 2.02 0.77

1988 1.85 0.48 2.11 0.36 2.20 0.38 2.38 0.43 2.49 1.04 2.76 1.36 3.43 2.40 3.93 3.03 3.92 3.36 2.96 1.96 2.44 1.14 2.24 1.14

1989 1.80 0.28 2.10 0.30 2.25 0.20 2.30 0.47 2.50 1.10 2.72 1.42 3.37 2.42 3.38 2.40 3.38 2.32 3.15 1.95 2.43 1.07 1.94 0.47

1990 1.91 0.12 2.14 0.12 2.37 0.30 2.52 0.62 2.44 0.77 2.74 1.42 3.53 2.53 3.60 2.81 3.23 2.30 3.33 2.43 2.70 1.20 2.10 0.48

1991 2.01 0.36 1.91 0.13 2.19 0.11 2.36 0.34 2.51 0.76 2.78 1.29 3.17 1.84 3.51 2.48 3.86 2.96 3.09 1.81 2.37 1.05 2.13 0.53

1992 2.11 0.29 2.30 0.21 2.39 0.24 2.33 0.30 2.45 0.76 2.66 1.16 3.06 1.64 3.43 2.01 3.36 2.15 2.86 1.45 2.40 1.09 2.06 0.60

1993 2.02 0.25 2.20 0.27 2.24 0.30 2.32 0.45 2.97 0.82 2.85 1.25 3.20 1.90 3.60 2.25 3.65 2.45 3.40 2.22 2.54 1.47 2.28 0.62

1994 2.17 0.42 2.37 0.24 2.67 0.35 2.69 0.45 2.60 0.60 2.85 1.30 3.23 1.81 3.65 2.30 3.40 2.08 2.93 1.23 2.42 0.52 2.17 0.22

1995 1.92 0.12 2.12 0.12 2.22 0.22 2.16 0.34 2.44 0.74 2.44 1.14 3.27 2.10 3.50 2.51 3.47 2.64 3.39 2.61 2.85 1.81 2.12 0.87

1996 1.93 0.20 2.31 0.20 2.33 0.28 2.53 0.38 2.58 0.73 2.73 1.01 3.65 2.30 3.90 2.55 3.82 2.74 3.22 1.52 2.94 1.36 2.38 0.66

1997 2.38 0.40 2.52 0.26 2.62 0.41 2.63 0.55 2.82 0.76 2.88 1.16 3.68 2.30 3.79 2.15 3.53 2.37 3.25 1.54 2.53 0.83 2.13 0.38

1998 2.18 0.83 2.46 0.48 2.61 0.36 2.78 0.53 3.37 1.39 3.47 1.67 4.23 3.03 4.40 3.35 4.02 3.28 3.35 1.61 2.97 1.28 2.47 0.78

1999 2.36 0.56 2.45 0.46 2.58 0.38 2.82 0.68 2.93 0.83 3.06 1.08 3.65 2.25 4.01 2.65 4.02 2.75 3.88 2.65 3.03 1.62 2.56 0.71

2000 2.36 0.61 2.45 0.49 2.58 0.48 2.79 0.85 2.84 1.11 3.50 1.90 3.62 2.05 3.85 2.57 3.69 2.44 3.56 1.88 2.83 1.12 2.40 0.78

2001 2.24 0.44 2.24 0.34 2.33 0.62 2.58 0.27 2.44 0.77 2.96 1.17 3.10 1.27 1.57 0.14 1.70 0.20 1.34 -0.32 3.12 1.24 2.71 0.86

2002 2.46 0.39 2.75 0.42 3.02 0.49 3.09 0.62 3.37 1.22 3.62 1.82 4.02 2.57 4.25 2.87 4.07 2.63 3.92 2.14 3.21 1.52 1.88 0.08

2003 2.76 0.76 2.87 0.71 3.10 0.71 3.46 0.91 3.56 1.36 3.43 1.46 4.30 2.81 4.44 2.83 4.46 2.96 4.24 2.77 3.50 2.11 3.10 1.36

2004 2.99 1.00 2.65 0.87 3.08 1.13 3.35 1.07 3.55 1.56 3.70 2.07 4.55 3.47 4.61 2.82 4.86 3.08 4.42 3.05 3.56 1.87 3.44 1.72

No. of Data = 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21 21

Mean, X = 2.13 0.43 2.27 0.33 2.43 0.37 2.58 0.52 2.73 0.90 2.94 1.37 3.53 2.26 3.71 2.52 3.66 2.60 3.32 2.05 2.77 1.33 2.30 0.72

Stdev = 0.33 0.23 0.29 0.19 0.33 0.23 0.37 0.21 0.41 0.29 0.40 0.32 0.43 0.49 0.60 0.64 0.59 0.67 0.60 0.75 0.37 0.37 0.39 0.36

Co-eff. of Skewness = 1.19 1.02 0.32 1.4 0.8 1.96 1.12 1.3 1.0 0.8 0.6 0.9 1.1 0.5 -2.06 -2.6 -1.4 -2.40 -1.35 -1.52 0.64 0.17 1.72 0.97

Feequency:

1 in 2 2.08 0.39 2.22 0.30 2.38 0.33 2.51 0.48 2.66 0.85 2.87 1.32 3.46 2.18 3.61 2.42 3.56 2.49 3.22 1.92 2.70 1.27 2.23 0.67

1 in 2.33 2.14 0.43 2.27 0.33 2.43 0.37 2.58 0.52 2.73 0.90 2.94 1.37 3.54 2.26 3.71 2.52 3.66 2.60 3.32 2.05 2.77 1.33 2.30 0.73

1 in 5 2.37 0.59 2.48 0.47 2.67 0.54 2.84 0.67 3.03 1.11 3.22 1.60 3.84 2.61 4.14 2.98 4.08 3.08 3.75 2.59 2.65 1.60 2.58 0.99

1 in 10 2.56 0.72 2.65 0.58 2.86 0.67 3.06 0.79 3.27 1.28 3.46 1.79 4.09 2.90 4.50 3.36 4.43 3.47 4.11 3.03 3.25 1.81 2.81 1.20

1 in 20 2.74 0.85 2.81 0.69 3.05 0.80 3.26 0.91 3.50 1.44 3.68 1.97 4.33 3.17 4.84 3.72 4.77 3.85 4.45 3.45 3.46 2.02 3.03 1.40

1 in 50 2.98 1.01 3.02 0.83 3.29 0.97 3.53 1.06 3.80 1.65 3.97 2.20 4.64 3.52 5.28 4.18 5.20 4.33 4.89 3.99 3.73 2.29 3.31 1.67

1 in 100 3.15 1.13 3.18 0.93 3.47 1.09 3.73 1.18 4.02 1.81 4.19 2.37 4.9 3.79 5.61 4.53 5.5 4.69 5.21 4.40 3.94 2.49 3.52 1.86

Page 182: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 11

2.4 Surface Water

Figure 1.2: Hydrograph of (Station: Gazirhat-SW219, Nabaganga river) Study Area

The availability of surface and ground water was assessed from TR-15 of MPO and FAP 4 reports. Above Table-2.4.2 & Figure-1.2 shows the availability of surface water in the area. Moreover invert level of the regulators in peripheral embankment are quite low (-0.60 mPWD), allowing 0.64 m to 2.27m depth of water during dry season. Water can be made available in the khals through the regulators during each high tide, which can be stored in the khal for dry season irrigation by closing the C/S lift gate.

Page 183: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 12

2.5 Drainage Rate Analysis (Pre-Monsoon) Table 2.5.1 : Analysis of Drainage Rate CRITERIA: Design Storm : 20-Yr 5-Day storm recorded at the nearest Rainfall Station

Crop Damage : Sub-Project WL during design storm may not inundate more than 5% area

by depth more than 300mm for duration of more than 3 days. ASSUMPTIONS: Infiltration, Evapo-Transpiration and Depression Storage are neglected. INPUT DATA: Drainage Area (Ha.) : 9951.94 Gross Benefited Area (Ha.) : 6966.36 Lowest Ground Level/Drainage Level (mPWD) : 1.25

Allaowable Damaged Area (% of Benefited Area) : : 5.00%

Area-Elevation-Storage Data :

Elevation (m) Cum. Area (Ha.) Cum. Stor.

(Ha-m)

LGL=> 1.25 13.23 8.27

1.50 229.41 38.60

1.75 544.12 135.29

2.00 1091.18 339.70

2.25 1542.65 668.93

2.50 1813.23 1088.42

2.75 2250.00 1596.32

3.00 2602.94 2202.94

3.25 2669.12 2861.95

3.50 2704.41 3533.64

3.75 2752.94 4215.81

4.00 2757.36 4904.59

4.25 2772.06 5595.77

Design Storm Rainfall (mm): Station, Narail - CL 461 Pre - Monsoon

Days 1 2 3 4 5

Cum Depth 233 244 255 271 281

Trial Drainage Rate (mm/day): 63.00

Page 184: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 13

Table 2.5.2 : Calculations for Basin Water Level (Pre-Monsoon):

Day Cum RF (mm)

Cum DR (mm)

Cum RO (mm)

Cum. Stor. (Ha-m)

WLbasin (mPWD)

WLdam% (mPWD)

WLdam% +0.3

(mPWD)

Day with WLFull dam

100% Crop Damage (Ha.)

Design Drain. Rate

(mm/day)

1 232.75 63.00 169.75 1689.34 2.79 1.55 1.85 Day-1

2 244.11 126.00 118.11 1175.39 2.54 1.55 1.85 Day-2

3 255.45 189.00 66.45 661.31 2.24 1.55 1.85 Day-3 3.48 63.00

4 271.09 252.00 19.09 189.96 1.82 1.55 1.85 -ve

5 281.10 315.00 -33.90 -337.40 -51.00 1.55 1.85 -ve

1. A day is counted as "day with WL corresponding to full damage of allowable % of Area" if WLbasin > WLdam% +0.3 for the day.

2. If 3 consecutive days are counted to be crop damage days, crops of land corresponding to allowable % area will be considered fully damaged.

3. If count of crop damage day < 3, rivise trial drainage rate downward.

4. If count of crop damage day > 3, rivise trial drainage rate upward.

Page 185: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 14

2.6 Drainage Rate Analysis ( Monsoon )

Table 2.6.1 : Drainage Rate Analysis

CRITERIA: Design Storm : 20-Yr 5-Day storm recorded at the nearest Rainfall Station

Crop Damage : Sub-Project WL during design storm may not inundate more than 5% area

by depth more than 300mm for duration of more than 3 days.

ASSUMPTIONS: Infiltration, Evapo-Transpiration and Depression Storage are neglected.

INPUT DATA: Drainage Area (Ha.) : 9951.94

Gross Benefited Area (Ha.) : 6966.36

Lowest Ground Level/Drainage Level (mPWD) : 1.25

Allaowable Damaged Area (% of Benefited Area) : : 5.00%

Area-Elevation-Storage Data :

Elevation (m) Cum. Area (Ha.) Cum. Stor. (Ha-m)

LGL=> 1.25 13.23 8.27

1.50 229.41 38.60

1.75 544.12 135.29

2.00 1091.18 339.70

2.25 1542.65 668.93

2.50 1813.23 1088.42

2.75 2250.00 1596.32

3.00 2602.94 2202.94

3.25 2669.12 2861.95

3.50 2704.41 3533.64

3.75 2752.94 4215.81

4.00 2757.36 4904.59

4.25 2772.06 5595.77

Design Storm Rainfall (mm): Station, Narail - CL 461

Monsoon

Days 1 2 3 4 5

Cum Depth 228 245 258 262 264

Trial Drainage Rate (mm/day): 61.00

Page 186: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 15

Table 2.6.2 : Calculations for Basin Water Level (Monsoon)

Day Cum RF (mm)

Cum DR (mm)

Cum RO (mm)

Cum. Stor. (Ha-m)

WLbasin (mPWD)

WLdam% (mPWD)

WLdam% +0.3

(mPWD)

Day with WLFull dam

100% Crop Damage

(Ha.)

Design Drain. Rate

(mm/day)

1 228.10 61.00 167.10 1662.94 2.78 1.55 1.85 Day-1

2 244.70 122.00 122.70 1221.13 2.57 1.55 1.85 Day-2

3 258.05 183.00 75.05 746.84 2.30 1.55 1.85 Day-3 3.48 61.00

4 262.16 244.00 18.16 180.72 1.81 1.55 1.85 -ve

5 264.34 305.00 -40.66 -404.64 -61.17 1.55 1.85 -ve

1. A day is counted as "day with WL corresponding to full damage of allowable % of Area" if WLbasin > WLdam% +0.3 for the day.

2. If 3 consecutive days are counted to be crop damage days, crops of land corresponding to allowable % area will be considered fully damaged.

3. If count of crop damage day < 3, rivise trial drainage rate downward.

4. If count of crop damage day > 3, rivise trial drainage rate upward.

Page 187: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 16

2.7 Structural vent size Analysis The total nos. of vent (for upper and lower catchment of Linar khal) becomes 16 (14+2 & Size 1.52m x 1.82m). The total numbers of vents existing in this part of the Chenchuri Beel Sub-project are 14 meaning that another 2 vents will be constructed.

Table 2.7.1: Sizing of Regulator/Sluice

When Hw > Hv and Htw > Hv , Flow Type I QI = 0.80xNxBwxHvx(2x9.81xh')0.5

When Hw > 1.5Hv and Htw < Hv , Flow Type III QIII = 0.60xNxBvxHvx{2x9.81x(Hw-Hv/2)}0.5

When Hw < 1.5Hv and Htw >2Hv/3 , Flow Type IV

QIV = 0.83xNxBvx(Hw-h')x(2x9.81xh')0.5

When Hw < 1.5Hv and Htw <2Hv/3 , Flow Type V QV = 1.56xNxBvxHw

3/2

Where: Hw = Upstream Water Depth N = Vent Nos.

Htw = Tail Water Depth

h' = Head Difference

Hv = Vent Hieght Q = Flow through Regulator

Bv = Vent Width

Input Data:

N = 16 nos. RWL 2.48 mPWD

BV = 1.52 m Basin WL = 2.78 mPWD

HV = 1.82 m Design

Q = 83.58 m3/Sec (20% addition)

Sill Level = -

0.61 mPWD

RWL HW HTW h' Flow Type Q

(mPWD) (m) (m) (m) m3/Sec

2.48 3.39 3.09 0.30 I 85.91

85.91 OK

Drainage Rate = 63.00 mm/day ( Monsoon )

Catchment Area = 9552 ha-m ( Considering SWC-14+, SWC-16

& SWC-17+18 area )

Discharge = 69.65 cumec

The present functioning of the existing and proposed vant ( 16 nos vent )are satisfactory.

