Chapter 5 Scheduling Tracking Work
description
Transcript of Chapter 5 Scheduling Tracking Work
-
CHAPTER 5
SCHEDULING AND TRACKING WORK IN CONSTRUCTION PROJECT MANAGEMENT
-
Introduction
Planning & Scheduling
Principles
Techniques
Work breakdown structure
Gantt Chart & S-Curve
Critical Path Method
Successor/ predecessor relationship
Arrow Diagram Method and Precedence Diagram Method
-
THE INTEGRATION OF TIME & SUSTAINABLE CONSTRUCTION
Our focus!!
Traditional Projects Critical Components (time, cost, & quality); in relation with sustainable construction concept
-
Introduction
Project planning
Process of identifying all the activities necessary to successfully complete the project.
Provides map to guide where to go and focused on how to get there
Planned in early stage of Project life Cycle or also before site activities start.
-
Introduction
Importance of planning
Reduce mistake and rework
Avoid wastage
minimize unnecessary in time and cost scheduling
better quality control
Effective project progress control
Effective usage resources
-
Introduction
Project scheduling
Process of determining the sequential order of the planned activities, assigning realistic durations to each activity and determining the start and finish dates for each activities.
it can be used to manage, coordinate, control and report.
Depending on the sophistication of the user, the schedule can take different forms.
-
Project Scheduling
Purpose of project scheduling Claim Project time and cost control Allocate project resources more efficiently As a monitoring tool Material delivery at site Storage all material cannot put in the site (confined space) Avoid delay of the work and activity. Minimize the cash flow as min as possible such as order material
stage by stage depend on the work needed. Control human resources and machinery To improve the efficiency
of the operation through the efficient use of resources and cost control.
Project planning is prerequisite to project planning!
-
Desired results of planning and scheduling Finish the project on time.
Continuous (uninterrupted) flow of work (no delays)
Reduced amount of rework (least amount of changes)
Minimized confusion on misunderstandings.
Increase knowledge of status of project by everyone.
Meaningful and timely reports to management.
You run the project instead the project running you.
Knowledge of scheduled times of key parts of the project.
Knowledge of the distributions of costs of the project
Accountability of people, define responsibility/authority.
Clear understanding of who does what, when & how much.
Integration of all work to ensure a quality project for the owner.
-
What are the different?
Planning is more difficult to accomplish than scheduling.
The term planning and scheduling are often used synonymously.
Planning is first step to project scheduling.
Tools used for planning and scheduling are different!
-
Principles of planning and scheduling Begin planning before starting work, rather than after starting
work. Involve people who will actually do the work in the planning
and scheduling process. Includes all aspects of the project: scope, budget, schedule &
quality. Build flexibility into the plan, include allowance for changes and
time for reviews and approvals. Remember the schedule is the plan for doing the work, and it
will never be precisely correct. Keep the plan simple, eliminate irrelevant details that prevent
the plans from being readable. Communicating the plan to all parties; any plan is worthless
unless it is known.
-
The Collection of Projects Critical Components (should be in equilibrium)
02468
101214161820
COST
RESOURCES
SCOPEQUALITY
TIME
Client Satisfaction
-
Steps in planning and scheduling
Scope definition
Cost Budgeting Cost Estimating
Activity resource planning
Activity Duration
Estimation
Schedule development
Activity Sequencing
Create WBS
Scope Management
Time & Resource
Management
Cost Management
-
Steps in planning and scheduling
1. Develop a work breakdown structure (WBS)
2. Prepare a drawing (network diagram)
3. Determine the time, cost and resources required
4. Compute the schedule to determine start, finish and float times
5. Analyze costs and resources for the project
6. Communicate the results of the plan and schedule
-
Work breakdown structure (WBS)
Identifies the tasks and activities that must be performed.
It divides the project into identifiable parts that can be managed.
Concept of WBS: in order to manage a whole project, one must manage and control each of its parts.
It defines: The work to be performed The need of expertise Assist in selection of project team Establish a base of project scheduling and control
-
Work breakdown structure (WBS)
WBS is display as a graphical or outline method that shows the division of work in a multi level system.
In developing WBS, we should consider:
Activities that require time
Activities that require cost
Activities that need to arrange
Activities that need to monitor
-
Work Breakdown Structure (Graphical)
Construction of one block office building
Start Project Preliminaries
Performance bond
Establish and removal of site
office
Block A
Earthwork
Structure Work
Architecture Work
M&E work
Testing & Commissioning
Project complete
Level 1
Level 2
Level 3
-
Work Breakdown Structure (Outline) Construction of one
block office building Start Project
Preliminaries
Performance bond
Establish and removal of site office
Block A
Earthwork
Structure Work
Architecture Work
M&E work
Testing and Commissioning
Project complete
-
Work breakdown structure (WBS) Importance of WBS
Overall program can be explain in summary according to each sub-element divided.
Planning could execute. Cost and budget could estimate more accurately. Time, Cost and Performance of each element could be
monitor from time to time. Objective could be relate directly with the available
resources in the company. Network diagram and control planning could be prepared
in early stages. Responsibilities for each parties involve in every element
could be identify and assign.
-
Work breakdown structure (WBS)
Example:
You are the Project Manager for a Construction of Proposed Construction and Completion of a Double Storey Bungalow House And Related Works For Messrs. Dato 'Kamal Jaafar. Develop a preliminary graphical work breakdown structure (up to level 4) for the project given. Your WBS should complete with all works needs in completing a one unit bungalow.
-
Example (WBS-Graphical Method)
Proposed Construction and Completion of A Double Storey Bungalow House and Related Works for Messrs. Dato 'Kamal Jaafar.
Preliminary works
Performance bond
Progress Report
Building works
Structure
Foundation
Ground level
1st floor level
2nd floor level
Architecture
Wall
Floor
Roof
Fittings
M&E
Wiring
Fittings installation
External works
Sewerage
Road and drainage
Landscape
Level 1
Level 2
Level 3
Level 4
-
Exercise (Outline Method)
Proposed Construction and Completion of A Double Storey Bungalow House and
Related Works for Messrs. Dato 'Kamal Jaafar.
-
Techniques for scheduling
Techniques used will vary depending on: Projects size Complexity Duration Personnel Owner requirements
Two general methods commonly used : Bar chart (Gantt chart) Critical path method (CPM/ network analysis
system)
-
Develop by Henry L.Gantt
Is a graphical time-scale of the schedule, length represent the duration of activity.
-
Advantages
Easy to interpret
Simplicity & ease of preparation and understanding (Simple graphical).
No theory or complicated calculation involved (Easy for general comprehension).
Time-scaled (the length of the bar representing certain activity is proportional to the duration of that activity.
