Chapter 5 Scheduling Tracking Work

download Chapter 5 Scheduling Tracking Work

of 146

description

CC603 Project Management for polytechnic civil department(DKA)

Transcript of Chapter 5 Scheduling Tracking Work

  • CHAPTER 5

    SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT

  • Introduction

    Planning & Scheduling

    Principles

    Techniques

    Work breakdown structure

    Gantt Chart & S-Curve

    Critical Path Method

    Successor/ predecessor relationship

    Arrow Diagram Method and Precedence Diagram Method

  • THE INTEGRATION OF TIME & SUSTAINABLE CONSTRUCTION

    Our focus!!

    Traditional Projects Critical Components (time, cost, & quality); in relation with sustainable construction concept

  • Introduction

    Project planning

    Process of identifying all the activities necessary to successfully complete the project.

    Provides map to guide where to go and focused on how to get there

    Planned in early stage of Project life Cycle or also before site activities start.

  • Introduction

    Importance of planning

    Reduce mistake and rework

    Avoid wastage

    minimize unnecessary in time and cost scheduling

    better quality control

    Effective project progress control

    Effective usage resources

  • Introduction

    Project scheduling

    Process of determining the sequential order of the planned activities, assigning realistic durations to each activity and determining the start and finish dates for each activities.

    it can be used to manage, coordinate, control and report.

    Depending on the sophistication of the user, the schedule can take different forms.

  • Project Scheduling

    Purpose of project scheduling Claim Project time and cost control Allocate project resources more efficiently As a monitoring tool Material delivery at site Storage all material cannot put in the site (confined space) Avoid delay of the work and activity. Minimize the cash flow as min as possible such as order material

    stage by stage depend on the work needed. Control human resources and machinery To improve the efficiency

    of the operation through the efficient use of resources and cost control.

    Project planning is prerequisite to project planning!

  • Desired results of planning and scheduling Finish the project on time.

    Continuous (uninterrupted) flow of work (no delays)

    Reduced amount of rework (least amount of changes)

    Minimized confusion on misunderstandings.

    Increase knowledge of status of project by everyone.

    Meaningful and timely reports to management.

    You run the project instead the project running you.

    Knowledge of scheduled times of key parts of the project.

    Knowledge of the distributions of costs of the project

    Accountability of people, define responsibility/authority.

    Clear understanding of who does what, when & how much.

    Integration of all work to ensure a quality project for the owner.

  • What are the different?

    Planning is more difficult to accomplish than scheduling.

    The term planning and scheduling are often used synonymously.

    Planning is first step to project scheduling.

    Tools used for planning and scheduling are different!

  • Principles of planning and scheduling Begin planning before starting work, rather than after starting

    work. Involve people who will actually do the work in the planning

    and scheduling process. Includes all aspects of the project: scope, budget, schedule &

    quality. Build flexibility into the plan, include allowance for changes and

    time for reviews and approvals. Remember the schedule is the plan for doing the work, and it

    will never be precisely correct. Keep the plan simple, eliminate irrelevant details that prevent

    the plans from being readable. Communicating the plan to all parties; any plan is worthless

    unless it is known.

  • The Collection of Projects Critical Components (should be in equilibrium)

    02468

    101214161820

    COST

    RESOURCES

    SCOPEQUALITY

    TIME

    Client Satisfaction

  • Steps in planning and scheduling

    Scope definition

    Cost Budgeting Cost Estimating

    Activity resource planning

    Activity Duration

    Estimation

    Schedule development

    Activity Sequencing

    Create WBS

    Scope Management

    Time & Resource

    Management

    Cost Management

  • Steps in planning and scheduling

    1. Develop a work breakdown structure (WBS)

    2. Prepare a drawing (network diagram)

    3. Determine the time, cost and resources required

    4. Compute the schedule to determine start, finish and float times

    5. Analyze costs and resources for the project

    6. Communicate the results of the plan and schedule

  • Work breakdown structure (WBS)

    Identifies the tasks and activities that must be performed.

    It divides the project into identifiable parts that can be managed.

    Concept of WBS: in order to manage a whole project, one must manage and control each of its parts.

    It defines: The work to be performed The need of expertise Assist in selection of project team Establish a base of project scheduling and control

  • Work breakdown structure (WBS)

    WBS is display as a graphical or outline method that shows the division of work in a multi level system.

    In developing WBS, we should consider:

    Activities that require time

    Activities that require cost

    Activities that need to arrange

    Activities that need to monitor

  • Work Breakdown Structure (Graphical)

    Construction of one block office building

    Start Project Preliminaries

    Performance bond

    Establish and removal of site

    office

    Block A

    Earthwork

    Structure Work

    Architecture Work

    M&E work

    Testing & Commissioning

    Project complete

    Level 1

    Level 2

    Level 3

  • Work Breakdown Structure (Outline) Construction of one

    block office building Start Project

    Preliminaries

    Performance bond

    Establish and removal of site office

    Block A

    Earthwork

    Structure Work

    Architecture Work

    M&E work

    Testing and Commissioning

    Project complete

  • Work breakdown structure (WBS) Importance of WBS

    Overall program can be explain in summary according to each sub-element divided.

    Planning could execute. Cost and budget could estimate more accurately. Time, Cost and Performance of each element could be

    monitor from time to time. Objective could be relate directly with the available

    resources in the company. Network diagram and control planning could be prepared

    in early stages. Responsibilities for each parties involve in every element

    could be identify and assign.

  • Work breakdown structure (WBS)

    Example:

    You are the Project Manager for a Construction of Proposed Construction and Completion of a Double Storey Bungalow House And Related Works For Messrs. Dato 'Kamal Jaafar. Develop a preliminary graphical work breakdown structure (up to level 4) for the project given. Your WBS should complete with all works needs in completing a one unit bungalow.

  • Example (WBS-Graphical Method)

    Proposed Construction and Completion of A Double Storey Bungalow House and Related Works for Messrs. Dato 'Kamal Jaafar.

    Preliminary works

    Performance bond

    Progress Report

    Building works

    Structure

    Foundation

    Ground level

    1st floor level

    2nd floor level

    Architecture

    Wall

    Floor

    Roof

    Fittings

    M&E

    Wiring

    Fittings installation

    External works

    Sewerage

    Road and drainage

    Landscape

    Level 1

    Level 2

    Level 3

    Level 4

  • Exercise (Outline Method)

    Proposed Construction and Completion of A Double Storey Bungalow House and

    Related Works for Messrs. Dato 'Kamal Jaafar.

  • Techniques for scheduling

    Techniques used will vary depending on: Projects size Complexity Duration Personnel Owner requirements

    Two general methods commonly used : Bar chart (Gantt chart) Critical path method (CPM/ network analysis

    system)

  • Develop by Henry L.Gantt

    Is a graphical time-scale of the schedule, length represent the duration of activity.

  • Advantages

    Easy to interpret

    Simplicity & ease of preparation and understanding (Simple graphical).

    No theory or complicated calculation involved (Easy for general comprehension).

    Time-scaled (the length of the bar representing certain activity is proportional to the duration of that activity.

    Appeal to persons who do not have a technical background

    Wide spread used in industry

    Mostly used in small project

    Fairly broad planning and scheduling tools, so they require less revision and updating than more sophisticated systems

    Disadvantages

    Difficult to update

    Very cumbersome as the number of line activities, or bars increases

    Does not integrate costs or resources with the schedule

    Limited application for detail construction work

    Difficult to use it for forecasting the effects that changes in a particular activity will have on the overall schedule

  • No. Description Month 1 2 3 4 5 6 7 8 9 10

    1 Mobilization

    2 Foundation Excavation

    3 Diversion Stage

    4 Foundation Grouting

    5 Dam Concrete

    6 Install Outlet Gates

    7 Install Trash Racks

    8 Prestress

    9 Radial Gates

    10 Spillway Bridge

    11 Curtain Grout

    12 Dismantle Plant, Clean Up

    Original Schedule

    Actual progress

    Bar chart basically use x-axis only (to depict time). The y-axis is use to show individual activities, to represent a variable across time

    (e.g.: man-hours, budget, % complete and so forth.