Page 188: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 17

3 BASIN OR SIP AREA WATER LEVEL 3.1 Findings

The nearest WL station is in the Gazirhat no. SW219, daily water level of Nabaganga river (Tidal river) analysis has been done and found from different return periods 1 in 2 year, 1 in 2.33 year and 1 in 5 year are 3.61m PWD, 3.70m PWD and 4.14m PWD respectively and are presented in Table 2.3.3.This WL will not control directly on SIP WL.. The rainfall of this area directly controls SIP area WL. The nearest rainfall station is in Naril no. R-461, 5-day maximum rainfall depth-duration data ( Pre-Monsoon & Monsoon ) has been done and also compute the basin water depth and drainage modulus during monsoon and found 2.78 mPWD, 61 mm/day respectively and are presented in Table-2.5.1, Table-2.5.2 & Table-3.6.1, Table-3.6.2 . Moreover checked vent size and nos and found satisfactory, shows in Table 2.7.1.Observed water level gauge had been putted in the individual SIP area, structure’s body cut-mark field Survey and depth of water above ground for individual SIP Plus Ground Level have been done and are presented in Table : 3.1.1 Table 3.1.1: Observed Water Level

SL. No.

Name of SIP

Existing Water Level

Based on Gauge reading

Based on survey of depth of water above ground for individual SIP Plus GL

Based on Cut-mark Survey

1 SWC-10+12 (Bagdanga) 3.00 2.85 2.68

2 SWC-13 (Islampur) 2.83 2.84

3 SWC-4~6,8,9+14 ( Diabari ) 2.93 2.89 2.80

4 SWC-15 (Madinar Khal) 2.97 2.93

5 SWC-16 & SWC-17+18 3.13 2.84

6 SWN- 8 (Tularumpur) - 2.81

7 SWN- 9 (Barenda) - 2.83

8 SWN- 16 (Singia) 2.48 2.41

9 SWN 17~19 (Ranagati) 2.41 2.38 2.30

10 SWN- 21 (Jamrildanga) 2.01 2.34

11 SWN- 22 (Peruli) 2.04 2.19 2.50

12 SWN 23~25 ( Ramgati ) 2.35 2.34 2.55

4 RECOMMENDATIONS AND CONCLUSIONS Water level before rehabilitation ( Pre-Project ) 2.81 mPWD and after rehabilitation ( Post Project ) 2.51 mPWD have suggested for SIP (SWC-16 & SWC- 17+18) by PMO and consultants ISPMC on 16 January 2011. This WL 2.81 mPWD is justified because observed gauge reading is 3.13 mPWD, depth of water above ground plus Ground Level is 2.84 mPWD and calculated basin water level at monsoon is 2.78 mPwd, those all are nearest to 2.81 mPWD.

Page 189: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-G

SWC-17+18; Noagram-Gazaria Scheme 18

5. BENEFITS OF THE PROPOSED INTERVENTIONS The expected benefits of the proposed interventions have been estimated using the findings of the hydrological analysis in terms of anticipated change in cropping patterns coverage in the study area. The benefit that has been found from the analysis seems to be very significant and encouraging. The anticipated changing land use patterns of SIP SWC-17+18 is given in Table 5.1 and graphically shown in Figure 5.1. It has been seen that F0 and F1 (productive land) land would be increased after proposed rehabilitation condition from 622.24 ha to 844.70 ha and 534.29 ha to 543.36 ha respectively. On the other hand, the F2 and F3 (deeply inundated land) lands will be decreased significantly. Table 5.1: Types of land under different inundation depth

Land Type Existing condition

Area (ha) After proposed rehabilitation

Area(ha) Remarks

F0 (d<0.3m) 622.24 844.70

F1 (0.3m<d<0.9m) 534.29 543.36

F2 (0.9m<d<1.8m) 313.77 82.53

F3 (d>1.8m) 0.29 0.00

0.00

200.00

400.00

600.00

800.00

Area (ha)

Existing condition Area (ha) 622.24 534.29 313.77 0.29

After proposed rehabilitation

Area(ha)

844.70 543.36 82.53 0.00

F0 (d<0.3m)F1

(0.3m<d<0.9m)

F2

(0.9m<d<1.8m)F3 (d>1.8m)

Figure 5.1: Changing land classes expected due to proposed interventions

Page 190: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

ANNEX-H

TRAINING

Page 191: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Training

Introduction:

The concept of Southwest Area Integrated Water Resources Planning and Management Project

(SAIWRPMP) is a new idea totally based on participation of beneficiaries / stakeholders in all phases

of planning, design, implementation and operation & maintenance cycle of the project. Moreover the

concept includes transfer of management to the stakeholders after completion of the rehabilitation

works of the project.

Plan

Training components have been incorporated for capacity development of the a) Officers of PMO,

SMOs, Line Agencies and the NGO Supervisor & Facilitators (Staff training) and b) Members of the

WMOs (WMO training) of Southwest Area Integrated Water Resources Planning and Management

Project (SAIWRPMP). In this process a total of 389 Nos. of training programs have been planned to

implement during 2009-2010, 2010-11, 2011-12 and 2012-13 to train up the officers of PMO / SMOs,

District / Upazilla level officers of line agencies, Facilitators of NGO (ASG), WMG members and other

beneficiaries of the project. Staff training – 42 & WMO training –347. Detailed Training plan

annexed in Tables.

Achievement

A total of 117 trainings have so far been imparted on (a) Drafting of Bylaw for WMG (b) Registration

procedures for WMG. ,(c) Procedure of Book Keeping for WMG, (d) Operation and Maintenance of

infrastructure through participatory water management , (e) Plantation Activities and Vegetable

Gardening in SAIWRPMP , (f) Cultivation Procedure of different crops and Vegetables gardening , (g)

Seed Production & Compost Preparation, (h) Poultry, Cow and Goat Rearing for Collective Action

Plan (CAP) in SAIWRPMP, (i) Meaning and Functions of WMG/ WMA/JMC in SAIWRPMP, (j) Basic

training on Carp poly-culture in SAIWRPMP area, (k) Basic training on GIFT (Tilapia) culture in

SAIWRPMP area, (l) Field Training and sharing experiences of High value crop production, (m)

Field Training and sharing experiences of CAP, (o) LCS Training For WMG members , (p) Gender

awareness for the WMG members,(q) Salinity of surface water and its safe use, (r) Multi disciplinary

delineation, planning and implementation of a sub-unit of SAIWRPM, (s) On-Job training on

delineation, planning and other related matters for implementation of a sub-unit of SAIWRPMP, (t)

Orientation Workshop of the newly recruited Facilitators and others, (u) Induction course on

preparation of SIP and formation of WMO , (u) Hydrography, Topography Survey & Data processing

by GIS, (v) Communication Tools and Techniques, (w) Workshop on “Participatory Action Plan for

Preparation of SIP and Formation of WMO, (x) Feedback training on “Participatory Action Plan for

Preparation of SIP and Formation of WMO, (y) Formation of WMO and Laws of Cooperative and (z)

Workshop on Micro Credit Management of SAIWRPMP etc. The rest 272 training courses will be

imparted during the next two and a half year.

Besides the above training there are some Foreign trainings and lots of Demonstrations on Fisheries

and Agriculture area.

Page 192: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Southwest Area Integrated water Resources planning and Management Project

Implemented Training Activities during 2009-2010 Staff Training (2009-10) Part-A

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

01/2009

-10

Formation of WMO,

Rules of

cooperatives,

Formation procedure

and activities of LCS.

Zilla

Parishad

Auditorium

, Narail

2 days

(8-9

Sept,09)

NGO Supervisor,

Facilitators &

Extension

Overseers of

BWDB

17(Male-13,

Female-4)

34 18,840.00 TL of ISPMC ,

WMA Specialist of ISPMC

District Co-Operative Officer, Narail and

EE,DP-3, (IPSWAM) BWDB, Dhaka

02/2009

-10

Formation of WMO,

Rules of co-

operatives,

Formation procedure

and activities of LCS.

Zilla

Parishad

Auditorium

, Narail

2 days (14 -

15 Sept,09)

Officers of PMO

& SMOs and

ED,NGO(ASG)

12( Male-12,

Female-0)

24 18,940.00 TL of ISPMC ,

WMO Specialist of ISPMC

District Co-Operative Officer, Narail and

EE,DP-3, (IPSWAM) BWDB, Dhaka

05/2009

-10

Basic Fisheries

Extension and Semi

intensive carf

Polyculture.

Zilla

Parishad

Auditorium

, Narail

3 days (03 -

05 Nov.,09)

Officers of

Fisheries

Department,

Officers of PMO ,

Officers of SMO

and NGO

Facilitator(Fish)

13( Male-11,

Female-2)

39 27,250.00 DTL,WMO Specialist and Fisheries Specialist of

ISPMC ,

Deputy Chief(Fishery),Dte of Planning-

3(IPSWAM),BWDB,Dhaka

,District Fisheries Officer, Narail and

Senior Scientific Officer ,BFRI, Jessore.

06/2009

-10

Water Management

of Different Crops,

Green Manuring and

Compost

preparetion"

Zilla

Parishad

Auditorium

, Narail

3 days (09 -

11

Nov.,2009)

Officers of

Department of

Agriculture

Extension,

Officers of PMO,

Officers of SMO

and NGO

Facilitators (Ag.)

13( Male-13,

Female-0)

39 28,200.00 DTL and Agriculture Development Specialist of

ISPMC ,

Deputy Director, DAE, Narail ,

Crop Production Specialist , DAE , Narail and

Plant Protection Specialist,DAE ,Narail.

Page 193: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

12/2009

-10

Guide Lines on

Gender and

Development

Zilla

Parishad

Auditorium

, Narail

3 days(19-21

January,201

0)

Officers of line

agencies,NGO

Supervisor and

NGO Facilitator.

13(Male-8

Female-5)

39 28,450.00 Dr. Rokeya Khatun (ADB),

Mr.A.Kashem (IPSWAM),

Dist. Women Affairs Officer and

Ms. Tajkera Khair (GL Specialist,)

20/2009

-10

Financial

Management for

SAIWRPMP

BWDB

Conferenc

e

room,Motij

heel,Dhak

a

2 days(14-15

March,2010)

Officers of

PMO,SMOs,RAC,

Dte of Finance,

Dte of Accounts

and Dte of Audit.

23(Male-22

Female-1)

46 100,000.00

(Expenditure

made from

consultant’s

budget fund)

Mr.Zahirul Islam(PD,SAIWRPMP)

Mr.R.Roostee(TL,ISPMC)

Mr.Alexandar Fox(Procurement

Specialist,ADB,BRM,Dhaka)

Mr.M.A. Ahad(Head of Disbursement,

ADB,BRM,Dhaka)

Mr.Zakirul Islam,(Director,

Finance,BWDB,Dhaka)

Mr.Rezaul Karim,(Director, Audit,BWDB,Dhaka)

Mr.Ataul Karim(Financial Adviser,ISPMC)

Page 194: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

30/2009

-10

Participatory

Integrated Water

Resources

Management.

CEGIS

Conferenc

e

Room,Guls

han,Dhaka

4days(14-

17

June,2010)

Officers of PMO,

Officers of SMOs,

NGO Superviser,

NGO Facilitators,

37(Male-29 +

Female-8)

148 666,626.00

(Expenditure

made from

consultant’s

budget fund)

Mr.Giasuddin Ahmed Choudhury, Executive

Director,CEGIS,Dhaka

Prof. Abdul Matin,BUET,Dhaka

Dr.Musfiqus Salehin, Prof.,IWMF, BUET, Dhaka

Mr.Ahmadul Hassan, Director, Research

Development and Training

Division,CEGIS,Dhaka

Mr.Wazi Ullah,Deputy Executive Director

,CEGIS,

Mr.H.S.Mozaddad Faruque, WR Expart,

CEGIS,

Mr.Mujibul Huq, Environmental Advisor, CEGIS,

Mr.Md.A. Rashid, Agriculture Engineer, CEGIS,

Mr.Sultan Ahmed, , Director, Business

Development Division, CEGIS,Dhaka

Dr.Dilruba Ahmed, , Director, Socio-economic

Division, CEGIS,Dhaka

Mr.Ehsan Hafiz Chowdhury, Director, Database

and IT Division, CEGIS,Dhaka

Mr.Mahfuzur Rahman,Executive Engineer,

CDSP,BWDB,Dhaka

Mr.Nityananda Chakravorty, Socio-economic

Advisor, CEGIS,Dhaka

Mr.Maminul Haque Sarker, Deputy Executive

Director(Development), CEGIS,Dhaka

Dr.Sujit Bala, Prof.,IWMF, BUET, Dhaka

Mr.Malik Fida Abdulla Khan, Director, Climate

Change Division, CEGIS,Dhaka

Sub-Total (A)

2009-10

128(male-108,

female-20)

369 888,306.00

Page 195: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

WMO Training (2009-10)

Part-B

Course No. Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

03/2009-10 Drafting of Bylaw

for WMG

(Batch-1)

Proshika

Auditorium

, Narail

2 days

(13-14

Oct.,09)

WMG Members of

SIP - 8

21( Male-14,

Female-7)

42 23,395.00 TL of ISPMC,

WMO Specialist of ISPMC

District Co-Operative Officer, Narail and

Upazilla Co-Operative Officer, Narail.

04/2009-10 Drafting of Bylaw

for WMG

(Batch-2)

Proshika

Auditorium

, Narail

2 days

(19-20

Oct.,09)

WMG Members of

SIP - 8 &9

27(Male-18,

Female-9)

54 26,055.00 TL of ISPMC,

WMO Specialist of ISPMC

District Co-Operative Officer, Narail and

Upazilla Co-Operative Officer, Narail.

07/2009-10 Registration

Procedure for

WMG Member

(Batch-1)

Proshika

Auditorium

, Narail

2 days (9 -

10 Dec,09)

WMG Members (

Chairman,Vice-

Chairman and

Cashier of SIP - 8

and 9)

24( Male-24+

Female-0)

48 26,000.00 TL&WMO Specialist of ISPMC,

District Co-Operative Officer, Narail and

Upazilla Co-Operative Officer, Narail.

08/2009-10 Registration

Procedure for

WMG Member

(Batch-2)

Proshika

Auditorium

, Narail

2 days (13

- 14

Dec,09)

WMG Members (

Chairman,Vice-

Chairman and

Cashier of SIP - 8

and 9)

24(Male-22

+Female-2) =

48

48 26,000.00 TL&WMO Specialist of ISPMC,

District Co-Operative Officer, Narail and

Upazilla Co-Operative Officer, Narail.

09/2009-10 Plantation

Activities and

Vegetable

Gardening.

(Batch-1)

Proshika

Auditorium

, Narail

2 days (23

- 24

Dec,09)

WMG Agriculture

Committee

Members ( SIP -

8 and 9)

24( Male-15+

Female-9)

48 26,550.00 Agriculture Extention Specialist of ISPMC ,

Upazila Agriculture Officer,Narail

, Upazilla Agriculture Officer, Lohagora,

Agriculture Extension officer ,DAE, Narail

and

Sub- Asstt. Agriculture Officer.