Appeal to persons who do not have a technical background
Wide spread used in industry
Mostly used in small project
Fairly broad planning and scheduling tools, so they require less revision and updating than more sophisticated systems
Disadvantages
Difficult to update
Very cumbersome as the number of line activities, or bars increases
Does not integrate costs or resources with the schedule
Limited application for detail construction work
Difficult to use it for forecasting the effects that changes in a particular activity will have on the overall schedule
-
No. Description Month 1 2 3 4 5 6 7 8 9 10
1 Mobilization
2 Foundation Excavation
3 Diversion Stage
4 Foundation Grouting
5 Dam Concrete
6 Install Outlet Gates
7 Install Trash Racks
8 Prestress
9 Radial Gates
10 Spillway Bridge
11 Curtain Grout
12 Dismantle Plant, Clean Up
Original Schedule
Actual progress
Bar chart basically use x-axis only (to depict time). The y-axis is use to show individual activities, to represent a variable across time
(e.g.: man-hours, budget, % complete and so forth.
Bar chart (Gantt Chart)
-
No. Description Month 1 2 3 4 5 6 7 8 9 10
1 Mobilization
2 Foundation Excavation
3 Diversion Stage
4 Foundation Grouting
5 Dam Concrete
6 Install Outlet Gates
7 Install Trash Racks
8 Prestress
9 Radial Gates
10 Spillway Bridge
11 Curtain Grout
12 Dismantle Plant, Clean Up
Original Schedule
Actual progress
Cu
mu
lati
ve p
rogr
ess
(%)
100
0
Bar chart basically use x-axis only (to depict time). The y-axis is use to show individual activities, to represent a variable across time (e.g.: man-hours,
budget, % complete and so forth. The variables usually shown as a curve superimposed on the bar chart.
Bar chart (Gantt Chart) + S curve
-
Bar chart (Gantt Chart)
Tutorial No.2: A project consist of five activities that should be
done in a period of time. Try to create a bar chart to ease the project planning and scheduling.
* consider 1 week as 7 days
Activity A : 1 week, starting from 1 Jun 2015 Activity B : 2 week, starting from 8 Jun 2015 Activity C : 3 week, starting from 15 Jun 2015 Activity D : 2 week, starting from 22 Jun 2015 Activity E : 2 week, starting from 29 Jun 2015
-
Bar chart (Gantt Chart)-Example 1
Step 1: identify start date and finish date for each activity Activity A : 1 week, starting from 1 Jun 2014 (1/6-7/6)
Activity B : 2 week, starting from 8 Jun 2014 (8/6-21/6)
Activity C : 3 week, starting from 15 Jun 2014 (15/6-5/7)
Activity D : 2 week, starting from 22 Jun 2014 (22/6-5/7)
Activity E : 2 week, starting from 29 Jun 2014 (29/6-12/7)
-
Bar chart (Gantt Chart)-Example 1
Step 2: Draw outline of bar chart
Activity Duration (week)
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
1/6 8/6 15/6 22/6 29/6 6/7
Act. A 1
Act. B 2
Act. C 3
Act. D 2
Act. E 2
-
Bar chart (Gantt Chart)-Example 1
Activity Duration (week)
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
1/6 8/6 15/6 22/6 29/6 6/7
Act. A 1
Act. B 2
Act. C 3
Act. D 2
Act. E 2
Step 3: Draw the activity bars
Activity A : 1 week, starting from 1 Jun 2014 (1/6-7/6) Activity B : 2 week, starting from 8 Jun 2014 (8/6-21/6) Activity C : 3 week, starting from 15 Jun 2014 (15/6-5/7) Activity D : 2 week, starting from 22 Jun 2014 (22/6-5/7) Activity E : 2 week, starting from 29 Jun 2014 (29/6-12/7)
-
Bar chart (Gantt Chart)-Example 2
Num Activity Duration (days)
Start Date Cost (RM)
Resources/ day
(person)
Work progress
percentage (%)
1 Activity A 3 4/5/2014 1,400.00 2 12
2 Activity B 5 7/5/2014 2,700.00 3 30
3 Activity C 7 10/5/2014 3,500.00 2 21
4 Activity D 5 15/5/2014 6,000.00 4 10
5 Activity E 4 17/5/2014 4,700.00 4 12
6 Activity F 6 19/5/2014 12,600.00 5 15
30,900.00 100
-
Bar chart (Gantt Chart)-Example 2
Step 1: identify start date and finish date for each activity Activity A : 3 days, starting from 4 May 2014 (4/5-6/5)
Activity B : 5 days, starting from 7 May 2014 (7/5-11/5)
Activity C : 7 days, starting from 10 May 2014 (10/5-16/5)
Activity D : 5 days, starting from 15 May 2014 (15/5-19/5)
Activity E : 4 days, starting from 17 May 2014 (17/5-20/5)
Activity F : 6 days, starting from 19 May 2014 (19/5-24/5)
-
Bar chart (Gantt Chart)-Example 2
Step 2: Draw outline of bar chart
Activity Duration (days) 4
/5
5/5
6/5
7/5
8/5
9/5
10
/5
11
/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18
/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3
Act. B 5
Act. C 7
Act. D 5
Act. E 4
Act. F 6
-
Bar chart (Gantt Chart)-Example 2
Step 3: Draw the activity bars
Activity Duration (days) 4
/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
Act. A 3
Act. B 5
Act. C 7
Act. D 5
Act. E 4
Act. F 6
Activity A : (4/5-6/5) Activity B : (7/5-11/5) Activity C : (10/5-16/5) Activity D : (15/5-19/5) Activity E : (17/5-20/5) Activity F : (19/5-24/5)
-
An S-curve is defined as:
"A display of cumulative costs, labor hours or other quantities plotted against time. The name derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the middle, which is typical of most projects. The beginning represents a slow, deliberate but accelerating start, while the end represents a deceleration as the work runs out."
