CenturyLink | Qwest SAP Integration Program Status Report – Week Ending 5/20/11
description
Transcript of CenturyLink | Qwest SAP Integration Program Status Report – Week Ending 5/20/11
CenturyLink & Qwest CommunicationsCreating a National, Industry-Leading Communications Company
CenturyLink | Qwest SAP Integration
Program Status Report – Week Ending 5/20/11
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
SAP Integration ScorecardKey Program InformationCurrent Gate:Planned Start:Planned Finish:Key Deliverables in Phase:
Realization – Design Confirmation & BuildMarch 7, 2011July 31, 2011Updated Functional Designs (FDs) SAP ConfigurationRICEF TD, Code & Unit Test
Work stream Last Week
This Week Trend Status Explanation Summary Watch Items
SAP Design (FDs and Open Solution Items)
Finalizing remaining open designs (Asset Center, Supplier Portal, BI, HR-Benefits, etc.). 174 FDs completed of revised planned of 181.
FD Wrap Up [revised due: 6/3 with exceptions]
SAP Configuration
67% of configuration effort completed vs. plan of 60%; cutover items being identified as part of configuration build.
PS/AM Inventory & Revised Plan [due: 5/27]
Legacy Qwest Development
222 TDs completed and signed off w/ 403 TDs in progress; Detailed build plans to be validated 5/27, will move to yellow when complete. Targeting 280 specs for completion this week.
Functional Spec reviews for Tax & CPE [due 5/20]; IT Tools [due 5/20]
Legacy CTL Development
TD Plan: 51 Completed vs. 49 Planned. WTX scope inventory drafted and under review; Real Estate scope pending; FW/BM scope is being reevaluated.
WTX & Real Estate RICEF Inventory & Plan [revised due: 6/3]FW/BM Work Plan [revised due: 6/3]
SAP Development TD Plan: 128. 126 TDs completed/pending approvalBuild Plan: 67. 73 objects completed/pending approval
TD Rework increasing per FD changes & TD Pipeline [monitored]
Technology / Architecture
Finalizing HR Support Pack approach with HR Functional team (UAT timeframe); defined approach to Security testing pending work plan detail.
QA Environment Builds [due: 6/15]SAP Transports [on-going]
Test Preparation / Execution
Test script inventory identified. Tool & environment approach communicated. Finalizing test iteration entry/exit criteria.
Test Prep Complete [7/11]
Change Mgmt & Training
Base-lined business/change impact information; on track for closure of Comms Strategy & Stakeholder Assessment
Stakeholder Assessment & Communication Strategy [revised due: 5/27]
Conversion / Cutover
Launched data conversion and mapping reviews/finalization with functional teams; drafted straw man as part of planning for first mock conversion (7/11).
IT Cycle 1 data loads [begin: 7/11]
BI Reporting On track to lock scope by 6/3; HR scope definition completion date under review.
Req’s Wrap-up [due; 6/3]Phase I reports build [due: 8/01]
TrendLast week This week
Status Date: Wk Ending 5.20.11
2
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement 3 3
SAP Integration: Escalated Issue & Risk Mgmt SummaryWork
streamSharePoi
ntIssue #
Description Progress Log / Action Plan Owner(s) Target Resolution
Finance 691
Real Estate requires the ability to track expenses at a building level of detail. The Address Id field is used today within Qwest systems. What is the equivalent field in SAP to meet this requirement?
• Newly escalated issue as of WE 5.6 In Progress. Solution options being
investigated. Next meeting on 5/17 before presenting to CCB.
Carol S. /Brian
Braxton31- May
Finance 716
Master Mapping will not begin until the Master Mapping Team (Deb Brallier/Angel Corie/Connie Silin) understand how Segment, State and Region will be held in SAP (inclusive of how populated & with what value(s))
• Newly escalated issue as of WE 5.6 Closed. Meetings conducted; master mapping
activities in progress per approach agreed upon.
GA Core Team 13- May
Finance 759Lack of SE resource availability to complete CPE-E2E Blueprint and Functional Spec.
• Newly escalated issue as of WE 5.13 In progress. Chris working w/ Meg Hall to identify backfill. Bob staying on project until contention resolved.
Chris Tweedy 03-Jun
Finance 685The Affilliate Auto Pay Process occurs in Revenue Journals (RJ) • Newly escalated issue as of WE 5.20
Escalated to PMO.PMO
GA Core Team
27- May
Finance 663
Qwest does an automtic payment of some affiliate bills within the CRIS, IABS, BART and B&C Systems today. We need the Treasury Netting website to continue or a replacement fashioned before 1/1/12.
• Newly escalated issue as of WE 5.20 Escalated to PMO.
PMOGA Core Team
18-May
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement 4
SAP Integration: Escalated Issue & Risk Mgmt Summary (cont.)
Work stream SharePointIssue # Description Progress Log / Action Plan Owner(s) Target
Resolution
Purchase to Pay 9
Supplier Portal selection: Decision to interface with legacy Qwest Supplier Portal versus implementing SAP Supplier Self-Service Portal (SUS).
• SRM workshops scheduled for week of 4/11. Final scope/solution determined by 4/29.In progress. Executive readout conducted on 5/12. Additional validation of implementation costs and benefits planned for week of 5/16.
Mary Sanders/Connie Walden
27-MayOld:29-Apr
Purchase to Pay 749
Sterling File transfer in place of QPID.WMS is BLOCKED until offshore has access to the overview (meeting was not recorded) and can give input into the overall design, and LOE.
• Newly escalated issue as of WE 5.13 Escalated to PMO.
Mary Sanders 3-June
Purchase to Pay 48
Coding on PICS Repair: Need to code PO for replenishment and Repair. (Carol Squires needs to answer this question)
• Newly escalated issue as of WE 5.13 Escalated to PMO.
Sean Breeze 27-May
BI 441
BI Blueprint: Data warehouse reporting requirements are not available. The build effort associated with SAP BI and legacy data warehousing is on hold while reporting approach and requirements are gathered.
