CESR Test Facility Plans Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and...
-
Upload
kevin-ramsey -
Category
Documents
-
view
215 -
download
0
Transcript of CESR Test Facility Plans Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and...
CESR Test Facility PlansMark Palmer
Cornell Laboratory for
Accelerator-Based Sciences and Education
October 6, 2006 LEPP Journal Club 2
Outline
• The International Linear Collider– ILC Accelerator Research at Cornell– Key Issues for the ILC Damping Rings
• CESR as a Vehicle for ILCDR Research - CesrTF– Concept and Goals– Ring Modifications– Parameters and Experimental Reach– The R&D Program
• Schedule• Collaborators and Projects
– Local Participants
• Conclusion
October 6, 2006 LEPP Journal Club 3
The International Linear Collider
• Key Milestones– Costed Reference Design by the end of 2006– Technical Design by the end of 2009
• An R&D Program To…– Demonstrate the baseline design– Optimize cost and perfomance– Develop improvements to the baseline
• Ready in 2010 to propose construction
See opening VLCW06 talk by B. Barishhttp://vlcw06.triumf.ca/
Baseline Layout as of July 2006
October 6, 2006 LEPP Journal Club 4
ILC Accelerator R&D At Cornell
• Ring to Final Focus - Low Emittance Transport and BBA• Helical Undulator for the Positron Source• Superconducting RF
– Facilities: BCP, EP, HPR, Cavity Test– Re-entrant cavity development– Basic R&D on Niobium Cavities– 650 MHz RF for Damping Rings
• Damping Rings– Simulation– Kickers– Wigglers– Instrumentation– CesrTF
Simulation Tools Based On BMADD. Sagan
http://www.lepp.cornell.edu/~dcs/bmad
Simulation Tools Based On BMADD. Sagan
http://www.lepp.cornell.edu/~dcs/bmad
October 6, 2006 LEPP Journal Club 5
ILC@Cornell: RTML and Main Linac
• Low Emittance Transport – Ring-to-Main Linac
(RTML)
– Bunch Compressor
– Spin Rotator
– Main Linac
• J. Smith BMAD/ILCv curve shows error bars
Simulation Benchmarking
Emittance Growth in Main Linac
October 6, 2006 LEPP Journal Club 6
Preliminary polarization analysis consistent with expectations
Preliminary polarization analysis consistent with expectations
Helical Undulator R&D
• Built at LEPP • Length = 1 m• K = 0.17 (undulator param)• = 2.5 mm• Aperture = 0.88 mm• 0.76 T• 2300 A• 12 s
• Built at LEPP • Length = 1 m• K = 0.17 (undulator param)• = 2.5 mm• Aperture = 0.88 mm• 0.76 T• 2300 A• 12 s
E166 Undulator
• Length ~ 200 m• K = 0.7• = 10 mm• Aperture = 8 mm
• Length ~ 200 m• K = 0.7• = 10 mm• Aperture = 8 mm
• Build 0.3 m unit• Optimize field quality• Evaluate effects on emittance and polarization of e- beam• Design, assemble and test• Field measurement in vacuumCollaboration with Daresbury
• Build 0.3 m unit• Optimize field quality• Evaluate effects on emittance and polarization of e- beam• Design, assemble and test• Field measurement in vacuumCollaboration with Daresbury
ILC Undulator
ILC Prototype
A. Mikhailichenko
October 6, 2006 LEPP Journal Club 7
SRF: Main Linac 9-cell Cavities
AssemblyComplete
VerticalTest
October 6, 2006 LEPP Journal Club 8
Re-entrant Cavity Collaboration with KEK
• Re-entrant Shape Single Cell Cavity Reached 47 MV/m in Nov 04
• 2nd Re-entrant Cavity (built at Cornell) Treated and Tested at KEK
Reached 50+ MV/m at KEK (Sept 05)
V. Shemelin
October 6, 2006 LEPP Journal Club 9
The ILC Damping Rings
Beam energy 5 GeV
Circumference 6695 m