-
S-Curve
Type of S-Curve
Physical S-Curve
Financial S-Curve
Both S-curve can be in Baseline (planned) or actual S-curve
-
S-Curve (Example) Num Activity Duration
(days) Start Date Cost (RM)
Resources/
day (person)
Work progress
percentage (%)
1 Activity A 3 4/5/2014 1,400.00 2 12
2 Activity B 5 7/5/2014 2,700.00 3 30
3 Activity C 7 10/5/2014 3,500.00 2 21
4 Activity D 5 15/5/2014 6,000.00 4 10
5 Activity E 4 17/5/2014 4,700.00 4 12
6 Activity F 6 19/5/2014 12,600.00 5 15
30,900.00 100
Based on bar chart in Example 2, construct S-curve (daily basis) for this project: 1. Financial S-Curve 2. Physical S-curve (resources vs time & work vs time)
-
Financial S-Curve
-
Financial S-Curve
Activity Duration (days)
Cost (RM)
Cost/day (RM) 4/
5
5/5
6/5
7/5
8/5
9/5
10
/5
11
/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18
/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 1,400
Act. B 5 2,700
Act. C 7 3,500
Act. D 5 6,000
Act. E 4 4,700
Act. F 6 12,600
Cost/day
Cumulative cost/day
STEP 1: DRAW BAR CHART (from Example 2), include Cost of each activity
-
Financial S-Curve
Activity Duration (days)
Cost (RM)
Cost/day (RM) 4/
5
5/5
6/5
7/5
8/5
9/5
10
/5
11
/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18
/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 1,400
Act. B 5 2,700
Act. C 7 3,500
Act. D 5 6,000
Act. E 4 4,700
Act. F 6 12,600
Cost/day
Cumulative cost/day
=1,400/3
=2,700/5
=3,500/7
=6,000/5
=4,700/4
=12,600/6
467
540
500
1200
1175
2100
STEP 2: Calculate COST/ DAY = Cost / duration
-
Financial S-Curve
Activity Duration (days)
Cost (RM)
Cost/day (RM) 4/
5
5/5
6/5
7/5
8/5
9/5
10
/5
11
/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18
/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 1,400
Act. B 5 2,700
Act. C 7 3,500
Act. D 5 6,000
Act. E 4 4,700
Act. F 6 12,600
Cost/day
Cumulative cost/day
467
540
500
1200
1175
2100
STEP 2: Calculate COST/ DAY = Cost / duration
-
Activity Duration (days)
Cost (RM)
Cost/day (RM) 4/
5
5/5
6/5
7/5
8/5
9/5
10
/5
11
/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18
/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 1,400
Act. B 5 2,700
Act. C 7 3,500
Act. D 5 6,000
Act. E 4 4,700
Act. F 6 12,600
Cost/day
Cumulative cost/day
Financial S-Curve
467
540
500
1200
1175
2100
STEP 3: Calculate the TOTAL COST of each DAY
46
7
10
40
46
7
46
7
10
40
5
00
5
00
5
00
1
70
0
17
00
2
37
5
23
75
4
47
5
32
75
2
10
0
21
00
2
10
0
21
00
54
0
54
0
54
0
540 +500
-
Activity Duration (days)
Cost (RM)
Cost/day (RM) 4/
5
5/5
6/5
7/5
8/5
9/5
10
/5
11
/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18
/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 1,400
Act. B 5 2,700
Act. C 7 3,500
Act. D 5 6,000
Act. E 4 4,700
Act. F 6 12,600
Cost/day
Cumulative cost/day
Financial S-Curve
467
540
500
1200
1175
2100
STEP 4: Calculate the CUMULATIVE COST of each DAY
46
7
10
40
46
7
46
7
10
40
5
00
5
00
5
00
1
70
0
17
00
2
37
5
23
75
4
47
5
32
75
2
10
0
21
00
2
10
0
21
00
54
0
54
0
54
0
46
7
93
4
1941
24
81
3021
40
61
5101
56
01
6101
66
01
8301
10
01
1237
6
1475
1
1922
6
2250
1
2460
1
2670
1
2880
1
3090
1
Cumulative cost (previous) + current cost/day = 467 + 467
Cumulative cost (previous) + current cost/day = 934 + 467
10
41
-
Financial S-Curve
Activity Duration (days)
Cost (RM)
Cost/da y (RM) 4/
5
5/5
6/5
7/5
8/5
9/5
10
/5
11
/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18
/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 1,400
Act. B 5 2,700
Act. C 7 3,500
Act. D 5 6,000
Act. E 4 4,700
Act. F 6 12,600
Cost/day
Cumulative cost/day
467
540
500
1200
1175
2100
30900
25750
20600
15450
10300
5150
0
46
7
10
40
46
7
46
7
54
0
54
0
54
0
10
40
5
00
5
00
5
00
1
70
0
17
00
2
37
5
23
75
4
47
5
32
75
2
10
0
21
00
2
10
0
21
00
46
7
93
4
10
41
1
94
1
24
81
3
02
1
40
61
5
10
1
56
01
6
10
1
66
01
8
30
1
10
00
1
12
37
6
14
75
1
19
22
6
22
50
1
24
60
1
26
70
1
28
80
1
30
90
1
STEP 5: Plot graph base on cumulative cost
Start from 0
Total cumulative cost
Get the medium (30900 /2)
Start from 0
467 934 1041
-
Financial S-Curve
Activity Duration (days)
Cost (RM)
Cost/da y (RM) 4/
5
5/5
6/5
7/5
8/5
9/5
10
/5
11
/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18
/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 1,400
Act. B 5 2,700
Act. C 7 3,500
Act. D 5 6,000
Act. E 4 4,700
Act. F 6 12,600
Cost/day
Cumulative cost/day
467
540
500
1200
1175
2100
30900
25750
20600
15450
10300
5150
0
46
7
10
40
46
7
46
7
54
0
54
0
54
0
10
40
5
00
5
00
5
00
1
70
0
17
00
2
37
5
23
75
4
47
5
32
75
2
10
0
21
00
2
10
0
21
00
46
7
93
4
10
41
1
94
1
24
81
3
02
1
40
61
5
10
1
56
01
6
10
1
66
01
8
30
1
10
00
1
12
37
6
14
75
1
19
22
6
22
50
1
24
60
1
26
70
1
28
80
1
30
90
1
STEP 5: Plot graph base on cumulative cost
-
Physical S-Curve (resources VS time)
-
Num Activity Duration (days)
Start Date Cost (RM)
Resources/ day
(person)
Work progress
percentage (%)
1 Activity A 3 4/5/2014 1,400.00 2 12
2 Activity B 5 7/5/2014 2,700.00 3 30
3 Activity C 7 10/5/2014 3,500.00 2 21
4 Activity D 5 15/5/2014 6,000.00 4 10
5 Activity E 4 17/5/2014 4,700.00 4 12
6 Activity F 6 19/5/2014 12,600.00 5 15
30,900.00 100
-
Physical S-Curve (resources VS time)
Activity Duration (days)
Resource/ day
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 2
Act. B 5 3
Act. C 7 2
Act. D 5 4
Act. E 4 4
Act. F 6 5
Resource/day
Cumulative resource/day
STEP 1: DRAW BAR CHART (from Example 2), include resource/day for each activity
2
2
2 3
3
3
5
5 2
2
2
6
6
8
8
13
9
5
5
5
5
-
Physical S-Curve (resources VS time)
Activity Duration (days)
Resource/ day
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 2
Act. B 5 3
Act. C 7 2
Act. D 5 4
Act. E 4 4
Act. F 6 5
Resource/day 2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5
Cumulative resource/day
STEP 2: Calculate the CUMULATIVE resource of each DAY
Cumulative resource (previous) + current resource/day = 2 + 2
2
4
6
9
12
1
5
20
2
5
27
2