• Qwest / CTL team members have been identified. Workshops scheduled for week of 4/4.On target. End date moved per open requirements definition for Finance & HCM; working with Stakeholders to solidify revised target of June 3rd
Brian Clement/Doniesha Miller
3-June
4
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement 5
SAP Integration: Escalated Issue & Risk Mgmt Summary (cont.)
Work stream SharePointIssue # Description Progress Log / Action Plan Owner(s) Target
Resolution
HCM 315Finalization of Leave/PTO policies for non-represented employees is not expected until June, 2011.
• Follow up to determine if policies can be provided to SAP team in advance of formal June release to initiate configuration activities. On target. Team requests executive decisions to be communicated by 5/20. Proposed policy impact analysis in progress.
Marina Pearson 20-May
HCM 315
Confirmation of Benefits offerings not expected until June, will impact the configuration build and RICEF development timeline. Depending on the degree of change from current CTL offerings, the build effort could be substantial and may not allow for adequate testing prior to go-live.
• Follow up to determine if benefits plans can be provided to SAP team in advance of formal June release to initiate configuration activities. On target. Team requests executive decisions to be communicated by 6/15 (health plans and vendors selected) and 6/30 (for vision, dental & prescription plans). Presence requested for Stewart Ewing and Stacey Goff at Benefit Committee meetings.
Marina Pearson 15-Jun
HCM 315Finalization of pay practices (shift differentials, OT, etc.) for non-represented employees is not expected until June, 2011.
• Follow up to determine if pay practices can be provided to SAP team in advance of formal June release to initiate configuration activities.Team requests executive decisions to be communicated by 5/20 in case of extensive changes. 6/15 otherwise. Timeline has been confirmed with Vicky Smith.
Marina Pearson 20-May
5
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Executive Summary Configuration item count: 219*
Note*: Change in FI inventory pending formal CR approval
5/20 - Actual vs. Plan Complete : 67% (effort) Complete vs. 60% Target Note: 131 Objects completed vs. 131
(Revised) Plan Configuration Action Item:
PS/AM: Object inventory & revised build plan recommendation in progress [due: 5.27]
Configuration Build - Planned v Actual Bertke Escher
6
TrendLast week This week
Status Date: Wk Ending 5.20.11
Key - Variance to Plan: (Actual– Plan) / (Plan), G = Within 3% Y = 4% – 10% R = Greater than 10%
Chart: Completed Configuration
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Blueprint: SAP FD Wrap Up - Planned v Actual Bertke Escher
7
TrendLast week This week
Status Date: Wk Ending 5.20.11
Key - Variance to Plan: (Actual– Plan) / (Plan), G = Within 3% Y = 4% – 10% R = Greater than 10%
Executive Summary RICEFW Inventory Count: 227
Note: Change for WE 05.20 per approved CRs 5/20 - Actual vs. Plan Complete : 174
Completed FDs vs. 181 Planned 22 In Progress // 2 Not Started // 29 On Hold
Action Required Summary: HCM: 21 On Hold w/ no target dates
published PS: 5 On Hold w/ no target date FI: 2 Pending Approval; 1 pending de-scope
(move to BI) P2P: 3 On Hold (SUS decision)
Chart: Complete & Approved FDs
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
# Roadblock Description Issue or Action# of FDs Impacted
Original FD Completion Date
Revised FD Completion
Date Owner
Project Systems & Asset Mgmt 91 FDs Pending Business Clarification
CTL-ARIAction 2 4/29/11 ESCALATED
5/13/11C. Johns
2 Business Approach PendingIT Tools
Action 3 4/29/11 5/27/11 K. DeRoseZ. Scozzari
3 Business Decision PendingAsset Center
Issue 2* (1 has been started)
4/29/11 ESCALATEDPending
C. Johns
4 Business Decision PendingBMSe
Issue 2 4/29/11 To be defined wk of 5/23
C. Johns
Finance 31 FDs Pending Approval
Open Vendor Invoices/ AP Vendor Extranet
Action 2 4/29/11 5/24/11 K. BaptisteK. Schamel
2 Pending CR - RICEF moving to BIQPAS
Action 1 5/19/11 Pending PMO
Procurement (P2P) 3*1 Executive Decision Pending –
SUS/SRM/CLM PortalAction 3 4/29/11 Pending Steering
Committee
2 Pending DescopeRICEF FDs moved to BI Reporting
Action 2* 4/29/11 Pending PMO
8
SAP Blueprint & Functional Design Wrap Up Summary as of Week Ending 5/20/11
53 Total Outstanding
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
# Roadblock Description Issue or Action# of FDs Impacted
Original FD Completion Date
Revised FD Completion
Date Owner
HR – Benefits 291
Business Approach Confirmed – FD In Progress
Action 10 5/20/11 6/3/116/17/116/30/11
N. Aguilar
2 Business Decision Pending – Reporting Approach (BI or R3)
Issue 5 Pending Pending D. Freeman
3 Business Approach Pending – Towers Watson
Issue 4 Pending Pending D. Freeman
4 Vendor Engagement – Kenexa
Issue 7 Pending Pending D. Freeman
5 Vendor Selection – Training & eTrade
Issue 3 Pending Pending D. Freeman
HR – Time & Payroll 91
Business Approach Confirmed – FD In Progress
Action 7 5/20/11 5/27/116/3/11
6/17/11
N. Aguilar
2 Business Approach Pending – Towers Watson
Issue 1 Pending Pending D. Freeman / E. Buckley
3 Vendor Selection – Reed Group
Issue 2 Pending Pending E. Buckley
9
SAP Blueprint & Functional Design Wrap Up Summary as of Week Ending 5/20/11
53 Total Outstanding
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Variance to Plan = (Team Actual– Team Plan) / (Team Plan), G = Within 5% Y = 6% – 10% R = Greater than 10%Variance is per week, cumulative of all deliverable groups
Development: SAP TD - Planned v Actual
Kiran Das, Jake Ford
10
TrendLast week This week
Status Date: Wk Ending 5.20.11
Executive Summary RICEFW Inventory Count: 202*
Note: FD Variance per No Dev required 5/20 - Actual vs. Plan Complete : 126
Completed vs. 128 (Revise) Plan Approved - 123 TDs | Pending - 3 TDs In Progress: 19 TDs KT In Progress or Pending: 29 TDs
TD Action Items: MM: Revised FDs require updates,
confirming TD rework effort; HCM/PS: Revised completion dates
dependent on closure of open issues
Key - Variance to Plan: (Actual– Plan) / (Plan), G = Within 3% Y = 4% – 10% R = Greater than 10%
Chart: Complete & Approved TDs
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Variance to Plan = (Team Actual– Team Plan) / (Team Plan), G = Within 5% Y = 6% – 10% R = Greater than 10%Variance is per week, cumulative of all deliverable groups
Development: SAP CDUT - Planned v Actual Kiran Das, Jake Ford
11
TrendLast week This week
Status Date: Wk Ending 5.20.11
Executive Summary RICEFW Inventory Count: 202*
Note: FD Variance per No Dev required* 5/20 Target vs. Actual: 73 Completed vs.