    Bar chart (Gantt Chart)

  • No. Description Month 1 2 3 4 5 6 7 8 9 10

    1 Mobilization

    2 Foundation Excavation

    3 Diversion Stage

    4 Foundation Grouting

    5 Dam Concrete

    6 Install Outlet Gates

    7 Install Trash Racks

    8 Prestress

    9 Radial Gates

    10 Spillway Bridge

    11 Curtain Grout

    12 Dismantle Plant, Clean Up

    Original Schedule

    Actual progress

    Cu

    mu

    lati

    ve p

    rogr

    ess

    (%)

    100

    0

    Bar chart basically use x-axis only (to depict time). The y-axis is use to show individual activities, to represent a variable across time (e.g.: man-hours,

    budget, % complete and so forth. The variables usually shown as a curve superimposed on the bar chart.

    Bar chart (Gantt Chart) + S curve

  • Bar chart (Gantt Chart)

    Tutorial No.2: A project consist of five activities that should be

    done in a period of time. Try to create a bar chart to ease the project planning and scheduling.

    * consider 1 week as 7 days

    Activity A : 1 week, starting from 1 Jun 2015 Activity B : 2 week, starting from 8 Jun 2015 Activity C : 3 week, starting from 15 Jun 2015 Activity D : 2 week, starting from 22 Jun 2015 Activity E : 2 week, starting from 29 Jun 2015

  • Bar chart (Gantt Chart)-Example 1

    Step 1: identify start date and finish date for each activity Activity A : 1 week, starting from 1 Jun 2014 (1/6-7/6)

    Activity B : 2 week, starting from 8 Jun 2014 (8/6-21/6)

    Activity C : 3 week, starting from 15 Jun 2014 (15/6-5/7)

    Activity D : 2 week, starting from 22 Jun 2014 (22/6-5/7)

    Activity E : 2 week, starting from 29 Jun 2014 (29/6-12/7)

  • Bar chart (Gantt Chart)-Example 1

    Step 2: Draw outline of bar chart

    Activity Duration (week)

    Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

    1/6 8/6 15/6 22/6 29/6 6/7

    Act. A 1

    Act. B 2

    Act. C 3

    Act. D 2

    Act. E 2

  • Bar chart (Gantt Chart)-Example 1

    Activity Duration (week)

    Week 1 Week 2 Week 3 Week 4 Week 5 Week 6

    1/6 8/6 15/6 22/6 29/6 6/7

    Act. A 1

    Act. B 2

    Act. C 3

    Act. D 2

    Act. E 2

    Step 3: Draw the activity bars

    Activity A : 1 week, starting from 1 Jun 2014 (1/6-7/6) Activity B : 2 week, starting from 8 Jun 2014 (8/6-21/6) Activity C : 3 week, starting from 15 Jun 2014 (15/6-5/7) Activity D : 2 week, starting from 22 Jun 2014 (22/6-5/7) Activity E : 2 week, starting from 29 Jun 2014 (29/6-12/7)

  • Bar chart (Gantt Chart)-Example 2

    Num Activity Duration (days)

    Start Date Cost (RM)

    Resources/ day

    (person)

    Work progress

    percentage (%)

    1 Activity A 3 4/5/2014 1,400.00 2 12

    2 Activity B 5 7/5/2014 2,700.00 3 30

    3 Activity C 7 10/5/2014 3,500.00 2 21

    4 Activity D 5 15/5/2014 6,000.00 4 10

    5 Activity E 4 17/5/2014 4,700.00 4 12

    6 Activity F 6 19/5/2014 12,600.00 5 15

    30,900.00 100

  • Bar chart (Gantt Chart)-Example 2

    Step 1: identify start date and finish date for each activity Activity A : 3 days, starting from 4 May 2014 (4/5-6/5)

    Activity B : 5 days, starting from 7 May 2014 (7/5-11/5)

    Activity C : 7 days, starting from 10 May 2014 (10/5-16/5)

    Activity D : 5 days, starting from 15 May 2014 (15/5-19/5)

    Activity E : 4 days, starting from 17 May 2014 (17/5-20/5)

    Activity F : 6 days, starting from 19 May 2014 (19/5-24/5)

  • Bar chart (Gantt Chart)-Example 2

    Step 2: Draw outline of bar chart

    Activity Duration (days) 4

    /5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11

    /5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18

    /5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3

    Act. B 5

    Act. C 7

    Act. D 5

    Act. E 4

    Act. F 6

  • Bar chart (Gantt Chart)-Example 2

    Step 3: Draw the activity bars

    Activity Duration (days) 4

    /5

    5/5

    6/5

    7/5

    8/5

    9/5

    10/5

    11/5

    12/5

    13/5

    14/5

    15/5

    16/5

    17/5

    18/5

    19/5

    20/5

    21/5

    22/5

    23/5

    24/5

    Act. A 3

    Act. B 5

    Act. C 7

    Act. D 5

    Act. E 4

    Act. F 6

    Activity A : (4/5-6/5) Activity B : (7/5-11/5) Activity C : (10/5-16/5) Activity D : (15/5-19/5) Activity E : (17/5-20/5) Activity F : (19/5-24/5)

  • An S-curve is defined as:

    "A display of cumulative costs, labor hours or other quantities plotted against time. The name derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the middle, which is typical of most projects. The beginning represents a slow, deliberate but accelerating start, while the end represents a deceleration as the work runs out."

  • S-Curve

    Type of S-Curve

    Physical S-Curve

    Financial S-Curve

    Both S-curve can be in Baseline (planned) or actual S-curve

  • S-Curve (Example) Num Activity Duration

    (days) Start Date Cost (RM)

    Resources/

    day (person)

    Work progress

    percentage (%)

    1 Activity A 3 4/5/2014 1,400.00 2 12

    2 Activity B 5 7/5/2014 2,700.00 3 30

    3 Activity C 7 10/5/2014 3,500.00 2 21

    4 Activity D 5 15/5/2014 6,000.00 4 10

    5 Activity E 4 17/5/2014 4,700.00 4 12

    6 Activity F 6 19/5/2014 12,600.00 5 15

    30,900.00 100

    Based on bar chart in Example 2, construct S-curve (daily basis) for this project: 1. Financial S-Curve 2. Physical S-curve (resources vs time & work vs time)

  • Financial S-Curve

  • Financial S-Curve

    Activity Duration (days)

    Cost (RM)

    Cost/day (RM) 4/

    5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11

    /5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18

    /5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 1,400

    Act. B 5 2,700

    Act. C 7 3,500

    Act. D 5 6,000

    Act. E 4 4,700

    Act. F 6 12,600

    Cost/day

    Cumulative cost/day

    STEP 1: DRAW BAR CHART (from Example 2), include Cost of each activity

  • Financial S-Curve

    Activity Duration (days)

    Cost (RM)

    Cost/day (RM) 4/

    5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11

    /5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18

    /5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 1,400

    Act. B 5 2,700

    Act. C 7 3,500

    Act. D 5 6,000

    Act. E 4 4,700

    Act. F 6 12,600

    Cost/day

    Cumulative cost/day

    =1,400/3

    =2,700/5

    =3,500/7

    =6,000/5

    =4,700/4

    =12,600/6

    467

    540

    500

    1200

    1175

    2100

    STEP 2: Calculate COST/ DAY = Cost / duration

  • Financial S-Curve

    Activity Duration (days)

    Cost (RM)

    Cost/day (RM) 4/

    5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11

    /5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18

    /5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 1,400

    Act. B 5 2,700

    Act. C 7 3,500

    Act. D 5 6,000

    Act. E 4 4,700

    Act. F 6 12,600

    Cost/day

    Cumulative cost/day

    467

    540

    500

    1200

    1175

    2100

    STEP 2: Calculate COST/ DAY = Cost / duration

  • Activity Duration (days)

