CERN 7-11-5 adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of...
-
Upload
nigel-lyons -
Category
Documents
-
view
217 -
download
0
Transcript of CERN 7-11-5 adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of...
CERN 7-11-5 adb
Chamber Support Structure Installation
MUON SYSTEM INTEGRATION MEETING
- Status of Production of support panels- Things to be settled prior to installation- Plans for the Installation of the support panels
2 m
2,4 cm
1,5 m M2 prototype at LNF transport & positioning
M2 proto
precision pin
glue
rivets
assembly steps
M2 proto
3 panels 4 panels
M2 proto
photogrammetry (50 m) in horizontal position of the holes for rivets (our main reference; much better than our needs 0,5 mm)
M5 real
Accuracy of Industrial photogrammetry
Accuracy of Cospal’s industrial photogrammetry = 1/120.000(certified by GSI)
8 microns per 1,0 meter of object size
Conditions: Photographs: from at least 2 different heights and from varied geometry.
Coded targets: 8 or more (we use 14 coded targets).
Scale bars: 2 or more (we use 2 scale bars).
Observations: each point seen at least 6 times.
Plan quality factor: between 1.00 and 2.00.
Image space RMS: < 0.3 micron
Scale bar agreement: better than 0.05 mm
Point RMS: better than 0.035 mm in each direction.
slide from COSPAL
Accuracy of Industrial photogrammetry
The measurement was performed on a 3D-measuring machine, type PM 302010, brand Leitz, at MAN Technologie AG in Ausburg (Germany). This type of measuring machine scans the surface mechanically whit a tip. The machine is installed in an air-conditioned room on a concrete plate which is supported by air bearings for vibration insulation. The measuring error is about 6 micron (absolute).
For having a comparison reference on the measurements we have carried out through the photogrammetry system, we have measured one panel using a different measuring system having a better accuracy.
Cospal’s photogrammetry Rms 54,5 micron
MAN 3D-Measuring machine (DEA) Rms 54,2 micronslide from COSPAL
delivery of two half-stations (PS & UZ) at the same time: long term stockage (3 - 4 months)
M5 real
M5 ready before end November; then two half-stations every two weeks (delivery completed at end of January)
lifting tools
prototype design
fixation joints
activities before installation
• SC document under preparation by Alessandro summarizing the calculations done to ensure that the walls and their assembling are adequate for our purpose: panels, connections, fixation joints, chamber supports final lifting system design (structural analysis) resistance verification of lifting system
• material procurement (all orders sent before middle December)
• PPSPS under preparation by Alessandro to finalize procedures for a safe assembling in the area
• transport to the pit of materials and installation tools (January) + working spaces organization
- panels arrival at Bld 156/similar spaces
- lifting tools installation in the pit
- panels transport to the pit
installation sequence
1 panel in vertical position
2 chamber supports fixation
3 grounding copper braid fixation
4 cable supports
5 panel lifting
6 positioning of the following panel
7 gluing & riveting
8 safety electrical soldering (metallic structure)
9 alignment check of some chamber supports (with ruler)
next
day
(gl
ue h
arde
ning
)
less than one working day for each panel: one half-station a week
2
3
4
installation plan for the supporting structure
Start cryo side (US) middle January (12/1/6)
• 2 weeks for the first half-station M5 (16/1-29/1)
• 1 week for the first M4 half-station (30/1-5/2)
• 1 week for the first M3 half-station (6/2-12/2)
• 1 week for the first M2 half-station (13/2-19/2)
Switch to pit (PZ) side on March
• 4 weeks for M5-M2 (20/2-19/3)
M1 immediately after