67 Planned Approved - 30 | Pending – 43 TDs Build In Progress: 25 Objects KT In Progress or Pending: 25 TDs
Build Plan: Baseline Plan updated to account for items taken off hold; plan excludes confirmed dates for On Hold items (HCM/HR, PS and P2P)
Key - Variance to Plan: (Actual– Plan) / (Plan), G = Within 3% Y = 4% – 10% R = Greater than 10%
Chart: Complete & Approved RICEFW Build
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Variance to Plan = (Team Actual– Team Plan) / (Team Plan), G = Within 5% Y = 6% – 10% R = Greater than 10%Variance is per week, cumulative of all deliverable groups
Development: Legacy Q TDs – Planned v Actual Chris Tweedy, Denise Aveline
12Key - Variance to Plan: (Actual– Plan) / (Plan), G = Within 3% Y = 4% – 10% R = Greater than 10%
TrendLast week This week
Status Date: Wk Ending 5.20.11
Executive Summary RICEFW Inventory Count: 997 5/20 - Actual vs. Plan Complete: 222
Complete vs. (revised) Plan of 236 Pending Approval: 9 TDs: In Progress: 395 TDs
Open Functional Specs: (13/282 ) Tax, CPE, IT Tools - Target 5/20
Chart: Completed & Approved TDs
24%Group Target Variance: (14) TDs
WE 5.20 Output: +51 TDs
Variance from Plan: -2%
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Variance to Plan = (Team Actual– Team Plan) / (Team Plan), G = Within 5% Y = 6% – 10% R = Greater than 10%Variance is per week, cumulative of all deliverable groups
Development: Legacy Q CDUT – Planned v Actual Chris Tweedy, Denise Aveline
13Key - Variance to Plan: (Actual– Plan) / (Plan), G = Within 3% Y = 4% – 10% R = Greater than 10%
TrendLast week This week
Status Date: Wk Ending 5.13.11
Executive Summary RICEFW Inventory Count: 997 5/20 - Actual vs. Plan Complete: 10
Complete vs. 14 Planned In Progress: 33 Build Objects in progress (25
Finance & 8 P2P) Confirmed Plan - Pending: The following
represents a drafted PMO plan; confirmed Build plans being completed with Functional Teams
Chart: Completed & Approved Build
Variance from Plan: -0%
1%Group Target
WE 5.13 Output: +1 Object
DRAFT Plan Under Review
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Legacy CTL TD – Planned v Actual Brandon West, Jake Ford, Vern Hatmaker, Jennifer Kemp, Neil Leguillow
14
Status Date: Wk Ending 5.20.11
Executive Summary Object Inventory Count: 261* Overall – TD: 20% Complete vs. 19%
Planned 5/20 Plan to Actual - TD: 49 Planned vs.
51 Actual (6 incremental) Note – FD Completion: 4 from FW/BM & 47
from CPR Yellow Status Driver(s)
WTX & RE: Pending scope lock & TD/Build Plan [target date: 6/3]
FW/BM: Revised TD/Build plan per add’l scope & complexity changes [target date: 5/27]
Chart: Complete & Approved TDs
Variance from Plan: +1%
19%Group Target
Variance Total: +2 TDs
WE 5.20 Output: +6 approved TDs
Key - Variance to Plan: (Actual– Plan) / (Plan), G = Within 3% Y = 4% – 10% R = Greater than 10%
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Legacy CTL Build – Planned v Actual Brandon West, Jake Ford, Vern Hatmaker, Jennifer Kemp, Neil Leguillow
15
Status Date: Wk Ending 5.20.11
Executive Summary Object Inventory Count: 261 Overall – Build: 5% Complete vs. 6%
Planned 5/20 Plan to Actual: 15 Planned vs.
