Chapter4 Project Time Management
-
Upload
ajayikayode -
Category
Documents
-
view
233 -
download
0
Transcript of Chapter4 Project Time Management
-
8/10/2019 Chapter4 Project Time Management
1/28
Importance of Project Schedules
Managers often cite delivering projects on time aof their biggest challenges
Time has the least amount of flexibility; it passes
matter what
Schedule issues are the main reason for conflictsprojects, especially during the second half of proj
-
8/10/2019 Chapter4 Project Time Management
2/28
Project Time Management Process
Project time management involves the processesrequired to ensure timely completion of a project.
Processes include:
Activity definition
Activity sequencingActivity duration estimating
Schedule development
Schedule control
-
8/10/2019 Chapter4 Project Time Management
3/28
Activity Definition
Project schedules grow out of the basic document th
initiate a projectProject charter includes start and end dates and
budget information
Scope statement and WBS help define what will be
doneActivity definition involves developing a more detaile
WBS and supporting explanations to understand all twork to be done so you can develop realistic duratioestimates
-
8/10/2019 Chapter4 Project Time Management
4/28
Activity Sequencing
Involves reviewing activities and determining
dependenciesMandatory dependencies: inherent in the nature of
the work; hard logic
Discretionary dependencies: defined by the project
team; soft logicExternal dependencies: involve relationships
between project and non-project activities
You mustdetermine dependencies in order to usecritical path analysis
-
8/10/2019 Chapter4 Project Time Management
5/28
-
8/10/2019 Chapter4 Project Time Management
6/28
Figure 4-1. Sample Activity-on-Arrow (AOA) Netw
Diagram for Project X
-
8/10/2019 Chapter4 Project Time Management
7/28
Arrow Diagramming Method (ADM)
Also called activity-on-arrow (AOA) project networkdiagrams
Activities are represented by arrows
Nodes or circles are the starting and ending points
activities Can only show finish-to-start dependencies
-
8/10/2019 Chapter4 Project Time Management
8/28
Process for Creating AOA Diagrams
1. Find all of the activities that start at node 1. Draw their finish nodes and
draw arrows between node 1 and those finish nodes. Put the activity l
or name and duration estimate on the associated arrow2. Continuing drawing the network diagram, working from left to right. Lo
for bursts and merges. Burstsoccur when a single node is followed by
two or more activities. A mergeoccurs when two or more nodes prece
a single node
3. Continue drawing the project network diagram until all activities areincluded on the diagram that have dependencies
4. As a rule of thumb, all arrowheads should face toward the right, and no
arrows should cross on an AOA network diagram
-
8/10/2019 Chapter4 Project Time Management
9/28
Precedence Diagramming Method (PD
Activities are represented by boxes Arrows show relationships between activities
More popular than ADM method and used by project
management software
Better at showing different types of dependencies
-
8/10/2019 Chapter4 Project Time Management
10/28
Sample PDM Network Diagram
4-2
-
8/10/2019 Chapter4 Project Time Management
11/28
Figure 4-3. Task Dependency Types
-
8/10/2019 Chapter4 Project Time Management
12/28
Activity Duration Estimating
After defining activities and determining their sequencethe next step in time management is duration estimating
Duration includes the actual amount of time worked on activitypluselapsed time
Effort is the number of workdays or work hours requiredcomplete a task. Effort does not equal duration
People doing the work should help create estimates, anan expert should review them
-
8/10/2019 Chapter4 Project Time Management
13/28
Schedule Development
Schedule development uses results of the other timemanagement processes to determine the start and enddate of the project and its activities
Ultimate goal is to create a realistic project schedule thaprovides a basis for monitoring project progress for thetime dimension of the project
Important tools and techniques include Gantt charts,PERT analysis, critical path analysis, and critical chainscheduling
Gantt Charts
-
8/10/2019 Chapter4 Project Time Management
14/28
Gantt Charts
Gantt charts provide a standard format for displayingproject schedule information by listing project activities
and their corresponding start and finish dates in acalendar format
Symbols include:
A black diamond: milestones or significant events on a projewith zero duration
Thick black bars: summary tasks
Lighter horizontal bars: tasks
Arrows: dependencies between tasks
-
8/10/2019 Chapter4 Project Time Management
15/28
Figure 4-4. Gantt Chart for Project X
-
8/10/2019 Chapter4 Project Time Management
16/28
Milestones
Milestones are significant events on a project that normahave zero duration
You can follow the SMART criteria in developing milestothat are:
Specific
MeasurableAssignable
Realistic
Time-framed
-
8/10/2019 Chapter4 Project Time Management
17/28
Critical Path Method (CPM)
CPM is a project network analysis technique used to
predict total project duration A critical path for a project is the series of activities that
determines the earliest timeby which the project can be
completed
The critical path is the longest paththrough the networkdiagram and has the least amount of slack or float
-
8/10/2019 Chapter4 Project Time Management
18/28
Finding the Critical Path
First develop a good project network diagram
Add the durations for all activities on each path throughproject network diagram
The longest path is the critical path
Simple Example of Determining th
-
8/10/2019 Chapter4 Project Time Management
19/28
Simple Example of Determining th
Critical Path
Consider the following project network diagram. Assum
times are in days.