Page 196: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course No. Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

10/2009-10 Operation and

Maintenance of

Infrastructure

through

participatory water

management(Batc

h-1)

Proshika

Auditorium,

Narail

2 days (11-

12 January,

2010)

WMG Members (

O&M sub-committee

SIP - 8 )

21( Male-14+

Female-7)

42 22,900.00 Team Leader, ISPM consultant

Deputy Team Leader, ISPM consultant

Water management specialist , ISPM consultant

,O&M specialist, ISPM consultant and

Quality control specialist of ISPM consultant

11/2009-10 Operation and

Maintenance of

Infrastructure

through

participatory water

management(Batc

h-2)

Proshika

Auditorium,

Narail

2 days (13-

14 January,

2010)

WMG Members (

O&M sub-committee

SIP - 8 and 9)

24(Male-16

+Female-8

48 24,100.00 Team Leader, ISPM consultant

Deputy Team Leader, ISPM consultant

Water management specialist , ISPM consultant

,O&M specialist, ISPM consultant and

Quality control specialist of ISPM consultant

13/2009-10 Plantation

Activities and

Vegetable

Gardening. (Batch-

2)

Proshika

Auditorium,

Narail

2 days (26 -

27 January,

2010)

WMG Agriculture

Committee

Members ( SIP - 8

and 9)

21( Male-12+

Female-9)

42 27,350.00

Agriculture Extension Specialist of ISPMC ,

Upazila Agriculture Officer,Narail

,Upazilla Agriculture Officer, Lohagora,,

Agriculture Extention officer,DAE,Narail and

Sub- Asstt. Agriculture Officer.

14/2009-10 Semi Intensive

carp Polyculture.

(Batch-1)

Proshika

Auditorium,

Narail

2 days (8-9

February,

2010)

WMG Members (

Fisheries sub-

committee SIP - 8 )

24( Male-16+

Female-8)

48 26,650.00 Mr.Md.Abbdul Wadud, District Fisheries

Officer,Narail,

Mr.Enamul Hoque, Upazila Fisheries

Officer,Narail Sador,Narail and

Ms.Hosneara Happy, Upazila Fisheries

Officer,Lohagora,,Narail,

15/2009-10 Semi Intensive

carp Polyculture.

(Batch-2)

Proshika

Auditorium,

Narail

2 days (10-

11

February,

2010)

WMG Members

(Fisheries sub-

committee SIP - 8

and 9)

24(Male-19

+Female-5)

48 26,650.00 Mr.Md.Abbdul Wadud, District Fisheries

Officer,Narail,

Mr.Enamul Hoque, Upazila Fisheries

Officer,Narail Sador,Narail and

Ms.Hosneara Happy, Upazila Fisheries

Officer,Lohagora,,Narail,

Page 197: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course No. Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

16/2009-10 Seed production

and Compost

preparation.

(Batch-1)

Proshika

Auditorium,

Narail

2 days(22-

23

February,

2010)

WMG Members (

Poor and

Vulnerable women

of the project

beneficiaries SIP -

8 )

24(Male-0

Female-24)

48 26,700.00 Mr.Md.Ruhul Amin, , Upazila Agriculture

Officer,Narail Sador,Narail

,Mr.Mohadev Chandra Sana,Agricuture Extension

Officer,Kalia,Narail and

Mr.Badal Chandra Biswas, SAAO, Tularampur

UP.

17/2009-10 Seed production

and Compost

preparation.

(Batch-2)

Proshika

Auditorium,

Narail

2 days (24 -

25

February,

2010)

WMG Members

(Poor and

Vulnerable women

of the project

beneficiaries SIP –

8 & 9 )

24( Male-0+

Female-24)

48 27,450.00 Mr.Md.Ruhul Amin, , Upazila Agriculture

Officer,Narail Sador,Narail,

Mr. Kingkor Chandra Das, Upazila Agriculture

officer,Kalia,Narail

, Mr.Mohadev Chandra Sana, Agricuture

Extension Officer, Kalia, Narail. And

Mr.Zakir Hossain, SAAO, Korola UP.

18/2009-10 Poultry,Goat and

Cow

rearing(Batch-1)

Proshika

Auditorium,

Narail

2 days (8-9

March,

2010)

WMG Members (

Poor and

Vulnerable women

of the project

beneficiaries SIP -

8 )

24( Male-0+

Female-24)

48 27,650.00

Dr.Ali Akbar Mia(DLO,Narail)

Dr.Pizush Kanti Ghosh(TLO,Narail)

Dr.Sushen Haldar(Veterinary Surgeon, Narail)

19/2009-10 Poultry,Goat and

Cow

rearing(Batch-2)

Proshika

Auditorium,

Narail

2 days (10-

11

March y,

2010)

WMG Members (

Poor and

Vulnerable women

of the project

beneficiaries SIP –

8 & 9 )

24(Male-

0+Female-24)

48 27,650.00 Dr.Ali Akbar Mia(DLO,Narail)

Dr.Pizush Kanti Ghosh(TLO,Narail)

Dr.Sushen Haldar(Veterinary Surgeon, Narail)

Page 198: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course No. Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

21/2009-10 Book keeping for

WMG

(SIP-8)

Proshika

Auditorium,

Narail and

Field visit

3 days (22 -

24

March,2010

)

Secretary, Cashier

and one signatory

member of the

WMG Executive

Committee.

24( Male- 22 +

Female- 2)

72 38,750.00 District Cooperative Officer, Narail.

Mr.Md.Hassan Mahmood, DAR, Office of the

District Cooperative Officer, Narail

Mr.Biraj Mohon Kundu, Upazila Cooperative

Officer, Narail Sador, Narail.

Mr.Tarikul Islam, Inspector, Office of the District

Cooperative Officer,

Mr.Shah Ahmed Ali Khan,WMA Specialist, ISPMC

22/2009-10 Book keeping for

WMG

(SIP-8&9)

Proshika

Auditorium,

Narail and

Field visit

3 days (29 -

31

March,2010

)

Secretary, Cashier

and one signatory

member of the

WMG Executive

Committee.

24( Male-19 +

Female- 5 )

72 38,750.00 District Cooperative Officer, Narail.

Mr.Md.Hassan Mahmood, DAR, Office of the

District Cooperative Officer, Narail

Mr.Biraj Mohon Kundu, Upazila Cooperative

Officer, Narail Sador, Narail.

Mr.Tarikul Islam, Inspector, Office of the District

Cooperative Officer,

Mr.Shah Ahmed Ali Khan,WMA Specialist, ISPMC

23/2009-10 Gender Awareness

for WMG Members

of NSP SIP -8

Proshika

Auditorium,

Narail

2 days (11-

12

April,2010)

WMG Members of

NSP SIP -8

24( Male-6+

Female-18)

48 25,450.00 Mr.Md.Ataul Hoque,DTL,ISPMC

Mr.Md.Lutfar Rahman, EE/SMO, Narail Sub-

Project,BWDB,Narail.

Mr.Shah Ahmed Ali Khan,WMA Specialist,ISPMC

Mrs. Mousumi Biswas, District Women Affairs

Officer,Narail.

Mr.Uttam Kumar Goldar ,Supervisor,NGO(ASG)

Mr.Bidhan Goldar ,Facilitator,NGO(ASG)

24/2009-10

Gender Awareness

for WMG Members

of NSP SIP -8 & 9

Proshika

Auditorium,

Narail

2 days (20-

21

April,2010)

WMG Members of

NSP SIP -8 & 9

24( Male-6+

Female-18)

48 25,450.00 Mr.Md.Ataul Hoque,DTL,ISPMC

Mr.Md.Lutfar Rahman, EE/SMO, Narail Sub-

Project, BWDB, Narail.

Mr.Shah Ahmed Ali Khan,WMA Specialist,ISPMC

Mrs. Mousumi Biswas, District Women Affairs

Officer, Narail.

Mr.Uttam Kumar Goldar ,Supervisor,NGO(ASG)

Mr.Bidhan Goldar ,Facilitator,NGO(ASG)

Page 199: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course No. Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

25/2009-10 Salinity of

surface water

and its safe use

Proshika

Auditorium

, Narail

2 days(3 -

4

May,2010)

WMG Members of

NSP SIP -8

(comparatively big

size farmer)

24( Male-24+

Female-0)

48 25,450.00 Mr.Md.Lutfar Rahman, EE/SMO, Narail Sub-

Project, BWDB, Narail.

Mr.Abu Bakar Siddique, Environmental

Specialist,ISPMC

Mr.King Kor Chandra Das, Upazila

Agriculture Officer, Kalia, Narail.

Mr.Raghu Nath Kar,Mr. Upazila Agriculture

Officer,Lohagora,Narail

Mr.Ruhul Amin, Upazila Agriculture Officer,

DAE, Narail Sador,Narail

26/2009-10 Salinity of

surface water

and its safe use

Proshika

Auditorium

, Narail

2 days(5 -

6

May,2010)

WMG Members of

NSP SIP -8 & 9

(comparatively big

size farmer)

24( Male-23+

Female-1)

48 25,450.00 Mr.Dipak Kumar Sarkar, EE/SMO, Chenchuri

Beel Sub-Project, BWDB, Narail.

Mr.Abu Bakar Siddique, Environmental

Specialist,ISPMC

Mr.King Kor Chandra Das, Upazila

Agriculture Officer, Kalia, Narail.

Mr.Raghu Nath Kar,Mr. Upazila Agriculture

Officer,Lohagora,Narail

Mr.Ruhul Amin, Upazila Agriculture Officer,

DAE, Narail Sador,Narail

27/2009-10 Refresher course

on O&M of

infrastructure

through

participatory

water

management

Proshika

Auditorium

, Narail

2 days(19

- 20

May,2010)

WMG members

(Chairman,

Secretary and 3

other members of

each WMG) of

NSP SIP-

9(5WMG).

25( Male-20+

Female-5)

50 24,700.00 Mr.Zahirul Islam,Project Director

,SAIWRPMP,BWDB,Jessore

Mr.M.H.Siddique,Water Resources Planner,

ISPMC.

Mr. Md. Lutfar Rahman, SMO /EE, Narail

Sub-project, BWDB, Narail.

Mr.Manzurul Karim, O&M Specialist , ISPMC

Mr.Abdur Razzaque,EE, Office of the PMO,

SAIWRPMP

Mr.Ataul Huq,,DTL,ISPMC

Mr. Shah A.A.Khan,WMA Specialist,ISPMC

Page 200: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course No. Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource person

28/2009-10 Refresher course

on O&M of

infrastructure

through

participatory

water

management

Proshika

Auditorium

, Narail

2 days(23

- 24

May,2010)

WMG members

(Chairman,

Secretary and 3

other members of

each WMG) of

NSP SIP-

8(5WMG).

25(Male-21+

Female-4)

50 24,700.00 Mr.Zahirul Islam, Project Director,

SAIWRPMP, BWDB, Jessore.

Mr.M.H.Siddique, Water Resources Planner,

ISPMC.

Mr. Dipak Kumar Sarkar, SMO /EE,

Chenchuri Beel Sub-project, BWDB, Narail.

Mr.Manzurul Karim, O&M Specialist , ISPMC

Mr.Abdur Razzaque,EE, Office of the PMO,

SAIWRPMP

Mr.Ataul Huq,,DTL,ISPMC

Mr. Shah A.A.Khan,WMA Specialist,ISPMC

29/2009-10 Refresher course

on O&M of

infrastructure

through

participatory

water

management

Proshika

Auditorium

, Narail

2 days(25

- 26

May,2010)

WMG members

(Chairman,

Secretary and 3

other members of

each WMG) of

NSP SIP-

8(6WMG).

30( Male-24+

Female-6)

60 27,100.00 Mr.Zahirul Islam,Project Director

,SAIWRPMP,BWDB,Jessore

Mr.M.H.Siddique, Water Resources Planner,

ISPMC.

Mr. Md. Lutfar Rahman, SMO /EE, Narail

Sub-project, BWDB, Narail.

Mr.Manzurul Karim, O&M Specialist , ISPMC

Mr.Fakrul Abedin,EE, Office of the PMO,

SAIWRPMP

Mr.Ataul Huq,,DTL,ISPMC

Mr. Shah A.A.Khan,WMA Specialist,ISPMC

Sub-total(B) 554(Male-335,

Female-219)

1156 620,900.00

Grant

Total(A+B)

For 2009-10

682(Male-

443+ Female-

239)

1525 1509,206.00

Page 201: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Southwest Area Integrated water Resources planning and Management Project Implemented Training Activities during 2010-2011

Part-A (Staff Training) 2010-11

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

01/

2010-11

Multi disciplinary

delineation, planning

and implementation of

a sub-unit of

SAIWRPMP

CEGIS conference

room,Gulshan,

Dhaka.

4 days (2-5

August,2010)

Officers of PMO,

SMOs and NGO

(ASG).

29( Male-27

Female-02)

116 666,000.00

(Expenditure

incurred from

consultant’s

training fund)

Mr.Giasuddin Ahmed Choudhury, Executive Director,CEGIS,Dhaka

Prof. Abdul Matin,BUET,Dhaka

Mr.Wazi Ullah,Deputy Executive Director(Operation),CEGIS , Dhaka

Mr.H.S.Mozaddad Faruque, WR Expart, CEGIS,Dhaka

Mr.Mujibul Huq, Environmental Advisor, CEGIS,Dhaka

Mr.Nityananda Chakravorty, Socio-economic Advisor, CEGIS, Dhaka

Mr.Ataul Huq and Mr.M.H.Siddiquee,ISPMC

02/

2010-11

On-Job training on

delineation, planning

and other related

matters for

implementation of a

sub-unit of

SAIWRPMP

BACHTE

SHEKHA

Conference room,

Arabpur, Jessore.

3 days ( 1-3

September,2010)

Officers of PMO,

SMOs and NGO

(ASG).

30( Male-30

Female-00)

90 60,000.00

(Expenditure

incurred from

consultant’s

training fund)

Mr.Zahirul Islam, Project Director,SAIWRPMP

Mr.Zahangir Islam, DCA, SAIWRPMP

Mr.Md.Masud Karim,DCEO, PMO

Mr.Mahbubar Rahman,EE, PMO

Mr.Abdur Razzak,AC(F), SAIWRPMP

Mr.R.F.Roostee,TL,ISPMC

Mr.Ataul Huq , ISPMC

Mr.M.H.Siddiquee,ISPMC

Mr.Shah Ahammed Ali Khan, ISPMC

Mr.Monzurul Karim,ISPMC

Dr.Rezaul Karim,ISPMC

Dr.Shamsul Huda,ISPMC

Page 202: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

03/

2010-11

Hydrography,

Topography Survey &

Data processing by

GIS.

BWDB Rest

House,

Narail

4 days ( 21-24

October,2010)

SDEs, AE and SAE

of PMO/SMO .

07( Male-07

Female-00)

28 27,500.00

Mr.Md.Fakrul Abedin, Executive Engineer, Office of the PMO, SAIWRPMP

Mr.Md.Amirul Islam, Executive Engineer, Office of the Chief Monitoring, BWDB, Dhaka.

04/

2010-11

Communication Tools

and Techniques.

BACHTE

SHEKHA

Auditorium,

Arabpur, Jessore

3 days(30.10.10

to 01.11.10)

Officers of PMO,

Extension Overseers

and Facilitators

35(Male-28

Female-07)

105 5,88,000.00

(Expenditure

incurred from

consultant’s

training fund)

Mr.Zahirul Islam, Project Director, SAIWRPMP

Mr.Md.Masud Karim,,DCEO, PMO

Mr.Giasuddin Ahmed Choudhury, Executive Director, CEGIS,Dhaka.