    Cost (RM)

    Cost/day (RM) 4/

    5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11

    /5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18

    /5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 1,400

    Act. B 5 2,700

    Act. C 7 3,500

    Act. D 5 6,000

    Act. E 4 4,700

    Act. F 6 12,600

    Cost/day

    Cumulative cost/day

    Financial S-Curve

    467

    540

    500

    1200

    1175

    2100

    STEP 3: Calculate the TOTAL COST of each DAY

    46

    7

    10

    40

    46

    7

    46

    7

    10

    40

    5

    00

    5

    00

    5

    00

    1

    70

    0

    17

    00

    2

    37

    5

    23

    75

    4

    47

    5

    32

    75

    2

    10

    0

    21

    00

    2

    10

    0

    21

    00

    54

    0

    54

    0

    54

    0

    540 +500

  • Activity Duration (days)

    Cost (RM)

    Cost/day (RM) 4/

    5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11

    /5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18

    /5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 1,400

    Act. B 5 2,700

    Act. C 7 3,500

    Act. D 5 6,000

    Act. E 4 4,700

    Act. F 6 12,600

    Cost/day

    Cumulative cost/day

    Financial S-Curve

    467

    540

    500

    1200

    1175

    2100

    STEP 4: Calculate the CUMULATIVE COST of each DAY

    46

    7

    10

    40

    46

    7

    46

    7

    10

    40

    5

    00

    5

    00

    5

    00

    1

    70

    0

    17

    00

    2

    37

    5

    23

    75

    4

    47

    5

    32

    75

    2

    10

    0

    21

    00

    2

    10

    0

    21

    00

    54

    0

    54

    0

    54

    0

    46

    7

    93

    4

    1941

    24

    81

    3021

    40

    61

    5101

    56

    01

    6101

    66

    01

    8301

    10

    01

    1237

    6

    1475

    1

    1922

    6

    2250

    1

    2460

    1

    2670

    1

    2880

    1

    3090

    1

    Cumulative cost (previous) + current cost/day = 467 + 467

    Cumulative cost (previous) + current cost/day = 934 + 467

    10

    41

  • Financial S-Curve

    Activity Duration (days)

    Cost (RM)

    Cost/da y (RM) 4/

    5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11

    /5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18

    /5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 1,400

    Act. B 5 2,700

    Act. C 7 3,500

    Act. D 5 6,000

    Act. E 4 4,700

    Act. F 6 12,600

    Cost/day

    Cumulative cost/day

    467

    540

    500

    1200

    1175

    2100

    30900

    25750

    20600

    15450

    10300

    5150

    0

    46

    7

    10

    40

    46

    7

    46

    7

    54

    0

    54

    0

    54

    0

    10

    40

    5

    00

    5

    00

    5

    00

    1

    70

    0

    17

    00

    2

    37

    5

    23

    75

    4

    47

    5

    32

    75

    2

    10

    0

    21

    00

    2

    10

    0

    21

    00

    46

    7

    93

    4

    10

    41

    1

    94

    1

    24

    81

    3

    02

    1

    40

    61

    5

    10

    1

    56

    01

    6

    10

    1

    66

    01

    8

    30

    1

    10

    00

    1

    12

    37

    6

    14

    75

    1

    19

    22

    6

    22

    50

    1

    24

    60

    1

    26

    70

    1

    28

    80

    1

    30

    90

    1

    STEP 5: Plot graph base on cumulative cost

    Start from 0

    Total cumulative cost

    Get the medium (30900 /2)

    Start from 0

    467 934 1041

  • Financial S-Curve

    Activity Duration (days)

    Cost (RM)

    Cost/da y (RM) 4/

    5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11

    /5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18

    /5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 1,400

    Act. B 5 2,700

    Act. C 7 3,500

    Act. D 5 6,000

    Act. E 4 4,700

    Act. F 6 12,600

    Cost/day

    Cumulative cost/day

    467

    540

    500

    1200

    1175

    2100

    30900

    25750

    20600

    15450

    10300

    5150

    0

    46

    7

    10

    40

    46

    7

    46

    7

    54

    0

    54

    0

    54

    0

    10

    40

    5

    00

    5

    00

    5

    00

    1

    70

    0

    17

    00

    2

    37

    5

    23

    75

    4

    47

    5

    32

    75

    2

    10

    0

    21

    00

    2

    10

    0

    21

    00

    46

    7

    93

    4

    10

    41

    1

    94

    1

    24

    81

    3

    02

    1

    40

    61

    5

    10

    1

    56

    01

    6

    10

    1

    66

    01

    8

    30

    1

    10

    00

    1

    12

    37

    6

    14

    75

    1

    19

    22

    6

    22

    50

    1

    24

    60

    1

    26

    70

    1

    28

    80

    1

    30

    90

    1

    STEP 5: Plot graph base on cumulative cost

  • Physical S-Curve (resources VS time)

  • Num Activity Duration (days)

    Start Date Cost (RM)

    Resources/ day

    (person)

    Work progress

    percentage (%)

    1 Activity A 3 4/5/2014 1,400.00 2 12

    2 Activity B 5 7/5/2014 2,700.00 3 30

    3 Activity C 7 10/5/2014 3,500.00 2 21

    4 Activity D 5 15/5/2014 6,000.00 4 10

    5 Activity E 4 17/5/2014 4,700.00 4 12

    6 Activity F 6 19/5/2014 12,600.00 5 15

    30,900.00 100

  • Physical S-Curve (resources VS time)

    Activity Duration (days)

    Resource/ day

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 2

    Act. B 5 3

    Act. C 7 2

    Act. D 5 4

    Act. E 4 4

    Act. F 6 5

    Resource/day

    Cumulative resource/day

    STEP 1: DRAW BAR CHART (from Example 2), include resource/day for each activity

    2

    2

    2 3

    3

    3

    5

    5 2

    2

    2

    6

    6

    8

    8

    13

    9

    5

    5

    5

    5

  • Physical S-Curve (resources VS time)

    Activity Duration (days)

    Resource/ day

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 2

    Act. B 5 3

    Act. C 7 2

    Act. D 5 4

    Act. E 4 4

    Act. F 6 5

    Resource/day 2

    2

    2

    3

    3

    3

    5

    5

    2

    2

    2

    6

    6

    8

    8

    13

    9

    5

    5

    5

    5

    Cumulative resource/day

    STEP 2: Calculate the CUMULATIVE resource of each DAY

    Cumulative resource (previous) + current resource/day = 2 + 2

    2

    4

    6

    9

    12

    1

    5

    20

    2

    5

    27

    2

    9

    31

    3

    7

    43

    5

    1

    59

    7

    2

    81

    8

    6

    91

    9

    6

    10

    1

  • Physical S-Curve (resources VS time)

    Activity Duration (days)

    Resource/ day

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 2

    Act. B 5 3

    Act. C 7 2

    Act. D 5 4

    Act. E 4 4

    Act. F 6 5

    Resource/day 2

    2

    2

    3

    3

    3

    5

    5

    2

    2

    2

    6

    6

    8

    8

    13

    9

    5

    5

    5

    5

    Cumulative resource/day

    STEP 3: Plot graph base on cumulative resource

    2

    4

    6

    9

    12

    1

    5

    20

    2

    5

    27

    2

    9

    31

    3

    7

    43

    5

    1

    59

    7

    2

    81

    8

    6

    91

    9

    6

    10

    1

  • Physical S-Curve (resources VS time)

    Activity Duration (days)

