Chap 6 Developing A Project Plan

26
Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6 McGraw-Hill/Irwin 6–1 Developing a Developing a Project Plan Project Plan

description

Project Management by Gary and Larson

Transcript of Chap 6 Developing A Project Plan

Page 1: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––11

Developing a Developing a Project PlanProject Plan

Developing a Developing a Project PlanProject Plan

Page 2: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––22

Developing the Project PlanDeveloping the Project PlanDeveloping the Project PlanDeveloping the Project Plan

• The Project Network–A flow chart that graphically depicts the sequence,

interdependencies, and start and finish times of the project job plan of activities that is the critical path through the network

•Provides the basis for scheduling labor and equipment

•Provides an estimate of the project’s duration

•Provides a basis for budgeting cash flow

•Highlights activities that are “critical” and should not be delayed

•Help managers get and stay on plan

Page 3: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––33

From Work Package…From Work Package…From Work Package…From Work Package…

FIGURE 6.1

WBS/Work Package- Sample

Page 4: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––44

……to Networkto Network……to Networkto Network

FIGURE 6.1 (cont’d)

Network based on prior WBS Sample

Page 5: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––55

Constructing a Project NetworkConstructing a Project NetworkConstructing a Project NetworkConstructing a Project Network

• Terminology

–Activity: an element of theproject that requires time.

–Merge activity: an activity that has two or more preceding activities on which it depends.

–Parallel (concurrent) activities: Activities that can occur independently and, if desired, at the same time…or not

A

C

B D

Page 6: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––66

Constructing a Project Network (cont’d)Constructing a Project Network (cont’d)Constructing a Project Network (cont’d)Constructing a Project Network (cont’d)

• Terminology

– Path: a sequence of connected, dependent activities.

– Critical path: the longest path through the activity network that allows for the completion of all project-related activities;It is also the shortest expected time in which the entire project can be completed. Delays on the critical path will delay completion of the entire project.

D

C

A B

(Assumes that minimum of A + B > minimum of C in length of times to complete activities.)

Page 7: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––77

• Terminology–Event: a point in time when an activity is started or

completed. It does not consume time.–Burst activity: an activity that has more than one activity

immediately following it (more than one dependency arrow flowing from it).

• Two Approaches to Networks–Activity-on-Node (AON)

•Uses a node to depict an activity•Used in Software Industry

–Activity-on-Arrow (AOA)•Uses an arrow to depict an activity•Traditional in Construction

B

D

A C

Constructing a Project Network (cont’d)Constructing a Project Network (cont’d)

Page 8: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––88

AoA vs. AoNAoA vs. AoNAoA vs. AoNAoA vs. AoN

• Fundamental difference in philosophy• DS856 will use only AoN because it:

– …Emphasizes the process (i.e. QA) more than the end result – …dominates in more Bay Area relevant industries (software and

consulting) • AoA is only in the text’s appendix

– Is supported by MSProject– Lends itself to “post-it notes on the whiteboard” brainstorming– Doesn’t require use of “dummy activities” or other confusing

conceits• Can duplicate an AoA network through use milestones

and deliverables

Page 9: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––99

Basic Guidelines to Follow in Developing Project Basic Guidelines to Follow in Developing Project NetworksNetworks

Basic Guidelines to Follow in Developing Project Basic Guidelines to Follow in Developing Project NetworksNetworks

• Networks typically flow from left to right.

• An activity cannot begin until all of its activities are complete.

• Arrows indicate precedence and flow and can cross over each other.

• Identify each activity with a unique number; this number must be greater than its predecessors.

• Looping is not possible!

• Conditional statements are not allowed.

• Use common start and stop nodes.

Page 10: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1010

Activity-on-Node FundamentalsActivity-on-Node FundamentalsActivity-on-Node FundamentalsActivity-on-Node Fundamentals

FIGURE 6.2

Page 11: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1111

Activity-on-Node Fundamentals (cont’d)Activity-on-Node Fundamentals (cont’d)Activity-on-Node Fundamentals (cont’d)Activity-on-Node Fundamentals (cont’d)

FIGURE 6.2 (cont’d)

Page 12: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1212

Example: Post-it WeddingExample: Post-it WeddingExample: Post-it WeddingExample: Post-it Wedding

• Below are a set of tasks and durations for a wedding. Break into groups of 3-5 and create a project network.– Put in a start and end activity

abrev Description Duration abrev Description Duration

OI Order Invitations 2 wks SB Select and Sign on Band 1 wk

DI Bride goes on Diet 6 wks UT Select Best Man&Usher's Tuxes 2 days

GA Get Wedding Gown altered 2 wks MB Audition Mariachi Bands 3 wks

BD Select Bridesmaids Dresses 4 wks FL Order Flowers 2 wks

SG Shop for Wedding Gown 4 wks PM Pick Menu 4 days

BA Get Bridemaids' Dresses altered 4 wks HO Hire Officiant 1 wk

HC Hire Caterers 2 wks OF Tell Caterer headcount & Order food 1 wk

SS Select Site&Date 3 wks CR Collect RSVPs 6 wks

GT Select Grooms Tux 2 days SI Sent Invitations to Guests 1 wk

Page 13: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1313

Network Information: ExampleNetwork Information: ExampleNetwork Information: ExampleNetwork Information: Example