Mr.Md. Wazi Ullah,,Deputy Executive Director (Operation), CEGIS , Dhaka.

Dr. Hamidul Hoque,…., Institute of Livelihood Studies,Dhaka.

Dr.M.A.Matin, Professor, BUET, Dhaka.

Dr.Md. Rezaul Karim,AE Specialist,ISPMC,SAIWRPMP

05/

2010-11

Orientation Workshop

of the newly recruited

Facilitators and others

BACHTE

SHEKHA

Auditorium,

Arabpur, Jessore

1day(03.11.10) Newly recruited

Facilitators and

others

51(Male-44

Female-7)

51 16,000.00

(Expenditure

incurred from

consultant’s

training fund)

Mr.Zahirul Islam, Project Director, SAIWRPMP

Mr.Zahangir Islam, DCA, SAIWRPMP

Mr.Mahbubar Rahman,EE, PMO .

Mr.Abdur Razzak,AC(F), SAIWRPMP

Mr.R.F.Roostee,TL,ISPMC

Mr.Ataul Huq , DTL,ISPMC

Mr.Shah Ahammed Ali Khan, ISPMC

Mr.Monzurul Karim,ISPMC

Dr.Shamsul Huda,ISPMC

Dr.Md. Rezaul Karim,ISPMC

Page 203: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

06/

2010-11

Induction course on

preparation of SIP and

formation of WMO

BACHTE

SHEKHA

Auditorium,

Arabpur, Jessore

3days

(10-12Nov.10)

Newly recruited

Facilitators and

others

35(Male-30

Female-5)

105 98,480.00 Mr.Md.Abdur Razzque,EE, PMO

Mr.Zahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Mahbubar Rahman,EE, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr.Md.Hafizur Rahman,EO, PMO

Mr.Md.Lutfor

Rahman,EE/SMO,Narail

Mr.Hasan Mahmood,DAR,Office of

the Dist.Cooperative Officer,Narail

Upazila Cooperative officer, Kalia,

Narail

Mr.Shah Ahammed Ali Khan,

ISPMC

Mr.Monzurul Karim,ISPMC

Dr.Shamsul Huda,ISPMC

Dr.Md. Rezaul Karim,ISPMC

Mr.Md.Aminul Karim,PMO

07/

2010-11

Orientation Workshop

of the newly recruited

Facilitators of

NGO(ASG) and others

Proshika

Auditorium, Narail

1day(22.11.10) Newly recruited

Facilitators of

NGO(ASG) and

others

15(Male-12

Female-3)

15 - Mr.Zahangir Islam, DCA, PMO

Mr.Md.Abdur Razzaque,EE, PMO

Mr.Masud Karim,

DCEO,SAIWRPMP

Mr.Md.Hafizur Rahman,EO, PMO

Mr.Abdur Razzak,AC(F),

SAIWRPMP

Page 204: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

08/

2010-11

Induction course on

preparation of SIP and

formation of WMO

Proshika

Auditorium, Narail

2days (25 and

27 Nov.10)

Newly recruited

Facilitators of NGO

and others

15(Male-12

Female-3)

30 41,050.00 Mr.Md.Abdur Razzque,, EE, PMO

Mr.Zahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Md.Lutfor Rahman,EE, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr.Md.Hafizur Rahman,EO, PMO

Mr.Biddut Kumar Shaha, EE/

SMO,Chenchury Beell Sub-project,

Mr.Hasan Mahmood,DAD,Office of

the Dist.Cooperative Officer,Narail

Mr.R.F.Roostee,TL,ISPMC

Mr.Ataul Haq,DTL,ISPMC

Mr.Shah Ahammed Ali Khan,

ISPMC

Mr.Monzurul Karim,ISPMC

Dr.Shamsul Huda,ISPMC

Dr.Md. Rezaul Karim,ISPMC

Mr.Md.Aminul Karim,ISPMC

09/

2010-11

Workshop on

Participatory Action

Plan

BANCHTE

SHEKHA

Auditorium,

Arabpur, Jessore

3days

(28 + 29 Nov. +

01 Dec..,10)

Officers of PMO and

Newly recruited

Facilitators and

others of PMO and

NGO

85(Male-68

Female-17)

255 200,000.00

(Expenditure

incurred from

consultant’s

training fund)

Mr.Md.Abdur Razzque,EE, PMO

Mr.Zahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Md.Lutfor Rahman,EE, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr.Md.Hafizur Rahman,EO, PMO

Mr.R.F.Roostee,TL,ISPMC

Mr.Ataul Haq,DTL,ISPMC

Mr.Shah Ahammed Ali Khan, ISPMC

Mr.Monzurul Karim,ISPMC

Dr.Shamsul Huda,ISPMC

Dr.Md. Rezaul Karim,ISPMC

Dr.C.M.Wijayaratna, Int.WMA Specialist

Mr.Abu Bakor Siddique

Page 205: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

16/

2010-11

Feedback training on

“Participatory Action

Plan for Preparation of

SIP and Formation of

WMO”

Bachte Shekha

Auditorium,

Arabpur, Jessore

2days (23&25

December,

2010.)

Facilitators and

others of PMO and

NGO

84(Male-66

Female-18)

168 1,34,850.00 Mr.Md.Abdur Razzque,EE, PMO

Mr.Zahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr.R.F.Roostee,TL,ISPMC

Mr.Ataul Haq,DTL,ISPMC

Mr.Shah Ahammed Ali Khan, ISPMC

Dr.Shamsul Huda,ISPMC

Dr.Md. Rezaul Karim,ISPMC

23/

2010-11

2nd Feedback training

on “Preparation of SIP

and Formation of

WMO”

Zila Parisad

Auditorium, Narail.

1day

(15.01.2011)

Officers of

PMO,Facilitators of

PMO and NGO

94(Male-77

Female-17)

94 74,650.00 Mr.Zahirul Islam,PD,SAIWRPMP

Mr.Md.Fakhrul Abedin, EE, Office of the PD,SAIWRPMP

Mr.Md.Didarul Islam, IWM.

Mr.R.F.Roostee,TL,ISPMC

58/

2010-11

Formation of WMO

and Laws of

Cooperative

Banchte Shekha

Auditorium,

Arabpur, Jessore

2 days

(04-05 May,

2011)

Officers of

PMO,Facilitators of

PMO and NGO

51( Male-42

Female-9)

102 91,750.00 Mr. Shah Ahmed Ali Khan, WMA. Specialist, ISPMC

Mr. Samir Kumar Biswas, Joint Registrar of Cooperatives, Khulna

Mr.Md.Jahangir Alam,Dist. Cooperative Officer,Narail

Ms. Pronati Bisnu, Dist.Cooperative Officer, Jessore

Mr. Mobarak Ali Talukdar, Cooperative Specialist, ISPMC

59/

2010-11

Formation of WMO

and Laws of

Cooperative

Banchte Shekha

Auditorium,

Arabpur, Jessore

2 days

(08-09 May,

2011)

Officers of

PMO,Facilitators of

PMO and NGO

51( Male-42

Female-9)

102 91,750.00 Mr. Shah Ahmed Ali Khan, WMA. Specialist, ISPMC

Mr. Samir Kumar Biswas, Joint Registrar of Cooperatives, Khulna

Mr.Md.Jahangir Alam,Dist. Cooperative Officer,Narail

Ms. Pronati Bisnu, Dist.Cooperative Officer, Jessore

Mr. Mobarak Ali Talukdar, Cooperative Specialist, ISPMC

Page 206: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

86/2010-

11

Workshop on Micro

Credit Management of

SAIWRPMP

Banchte Shekha

Auditorium,

Arabpur, Jessore

1 day

(30 June,2011)

Officers of PMO,

RA,SF,CF and

WMCA president

72( Male-70

Female-2)

72 58,750.00 Mr.Mobarak Ali Talukdar, Cooperative Specialist, ISPMC

Mr.Zahangir Islam, DCO,Narail

Ms. Pronoti Bisnu, DCO,Jessore

Total(Staff

Training) Part –

A(2010-11)

Total Course = 14 654( Male

555+

Female-99)

1333 2148,780.00

Page 207: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Part-B (WMO Training) (2010-11)

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

10/

2010-11 Drafting of Bylaw

for WMG

Union parisad

auditorium,

Purulia U.P.

3days(07-09

Dec.,2010)

WMG Members of

(CSP/SIP:16-18) WMG

# 16/1, 16/2, 16/3, 16/4

and 16/5

31(Male-21

Female-10)

93 97,150.00 Mr.Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the PD,SAIWRPMP

Mr.Md.Hafizur Rahman,EO, Office of the PD,SAIWRPMP

Mr.Jahangir Alam, Dist. Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Mudasser Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr.R.F.Roostee,TL,ISPMC

Mr.Shah Ahammed Ali Khan, ISPMC

11/

2010-11 Cultivation

Procedure of

different crops and

Vegetables

gardening

Union parisad

auditorium,

Babra-Hasla

U.P.

3days(07-09

Dec.,2010)

WMG Members of

(CSP/SIP:16-18) WMG

# 16/1, 16/2, 16/3, 16/4

and 16/5

31(Male-20

Female-11)

93 98,200.00 Mr.Zahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the PD,SAIWRPMP

Deputy Director, DAE, Narail.

Mr.King Kor Chandra Das, Upazila Agriculture Officer, Kalia, Narail.

Upazila Agriculture Officer, Narail.

SAAO (BS), Purulia Block, Kalia, Narail.

Mr.Ataul Haq,DTL,ISPMC

Dr.Rezaul Karim, ISPMC

Page 208: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

13/

2010-11 Cultivation

Procedure of

different crops and

Vegetables

gardening.

Union parisad

auditorium,

Babra-Hasla

U.P.

3days(14+15+17

Dec.,2010)

WMG Members of

(CSP/SIP:16-18) WMG

# 16/6, 18/2, 18/3, 18/4

and 18/5

30(Male-19

Female-11)

90 98,200.00 Mr.Zahangir Islam, DCA, PMO SAIWRPMP

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

Deputy Director, DAE, Narail.

Mr.King Kor Chandra Das, Upazila Agriculture Officer, Kalia, Narail.

Upazila Agriculture Officer, Narail.

SAAO (BS), Purulia Block, Kalia, Narail.

14//

2010-11 Drafting of Bylaw

for WMG

Union parisad

auditorium,

Purulia U.P.

3days(20-22

Dec.,2010)

WMG Members of

(CSP/SIP:16-18) WMG

# 18/5A, 18/6, 18/6A,

18/7 and 18/8

30(Male-20

Female-10)

90 97,150.00 Mr.Zahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the PD,SAIWRPMP

Mr.Md.Hafizur Rahman,EO, Office of the PD,SAIWRPMP

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Mudasser Hossain, Upazila Cooperative Officer, Kalia, Narail.

15/

2010-11 Cultivation

Procedure of

different crops and

Vegetables

gardening.

Union parisad

auditorium,

Babra-Hasla

U.P.

3days(20-22

Dec.,2010)

WMG Members of

CSP/SIP:16-18) WMG

# 18/5A, 18/6, 18/6A,

18/7 and 18/8

30(Male-20

Female-10)

90 98,200.00 Mr.Zahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

Deputy Director, DAE, Narail.

Mr.King Kor Chandra Das, Upazila Agriculture Officer, Kalia, Narail.

Upazila Agriculture Officer, Narail.

SAAO (BS), Purulia Block, Kalia, Narail.

Page 209: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

17/

2010-11

Registration

procedures for

WMG.

Union parisad

auditorium,

Purulia U.P

3 days (28-30

December,

2010.)

WMG members of

CSP/SIP: 16-18

WMG#16/1, 16/2, 16/3,

16/4 and16/5.

30(Male-19

Female-11)

90 96,100.00 Mr.Md.Abdur Razzque,EE, ,PMO

Mr.Zahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Musaddek Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr.Parimal Kumar Das,Assitant Inspector,Upazila Cooperative office ,Narail

18/

2010-11

Basic training on

Carp poly-culture in

SAIWRPMP area.

Union parisad

auditorium,

Babra-Hasla

U.P.

3 days (28-30

December,

2010.)

WMG members of

CSP/SIP:16-18

(Fishery Sub-

committee) of WMG #

18/5A, 18/6,

18/6A,18/7 and18/8

30(Male-20

Female-10)

90 96,850.00 Mr.Md.Lutfor Rahman,EE, ,PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

, Dist.Fisheries Officer, Narail.

Mr.S.M.Enamul Hoque,Sr.Fisheries Officer,Narail

Ms. Hosne Ara Happy, Upazila Fisheries Officer,Lohagora, Narail.

Mr.Md.Azizul Hoque,Assitant Fisheries Officer,KaliaNarail

Dr.Shamsul Huda,ISPMC

19/

2010-11

Registration

procedures for

WMG.

Union parisad

auditorium,

Purulia U.P

3 days (04-06

January, 2011.)

WMG members of

CSP/SIP: 16-18

WMG#16/6, 18/2, 18/3,

18/4 and18/5.

30(Male-20

Female-10)

90 96,100.00 Mr.Md.Abdur Razzque,EE, ,PMO

Mr.Zahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(S), PMO

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAR,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Musaddek Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr.Parimal Kumar Das,Assitant Inspector,Upazila Cooperative office ,Narail

Page 210: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

20/

2010-11

Basic training on

Carp poly-culture in

SAIWRPMP area.

Union parisad

auditorium,

Babra-Hasla

U.P.

3 days (04-06

January, 2011.)

WMG members of

CSP/SIP: 16-18

(Fishery Sub-

committee) of WMG #

16/1, 16/2, 16/3, 16/4

and16/5.

30(Male-18

Female-12)

90 96,850.00 Mr.Md.Lutfor Rahman,EE, ,PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(S), PMO

, Dist.Fisheries Officer, Narail.

Mr.S.M.Enamul Hoque,Sr.Fisheries Officer,Narail

Ms..Hosne Ara Happy, Upazila Fisheries Officer,Lohagora, Narail.

Mr.Md.Azizul Hoque,Assitant Fisheries Officer,KaliaNarail

21/

2010-11

Registration

procedures for

WMG.

Union parisad

auditorium,

Purulia U.P

3 days (11-13

January, 2011.)

WMG members of

CSP/SIP: 16-18

WMG#18/5A, 18/6,

18/6A,18/7 and18/8

30(Male-20

Female-10)

90 96,100.00 Mr.Md.Abdur Razzque,EE, ,PMO

Mr.Zahangir Islam, DCA, PMO Mr.Md.Masud Karim, DCEO, PMO Mr.Abdur Razzak,AC(S), PMO Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Musaddek Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr.Parimal Kumar Das,Assitant Inspector,Upazila Cooperative office ,Narail

22/

2010-11

Basic training on

Carp poly-culture in

SAIWRPMP area.

Union parisad

auditorium,

Babra-Hasla

U.P.