    Resource/ day

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 2

    Act. B 5 3

    Act. C 7 2

    Act. D 5 4

    Act. E 4 4

    Act. F 6 5

    Resource/day 2

    2

    2

    3

    3

    3

    5

    5

    2

    2

    2

    6

    6

    8

    8

    13

    9

    5

    5

    5

    5

    Cumulative resource/day 2 4 6 9 12

    15

    20

    25

    27

    29

    31

    37

    43

    51

    59

    72

    81

    86

    91

    96

    10

    1

    102

    85

    68

    51

    34

    17

    0

    STEP 3: Plot graph base on cumulative resource

    Start from 0

    Total cumulative resource

    102/6 = 17

    102/6 x 2 = 34

  • Physical S-Curve (resources VS time)

    Activity Duration (days)

    Resource/ day

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 2

    Act. B 5 3

    Act. C 7 2

    Act. D 5 4

    Act. E 4 4

    Act. F 6 5

    Resource/day 2

    2

    2

    3

    3

    3

    5

    5

    2

    2

    2

    6

    6

    8

    8

    13

    9

    5

    5

    5

    5

    Cumulative resource/day 2 4 6 9 12

    15

    20

    25

    27

    29

    31

    37

    43

    51

    59

    72

    81

    86

    91

    96

    10

    1

    102

    85

    68

    51

    34

    17

    0

    STEP 3: Plot graph base on cumulative resource

  • Physical S-Curve (work VS time)

  • Num Activity Duration (days)

    Start Date Cost (RM)

    Resources/ day

    (person)

    Work progress

    percentage (%)

    1 Activity A 3 4/5/2014 1,400.00 2 12

    2 Activity B 5 7/5/2014 2,700.00 3 30

    3 Activity C 7 10/5/2014 3,500.00 2 21

    4 Activity D 5 15/5/2014 6,000.00 4 10

    5 Activity E 4 17/5/2014 4,700.00 4 12

    6 Activity F 6 19/5/2014 12,600.00 5 15

    30,900.00 100

  • Physical S-Curve (work VS time)

    Activity Duration (days)

    Work progress

    percentage (%)

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 12

    Act. B 5 30

    Act. C 7 21

    Act. D 5 10

    Act. E 4 12

    Act. F 6 15

    Work progress/day

    Cumulative work progress/day

    STEP 1: DRAW BAR CHART (from Example 2), include work progress

    percentage/day for each activity

  • Physical S-Curve (work VS time)

    Activity Duration (days)

    Work progress

    percentage (%)

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 12

    Act. B 5 30

    Act. C 7 21

    Act. D 5 10

    Act. E 4 12

    Act. F 6 15

    Work progress/day

    Cumulative work progress/day

    STEP 2: Calculate work progress percentage of each day for every activities

    12% / 3 days = 4%/ day 4 4 4

    30% / 5days = 6%/ day 6 6 6 6 6

    3 3 3 3 3 3 3

    2 2 2 2 2

    3 3 3 3

    2.5 2.5 2.5 2.5 2.5 2.5

  • Physical S-Curve (work VS time)

    Activity Duration (days)

    Work progress

    percentage (%)

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 12

    Act. B 5 30

    Act. C 7 21

    Act. D 5 10

    Act. E 4 12

    Act. F 6 15

    Work progress/day

    Cumulative work progress/day

    4

    9

    4

    4

    9

    3

    3

    3

    5

    5

    5

    5

    7.5

    5

    .5

    2.5

    2

    .5

    2.5

    2

    .5

    6

    6

    6

    6 +3

    4 4 4

    6 6 6 6 6

    3 3 3 3 3 3 3

    2 2 2 2 2

    3 3 3 3

    2.5 2.5 2.5 2.5 2.5 2.5

    STEP 2: Calculate work progress percentage of each day

  • Physical S-Curve (work VS time)

    Activity Duration (days)

    Work progress

    percentage (%)

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 12

    Act. B 5 30

    Act. C 7 21

    Act. D 5 10

    Act. E 4 12

    Act. F 6 15

    Work progress/day

    Cumulative work progress/day

    4

    9

    4

    4

    9

    3

    3

    3

    5

    5

    5

    5

    7.5

    5

    .5

    2.5

    2

    .5

    2.5

    2

    .5

    6

    6

    6

    4 4 4

    6 6 6 6 6

    3 3 3 3 3 3 3

    2 2 2 2 2

    3 3 3 3

    2.5 2.5 2.5 2.5 2.5 2.5

    STEP 3: Calculate cumulative work progress percentage of each day

  • Physical S-Curve (work VS time)

    Activity Duration (days)

    Work progress

    percentage (%)

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 12

    Act. B 5 30

    Act. C 7 21

    Act. D 5 10

    Act. E 4 12

    Act. F 6 15

    Work progress/day

    Cumulative work progress/day

    4

    8

    12

    18

    24

    30

    39

    48

    51

    54

    57

    62

    67

    72

    77

    84

    .5

    90

    92

    .5

    95

    97

    .5

    10

    0

    4

    9

    4

    4

    9

    3

    3

    3

    5

    5

    5

    5

    7.5

    5

    .5

    2.5

    2

    .5

    2.5

    2

    .5

    6

    6

    6

    4 4 4

    6 6 6 6 6

    3 3 3 3 3 3 3

    2 2 2 2 2

    3 3 3 3

    2.5 2.5 2.5 2.5 2.5 2.5

    STEP 3: Calculate cumulative work progress percentage of each day

  • Physical S-Curve (work VS time)

    Activity Duration (days)

    Work progress

    percentage (%)

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 12

    Act. B 5 30

    Act. C 7 21

    Act. D 5 10

    Act. E 4 12

    Act. F 6 15

    Work progress/day

    Cumulative work progress/day

    4

    8

    12

    18

    24

    30

    39

    48

    51

    54

    57

    62

    67

    72

    77

    84

    .5

    90

    92

    .5

    95

    97

    .5

    10

    0

    4

    9

    4

    4

    9

    3

    3

    3

    5

    5

    5

    5

    7.5

    5

    .5

    2.5

    2

    .5

    2.5

    2

    .5

    6

    6

    6

    4 4 4

    6 6 6 6 6

    3 3 3 3 3 3 3

    2 2 2 2 2

    3 3 3 3

    2.5 2.5 2.5 2.5 2.5 2.5

    STEP 4: Plot S-curve

  • Physical S-Curve (work VS time)

    Activity Duration (days)

    Work progress

    percentage (%)

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 12

    Act. B 5 30

    Act. C 7 21

    Act. D 5 10

    Act. E 4 12

    Act. F 6 15

    Work progress/day

    Cumulative work progress/day

    4

    8

    12

    18

    24

    30

    39

    48

    51

    54

    57

    62

    67

    72

    77

    84

    .5

    90

    92

    .5

    95

    97

    .5

    10

    0

    4

    9

    4

    4

    9

    3

    3

    3

    5

    5

    5

    5

    7.5

    5

    .5

    2.5

    2

    .5

    2.5

    2

    .5

    6

    6

    6

    4 4 4

    6 6 6 6 6

    3 3 3 3 3 3 3

    2 2 2 2 2

    3 3 3 3

    2.5 2.5 2.5 2.5 2.5 2.5

    STEP 4: Plot S-curve

    100

    75

    50

    25

    0

  • Physical S-Curve (work VS time)

    Activity Duration (days)

    Work progress

    percentage (%)

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 12

    Act. B 5 30

    Act. C 7 21

    Act. D 5 10

    Act. E 4 12

    Act. F 6 15

    Work progress/day

    Cumulative work progress/day

    4

    8

    12

    18

    24

    30

    39

    48

    51

    54

    57

    62

    67

    72

    77

    84

    .5

    90

    92

    .5

    95

    97

    .5

    10

    0

    4

    9

    4

    4

    9

    3

    3

    3

    5

    5

    5

    5

    7.5

    5

    .5

    2.5

    2

    .5

    2.5

    2

    .5

    6

    6

    6

    4 4 4

    6 6 6 6 6

    3 3 3 3 3 3 3

    2 2 2 2 2

    3 3 3 3

    2.5 2.5 2.5 2.5 2.5 2.5

    STEP 4: Plot S-curve

    100

    75

    50

    25

    0

  • Physical S-Curve (work VS time)