12 Actual (1 incremental) Yellow Status Driver(s): See CTL TD
slide (14)
Chart: Complete & Approved Builds
Variance from Plan: -1%
6%Group Target
Variance Total: 3 TDs
WE 5.20 Output: 1 approved Builds
Key - Variance to Plan: (Actual– Plan) / (Plan), G = Within 3% Y = 4% – 10% R = Greater than 10%
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Change Management & Training – Team StatusDenise Lee, Toni Solano, Karen Farwell
16
TrendLast week This week
Status Date: Wk Ending 5.20.11
Deliverable Completion Progress
Key Activities for Next Week
Status SummarySAP Change Mgmt & Training Base-lined current business/change impact info, agreed
format, planned for completion Continued building stakeholder approach Engaged Program Steering Committee on topic of business
readiness and agreed next steps Completed installation of UPK on production servers Met with Assima (training product vendor) Finalized deliverable templates for Training Plan,
Communication Plan, and Change Impacts Initialized process for unplanned training requests from other
teams, other projects Planned approach for QC training, to be validated by Testing Conducted CTL/Qwest Communication vehicle audit
Non-ERP Status (Business Readiness) Overall Green Status
Sign-off Communication Strategy & Stakeholder Assessment Advance Business/Change Impacts for revised 6/3 deadline Meet with Testing team re QC training approach Understand BPC training needs and introduce CR as needed Conduct content testing on TEDS Start migrating UPK content from development to production
server Create mock up for project website Conduct 1:1 discussions with Program Steering Committee
members Schedule CMT deep dive for week of 6/13
DeliverableTarget CompDate
Progress
Status%
CompRevised Comp
Date
Stakeholder Assessment 3/18/2011
In progres
s 50% 5/27/11
Training Strategy 3/18/2011 Signed off 100% 3/31/11
Communication Strategy 3/18/2011 In
signoff 100% 5/24/11
Business/Change Impact Assessm’t
4/18/2011In
progress
25% 6/3/11
ID Summary Description(per SharePoint)
Impact(H/M/L) Owner Due
Date
No new or escalated issues
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Tech Architecture – Team StatusJake Ford, Mike Sportack
TrendLast week This week
Status Date: Wk Ending 5.20.11
Key Activities for Next Week
Transports: Applied this week’s approved ECD transports to TRN. This brings the box in synch with ECD.
SAP Security: Met with the SAP Security. Confirmed the team structure and the need for project workplan. Decided to have new roles tested in early test iterations; all role driven testing during UAT.
IBM Sizing: Awaiting response from IBM on the submitted hardware sizing sheet. This should confirm the capabilities of the SAP production machine.
HR Support Packs: Awaiting confirmation from the HR functional leads on the strategy for mitigating the risks of applying during UAT.
Payroll Test System: Gathered requirements for the build of the new environment. Finalize possible interfaces with Qwest time systems and SAP EP (ESS/MSS).
On-going Maintenance Areas: Apply SAP Code Inspector to support adherence to
coding standards. Issue and updates SAP IDs for both the offshore and
onshore teams Perform technical support and maintenance on the SBN
and TRN instances. Provide technical design guidance to the technical and
functional teams.
Build project workplan for Security work and confirm the schedule with Mary and the team.
Acquire deeper technical details and requirements on the Vertex O Series implementation.
Review and communicate the IBM hardware sizing results. Continue documenting all systems, their architectures (dev,
QA, Prod) and their methods of communication in the integrated environment.
Build and review a list of next week’s new ECD transports slated to be applied to TRN.
Continue to employ Code Inspector to help analyze code quality and enforce standards.
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
SAP Security Project Plan 5/27 Started 10%
Applied the transports inbound from ECD to TRN with the functional teams
Complete 100%
Continue to apply the SAP Code Inspector to new custom objects.
On going
Continue to issue IDs and VPN access to new team members
On going
ID Description Impact(H/M/L)
Owner Due Date
17
Issues & Risks – New Only
Deliverable Completion ProgressStatus Summary
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement 18
Conversion/Cutover – Team StatusCenturyLink – SAP Work streamSudhakar Bhaskar, Jake Ford, Brian Liedtke
TrendLast week This week
Status Date: Week Ending 5.20.11
18
Deliverable Completion ProgressStatus Summary
Key Activities for Next Week
YELLOW Status Driver(s): Framework in place to speed up conversion finalizations; straw
man for conversions being reviewed for fit/ data verification criteria Reviewed P2P SAP Mapping Documents Applications as part of conversions: 173 Tech Spec Completion Status:
Legacy Conversion (72) • P2P: 0/15• P&A: 0/24• GA: 0/1 (2 CRs pending)• HCM: 13/32
SAP Mapping Documents (65)• P2P: 0/10 (0%)• P&A: 0/15 (0%)• GA: 0/1 – (2 CRs – Invoices & Tracker)• HCM: 13/39
SAP Conversion (18)• P2P: 9/9• P&A: 7/8• GA: 0/1 (2 CRs pending)• HCM: N/A Review and begin to populate the SAP Mapping Documents to
complete Legacy Tech Specs. Gather inputs from all process teams to complete the straw man
Mock Conversion plan. This is in preparation for SIT1. Team leads complete 1st draft by 5/27.
Continue developing integrated conversion plans and requirements.
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
Integrated Conversion Plan 5/27 In progress 70%
SAP Map Doc Sign Off 5/27 In progress 20% 6/3
TS Complete – Legacy 6/3 In progress 18%
TS Complete - SAP 5/27 In progress 89%
MM Req Defined 5/27 In progress 50%
MM TS Complete 6/17 In progress 50%
Mock Conversion Plan 6/17 In progress 5%
Build Complete – Legacy 7/3 In progress 7/29
Build Complete – SAP 6/24 In progress
Mock 1 Load Start 7/11
ID Summary Description Impact(H/M/L)
Owner Due Date
760 Master Mapping requirements from each Process Team are not complete.
H S.Thompson/ C. Silin
5/27
761 Build completion dates extend past the start of Mock 1 conversion test on 7/11, some to 7/29
H Dev Teams
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
SAP Reporting / BI – Team Status Brian Clement, Doniesha Miller
19
TrendLast week This week
Status Date: Wk Ending 5.20.11
YELLOW Status Driver(s): Requirement scope lock for each Process work-stream on track for 6/3 requirements/ scope lock: Finance: Conducted requirements gathering discussions for
Regulatory and Capital reporting. Continuation of FICUS data mapping exercises; watch item: progress against 6/3 target date is behind plan
P2P: Submitted six reporting functional specifications for business owner sign off . Reports are to be turned over for technical design this week;.
P&A: Already conducted several meetings and closing out requirements gathering sessions;.
HR: Met with HR business owners to discuss reporting requirements and 6/3 timeline;.
Current BI Reporting inventory: 41 reports submitted for review and development.
Functional Specs for 31pending sign-off from Bus owners; working to close out all by we 5.27
Technical specifications in progress for (4) reports approved - Cycle Time, Point of Sale, Contract Headers, and HR Director Manager. Will begin technical specs for 6 additional P2P reports this week.