TABLE 6.1

Let’s build the structure first…

Page 14: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1414

Koll Business CenterKoll Business Center—Complete Network—Complete NetworkKoll Business CenterKoll Business Center—Complete Network—Complete Network

FIGURE 6.4

Page 15: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1515

Network Computation ProcessNetwork Computation ProcessNetwork Computation ProcessNetwork Computation Process

• Forward Pass—Earliest Times

– How soon can the activity start? (early start—ES)

– How soon can the activity finish? (early finish—EF)

– How soon can the project finish? (expected time—ET)

• Backward Pass—Latest Times

– How late can the activity start? (late start—LS)

– How late can the activity finish? (late finish—LF)

– Which activities represent the critical path?

– How long can it be delayed? (slack or float—SL)

Page 16: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1616

Network InformationNetwork InformationNetwork InformationNetwork Information

TABLE 6.2

Page 17: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1717

Activity-on-Node NetworkActivity-on-Node NetworkActivity-on-Node NetworkActivity-on-Node Network

FIGURE 6.5

Page 18: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1818

Forward Pass ComputationForward Pass ComputationForward Pass ComputationForward Pass Computation

• Add activity times along each path in the network (ES + Duration = EF).

• Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless…

– The next succeeding activity is a merge activity, in which case the largest EF of all preceding activities is selected.

Page 19: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––1919

Activity-on-Node Network Forward PassActivity-on-Node Network Forward PassActivity-on-Node Network Forward PassActivity-on-Node Network Forward Pass

FIGURE 6.6

Page 20: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––2020

Backward Pass ComputationBackward Pass ComputationBackward Pass ComputationBackward Pass Computation

• Subtract activity times along each path in the network (LF - Duration = LS).

• Carry the late start (LS) to the next activity where it becomes its late finish (LF) unless...

– The next succeeding activity is a burst activity, in which case the smallest LF of all preceding activities is selected.

Page 21: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––2121

Activity-on-Node Network Backward PassActivity-on-Node Network Backward PassActivity-on-Node Network Backward PassActivity-on-Node Network Backward Pass

FIGURE 6.7

Don’t panic!- the ES-EF boxes are still filled in, but this diagram is just emphasizing how to get LS and LF

Page 22: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––2222

Activity-on-Node Network with SlackActivity-on-Node Network with SlackActivity-on-Node Network with SlackActivity-on-Node Network with Slack

FIGURE 6.8

Now that we have LS,LF in addition to EF, ES, we can fill LAST box in

Page 23: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––2323

Another Way to Find Slack-Another Way to Find Slack- The Gantt Chart The Gantt Chart

Another Way to Find Slack-Another Way to Find Slack- The Gantt Chart The Gantt Chart

• Once activity precedence and durations are established, we can determine the critical path and slack via a gantt chart.

• Gantt charts can be hand-drawn, but practitioners generally use

MS-Project.

Page 24: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––2424

Determining Slack Determining Slack (Not All Slack is Equal)(Not All Slack is Equal)Determining Slack Determining Slack

(Not All Slack is Equal)(Not All Slack is Equal)• Free Slack (or Float)

– The amount of time an activity can be delayed without delaying connected successor activities

– Tends to happen as the last activity in a path before a merge activity (when another path is the critical one).

• Total Slack– The amount of time an activity can be delayed without delaying the entire

project

• The critical path is the network path(s) that has (have) the least slack in common.– This class will avoid the confusion of negative slack! … thus all projects will

have their end activity have LF=EF

– So all critical path activities will have a total slack of 0.

Page 25: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––2525

Slack and Slackers: The Simplest Example of Slack and Slackers: The Simplest Example of Free SlackFree Slack

Slack and Slackers: The Simplest Example of Slack and Slackers: The Simplest Example of Free SlackFree Slack

• Take a 5 person marketing project –Team5– Remy writes the requirements doc- which will take 2 days– Polly can build the prototype from the requirements doc in 7 days– Su needs 3 days to survey potential consumers once he has the requirements

doc.– Al gets to analyze the consumer responses to the survey, which will take 2

days. – Fatima prepares the final presentation to management, so she needs the

prototype and the analysis from the survey. This will take 2 days. Which activities are:

1. Critical2. Have total slack but not free slack3. Have free slack

• Who can disappear for a day in the middle of their project and annoy the fewest people?

Page 26: Chap 6 Developing A Project Plan

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 6McGraw-Hill/Irwin 6––2626

Extended Network Techniques Extended Network Techniques to Come Close to Realityto Come Close to Reality

Extended Network Techniques Extended Network Techniques to Come Close to Realityto Come Close to Reality

• Laddering– Activities are broken into segments so the following activity can

begin sooner and not delay the work.• Lags

– The minimum amount of time a dependent activity must be delayed to begin or end

•Lengthy activities are broken down to reduce the delay in the start of successor activities.

•Lags can be used to constrain finish-to-start, start-to-start, finish-to-finish, start-to-finish, or combination relationships.– MS project defaults to finish-to-start, but represents all the others,

as well…