    Scope Management

    Practice Exam

    1. A work breakdown structure numbering system allows project staff to:

    A. Systematically estimate costs of work breakdown structure elements.

    B. Provide project justification

    C. Identify the levels at which individual elements are found.D. Use it in project management software

    2. The work breakdown structure can BEST be thought of as effective aid for ______

    communications.A. team

    B .project manager

    C. customer

    D. stakeholder

    3. Which of the following is a KEY attribute of scope verification?

    A. More complete project scope management plan

    B. Customer acceptance of project deliverablesC. Improved schedule estimates

    D. An improved project management information system

    4. During project executing, a team member comes to the project manager because he is not sureof what work he needs to accomplish on the project. Which of the following documents contain

    detailed descriptions of work packages?

    A. Work breakdown structure (WBS) dictionary

    B. Activity List

    C. Preliminary project scope statementD. Project scope management plan

    5. During what part of the project management process is the project scope statement created?

    A. Initiating

    B. Planning

    C. ExecutingD. Monitoring and controlling

    6. The program was planned years ago before there was a massive introduction of new technology.While planning the next project to start in this program, the project manager has expanded the

    project scope management plan because as a project becomes more complex, the level of

    uncertainty in the scope:

    A. remains the same

    1

  • 7/29/2019 Chap 05 Scope-Management

    2/8

    Scope Management

    B. decreases

    C. decreases then increasesD. increases

    7. A project management plan should be realistic in order to be used to manage the project. Whichof the following is the best method to achieve a realistic project management plan?

    A. Sponsor creates the project management plan based on input from the projectmanager.

    B. Functional manager creates the project management plan based on input from the

    project manager.

    C. Project manager creates the project management plan based on input from seniormanagement

    D. Project manager creates the project management plan based on input from the team.

    8.A new project manager is being mentored by a more experienced certified project managementprofessional(PMP).The new project manager id finding it difficult to find enough time to manage

    the project because the product and project scope are being progressively elaborated. The PMPmentions that the basic tools for project management, such as work breakdown structure, can be

    used during project executing to assist the project.

    For which of the following can a work breakdown structure be used?

    A. Communicating with the customer.

    B. Showing calendar dates foe each work package.

    C. Showing the functional managers for each team member.D. Showing the business need for the project.

    9. During a project team meeting, a team member suggests an enhancement to the scope that isbeyond the scope of the project charter. The project manager points out that the team needs to

    concentrate on completing all the work and only the work required. This is an example of:

    A. change management processB. scope management

    C. quality analysis

    D. scope decomposition

    10. When should scope verification be done?

    A. At the end of the project

    B. At the beginning of the projectC. At the end if each phase of the project

    D. During the planning processes

    11. The project is mostly complete. The project has a schedule variance of 300 and a cost variance

    of 900.All but one of the quality control inspections have been completed and all have met the

    quality requirements. All items in the issue log have been resolved. Many of the resources have

    been released. The sponsor is about to call a meeting to obtain product verification when the

    2

  • 7/29/2019 Chap 05 Scope-Management

    3/8

    Scope Management

    customer notifies the project manager that they want to make a major change to the scope. The

    project manager should:A. meet with the project team to determine if this change can be made.

    B. ask the customer for a description of the change

    C. explain that the change cannot be made at this point in the process.D. inform management.

    12. You have joined the project management office after five years of working on projects. One ofthe things you want to introduce to your company is the need to do WBSs. Some of the project

    managers are angry that you are asking them to do extra work. Which of the following would be

    the BEST thing you could tell the project managers to convince them to use WBSs?

    A. Tell them it will prevent work from slipping through the cracks.B. Tell them that it is not needed.

    C. Tell them it is required if the project involves contracts.

    D. Tell them it is the only way to identify risks.

    13. A new project manager has asked you for advice on creating a work breakdown structure.

    After you explain the process to him, he asks you what software he should use to create the WBSand what should he do with it when he is finished creating it. You might respond that it is not the

    picture that is the most valuable result of creating a WBS. It is:

    A. a bar chartB. team buy-in

    C. activities

    D. a list of risks.

    14. To manage a project effectively, work should be broken down into small pieces. Which of the

    following does NOT describe how far to decompose the work?

