CED 2 Final Presentation_Compile PDF

download CED 2 Final Presentation_Compile PDF

of 133

description

Useful for UTP Civil Engineering Final year Students for their capstone onshore projects.

Transcript of CED 2 Final Presentation_Compile PDF

  • CONCEPTUAL

    DESIGN

    SUPERVISOR : DR TEO WEE

    MUHAMMAD SYAFIE BIN MAZLAN 12050

    ABDULLAH SOFIY BIN MANSOR 11848

    ABDUL HALIM BIN ROSLY 11840

    NORAZY SHAKILA BINTI MD. SALLIH 12124

    NURUL NASYIHAH BINTI HAMBALI 12168

    By Consultant :-

    For Client :-

  • ORGANIZATION

    CHART

  • PROJECT OVERVIEW

  • PROJECT DESCRIPTION

    Office Building of 13-storey at Ara Damansara, Mukim Damansara, Daerah Petaling, Selangor consists:- Basement - 2 levels of car park, Level 1 - Auditorium, Cafeteria, Childcare, Clinic, Multipurpose Shop,

    Office Space, Prayer room Level 2-12 Office spaces

  • SITE LOCATION

  • FOUNDATION AND

    GEOTECHNICAL

    ENGINEER PART

    1. SOIL INVESTIGATION 2. FOUNDATION 3. BASEMENT WALL AND SYSTEM 4. PILE CAP 5. GROUND BEAM AND GROUND SLAB 6. OTHER CONSIDERATION

  • 1. SITE INVESTIGATION

    Soil constitutive properties Design consideration for such soil

    properties Risk and integrity of the foundation

    on such soil properties

  • Soil constitutive properties

  • Soil constitutive properties

    SPT from borelog

    Standard SPT

    Allowable bearing capacity

  • Design consideration for such soil properties

    Platform level is 17-18m.

    Average surface level is 53m, we have to cut the soil up to the platform level.

    The main constituent of soil is silty sand. Major portion is silt.

    Minor portion is sand.

    The strength of sandy soil is represented with friction angle (). Pure silts are frictional material and for all practical purposes, it behaves as sands. No clay present.

    Ground water table is very high = 42m

  • Design consideration for such soil properties

    Assumptions

    SPT value from the borelog are conducted using safety hammer with 70% energy ratio.

    Highest GWT after excavation is equal to platform level.

    Based on Standard SPT:

    Friction angle, = 38

    Relative density = 0.85

    Unit weight = 22kN/m3

    Since we decided to use concrete spun pile:

    Lateral earth pressure coefficient, K = 1.0-1.5

    Pile skin friction angle, =

  • Risk and integrity of the foundation on such soil properties

    Risk Risk assessment Propose mitigation

    High ground water table Causes wet excavation, pile driving and ground beam construction.

    Adoptions of water proof reinforce concrete basement wall, drainage culvert and installation of sump pump.

  • Risk and integrity of the foundation on such soil properties

    Risk Risk assessment Propose mitigation

    Absence of bed rock Cause excessive settlement of pile.

    Pile design based on both skin friction and tip bearing capacity.

  • Risk and integrity of the foundation on such soil properties

    Risk Risk assessment Propose mitigation

    Main soil composition is silt Silt can get loose easily. Static compaction is done to the soil before installation of piles.

  • 2. FOUNDATION

    Type of foundation use Design of the foundation and type Risk assessment of the foundation

    chosen

  • Type of foundation use Silty sand load bearing capacity = 144kN/m2

    Maximum building load = 180kN/m2

    Shallow foundation is not sufficient, hence deep foundation is needed.

    Type = spun pile

    Supplier = Industrial Concrete Product Berhad(ICP)

    Pile shoes = open ended

    Installation method = jacked in

    Codes applied: BS EN 1997-1:2004 Eurocode 7: Geotechnical design

    solution Section 7.1 1(P)

    BS EN 1997-1:2004 Section 7.4.2 Design Consideration 4(P)

  • Design of the foundation and types

    Using Meyerhof equation correlated with SPT value

    Result:

    Spun pile class B(effective prestress=5N/mm2)

    Diameter = 500mm

    Thickness = 90mm

    Length = 18m (12m + 6m)

    Spun pile individual capacity = 207ton

  • Design of the foundation and types

  • Design of the foundation and types

    Cross section detail of the ICP piles

  • Design of the foundation and types

    Bonding of ICP pile into pile caps

  • Design of the foundation and types

  • Risk assessment of the foundation chosen

    Risk Risk assessment Propose mitigation

    Improper welding of pile during splicing.

