Chapter4 Project Time Management

download Chapter4 Project Time Management

of 28

Transcript of Chapter4 Project Time Management

  • 8/10/2019 Chapter4 Project Time Management

    1/28

    Importance of Project Schedules

    Managers often cite delivering projects on time aof their biggest challenges

    Time has the least amount of flexibility; it passes

    matter what

    Schedule issues are the main reason for conflictsprojects, especially during the second half of proj

  • 8/10/2019 Chapter4 Project Time Management

    2/28

    Project Time Management Process

    Project time management involves the processesrequired to ensure timely completion of a project.

    Processes include:

    Activity definition

    Activity sequencingActivity duration estimating

    Schedule development

    Schedule control

  • 8/10/2019 Chapter4 Project Time Management

    3/28

    Activity Definition

    Project schedules grow out of the basic document th

    initiate a projectProject charter includes start and end dates and

    budget information

    Scope statement and WBS help define what will be

    doneActivity definition involves developing a more detaile

    WBS and supporting explanations to understand all twork to be done so you can develop realistic duratioestimates

  • 8/10/2019 Chapter4 Project Time Management

    4/28

    Activity Sequencing

    Involves reviewing activities and determining

    dependenciesMandatory dependencies: inherent in the nature of

    the work; hard logic

    Discretionary dependencies: defined by the project

    team; soft logicExternal dependencies: involve relationships

    between project and non-project activities

    You mustdetermine dependencies in order to usecritical path analysis

  • 8/10/2019 Chapter4 Project Time Management

    5/28

  • 8/10/2019 Chapter4 Project Time Management

    6/28

    Figure 4-1. Sample Activity-on-Arrow (AOA) Netw

    Diagram for Project X

  • 8/10/2019 Chapter4 Project Time Management

    7/28

    Arrow Diagramming Method (ADM)

    Also called activity-on-arrow (AOA) project networkdiagrams

    Activities are represented by arrows

    Nodes or circles are the starting and ending points

    activities Can only show finish-to-start dependencies

  • 8/10/2019 Chapter4 Project Time Management

    8/28

    Process for Creating AOA Diagrams

    1. Find all of the activities that start at node 1. Draw their finish nodes and

    draw arrows between node 1 and those finish nodes. Put the activity l

    or name and duration estimate on the associated arrow2. Continuing drawing the network diagram, working from left to right. Lo

    for bursts and merges. Burstsoccur when a single node is followed by

    two or more activities. A mergeoccurs when two or more nodes prece

    a single node

    3. Continue drawing the project network diagram until all activities areincluded on the diagram that have dependencies

    4. As a rule of thumb, all arrowheads should face toward the right, and no

    arrows should cross on an AOA network diagram

  • 8/10/2019 Chapter4 Project Time Management

    9/28

    Precedence Diagramming Method (PD

    Activities are represented by boxes Arrows show relationships between activities

    More popular than ADM method and used by project

    management software

    Better at showing different types of dependencies

  • 8/10/2019 Chapter4 Project Time Management

    10/28

    Sample PDM Network Diagram

    4-2

  • 8/10/2019 Chapter4 Project Time Management

    11/28

    Figure 4-3. Task Dependency Types

  • 8/10/2019 Chapter4 Project Time Management

    12/28

    Activity Duration Estimating

    After defining activities and determining their sequencethe next step in time management is duration estimating

    Duration includes the actual amount of time worked on activitypluselapsed time

    Effort is the number of workdays or work hours requiredcomplete a task. Effort does not equal duration

    People doing the work should help create estimates, anan expert should review them

  • 8/10/2019 Chapter4 Project Time Management

    13/28

    Schedule Development

    Schedule development uses results of the other timemanagement processes to determine the start and enddate of the project and its activities

    Ultimate goal is to create a realistic project schedule thaprovides a basis for monitoring project progress for thetime dimension of the project

    Important tools and techniques include Gantt charts,PERT analysis, critical path analysis, and critical chainscheduling

    Gantt Charts

  • 8/10/2019 Chapter4 Project Time Management

    14/28

    Gantt Charts

    Gantt charts provide a standard format for displayingproject schedule information by listing project activities

    and their corresponding start and finish dates in acalendar format

    Symbols include:

    A black diamond: milestones or significant events on a projewith zero duration

    Thick black bars: summary tasks

    Lighter horizontal bars: tasks

    Arrows: dependencies between tasks

  • 8/10/2019 Chapter4 Project Time Management

    15/28

    Figure 4-4. Gantt Chart for Project X

  • 8/10/2019 Chapter4 Project Time Management

    16/28

    Milestones

    Milestones are significant events on a project that normahave zero duration

    You can follow the SMART criteria in developing milestothat are:

    Specific

    MeasurableAssignable

    Realistic

    Time-framed

  • 8/10/2019 Chapter4 Project Time Management

    17/28

    Critical Path Method (CPM)

    CPM is a project network analysis technique used to

    predict total project duration A critical path for a project is the series of activities that

    determines the earliest timeby which the project can be

    completed

    The critical path is the longest paththrough the networkdiagram and has the least amount of slack or float

  • 8/10/2019 Chapter4 Project Time Management

    18/28

    Finding the Critical Path

    First develop a good project network diagram

    Add the durations for all activities on each path throughproject network diagram

    The longest path is the critical path

    Simple Example of Determining th

  • 8/10/2019 Chapter4 Project Time Management

    19/28

    Simple Example of Determining th

    Critical Path

    Consider the following project network diagram. Assum

    times are in days.

    2 3

    4

    5

    A=2 B=5

    C=2

    D=7

    1 6

    F=2

    E=1

    start

    a. How many paths are on this network diagram?

    b. How long is each path?

    c. Which is the critical path?

    d. What is the shortest amount of time needed to complete this project?

    Figure 4-5 Determining the Critical P

  • 8/10/2019 Chapter4 Project Time Management

    20/28

    Figure 4-5. Determining the Critical Pfor Project X

    More on the Critical Path

  • 8/10/2019 Chapter4 Project Time Management

    21/28

    More on the Critical Path

    If one or more activities on the critical path takes longer planned, the whole project schedule will slip unlesscorr

    action is taken Misconceptions:

    The critical path is not the one with all the critical activities; iaccounts for time. Remember the example of growing grasbeing on the critical path for Disneys Animal Kingdom Park

    There can be more than one critical path if the lengths of twomore paths are the same

    The critical path can change as the project progresses

    Using Critical Path Analysis to Ma

  • 8/10/2019 Chapter4 Project Time Management

    22/28

    Using Critical Path Analysis to Ma

    Schedule Trade-offs

    Knowing the critical path helps you make schedule trade-offs

    Free slack or free floatis the amount of time an activity can bedelayed without delaying the early start of any immediately folloactivities

    Total slack or total floatis the amount of time an activity may bedelayed from its early start without delaying the planned project

    finish date A forward passthrough the network diagram determines the ea

    start and finish dates

    A backward passdetermines the late start and finish dates

    Project 2002 Schedule Table View Sho

  • 8/10/2019 Chapter4 Project Time Management

    23/28

    Project 2002 Schedule Table View Sho

    Free and Total Slack

    4-1

    Techniques for Shortening a Proje

  • 8/10/2019 Chapter4 Project Time Management

    24/28

    Techniques for Shortening a ProjeSchedule

    Shorten durations of critical tasks by adding more resou

    or changing their scope

    Crashing tasks by obtaining the greatest amount of

    schedule compression for the least incremental cost

    Fast trackingtasks by doing them in parallel or overlapp

    them

    C hi d F T ki

  • 8/10/2019 Chapter4 Project Time Management

    25/28

    Crashing and Fast Tracking

    Overlapp

    Tasks or tracking

    Shorten

    duration

    crashing

    Original

    schedule

    C iti l Ch i S h d li

  • 8/10/2019 Chapter4 Project Time Management

    26/28

    Critical Chain Scheduling

    Technique that addresses the challenge of meeting or beatingproject finish dates and an application of the Theory of Constra

    (TOC)

    Developed by Eliyahu Goldratt in his books The Goaland CriticChain

    Critical chain scheduling is a method of scheduling that takeslimited resources into account when creating a project schedule

    and includes buffers to protect the project completion date Critical chain scheduling assumes resources do not multitask

    because it often delays task completions and increases totaldurations

    Program Evaluation and Review

  • 8/10/2019 Chapter4 Project Time Management

    27/28

    Program Evaluation and ReviewTechnique (PERT)

    PERT is a network analysis technique used to estimate

    project duration when there is a high degree of uncertain

    about the individual activity duration estimates

    PERT uses probabilistic time estimates based on using

    optimistic, most likely, and pessimistic estimates of activ

    durations

    Controlling Changes to the Projec

  • 8/10/2019 Chapter4 Project Time Management

    28/28

    Controlling Changes to the ProjecSchedule

    Perform reality checks on schedules

    Allow for contingencies

    Dont plan for everyone to work at 100% capacity all the

    time

    Hold progress meetings with stakeholders and be clear honest in communicating schedule issues