9
31
3
7
43
5
1
59
7
2
81
8
6
91
9
6
10
1
-
Physical S-Curve (resources VS time)
Activity Duration (days)
Resource/ day
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 2
Act. B 5 3
Act. C 7 2
Act. D 5 4
Act. E 4 4
Act. F 6 5
Resource/day 2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5
Cumulative resource/day
STEP 3: Plot graph base on cumulative resource
2
4
6
9
12
1
5
20
2
5
27
2
9
31
3
7
43
5
1
59
7
2
81
8
6
91
9
6
10
1
-
Physical S-Curve (resources VS time)
Activity Duration (days)
Resource/ day
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 2
Act. B 5 3
Act. C 7 2
Act. D 5 4
Act. E 4 4
Act. F 6 5
Resource/day 2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5
Cumulative resource/day 2 4 6 9 12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
10
1
102
85
68
51
34
17
0
STEP 3: Plot graph base on cumulative resource
Start from 0
Total cumulative resource
102/6 = 17
102/6 x 2 = 34
-
Physical S-Curve (resources VS time)
Activity Duration (days)
Resource/ day
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 2
Act. B 5 3
Act. C 7 2
Act. D 5 4
Act. E 4 4
Act. F 6 5
Resource/day 2
2
2
3
3
3
5
5
2
2
2
6
6
8
8
13
9
5
5
5
5
Cumulative resource/day 2 4 6 9 12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
10
1
102
85
68
51
34
17
0
STEP 3: Plot graph base on cumulative resource
-
Physical S-Curve (work VS time)
-
Num Activity Duration (days)
Start Date Cost (RM)
Resources/ day
(person)
Work progress
percentage (%)
1 Activity A 3 4/5/2014 1,400.00 2 12
2 Activity B 5 7/5/2014 2,700.00 3 30
3 Activity C 7 10/5/2014 3,500.00 2 21
4 Activity D 5 15/5/2014 6,000.00 4 10
5 Activity E 4 17/5/2014 4,700.00 4 12
6 Activity F 6 19/5/2014 12,600.00 5 15
30,900.00 100
-
Physical S-Curve (work VS time)
Activity Duration (days)
Work progress
percentage (%)
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 12
Act. B 5 30
Act. C 7 21
Act. D 5 10
Act. E 4 12
Act. F 6 15
Work progress/day
Cumulative work progress/day
STEP 1: DRAW BAR CHART (from Example 2), include work progress
percentage/day for each activity
-
Physical S-Curve (work VS time)
Activity Duration (days)
Work progress
percentage (%)
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 12
Act. B 5 30
Act. C 7 21
Act. D 5 10
Act. E 4 12
Act. F 6 15
Work progress/day
Cumulative work progress/day
STEP 2: Calculate work progress percentage of each day for every activities
12% / 3 days = 4%/ day 4 4 4
30% / 5days = 6%/ day 6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
-
Physical S-Curve (work VS time)
Activity Duration (days)
Work progress
percentage (%)
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 12
Act. B 5 30
Act. C 7 21
Act. D 5 10
Act. E 4 12
Act. F 6 15
Work progress/day
Cumulative work progress/day
4
9
4
4
9
3
3
3
5
5
5
5
7.5
5
.5
2.5
2
.5
2.5
2
.5
6
6
6
6 +3
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
STEP 2: Calculate work progress percentage of each day
-
Physical S-Curve (work VS time)
Activity Duration (days)
Work progress
percentage (%)
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 12
Act. B 5 30
Act. C 7 21
Act. D 5 10
Act. E 4 12
Act. F 6 15
Work progress/day
Cumulative work progress/day
4
9
4
4
9
3
3
3
5
5
5
5
7.5
5
.5
2.5
2
.5
2.5
2
.5
6
6
6
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
STEP 3: Calculate cumulative work progress percentage of each day
-
Physical S-Curve (work VS time)
Activity Duration (days)
Work progress
percentage (%)
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 12
Act. B 5 30
Act. C 7 21
Act. D 5 10
Act. E 4 12
Act. F 6 15
Work progress/day
Cumulative work progress/day
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84
.5
90
92
.5
95
97
.5
10
0
4
9
4
4
9
3
3
3
5
5
5
5
7.5
5
.5
2.5
2
.5
2.5
2
.5
6
6
6
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
STEP 3: Calculate cumulative work progress percentage of each day
-
Physical S-Curve (work VS time)
Activity Duration (days)
Work progress
percentage (%)
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 12
Act. B 5 30
Act. C 7 21
Act. D 5 10
Act. E 4 12
Act. F 6 15
Work progress/day
Cumulative work progress/day
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84
.5
90
92
.5
95
97
.5
10
0
4
9
4
4
9
3
3
3
5
5
5
5
7.5
5
.5
2.5
2
.5
2.5
2
.5
6
6
6
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
STEP 4: Plot S-curve
-
Physical S-Curve (work VS time)
Activity Duration (days)
Work progress
percentage (%)
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 12
Act. B 5 30
Act. C 7 21
Act. D 5 10
Act. E 4 12
Act. F 6 15
Work progress/day
Cumulative work progress/day
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84
.5
90
92
.5
95
97
.5
10
0
4
9
4
4
9
3
3
3
5
5
5
5
7.5
5
.5
2.5
2
.5
2.5
2
.5
6
6
6
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
STEP 4: Plot S-curve
100
75
50
25
0
-
Physical S-Curve (work VS time)
Activity Duration (days)
Work progress
percentage (%)
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 12
Act. B 5 30
Act. C 7 21
Act. D 5 10
Act. E 4 12
Act. F 6 15
Work progress/day
Cumulative work progress/day
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84
.5
90
92
.5
95
97
.5
10
0
4
9
4
4
9
3
3
3
5
5
5
5
7.5
5
.5
2.5
2
.5
2.5
2
.5
6
6
6
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
STEP 4: Plot S-curve
100
75
50
25
0
-
Physical S-Curve (work VS time)
Activity Duration (days)
Work progress
percentage (%)
4/5
5/5
6/5
7/5
8/5
9/5
10
/5
11/5
12
/5
13
/5
14
/5
15
/5
16
/5
17
/5
18/5
19
/5
20
/5
21
/5
22
/5
23
/5
24
/5
Act. A 3 12
Act. B 5 30
Act. C 7 21
Act. D 5 10
Act. E 4 12
Act. F 6 15
Work progress/day
Cumulative work progress/day
4
8
12
18
24
30
39
48
51
54
57
62
67
72
77
84
.5
90
92
.5
95
97
.5
10
0
4
9
4
4
9
3
3
3
5
5
5
5
7.5
5
.5
2.5
2
.5
2.5
2
.5
6
6
6
4 4 4
6 6 6 6 6
3 3 3 3 3 3 3
2 2 2 2 2
3 3 3 3
2.5 2.5 2.5 2.5 2.5 2.5
STEP 4: Plot S-curve
100
75
50
25
0
-
Planning VS Actual S-curve??
