Changes to IR6 dump protection elements B.Goddard, W.Weterings, C.Maglioni, R.Versaci,...

17
Changes to IR6 dump protection elements B.Goddard, W.Weterings, C.Maglioni, R.Versaci, T.Antonakakis, R.Schmidt, J.Borburgh, J.Blanco, plus many other colleagues

Transcript of Changes to IR6 dump protection elements B.Goddard, W.Weterings, C.Maglioni, R.Versaci,...

Changes to IR6 dump protection elements

B.Goddard, W.Weterings, C.Maglioni, R.Versaci, T.Antonakakis, R.Schmidt,

J.Borburgh, J.Blanco, plus many other colleagues

Contents

• TCDQ upgrade– Absorber material and length– Movement bellows– Controls

• Additional TCLA• Buttons in TCSG

TCDQ upgrade• Issue with robustness of present TCDQ design– Dynamic stresses exceed limit for damage at block corners– Graphite jaws, 1.8g/cc– Replace with graded Carbon Composite (1.4g/cc and 1.65

g/cc)

Absorber composition

1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12

1.8 g/cc 1.8 g/cc 10.8 g/cc.m

1.65 g/cc 1.4 g/cc 1.4 g/cc 1.65 g/cc 1.65 g/cc 13.9 g/cc.m

• Lower density and higher yield stress material – should be below damage limit for beyond ultimate beams– FLUKA and stress analyses ongoing to derive limits

• Total amount of material seen by beam increases from 10.8 kg/cm2 to 13.9 kg/cm2– Should be better for asynch dump protection

Beam

Absorber length 6m -> 9m

Location of extra module

• More difficult upstream, due to dump line interference, but would like to maintain location of TCSG and drift to Q4, so will extend upstream.

Layout

• Relocation of interlock BPMs by about 3m• No impact on functionality

TCDQ

BPMSA

TCSG

Schedule

• Install during LS1

Another benefit?

• Will have 9m of CC next to beam at location with largest H beta function– Could help reduce damage elsewhere in case of

major failure– Being investigated by J.Blanco & R.Schmidt

Improve present bellows (±20 mm)

• Presently large mechanical stress to displace• Distortion of RF fingers (away from beam!)

Will make double bellows system -> TE/VSC?

Controls

• Don’t expect any change in movement precision with 9m long absorber (10.4m)

• Are investigating an upgrade of controls to use collimation stepping motor system and low-level (although some other issues have been solved with existing DC motors)– Needs mechanical changes, and there is concern

about precision attainable in open-loop.

Additional TCLA?

• Space reserved in layout for TCLA, just before TCDQM

Reduction of heat load on Q4 with MQY

Factor 2 improvement

FLUKA studies of asynch dump

R.Versaci

Justification for TCLA

• “Not needed for beam cleaning” – Ralph• Two remaining justifications

– Reduce scale of quench if asynch dump• FLUKA studies in progress

– Help contain damage if “beyond design” failure• Energy tracking, retrigger failure

• Decision still to take – when is deadline for Coll project?– Would be good to do all IR6 work together in LS1 (TCSG

with buttons, new TCDQ plus motorisation, TCLA)

Buttons in TCSGs

• Requested by Ralph• Can only support this– Will need to investigate ‘servo’ of TCDQ position

with TCSG, beyond certain offset, if TCSGs are automatically adjusted

Conclusions• Some non-negligible upgrades for IR6 dump

protection– TCDQ upgrade for robustness (also adds more

material close to beam)– TCDQ controls – to be decided formally– New improved TCDQ bellows– TCSG with buttons– Additional TCLA – to be decided after FLUKA

studies