ch09 Finance

download ch09 Finance

of 46

Transcript of ch09 Finance

  • 8/7/2019 ch09 Finance

    1/46

    0

    Net Present Value and OtherInvestment Criteria

    Chapter 9

  • 8/7/2019 ch09 Finance

    2/46

    MBA 819 1

    Key Concepts and SkillsBe able to compute payback and discountedpayback and understand their shortcomings

    Understand accounting rates of return andtheir shortcomingsBe able to compute the internal rate of returnand understand its strengths and weaknessesBe able to compute the net present value andunderstand why it is the best decisioncriterion

  • 8/7/2019 ch09 Finance

    3/46

    MBA 819 2

    Chapter OutlineNet Present Value

    The Payback RuleThe Discounted PaybackThe A verage A ccounting Return

    The Internal Rate of ReturnThe Profitability IndexThe Practice of Capital Budgeting

  • 8/7/2019 ch09 Finance

    4/46

    MBA 819 3

    Good Decision CriteriaWe need to ask ourselves the followingquestions when evaluating decisioncriteria

    Does the decision rule adjust for the timevalue of money?

    Does the decision rule adjust for risk?Does the decision rule provide informationon whether we are creating value for thefirm?

  • 8/7/2019 ch09 Finance

    5/46

    MBA 819 4

    Project Example InformationYou are looking at a new project and youhave estimated the following cash flows:

    Year 0: CF = -165,000Year 1: CF = 63,120; NI = 13,620Year 2: CF = 70,800; NI = 3,300Year 3: CF = 91,080; NI = 29,100

    A verage Book Value = 82,500Your required return for assets of this risk is12%.

  • 8/7/2019 ch09 Finance

    6/46

    MBA 819 5

    Net Present ValueThe difference between the market value of aproject and its cost

    Value A dditivity PrincipleHow much value is created from undertakingan investment?

    The first step is to estimate the expected future

    cash flows.The second step is to estimate the required returnfor projects of this risk level.The third step is to find the present value of thecash flows and subtract the initial investment.

  • 8/7/2019 ch09 Finance

    7/46

    MBA 819 6

    NPV Decision RuleIf the NPV is positive, accept the project A positive NPV means that the project isexpected to add value to the firm and willtherefore increase the wealth of the owners.Since our goal is to increase owner wealth,NPV is a direct measure of how well thisproject will meet our goal.However, you may accept a project with annegative NPV for strategic reasons.

  • 8/7/2019 ch09 Finance

    8/46

    MBA 819 7

    Computing NPV for the Project Using the formulas:

    NPV = 63,120/(1.12) + 70,800/(1.12) 2 +91,080/(1.12) 3 165,000 = 12,627.41

    Using the calculator:CF0 = -165,000; CF 1 = 63,120; CF 2 =70,800; CF 3 = 91,080; I/YR = 12; thenyellow NPV = 12,627.41

    D o we accept or reject the project?

  • 8/7/2019 ch09 Finance

    9/46

    MBA 819 8

    Decision Criteria Test - NPVDoes the NPV rule account for the timevalue of money?

    A ssumes reinvestment at the required rate of return

    Does the NPV rule account for the risk of the cash flows?

    Does the NPV rule provide an indicationabout the increase in value?Should we consider the NPV rule for ourprimary decision criteria?

  • 8/7/2019 ch09 Finance

    10/46

    MBA 819 9

    Calculating NPVs with a

    Spreadsheet Spreadsheets are an excellent way tocompute NPVs, especially when you have to

    compute the cash flows as well.Using the NPV functionThe first component is the required return enteredas a decimalThe second component is the range of cash flowsbeginning with year 1Subtract the initial investment after computing theNPV

  • 8/7/2019 ch09 Finance

    11/46

    MBA 819 10

    Payback PeriodHow long does it take to get the initial cost back in a nominal sense?Computation

    Estimate the cash flowsSubtract the future cash flows from the initial cost until the initial investment has been recovered

    Decision Rule A ccept if the payback period is less than some preset limit

  • 8/7/2019 ch09 Finance

    12/46

    MBA 819 11

    Computing Payback For The

    Project A ssume we will accept the project if it paysback within two years.