Before this, we just create a planning bar chart.
What if, the real activities has started? How to create actual S-curve?
-
Planning VS Actual S-curve (Example 2) Physical S-Curve (work vs time)
Num. Activity Duration (days)
Start Date Actual Start Date
Actual Finish Date
Cost (RM)
Resources (person)
1 Activity A 3 4/5/2014 4/5/2014 6/5/2014 1,400.00 2
2 Activity B 5 7/5/2014 7/5/2014 12/5/2014 2,700.00 3
3 Activity C 7 10/5/2014 11/5/2014 17/5/2014 3,500.00 2
4 Activity D 5 15/5/2014 17/5/2014 21/5/2014 6,000.00 4
5 Activity E 4 17/5/2014 18/5/2014 22/5/2014 4,700.00 4
6 Activity F 6 19/5/2014 21/5/2014 26/5/2014 12,600.00 5
30,900.00
-
Planning VS Actual S-curve Activity Duration
(days) Start Date
Actual Start Date
Actual Finish Date
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
Act. A 3 4/5/14 4/5/14 6/5/14
Act. B 5 7/5/14 7/5/14 12/5/14
Act. C 7 10/5/14 11/5/14 17/5/14
Act. D 5 15/5/14
17/5/14 21/5/14
Act. E 4 17/5/14 18/5/14 22/5/14
Act. F 6 19/5/14 21/5/14 26/5/14
Planning cumulative work / day
Actual cumulative work/ day
STEP 1: DRAW BAR CHART (planning and actual)
Planning
Actual
-
Planning VS Actual S-curve Activity Duration
(days) Start Date
Actual Start Date
Actual Finish Date
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
Act. A 3 4/5/14 4/5/14 6/5/14
Act. B 5 7/5/14 7/5/14 12/5/14
Act. C 7 10/5/14 11/5/14 17/5/14
Act. D 5 15/5/14
17/5/14 21/5/14
Act. E 4 17/5/14 18/5/14 22/5/14
Act. F 6 19/5/14 21/5/14 26/5/14
Planning cumulative work / day
Actual cumulative work/ day
STEP 2: Calculate cumulative for both planning & actual work/day
-
Activity Duration (days)
Start Date
Actual Start Date
Actual Finish Date
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
Act. A 3 4/5/14 4/5/14 6/5/14
Act. B 5 7/5/14 7/5/14 12/5/14
Act. C 7 10/5/14 11/5/14 17/5/14
Act. D 5 15/5/14
17/5/14 21/5/14
Act. E 4 17/5/14 18/5/14 22/5/14
Act. F 6 19/5/14 21/5/14 26/5/14
Planning cumulative work / day 1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30
Actual cumulative work/ day 1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32
STEP 2: Calculate cumulative for both planning & actual work/day
Planning VS Actual S-curve
-
Activity Duration (days)
Start Date
Actual Start Date
Actual Finish Date
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
Act. A 3 4/5/14 4/5/14 6/5/14
Act. B 5 7/5/14 7/5/14 12/5/14
Act. C 7 10/5/14 11/5/14 17/5/14
Act. D 5 15/5/14
17/5/14 21/5/14
Act. E 4 17/5/14 18/5/14 22/5/14
Act. F 6 19/5/14 21/5/14 26/5/14
Planning cumulative work / day 1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30
Actual cumulative work/ day 1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32
Planning VS Actual S-curve STEP 3: Plot the S -curves
-
Activity Duration (days)
Start Date
Actual Start Date
Actual Finish Date
4/5
5/5
6/5
7/5
8/5
9/5
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
Act. A 3 4/5/14 4/5/14 6/5/14
Act. B 5 7/5/14 7/5/14 12/5/14
Act. C 7 10/5/14 11/5/14 17/5/14
Act. D 5 15/5/14
17/5/14 21/5/14
Act. E 4 17/5/14 18/5/14 22/5/14
Act. F 6 19/5/14 21/5/14 26/5/14
Planning cumulative work / day 1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30
Actual cumulative work/ day 1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32
Planning
Actual
STEP 3: Plot the S -curves
Planning VS Actual S-curve
-
Arrow Diagram Method (ADM) -Activity-on-Arrow (AOA) Network
Precedence Diagram Method (PDM) - Activity-on-Nodes (AON) Network
-
Network Diagram Activity on Arrow (AOA)/ Arrow Diagram
Method (ADM) In arrow diagram project task or activities are
represented by the arrow and connected by the node to express their logical relationship
Node represents an event. An activity starts or ends at a node.
Activity A
Node
Activity B
Node Node
-
ADM
Pour concrete Fixed rebar Fixed fwk
Fabricated rebar
Excavate trench
Fabricated formwork
Diagram for construction of pad footing
-
Network Diagram Activity on Node (AON)/ Precedence Diagram
Method (PDM)
activity is place on the node
The arrow used to connect between project task to show their logical relationship
Act. A Act. B
Node Node
-
Network Diagram
Diagram for construction of pad footing Arrow - Logical Node - Activity Logical Show the relationship between activities - Sequences of interrelated activity
-
Basic definition in network diagram
Activity- the performance of a task required to complete the project. An activity require time, cost, or both.
Network- a diagram to represent the relationship of activities to complete a project. The network may be drawn as ADM or PDM.
Duration- the estimated time required to perform an activity.
-
Activity Sequencing
Understand the order of how the job to be accomplished in the field.
The planner must understand how various activities of the project related to each other in term of their logical sequence.
Example preparing formwork before reinforcement could be place & than pouring concrete.
-
Activity Sequencing
Predecessor
A task whose start or finish date determines the start or finish date of its successor task.
Successor
A task whose start or finish date is driven by its predecessor task.
-
ADM vs. PDM
Item ADM PDM
Activity
Activities shown as an arrow or sometimes as a line.
ES: Early Start LS: Late Start
EF: Early Finish LF: Late Finish
D : Duration TF: Total Float
Activities shown on node.
Event/ Node
2 events / nodes
1 event
A ES EF
LS LF
A
D
TF
ES EF
LS LF
A D
TF
ES EF
LS LF
B D
TF
1 ES
LS 1
EF
LF 2
A
-
ADM vs. PDM ADM PDM
Early Start (ES) is the earliest possible time an activity can start.
