Chapter 5 Present Worth (PW) Analysis

download Chapter 5 Present Worth (PW) Analysis

of 32

Transcript of Chapter 5 Present Worth (PW) Analysis

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    1/32

    1

    GENG 360:EngineeringEconomics

    Chapter 5. Present Worth

    (PW) Analysis

    2

    Contents

    Formulating Alternatives PW of Equal-Life Alternatives PW of Different-Life alternatives Future Worth Analysis Capitalized Cost Analysis Payback Period

    Life-Cycle Costs PW of Bonds Spreadsheet Applications

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    2/32

    3

    5.1. Formulating Mutually Exclusive

    Alternatives

    Firms have the capability to generatepotential projects for investment

    Two types of investment categories

    Mutually Exclusive Set

    Independent Project Set

    4

    Mutually Exclusive set

    It is a set where a candidate set ofalternatives exist (more than one)

    Objective: Pick one and only one from theset.

    Once selected, the remaining alternativesare excluded.

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    3/32

    5

    Independent Project Set

    Given a set of alternatives (more than one)

    Objective is to:

    Select the best possible combination of projects fromthe set that will optimize a given criteria.

    Subjects to constraints

    More difficult problem than the mutually exclusive

    approach

    6

    Mutually Exclusive Vs.Independent Alternatives

    Mutually exclusive alternatives compete witheach other.

    Independent alternatives may or may notcompete with each other

    The independent project selection problem dealswith constraints and may require a mathematicalprogramming or bundling technique to evaluate

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    4/32

    7

    Type of Alternatives

    (Revenue based or service-based)Cash Flows determine whether the alternativesare revenue based or service based. Revenue/Cost the alternatives consist of cash

    inflow and cash outflows

    Select the alternative with the maximumeconomic value

    Service the alternatives consist mainly of costelements

    Select the alternative with the minimumeconomic value (min. cost alternative)

    8

    Problem

    DoNothing

    Alt.1

    Alt.2

    Alt.m

    Analysis

    Selection

    Execution

    Selection depends upon data, life, discount rate, and assumptions made.

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    5/32

    9

    5.2 Present Worth Approach with Equal-Lives

    Simple: Transform all of the current and future

    estimated cash flow back to a point in time (time t = 0)

    Result is in equivalent dollars now!

    P(i%) = P(+cash flows) +P(-cash flows)

    10

    If P(%) is:

    > 0 then the project is deemed acceptable.

    < 0 the project is usually rejected= 0 (Present worth of costs = Present

    worth of revenues) Indifferent!If P(%) = 0 that meansthe project earned exactlythe discount rate that wasused to discount the cash

    flows!

    The interest rate that causesa cash flows NPV to equal 0is called the Rate of Returnof the cash flow!

    The net present worth is purely a function of theMARR (the discount rate one uses).

    If one changes the discount rate, a different NPV willresult.

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    6/32

    11

    For P(i%) > 0, the following holds true:

    A positive present worth is a dollar amount

    of "profit" over the minimum amount

    required by the investors (owners).

    Acceptance or rejection of a project is afunction of the timing and magnitude of theproject's cash flows, and the choice of thediscount rate.

    12

    PRESENT WORTH: Special Applications

    Present Worth of Equal Lived Alternatives

    Alternatives with unequal lives: Beware

    Capitalized Cost Analysis

    Both Calculations Require knowledge of the discount rate before

    we conduct the analysis

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    7/32

    13

    Present Worth of Equal Lived

    Alternatives Straightforward: Compute the PW of each

    alternative and select the best,

    i.e., smallest if cost and largest if profit

    14

    Example:

    Consider: Machine A Machine B

    First Cost $2,500 $3,500

    Annual Operating Cost 900 700

    Salvage Value 200 350

    Life 5 years 5 years

    i = 10% per year

    Which alternative should we select?