3 days (11-13

January, 2011.)

WMG members of

CSP/SIP:16-18

(Fishery Sub-

committee) of WMG #

16/6, 18/2, 18/3, 18/4

and18/5.

30(Male-20

Female-10)

90 96,850.00 Mr.Md.Lutfor Rahman,EE, , PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(S), PMO

Mr.S.M.Enamul Hoque,Sr.Fisheries Officer,Narail

Ms.Hosne Ara Happy, Upazila Fisheries Officer, Lohagora, Narail.

Mr.Md.Azizul Hoque,Assitant Fisheries Officer,KaliaNarail

Dr.Shamsul Huda,ISPMC

Page 211: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

24/

2010-11

Procedure of Book

Keeping for WMG

Union parisad

auditorium,

Purulia U.P

3 days (19-21

January, 2011.)

WMG members of

CSP/SIP: 16-18 WMG

# 16/1, 16/2, 16/3, 16/4

and16/5.

30(Male-23

Female-7)

90 95,600.00 Mr.Md.Abdur Razzaque, EE, PMO,

Mr.Md.Lutfor Rahman,EE, , PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(S), PMO

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Musaddek Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr.Parimal Kumar Das,Assitant Inspector,Upazila Cooperative office ,Narail

25/

2010-11

Seed Production &

Compost

Preparation.

Union parisad

auditorium,

Babra-Hasla

U.P.

3 days (19-21

January, 2011.)

WMG members of

CSP/SIP:16-18) WMG

# 16/2, 16/3, 16/4,

18/2, and 18/3

30(Male-10

Female-20)

90 97,750.00 Mr.Zahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Md.Lutfor Rahman, EE, PMO,

Mr.Abdur Razzak,AC(S), PMO

Deputy Director, DAE, Narail.

Mr.King Kor Chandra Das, Upazila Agriculture Officer, Kalia, Narail.

Upazila Agriculture Officer, Narail.

SAAO (BS), Kalia, Narail.

26/

2010-11

Procedure of Book

Keeping for WMG

Union parisad

auditorium,

Purulia U.P

3 days (23-25

January, 2011.)

WMG members of

CSP/SIP: 16-18 WMG

# 16/6, 18/2, 18/3, 18/4

and18/5.

32(Male-29

Female-3)

96 97,700.00 Mr.Md.Abdur Razzaque, EE, PMO,

Mr.Md.Lutfor Rahman,EE, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(S), PMO

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Musaddek Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr.Parimal Kumar Das,Assitant Inspector,Upazila Cooperative office ,Narail

Page 212: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

27/

2010-11

Seed Production &

Compost

Preparation.

Union parisad

auditorium,

Babra-Hasla

U.P.

3 days (23-25

January, 2011.)

WMG members of

CSP/SIP:16-18) WMG

# 18/4,18/5,18/8,18/6

and 18/7

30(Male-17

Female-13)

90 97,750.00 Mr.Jahangir Islam, DCA, PMO.

Mr.Md.Masud Karim, DCEO, PMO.

Mr.Md.Lutfor Rahman, EE, PMO.

Mr.Abdur Razzak,AC(S), PMO

Deputy Director, DAE, Narail.

Mr.King Kor Chandra Das, Upazila Agriculture Officer, Kalia, Narail.

Upazila Agriculture Officer, Narail.

SAAO (BS), Kalia, Narail.

28/

2010-11

Procedure of Book

Keeping for WMG

Union parisad

auditorium,

Purulia U.P

3 days (29-31

January, 2011.)

WMG members of

CSP/SIP: 16-18 WMG

# 18/5A, 18/6, 18/7 and

18/8.

28(Male-20

Female-8)

84 93,500.00 Mr.Md.Abdur Razzaque, EE, PMO.

Mr.Md.Lutfor Rahman,EE, , PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(S), PMO .

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Musaddek Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr.Parimal Kumar Das,Assitant Inspector,Upazila Cooperative office ,Narail

29/

2010-11

Seed Production &

Compost

Preparation.

Union parisad

auditorium,

Babra-Hasla

U.P.

3 days (29-31

January, 2011.)

WMG members of

CSP/SIP:16-18) WMG

# 16/1, 16/5,16/6 and

18/5A

30(Male-2

Female-28)

90 97,750.00 Mr.Jahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO.

Mr.Md.Lutfor Rahman, EE, PMO.

Mr.Abdur Razzak,AC(S), PMO

Deputy Director, DAE, Narail.

Mr.King Kor Chandra Das, Upazila Agriculture Officer, Kalia, Narail.

Upazila Agriculture Officer, Narail.

SAAO (BS), Kalia, Narail.

Page 213: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

30/

2010-11

LCS Training For

WMG members.

Union parisad

auditorium,

Purulia U.P

1 day (14.02

2011.)

WMG members of

CSP/SIP:16-18) WMG

# 18/5,16/4, 16/3, 16/6

and 16/5

45(Male-34

Female-11)

45 37,150.00 Mr.Shah Ahmed Ali Khan, ISPMC.

Mr. .Masud Karim, DCEO, PMO,

Mr.Md. Abdur Razzaque, EE, PMO.

Mr. Biddut Kumar Shaha, EE/SMO, CSP, SAIWRPMP

Mr. Hasan Mahmud, SDE, Chnchuri Beel Sub-project, SAIWRPMP.

31/

2010-11

LCS Training For

WMG members.

Union parisad

auditorium,

Babra-Hasla

U.P.

1 day (14.02

2011.)

WMG members of

CSP/SIP:16-18) WMG

# 18/7, 18/2, 18/3, 16/2

and 18/4

40(Male-33

Female-7)

40 34,400.00

Mr.Shah Ahmed Ali Khan, ISPMC,

Mr.Md. Jahangir Islam, DCA, PMO,

Mr.Md. Abdur Razzaque, EE, PMO,

Mr. Zulfikar Ali Hawlader, EE, Narail Sub-project, SAIWRPMP

Mr. Amrito Kumar Das, SDE, Narail Sub-project, SAIWRPMP.

32/

2010-11

LCS Training For

WMG members.

Union parisad

auditorium,

Purulia U.P

1 day (15.02

2011.)

WMG members of

CSP/SIP:16-18) WMG

# 18/4, 18/8, 18/6, 16/1

and 18/5A

42(Male-33

Female-9)

42 36,100.00 Mr.Shah Ahmed Ali Khan, ISPMC,

Mr. .Masud Karim, DCEO, PMO,

Mr.Md. Abdur Razzaque, EE, PMO,

Mr. Biddut Kumar Shaha, EE/SMO, CSP,SAIWRPMP

Mr. Hasan Mahmud, SDE, Chnchuri Beel Sub-project, SAIWRPMP.

33/

2010-11

LCS Training For

WMG members.

Zila parisad

auditorium,

Narail

1 day (15.02

2011.)

WMG members of

NSP/SIP:8 & 9) WMG

#

8/1, 8/1A, 8/2, 8/3, 8/4,

8/5, 8/6, 8/7, 8//, 8/9,

8/10, 9/1, 9/2, 9/3, 9/4

and 9/5

42(Male-27

Female-15)

42 36,100.00 Mr.Shah Ahmed Ali Khan, ISPMC

Mr.Md. Jahangir Islam, DCA, PMO

Mr.Md. Abdur Razzaque, EE, PMO,

Mr. Zulfikar Ali Hawlader, EE, Narail Sub-project, SAIWRPMP

Mr. Amrito Kumar Das, SDE, Narail Sub-project, SAIWRPMP.

Page 214: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

34/

2010-11

Drafting of Bylaw

for WMG

Union parisad

auditorium,

Singa-Soalpur

U.P., Narail.

3days(22-24

February, 2011)

WMG Members of (SW

NSP/SIP:16 and 21)

6WMG

36(Male-23

Female-13)

108 100,400.00 Mr.Md.Abdur Razzaque, EE, PMO.

Mr.Zahangir Islam, DCA, PMO.

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(S), PMO

Mr.Md.Hafizur Rahman,EO, PMO

Mr.Md.Jahangir Alam,Dist. Cooperative Officer,Narail

Mr.Hashan Mahmood, DAD, Office of the Dist.Cooperative Officer, Narail.

Upazila Cooperative Officer, Narail Sador, Narail.

Inspector of Cooperative, Narail Sador, Narail

Mr.Shah Ahammed Ali Khan, ISPMC

35/

2010-11

Cultivation

Procedure of

different crops and

Vegetables

gardening.

Union parisad

auditorium,

Singa-Soalpur

U.P., Narail.

3days(22-24

February, 2011)

WMG Members of (SW

NSP/SIP:16 and 21)

6WMG

36(Male-23

Female-13)

108 100,100.00 Deputy Director,DAE,Narail

Upazila Agriculture officer, Narail Sador, Narail.

Mr.Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(Sociology), PMO

Dr.Rezaul Karim, ISPMC

Mr. Provat Kumar Tarafdar,SAAO (BS), Narail Sador , Narail.

Mr.Badal Kumar Das,SAAO (BS), Narail Sador , Narail

Page 215: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

36/

2010-11

Registration

Procedures for

WMG

Union parisad

auditorium,

Singa-Soalpur

U.P., Narail.

3days(26-28

February, 2011)

WMG Members of (SW

NSP/SIP:16 and 21)

6WMG

36(Male-26

Female-10)

108 100,400.00 Mr.Md.Abdur Razzaque,EE,Office of the PD,SAIWRPMP

Mr.Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(Sociology), Office of the PD,SAIWRPMP

Mr.Md.Hafizur Rahman,EO, Office of the PD,SAIWRPMP

Mr.Md.Jahangir Alam,Dist. Cooperative Officer,Narail

Mr.Hashan Mahmood, DAR, Office of the Dist.Cooperative Officer, Narail.

Upazila Cooperative Officer, Narail Sador, Narail.

Inspector of Cooperative, Narail Sador, Narail

Mr.Shah Ahammed Ali Khan, ISPMC

37/

2010-11

Basic training on

Carp poly-culture in

SAIWRPMP area.

Union parisad

auditorium,

Singa-Soalpur

U.P., Narail.

3days(26-28

February, 2011)

WMG Members of (SW

NSP/SIP:16 and 21)

6WMG

36(Male-27

Female-9)

108 100,350.00 Mr. Md. Lutfor Rahman, EE, PMO, SAIWRPMP.

District Fisheries Officer,Narail

Mr. S.M. Enamul Hoque, Senior Fisheries Officer, Narail.

Ms. Hosneara Happy, Upazila Fisheries Officer, Lohagora, Narail.

Asstt. Fisheries Officer, Narail Sador, Narail.

Mr.Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(Sociology), Office of the PD,SAIWRPMP

Dr. Shamsul Huda, ISPMC

Page 216: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

38/

2010-11

Procedure of Book

Keeping for WMG

Union parisad

auditorium,

Singa-Soalpur

U.P

3 days (7-9

March, 2011.)

WMG members of

NSP/SIP: 16 and 21

(6 WMG).

36(Male-22

Female-14)

108 100,500.00 Mr.Md.Lutfor Rahman,EE, ,PMO PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Golam Rasul, Upazila Cooperative Officer, Narail.

Inspector of Cooperative, Cooperative office ,Narail

39/

2010-11

Seed Production &

Compost

Preparation.

Union parisad

auditorium,

Singa-Soalpur

U.P.

3 days (7-9

March, 2011.)

WMG members of

NSP/SIP: 16 and 21

(6 WMG).

36(Male-23

Female-13)

108 100,350.00 Mr.Zahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, PMO

Mr.Md.Lutfor Rahman, EE, PMO, SAIWRPMP.

Mr.Abdur Razzak,AC(F), PMO

Deputy Director, DAE, Narail.

Upazila Agriculture Officer, Narail.

SAAO (BS), Narail.

40/

2010-11 Drafting of Bylaw

for WMG

Union parisad

auditorium,

Purulia U.P.,

Kalia, Narail.

3days(15-17

March,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 15/3,

15/4,15/5,15/6 and

15/7

30(Male-20

Female-10)

90 95,600.00 Mr.Zahangir Islam, DCA,

PMO,SAIWRPMP

Mr. Md. Lutfor Rahman, EE, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr.Md.Hafizur Rahman,EO, PMO

Mr.Jahangir Alam, Dist.Cooperative

Officer, Narail.

Mr.Hasan Mahmood,DAR,Office of the

Dist.Cooperative Officer,Narail

Mr.Md.Mossaddek Hossain, Upazila

Cooperative Officer, Narail.

Mr.M.A. Talukdar,ISPMC

Page 217: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

41/

2010-11

Basic training on

Carp poly-culture in

SAIWRPMP area.

Union parisad

auditorium,

Babra-Hasla

U.P., Kalia,

Narail.

3days(15-17

March,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 15/3,

15/4,15/5,15/6 and

15/7

31(Male-22

Female-9

93 98,250.00 Mr.Md.Lutfor Rahman,EE, ,Office of the

PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of

the PD,SAIWRPMP

Mr.Amimul Ehsan,Asstt.Chief(Fish),

Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the

PD,SAIWRPMP

, Dist.Fisheries Officer, Narail.

Mr.S.M.Enamul Hoque,Sr.Fisheries

Officer,Narail

Ms..Hosne Ara Happy, Upazila

Fisheries Officer,Lohagora, Narail.

Mr.Md.Azizul Hoque,Assitant Fisheries

Officer,KaliaNarail

Dr.Shamsul Huda,ISPMC

42/

2010-11 Drafting of Bylaw

for WMG

Union parisad

auditorium,

Purulia U.P.,

Kalia, Narail.

3days(21-23

March,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 15/1,

15/2,15/3,13/5 and

13/6

30(Male-18

Female-12)

90 95,600.00 Mr.Zahangir Islam, DCA, Office of the

PD,SAIWRPMP

Mr. Md. Lutfor Rahman, EE, Office of

the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of

the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the

PD,SAIWRPMP

Mr.Md.Hafizur Rahman,EO, Office of

the PD,SAIWRPMP

Mr.Jahangir Alam, Dist.Cooperative

Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the

Dist.Cooperative Officer,Narail

Mr.Md.Mossaddek Hossain, Upazila

Cooperative Officer, Kalia, Narail.

Mr.M.A. Talukdar,ISPMC

Page 218: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

43/

2010-11

Basic training on

Carp poly-culture in

SAIWRPMP area.

Union parisad

auditorium,

Babra-Hasla

U.P., Kalia,

Narail.

3days(21-23

March,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 15/1,

15/2,15/3,13/5 and

13/6

30(Male-19

Female-11)

90 97,200.00 Mr.Md.Lutfor Rahman,EE, ,Office of the

PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of

the PD,SAIWRPMP

Mr.Amimul Ehsan,Asstt.Chief(Fish),

Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the

PD,SAIWRPMP

, Dist.Fisheries Officer, Narail.

Mr.S.M.Enamul Hoque,Sr.Fisheries

Officer,Narail

Ms..Hosne Ara Happy, Upazila

Fisheries Officer,Lohagora, Narail.