Late Finish (LF) is the latest possible time an activity can finish without extending the completion date of the project.
Total float (TF)- the amount of time an activity may be delayed without delaying the completion date of the project.
TF = LF ES D or TF = LS ES or TF = LF EF
Free float (FF)- the amount of time an activity may be delayed without delaying the early start time of the
immediately following activity.
FF(i) = ES(j) EF(i) ; i-preceding activity, j-following activity
Late Start (LS) is the latest possible time an activity can start without extending the completing date of the project.
LS = LF - D
Early Finish (EF) is the earliest possible time an activity can finish if it is start on Early Start Time (ES) and finish within the planned duration.
EF = ES + D *D = duration
-
ADM vs. PDM ADM
-A and B are activities. 1, 2 and 3 are events
-Activity A has ID or label 1-2 ; Activity B has ID or label 2-3
-Activity A precedes activity B
PDM
1 2 A
ES EF
LS LF
A D
TF
ES EF
LS LF
B D
TF
1
3 B
ES EF
LS LF
B D
TF
2
Activity Nodes
Predecessor Activity
Current Activity
Successor Activity
-
ADM vs. PDM Item ADM PDM
Relationshi
p
F S
ADM only shows finish-to-
start relationships, meaning
that each activity is
completed before the
successor activity starts.
F S F F S S S - F
Critical
path
- Critical Path
- A series of interconnected activities through the network
diagram, with each activity having zero total float time. The
critical path determines the minimum time to complete the
project.
- Possible to have more than one critical path
- Activities which lay on critical path cannot suffer any delay
1. ESX = LSX, or
2. LFX = EFX, or
3. Total Float (TF) = 0
-
ADM vs. PDM Item ADM PDM
Dummy Activity
or
Definition
An activity that
indicates any activity
following the dummy
cannot be started until
the activity(ies)
preceding the dummy are
completed.
Activity which has not
duration. It is only used
to show any relationship
between activities.
Function
If there is a situation
where one event is used
to show relationship more
than one activity.
To show a complicated
relationship clearly
Dummy activity is not used
in Precedence Diagram
Method (PDM)
D
-
ADM
-
Item ADM
Dummy Activity
or
False
True
D
1 2 1 2
3
A
B
A
B
C
D
A
B
A
B
C
D
Activity A & B have the same
ID
A: 1-2
B: 1-2
ID for Activity A & B are not
same.
A: 1-2
B: 1-3
If C is to follow A & B,
but D is to follow only B.
(not fulfill)
If C is to follow A & B,
but D is to follow only B.
(use dummy)
-
Item ADM
Dummy Activity
or
False
True
D
A 1 2 Q
3 B
4
P
R
If P, Q and R follow A, and B follows P, Q and R. The following diagram is not the correct representation of the same.
A 1 2 Q
3 B
4
P
R
5
6
Reason: Activities P, Q and R have the same ID (2-3).
Activities P has the ID (2-5), Q (2-3) and R (2-6).
-
Item ADM
Dummy Activity
or
False
True
D
1. D is preceded by A only 2. E is preceded by A and B 3. F is preceded by B and C
A
B
C
D
F
E
A
B
C
D
F
E
Statement 3 not fulfill
where F is preceded by
A, B and C.
-
92
ADM vs. PDM
Item ADM PDM
Estimating
duration
- FORWARD PASS
: To establish the earliest expected start and finish times for each activity in the network.
- BACKWARD PASS
: To establish the latest allowable start and finish times for each activity in the network.
Early Start
Early Finish
Late Start
Late Finish
FORWARD PASS
BACKWARD PASS
-
93
Arrow Diagram Method
A 1
a
b 2 c
d X
B 3 e
f Y
Forward pass
Backward pass
Note a : Early Start (ES)A b : Late Start (LS)A c : Early Finish (EF)A = (ES)B d : Late Finish (LF)A = (EF)B e : Early Finish (EF)B
f : Late Finish (LF)B X : Duration of activity A
Y : Duration of activity B
Forward pass Backward pass a = 0 f = e
c = a + X d = f Y
e = c + Y b = d - X
c = a + X e = c + Y
d = f Y
-
ACTIVITY DURATION(DAY) PREDECESSOR
A 3 -
B 5 A
C 3 B
D 4 -
E 4 A
F 10 E,D
G 9 C,F
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4 9
ACTIVITY DURATION (DAY)
PREDECESSOR
A 3 -
B 5 A
C 3 B
D 4 -
E 4 A
F 10 E,D
G 9 C,F
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4 9
Early Start Box
Early Finish Box
Early Start at node 1 is zero
Make forward pass through the network by adding duration times.
0
0+3=3
3
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4 9
Early Start Box Early Finish Box
Make forward pass through the network by adding duration times.
0
3+5=8 3 8
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4 9
0
3 8
If two or more activities terminate at a junction node, place the larger sum at ES box.
3+4=7
0+4=4 Larger=7
7
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4 9
0
3 8
7
17 26
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4 9
0
3 8
7
17 26
Enter 26 into Late Finish box at the node 6, and make a backward pass to establish LF for each activity by deducting the durations.
26
Early finish of activity G in the node 6 =26 days. Thats means it will take 26 days to complete the project. Therefore, 26 days represents Late Finish of the project.
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4
9
0
3 8
7
17 26
26
26-9=17
17
14
7
In the case of junction nodes (with two or more activities), place the smaller value in the LF box of that node.
14-5=9
7-4=3
3 Smaller=3
0
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4
9
0
3 8
7
17 26
26 17
14
7
3
0
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4
9
0
3 8
7
17 26
26 17
14
7
3
0
Total Float (TF) =LF-D-ES
TFA = LF-D-ES =3-3-0
=0
TFA=0
TFB=6
TFC=6
TFD=3
TFE=0
TFF=0
TFG=0
TFB = LF-D-ES =14-5-3
=6
-
1
2 3
5
4
6
A
D
B
E
C
F
G 3
5
3
4 10
4
9
0
3 8
7
17 26
26 17
14
7
3
0
Activities on critical path : A,E,F and G.