RF frequency 650 MHz
Harmonic number 14516
Injected (normalised) positron emittance
0.01 m
Extracted (normalised) emittance
8 μm × 20 nm
Extracted energy spread <0.15%
Average current 400 mA
Maximum particles per bunch 2×1010
Bunch length (rms) 6 mm
Minimum bunch separation 3.08 ns
2 pm-rad geometric emittance
OCS v6TME Lattice
Circled items play a key role in our local R&D plans…
250 km main linac bunch trainis “folded” into the DRs
October 6, 2006 LEPP Journal Club 10
ILCDR R&D Issues
• Some High and Very High Priority R&D Items– Electron Cloud
• Growth in bend magnets and wigglers• Suppression in bend magnets and wigglers• Instability thresholds and emittance growth in the positron damping ring• This issue has become more significant due to the decision to employ a single positron damping
ring– Ion Effects
• Instability thresholds and emittance growth in the electron damping ring– Ultra-low Emittance Operation
• Alignment and Survey• Beam-based Alignment• Optics Correction• Measurement and Tuning
– Fast (single bunch) high voltage kickers for injection/extraction• >100 kV-m of stripline kick required• <6 ns wide pulse into a 0.3 m long stripline so as not to perturb neighboring bunches in the
damping ring– Development of 650 MHz SRF System
• We are in a position to make significant contributions to R&D in all of these areas at Cornell
October 6, 2006 LEPP Journal Club 11
Highlight One Issue
• Electron Cloud– What is it?
• Primary electrons can be produced as photoelectrons from synchrotron radiation, by gas ionization, and by lost beam particles striking the vacuum chamber wall
• Secondary electrons are produced when free electrons are kicked by the beam and strike the vacuum chamber walls
• Large amplification factors are possible and an electron cloud results
– Positively charged beams are particularly susceptible to emittance growth and instabilities if the cloud density is high
– The cloud particles can be trapped by the fields of the magnets around the ring
• Very strong fields in wigglers
– Cloud growth is very sensitive to the average currents and bunch structure in the ring
October 6, 2006 LEPP Journal Club 12
Moving to a Single Positron DR
Cloud density near (r=1mm) beam (m-3) before bunch passage, values are taken at a cloud equilibrium density. Solenoids decrease the cloud density in DRIFT regions, where they are only effective. Compare options LowQ and LowQ+train gaps. All cases wiggler aperture 46mm.
M. PiviILCDR06
October 6, 2006 LEPP Journal Club 13
Suppressing Electron Cloud in Wigglers
0 20 40 60 80 100 12010
9
1010
1011
1012
1013
1014
Bunch ID
e (
m-3
)
average density, long traincentral density, long trainaverage density, bunch train, -100Vcentral density, bunch train, -100Vaverage density, bunch train, 200Vcentral density, bunch train, 200V
stripline position
Strip-line typeWire type
Strip-line type Wire type
Calculation of the impedance ( Cho, Lanfa)
Design & test of impedance is under the way, test in PEPII Dipole & CESR Wiggler
Submitted to PRSTAB
Suetsugu’s talk
L. WangILCDR06
October 6, 2006 LEPP Journal Club 14
CesrTF Overview
• CESR-c HEP operations scheduled to conclude on March 31, 2008
• Design studies are presently underway to modify CESR for ILC Damping Ring R&D CesrTF
• 4 Key Questions:1. What can CESR offer as a damping
ring test facility?