    Year 1: 165,000 63,120 = 101,880 still torecoverYear 2: 101,880 70,800 = 31,080 still to recoverYear 3: 31,080 91,080 = -60,000 project pays

    back in year 3A nswer is 2 + .34 years or 2.34 years (assumingcash flows are continuous during the year).

    D o we accept or reject the project?

  • 8/7/2019 ch09 Finance

    13/46

    MBA 819 12

    Decision Criteria Test -

    PaybackDoes the payback rule account for the

    time value of money?Does the payback rule account for therisk of the cash flows?Does the payback rule provide anindication about the increase in value?Should we consider the payback rule forour primary decision criteria?

  • 8/7/2019 ch09 Finance

    14/46

    MBA 819 13

    A dvantages and Disadvantages

    of PaybackA dvantages

    Easy to understandA djusts foruncertainty of latercash flowsB iased towardsliquidity

    DisadvantagesIgnores the time valueof moneyRequires an arbitrarycutoff point Ignores cash flowsbeyond the cutoff dateB

    iased against long-term projects, such asresearch anddevelopment, and newprojects

  • 8/7/2019 ch09 Finance

    15/46

    MBA 819 14

    Discounted Payback PeriodCompute the present value of each cashflow and then determine how long it takes to payback on a discounted basisCompare to a specified required periodDecision Rule - A ccept the project if it pays back on a discounted basis within the specified time

  • 8/7/2019 ch09 Finance

    16/46

    MBA 819 15

    Computing Discounted Payback

    for the Project A ssume we will accept the project if it paysback on a discounted basis in 2 years.

    Compute the PV for each cash flow anddetermine the payback period usingdiscounted cash flows

    Year 1: 165,000 63,120/1.12 1 = 108,643

    Year 2: 108,643

    70,800/1.122

    = 52,202Year 3: 52,202 91,080/1.12 3 = -12,627 project pays back in year 3The answer is 2.57 years.

    D o we accept or reject the project?

  • 8/7/2019 ch09 Finance

    17/46

    MBA 819 16

    Decision Criteria Test

    Discounted PaybackDoes the discounted payback rule account forthe time value of money?Does the discounted payback rule account forthe risk of the cash flows?Does the discounted payback rule provide an

    indication about the increase in value?Should we consider the discounted paybackrule for our primary decision criteria?

  • 8/7/2019 ch09 Finance

    18/46

    MBA 819 17

    A dvantages and Disadvantages of Discounted Payback

    A dvantagesIncludes time valueof moneyEasy to understandDoes not accept negative estimatedNPV investmentsB iased towardsliquidity

    DisadvantagesM ay reject positive

    NPV investmentsRequires an arbitrarycutoff point Ignores cash flowsbeyond the cutoff point B iased against long-term projects, suchas R&D and newproducts

  • 8/7/2019 ch09 Finance

    19/46

    MBA 819 18

    A verage A ccounting ReturnThere are many different definitions foraverage accounting return

    The one used in the book is:A verage net income / average book valueNote that the average book value depends on howthe asset is depreciated.

    Need to have a target cutoff rateDecision Rule: Acc ept the proje c t if theAAR is greater than a preset rate.

  • 8/7/2019 ch09 Finance

    20/46

    MBA 819 19

    Computing AA R For The

    Project A ssume we require an average

    accounting return of 25%A verage Net Income:(13,620 + 3,300 + 29,100) / 3 = 15,340

    AA R = 15,340 / 82,500 = .186 =18.6%

    D o we accept or reject the project?

  • 8/7/2019 ch09 Finance

    21/46

    MBA 819 20

    Decision Criteria Test - AA RDoes the AA R rule account for the timevalue of money?Does the AA R rule account for the riskof the cash flows?Does the AA R rule provide an indication

    about the increase in value?Should we consider the AA R rule for ourprimary decision criteria?