TFA=0
TFB=6
TFC=6
TFD=3
TFE=0
TFF=0
TFG=0
-
ACTIVITY DURATION(DAY) ES EF LS LF TF
A 3 0 3 0 3 0*
B 5 3 8 3 14 6
C 3 8 17 14 17 6
D 4 0 7 0 7 3
E 4 3 7 3 7 0*
F 10 7 17 7 17 0*
G 9 17 26 17 26 0*
* Critical Activity
Total Float (TF) =LF-D-ES
-
BAR CHART
Activity Duration (days)
1 2 3 4 5 6 7 8 9 10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
A 3
B 5
C 3
D 4
E 4
F 10
G 9
ACTIVITY DURATION (DAY)
ES EF LS LF TF
A 3 0 3 0 3 0*
B 5 3 8 3 14 6
C 3 8 17 14 17 6
D 4 0 7 0 7 3
E 4 3 7 3 7 0*
F 10 7 17 7 17 0*
G 9 17 26 17 26 0*
-
Example 2 (ADM) Activity Duration (day) Predecessor (s)
Act. A 2 -
Act. B 3 -
Act. C 3 A
Act. D 4 B
Act. E 3 C,D
Act. F 2 C,D
Act. G 4 E
Act. H 3 F
1. Develop an arrow diagram for the project. 2. Identify critical activity and critical path for the project.
-
1
2
4
5
3
7
A
B
C
D
E
F
G
2 3
3
3 2 4
4
Activity Duration (day) Predecessor (s)
Act. A 2 -
Act. B 3 -
Act. C 3 A
Act. D 4 B
Act. E 3 C,D
Act. F 2 C,D
Act. G 4 E
Act. H 3 F
6
H
3
-
1
2
4
5
3
7
A
B
C
D
E
F
G
2 3
3
3 2 4
4
6
H
3
Forward pass
0
2
3
7
10
9
14
-
1
2
4
5
3
7
A
B
C
D
E
F
G
2 3
3
3 2 4
4
6
H
3
Backward pass
0
2
3
7
10
9
14
14
11
10
7
3
0
4
-
Total Float
Activity Duration (day)
ES EF LS LF TF
Act. A 2 0 2 0 4 2
Act. B 3 0 3 0 3 0*
Act. C 3 2 7 4 7 2
Act. D 4 3 7 3 7 0*
Act. E 3 7 10 7 10 0*
Act. F 2 7 9 7 11 2
Act. G 4 10 14 10 14 0*
Act. H 3 9 14 11 14 2
* Critical Activity Total Float (TF) =LF-D-ES
-
2
4
5
3
7
A
B
C
D
E
F
G
2 3
3
3 2 4
4
6
H
3
Critical Path
2
3
7
10
9
14
14
11
10
7
3
1 0
0
4
Critical path Activities on critical path : B,D,E and G.
-
Exercise 3 (ADM)
Prepare a arrow diagram for the project. Identify critical path for the project.
Activity Duration (day) Predecessor (s)
Act. A 2 -
Act. B 3 A
Act. C 5 A
Act. D 4 A
Act. E 2 B,C
Act. F 3 C
Act. G 4 C,D
Act. H 2 E,F,G
-
A C
Exercise 3 Forward pass
D 4
B 3
F 3
H 1
0 2
2 3
7
4 7
6 11 7
13
5 7
2 2 5
5,7
6,7
9,10,11
-
A C
Exercise 3 Backward pass
D 4
B 3
F 3
H 1
0
0 2
2
2 3
7
7
4 7
9
6 11
11 7
13
13
5 7
7
2 2 5
9,8,7
6,2,3
-
A 2
C 5
Exercise 3 (ADM-Solution)
Critical path
D 4
B 3
F 3
H 2
1 0
0 2
2
2 3
7
7
4 7
9
6 11
11 7
13
13
5 7
7
Activities on critical path : A,C,G and H.
-
Link (Relationship)
Finish to Start (FS)
Activity B cannot start until Activity A finish
Start to Start (SS)
Activity B cannot start until Activity A start
Act. A Act. B
Act. A
Act. B
-
Finish to Finish (FF)
Activity B cannot finish until Activity A finish.
Start to Finish (SF)
Activity B cannot finish until Activity A start.
Act. A
Act. B
Act. A
Act. B
Link (Relationship)
-
Lead time & lag time
Lead time Overlap between
dependent activity
Eg : FS 5d
Lag time Delay between
dependent activity
Eg: FS + 2 d
Act. A
Act. B
5d
Act. A
Act. B
2d
-
ACTIVITY DURATION(DAY) PREDECESSOR
A 2 START
B 6 A
C 6 B
D 1 B
E 3 A
F 3 D,E
G 2 C(+2),F
-
A
2
B
6
C
6
D
1
E
3
F
3
G
2 FS +2
EXAMPLE 1
ACTIVITY DURATION (DAY)
PREDECESSOR
A 2 START
B 6 A
C 6 B
D 1 B
E 3 A
F 3 D,E
G 2 C(+2),F
ES LS D
LS LF TF
Activity
-
A
2 0 2
B
6 2 8
C
6 8 14
D
1 8 9
E
3 2 5
F
3 9 12
G
2 16 18
16,12
FS +2
5,9
FORWARD PASS
EXAMPLE 1
-
A
2 0 2
B
6 2 8
C
6 8 14
D
1 8 9
E
3 2 5
F
3 9 12
G
2 16 18
16,12
FS +2
5,9
EXAMPLE 1
18 16
16
BACKWARD PASS
-
A
2 0 2
B
6 2 8
C
6 8 14
D
1 8 9
E
3 2 5
F
3 9 12
G
2 16 18
16,12
FS +2
5,9
EXAMPLE 1
2 2 8 8 14
12 13
18 16
16 13
13 10
8,12 2,10
BACKWARD PASS
-
A
2 0 2
B
6 2 8
C
6 8 14
D
1 8 9
E
3 2 5
F
3 9 12
G
2 16 18
16,12
FS +2
5,9
EXAMPLE 1
0 2 2 8 8 14
12 13
18 16
16 13
13 10
8,12 2,10
BACKWARD PASS
-
A
2 0 2
0 2
B
6 2 8
2 8
C
6 8 14
8 14
D
1 8 9
12 13
E
3 2 5
F
3 9 12
G
2 16 18
16,12
FS +2
5,9
18 16
16 13
13 10
8,12 2,10
COMPLETED
EXAMPLE 1
-
127
A
2 0 2
0 2
B
6 2 8
2 8
C
6 8 14
8 14
D
1 8 9
12 13
E
3 2 5
F
3 9 12
G
2 16 18 FS +2
18 16
16 13
13 10
TOTAL FLOAT
EXAMPLE 1
TFA = LF-EF
=2-2
=0
TFB = LF-EF
=8-8
=0
TFC = LF-EF
=14-14
=0
TFD = LF-EF
=13-9
=4
TFE = LF-EF
=13-5 =8
TFG = LF-EF
=18-18
=0
TFF = LF-EF
=16-12
=4
0 0
4
8
0
4
0
-
128
A
2 0 2
0 2
B
6 2 8
2 8
C
6 8 14
8 14
D
1 8 9
12 13
E
3 2 5
F
3 9 12
G
2 16 18 FS +2
18 16
16 13
13 10
FREE FLOAT
EXAMPLE 1
FFA = ESSUCC-EF-
Lag
=2-2-0
=0
0 0
4
8
0
4
0
FFB = ESSUCC-EF-
Lag
=8-8-0
=0
FFC = ESSUCC-EF-
Lag
=16-14-2
=0
FFD = ESSUCC-EF-
Lag
=9-9-0
=0
FFF = ESSUCC-EF-
Lag
=16-12-0
=4
FFA = ESSUCC-
EF- Lag
=18-18-
0
=0
-
A
2 0 2
0 2
B
6 2 8
2 8
C
6 8 14
8 14
D
1 8 9
12 13
F
3 9 12
G
2 16 18
16,12
FS +2
5,9
18 16
16 13
8,12 2,10
CRITICAL PATH
EXAMPLE 1
0 0
4
E
3 2 5
13 10 8
0
4
0
-
Example 2 (PDM) Activity Duration (day) Predecessor (s)
