Ch08 Crashing

23
8-1 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall Project Management Chapter 8 (Crashing)

description

crashingg

Transcript of Ch08 Crashing

No Slide TitleProject Management
Project Crashing
Basic Concept
In last lecture, we studied on how to use CPM and PERT to identify critical path for a project problem
Now, the question is:
If so, how!
Solution!
Yes, the project duration can be reduced by assigning more resources to project activities. But, doing this would somehow increase our project cost!
How do we strike a balance?
Project crashing is a method for shortening project duration by reducing one or more critical activities to a time less than normal activity time.
8-*
Here, we adopt the “Trade-off” concept
We attempt to “crash” some “critical” events by allocating more resources to them, so that the time of one or more critical activities is reduced to a time that is less than the normal activity time.
How to do that:
Question: What criteria should it be based on when deciding to crashing critical times?
8-*
How? Path: 1-2-3 = 5+6=11 weeks
Path: 1-3 = 5 weeks
1
3
2
8-*
Path 1-2-3 = 1 + 3 = 4
Path 1-3 = 0
8-*
If we used all 4 days, then path 1-2-3 has
(5-1) + (6-3) = 7 completion weeks
Now, we need to check if the completion time for path 1-3 has lesser than 7 weeks (why?)
Now, path 1-3 has (5-0) = 5 weeks
Since path 1-3 still shorter than 7 weeks, we used up all 4 crashed weeks
Question: What if path 1-3 has, say 8 weeks completion time?
4(0)
3(0)
8-*
Because path 1-2-3 will not be critical path anymore as
path 1-3 would now has longest hour to finish
Rule: When a path is a critical path, it will not stay as a critical path
So, we can only reduce the path 1-2-3 completion time to the same time
as path 1-3. (HOW?)
6(3)
8(0)
Solution:
We can only reduce total time for path 1-2-3 = path 1-3,
that is 8 weeks
If the cost for path 1-2 and path 2-3 is the same then
We can random pick them to crash so that its completion
Time is 8 weeks
8-*
Figure 8.6
House Showing Concurrent Activities
*
Project Crashing and Time-Cost Trade-Off
Example Problem (1 of 5)
Figure 8.19 The Project Network for Building a House
*
Table 8.4
*
Figure 8.20
Crash cost & crash time have a linear relationship:
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
*
General Relationship of Time and Cost (2 of 2)
Figure 8.23
*
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Figure 8.21 Network with Normal Activity Times and Weekly Crashing Costs
Project Crashing and Time-Cost Trade-Off
Example Problem (4 of 5)
*
Figure 8.22
Project Crashing and Time-Cost Trade-Off
Example Problem (5 of 5)
*
Exhibit 8.16
Project Crashing with QM for Windows
*
Figure 8.6
House Showing Concurrent Activities
*
Example Problem Formulation and Data (1 of 2)
Figure 8.24
*
subject to:
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
*
Minimize Z = xi
xi, xj 0
tij = time of activity i j
The objective is to minimize the project duration (critical path time).
The CPM/PERT Network
i
*
subject to:
y23 3 y23 + x3 - x2 8 xi, yij ≥ 0
y24 1 y24 + x4 - x2 4
y34 0 y34 + x4 - x3 0
y45 3 y45 + x5 - x4 4
y46 3 y46 + x6 - x4 12
y56 3 y56 + x6 - x5 4
y67 1 x67 + x7 - x6 4
xi = earliest event time of node i
xj = earliest event time of node j
yij = amount of time by which activity i j is crashed
Project Crashing with Linear Programming
Example Problem – Model Formulation
Objective is to minimize the cost of crashing
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall
*