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    8/32

    15

    Solution: Cash Flow Diagrams:

    0 1 2 3 4 5

    $2,500A = $900

    F5=$200

    MA

    0 1 2 3 4 5

    $3,500

    F5=$350

    A = $700

    MB

    PA = 2,500 + 900 (P|A, 0.10, 5) 200 (P|F,0.10, 5)= 2,500 + 900 (3.7908) - 200 (0.6209)= 2,500 + 3,411.72 - 124.18 = $5,788

    PB = 3,500 + 700 (P|A, 0.10, 5) 350 (P|F,0.10, 5)= 3,500 + 2,653.56 - 217.31 = $5,936

    Which alternativeshould we select?

    SELECTMACHINE A:Lower PW cost!

    16

    Present Worth of Alternativeswith Different Lives

    BASIC RULE: In an analysis one cannot effectivelycompare the PW of one alternative with a study period

    different from another alternative that does not have the

    same study period.

    Comparison must be made over equal time periods

    Compare over the Least Common Multiple (LCM) for their lives

    Example:You have different projects over{3,4, and 6}yearsThe LCM life is 12 years (6x2) Evaluate all over 12 years for aPW analysis.

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    9/32

    17

    Example:Machine A Machine B

    First Cost $11,000 $18,000

    Annual Operating Cost 3,500 3,100

    Salvage Value 1,000 2,000

    Life 6 years 9 years

    i = 15% per year

    Note: Where costs dominate a problem it is customary to assign apositive value to cost and negative to inflows

    18

    LCM(6,9) = 18 year study period will apply for present worth

    A commonmistake isto computethe presentworth of

    the 6-yearproject andcompare it

    to thepresentworth of

    the 9-yearproject.

    i = 15% per year

    0 1 2 3 4 5 6

    $11,000

    F6=$1,000

    A 1-6

    =$3,500

    Machine A

    0 1 2 3 4 5 6 7 8 9

    F6=$2,000

    A 1-9

    =$3,100

    $18,000

    Machine B

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    10/32

    19

    i = 15% per year

    Machine A

    LCM(6,9) = 18 year study period will apply for present worth

    Cycle 1 for A Cycle 2 for A Cycle 3 for A

    6 years 6 years 6 years

    Cycle 1 for B Cycle 2 for B

    18 years

    9 years 9 years

    Machine B

    20

    First, Calculate the PW of Machine A:

    Machine A

    Cycle 1 for A Cycle 2 for A Cycle 3 for A

    6 years 6 years 6 years

    PA6 = 11,000 + 3,500 (P|A, .15, 6) 1,000 (P|F, .15, 6)= 11,000 + 3,500 (3.7845) 1,000 (.4323)= $23,813, which occurs at time 0, 6 and 12

    0 1 2 3 4 5 6

    $11,000

    F6=$1,000

    A 1-6 =$3,500

    Machine A

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    11/32

    21

    0 6 12 18

    $23,813 $23,813 $23,813

    Machine A

    PA18=23,813 +23,813 (P|F, 0.15, 6) +23,813 (P|F, 0.15, 12)

    =23,813 +10,294 +4,451 =$38,558

    22

    Calculate the Present Worth of a 9-year cycle for B

    0 1 2 3 4 5 6 7 8 9

    F6=$2,000

    A 1-9

    =$3,100

    $18,000

    PB9 = 18,000+3,100(P|A, .15, 9) 2,000(P|F, .15, 9)= 18,000 + 3,100(4.7716) - 2,000(.2843)= $32, 223 which occurs at time 0 and 9

    0 9 18

    $32,508 $32,508

    PB18 = 32,508 + 32,508 (P|F, .15, 9)= 32,508 + 32,508(.2843) = $41,750

    Choose Machine A because it costs less

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    12/32

    23

    11000

    18 years

    Alternative (A) cash flow:

    3500 35003500

    11000 11000

    1000 10001000

    Alternative (B) cash flow:

    18000

    3100 3100

    18000

    20002000

    18 years

    PWA = - 11,000 3,500 (P/A, 15%, 18) 10,000 (P/F, 15%, 6)-10,000 (P/F, 15%, 12) + 1,000 (P/F, 15%, 18)= - 38,559

    PWB = - 18,000 3,100 (P/A, 15%, 18) 16,000 (P/F, 15%, 9)

    + 2,000 (P/F, 15%, 18) = -41,384

    We Select (A)

    24

    5.4. FUTURE WORTH APPROACH

    Compound all cash flows forward in time to somespecified time period using (F/P), (F/A), factors or,

    Given P, the F = P(1+i)N

    Applications of FW Analysis: Projects that do not come on line until the end of the investment

    period Commercial Buildings

    Marine Vessels Power Generation Facilities

    Public Works Projects

    Key long time periods involving construction activities

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    13/32

    25

    FW Exercise See Example 5.3

    Calculate the Future Worth of determiningthe selling price in order to earn exactly25% on the investment

    Draw the cash-flow diagram!!

    26

    5.5 Capitalized Cost

    Capitalized Cost: the PW of a project that lastsforever, such as:Government Projects

    Roads, Dams, Bridges (projects that possessperpetual life)

    Infinite analysis period

    Perpetual Investments: Investments that lastfor such a long time (n ~ )

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    14/32

    27

    Derivation for Capitalized Cost:

    Start with the closed form for the P/A factor:

    Next, let N approach infinity and divide thenumerator and denominator by (1+i)N

    (1 ) 1

    (1 )

    N

    N

    iP A

    i i

    1

    1 (1 )NiP A

    i

    28

    Now, let n approach infinity and the right hand sidereduces to.

    iAPn

    1CostdCapitalize

    Or,

    CC(i%) = A/i

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    15/32

    29

    Example:Calculate the Capitalized Cost of a project

    that has an initial cost of $150,000. Theannual operating cost is $8,000 for thefirst 4 years and $4,000 thereafter. Thereis an recurring $15,000 maintenancecost each 15 years. Interest is 15% per

    year.

    30

    Cash Flow Diagram:

    $4,000

    0 1 2 3 4 5 6 7 15 30

    $150,000

    $8,000

    $15,000 $15,000 $15,000 $15,000How much $$ at t = 0is required to fundthis project?

    The capitalized cost is thetotal amount of $ at t = 0,when invested at theinterest rate, will provideannual interest that coversthe future needs of theproject.

    i=15%/YR

    Solution:

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    16/32

    31

    1. Consider $4,000 of the $8,000 cost for thefirst four years to be a one-time cost, leaving

    a $4,000 annual operating cost forever:

    P0= 150,000 + 4,000 (P|A, .15, 4) = $161,420

    Recurring annual cost is $4,000 plus theequivalent annual of the 15,000 end-of-cyclecost.

    .0 15 30 45 60 ..

    Take any 15-year period and find the equivalentannuity for that period using the F/A factor.

    32

    Take any 15-year period and find the equivalentannuity for that period using the F/A factor

    $15,000

    A for a 15-year period

    0 15 30 45 60 ...

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    17/32

    33

    2. Recurring annual cost is $4,000 plus

    the equivalent annual of the 15,000 end-of-cycle cost.

    A= 4,000 + 15,000 (A|F, .15, 15)

    = 4,000 + 15000 (.0210) = $4,315/yr

    Recurring costs = $4,315/i = 4,315/0.15

    =$28,767

    34

    Capitalized Cost = 161,420 + 4315/.15

    = $190,187

    Thus, if one invests $190,187 at time t = 0,then the interest at 15% will supply the end-of-year cash flow to fund the project so longas the principal sum is not reduced or theinterest rate changes (drops).

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    18/32

    35

    Example: Find the capitalized cost for the following project (use i =15%).