Act. A 10 -
Act. B 11 A
Act. C 5 B
Act. D 4 B
Act. E 12 A
Act. F 3 C,D
Act. G 7 F
Act. H 11 E
Act. I 4 G,H
1. Develop a precedence diagram for the project. 2. Identify critical activity and critical path for the project.
-
Example 2 (PDM)
A
10
B
11
E
12
H
11
I
4
ES LS D
LS LF TF
Activity
C
5
D
4
F
3
G
7
-
Example 2 (PDM-forward pass)
A
10 0 10
B
11 10 21
E
12 10 22
H
11 22 33
I
4 36 40
ES LS D
LS LF TF
Activity
C
5 21 26
D
4 21 25
F
3 26 29
G
7 29 36
-
Example 2 (PDM-backward pass)
A
10 0 10
10 0
B
11 10 21
21 10
E
12 10 22
25 13
H
11 22 33
36 25
I
4 36 40
40 36
ES LS D
LS LF TF
Activity
C
5 21 26
26 21
D
4 21 25
26 22
F
3 26 29
29 26
G
7 29 36
36 29
-
Example 2 (PDM-Total float)
A
10 0 10
10 0 0
B
11 10 21
21 10 0
E
12 10 22
25 13 3
H
11 22 33
36 25 3
I
4 36 40
40 36 0
ES LS D
LS LF TF
Activity
C
5 21 26
26 21 0
D
4 21 25
26 22 1
F
3 26 29
29 26 0
G
7 29 36
36 29 0
Critical path TF = LF ES D or TF = LS ES or TF = LF EF
-
Example 3 (PDM) Activity Duration (week) Predecessor (s)
Act. A 2 -
Act. B 3 A (FS+2), C (FF+1),
D(FF)
Act. C 2 A
Act. D 1 C (SS)
1. Develop a precedence diagram for the project. 2. Identify critical activity and critical path for the project.
-
Example 3 (PDM-forward pass)
+2
+1
A
2 0 2
B
3 4 7
C
2 2 4
D
1 2 3
-
Example 3 (PDM-backward pass)
Critical path
+2
+1
Total Float = LF ES D TF(A) = 2-0-2 = 0 TF(B) = 7-4-3 = 0 TF(C) = 6-2-2 = 2 TF(D) = 7-2-1 = 4
A
2 0 2
2 0 0
B
3 4 7
7 4 0
C
2 2 4
6 4 2
D
1 2 3
7 6 4
-
Exercise 4(PDM)
Prepare a precedence diagram for the project. Identify critical path for the project.
Activity Duration (day) Predecessor (s)
Act. A 2 -
Act. B 3 A
Act. C 5 A
Act. D 4 A
Act. E 2 B,C
Act. F 3 C
Act. G 4 C,D
Act. H 2 E,F,G
-
Exercise (PDM-Solution)
A
2 0 2
2 0 0
B
3 2 5
9 6 4
C
5 2 7
7 2 0
D
4 2 6
7 3 1
E
2 7 9
11 9 2
F
3 7 10
11 8 1
G
4 7 11
11 7 0
H
2 11 13
13 11 0
-
BUT WAIT!!
Are there any other type of Scheduling method??
How if the Gantt Chart and CPM did not actually work/represent well with the nature/requirement of the particular construction project??
So, actually we have LINEAR SCHEDULING METHOD (LSM) / LINE OF BALANCE (LOB)
-
This method is actually appropriate for a project that:
Progress linearly (straight without major fluctuation of activities),
Highly repetitive works,
Have fixed starting point and end,
Such as; highways, airfields, pipelines, multiple housing units, high-rise buildings, etc.
-
LINEAR SCHEDULING METHOD (LSM) (cont.)
Take for example; a highway construction project:
-
LINEAR SCHEDULING METHOD (LSM) (cont.)
LSM Diagram for highway project (adopted from Nunnally, 2014)
Kilo
met
er (
km)
We have 5 linear activities: 1. Clear & strip 2. Drainage 3. Subgrade 4. Base course 5. Pave Width of B: At 40km, the subgrade works will starts at week 4.4 until week 5. Height of A: At week 3, subgrade works from 13km to 21km. Distance of C: It is a time lag / time float for 10km; between subgrade works and base course works. 1.4 weeks to be exact.
-
QUESTION 2
A project have a detail as below:
1. Draw the precedence diagram for the schedule shown next.
2. Determine the duration of project required.
3. Determine the Total Float for each activities and give the critical path for this project.
4. Draw a bar chart.
ACTIVITY PREDECESSOR DURATION (WEEK) A - 3 B - 1 C - 2 D A 3 E B 1 F C 4 G D 2 H D,E 1 I D,E,F 2 J G 3 K H 2 L I 1 M J,K,L 2
-
ACTIVITY SUCESSOR DURATION
(WEEK) A A-B (S-S),L=5 3 A-C (F-S),L=2 B B-E (F-S),L=3 1 C C-E (F-S),L=0 2 D D-E (F-S),L=0 2 E E-F (F-S),L=0 3 F 2
1. Draw the precedence diagram for the schedule shown next. 2. Determine the duration of project required. 3. Determine the Total Float for each activities and give the critical path for this project. 4. Draw a bar chart.
-
No. Activity Duration (week)
Successor Relationship Lag (week)
1 A 5 B, C, D AB (SS) AC (FS) AD (FS)
1 2 0
2 B 4 E BE (FS) 0 3 C 3 F, G CF (FS)
CG (FS) 0 0
4 D 2 H DH (FS) 0 5 E 7 F, G EF (FS)
EG (FS) 0 0
6 F 2 I FI (FS) 0 7 G 5 I GI (FS) 0 8 H 3 I HI (FS) 3 9 I 6 - - -
1. Estimate the total project duration. 2. Calculate the total float for each activity in the project. 3. State the critical path.