Mr.Md.Azizul Hoque,Assitant Fisheries

Officer,KaliaNarail

Dr.Shamsul Huda,ISPMC

44/

2010-11 Drafting of Bylaw

for WMG

Union parisad

auditorium,

Purulia U.P.,

Kalia, Narail.

3days(29-31

March,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 13/2,

13/3,13/4, and 13/5

24(Male-14

Female-10)

72 86,300.00 Mr.Zahangir Islam, DCA, Office of the

PD,SAIWRPMP

Mr. Md. Lutfor Rahman, EE, Office of

the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of

the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the

PD,SAIWRPMP

Mr.Md.Hafizur Rahman,EO, Office of

the PD,SAIWRPMP

Mr.Jahangir Alam, Dist.Cooperative

Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the

Dist.Cooperative Officer,Narail

Mr.Md.Mossaddek Hossain, Upazila

Cooperative Officer, Kalia, Narail.

Mr.M.A. Talukdar,ISPMC

Page 219: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

45/

2010-11

Basic training on

Carp poly-culture in

SAIWRPMP area.

Union parisad

auditorium,

Babra-Hasla

U.P., Kalia,

Narail.

3days(29-31

March,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 13/2, 13/3,13/4

and 13/5

24(Male-16

Female-8)

72 89,100.00 Mr.Md.Lutfor Rahman,EE, ,Office of the

PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of

the PD,SAIWRPMP

Mr.Amimul Ehsan,Asstt.Chief(Fish),

Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the

PD,SAIWRPMP

, Dist.Fisheries Officer, Narail.

Mr.S.M.Enamul Hoque,Sr.Fisheries

Officer,Narail

Ms..Hosne Ara Happy, Upazila

Fisheries Officer,Lohagora, Narail.

Mr.Md.Azizul Hoque,Assitant Fisheries

Officer,KaliaNarail

Dr.Shamsul Huda,ISPMC

46/

2010-11 Cultivation

Procedure of

different crops and

Vegetables

gardening.

Union parisad

auditorium,

Babra-Hasla

U.P.

3days(04-06

April, 2011)

WMG Members of

CSP/SIP:13-15) WMG

# 15/4, 15/5, 15/6 and

15/7

32(Male-25

Female-7)

96 100,700.00 Mr.Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(Sociology), Office of the PD,SAIWRPMP

Mr. Md Alamgir, Research Officer (Economics),Office of the PD,SAIWRPMP

Deputy Director,DAE,Narail

Mr. King Kor Chandra Das, Upazila Agriculture officer, Kalia, Narail.

Mr.Ruhul Amin, Upazila Agriculture Officer, Narail Sador , Narail

SAAO (BS), Babra-Hasla UP, Kalia, Narail.

Page 220: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

47/

2010-11

Registration

procedures for

WMG.

Union parisad

auditorium,

Purulia U.P

3days(04-06

April, 2011)

WMG Members of

CSP/SIP:13-15) WMG

# 13/3, 13/4, 13/5 and

13/6

32(Male-18

Female-14)

96 98,800.00 Mr.Md. Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(Sociology), Office of the PD,SAIWRPMP

Mr.Md.Hafizur Rahman,EO, Office of the PD,SAIWRPMP

Mr.Md. Alamgir, Research Offecer (Economics), Office of the PD, SAIWRPMP.

Mr.Md.Jahangir Alam,Dist. Cooperative Officer,Narail

Mr.Hashan Mahmood, DAR, Office of the Dist.Cooperative Officer, Narail.

Mr. Mosaddeque Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr. Parimal Kumar Das, Assit Inspector Upazila Cooperative Office, Kalia, Narail

Mr. Mobarok Ali Talukdar, Cooperative Specialist, ISPMC

48/

2010-11 Cultivation

Procedure of

different crops and

Vegetables

gardening.

Union parisad

auditorium,

Babra-Hasla

U.P.

3days(10-12

April, 2011)

WMG Members of

CSP/SIP:13-15) WMG

# 15/1, 15/2, 15/3 and

13/6

32(Male-23

Female-9)

96 100,700.00 Mr.Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(Sociology), Office of the PD,SAIWRPMP

Mr. Md Alamgir, Research Officer (Economics),Office of the PD,SAIWRPMP

Deputy Director,DAE,Narail

Mr. King Kor Chandra Das, Upazila Agriculture officer, Kalia, Narail.

Mr.Ruhul Amin, Upazila Agriculture Officer, Narail Sador , Narail

SAAO (BS), Babra-Hasla UP, Kalia, Narail.

Page 221: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

49/

2010-11

Registration

procedures for

WMG.

Union parisad

auditorium,

Purulia U.P

3days(10-12

April, 2011)

WMG Members of

CSP/SIP:13-15) WMG

# 13/2, 15/7, 15/6 and

15/5

32(Male-22

Female-10)

96 98,800.00 Mr.Md. Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(Sociology), Office of the PD,SAIWRPMP

Mr.Md.Hafizur Rahman,EO, Office of the PD,SAIWRPMP

Mr.Md. Alamgir, Research Offecer (Economics), Office of the PD, SAIWRPMP.

Mr.Md.Jahangir Alam,Dist. Cooperative Officer,Narail

Mr.Hashan Mahmood, DAR, Office of the Dist.Cooperative Officer, Narail.

Mr. Mosaddeque Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr. Parimal Kumar Das, Assit Inspector Upazila Cooperative Office, Kalia, Narail

Mr. Mobarok Ali Talukdar, Cooperative Specialist, ISPMC

50/

2010-11 Cultivation

Procedure of

different crops and

Vegetables

gardening.

Union parisad

auditorium,

Babra-Hasla

U.P.

3days(16-18

April, 2011)

WMG Members of

CSP/SIP:13-15) WMG

# 13/5, 13/4, 13/3 and

13/2

32(Male-21

Female-11)

96 100,700.00 Mr.Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(Sociology), Office of the PD,SAIWRPMP

Mr. Md Alamgir, Research Officer (Economics),Office of the PD,SAIWRPMP

Deputy Director,DAE,Narail

Mr. King Kor Chandra Das, Upazila Agriculture officer, Kalia, Narail.

Mr.Ruhul Amin, Upazila Agriculture Officer, Narail Sador , Narail

SAAO (BS), Babra-Hasla UP, Kalia, Narai

Page 222: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

51/

2010-11

Registration

procedures for

WMG.

Union parisad

auditorium,

Purulia U.P

3days(16-18

April, 2011)

WMG Members of

CSP/SIP:13-15) WMG

# 15/4, 15/3, 15/2 and

15/1

32(Male-18

Female-14)

96 98,800.00 Mr.Md. Jahangir Islam, DCA, Office of the PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(Sociology), Office of the PD,SAIWRPMP

Mr.Md.Hafizur Rahman,EO, Office of the PD,SAIWRPMP

Mr.Md. Alamgir, Research Offecer (Economics), Office of the PD, SAIWRPMP.

Mr.Md.Jahangir Alam,Dist. Cooperative Officer,Narail

Mr.Hashan Mahmood, DAR, Office of the Dist.Cooperative Officer, Narail.

Mr. Mosaddeque Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr. Parimal Kumar Das, Assit Inspector Upazila Cooperative Office, Kalia, Narail

Mr. Mobarok Ali Talukdar, Cooperative Specialist, ISPMC

52/2010-

11

Basic training on

Gift Telapia culture

in SAIWRPMP

area.

Union parisad

auditorium,

Babra-Hasla

U.P., Kalia,

Narail.

3days(19-21

April,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 13/2, 13/3,13/5

and 13/6

32(Male-24

Female-8)

96 100,550.00 Mr.Md.Lutfor Rahman,EE, ,Office of the

PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of

the PD,SAIWRPMP

Mr.Amimul Ehsan,Asstt.Chief(Fish),

Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the

PD,SAIWRPMP

, Dist.Fisheries Officer, Narail.

Mr.S.M.Enamul Hoque,Sr.Fisheries

Officer,Narail

Ms..Hosne Ara Happy, Upazila

Fisheries Officer,Lohagora, Narail.

Mr.Md.Alamgir, RO, SAIWRPMP

Dr.Shamsul Huda, Fisheries Specialist,

ISPMC

Page 223: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

53/

2010-11

Procedure of Book

Keeping for WMG

Union parisad

auditorium,

Purulia U.P.,

Kalia, Narail.

3days(19-21

April,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 13/3, 13/4,13/5

and 13/6

32(Male-15

Female-17)

96 98,800.00 Mr.Md.Lutfor Rahman,EE, ,Office of the PD,SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr. Md. Hafizur Rahman, EO, Office of the PD,SAIWRPMP

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAD,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Mossaddek Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr. Parimal mKumar Das, Inspector of Cooperative, Kalia , Narail

Mr. Mobarak Ali Talukdar, Cooperative Specialist, ISPMC.

Mr.Md.Alamgir, RO, SAIWRPMP

54/2010-

11

Basic training on

Gift Telapia culture

in SAIWRPMP

area.

Union parisad

auditorium,

Babra-Hasla

U.P., Kalia,

Narail.

3days(23-25

April,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 13/4, 15/1,15/5

and 15/6

32(Male-21

Female-11)

96 100,550.00 Mr. Ferdous Ahmmed, Asstt. Director,

Dte of Fisheries, Dhaka.

Mr.Md.Lutfor Rahman,EE, ,Office of the

PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of

the PD,SAIWRPMP

Mr.Amimul Ehsan,Asstt.Chief(Fish),

Office of the PD,SAIWRPMP

Mr.Abdur Razzak,AC(F), Office of the

PD,SAIWRPMP

, Dist.Fisheries Officer, Narail.

Mr.S.M.Enamul Hoque,Sr.Fisheries

Officer,Narail

Ms..Hosne Ara Happy, Upazila

Fisheries Officer,Lohagora, Narail.

Mr.Md.Alamgir, RO, SAIWRPMP

Dr.Shamsul Huda, Fisheries Specialist,

ISPMC

Page 224: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

55/2010-

11

Procedure of Book

Keeping for WMG

Union parisad

auditorium,

Purulia U.P.,

Kalia, Narail.

3days(23-25

April,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 13/2, 15/5,15/6

and 15/7

32(Male-23

Female-9)

96 98,800.00 Mr.Md.Lutfor Rahman,EE, ,Office of the PD,SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr. Md. Hafizur Rahman, EO, PMO

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAR,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Mossaddek Hossain, Upazila Cooperative Officer, Kalia, Narail.

Mr. Parimal mKumar Das, Inspector of Cooperative, Kalia , Narail

Mr. Mobarak Ali Talukdar, Cooperative Specialist, ISPMC.

Mr.Md.Alamgir, RO, SAIWRPMP

56/2010-

11

Basic training on

Gift Telapia culture

in SAIWRPMP

area.

Union parisad

auditorium,

Babra-Hasla

U.P., Kalia,

Narail.

3days(26-28

April,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 15/7, 15/3,15/2

and 15/4

32(Male-24

Female-8)

96 100,550.00 Mr. Ferdous Ahmmed, Asstt. Director,

Dte of Fisheries, Dhaka.

Mr.Md.Lutfor Rahman,EE, ,Office of the

PD,SAIWRPMP

Mr.Md.Masud Karim, DCEO, Office of

the PD,SAIWRPMP

Mr.Amimul Ehsan, Asstt. Chief (Fish),

PMO

Mr.Abdur Razzak,AC(F), PMO

, Dist.Fisheries Officer, Narail.

Mr.S.M.Enamul Hoque,Sr.Fisheries

Officer,Narail

Ms..Hosne Ara Happy, Upazila

Fisheries Officer,Lohagora, Narail.

Mr.Md.Alamgir, RO, SAIWRPMP

Dr.Shamsul Huda, Fisheries Specialist,

ISPMC

Page 225: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

57/2010-

11

Procedure of Book

Keeping for WMG

Union parisad

auditorium,

Purulia U.P.,

Kalia, Narail.

3days(26-28

April,2011)

WMG Members of

(CSP/SIP:13 and 15)

WMG # 15/1, 15/2,

15/3 and 15/4

32(Male-26

Female-6)

96 98,800.00 Mr.Md.Lutfor Rahman,EE, ,Office of the PD,SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO

Mr.Md.Masud Karim, DCEO, PMO

Mr.Abdur Razzak,AC(F), PMO

Mr. Md. Hafizur Rahman, EO, PMO

Mr.Jahangir Alam, Dist.Cooperative Officer, Narail.

Mr.Hasan Mahmood,DAR,Office of the Dist.Cooperative Officer,Narail

Mr.Md.Mossaddek Hossain, Upazila Cooperative Officer, Kalia,

Mr. Parimal mKumar Das, Inspector of Cooperative, Kalia ,

Mr. Mobarak Ali Talukdar, Cooperative Specialist, ISPMC.

Mr.Md.Alamgir, RO, SAIWRPMP

60/2010-

11

Field Training and

sharing

experiences of

High value crop

production.

BARRI Regional

office, Tala,

Satkhira

1 day

(10.05.2011)

WMG members

(Conveners of

Agriculture sub-

committee of

SW/NSP/SIP# 8, 9, 16,

21 and

SW/CSP/SIP#13, 15,

16-18).

52( Male-50

Female-2)

52 72,330.00 Mr. Masud Karim, DCEO, PMO, Dr. AKM Habibur Rahman, PSO, BARRI, Tala, Satkhira.

Mr. Md. Abdus Samad, Scientific Asstt., BARRI, Satkhira.

Mr. Mainuddin Fakir, PSO, BARRI, Satkhira.

Mr. Md. Hafizur Rahman , EO, PMO,SAIWRPMP

61/2010-

11

Field Training and

sharing

experiences of

CAP

Giala-Ghosh

para Dugdha

Utpadon Kari

Samity, Tala,

Satkhira.

1 day

(10.05.2011)

WMG members

(Conveners of

Livelihood sub-

committee of

SW/NSP/SIP# 8, 9, 16,

21 and

SW/CSP/SIP#13, 15,

16-18).

52( Male-4

Female-48)

52 71,000.00 Mr. Md. Jahangir Islam, DCA, PMO,

Mr. Proshanto Kumar Ghos, Secretary, Giala-Ghosh para Dugdha Utpadon Kari Samity, Tala, Satkhira.

Mr. Chironjit Ghos, Giala-Ghosh para Dugdha Utpadon Kari Samity, Tala, Satkhira.

Mr. Subir Kumar Ghos, Giala-Ghosh para Dugdha Utpadon Kari Samity, Tala, Satkhira.

Mr. Md. Abdur Razzak, ACS,PMO,

Page 226: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

62/2010-

11 Operation and

Maintenance of

infrastructure

through

participatory water

management.

UP auditorium,

Purulia UP,

Kalia, Narail.

3 days

(11-13 May,

2011)

WMG members (O&M

sub-committee) of

SW/CSP/SIP#13-

15(WMG#S-13/6, 13/5,

13/4 and 13/3)

33( Male-19

Female-14)

99 97,450.00 Mr. Masud Karim, DCEO, PMO.

Mr. Md. Jahangir Islam, DCA, PMO,SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,SAIWRPMP

Mr. Md. Manzurul Karim, O&M specialist, ISPMC

63/2010-

11

Seed Production

and Compost

Preparation.