2. How extensive are the required modifications?
3. What is the resulting experimental reach?
4. Can important R&D results be provided in a timely fashion for the ILC TDR and (hoped for) start of construction?
South (CLEO) and NorthInteraction Regions
October 6, 2006 LEPP Journal Club 15
CesrTF Concept
• Reconfigure CESR as a damping ring test facility– Move wigglers to zero dispersion regions for low emittance
operation
– Open up space for insertion devices and instrumentation
• Provide an R&D program that is complementary to work going on elsewhere (eg, KEK-ATF)
• Provide a vehicle for – R&D needed for TDR decisions (TDR complete at end of 2009)
– Operating and tuning experience with ultra-low emittance beams
– DR technical systems development
• Provide significant amounts of dedicated running time for damping ring experiments
October 6, 2006 LEPP Journal Club 16
Unique Features of R&D at CESR
CESR offers:– The only operating wiggler-dominated storage ring in the world– The CESR-c damping wigglers
• Technology choice for the ILC DR baseline design– Physical aperture: Acceptance for the injected positron beam– Field quality: Critical for providing sufficient dynamic aperture in the damping rings
– Flexible operation with positrons and electrons– Flexible bunch spacings suitable for damping ring tests
• Presently operate with 14 ns spacing• Can operate down to 4ns (or 2ns) spacings with suitable feedback system upgrades
– Flexible energy range from 1.5 to 5.5 GeV• CESR-c wigglers and vacuum chamber specified for 1.5-2.5 GeV operation• An ILC DR prototype wiggler and vacuum chamber could be run at 5 GeV
– Dedicated focus on damping ring R&D for significant running periods after the end of CLEO-c data-taking
– A useful set of damping ring research opportunities…• The ability to operate with positrons and with the CESR-c damping wigglers offers a
unique experimental reach
October 6, 2006 LEPP Journal Club 17
• Primary Goals– Electron cloud measurements
• e- cloud buildup in wigglers• e- cloud mitigation in wigglers• Instability thresholds• Validate the ILC DR wiggler and vacuum chamber design (critical for the
single 6 km positron ring option)
– Ultra-low emittance operations and beam dynamics• Study emittance diluting effect of the e- cloud on the e+ beam• Detailed comparisons between electrons and positrons• Also look at fast-ion instability issues for electrons• Study alignment issues and emittance tuning methods• Emittance measurement techniques
– ILC DR hardware development and testing• ILCDR wiggler prototype, wiggler vacuum chamber, 650 MHz SRF ,
kickers, alignment & survey techniques, instrumentation, etc.
CesrTF Goals
October 6, 2006 LEPP Journal Club 18
CESR Modifications
CLEO
North IR
South IR
• Move 6 wigglers from the CESR arcs to the North IR (zero dispersion region)– New cryogenic transfer line required– Zero dispersion regions can be created
locally around the wigglers left in the arcs
• Make South IR available for insertion devices and instrumentation
• Instrumentation and feedback upgrades
October 6, 2006 LEPP Journal Club 19
The North IR
North IR Modifications:• Remove vertical separators and install 6 wigglers• Add cryogenics capability• Instrumented vacuum chambers for local electron cloud diagnostics• Eventual test location for prototype ILC damping ring wiggler and vacuum chambers• Move present streak camera diagnostics area to South IR
18 m region for wigglers and instrumented vacuum chambers
October 6, 2006 LEPP Journal Club 20
The South IR
South IR Modifications:• Approx. 14 m of insertion device space available after CLEO removal• Cryogenics infrastructure available• Beige volumes indicate insertion regions• Support for beam instrumentation
RF Cavitiesfor short bunchlength operationshown here
Possible location for laserwireinstallation. A 0.26 X0 Al window is available 16.1 m to the west. It is also possible to place a 2nd window in the east.