    Activity Duration (days)

    Work progress

    percentage (%)

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10

    /5

    11/5

    12

    /5

    13

    /5

    14

    /5

    15

    /5

    16

    /5

    17

    /5

    18/5

    19

    /5

    20

    /5

    21

    /5

    22

    /5

    23

    /5

    24

    /5

    Act. A 3 12

    Act. B 5 30

    Act. C 7 21

    Act. D 5 10

    Act. E 4 12

    Act. F 6 15

    Work progress/day

    Cumulative work progress/day

    4

    8

    12

    18

    24

    30

    39

    48

    51

    54

    57

    62

    67

    72

    77

    84

    .5

    90

    92

    .5

    95

    97

    .5

    10

    0

    4

    9

    4

    4

    9

    3

    3

    3

    5

    5

    5

    5

    7.5

    5

    .5

    2.5

    2

    .5

    2.5

    2

    .5

    6

    6

    6

    4 4 4

    6 6 6 6 6

    3 3 3 3 3 3 3

    2 2 2 2 2

    3 3 3 3

    2.5 2.5 2.5 2.5 2.5 2.5

    STEP 4: Plot S-curve

    100

    75

    50

    25

    0

  • Planning VS Actual S-curve??

    Before this, we just create a planning bar chart.

    What if, the real activities has started? How to create actual S-curve?

  • Planning VS Actual S-curve (Example 2) Physical S-Curve (work vs time)

    Num. Activity Duration (days)

    Start Date Actual Start Date

    Actual Finish Date

    Cost (RM)

    Resources (person)

    1 Activity A 3 4/5/2014 4/5/2014 6/5/2014 1,400.00 2

    2 Activity B 5 7/5/2014 7/5/2014 12/5/2014 2,700.00 3

    3 Activity C 7 10/5/2014 11/5/2014 17/5/2014 3,500.00 2

    4 Activity D 5 15/5/2014 17/5/2014 21/5/2014 6,000.00 4

    5 Activity E 4 17/5/2014 18/5/2014 22/5/2014 4,700.00 4

    6 Activity F 6 19/5/2014 21/5/2014 26/5/2014 12,600.00 5

    30,900.00

  • Planning VS Actual S-curve Activity Duration

    (days) Start Date

    Actual Start Date

    Actual Finish Date

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10/5

    11/5

    12/5

    13/5

    14/5

    15/5

    16/5

    17/5

    18/5

    19/5

    20/5

    21/5

    22/5

    23/5

    24/5

    25/5

    26/5

    Act. A 3 4/5/14 4/5/14 6/5/14

    Act. B 5 7/5/14 7/5/14 12/5/14

    Act. C 7 10/5/14 11/5/14 17/5/14

    Act. D 5 15/5/14

    17/5/14 21/5/14

    Act. E 4 17/5/14 18/5/14 22/5/14

    Act. F 6 19/5/14 21/5/14 26/5/14

    Planning cumulative work / day

    Actual cumulative work/ day

    STEP 1: DRAW BAR CHART (planning and actual)

    Planning

    Actual

  • Planning VS Actual S-curve Activity Duration

    (days) Start Date

    Actual Start Date

    Actual Finish Date

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10/5

    11/5

    12/5

    13/5

    14/5

    15/5

    16/5

    17/5

    18/5

    19/5

    20/5

    21/5

    22/5

    23/5

    24/5

    25/5

    26/5

    Act. A 3 4/5/14 4/5/14 6/5/14

    Act. B 5 7/5/14 7/5/14 12/5/14

    Act. C 7 10/5/14 11/5/14 17/5/14

    Act. D 5 15/5/14

    17/5/14 21/5/14

    Act. E 4 17/5/14 18/5/14 22/5/14

    Act. F 6 19/5/14 21/5/14 26/5/14

    Planning cumulative work / day

    Actual cumulative work/ day

    STEP 2: Calculate cumulative for both planning & actual work/day

  • Activity Duration (days)

    Start Date

    Actual Start Date

    Actual Finish Date

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10/5

    11/5

    12/5

    13/5

    14/5

    15/5

    16/5

    17/5

    18/5

    19/5

    20/5

    21/5

    22/5

    23/5

    24/5

    25/5

    26/5

    Act. A 3 4/5/14 4/5/14 6/5/14

    Act. B 5 7/5/14 7/5/14 12/5/14

    Act. C 7 10/5/14 11/5/14 17/5/14

    Act. D 5 15/5/14

    17/5/14 21/5/14

    Act. E 4 17/5/14 18/5/14 22/5/14

    Act. F 6 19/5/14 21/5/14 26/5/14

    Planning cumulative work / day 1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30

    Actual cumulative work/ day 1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32

    STEP 2: Calculate cumulative for both planning & actual work/day

    Planning VS Actual S-curve

  • Activity Duration (days)

    Start Date

    Actual Start Date

    Actual Finish Date

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10/5

    11/5

    12/5

    13/5

    14/5

    15/5

    16/5

    17/5

    18/5

    19/5

    20/5

    21/5

    22/5

    23/5

    24/5

    25/5

    26/5

    Act. A 3 4/5/14 4/5/14 6/5/14

    Act. B 5 7/5/14 7/5/14 12/5/14

    Act. C 7 10/5/14 11/5/14 17/5/14

    Act. D 5 15/5/14

    17/5/14 21/5/14

    Act. E 4 17/5/14 18/5/14 22/5/14

    Act. F 6 19/5/14 21/5/14 26/5/14

    Planning cumulative work / day 1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30

    Actual cumulative work/ day 1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32

    Planning VS Actual S-curve STEP 3: Plot the S -curves

  • Activity Duration (days)

    Start Date

    Actual Start Date

    Actual Finish Date

    4/5

    5/5

    6/5

    7/5

    8/5

    9/5

    10/5

    11/5

    12/5

    13/5

    14/5

    15/5

    16/5

    17/5

    18/5

    19/5

    20/5

    21/5

    22/5

    23/5

    24/5

    25/5

    26/5

    Act. A 3 4/5/14 4/5/14 6/5/14

    Act. B 5 7/5/14 7/5/14 12/5/14

    Act. C 7 10/5/14 11/5/14 17/5/14

    Act. D 5 15/5/14

    17/5/14 21/5/14

    Act. E 4 17/5/14 18/5/14 22/5/14

    Act. F 6 19/5/14 21/5/14 26/5/14

    Planning cumulative work / day 1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30

    Actual cumulative work/ day 1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32

    Planning

    Actual

    STEP 3: Plot the S -curves

    Planning VS Actual S-curve

  • Arrow Diagram Method (ADM) -Activity-on-Arrow (AOA) Network

    Precedence Diagram Method (PDM) - Activity-on-Nodes (AON) Network

  • Network Diagram Activity on Arrow (AOA)/ Arrow Diagram

    Method (ADM) In arrow diagram project task or activities are

    represented by the arrow and connected by the node to express their logical relationship

    Node represents an event. An activity starts or ends at a node.

    Activity A

    Node

    Activity B

    Node Node

  • ADM

    Pour concrete Fixed rebar Fixed fwk

    Fabricated rebar

    Excavate trench

    Fabricated formwork

    Diagram for construction of pad footing

  • Network Diagram Activity on Node (AON)/ Precedence Diagram

    Method (PDM)

    activity is place on the node

    The arrow used to connect between project task to show their logical relationship

    Act. A Act. B

    Node Node

  • Network Diagram

    Diagram for construction of pad footing Arrow - Logical Node - Activity Logical Show the relationship between activities - Sequences of interrelated activity

  • Basic definition in network diagram

    Activity- the performance of a task required to complete the project. An activity require time, cost, or both.

    Network- a diagram to represent the relationship of activities to complete a project. The network may be drawn as ADM or PDM.

    Duration- the estimated time required to perform an activity.

  • Activity Sequencing

    Understand the order of how the job to be accomplished in the field.