UP auditorium,

Babra-Hasla

UP, Kalia,

Narail.

3 days

(11-13 May,

2011)

WMG members (GL

sub-committee) of

SW/CSP/SIP#13-

15(WMG#S-13/6, 13/5,

13/4 and 13/3)

32( Male-6

Female-26)

96 100,700.00 Mr. Masud Karim, DCEO, PMO,SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO,SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,SAIWRPMP

Deputy Director, DAE, Narail

Mr. King Kor Chandra Das, Upazila Agriculture officer, Kalia,

Mr.Ruhul Amin, Upazila Agriculture Officer, Narail Sador ,

SAAO (BS), Babra-Hasla UP, Kalia, Narail.

64/2010-

11 Operation and

Maintenance of

infrastructure

through

participatory water

management.

UP auditorium,

Purulia UP,

Kalia, Narail.

3 days

(14-16 May,

2011)

WMG members (O&M

sub-committee) of

SW/CSP/SIP#13-

15(WMG# S-13/2,

15/5, 15/6 and 15/7)

32( Male-23

Female-9)

96 96,400.00 Mr. Masud Karim, DCEO, PMO,SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO,SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,SAIWRPMP

Mr. Md. Manzurul Karim, O&M specialist, ISPMC

65/2010-

11

Seed Production

and Compost

Preparation.

UP auditorium,

Babra-Hasla

UP, Kalia,

Narail.

3 days

(14-16 May,

2011)

WMG members (GL

sub-committee) of

SW/CSP/SIP#13-

15(WMG#S-13/2, 15/5,

15/6 and 15/7)

32( Male-10

Female-22)

96 100,700.00 Mr. Masud Karim, DCEO, PMO,

Mr. Md. Jahangir Islam, DCA, PMO,

Mr. Md. Abdur Razzak, ACS, PMO,

Deputy Director, DAE, Narail

Mr. King Kor Chandra Das, Upazila Agriculture officer, Kalia,

Mr.Ruhul Amin, Upazila Agriculture Officer, Narail Sador ,

SAAO (BS), Babra-Hasla UP, Kalia,

Page 227: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

66/2010-

11 Operation and

Maintenance of

infrastructure

through

participatory water

management.

UP auditorium,

Purulia UP,

Kalia, Narail.

3 days

(17-19 May,

2011)

WMG members (O&M

sub-committee) of

SW/CSP/SIP#13-

15(WMG# S-15/1,

15/2, 15/3 and 15/4)

32( Male-24

Female-8)

96 96,400.00 Mr. Masud Karim, DCEO, PMO.

Mr. Md. Jahangir Islam, DCA, PMO,SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,SAIWRPMP

Mr. Md. Manzurul Karim, O&M specialist, ISPMC

67/2010-

11

Seed Production

and Compost

Preparation.

UP auditorium,

Babra-Hasla

UP, Kalia,

Narail.

3 days

(17-19 May,

2011)

WMG members (GL

sub-committee) of

SW/CSP/SIP#13-

15(WMG#S-15/1, 15/2,

15/3 and 15/4)

32( Male-8

Female-24)

96 100,700.00 Mr. Masud Karim, DCEO, PMO,SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO,SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,SAIWRPMP

Deputy Director, DAE, Narail

Mr. King Kor Chandra Das, Upazila Agriculture officer, Kalia,

Mr.Ruhul Amin, Upazila Agriculture Officer, Narail Sador ,

SAAO (BS), Babra-Hasla UP, Kalia,

68/

2010-11

Operation and

Maintenance of

infrastructure

through

participatory water

management.

UP auditorium,

Purulia UP,

Kalia, Narail.

3days

(22-24 May,

2011)

WMG members(O&M

sub-committee) of

SW/CSP/SIP#16-

18(WMG# Doel,

Koel,Babui,Moyna and

Satodal )

33( Male-26

Female-7)

99 97,450.00 Mr. Masud Karim, DCEO, PMO,

Mr. Md. Jahangir Islam, DCA, PMO,

Mr. Md. Abdur Razzak, ACS, PMO

Mr. Md. Manzurul Karim, O&M

specialist, ISPMC

Mr. Aminul Karim, P E, PMO

69

/2010-11

Basic training on

Gift Telapia culture

in SAIWRPMP

area.

UP auditorium,

Babra-Hasla

UP, Kalia,

Narail.

3days

(22-24 May,

2011)

WMG Members of

(CSP/SIP:16-18) WMG

# Koel, Babui,Moyna

,Surjamukhi and

Satodal )

33( Male-21

Female-12)

99 100,900.00 Mr.Md.Masud Karim, DCEO, PMO

Mr.Amimul Ehsan, Asstt. Chief (Fish),

PMO

Mr.Abdur Razzak,AC(F), PMO

Mr.S.M.Enamul Hoque,Sr.Fisheries

Officer,Narail

Ms..Hosne Ara Happy, Upazila

Fisheries Officer,Lohagora, Narail.

Mr.Md.Alamgir, RO, SAIWRPMP

Page 228: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

70/

2010-11

Operation and

Maintenance of

infrastructure

through

participatory water

management.

UP auditorium,

Purulia UP,

Kalia, Narail.

3days

(25-27 May,

2011)

WMG members(O&M

sub-committee) of

SW/CSP/SIP#16-

18(WMG# Beli, Keya,

Surjamukhi,

Noboganga and Ekota

33( Male-26

Female-7)

99 97,450.00 Mr. Masud Karim, DCEO, PMO

Mr. Md. Jahangir Islam, DCA, PMO,

Mr. Md. Abdur Razzak, ACS, PMO,

Mr. Md. Manzurul Karim, O&M

specialist, ISPMC

Mr. Aminul Karim, P E, PMO

71

/2010-11

Basic training on

Gift Telapia culture

in SAIWRPMP

area.

UP auditorium,

Babra-Hasla

UP, Kalia,

Narail.

3days

(25-27 May,

2011)

WMG Members of

(CSP/SIP:16-18) WMG

# Koel, Doyel,Ekota,

Surovi, Hasnahena and

Keya )

33( Male-21

Female-12)

99 100,900.00 Mr.Md.Masud Karim, DCEO, PMO

Mr.Amimul Ehsan, A C (Fish), PMO

Mr.Abdur Razzak,AC(S), PMO

Mr.S.M.Enamul Hoque, Sr.Fisheries

Officer,Narail

Ms..Hosne Ara Happy, Upazila

Fisheries Officer,Lohagora, Narail.

Mr.Md.Alamgir, RO, SAIWRPMP

72/2010-

11 Operation and

Maintenance of

infrastructure

through

participatory water

management.

Union parisad

auditorium,

Purulia U.P

3days

(01-03 June,

2011)

WMG members(O&M

sub-committee) of

SW/CSP/SIP#16-

18(WMG# Ekota,

Surovi, Hasnahena,

Kanokchapa and

Gondhoraj)

32 96 97,450.00 Mr. Masud Karim, DCEO, PMO,

Mr. Md. Jahangir Islam, DCA, PMO,

Mr. Md. Abdur Razzak, ACS, PMO,

SAIWRPMP

Mr. Md. Manzurul Karim, O&M

specialist, ISPMC

73

/2010-11

Basic training on

Gift Telapia culture

in SAIWRPMP

area.

Union parisad

auditorium,

Babra-Hasla

U.P.

3days

(01-03 June,

2011)

WMG Members of

(CSP/SIP:16-18) WMG

# Keya, Beli,

Gondhoraj,

Kanokchapa and

Novoganga))

32 96 100,900.00 Mr.Md.Masud Karim, DCEO, PMO

Mr. Ferdous Ahmed, Assist. Director,

Directorate of Fisheries,

Mr.Amimul Ehsan, Asstt. Chief (Fish),

PMO

Mr.Abdur Razzak,AC(F), PMO

Mr.Md.Alamgir, RO, SAIWRPMP

Dr. Shamsul Huda, Fisheries

Specialist,ISPMC

Page 229: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

74/2010-

11

Meaning and

Functions of WMG/

WMA/JMC in

SAIWRPMP

Union parisad

auditorium,

Purulia U.P

3days

(07-09 June,

2011)

WMG membersof

SW/CSP/SIP#16-

18(WMG# Babui,

Moyna, Doel,Satodol

and Surjamukhi)

33( Male-

25,Female- 8)

99 99,850.00 Mr. Md. Zahirul Islam, PD, SAIWRPMP

Mr. Masud Karim, DCEO, PMO,

SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO,

SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,

SAIWRPMP

Mr. Md. Hafizur Rahman, EO,PMO,

SAIWRPMP

Mr. Md. Jahangir Alam, DCO, Narail

Mr. Md. Hassan Mahmud, DAR, Office

of the DCO, Narail

Mr. Md. Mossaddek Hossain, Upazila

Cooperative Officer, Kalia, Narail

Mr. Parimal Kumar Das, Asstt.

Inspector, Office of the Upazila

Cooperative Officer, Kalia, Narail

75

/2010-11

Plantation Activities

and Vegetable

Gardening in

SAIWRPMP

Union parisad

auditorium,

Babra-Hasla

U.P.

3days

(07-09 June,

2011)

WMG Members of

(CSP/SIP:16-18) WMG

# Keya, Beli,

Hasnahena, Surovi and

Ekota)

33( Male-

24,Female- 9)

99 101,750.00 Mr. Masud Karim, DCEO, PMO,

SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO,

SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,

SAIWRPMP

Mr. Md. Hafizur Rahman, EO,PMO,

SAIWRPMP

Deputy Director, DAE, Narail

Mr. King Kor Chandra Das, Upazila

Agriculture Officer, Kalia, Narail

Mr. Ruhul Amin, Upazila Agriculture

Officer, Narail Sador, Narail

SAAO(BS), Babra Hasla UP

Page 230: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

76/2010-

11

Meaning and

Functions of WMG/

WMA/JMC in

SAIWRPMP

Union parisad

auditorium,

Purulia U.P

3days

(18-20 June,

2011)

WMG membersof

SW/CSP/SIP#16-

18(WMG# Surjamukhi,

Koyel, Bely, Keya,

Hasnahena and

Surovi)

33( Male-

20,Female-

13)

99 99,850.00 Mr. Masud Karim, DCEO, PMO,

SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO,

SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,

SAIWRPMP

Mr. Md. Hafizur Rahman, EO,PMO,

SAIWRPMP

Mr. Md. Jahangir Alam, DCO, Narail

Mr. Md. Hassan Mahmud, DAR, Office

of the DCO, Narail

Mr. Md. Mossaddek Hossain, Upazila

Cooperative Officer, Kalia, Narail

Mr. Parimal Kumar Das, Asstt.

Inspector, Office of the Upazila

Cooperative Officer, Kalia, Narail

77

/2010-11

Plantation Activities

and Vegetable

Gardening in

SAIWRPMP

Union parisad

auditorium,

Babra-Hasla

U.P.

3days

(18-20 June,

2011)

WMG Members of

(CSP/SIP:16-18) WMG

# Gondoraj, Koyel,

Doyel, Satodal and

Ekota)

33( Male-

18,Female-

15)

99 101,750.00 Mr. Masud Karim, DCEO, PMO,

SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO,

SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,

SAIWRPMP

Mr. Md. Hafizur Rahman, EO,PMO,

SAIWRPMP

Deputy Director, DAE, Narail

Mr. King Kor Chandra Das, Upazila

Agriculture Officer, Kalia, Narail

Mr. Ruhul Amin, Upazila Agriculture

Officer, Narail Sador, Narail

SAAO(BS), Babra Hasla UP

Page 231: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

78/2010-

11

Meaning and

Functions of WMG/

WMA/JMC in

SAIWRPMP

Union parisad

auditorium,

Purulia U.P

3days

(14-16 June,

2011)

WMG membersof

SW/CSP/SIP#16-

18(WMG# Ekota,

Gondoraj,

Kanokchapa,

Noboganga and

Surovi)

32( Male-

21,Female-

11)

96 98,800.00 Mr. Masud Karim, DCEO, PMO,

SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO,

SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,

SAIWRPMP

Mr. Md. Hafizur Rahman, EO,PMO,

SAIWRPMP

Mr. Md. Jahangir Alam, DCO, Narail

Mr. Md. Hassan Mahmud, DAR, Office

of the DCO, Narail

Mr. Md. Mossaddek Hossain, Upazila

Cooperative Officer, Kalia, Narail

Mr. Parimal Kumar Das, Asstt.

Inspector, Office of the Upazila

Cooperative Officer, Kalia, Narail

79/2010-

11

Plantation Activities

and Vegetable

Gardening in

SAIWRPMP

Union parisad

auditorium,

Babra-Hasla

U.P.

3days

(14-16 June,

2011)

WMG Members of

(CSP/SIP:16-18) WMG

# Babui, Moyna,

Surjamukhi,

Kanokchapa and

Novoganga)

32( Male-

22,Female-

10)

96 100,700.00 Mr. Masud Karim, DCEO, PMO,

SAIWRPMP

Mr. Md. Jahangir Islam, DCA, PMO,

SAIWRPMP

Mr. Md. Abdur Razzak, ACS, PMO,

SAIWRPMP

Mr. Md. Hafizur Rahman, EO,PMO,

SAIWRPMP

Deputy Director, DAE, Narail

Mr. King Kor Chandra Das, Upazila

Agriculture Officer, Kalia, Narail

Mr. Ruhul Amin, Upazila Agriculture

Officer, Narail Sador, Narail

SAAO(BS), Babra Hasla UP

Page 232: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

80/2010-

11 Cow and Goat

Rearing for

Collective Action

Plan (CAP) in

SAIWRPMP

UP Auditorium,

Tularampur UP,

Narail

3 days(21-23

June,2011)

WMG membersof SW

/NSP/SIP#8 & 9

(WMG# Madhobilata,

Kalmilata, Sapla,

Balaka, Sraboni,

Falguni, Mollika and

Agroni )

33(Male- 26,

Female-7)

99 100,850.00 Mr. Md. Jahangir Islam, DCA, PMO,

SAIWRPMP

Mr. Masud Karim, DCEO, PMO,

Mr. M.M. Doalatana, District Livestock

Officer, Narail.

Veterinary Surgeon, Narail.

Mr. Pijush Kumar Saha, Upazila

Livestock Officer, Narail Sador,

Mr. Md. Abdur Razzak, ACS, PMO,

Mr. Md. Hafizur Rahman, EO,PMO,

SAIWRPMP

81/2010-

11

GIFT (Tilapia)

Culture in

SAIWRPMP

Proshika

Auditorium,

Narail

3 days(21-23

June,2011)

WMG members of NSP

SIP: 08-09 WMG #

Swarnalata, Torulata

and Madhobilata

33(Male- 23,

Female-10)

99 100,900.00 Mr. Amimul Ehsan, AC(F), PMO,

Mr. Masud Karim, DCEO, PMO,

Mr. Md. Abdur Razzak, ACS, PMO,

SAIWRPMP

District Fisheries Officer, Narail

Mr. S.M. Enamul Hoque, , Sr. Fisheries

Officer, Narail

Ms. Hosneara Happy, Upazila Fisheries

Officer, Lohagara, Narail

Asstt. Fisheries Officer,Narail Sador,N

arail

82/2010-

11 Cow and Goat

Rearing for

Collective Action

Plan (CAP) in

SAIWRPMP

UP Auditorium,

Tularampur UP,

Narail

3 days(24-26

June,2011)

WMG members of NSP

SIP: 08-09 WMG#

Baishakhi, Bonolata

and Agroni

33(Male- 20,

Female-13)

99 100,850.00 Mr. Md. Jahangir Islam, DCA, PMO,

SAIWRPMP

Mr. Masud Karim, DCEO, PMO,

SAIWRPMP

Mr. M.M. Doalatana, District Livestock

Officer, Narail.

