Ch - 7 Project Risk Managemtn

download Ch - 7 Project Risk Managemtn

of 20

Transcript of Ch - 7 Project Risk Managemtn

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    1/20

    Project Risk Management

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    2/20

    Introduction to risk

    Types of Risks

    Risk Management Risk management plans

    Role of Risk Management in Project Management

    Steps in Risk Management

    Risk Identification Risk Analysis

    Reducing Risks

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    3/20

    What is Risk

    Risk is the potential that a chosen action or activity will lead to a loss.

    It can be described both qualitatively and quantitatively.

    Qualitatively, It is proportional to the expected losses that may be

    induced by an event and to the probability of the event. Greater loss and greater event probability culminate in a greater overall

    risk.

    Quantitatively, there are various formal methods that can be used toevaluate or to "measure" risk. Some of the quantitative definitions of

    risk can be related to the statistics theory and naturally lead tostatistical estimates, while others are more subjective.

    For example, in many cases, a decisive factor is human decision making

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    4/20

    Internal factors: Risks to the project may involve labour strike, change in management,

    change in consumer preferences, the financial solvency of the company, theability of the company to have the required equipment and other resourcesin hand in time to support the project.

    Personnel issues such as sickness or unanticipated termination of a keyteam member also can be considered as internal risks to the project.

    External factors: External risks are those risks that cannot be controlled by the project team

    and its host organisation. They are usually more difficult to foresee and control. It include key vendor going bankrupt, level of economic activities

    recession or boom, inflation, political development, change in credit

    policies, and related events. These factors may have a direct impact on project's effectiveness. Risk caused by external factors also affects the return on investment. Such

    risks are non diversifiable

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    5/20

    Types of risks

    Macro risk levels(1) Systematic risk:

    A systematic risk cannot be controlled or foreseen in any manner,therefore it is almost impossible to predict or protect the organisation ora project against this type of risk.

    It can affect the entire market.

    For ex. the stock market is in bear hug or in bull grip.

    The changes in the economic, political and the sociological conditionsaffect the security market.

    These are the factors that cannot be controlled by organisation andinvestor.

    The smartest way to tackle this risk is to simply recognise that this type ofrisk will occur and plan for your project to be affected by it.

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    6/20

    (2) Unsystematic risk: It is sometimes referred to as "specific risk". It is unique and peculiar to

    a firm or an industry and can usually be eliminated through a process

    called diversification. Unsystematic risk stems from managerial inefficiency, technological

    change in the production process, availability of raw material, changesin the consumer preference, and labour problems.

    For example, the changes in the consumer preference affect the

    consumer products like TV, washing machines, refrigerators, etc morethan that of consumer product industry.

    The nature and mode of raising finance and paying back the loansinvolve a risk element.

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    7/20

    (3) Business risk:

    It is that portion of unsystematic risk caused by the operating environmentof the business which arises from the inability of a firm to maintain itscompetitive edge and the growth or stability of earnings.

    Variation that occurs in the operating environment is reflected on the

    operating income and expected dividends. The variation in expectedoperating income indicates the business risk.

    (4) Financial risk:

    It refers to the variability of the income to the equity capital due to the

    debt capital. Financial risk in a company is associated with the capital structure of the

    company.

    Capital structure of the company consists of equity funds and borrowedfunds.

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    8/20

    Micro level risk

    (1) Project risk: It is related to the uncertain events or situations that have the potential

    to adversely affect a planned project, usually in terms of cost, schedule,and/or product quality.

    Project risk is a function of two components: likelihood and

    consequence.(2) Country risk:

    It is referred to as political risk, is an important risk for investors today.

    With more investors investing internationally, both directly andindirectly, the political and economic stability and viability of acountry's economy needs to be considered.

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    9/20

    Factors Affecting Country Risk

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    10/20

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    11/20

    (3)Market risk The price fluctuations or volatility increases and decreases in the day-today

    market. It is caused by the alternating forces of bull and bear market.

    (4) Interest rate risk It is simply the risk to which an institution is exposed because future interest rates

    are uncertain. The assets and liabilities of a financial institution have different maturity and

    liquidity. Financial institutions create assets and at the same time create liabilities. These

    loans are invested by the financial institutions at a certain rate of interest andsimilarly interest cost has to be paid to the lenders of deposit.

    The mismatches of interest rates of the assets and liabilities expose to interest raterisk.

    For example: An Indian bank borrows Rs. 200 crore from the market for 4 years @10% (Floating p.a.) and creates a loan asset of the same amount for 4 Year period@ 13% (Fixed p.a.).

    If, there is a an upward trend of interest rate after 2 years and the rate of interestgoes up to 15% thenInterest Loss = Crores = 200 (15% 13%)

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    12/20

    (5) Purchasing power risk Variations in the returns are caused also by the loss of purchasing

    power of currency. Inflation is the reason behind the loss of purchasing power. Purchasing power risk is the probable loss in purchasing power of the

    returns to be received.

    The rise in price penalises the returns to the investor, and everypotential rise in price is a risk to the investor.(6) Liquidity risks It is that part of an assets total inconsistency of returns which

    consequences from price discounts given or sales commissions paid inorder to sell the asset without delay.

    It is a condition wherein it may not be possible to sell the asset.