Deliver next set up functional specifications to development team
Requirements gathering sessions wrap-up Support on-going BI reporting requirements definition
with focus on Finance and HR
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
BI tool selection 3/18/2011 Complete 100% 03/18/2011
Develop BI Project Plan 4/8/2011 Complete 100% 4/29/2011
Functional Requirements 5/15/2011 In Progress 95% 6/3/2011
Functional Design 5/18/2011* In Progress 70% Pending*
Technical Design 7/29/2011* In Progress Pending*
BI Report Development 7/29/2011* Pending Pending*
ID Summary Description(per SharePoint)
Impact(H/M/L)
Owner Due Date
No new or escalated issues
Deliverable Completion Progress
Key Activities for Next Week
Issues & Risks – New Only
Status Summary
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Deliverable Completion Progress
Key Activities for Next Week
Status Summary Continued development in Integrated Test Timeline
Defined requirements for Mock Conversion schedule Defined a proposed Parallel Payroll Test timeline Confirmed Legacy Q Test Coordinators for Test
Continued Tools Preparation Confirmed connectivity for onshore resources for
Qwest QC Instance. Offshore confirmation pending. Began Tools requirements definition (configurations
& metrics reporting, etc.) Began plans for QC Training with the Training Team
Continued Test Preparation with Functional Teams P2P – 225 unique scripts identified, 16 in-stream HCM – 212 unique scripts identified, 0 in-streams FI – 51 unique scripts identified, 0 in-streams PS/Assets – 58 unique scripts identified, 0 in-
streams
Continue to work through Integrated Test Timeline dependencies across Development, Conversion, & Tech Arch
Continue Test Prep work with SAP Functional Teams to build out Business Process Model with Test Scenarios / Scripts
Continue Legacy Q & Legacy CTL Teams Test scope / plans & identification Test Coordinators for testing & support
Conduct offshore connectivity test of Quality Center & define Configuration / Training requirements
Define Plans for Integrated Test Prep Workshops (SAP, Legacy CTL & Q) for Integration Test Scenarios
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
Test Workplan Complete 100%
Test Strategy 5/27/2011 In Progress
90%
Integration Test Approach / Plan
7/29/2011 In Progress
15%
Integration Test Script Writing Complete
9/16/2011 Not Started
0%
Integration Test Execution Complete
11/4/2011 Not Started
0%
Testing – Team StatusLandi Foster, Alex Bohl, Mike Schwein
ID Description Impact(H/M/L)
Owner Due Date
20
Issues & Risks – New Only
TrendLast week This week
Status Date: Wk Ending 5.20.11
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
TrendLast week This week
Status Date: Wk Ending 5.20.11Procure to Pay – Team StatusCenturyLink – SAP Work streamCam Nolan, Fritz Ticar
21
Deliverable Completion Progress
Key Activities for Next Week
Status Summary
Finalize initial test script repository with Test lead. Engaged on Conversion Team activities Completed RICEF Configuration Documents Engaged in WTX discussions. WTX Team set up
weekly follow up meetings to ensure alignment Outstanding RICEF FD work pending Portal direction
Support TD, KT & build progress Support Legacy Qwest TD process Support Test process Support Conversion Process
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
FD Ready for TD Handoff
03/15/2011 completed 100% 4/29/2011
Configuration Build 5/6/2011 completed 100% 5/10/2011
ID Summary Description(per SharePoint)
Impact(H/M/L)
Owner Due Date
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Procure to Pay – Team StatusQwest Procurement Work streamBill Milligan, Mary Sanders and Rich Wyn
TrendLast week This week
Status Date: Wk Ending 5.20.11
22
Deliverable Completion Progress
Key Activities for Next Week
Status SummaryYELLOW Status Driver(s): Yellow pending decision on
procurement strategy. Issue resolution – reduced all open issues to 14
2 of 14 issues were just opened 98 TS started out of 98 = 100% 28 TS Completed out of 98 60 TS To Be Completed 10 TS Are in CCB pending de-scoping
– not working on these TS’s CCB Decisions
De-scoped = x Specs Increased scope = x Spec
TS Completion Schedule Week 5/23 = 22 Week 5/30 = 24 Week 6/6 = 12 Week 7/11 = 2
Start development for the 28 completed TD’s SUS/SRM/CLM funding decision
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
Complete Functional Decision for Portal, Services Purchasing and Contract Management
4/29/11 Completed 100%
Tech Specs Completed 6/3/11 28 Completed out of 98
Total
29% 6/10/11
RICEF Development 7/29/11 In progress 0%
ID Description Impact(H/M/L)
Owner Due Date
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement 23
Finance – Team StatusCenturyLink – SAP Work streamBrian Braxton, Lakeshia Baptiste, Kirk Schamel
TrendLast week This week
Status Date: Wk Ending 5.20.11
23
Deliverable Completion ProgressStatus Summary
Key Activities for Next Week
Yellow Status Driver(s): Closure of 3 past due FDs: CRs Pending
QPAS - aligned that data source will be BI report Extract and Load Invoice and Payment data into
the AP Vendor Extranet – SRM SUS Open Vendor Invoices AP Conversion submitted to Brian
for approval 5/24Configuration Progress
Special Ledger configuration completed by 5/27 GL Integration configuration completed by 6/3 Internal Order configuration completed by 6/3
Confirm E2E Internal Order requirements Indirect tax configuration to support International by 6/3 Cash Mgmt configuration completed by 6/24
Depending on Treasury project go/no go decision