October 6, 2006 LEPP Journal Club 21
Instrumentation for Ultra-Low Emittance Measurement
• Typical Beam Sizes– Vertical: y~10-12 m
– Horizontal: x ~ 80 m (at a zero dispersion point)
• Have considered laserwire and X-ray profile monitors– Fast X-ray imaging system (Alexander)
• Core diagnostic for CesrTF – high resolution and bunch-by-bunch capability
• Plan for integrating systems into CHESS lines
• First pinhole camera tests were successful! (see next slide)
– Laserwire• CESR-c fast luminosity monitor offers window suitable for laserwire use
• Detector potentially could be used for fast segmented readout of Compton photon distribution
October 6, 2006 LEPP Journal Club 22
GaAs Detector for X-ray Imaging
Sig
nal
(A
DC
Cou
nts
)
Position (m)Fast enough for single bunch resolution
First bunch-by-bunch beam size data in CHESS conditions Significant CHESS support
= 142 +/- 7 mDifferent symbolsrepresent differentbunches
Pinhole camerasetup at B1 hutch
NEW: GaAs arrays from Hamamatsu• 1x512 linear array• 25 m pitch• 1st sample has just arrived
October 6, 2006 LEPP Journal Club 23
Luminosity Monitor Window
• Available for laserwire use• Aluminum Window
– Faces into South IR– ~1 in thick (0.26 X0)– 16.1 m from center of CesrTF
insertion region– Looks at e+ beam– Aperture (for 16.1 m):
• +/- 1.7 mrad vertical• -7 to +2 mrad horizontal (negative
is to inside of ring)
• A similar window, but with smaller horizontal aperture, could potentially be added for monitoring the electron beam
October 6, 2006 LEPP Journal Club 24
CESR Modifications Summary
• How extensive are the modifications?– Significant changes to the two IRs (however, certainly no more difficult than a
detector and IR magnet upgrade)– Cryogenics transfer line must be run to the North IR– 6 wigglers must be moved to the North IR– Remove the electrostatic separators (single beam on-axis operation for CesrTF
and CHESS) – room for proposed CHESS undulators– Feedback amplifiers and electronics will be upgraded to allow operation with 4
ns bunch spacing• Could go to 2 ns with a more substantial upgrade
– Instrumentation must be upgraded• Extend multi-bunch turn-by-turn BPM system to entire ring (presently single sector)• High resolution emittance measurement techniques
• Conversion is relatively modest– Approx. 7 months of down time required (with existing laboratory resources) to
remove CLEO and carry out the conversion– Key preparation work carried out between now and April 2008
October 6, 2006 LEPP Journal Club 25
Experimental Reach
x
y
x
Wigglers
Parameter Value
E 2.0 GeV
Nwiggler 12
Bmax 2.1 T
x 2.25 nm
Qx 14.59
Qy 9.63
Qz 0.098
E/E 8.6 x 10-4
x,y 47 ms
z (with VRF=15MV) 6.8 mm
c 6.4 x 10-3
Touschek(Nb=2x1010 &
y=5pm )
7 minutes
Baseline Lattice
October 6, 2006 LEPP Journal Club 26
Tune scans• Tune scans used to identify suitable working points
Qx~14.59 Qy~9.63
October 6, 2006 LEPP Journal Club 27
Lattice Evaluation
Misalignment Nominal Value
Quadrupole, Bend and Wiggler Offsets 150 m
Sextupole Offsets 300 m
Quadrupole, Bend, Wiggler and Sextupole Rotations
100 rad
• Dynamic aperture– 1 damping time– Injected beam fully
coupled• x = 1 mm• y = 500 nm
• Alignment sensitivity and low emittance correction algorithms– Simulations based on
nominal CESR alignment capabilities
October 6, 2006 LEPP Journal Club 28
Vertical Emittance Sensitivities(Selected Examples)
October 6, 2006 LEPP Journal Club 29
Low Emittance Operations
• Have evaluated our ability to correct for ring errors with the above lattice– Goal: y~5-10 pm
at zero current
– Simulation results indicate that we can reasonably expect to meet our targets
Correction Type Average Value 95% Limit
Orbit Only 10.2 pm 21.4 pm
Orbit+Dispersion 3.9 pm 8.2 pm
Nominal Values
October 6, 2006 LEPP Journal Club 30
IBS Evaluation (2 GeV Lattice)
Horizontal Emittance (nm)
Vertical Emittance (pm)Assumes coupling dominated
Bunch Length (mm)
103 x Energy Spread
Growth by 3.5x
October 6, 2006 LEPP Journal Club 31
Alternate Operating Point• Want to study ECE impact at
ILC DR bunch currents – 2.5 GeV lattice with z ~ 9mm
– Zero current vertical emittance chosen to be consistent with above alignment simulations
– This emittance regime appears consistent with studying the impact of the ECE (and other effects) on emittance dilution
• Presently working towards more complete beam dynamics simulations
Horizontal Emittance
Vertical Emittance
Bunch Length
Growth by 1.6x
October 6, 2006 LEPP Journal Club 32
When Will R&D Results Become Available?