    Time $

    Initial Cost At end of year 0 150,000

    Additional Cost At end of year 10 50,000

    Annual Cost From end of year 1 to end of year 4 5000

    Annual Cost From end of year 5 to 8000

    Operation Cost End of every13 years 15000

    36

    Solution:

    8 15 ( / ,15%,13)150 50 ( / ,15%,10) 5 8 ( / ,15%,4)

    0.15 0.15

    15 0.029118150 50 0.1229 3 5.8474

    0.15 0.15

    $194.847K

    K K A FP K K P F K K P A

    KKK K K

    5000

    150000

    8000

    5000015000 15000 15000

    0 1 4 5 10 13 26 39

    13 years

    8 15150 50 ( / ,15%,10) 5 8 / ,15%,40.15

    8 15150 50 0.1229 3 5.8474

    0.15 5.1528

    $194.847K

    K KP K K P F K K P A

    K KK

    i

    K K

    OR:

    i13 years =(1+0.15)13 1 =5.1528

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    19/32

    37

    Example:

    38Which one do you choose?

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    20/32

    39

    Incremental Analysis:The value of the present worth can be

    calculated by using either incrementalmethod or individual method.

    Both methods should lead to the sameanswer.

    40

    Example:

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    21/32

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    22/32

    43

    5.6 Payback Period Analysis Payback period is the period of time it

    takes for the cash flows to recover theinitial investment.

    Two forms for this methodDiscounted Payback Period (uses an interest

    rate)

    Conventional Payback Period (does not use

    an interest rate)

    44

    Payback period is only a rough estimator of desirability

    Use it as an initial screening method

    Avoid using this method as a primary analysis techniquefor selection projects

    Totally avoid the no-return payback period

    The No-return method (example follows):

    Does not employ the time value of money

    Disregards all cash flows past the payback time period

    If used, can lead to conflicting selections when compared tomore technically correct methods like present worth!

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    23/32

    45

    Discounted Payback Approach: Find the value of np such that:

    1

    0 ( / , , )pt n

    tt

    P NCF P F i t

    NCFt = Net CashFlow at time t

    46

    Example 5.8 (Discounted Analysis)Machine A: N=7 i = 15%

    Payback

    isbetween6 and 7yeas(6.57yrs)

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    24/32

    47

    Non-Discounted Analysis

    At a 0interest ratethe PB timeis seen to

    equal 4years!

    48

    Machine B (Discounted):Machine B: N=14 i = 15%

    Payback for B isbetween 9 and

    10 years!Longer time

    period torecover theinvestment.

    9.52 years

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    25/32

    49

    Machine B (Undiscounted):

    Payback for B at0% is 6 years!

    50

    Example Summary

    Discounted

    Machine A: 6.57 years

    Machine B: 9.52 years

    Undiscounted

    Machine A: 4.0 years

    Machine B: 6.0 years Go with Machine A lower time period payback

    to recover the original investment

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    26/32

    51

    5.8 Present Worth of Bonds

    Bonds represent a source of funds for thefirm.

    Bonds are sold (floated) by investmentbanks for firms in order to raise additionaldebt capital

    A bond is similar to an IOU

    Bonds are evidence of Debt

    52

    Bond Types: Treasury bonds

    Issued by Federal Government

    Full backing of the Government

    Conservative-type investment

    State and Municipal Bonds

    Issued by states and local governments

    Generally tax-exempt by the Federal Government

    Used to finance state and local projects

    Backed by future tax and user fees to pay the interestand face value

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    27/32

    53

    Mortgage Bonds Issued by Corporations

    Secured by the firms assets Money received by the firm is used to fund projects

    Referred to a Debt Capital

    Buyers of these bonds are not owners they are lenders to thefirm

    Debenture Bond Issued by Corporations

    Not backed by specific assets

    Backing good faith of the firm

    Pays higher interest rates

    Higher risks involved Bond interest rate may float

    Could be convertible to common stock

    54

    PW of Bonds - Overview

    The Firm

    Investment Bankers

    Proceeds from

    The sale

    Sell the Bonds toThe lending public

    Bondholders

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    28/32

    55

    Basics of Bonds: The bond itself is just a piece of paper Bonds are negotiable instruments