    The planner must understand how various activities of the project related to each other in term of their logical sequence.

    Example preparing formwork before reinforcement could be place & than pouring concrete.

  • Activity Sequencing

    Predecessor

    A task whose start or finish date determines the start or finish date of its successor task.

    Successor

    A task whose start or finish date is driven by its predecessor task.

  • ADM vs. PDM

    Item ADM PDM

    Activity

    Activities shown as an arrow or sometimes as a line.

    ES: Early Start LS: Late Start

    EF: Early Finish LF: Late Finish

    D : Duration TF: Total Float

    Activities shown on node.

    Event/ Node

    2 events / nodes

    1 event

    A ES EF

    LS LF

    A

    D

    TF

    ES EF

    LS LF

    A D

    TF

    ES EF

    LS LF

    B D

    TF

    1 ES

    LS 1

    EF

    LF 2

    A

  • ADM vs. PDM ADM PDM

    Early Start (ES) is the earliest possible time an activity can start.

    Late Finish (LF) is the latest possible time an activity can finish without extending the completion date of the project.

    Total float (TF)- the amount of time an activity may be delayed without delaying the completion date of the project.

    TF = LF ES D or TF = LS ES or TF = LF EF

    Free float (FF)- the amount of time an activity may be delayed without delaying the early start time of the

    immediately following activity.

    FF(i) = ES(j) EF(i) ; i-preceding activity, j-following activity

    Late Start (LS) is the latest possible time an activity can start without extending the completing date of the project.

    LS = LF - D

    Early Finish (EF) is the earliest possible time an activity can finish if it is start on Early Start Time (ES) and finish within the planned duration.

    EF = ES + D *D = duration

  • ADM vs. PDM ADM

    -A and B are activities. 1, 2 and 3 are events

    -Activity A has ID or label 1-2 ; Activity B has ID or label 2-3

    -Activity A precedes activity B

    PDM

    1 2 A

    ES EF

    LS LF

    A D

    TF

    ES EF

    LS LF

    B D

    TF

    1

    3 B

    ES EF

    LS LF

    B D

    TF

    2

    Activity Nodes

    Predecessor Activity

    Current Activity

    Successor Activity

  • ADM vs. PDM Item ADM PDM

    Relationshi

    p

    F S

    ADM only shows finish-to-

    start relationships, meaning

    that each activity is

    completed before the

    successor activity starts.

    F S F F S S S - F

    Critical

    path

    - Critical Path

    - A series of interconnected activities through the network

    diagram, with each activity having zero total float time. The

    critical path determines the minimum time to complete the

    project.

    - Possible to have more than one critical path

    - Activities which lay on critical path cannot suffer any delay

    1. ESX = LSX, or

    2. LFX = EFX, or

    3. Total Float (TF) = 0

  • ADM vs. PDM Item ADM PDM

    Dummy Activity

    or

    Definition

    An activity that

    indicates any activity

    following the dummy

    cannot be started until

    the activity(ies)

    preceding the dummy are

    completed.

    Activity which has not

    duration. It is only used

    to show any relationship

    between activities.

    Function

    If there is a situation

    where one event is used

    to show relationship more

    than one activity.

    To show a complicated

    relationship clearly

    Dummy activity is not used

    in Precedence Diagram

    Method (PDM)

    D

  • ADM

  • Item ADM

    Dummy Activity

    or

    False

    True

    D

    1 2 1 2

    3

    A

    B

    A

    B

    C

    D

    A

    B

    A

    B

    C

    D

    Activity A & B have the same

    ID

    A: 1-2

    B: 1-2

    ID for Activity A & B are not

    same.

    A: 1-2

    B: 1-3

    If C is to follow A & B,

    but D is to follow only B.

    (not fulfill)

    If C is to follow A & B,

    but D is to follow only B.

    (use dummy)

  • Item ADM

    Dummy Activity

    or

    False

    True

    D

    A 1 2 Q

    3 B

    4

    P

    R

    If P, Q and R follow A, and B follows P, Q and R. The following diagram is not the correct representation of the same.

    A 1 2 Q

    3 B

    4

    P

    R

    5

    6

    Reason: Activities P, Q and R have the same ID (2-3).

    Activities P has the ID (2-5), Q (2-3) and R (2-6).

  • Item ADM

    Dummy Activity

    or

    False

    True

    D

    1. D is preceded by A only 2. E is preceded by A and B 3. F is preceded by B and C

    A

    B

    C

    D

    F

    E

    A

    B

    C

    D

    F

    E

    Statement 3 not fulfill

    where F is preceded by

    A, B and C.

  • 92

    ADM vs. PDM

    Item ADM PDM

    Estimating

    duration

    - FORWARD PASS

    : To establish the earliest expected start and finish times for each activity in the network.

    - BACKWARD PASS

    : To establish the latest allowable start and finish times for each activity in the network.

    Early Start

    Early Finish

    Late Start

    Late Finish

    FORWARD PASS

    BACKWARD PASS

  • 93

    Arrow Diagram Method

    A 1

    a

    b 2 c

    d X

    B 3 e

    f Y

    Forward pass

    Backward pass

    Note a : Early Start (ES)A b : Late Start (LS)A c : Early Finish (EF)A = (ES)B d : Late Finish (LF)A = (EF)B e : Early Finish (EF)B

    f : Late Finish (LF)B X : Duration of activity A

    Y : Duration of activity B

    Forward pass Backward pass a = 0 f = e

    c = a + X d = f Y

    e = c + Y b = d - X

    c = a + X e = c + Y

    d = f Y

  • ACTIVITY DURATION(DAY) PREDECESSOR

    A 3 -

    B 5 A

    C 3 B

    D 4 -

    E 4 A

    F 10 E,D

    G 9 C,F

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4 9

    ACTIVITY DURATION (DAY)

    PREDECESSOR

    A 3 -

    B 5 A

    C 3 B

    D 4 -

    E 4 A

    F 10 E,D

    G 9 C,F

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4 9

    Early Start Box

    Early Finish Box

    Early Start at node 1 is zero

    Make forward pass through the network by adding duration times.

    0

    0+3=3

    3

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4 9

    Early Start Box Early Finish Box

    Make forward pass through the network by adding duration times.

    0

    3+5=8 3 8

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4 9

    0

    3 8

    If two or more activities terminate at a junction node, place the larger sum at ES box.

    3+4=7

    0+4=4 Larger=7

    7

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4 9

    0

    3 8

    7

    17 26

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4 9

    0

    3 8

    7

    17 26

    Enter 26 into Late Finish box at the node 6, and make a backward pass to establish LF for each activity by deducting the durations.

    26

    Early finish of activity G in the node 6 =26 days. Thats means it will take 26 days to complete the project. Therefore, 26 days represents Late Finish of the project.

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4

    9

    0

    3 8

    7

    17 26

    26

    26-9=17

    17

    14

    7

    In the case of junction nodes (with two or more activities), place the smaller value in the LF box of that node.

    14-5=9

    7-4=3

    3 Smaller=3

    0

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4

    9

    0

    3 8

    7

    17 26

    26 17

    14

    7

    3

    0

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4

    9

    0

    3 8

    7

    17 26

    26 17

    14

    7

    3

    0

    Total Float (TF) =LF-D-ES

    TFA = LF-D-ES =3-3-0

    =0

    TFA=0

    TFB=6

    TFC=6

    TFD=3

    TFE=0

    TFF=0

    TFG=0

    TFB = LF-D-ES =14-5-3

    =6

  • 1

    2 3

    5

    4

    6

    A

    D

    B

    E

    C

    F

    G 3

    5

    3

    4 10

    4

    9

    0

    3 8

    7

    17 26

    26 17

    14

    7

    3

    0

    Activities on critical path : A,E,F and G.