Veterinary Surgeon, Narail.

Mr. Pijush Kumar Saha, Upazila

Livestock Officer, Narail Sador, Narail

Mr. Md. Abdur Razzak, ACS, PMO,

SAIWRPMP

Mr. Md. Hafizur Rahman, EO,PMO,

Page 233: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Course

No.

Course Title Venue Duration Participants Total No. of

Participants

Total

Trainee

days

Cost

incurred

(Taka)

Remarks/Resource Person

83/2010-

11

GIFT (Tilapia)

Culture in

SAIWRPMP

Proshika

Auditorium,

Narail

3 days(24-26

June,2011)

WMG members of NSP

SIP: 08-09 WMG #

Kalmilata, Jaba, Mollika

and Falguni

33(Male- 22,

Female-11)

99 100,900.00 Mr. Masud Karim, DCEO, PMO,

Mr. Amimul Ehsan, AC(F), PMO,

Mr. Md. Abdur Razzak, ACS,PMO,

District Fisheries Officer, Narail

Mr. S.M. Enamul Hoque, , Sr. Fisheries

Officer, Narail

Ms. Hosneara Happy, Upazila Fisheries

Officer, Lohagara, Narail

Asstt. Fisheries Officer,Narail

84/2010-

11 Cow and Goat

Rearing for

Collective Action

Plan (CAP) in

SAIWRPMP

UP Auditorium,

Tularampur UP,

Narail

3 days(27-29

June,2011)

WMG members of NSP

SIP: 08-09 WMG#

Borsha, Bonolata ,

Hoimonty and Chaity

33(Male- 9,

Female-24)

99 100,850.00 Mr. Md. Jahangir Islam, DCA, PMO,

Mr. Masud Karim, DCEO, PMO,

Mr. M.M. Doalatana, District Livestock

Officer, Narail.

Veterinary Surgeon, Narail.

Mr. Pijush Kumar Saha, Upazila

Livestock Officer, Narail Sador,

Mr. Md. Abdur Razzak, ACS, PMO,

Mr. Md. Hafizur Rahman, EO,PMO,

85/2010-

11

GIFT (Tilapia)

Culture in

SAIWRPMP

Proshika

Auditorium,

Narail

3 days(27-29

June,2011)

WMG members of NSP

SIP: 08-09 WMG #

Falguni, Sapla,Balaka

and Sraboni

33(Male- 23,

Female-10)

99 102,000.00 Mr. Amimul Ehsan, AC(F), PMO,

Mr. Masud Karim, DCEO, PMO,

Mr. Md. Abdur Razzak, ACS, PMO,

Dr. Khalilur Rahman, SSO, BFRI,

Jessore

Mr. Ferdous Ahmed, Asstt. Director,

DoF, Dhaka

Total

Part-B = 72

2367(Male-

1513 ,

Female- 854)

6553 6789,180.00

For 2010 - 11 G.Total:

(Part - A + Part - B)

3021(Male-

2068 ,

Female-953)

7886 8937,960.00

Page 234: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Southwest Area Integrated Water Resources Planning and Management Project Bangladesh Water Development Board

Training Plan for 2011 – 12

Capacity development for officers of PMO,SMOs,Line Agencies & NGO (Staff Training) 2011-12 Part-A

Sl. No. Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated cost

1 Delineation of Sub-unit

Implementation Plan(SIP)

and Sub-project

Implementation Procedure.

Officers of PMO, SMOs and

Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore/

Narail

1 3 days 30 30 90 150,000.00

2 Communication tools and

techniques

Officers of PMO, SMOs and

Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore/

Narail

1 3 days 30 30 90 150,000.00

3 Participatory Integrated

Water Resources

Management

Officers of PMO, SMOs and

Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore/

Narail

1 3 days 30 30 90 150,000.00

4 Formation of WMO &Rules

of Co-operatives,

Officers of PMO, SMOs and

Staff of NGO (ASG)

ISPMC, Officers of

Department of

Cooperatives &

BWDB Officials.

Jessore/

Narail

1 3 days 30 30 90 150,000.00

5 Agriculture Extension :

Basic training on

Agriculture Extension

Concerned Upazila Officers

of DAE & NGO Facilitator

(Agriculture)

ISPMC, Officers of

Department of

Agriculture

Extension.

Jessore/

Narail

1 3 days 30 30 90 150,000.00

6 Fisheries Extension:

Basic Training on Fisheries

Development.

Concerned Upazila Officers

of Deptt. of Fisheries & NGO

Facilitator (Fisheries)

ISPMC, Officers of

Department of

Fisheries.

Jessore/

Narail

1 3 days 30 30 90 150,000.00

7 Financial Management for

SAIWRPMP

Officers of PMO,

SMOs,RAC & concerned

officers of

Accounts,Audit,Finance Dte.

and Staff of NGO (ASG)

ISPMC, Senior

officers of BWDB &

Resource persons

from ADB, BRM.

Jessore/

Narail

1 3 days 30 30 90 150,000.00

Page 235: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Sl. No. Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated cost

8 Guidelines of Gender and

Livelihood.

Concerned Upazila Officers

of Department of Women

Affairs, Livestock, Youth

Development, Social

Welfare & NGO Facilitator

(Gender and Livelihood).

ISPMC, Officers of

DWA & BWDB

Jessore/

Narail

1 3 days 30 30 90 150,000.00

9 O&M of Project

Infrastructure & Upfront

contribution

Officers of PMO, SMOs and

Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore/

Narail

1 3 days 30 30 90 150,000.00

10 On-job training for use of

Leveling instrument ,Total

Station,DGPS &

Echosounder

Officers of PMO, SMOs and

Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore/

Narail

1 3 days 30 30 90 150,000.00

Sub-Total Capacity development for officers of PMO,SMOs,Line

Agencies & NGO (Staff Training) (Part-A)

2011 - 12 10 300 900 1500,000.00

Page 236: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

WMO Training 2011-12 Part B

Sl.

No.

Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated

cost

1

Formation of WMO

&Rules of Co-

operatives,

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Cooperatives & BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

2 Drafting of Bylaws of

Water Management

Groups (WMG)

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Cooperatives & BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

3 Procedure for

Registration of WMG

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Cooperatives & BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

4 Procedure for Book

Keeping of WMG

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Cooperatives & BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

5 Operation and

Maintenance (O&M)

of infrastructure

through participatory

water management

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

6 Plantation activities

and

Vegetable Gardening

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Agriculture Extension &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

7 Seed Production &

Compost Preparation

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Agriculture Extension &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

8 Poultry, Goat, Cow

rearing

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Livestock

& BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

Page 237: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Sl.

No.

Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated

cost

9 Meanings and

Functions of

WMG,WMCA/WMCS

,JMC in SAIWRPMP

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Cooperatives & BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

10 Fisheries Extension

Basic Training on

Carp-poly culture,

Nursery

Management, Rice-

Fish Farming, Fish

Culture in Borrow-pit,

Monosex GIFT

Telapia & Sanctuary

Development.

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Fisheries

& BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

11 Integrated Water

Management,

Objective of WMO,

GPWM and its

application, Co-

operatives, Rules.

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Cooperatives & BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

12 Gender Awareness

for WMA Members

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Women

Affairs & BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

13 Salinity of

River/Surface Water

and its Safe use

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Agriculture Extension &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

14 Cultivation of HYV

crop & Crop

diversification (Water

Management,

Fertilizer

Management & Pest

Control)

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of

Agriculture Extension &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

Page 238: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Sl.

No.

Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated

cost

15 Income Generating

Activities for WMG

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Women

Affairs & BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

16 Leadership

Development

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Women

Affairs & BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

17 IPM Techniques for

Crop production

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Women

Affairs & BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

18 Soil Management

and its safe use in

the project area

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Women

Affairs & BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

19 Refreshers course

on Procedure for

Book Keeping of

WMG

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Women

Affairs & BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

20 Refreshers course

on Operation and

Maintenance (O&M)

of infrastructure

through participatory

water management

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Women

Affairs & BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

21 Understanding of the

Concept of

Environment and its

protection from

degradation

WMG Members of NSP

Batch-3(14,15,24,25) and

CSP Batch-2(13,15,)

ISPMC, Officers of

Department of Women

Affairs & BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

Sub-total for WMO Training, 2011-12 126 3780 11340 9450,000.00

Grant Total for 2011-12 136 4080 12240 10950000.00

Page 239: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Southwest Area Integrated Water Resources Planning and Management Project Bangladesh Water Development Board

Training Plan for 2012 – 13

Capacity development for officers of PMO, SMOs,Line Agencies & NGO (Staff Training) Part-A

Sl.

No

Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated

cost

1 Delineation of Sub-unit

Implementation Plan(SIP)

and Sub-project

Implementation

Procedure.

Officers of PMO, SMOs

and Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore

/Narail

1 3 days 30 30 90 150,000.00

2 Communication tools and

techniques

Officers of PMO, SMOs

and Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore

/Narail

1 3 days 30 30 90 150,000.00

3 Participatory Integrated

Water Resources

Management

Officers of PMO, SMOs

and Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore

/Narail

1 3 days 30 30 90 150,000.00

4 Formation of WMO

&Rules of Co-operatives,

Officers of PMO, SMOs and

Staff of NGO (ASG)

ISPMC, Officers

of Department of

Cooperatives &

BWDB Officials.

Jessore

/Narail

1 3 days 30 30 90 150,000.00

5 Agriculture Extension :

Basic training on

Agriculture Extension

Concerned Upazila Officers

of DAE & NGO Facilitator

(Agriculture)

ISPMC, Officers

of Department of

Agriculture

Extension.

Jessore

/Narail

1 3 days 30 30 90 150,000.00

6 Fisheries Extension:

Basic Training on

Fisheries Development.

Concerned Upazila Officers

of Deptt. of Fisheries &

NGO Facilitator (Fisheries)

ISPMC, Officers

of Department of

Fisheries.

Jessore

/Narail

1 3 days 30 30 90 150,000.00

7 Financial Management for

SAIWRPMP

Officers of PMO,

SMOs,RAC & concerned

officers of

Accounts,Audit,Finance Dte.

and Staff of NGO (ASG)

ISPMC, Senior

officers of BWDB

& Resource

persons from

ADB, BRM.

Jessore

/Narail

1 3 days 30 30 90 150,000.00

Page 240: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Sl.

No.

Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated

cost

8 Guidelines of Gender and

Livelihood.

Concerned Upazila Officers

of Department of Women

Affairs, Livestock, Youth

Development, Social

Welfare & NGO Facilitator

(Gender and Livelihood).

ISPMC, Officers

of DWA & BWDB

Jessore

/Narail

1 3 days 30 30 90 150,000.00

9 O&M of Project

Infrastructure & Upfront

contribution

Officers of PMO, SMOs

and Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore

/Narail

1 3 days 30 30 90 150,000.00

10 On-job training for use of

Leveling instrument ,Total

Station,DGPS &

Echosounder

Officers of PMO, SMOs

and Staff of NGO (ASG)

ISPMC & BWDB

Officials.

Jessore

/Narail

1 3 days 30 30 90 150,000.00

Sub-Total Capacity development for officers of

PMO,SMOs,Line Agencies & NGO (Staff Training) (Part-A)

2012 - 13 10 300 900 1500,000.00

Page 241: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

WMO Training(2012-13)

Part-B

Sl.

No.

Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated

cost

1

Formation of WMO

&Rules of Co-operatives,

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Cooperatives &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6

3 days 30 180 540 450,000.00

2 Drafting of Bylaws of

Water Management

Groups (WMG)

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Cooperatives &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

3 Procedure for

Registration of WMG

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Cooperatives &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

4 Procedure for Book

Keeping of WMG

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Cooperatives &

BWDB

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

5 Operation and

Maintenance (O&M) of

infrastructure through

participatory water

management

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

6 Plantation activities and

Vegetable Gardening

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Agriculture Extension

& BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

7 Seed Production &

Compost Preparation

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Agriculture Extension

& BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

Page 242: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Sl.

No.

Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated

cost

8 Poultry, Goat, Cow

rearing

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Livestock & BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

9 Meanings and Functions

of

WMG,WMCA/WMCS,JM

C in SAIWRPMP

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Cooperatives &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

10 Fisheries Extension Basic

Training on Carp-poly

culture, Nursery

Management, Rice-Fish

Farming, Fish Culture in

Borrow-pit, Monosex

GIFT Telapia &

Sanctuary Development.

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Fisheries & BWDB

Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

11 Integrated Water

Management, Objective

of WMO, GPWM and its

application, Co-

operatives, Rules.

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Cooperatives &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

12 Gender Awareness for

WMA Members

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Women Affairs &

BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

13 Salinity of River/Surface

Water and its Safe use

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Agriculture Extension

& BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

Page 243: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Sl.

No.

Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated

cost

14 Cultivation of HYV crop &

Crop diversification

(Water Management,

Fertilizer Management &

Pest Control)

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Agriculture Extension

& BWDB Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

15 Income Generating

Activities for WMG

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Women Affairs &

BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

16 Leadership Development WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Women Affairs &

BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

17 IPM Techniques for Crop

production

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Women Affairs &

BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

18 Soil Management and its

safe use in the project

area

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Women Affairs &

BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

19 Refreshers course on

Procedure for Book

Keeping of WMG

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Women Affairs &

BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

Page 244: CHENCHURI BEEL SUB-PROJECT AREAsouthwest.bwdb.gov.bd/files/report/8001ed4fd0013f... · define the sub-unit as a hydrological entity as far as practicable. 3. SUB PROJECT OVERVIEW

Southwest Area Integrated Water Resources Planning and Management Project, BWDB Annex-H

For all SIP

Sl.

No.

Name of Course Participants Trainers Venue Total

event

Duration Trainee Total

Trainees

Trainee

Days

Estimated

cost

20 Refreshers course on

Operation and

Maintenance (O&M) of

infrastructure through

participatory water

management

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Women Affairs &

BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

21 Understanding of the

Concept of Environment

and its protection from

degradation

WMG Members of NSP

Batch-4(17,18,19) and

CSP Batch-3&4(10-12,4-

9,14)

ISPMC, Officers of

Department of

Women Affairs &

BSIC Officials.

Suitable Venue

at Narail or

Project area.

6 3 days 30 180 540 450,000.00

Sub-total for WMO Training 126 3780 11340 9450,000.00

Grant Total for 2012-13 136 4080 12240 10950000.00