• Immediate Plans– Complete conceptual design work and validation– Proposal submission in December – Proposal will encompass our other areas of ILC accelerator research as well as
the test facility
• FY07– Engineering design work– Begin fabrication of items critical for 2008 down
• End of scheduled CESR-c/CLEO-c physics: March 31, 2008– Install wigglers with new vacuum chambers immediately
• First dedicated CesrTF run in June 2008!– Alternating operation with CHESS– Estimate ~4 months/year of operations as a DR test facility
• This schedule is consistent with: – Early results before TDR completion– Significant program contributions before start of ILC construction
October 6, 2006 LEPP Journal Club 33
The Next 1.5 Years
• Continue to develop the CesrTF Conversion Plan• Prepare for wiggler vacuum chamber studies
– Collaboration: SLAC, LBNL• Machine Studies
– Electron cloud and ion studies underway (see following slides)– Plan to continue such work through the end of CESR-c– Low emittance CESR-c (existing machine layout) optics have been designed: x ~ 6.5 nm
• General infrastructure preparation as can be supported by manpower and funding resources
FY07 FY08
Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar
Ongoing Development Work for CesrTF
Retrofit 2 spare CESR-c 8-pole wigglers with new vacuum chambers
Preparatory Machine Studies: Electron Cloud, Ions, Low Emittance CESR-c Optics
General Preparation: Cryogenic Transfer Lines to North IR, Instrumentation,…
October 6, 2006 LEPP Journal Club 34
CESR-c Wiggler Modifications
• Initial tests in CesrTF • Remove Cu beam-pipe• Replace with beam-pipe with ECE suppression and diagnostics hardware• SLAC/LBNL Collaboration
October 6, 2006 LEPP Journal Club 35
e+ Beam Size vs Bunch Current
0.5 mA
0.75 mA 1 mA
2 GeV vertical bunch-by-bunch
beam size for 1x45 pattern, positrons
Notice advancing onset of beam size blow up as a function of bunch current
0.25 mA 0.35 mA
October 6, 2006 LEPP Journal Club 36
Theory and measurement of instability onset
0.35 mA
0 10 20 30 40 500.1
0.15
0.2
0.25
0.3
0.35
0.4
b
103
0.11
0.4
[ ]b mm
0.5
60
pf MHz
a m
1/2 4
221 y
bb
c
Qualitative comparison: if the transverse eigen-frequency of the electron cloud
becomes comparable with the corresponding betatron frequency (xc), then the transverse motion becomes
unstable. Need to take into account the horizontal motion as well.
See ILCDR06 Talk by L. Schachter – https://wiki.lepp.cornell.edu/ilc/pub/Public/DampingRings/CornellWorkshopTalks/Schachter.Wake-Field_in_eCloud.ppt
October 6, 2006 LEPP Journal Club 37
Proposed Transition Plan
• Initial focus on local ECE measurements– Provides key TDR information– Provides guidance for subsequent CesrTF investigations
• Start exploring low emittance operations• 650 MHz SRF development getting underway• ILC Wiggler Prototype development getting underway
FY08 FY09
Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar
Down
CHESS CesrTF
Down for North IR Conversion
CHESS CesrTF Down for South IR Conversion (4 months)
Install/Test 2 wigglers w/modified Vacuum
Chambers
Install/Test full wiggler complement (including cryo support) and vacuum diagnostics in North IR.