Continue configuration in TRN; evaluate completion plan targets per outstanding Segment Reporting issue/decision
Continue solution prototype for management and regulatory reporting
Continue design integration workshops – Assets, International accounting
Continue conversion mapping and test prep activities
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
RICEF Inventory Confirmed
03/04/11 Completed 100% 03/08/11
FD Confirmation 2/28/2011 Completed 100% 03/15/2011
FD Ready for TD Handoff
04/29/11 In progress 90% 5/24/2011
Configuration Build 5/6/2011 In progress 60% 6/24/11
ID Description Impact(H/M/L)
Owner Due Date
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
TrendLast week This week
Status Date: Wk Ending 5.20.11Finance – Team StatusQwest Work stream - General Accounting, Accounts Payable, Revenue JournalsAileen Karamaroudis, Jim O’Keefe, John Quickstad (Tax), Bob Kulp (CPE)
Deliverable Completion Progress
Key Activities for Next Week
Status SummaryRED Status Driver(s): Red pending review of AP/GA plan. Approved: 163/475 (34%)
8 Revenue Journal 79 GA/AP 76 Billing
Drafted: 180/475 (37%) 76 Revenue Journal 100 GA/AP 4 Billing
Tech Spec Blocks: 2 issues remain open (Block-Start) (Conv Unc Prop) 2 issues remain open (Block-Finish) (Invoice ID, CPID)
CPE-E2E Blueprint/Func Specs Verbal Approval Received Tax Func Spec Drafted
Finish Field Mapping/Resolve blocked issues Approve Tax Functional Specs (Incremental Use Tax) Receive formal approvals CPE-E2E Func Specs Remaining Tech Specs to be Approved:
Revenue Journal (65 remain, all drafted over 75%) GA/AP (190 remain, 100 drafted) Billing (11, 4 drafted)
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
Tax Blueprint – Func Specs Review/Approved
4/15/11 In progress 94% 5/27
CPE-E2E Func Specs Reviewed/Approved
4/15/11 In progress 95% 5/25
Tech Design 5/27/11 In progress 50%
RICEF Dev 7/29/11 Not Started
0%
ID Description Impact(H/M/L)
Owner Due Date
24
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
TrendLast week This week
Status Date: Wk Ending 5.20.11HR Time & Payroll – Team StatusCenturyLink SAP Work stream Ed Buckley, Noemi Aguilar
25
Key Activities for Next Week
Yellow Status Driver(s): Tracking YELLOW per outstanding FDs (on hold or in progress) against revised target dates (see slide 9).
Completed garnishment ACH/Check configuration Worked on configuration of absences/attendances,
worksites, and work schedules Continued configuration design solutioning Confirmed work schedule conversion approach Provided 3 updated FDs w/TS to Dev team Started impact analysis of TOP policy changes to Time
solution
ID Description Impact(H/M/L)
Owner Due Date
745 Risk: There is a production project streamlining Time Schema code for overtime processing that will delay any project OT calculation config until at least 5/15 or later.
High Noemi Aguilar
5/20/2011
Issues & Risks – New Only Complete past due configuration for represented
employees- garnishment letters & work on config due on Monday 5/30- work schedules, attendances, non benefit deductions, etc.(8 total), Potentially descope 2
Provide Dev team with 6 updated FDs Continue to work with Legacy on Payroll conversion Continue assessment of pending policy/pay decisions to
solution
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
RICEF Inventory Confirmed
02/01/2011 In progress 100% 04/19/2011
FD Updates 03/01/2011 In progress 77% June/July 2011*
Configuration Build 05/06/2011 Started 21.1% 07/15/2011
Deliverable Completion ProgressStatus Summary
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement 26
HR-Payroll– Team StatusQwest HR Work StreamBob Platt
TrendLast week This week
Status Date: Wk Ending 4.8.11
TrendLast week This week
Status Date: Wk Ending 5.20.11
26
TrendLast week This week TrendLast week This week
Deliverable Completion Progress
Key Activities for Next Week
Status SummaryYELLOW Status Driver(s):
RICEFW Technical Specs:Q- Conversions:• HR Sub Team- (Pace)
- 10/19 (Completed)- 16/19 (In Progress or Completed)
• Payroll Sub Team- (Pace) - 5/11 (Completed)- 9/11 (In Progress or Completed)
Q- Time Feeder Interfaces:• Time Sub Teams- (Pace)
- 0/9 (Completed ) - 9/9 (In Progress)
RICEFW Build:Q- Conversions• HR Sub Team
- 9/19 (Completed)
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
RICEFW Tech Specs 5/27/2011 15/41 37% 6/17/2011
RICEFW Build 7/29/2011 9/41 22%
ID Description Impact(H/M/L)
Owner Due Date
No New Issues/Risks this week
Issues & Risks – New Only
Continue progressing against published RICEF TD & Build Plan
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
HR Benefits/Self Service – Team StatusCenturyLink SAP Work stream Deborah Freeman, Humberto Saenz, Jesslyna De Rozario
Status Date: Wk Ending 4.8.11
TrendLast week This week
Status Date: Wk Ending 5.20.11
Status Summary Deliverable Completion Progress
Key Activities for Next Week
Status SummaryYELLOW Status Driver(s): Pending wrap up for outstanding
(SAP) Functional Specs (see slide 9) Continued Functional Spec reviews of RICEFW Objects
Completed 3 Functional Specs Approved for TS Removed 1 Conversion Spec from Scope
Conducted vendor meeting with Sedgwick for Workers Comp Eligibility File
Conducted review of Date Mapping and Action/Reason proposals with Business
Reviewed initial portal configuration with HRIS team Created new HRBP and a Admin proxy role based on
feedback on MSS role. Continued work with developer on Pay Change form and
Position Change form – clarify requirements and functional testing.