    TFA=0

    TFB=6

    TFC=6

    TFD=3

    TFE=0

    TFF=0

    TFG=0

  • ACTIVITY DURATION(DAY) ES EF LS LF TF

    A 3 0 3 0 3 0*

    B 5 3 8 3 14 6

    C 3 8 17 14 17 6

    D 4 0 7 0 7 3

    E 4 3 7 3 7 0*

    F 10 7 17 7 17 0*

    G 9 17 26 17 26 0*

    * Critical Activity

    Total Float (TF) =LF-D-ES

  • BAR CHART

    Activity Duration (days)

    1 2 3 4 5 6 7 8 9 10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    22

    23

    24

    25

    26

    A 3

    B 5

    C 3

    D 4

    E 4

    F 10

    G 9

    ACTIVITY DURATION (DAY)

    ES EF LS LF TF

    A 3 0 3 0 3 0*

    B 5 3 8 3 14 6

    C 3 8 17 14 17 6

    D 4 0 7 0 7 3

    E 4 3 7 3 7 0*

    F 10 7 17 7 17 0*

    G 9 17 26 17 26 0*

  • Example 2 (ADM) Activity Duration (day) Predecessor (s)

    Act. A 2 -

    Act. B 3 -

    Act. C 3 A

    Act. D 4 B

    Act. E 3 C,D

    Act. F 2 C,D

    Act. G 4 E

    Act. H 3 F

    1. Develop an arrow diagram for the project. 2. Identify critical activity and critical path for the project.

  • 1

    2

    4

    5

    3

    7

    A

    B

    C

    D

    E

    F

    G

    2 3

    3

    3 2 4

    4

    Activity Duration (day) Predecessor (s)

    Act. A 2 -

    Act. B 3 -

    Act. C 3 A

    Act. D 4 B

    Act. E 3 C,D

    Act. F 2 C,D

    Act. G 4 E

    Act. H 3 F

    6

    H

    3

  • 1

    2

    4

    5

    3

    7

    A

    B

    C

    D

    E

    F

    G

    2 3

    3

    3 2 4

    4

    6

    H

    3

    Forward pass

    0

    2

    3

    7

    10

    9

    14

  • 1

    2

    4

    5

    3

    7

    A

    B

    C

    D

    E

    F

    G

    2 3

    3

    3 2 4

    4

    6

    H

    3

    Backward pass

    0

    2

    3

    7

    10

    9

    14

    14

    11

    10

    7

    3

    0

    4

  • Total Float

    Activity Duration (day)

    ES EF LS LF TF

    Act. A 2 0 2 0 4 2

    Act. B 3 0 3 0 3 0*

    Act. C 3 2 7 4 7 2

    Act. D 4 3 7 3 7 0*

    Act. E 3 7 10 7 10 0*

    Act. F 2 7 9 7 11 2

    Act. G 4 10 14 10 14 0*

    Act. H 3 9 14 11 14 2

    * Critical Activity Total Float (TF) =LF-D-ES

  • 2

    4

    5

    3

    7

    A

    B

    C

    D

    E

    F

    G

    2 3

    3

    3 2 4

    4

    6

    H

    3

    Critical Path

    2

    3

    7

    10

    9

    14

    14

    11

    10

    7

    3

    1 0

    0

    4

    Critical path Activities on critical path : B,D,E and G.

  • Exercise 3 (ADM)

    Prepare a arrow diagram for the project. Identify critical path for the project.

    Activity Duration (day) Predecessor (s)

    Act. A 2 -

    Act. B 3 A

    Act. C 5 A

    Act. D 4 A

    Act. E 2 B,C

    Act. F 3 C

    Act. G 4 C,D

    Act. H 2 E,F,G

  • A C

    Exercise 3 Forward pass

    D 4

    B 3

    F 3

    H 1

    0 2

    2 3

    7

    4 7

    6 11 7

    13

    5 7

    2 2 5

    5,7

    6,7

    9,10,11

  • A C

    Exercise 3 Backward pass

    D 4

    B 3

    F 3

    H 1

    0

    0 2

    2

    2 3

    7

    7

    4 7

    9

    6 11

    11 7

    13

    13

    5 7

    7

    2 2 5

    9,8,7

    6,2,3

  • A 2

    C 5

    Exercise 3 (ADM-Solution)

    Critical path

    D 4

    B 3

    F 3

    H 2

    1 0

    0 2

    2

    2 3

    7

    7

    4 7

    9

    6 11

    11 7

    13

    13

    5 7

    7

    Activities on critical path : A,C,G and H.

  • Link (Relationship)

    Finish to Start (FS)

    Activity B cannot start until Activity A finish

    Start to Start (SS)

    Activity B cannot start until Activity A start

    Act. A Act. B

    Act. A

    Act. B

  • Finish to Finish (FF)

    Activity B cannot finish until Activity A finish.

    Start to Finish (SF)

    Activity B cannot finish until Activity A start.

    Act. A

    Act. B

    Act. A

    Act. B

    Link (Relationship)

  • Lead time & lag time

    Lead time Overlap between

    dependent activity

    Eg : FS 5d

    Lag time Delay between

    dependent activity

    Eg: FS + 2 d

    Act. A

    Act. B

    5d

    Act. A

    Act. B

    2d

  • ACTIVITY DURATION(DAY) PREDECESSOR

    A 2 START

    B 6 A

    C 6 B

    D 1 B

    E 3 A

    F 3 D,E

    G 2 C(+2),F

  • A

    2

    B

    6

    C

    6

    D

    1

    E

    3

    F

    3

    G

    2 FS +2

    EXAMPLE 1

    ACTIVITY DURATION (DAY)