    Any asset that can be bought and sold promptly is said to be liquid. Failure to realise with minimum discount to its value of an asset is

    called liquidity risk.

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    13/20

    Risk Management

    It is a field of management that deals with the possibility that variousfuture events may cause harm or threat to the organisation.

    It comprises of strategies and techniques to recognise and confront anythreat faced by a business in fulfilling its mission.

    Risk management information systems/services (RMIS) are often used

    by enterprises to provide expert advice and cost-effective informationmanagement solutions.

    It deals with key processes such as:

    Risk identification and assessment

    Risk quantification

    Risk control

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    14/20

    Risk management plans

    Creation Select appropriate controls & counter measures to quantify each risk.

    Risk mitigation must also be approved by the suitable level of management asper the level/domain of risk.

    It must suggest valid and effectual security controls for managing the risks. Forex, If there is high risk of computer viruses then it could be mitigated by

    installing an antivirus software on the system. It consists of a schedule for control operation and people accountable for those

    actions.

    It must clearly state the decisions about how each of the identified risks shouldbe dealt with.

    Implementation

    Take measures for mitigating the effect of the risks. Purchase insurance policies for all those risks that could be insured.

    Try to avoid and minimise all risks without sacrificing the entity's goals. Therisks left after all these are retained.

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    15/20

    Review and evaluation of the plan

    Initial risk management plans may not be perfect. So actual risk controlmeasures are based on a number of factors & hence there is a high probabilitythat management might change the plan.

    Risk results and management plans must be periodically updated.

    It is done basically for two underlying reasons:

    To find out if the previously selected security measures are still valid and

    effective, and

    To determine the possible risk level changes in the business atmosphere.

    For ex, Market risks are an example of rapidly changing business

    environment.

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    16/20

    Risk Identification

    It is done at each stage of a project life cycle.

    During risk identification, risks are identified and categorised. It must be done by the concerned people such as IT people, marketing managers or top level

    management.Business risks: It is related to business activity. For example, if a key team member becomes unavailable or sick then

    it may delay the project and the organisation might not be able to complete the project in the givenfinancial year.

    Generic risks: Generic risks are those risks that are common to all projects. For example, system failure or flaw may

    cause the project to be delayed. Risks must be defined in two parts. The first part must define the cause of the risk and the other must

    define the impact of the risk. For example, a risk may be defined as "The supplier not meetingdeadline will mean that budget will exceed".

    For comprehensive identification of risks, we may adopt risk matrix as suggested by Well-Stam et al. Vertical axis of matrix represents various phases of the project and horizontal axis represents various

    points of view or perspective. For each class proven risk identification techniques are used which includes:

    Assumption analysis: Assumptions made in planning stage of the project are taken as true, real, or certain. A closure

    scrutiny of these may reveal possible risks.Brain storming: Brain storming is a useful tool to generate the possible risk events in quick time. It is performed by a

    cross-function team following set procedures (see chapter 8 for details)

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    17/20

    Risk identification techniques :

    Assumption analysis: Assumptions made in planning stage of the project are taken as true, real, or certain. A closure

    scrutiny of these may reveal possible risks.

    Brain storming: Brain storming is a useful tool to generate the possible risk events in quick time. It is performed

    by a cross-function team following set procedures.Checklist: The checklist is developed based on past experience. It provides a useful guide in listing

    foreseeable risks.Delphi:

    Delphi study is carried out with the help of a group of experts. Since the experts are people whohave a deep insight into the system functioning, it is possible to gather useful information in thisway.

    Interview: Interview may be held with knowledgeable people to identify or to gain more in-depth

    knowledge of certain risks or to create a list of control measures.Observations: It is possible to visualise the risks by directly examining/ observing the current process.Previous documentation: Past experiences recorded in company files, reports, third party reports, or news paper reports

    on electronic or paper format provide help in listing risks.Modelling: Use of risk tool kits or simulation by computer or other aids may uncover risks. There are a number of diagrams like cause and effect diagram, fault tree, event tree, influence

    diagram, etc to capture risks

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    18/20

    Reducing Risks

    Risk avoidance: It includes not performing an activity that could carry risk. For example, not

    buying a property or business to avoid the liability attached to it or not flyingan airplane to avoid the risk of a crash.

    It is very easy but also means losing out on the potential gain that performing

    the activities with risk may have allowed. For example, not entering a business to avoid the risk of loss also ends the

    possibility of earning profits.

    Risk reduction:

    It involves methods that reduce the severity of loss from occurring.

    For example, use of sprinklers to put out a fire to reduce the risk of loss by fire.

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    19/20

    Risk retention: It involves accepting the loss as when it arises.

    For ex. self insurance

    It is a feasible strategy for small risks where the cost of insuring against the riskis higher than the total losses sustained.

    Risks which are not avoided or transferred are retained by default.

    For ex. during a war, most property was not insured against war, so the losscaused by war is retained by the insured.

    Risk transfer:

    It means causing another party to accept the risk, usually by means of contractor by hedging like insurance.

    In other cases, it may involve contract language that transfers a risk to the otherparty without the payment of an insurance premium.

    The liability among construction or other contractors is transferred this way.

    Taking offsetting positions in derivatives is normally how firms use hedging tofinancially manage risk.

  • 8/12/2019 Ch - 7 Project Risk Managemtn

    20/20

    THE END