Instrumentation and Vacuum Diagnostics Upgrades
LiCAS Alignment/Survey Upgrades
October 6, 2006 LEPP Journal Club 38
Survey and Alignment
collider component
Rapid Tunnel Reference Surveyor (RTRS) ConceptProposal submitted for ILC DR alignment and survey studies using CesrTF
Tunnel Wall
Reconstructed tunnel shapes(relative co-ordinates)
wall markers internal FSI external FSISM beam
LiCAS technologyfor automated stake-out process
A. Reichold
October 6, 2006 LEPP Journal Club 39
Prototype Operations Schedule
• Schedule along these lines presently under discussion– Provides 4 dedicated running periods prior to TDR completion
• Envision a 5-year NSF operations proposal: April 1, 2008 – March 31, 2013– Last 3 years would have a similar operating schedule to the FY09-FY10 version
FY09 FY10
May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr
CHESS
Supporting work can occur here
(eg, instrument-
ation)
CesrTF
Flexible Operations
and Machine Access
Down
CHESS
Supporting work can occur
here (eg, instrument-
ation)
CesrTF
Flexible Operations
and Machine Access
CHESS
Supporting work can occur here
(eg, instrument-
ation)
CesrTF
Flexible Operations
and Machine Access
Down
Install ILC
Proto-type
Wig-gler?
Running periods approximately
50% CHESS/50% CesrTF
Running periods approximately
50% CHESS/50% CesrTF
Running periods approximately
50% CHESS/50% CesrTF
October 6, 2006 LEPP Journal Club 40
Organization
• CesrTF will be a collaborative endeavor– LEPP will operate the machine– LEPP will also contribute to the experimental program– We expect to provide a significant fraction of the
machine time to collaborator experiments– LEPP will provide accelerator physics and machine
support for collaborator experiments
October 6, 2006 LEPP Journal Club 41
Collaborators
• Electron Cloud Simulation/Measurement/Suppression – M. Pivi, L. Wang – SLAC; L. Schachter – Technion; K. Harkay – ANL; K.
Ohmi and J. Flannagan – KEK • Wiggler vacuum chamber
– S. Marks, etal. – LBNL; M. Pivi, L. Wang – SLAC• Alignment and Survey
– A. Reichold, D. Urner – LiCAS, Oxford• Requirements and experimental plan
– J. Urakawa – KEK; A. Wolski – Cockroft Institute• Low emittance instrumentation
– G. Blair – Adams Inst.; J. Alpert – CalTech; CHESS Colleagues• Beam Dynamics Simulations
– A. Wolski – Cockroft Inst., M. Pivi, L. Wang – SLAC; P. Spentzouris, etal. – FNAL; C. Celata – LBNL
October 6, 2006 LEPP Journal Club 42
Acknowledgments
• CesrTF Studies– M. Ehrlichman (Minn)
– J. Shanks (REU)
– R. Helms
– J. Urban
– D. Sagan
– D. Rubin
• CESR Machine Studies– G. Codner
– E. Tanke
– L. Schachter
– M. Billing
– M. Forster
– D. Rice
– J. Crittenden
October 6, 2006 LEPP Journal Club 43
Conclusion
• CesrTF conceptual design work is ongoing– The machine offers unique features for critical ILC
damping ring R&D• CESR-c wigglers• Operation with positrons and electrons• Flexible bunch configuration• Wide range in operating energy
– Simulations indicate that the emittance reach is suitable for a range of damping ring beam dynamics studies
– The experimental schedule will allow timely results for ILC damping ring R&D
• We would like to extend an open invitation to anyone interested in collaborating on this project