  • 8/7/2019 ch09 Finance

    22/46

    MBA 819 21

    A dvantages and

    Disadvantages of AA RA dvantages

    Easy to calculateNeeded informationwill usually beavailable

    DisadvantagesNot a true rate of return; time value of money is ignoredUses an arbitrarybenchmark cutoff rateBased on accounting

    net income and bookvalues, not cash flowsand market valuesOvervalues longerprojects

  • 8/7/2019 ch09 Finance

    23/46

    MBA 819 22

    Internal Rate of Return (IRR)This is the most important alternative toNPV (also it was the first DCF methodused)It is often used in practice and isintuitively appealing

    It is based entirely on the estimatedcash flows and is independent of interest rates found elsewhereA ssumes reinvestment at the IRR

  • 8/7/2019 ch09 Finance

    24/46

    MBA 819 23

    IRR Definition and Decision

    RuleDefinition: IRR is the return that makesthe NPV = 0Decision Rule: A ccept the project if the I RR is greater than therequired return

  • 8/7/2019 ch09 Finance

    25/46

    MBA 819 24

    Computing IRR For The

    Project If you did not have a financial calculator,then this calculation becomes a trial anderror processCalculator

    Enter the cash flows as you did with NPV

    Press yellow IRR/YRIRR = 16.13% > 12% required returnD o we accept or reject the project?

  • 8/7/2019 ch09 Finance

    26/46

    MBA 819 25

    NPV Profile For The Project

    -20,000

    -10,000

    0

    10,000

    20,000

    30,000

    40,000

    50,000

    60,000

    70,000

    0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22

    Discount Rate

    NPV

    IRR = 16.13%

  • 8/7/2019 ch09 Finance

    27/46

    MBA 819 26

    Decision Criteria Test - IRRDoes the IRR rule account for the timevalue of money?Does the IRR rule account for the riskof the cash flows?Does the IRR rule provide an indication

    about the increase in value?Should we consider the IRR rule for ourprimary decision criteria?

  • 8/7/2019 ch09 Finance

    28/46

    MBA 819 27

    A dvantages of IRRKnowing a return is intuitively appealing

    It is a simple way to communicate thevalue of a project to someone whodoesn t know all the estimation detailsIf the IRR is high enough, you may not need to estimate a required return,which is often a difficult task

  • 8/7/2019 ch09 Finance

    29/46

    MBA 819 28

    Summary of Decisions For The

    Project Summary

    Net Present ValueA

    ccept Payback Period R eject

    Discounted Payback Period R eject

    A verage A ccounting Return R eject

    Internal Rate of Return A ccept

  • 8/7/2019 ch09 Finance

    30/46

    MBA 819 29

    Calculating IRRs With A

    Spreadsheet You start with the cash flows the same asyou did for the NPVYou use the IRR function

    You first enter your range of cash flows, beginningwith the initial cash flowYou can enter a guess, but it is not necessaryThe default format is a whole percent you willnormally want to increase the decimal places toone or two places.

  • 8/7/2019 ch09 Finance

    31/46

    MBA 819 30

    NPV Vs. IRRNPV and IRR will generally give us thesame decision

    ExceptionsNon-conventional cash flows cash flowsigns change more than onceM utually exclusive projects

    Initial investments are substantially different (Size of outflow)Timing of cash flows is substantially different

  • 8/7/2019 ch09 Finance

    32/46

    MBA 819 31

    IRR and Non-conventional

    Cash FlowsWhen the cash flows change sign more thanonce, there is more than one IRR

    When you solve for IRR you are solving forthe root of an equation and when you crossthe x-axis more than once, there will be morethan one return that solves the equation

    If you have more than one IRR, which one doyou use to make your decision?Your financial calculator typically will report not found.

  • 8/7/2019 ch09 Finance

    33/46

    MBA 819 32

    A n Example Non-conventional

    Cash FlowsSuppose an investment will cost $90,000 initially and will generate the

    following cash flows:Year 1: 132,000Year 2: 100,000Year 3: -150,000

    The required return is 15%.Should we accept or reject the project?

  • 8/7/2019 ch09 Finance

    34/46

    MBA 819 33

    NPV Profile

    ($10 ,000 .00)

    ($8 ,000 .00)

    ($6 ,000 .00)

    ($4 ,000 .00)

    ($2 ,000 .00)

    $0 .00

    $2 ,000 .00

    $4 ,000 .00

    0 0 .05 0 .1 0 .15 0 .2 0 .25 0 . 0 . 5 0 .4 0 .45 0 .5 0 .55

    D isc t te

    I = 10 .11 % d 42 .66 %

  • 8/7/2019 ch09 Finance

    35/46

    MBA 819 34

    Summary of Decision RulesThe NPV is positive at a required returnof 15%, so you should A ccept

    If you use the HP 10 B II financialcalculator, you would get an IRR of not found.

