• Objectives• Global analysis• Activities analysis• Files delay in the design department• Final suggestions
• On average among all the late files :– 3 days to create a file– 2 days to go from the HQ to the « Cellule
entrée »– 3 days to arrive with the computer data to
the factory
• About the “pontage”– Data errorOr– Process error (the file is passed to the factory
before the computer map)
• 3.5 days to complete the design study
Récep-tion
com-mande
Dossier créé
Sortie "Cellule Entrée"
Sortie BE
Dossier ponté
Arrivée atelier
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
0.0
3.2
5.2
8.7
11.711.3
Ave
rage
cum
ulati
ve ti
me
betw
een
mile
ston
esGlobal analysis
Création/O
uvertu
re dossi
er
Traite
ment Cellu
le entrée
Bureau d'étude
Fabric
ation (esti
mée)
Temps de M
AD (esti
mée)0%
5%
10%
15%
20%
25%
19%
12%
21%22%
10%
Time spent in each department • Too much time spent in the 2 first tasks
• Time spent in the design department and the factory is only about 43% of the total time
Global analysis
Suggestions
• Reduce the stages before the design department– Too many people involved (4 departments)– Too long (5 days, 31%)– Could help to reduce misunderstandings
• 3 days to set the plans on the computers– Could it be reduced?
« BE-Chiffrage » Activities Analysis
• The major part of the time is lost (47%)
• Unjustified modification:– Errors in design– No Reference on drawings– Unclear Needs
From 9:00 to 12:00
Time distribution of the nomenclature department technician
« Chargé d'Affaires » Activities Analysis
• One fifth of the time is lost (21%)
• Lost time due to :– Information missing– Components missing– Calls to correct erroneous
information
Time distribution of the business manager
From 8:33 to 12:00
Suggestions
• Improve the quality of the information exchange with the design department– No error in the drawings– Less missing information or components
Files delays in the design department
• The more files to process in a day the higher the delay– 10 files ≈ 15% files are late– 30 files ≈ 45% files are late
• Quotes are more often late than orders– 40% of the quotes are late– Vs 15% for the orders
• 30% of the files are at least one day late
Day Number of files
On time quotes
On time orders
On time files
Thursday 8 80% 100% 86%
Friday 31 38% 80% 54%
Monday 14 86% 100% 92%
Tuesday 7 100% 80% 86%
60 60% 86% 71%
• Lack of quality in transmitting information affects differently the departments, on average:– Every file in the nomenclature department is delayed by 53 min– Every file in the Setting-up department is delayed by 117 min
• Top 4 causes of delays is also changed accordingly to the department
Part of the fileMissing
information occurrence
Erroneous information occurrence
Expected delay per file
Chiffrage42 files
av. Time :193 min
Clarté de l'expression du besoin 5% 7% 19 min 36%
Couleur - Traitement de surface 10% 2% 14 min 27%
Plan de coupe 7% 12% 11 min 21%
Dimensions équipement 12% 5% 2 min 3%
Total 53 min
Implantation23 files
av. Time :784 min
Plan d'implantation informatique (transmis) 13% 4% 42 min 36%
Spécifique identifié 13% 4% 38 min 32%
Clarté de l'expression du besoin 35% 0% 27 min 23%
Couleur - Traitement de surface 13% 9% 6 min 5%
Total 117 min
Files delays within the design department
Final suggestions (1/2)
• Reduce the delay of the files in the design department– Every file is delayed by 53 min or 117 min depending on the dep.
• What could be the main causes to tackle in the design department?– The clarity of the need expression (19 min & 27 min)– The surface treatment & color (14 min & 6 min)– Drawings on computer (42 min)
Final suggestions (2/2)
• Reduce the stages number before the design department– 4 departments involved, 5 days long
• Reduce the time needed to get the drawings on the computer– 3 days long
• Improve the quality of the information exchange with the design department– 47% of the technician time & 21% of the business manager time is “lost”