    A. Until it has a meaningful conclusion.B. Until it cannot be logically subdivided further

    C. Until it can be done by one person

    D. Until it can be realistically estimated

    15. A project manager may use ________to make sure the team clearly knows that work is

    included in each of their work packages.

    A. the project scope statementB. the product scope

    C. a WBS dictionary

    D. a schedule

    16. A project manager has just been assigned to a new project and has been given the preliminary

    project scope statement and the project charter. The FIRST thing the project manager must do is:A. create a project scope statement

    B. confirm that all the stakeholders have had input the scope

    C. analyze project risk

    D. begin work on a project management plan.

    3

  • 7/29/2019 Chap 05 Scope-Management

    4/8

    Scope Management

    17. The construction phase of a new software product is near completion. The next phase is testing

    and implementation. The project is two weeks ahead of schedule. What should the project manager

    be MOST concerned with before moving on to the final phase?A. scope verification

    B. quality control

    C. performance reportsD. cost control

    18. You are managing a six-month project and have held bi-weekly meetings with your project

    stakeholders. After five and a half months of work, the project is on schedule and budget, but thestakeholders are not satisfied with the deliverables. This situation will delay the project completion

    by one month. The MOST important process that could have prevented this situation is:

    A. risk monitoring and control

    B. schedule controlC. scope planning

    D. scope control

    19. All of the following are part of the scope baseline EXPECT the:

    A. project scope management planB. project scope statement

    C. work breakdown structure

    D. work breakdown structure dictionary

    20. One of the stakeholders on the project contacts the project manager to discuss some additional

    scope they would like to add to the project. The project manager asks for details in writing and

    then works through the scope control process. What should the project manager do NEXT whenthe evaluation of the requested scope is completed?

    A. Ask the stakeholder if there are anymore changes expected

    B. complete integrated change controlC. make sure the impact of the change is understood by the stakeholder

    D. find out the root cause of why the scope was not discovered during project planning

    4

  • 7/29/2019 Chap 05 Scope-Management

    5/8

    Scope Management

    Scope Management Answers1. Answer C

    Explanation The numbering system allows you to quickly identify the level in the

    work breakdown structure where the specific element is found. It also helps to locate

    the element in the WBS dictionary

    2. Answer D

    Explanation The term stakeholder encompasses all the other choices. In this case, it

    is the best answer since the WBS can be used (but does not need to be used) as acommunication tool for all stakeholders to see what is included in the project.

    3. Answer B

    Explanation The output of scope verification is customer acceptance of projectdeliverables. The other choices all happen during project planning, well before the

    time that scope verification takes place.

    4. Answer A

    Explanation Activity lists (choice B) may list the work package they relate to, butthey do not contain detailed description of work packages. The preliminary projectscope statement (choice C) may contain project scope, but does not describe the work

    a team member is assigned. The project scope management plan (choice D) describes

    how scope will be planned, managed and controlled. It does not include a descriptionof each work package. The WBS dictionary defines each element in the WBS.

    Therefore, descriptions of the work package are in the WBS dictionary.

    5. Answer B

    Explanation Did you say project initiating? I so, you did not read the question. It did

    not refer to the preliminary project scope statement, just the project scope statement.Tricky I Know. Do you hate me yet? And you were worried about long wordy

    questions!

    5

  • 7/29/2019 Chap 05 Scope-Management

    6/8

    Scope Management

    6. Answer D

    Explanation Not all questions will be difficult. The level of uncertainty in scope

    increases based on the scale of effort required to identify all the scope. For largerprojects it is more difficult to catch everything.

