US Army Corps of Engineers

BUILDING STRONG®

Center Hill Dam Safety Rehabilitation Status Update – Team Cumberland 6 April 2016

Linda H. Adcock

Project Manager

Nashville District

BUILDING STRONG®

Rehabilitation Project Scope

Main Embankment & Left Rim Grouting and Barrier Wall

Legend

Grouting FY08-11

Barrier Wall FY12-15

RCC Berm FY16-19

Saddle Dam RCC Berm

BUILDING STRONG®

Alluvial Soils

Grout Curtain and Barrier Wall

Grout Curtains

Concrete

Barrier Wall

Lake

Limestone Foundation

BUILDING STRONG®

Grouting and Barrier Wall

Profile View – Looking DS

BUILDING STRONG®

Barrier Wall Geometry

10.5’ 2.72’

Hermitage

Cannon LS

Upper Carters LS T3

Lower Carters LS

Lebanon LS

307’

175’

Plan View

Profile View – Looking DS

BUILDING STRONG®

Wall Excavation-BC50 Cutter

Pump for

slurry

circulation

and removal

of cuttings

Onboard instrumentation (inclinometers) for

monitoring orientation

Cutter head fitted with rock picks

and soil cutters

BUILDING STRONG®

Center Hill Dam 1992

BUILDING STRONG®

Existing Saddle Dam

and Fuse Plug

BUILDING STRONG®

RCC Berm at Saddle Dam

Existing

Fuse Plug

Rock Fill RCC

Berm

Section View

EL. 658.0

RCC

Berm Existing Saddle Dam

BUILDING STRONG®

Completion and Pool Raising Activities Center Hill Dam Safety Modification Pool Raising Plan/Schedule

J A S O N D Jan F M A M J J A S O N D Jan F M A M J J A S O N D Jan F M A M J J A S O N D Jan F M A M J J A S O N D

RCC at Elev. 658

(80% confidence 1 July 2018)

Berm & LR Solicitation Construct Saddle Dam RCC Berm & Left Rim Stabilization

& Source Selection

Fiscal Closeout

Sep 2019

Calendar Yr. 2019

Conduct PIE Risk Estimate of Barrier Wall,

Summary Report of Environmental

Commitments

Potential

Incremental

Pool Raise

Return

Full

Pool

Conduct PIE Risk Estimate of Saddle Dam with Berm,

Compile and Approve Report, revise DSAC Rating

Barrier Wall Documentation

for Evaluation and Fiscal

Closeout

Barrier Wall Physical

Completion

Cal Yr. 2015 Calendar Yr. 2016 Calendar Yr. 2017 Calendar Yr. 2018

BUILDING STRONG®

BUILDING STRONG®

Questions?