Central Valley Flood Protection Plan GIS

9
Central Valley Flood Protection Plan GIS Presentation to Flood Emergency Response GIS Subcommittee September 5, 2010 Presented by: Marill Jacobson, GIS Analyst

description

Central Valley Flood Protection Plan GIS. Presentation to Flood Emergency Response GIS Subcommittee September 5 , 2010. Presented by: Marill Jacobson, GIS Analyst. Key Products of the Central Valley Flood Management Planning Program. State Plan of Flood Control Descriptive Document - PowerPoint PPT Presentation

Transcript of Central Valley Flood Protection Plan GIS

Page 1: Central Valley  Flood Protection Plan GIS

Central Valley Flood Protection Plan

GIS

Presentation to Flood Emergency Response GIS SubcommitteeSeptember 5, 2010

Presented by: Marill Jacobson, GIS Analyst

Page 2: Central Valley  Flood Protection Plan GIS

Key Products of the Central Valley Flood Management Planning Program

State Plan of Flood Control Descriptive Document Inventories, describes the State-Federal flood management system Document released in November 2010

Flood Control System Status Report Describes how the facilities are working Document release December 2011

Central Valley Flood Protection Plan Plan adopted by the Central Valley Flood Protection

Board June 29, 2012 Includes 5 Volumes of Technical Analysis and a

Program Environmental Impact Report. Updated every five years

Page 3: Central Valley  Flood Protection Plan GIS

Describes SPFC facilities in the CVFPP Planning Areas

Geospatial Data Levees, Weirs, Flood Control

Structures, Pumping Plants

SPFC Map Book Based on O & M Manuals CD with Interactive PDF Maps

Updated August 2012 NRO: \\P:\CVFPP\SPFC_MapBook Shared Drive:

\\Gis1\DFMLAN\SFPO\data\Documents\SPFC_Descriptive_Document\Final_201011

State Plan of Flood Control (SPFC)Descriptive Document

Page 4: Central Valley  Flood Protection Plan GIS

Flood Control System Status Report (FCSSR)

How are the SPFC Facilities working.

Urban (ULE) and Non-Urban Levee Evaluations (NULE) As of August 2011

ULE & NULE Points of Interest 2009 levee and facility inspections Early Implementation (EIP) and

Board Projects

Page 5: Central Valley  Flood Protection Plan GIS

Central Valley Flood Protection Plan(CVFPP)

Compares 3 approaches to fixing SPFC facilities

Describes the State System-wide Investment Approach (SSIA), the State preferred plan.

Includes 5 Volumes of technical analysis results and the Program Environmental Impact Report (PEIR).

Page 6: Central Valley  Flood Protection Plan GIS

CVFPO Geodatabases Geodatabases for each of the primary documents located:

\\GIS1\Staff Data\CVFPO\Data\GIS_Data\Geodatabases

Additional geodatabases for the ULE/NULE Point of Interest data

Page 7: Central Valley  Flood Protection Plan GIS

CVFPO - ArcGIS, Map Documents Map Documents used to create the figures for the CVFPP

Reports are located: \\Gis1\Staff Data\CVFPO\Data\GIS_Projects

Page 8: Central Valley  Flood Protection Plan GIS

Implementation Activities

2009 2010 2011 2012 2017

Milestone DocumentKey:

-- Feasibility Studies, Environmental Compliance, Design, Construction

BoardAdoption

ProgressReport

Draft CVFPP

CVFPP 5-Year Updates

Central Valley Flood Protection Plan (CVFPP)-- 2012 Plan

Flood Control System Status Report

2017Update

State Plan of Flood Control Descriptive Document

Schedule And Major Products

Page 9: Central Valley  Flood Protection Plan GIS

For more informationCVFMP Website: www.water.ca.gov/cvfmp