    Can be traded by the current bondholder

    Source of funds to the firm (Debt capital)

    Bondholders are loaning $$ to the firm, they Earn periodicinterest

    They can sell the bonds at any time

    The bondholders are lenders not owners

    The firm pays periodic interest payments to the currentbond holders

    At the end of the bonds life, the bonds are redeemed(bought back) from the current bond holder

    56

    Bonds Notations: P0:The time (t = 0) selling price of the bond the cost to

    the buyer of the bond

    V:The face value of the bond

    The value printed on the bond

    Face values are usually: $100, $1,000, $5,000, $10,000 increments

    N:The life of the bond in years (Defining the Maturity Date)

    r: The nominal annual bond interest rate

    Given the nominal annual bond interest rate, the payment

    frequency of the interest (monthly, quarterly semi-annually, etc.) is

    also stated(Facevalue)(Bondinerestrate)

    Numberof paymentperiodperyearI I: Amount of interest

    paid per period

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    29/32

    57

    Example: Calculate the Bond Semiannual interest if:

    V = $5,000 (face value)

    r = 4.5% per year paid semiannually

    N = 10 years

    Solution:

    0.045$5,000( ) $5,000(0.0225)

    2$112.50 every 6 months

    I

    I

    The bondholder,buys the bondand will receive

    $112.50 every 6months for thelife of the bond

    58

    Example 5.11

    Given V = $5,000 (Face value of the bond)

    r = 4.5% paid semiannually

    N = 10 years or 20 interest periods

    $I per 6 months = $5,000(0.045/2) = $112.50 paid tothe current bondholder

    The buyer will consider buying this bond if he canearn a nominal rate of return of 8%/yr c.q.

    (compounded quarterly)

    Calculate the acceptable purchase price

    Bonds are bought and sold in a bond market. Thus the priceof the bond is subject to the pressures of the bond market.

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    30/32

    59

    Solution: What is fixed?

    The future interest payments are fixed

    The future face value of the bond is fixed

    What can vary?

    The purchase price such that the buyer can earn at least the 8%/yr c.q.

    8% c.q is the same as

    0.08/4 =0.02 =2% per quarter.

    Bond interest flows every 6 months

    Need an effective 6-month rate

    The effective 6-month rate is then

    (1.02)2 1 =0.0404 =4.04%/6 months

    This is the potential buyers required interest rate

    The objective is to determine the purchase price of this bonddiscounted at the buyers required rate of 4.04% per 6 months

    60

    Draw the cash-flow diagram

    Work the problem with N = 20 (not 10): We have 20 interest payments (every 6 months for 10 years)

    A = 112.50/6 months

    0 1 2 3 4 . .. 19 20

    P=??

    $5,000

    i=4.04%/6 months

    Find the PW(4.04%) of the future cashflows to the potential bond buyer

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    31/32

    61

    P = $112.50(P/A,4.04%,20)+

    $5,000(P/F,4.04%,20)= $3,788

    IF the buyer can buy this bond for $3,788 orless, he/she will earn at least the 8% c.q. rate.

    62

    Example:

    A 15-year bond with a face value of$10,000 is offered for sale.

    The rate of interest on the bond is 6%,paid semi-annually.

    Assume that MARR = 8% nominal

    compounded semi-annually, what would be the selling price of the

    bond?

  • 7/29/2019 Chapter 5 Present Worth (PW) Analysis

    32/32

    63

    Solution:( )( ) (10000)(0.06) $300

    2Facevalue Bond inerest rateI

    Numberof payment period per year

    I =$300

    Price of bond =?

    30

    Face value =$ 10,000

    P =300(P/A, 4%, 30) +10,000(P/F, 4%, 30) =$8,270.6