    PREDECESSOR

    A 2 START

    B 6 A

    C 6 B

    D 1 B

    E 3 A

    F 3 D,E

    G 2 C(+2),F

    ES LS D

    LS LF TF

    Activity

  • A

    2 0 2

    B

    6 2 8

    C

    6 8 14

    D

    1 8 9

    E

    3 2 5

    F

    3 9 12

    G

    2 16 18

    16,12

    FS +2

    5,9

    FORWARD PASS

    EXAMPLE 1

  • A

    2 0 2

    B

    6 2 8

    C

    6 8 14

    D

    1 8 9

    E

    3 2 5

    F

    3 9 12

    G

    2 16 18

    16,12

    FS +2

    5,9

    EXAMPLE 1

    18 16

    16

    BACKWARD PASS

  • A

    2 0 2

    B

    6 2 8

    C

    6 8 14

    D

    1 8 9

    E

    3 2 5

    F

    3 9 12

    G

    2 16 18

    16,12

    FS +2

    5,9

    EXAMPLE 1

    2 2 8 8 14

    12 13

    18 16

    16 13

    13 10

    8,12 2,10

    BACKWARD PASS

  • A

    2 0 2

    B

    6 2 8

    C

    6 8 14

    D

    1 8 9

    E

    3 2 5

    F

    3 9 12

    G

    2 16 18

    16,12

    FS +2

    5,9

    EXAMPLE 1

    0 2 2 8 8 14

    12 13

    18 16

    16 13

    13 10

    8,12 2,10

    BACKWARD PASS

  • A

    2 0 2

    0 2

    B

    6 2 8

    2 8

    C

    6 8 14

    8 14

    D

    1 8 9

    12 13

    E

    3 2 5

    F

    3 9 12

    G

    2 16 18

    16,12

    FS +2

    5,9

    18 16

    16 13

    13 10

    8,12 2,10

    COMPLETED

    EXAMPLE 1

  • 127

    A

    2 0 2

    0 2

    B

    6 2 8

    2 8

    C

    6 8 14

    8 14

    D

    1 8 9

    12 13

    E

    3 2 5

    F

    3 9 12

    G

    2 16 18 FS +2

    18 16

    16 13

    13 10

    TOTAL FLOAT

    EXAMPLE 1

    TFA = LF-EF

    =2-2

    =0

    TFB = LF-EF

    =8-8

    =0

    TFC = LF-EF

    =14-14

    =0

    TFD = LF-EF

    =13-9

    =4

    TFE = LF-EF

    =13-5 =8

    TFG = LF-EF

    =18-18

    =0

    TFF = LF-EF

    =16-12

    =4

    0 0

    4

    8

    0

    4

    0

  • 128

    A

    2 0 2

    0 2

    B

    6 2 8

    2 8

    C

    6 8 14

    8 14

    D

    1 8 9

    12 13

    E

    3 2 5

    F

    3 9 12

    G

    2 16 18 FS +2

    18 16

    16 13

    13 10

    FREE FLOAT

    EXAMPLE 1

    FFA = ESSUCC-EF-

    Lag

    =2-2-0

    =0

    0 0

    4

    8

    0

    4

    0

    FFB = ESSUCC-EF-

    Lag

    =8-8-0

    =0

    FFC = ESSUCC-EF-

    Lag

    =16-14-2

    =0

    FFD = ESSUCC-EF-

    Lag

    =9-9-0

    =0

    FFF = ESSUCC-EF-

    Lag

    =16-12-0

    =4

    FFA = ESSUCC-

    EF- Lag

    =18-18-

    0

    =0

  • A

    2 0 2

    0 2

    B

    6 2 8

    2 8

    C

    6 8 14

    8 14

    D

    1 8 9

    12 13

    F

    3 9 12

    G

    2 16 18

    16,12

    FS +2

    5,9

    18 16

    16 13

    8,12 2,10

    CRITICAL PATH

    EXAMPLE 1

    0 0

    4

    E

    3 2 5

    13 10 8

    0

    4

    0

  • Example 2 (PDM) Activity Duration (day) Predecessor (s)

    Act. A 10 -

    Act. B 11 A

    Act. C 5 B

    Act. D 4 B

    Act. E 12 A

    Act. F 3 C,D

    Act. G 7 F

    Act. H 11 E

    Act. I 4 G,H

    1. Develop a precedence diagram for the project. 2. Identify critical activity and critical path for the project.

  • Example 2 (PDM)

    A

    10

    B

    11

    E

    12

    H

    11

    I

    4

    ES LS D

    LS LF TF

    Activity

    C

    5

    D

    4

    F

    3

    G

    7

  • Example 2 (PDM-forward pass)

    A

    10 0 10

    B

    11 10 21

    E

    12 10 22

    H

    11 22 33

    I

    4 36 40

    ES LS D

    LS LF TF

    Activity

    C

    5 21 26

    D

    4 21 25

    F

    3 26 29

    G

    7 29 36

  • Example 2 (PDM-backward pass)

    A

    10 0 10

    10 0

    B

    11 10 21

    21 10

    E

    12 10 22

    25 13

    H

    11 22 33

    36 25

    I

    4 36 40

    40 36

    ES LS D

    LS LF TF

    Activity

    C

    5 21 26

    26 21

    D

    4 21 25

    26 22

    F

    3 26 29

    29 26

    G

    7 29 36

    36 29

  • Example 2 (PDM-Total float)

    A

    10 0 10

    10 0 0

    B

    11 10 21

    21 10 0

    E

    12 10 22

    25 13 3

    H

    11 22 33

    36 25 3

    I

    4 36 40

    40 36 0

    ES LS D

    LS LF TF

    Activity

    C

    5 21 26

    26 21 0

    D

    4 21 25

    26 22 1

    F

    3 26 29

    29 26 0

    G

    7 29 36

    36 29 0

    Critical path TF = LF ES D or TF = LS ES or TF = LF EF

  • Example 3 (PDM) Activity Duration (week) Predecessor (s)

    Act. A 2 -

    Act. B 3 A (FS+2), C (FF+1),

    D(FF)

    Act. C 2 A

    Act. D 1 C (SS)

    1. Develop a precedence diagram for the project. 2. Identify critical activity and critical path for the project.

  • Example 3 (PDM-forward pass)

    +2

    +1

    A

    2 0 2

    B

    3 4 7

    C

    2 2 4

    D

    1 2 3

  • Example 3 (PDM-backward pass)

    Critical path

    +2

    +1

    Total Float = LF ES D TF(A) = 2-0-2 = 0 TF(B) = 7-4-3 = 0 TF(C) = 6-2-2 = 2 TF(D) = 7-2-1 = 4

    A

    2 0 2

    2 0 0

    B

    3 4 7

    7 4 0

    C

    2 2 4

    6 4 2

    D

    1 2 3

    7 6 4

  • Exercise 4(PDM)

    Prepare a precedence diagram for the project. Identify critical path for the project.

    Activity Duration (day) Predecessor (s)

    Act. A 2 -

    Act. B 3 A

    Act. C 5 A

    Act. D 4 A

    Act. E 2 B,C

    Act. F 3 C

    Act. G 4 C,D

    Act. H 2 E,F,G

  • Exercise (PDM-Solution)

    A

    2 0 2

    2 0 0

    B

    3 2 5

    9 6 4

    C

    5 2 7

    7 2 0

    D

    4 2 6

    7 3 1

    E

    2 7 9

    11 9 2

    F

    3 7 10

    11 8 1

    G

    4 7 11

    11 7 0

    H

    2 11 13

    13 11 0

  • BUT WAIT!!

    Are there any other type of Scheduling method??

    How if the Gantt Chart and CPM did not actually work/represent well with the nature/requirement of the particular construction project??

    So, actually we have LINEAR SCHEDULING METHOD (LSM) / LINE OF BALANCE (LOB)

  • This method is actually appropriate for a project that:

    Progress linearly (straight without major fluctuation of activities),

    Highly repetitive works,

    Have fixed starting point and end,

    Such as; highways, airfields, pipelines, multiple housing units, high-rise buildings, etc.

  • LINEAR SCHEDULING METHOD (LSM) (cont.)

    Take for example; a highway construction project:

  • LINEAR SCHEDULING METHOD (LSM) (cont.)

    LSM Diagram for highway project (adopted from Nunnally, 2014)

    Kilo

    met

    er (

    km)

    We have 5 linear activities: 1. Clear & strip 2. Drainage 3. Subgrade 4. Base course 5. Pave Width of B: At 40km, the subgrade works will starts at week 4.4 until week 5. Height of A: At week 3, subgrade works from 13km to 21km. Distance of C: It is a time lag / time float for 10km; between subgrade works and base course works. 1.4 weeks to be exact.

  • QUESTION 2

    A project have a detail as below:

    1. Draw the precedence diagram for the schedule shown next.

    2. Determine the duration of project required.

    3. Determine the Total Float for each activities and give the critical path for this project.

    4. Draw a bar chart.

    ACTIVITY PREDECESSOR DURATION (WEEK) A - 3 B - 1 C - 2 D A 3 E B 1 F C 4 G D 2 H D,E 1 I D,E,F 2 J G 3 K H 2 L I 1 M J,K,L 2

  • ACTIVITY SUCESSOR DURATION

    (WEEK) A A-B (S-S),L=5 3 A-C (F-S),L=2 B B-E (F-S),L=3 1 C C-E (F-S),L=0 2 D D-E (F-S),L=0 2 E E-F (F-S),L=0 3 F 2

    1. Draw the precedence diagram for the schedule shown next. 2. Determine the duration of project required. 3. Determine the Total Float for each activities and give the critical path for this project. 4. Draw a bar chart.

  • No. Activity Duration (week)

    Successor Relationship Lag (week)

    1 A 5 B, C, D AB (SS) AC (FS) AD (FS)

    1 2 0

    2 B 4 E BE (FS) 0 3 C 3 F, G CF (FS)

    CG (FS) 0 0

    4 D 2 H DH (FS) 0 5 E 7 F, G EF (FS)

    EG (FS) 0 0

    6 F 2 I FI (FS) 0 7 G 5 I GI (FS) 0 8 H 3 I HI (FS) 3 9 I 6 - - -

    1. Estimate the total project duration. 2. Calculate the total float for each activity in the project. 3. State the critical path.