2 3
4
5
A=2 B=5
C=2
D=7
1 6
F=2
E=1
start
a. How many paths are on this network diagram?
b. How long is each path?
c. Which is the critical path?
d. What is the shortest amount of time needed to complete this project?
Figure 4-5 Determining the Critical P
-
8/10/2019 Chapter4 Project Time Management
20/28
Figure 4-5. Determining the Critical Pfor Project X
More on the Critical Path
-
8/10/2019 Chapter4 Project Time Management
21/28
More on the Critical Path
If one or more activities on the critical path takes longer planned, the whole project schedule will slip unlesscorr
action is taken Misconceptions:
The critical path is not the one with all the critical activities; iaccounts for time. Remember the example of growing grasbeing on the critical path for Disneys Animal Kingdom Park
There can be more than one critical path if the lengths of twomore paths are the same
The critical path can change as the project progresses
Using Critical Path Analysis to Ma
-
8/10/2019 Chapter4 Project Time Management
22/28
Using Critical Path Analysis to Ma
Schedule Trade-offs
Knowing the critical path helps you make schedule trade-offs
Free slack or free floatis the amount of time an activity can bedelayed without delaying the early start of any immediately folloactivities
Total slack or total floatis the amount of time an activity may bedelayed from its early start without delaying the planned project
finish date A forward passthrough the network diagram determines the ea
start and finish dates
A backward passdetermines the late start and finish dates
Project 2002 Schedule Table View Sho
-
8/10/2019 Chapter4 Project Time Management
23/28
Project 2002 Schedule Table View Sho
Free and Total Slack
4-1
Techniques for Shortening a Proje
-
8/10/2019 Chapter4 Project Time Management
24/28
Techniques for Shortening a ProjeSchedule
Shorten durations of critical tasks by adding more resou
or changing their scope
Crashing tasks by obtaining the greatest amount of
schedule compression for the least incremental cost
Fast trackingtasks by doing them in parallel or overlapp
them
C hi d F T ki
-
8/10/2019 Chapter4 Project Time Management
25/28
Crashing and Fast Tracking
Overlapp
Tasks or tracking
Shorten
duration
crashing
Original
schedule
C iti l Ch i S h d li
-
8/10/2019 Chapter4 Project Time Management
26/28
Critical Chain Scheduling
Technique that addresses the challenge of meeting or beatingproject finish dates and an application of the Theory of Constra
(TOC)
Developed by Eliyahu Goldratt in his books The Goaland CriticChain
Critical chain scheduling is a method of scheduling that takeslimited resources into account when creating a project schedule
and includes buffers to protect the project completion date Critical chain scheduling assumes resources do not multitask
because it often delays task completions and increases totaldurations
Program Evaluation and Review
-
8/10/2019 Chapter4 Project Time Management
27/28
Program Evaluation and ReviewTechnique (PERT)
PERT is a network analysis technique used to estimate
project duration when there is a high degree of uncertain
about the individual activity duration estimates
PERT uses probabilistic time estimates based on using
optimistic, most likely, and pessimistic estimates of activ
durations
Controlling Changes to the Projec
-
8/10/2019 Chapter4 Project Time Management
28/28
Controlling Changes to the ProjecSchedule
Perform reality checks on schedules
Allow for contingencies
Dont plan for everyone to work at 100% capacity all the
time
Hold progress meetings with stakeholders and be clear honest in communicating schedule issues