    You need to recognize that there arenon-conventional cash flows and look at the NPV profileUse the Net Present Value for decision

  • 8/7/2019 ch09 Finance

    36/46

    MBA 819 35

    IRR and M utually Exclusive

    ProjectsM utually exclusive projects

    If you choose one, you can t choose the other

    Example: You can choose to purchase a ToyotaCamry or a Ford Taurus, but not both

    Intuitively you would use the followingdecision rules:

    NPV choose the project with the higher NPVIRR choose the project with the higher IRR

  • 8/7/2019 ch09 Finance

    37/46

    MBA 819 36

    Example With M utually ExclusiveProjects

    Period Project A

    Project B

    0 -500 -400

    1 325 325

    2 325 200

    IRR 19.43% 22.17%

    NPV 64.05 60.74

    The required return

    for both projects is10%.

    Which projectshould you acceptand why?

  • 8/7/2019 ch09 Finance

    38/46

    MBA 819 37

    NPV Profiles

    ($40 .00)

    ($20 .00)$0 .00

    $20 .00

    $40 .00

    $60 .00

    $80 .00

    $100 .00

    $120 .00

    $140 .00

    $160 .00

    0 0 .05 0 .1 0 .15 0 .2 0 .25 0 .

    D isc t te

    AB

    I f r A = 19 .43 %

    I f r B = 22 .17 %

    Cr ss ver i t = 11 .8%

  • 8/7/2019 ch09 Finance

    39/46

    MBA 819 38

    Conflicts Between NPV and

    IRRNPV directly measures the increase in valueto the firm (Value A dditivity)

    Whenever there is a conflict between NPVand another decision rule, you shouldalways use NPVIRR is unreliable in the following situations

    Non-conventional cash flowsM utually exclusive projects

  • 8/7/2019 ch09 Finance

    40/46

    MBA 819 39

    Profitability IndexM easures the benefit per unit cost, based onthe time value of money ( Bang for theB

    uck

    )A profitability index of 1.1 implies that forevery $1 of investment, we create anadditional $0.10 in value

    This measure can be very useful in situationswhere we have limited capitalThis technique is used in capital rationing.

  • 8/7/2019 ch09 Finance

    41/46

    MBA 819 40

    A dvantages and Disadvantages of Profitability Index

    A dvantagesClosely related to NPV,generally leading toidentical decisionsEasy to understand andcommunicate

    M ay be useful whenavailable investment funds are limited

    DisadvantagesM ay lead to incorrect decisions incomparisons of mutually exclusiveinvestments

  • 8/7/2019 ch09 Finance

    42/46

  • 8/7/2019 ch09 Finance

    43/46

    MBA 819 42

    Summary Discounted Cash

    Flow CriteriaNet present value

    Difference between market value and cost Take the project if the NPV is positiveHas no serious problemsPreferred decision criterion

    Internal rate of returnDiscount rate that makes NPV = 0Take the project if the IRR is greater than required returnSame decision as NPV with conventional cash flowsIRR is unreliable with non-conventional cash flows or mutuallyexclusive projects

    Profitability IndexBenefit-cost ratioTake investment if PI > 1Cannot be used to rank mutually exclusive projectsM ay be used to rank projects in the presence of capital rationing

  • 8/7/2019 ch09 Finance

    44/46

    MBA 819 43

    Summary

    Payback CriteriaPayback period

    Length of time until initial investment is recoveredTake the project if it pays back in some specifiedperiodDoesn t account for time value of money andthere is an arbitrary cutoff period

    Discounted payback period

    Length of time until initial investment is recoveredon a discounted basisTake the project if it pays back in some specifiedperiodThere is an arbitrary cutoff period

  • 8/7/2019 ch09 Finance

    45/46

    MBA 819 44

    Summary A ccounting

    CriterionA verage A ccounting ReturnM easure of accounting profit relative to

    book valueSimilar to return on assets measureTake the investment if the AA R exceedssome specified return levelSerious problems and should not beused

    But it is used in industry, and it may

    determine compensation of the manager.

  • 8/7/2019 ch09 Finance

    46/46

    MBA 819 45

    ConclusionCapital Investment Decision Techniques

    Net Present ValuePayback PeriodDiscounted PaybackInternal Rate of ReturnProfitability IndexA ccounting Rate of Return

    Industry usage