Position Change form is at 60% complete. The form layout has been completed and tested. Finalize & Execute plan for Date Mapping and
Action/Reason proposals Begin work on non-union pay structures Conduct Functional Design meetings to complete
scheduled functional specs Continue HR field data mapping between PeopleSoft and
SAP Continue Functional testing for Pay Change and Position
Change forms
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
RICEF Inventory Confirmed
03/10/2011 Completed 100% 03/24/2011
FD Completion 04/25/2011 In progress 45% June/July 2011*
Configuration Build 07/05/2011 In progress 22% Aug 2011
ID Description Impact(H/M/L)
Owner Due Date
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Project Systems/Assets – Team StatusCenturyLink – SAP Work stream Zita Scozzari, Cindy Johns
TrendLast week This week
Status Date: Wk Ending 5.20.11
Deliverable Completion Progress
Key Activities for Next Week
YELLOW Status Driver(s): KA Team remains YELLOW until closure of the following solution design issues impacting FD wrap up (see slide 8):
Projects• IT Tools Future State
o Held future state process meetings and confirmed design with team last week
o Additional RICEF Items begin reviewed o Set up meeting with FI team to review financial
process for IT projectso Still need to meet with reporting/metrics team
Assets• Data migration workshops in Seattle last week for SAP
AM and FEV Assets• Cost Center assignment rules on FEV• Field Mapping work for conversion team
RICEF• Working on BidMaster FD’s for enhancements needed to
meet the IT Tools requirements• Working with CATS team on FD to meet requirements for
IT Tools in SAP PS
IT Tools Future State meeting documentation IT Tools Reporting/Metrics Requirements gathering Leased Assets review of process/configuration
requirements once the additional resource is on site Meetings for BMSe functional design for RICEF needed Working with conversion team to provide field mapping
details Work on conversion steps required for projects & assets Work on business processes/sub-processes for training
team documentation Finalize revised PS/AM Configuration Inventory & Build
Plan
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
RICEF Inventory Confirmed
2/28/2011 In progress 100% 4/14/2011
FD Completion 2/28/2011 In progress 50% June/2011
Tech Design 5/6/2011 In progress 30% N/A
Configuration Build 5/27/2011 Not Started
0% N/A
RICEF Dev 7/29/2011 Not Started
0% N/A
ID Summary Description(per SharePoint)
Impact(H/M/L)
Owner Due Date
No new issues or risks
Issues & Risks – New Only
Status Summary
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Projects & Assets – Team StatusQwest HR Work StreamKaren DeRose, Ken Littrell
TrendLast week This week
Status Date: Wk Ending 5.20.11
29
Deliverable Completion Progress
Key Activities for Next Week
Status SummaryRed Status Driver(s): Red pending completion of Network
build plan, as result of Network scope changes.Technical specs: 42% tech specs started (162/383) 4% tech specs approved (15/383)
203 tech specs targeting 5/27 complete 98 tech specs targeting 6/10 complete 82 tech specs targeting 6/17 complete
Key Accomplishments: Assets tech design sessions complete IT Tools: Qwest functional specs drafted; SAP transition complete
[5/25] IT Tools: Qwest functional spec approval; ready for tech spec assessment
[5/27] Tech spec completion
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp
Date
Complete IT Tools Functional Specs
3/18/11 In progress 95% 5/20/11
Design Completion 5/27/11 In progress 31% 6/17/11
RICEFWD Dev 7/29/11 Not started 0%
Integration Test TBD Not started
ID Description Impact(H/M/L)
Owner Due Date
811 Asset Center end-state decision
M Dave Kohler
6/3/11
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Real Estate Integration – Team StatusNeil Leguillow (PM) / John Quickstad (SE)
30 30
TrendLast week This week
Status Date: Wk Ending 5.20.11
Deliverable Completion ProgressStatus Summary Deliverable Completion Progress
Key Activities for Next Week
Status Summary Real Estate has identified a Business Program Manager
and Business Project Managers for each of seven different areas.
YELLOW Status Driver(s): BMSe Functional Spec document revision continues and
requires completion. Location Identifier evaluation provided a read-out
5/18/2011 with final determination pending. ARI meetings continue to address Interfaces between ARI
and SAP for assets and retirements. 15 RICEF elements have been identified in Caliber for BMSe and FLEET; emphasis is on SAP-impacting elements.
Business Benefit Summary: Discussion continues. Resolution anticipated week ending 5/20/2011.
Align with Business Project Managers for timeline, responsibilities, requirements, and next steps.
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
RICEF Inventory Confirmed
4/15/2011 In progress 75%
FD Confirmation 4/22/2011 In progress 75%
Tech Design 6/30/11* In progress 5%
Interface build 7/29/11* Not started 0%
RICEF Dev 7/29/11* Not started 0%
ID Description Impact(H/M/L)
Owner Due Date
No new Risks / Issues this week
30
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
FW/ BidMaster Integration – Team StatusCenturyLink FW/BM Work StreamNeil Leguillow (PM) / Ken Littrell (SE)
TrendLast week This week
Status Date: Wk Ending 5.20.11
31
Deliverable Completion Progress
Key Activities for Next Week
Status SummaryRed Status Driver(s): Approach to recover from Red
Status continues: Rescoping: Work in progress, ETC 5/24/2011, with
impact assessment underway. Reorganizing: Complete. Meeting methodology
adjusted to maximize IT effectiveness, additional assistance on requirements gathering and project management provided.
Replanning: Work in progress, ETC 5/27/2011. Projects to be grouped by internal and external dependencies, and project plan update appropriately. Dependencies and HLEs will then drive dates.
Contract Administration has a high priority, high HLE project with a very rapid timeline. That will reduce ability to focus resources on remaining projects.
Finalize mitigation approach to remediate from RED status. Define and lock down new-and-appropriate scope for Fireworks/BidMaster development.
Continue scheduling and launching appropriate RICEF elements in priority sequence with focus on Interface items and SAP impact. Four sessions currently scheduled.
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
RICEF Inventory Confirmed
2/25/2011 Complete 100% 4/1/2011
FD Confirmation 2/25/2011 Complete 100% 4/8/2011
Tech Design: Test Bed Impact
6/30/11* Underway 26%
RICEF Development: Test Bed Impact
7/29/11* Underway 8%
RICEF Testing ‘DEC 2011* Not started 0%
ID Description Impact(H/M/L)
Owner Due Date
No new Issues this week
31
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
CPR– Team StatusJennifer Kemp, Jake Ford
32
TrendLast week This week
Status Date: Wk Ending 5.20.11
Deliverable Completion Progress
Key Activities for Next Week
Status Summary Task breakdown
Interfaces = 11 Conversion = 11 CPR functionality = 40 (8 tasks added this week!)