    7. Answer D

    Explanation If we were to rephrase the question, it is asking, Who creates the

    project management plan? The best answer is that project management plans are

    created by the project manager but require input from the team

    8. Answer A

    Explanation A WBS does not show dates or responsibility assignments (choices Band C). Those are included on the bar chart and possibly in the communications

    management plan. The business need (choice D) is shown in the project charter.Never thought that a WBS could be shown to the customer? Made you think! Of

    course it could be used for that purpose. In this situation, the product and project

    scope are fine tuned. It would save the project manager time to effectivelymanage progressive elaboration if the WBS were used to assist. The WBS helps

    ensure everyone understands the scope of the work.

    9. Answer B

    Explanation The team member is suggesting an enhancement that is outside the

    project charter. Scope management involves focusing on doing the work and onlythe work in the project management plan that meets the needs of the project

    charter. The project manager is performing scope management.

    10. Answer C

    Explanation it is product verification that occurs at the project (choice A). Scope

    verification is done during the monitoring and controlling process group, sochoices B and C cannot be correct. The description of scope verification defines it

    as being done at the end of each phase (the end of design, implementation)

    making choice C the best answer.

    11. Answer B

    Explanation do not jump into the problem without thinking. The customer only

    notified the project manager that they want to make a change. They did not

    describe the change. The project manager would need to understand the nature of

    the change and have time to evaluate the impact of the change before doing

    6

  • 7/29/2019 Chap 05 Scope-Management

    7/8

    Scope Management

    anything else. Of these choices, the first thing to do is to determine what is thechange (choice B) and then meet with the team (choice A), but only if their input

    is required. The project manager should not just say no (choice C) until he knows

    more about the possible change. He also should not go to management (choice D)without more information.

    12. Answer A

    Explanation Choice C is not generally true. The WBS is not only needed in order

    to have a contract, every project must have a WBS. Risks can be identified using

    various methods. Therefore, choice D is an incorrect statement and not the bestanswer. Choice A, preventing work from being forgotten (slipping through the

    cracks) is ONE of the reasons the tool is used.

    13. Answer B

    Explanation The WBS is an input to all of these choices. However, team buy-in(choice B) is a direct result of the WBS creation process, while the other choices

    use the WBS to assist in their completion. The best answer is B.

    14. Answer C

    Explanation The lowest level of the WBS is a work package, which can be

    performed by more than one person.

    15. Answer C

    Explanation The project scope statement (choice A) describes work on a high-

    level basis. Work packages need to be specific to enable team members to

    complete their work with less gold plating. The product scope (choice B) wouldnot tell the team members what work is assigned to them. The team should have

    the copy of the schedule (choice D) but a schedule will not show them what work

    is included in each of their work packages. Work packages are described in the

    WBS dictionary (choice C).NOTE: Do not think of the WBS dictionary as a dictionary of terms.

    16. Answer B

    Explanation this question can be tricky, especially if you have spent so much

    time studying that you have forgotten some good project management practices.A quick look at Ritas process charts in this book might draw you to conclude that

    the FIRST thing would be to start planning. Wouldnt it be smart to make sure

    what you have in before moving on? This is why choice B is the best choice.

    7

  • 7/29/2019 Chap 05 Scope-Management

    8/8

    Scope Management

    17. Answer A

    Explanation Scope verification deals with acceptance by the customer. Without

    this acceptance, you will not be able to over into the next project phase.

    18. Answer C

    Explanation Choices A, B and D are processes in the monitoring and controlling

    process group. This situation asks how to prevent the problem. This would havebeen done during the planning processes (choice C), as the project deliverables

    are defined in scope planning. Good planning reduces the likelihood of a similar

    situation by including the right people and spending adequate time in clarifying

    the project scope.

    19. Answer A

    Explanation The project scope management plan is not part of the scope

    baseline.

    20. Answer B

    Explanation Notice that there are many things that the project manager could dolisted in the choices. The question asks what the BEST thing to do NEXT is.

    Though they are great things to do, choices A and D are not next. Choice C would

    be done as part of integrated change control. Management of the change is notcomplete when scope control is completed. It is important to look at the impact of

    the change on other parts of the project such as time and cost. Therefore, choice B

    is the best thing to do next, probably followed by C and D and A.