Tech Spec development 47 of 62 specs completed (6 completed this week)
Resource management New contractor to arrive Tue 5/31
Development 14 of 62 tasks in development (all tracking green to target
dates) 12 of 62 tasks completed
Other Activities Incremental Use Tax continues to be an issue – several
meetings going on to discuss. Hoping for resolution next week!
Work on interfaces proceeding very will Several major DB changes were implemented in the DEV
environment this week – all went smoothly Met with FW team to discuss Data tables and structure
Development continues on 14 tasks (DB changes and interfaces)
Continue writing specs for CPR application changes Resolve IUT issue On-boarding tasks for new contractor
Deliverable Target CompDate
Progress Status
% Com
p
Revised Comp Date
FD Confirmation 5/1/11 In progress 76%
Tech Design Specs 5/13/11 In progress 76%
Devl / Testing (enh, interfaces) 9/15/11 In progress 19%
Devl / Testing (Conversions) 12/15/11 Not Started
0%
Interface Integration Testing 8/30/11 Not Started
0%
ID Description Impact(H/M/L)
Owner Due Date
Issues & Risks – New Only
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
WTX – Team StatusVern Hatmaker, Jake Ford
TrendLast week This week
Status Date: Wk Ending 5.20.11
Deliverable Completion Progress
Key Activities for Next Week
RED Status Driver(s): Waiting on requirements for an estimated 100 – 150 FI Interfaces;
Delivery date of requirements TBD; Finalize transition plan with Brian Braxton the wk of 5/23 to allow
creation of TD & Build plan for FI Interfaces.
Other Updates Continue meetings with P2P to confirm approach and verify completed TDs Implementation Guides with anticipated merger related changes to EDI810,
850, 860, 855, and 856 sent to vendors on 5/13/11. Continue preliminary design work based on the 8 FD RICEF documents WTX
has been received from P2P team 8 RICEF Objects Identified
7 ( 88 %) – In progress 1 ( 12 %) – Not Started 0 ( 0 %) – Complete
46 Qwest/CenturyLink vendors identified 46 ( 100 %) – Communications Complete 0 ( 0 %) – Connectivity Test Complete 15 ( 33 %) – In progress 3 ( 7 %) – vendor confirmation form outstanding
Begin Vendor Connectivity tests Close out FI Interface transition plan to support ability to
initiate TD
Deliverable Target CompDate
Progress Status
% Comp
Revised Comp Date
EDI Inventory Confirmed
5/1/11 25% 0%
RJ Inventory Confirmed
5/1/11 2% 0%
TD Design 5/1/11 15% 0%
EDI Build 7/29/11 0% 0%
RJ Build 7/29/11 0% 0%
ID Description Impact(H/M/L)
Owner Due Date
FI Technical designs not handed off to WTX.
H TBD
Issues & Risks – New Only
Status Summary
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
• Blueprint Wrap Up Mar 31, 2011(Outstanding: Scope Lock – 4/29)• FD Acceptance Mar 31, 2011(Revised FD complete – end of June 2011 SAP Configuration June 24, 2011 -
non-HCM(HCM Revised Complete – August 2011) Tech Design May 13, 2011(SAP - 6/17 non-HCM; Leg Qwest – 6/17)
Upcoming Milestone(s) Critical Program Dates
Project Start Date: Feb. 21, 2011 Project End Date: Jan. 31, 2012 Tech Design: March – June ‘11 Config Build: March – June ’11 RICEF Build: March – July ’11
Bus Readiness/Training Des.: Feb -Apr’11 Test Preparation: July – Nov ’11 Data Cleansing Prep: Mar. – June ‘11 Cut Over: Dec. 2011 Post-Production Support: Jan -Mar ‘12
SAP Integration Program Revised Schedule -- January 2012 Go-Live
We are here
35
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
SAP Integration: Issue & Risk Mgmt Summary(1 of 3)
36
Past Due Tickets by Priority & Process Area
High – Priority Issues Escalated Items by Process Area
Executive Summary Overall: 171 open items (increase of 17 from we
5.13.11) 14 of the 59 High Priority items are currently in an
escalated status Team Past Due Items (10+ Days)
FI: 19 HR/Payroll: 0 P2aP: 1 KA: 1 Tech Arch: 1 Testing: 0 WTX: 1
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement 37
Past Due Tickets by Process Area – All Types Ticket Age by Process Area – All Priorities
Executive Summary Past Due Tickets: 6 Tickets past due greater than 30 Days [1 - Gen Acct.; 1-TechArch; 1- P2P] Ticket Age by Process Area: 23 tickets older than 30 Days; [11 tickets – Gen. Acct.; 5 tickets KA] 52
tickets older than 60 days [24 tickets – Gen Acct.; 13 tickets - KA]
SAP Integration: Issue & Risk Mgmt Summary(2 of 3)
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Executive Summary Overall: 17 tickets Opened between 5/13- 5/20
SAP Integration: Issue & Risk Mgmt Summary(3 of 3)
Open vs. Closed (Detailed View) – All Types Open vs. Closed (Summary View) – All Teams
38
Confidential and Proprietary - Provide Pursuant to Non-Disclosure Agreement
Wave 1 ERP - Change Control Board Summary
39
Escalated Items by Process Area
Summary Overall: 106 Items reviewed / in progress, 13 CR’s to
be reviewed this week
Status• 13 Intake• 13 Ready for CCB• 12 Approved for Impact Assessment• 75 CCB Approved• 11 On Hold• 7 Rejected
CR’s by Team Real Estate: 1 HR/Payroll: 6 P2aP: 51 KA: 26 Finance: 43 Day 1 & Others: 4
• Process document in Change Control folder:https://ctlqwest/w1erp/Program%20Level%20Docs/Forms/AllItems.aspx?RootFolder=%2fw1erp%2fProgram%20Level%20Docs%2fChange%20Control&FolderCTID=&View=%7bEB551492%2d5243%2d4DDD%2d9E65%2d8550A1D197BE%7d