    Pile performance will be affected and load transfer will be disturbed.

    Site supervision must ensure that the welding thickness must not be less than 6mm and after done with the welding, it must be cooled at least 5 minutes before applying the anti rust protection paint.

  • Risk assessment of the foundation chosen

    Risk Risk assessment Propose mitigation

    Structural damage to the pile head or pile toe.

    This might be due to overdriving of pile. The existence of boulder can cause spalling, cracking or breaking of pile structure.

    Pile capacity must always be checked and ensure during pile driving, the driving force does not exceed the pile capacity. It s useless to force the pile into the soil while damaging it. Practice good driving technique.

  • Risk assessment of the foundation chosen

    Risk Risk assessment Propose mitigation

    Expose end of pile reinforcement after pile trimming provide hazard to the working personnel.

    Potential to cause injuries.

    Use protection caps on the bars after pile trimming and before placing foundation concrete.

  • 3. BASEMENT WALL

    AND SYSTEM

    Type of basement wall and system chosen Design consideration of the basement wall

    and system Sequence of work and risk assessment of

    the basement wall and system

  • Type of basement wall and system chosen

    Total area = 14, 030 m2.

    Depth of excavation = 4.59m +3.425m = 8.015m

    Excavation volume= 8.015m X 14, 030m2 = 112,450 m3.

    Code used:

    BS 8004: 1986 Code of practice for foundations

    BS 8002: 1994 Code of practice for earth retaining structures

    BS 8110: 1985 Structural use of concrete

    DFCP 4: Drilling fluid material - bentonite

  • Type of basement wall and system chosen

    Based on BS8102, the function of basement allowed us to design based on Type B.

  • Type of basement wall and system chosen

    Support system = braced

    Why not anchored?

    problem in maintenance in long term. (BS8081:1889 Code of Practise for Ground Anchorages)

    If the local authorities require to be removed, then it may pose problems if the system has not been proven at site to be fully removable.

    Approval from the adjacent owners should be acquired if there is encroachment of ground anchors into adjacent properties.

    Leakages and loss of fine through drill holes need additional precautionary measures in the construction.

  • Design consideration of the basement wall and system

    Concrete compressive strength = 30N/mm2

    Reinforcement yield strength = 410N/mm2

    Soil equivalent fluid pressure = 60psf/f = 293kg/m2 per meter

    Total service level vertical dead load on wall = 481 kN/m

    Total service level vertical live load on wall = 286 kN/m

    Design assumption Design wall with fixed base

    Ground water table is at platform level for conservative design.

    Use 2ft additional soil surcharge to account for compaction pressure.

  • Design consideration of the basement wall and system

    Dimension of diaphragm wall

    Basement depth = 8m

    Depth of diaphragm wall = 14m

    Thickness = 600mm

    Vertical reinforcement = 20mm diameter at 200mm c/c

    Horizontal reinforcement = 14mm diameter at 300mm c/c

    Length of interval for alternating diaphragm wall excavation = 5m to 7m

  • Design consideration of the basement wall and system

    Method of construction = top down

    Advantages: reduces the time Reduced

    settlement. saves the cost of

    formwork.

  • Sequence of work

    Earthwork Diaphragm

    wall Bored, casing and spun pile

    Stanchions Superstructure

    and substructure Top down

    construction sequence

  • Sequence of work

    Diaphragm wall sequence

    Install guide wall at 1.5m to 2m depth and 0.6m wide.

    Trench excavation and deposit soil to a holding tank

    Install rebar cage

    Checking verticality by Coden Test.

    Tremie concrete.

    Disposal of excavated soil from holding tank.

  • Risk assessment of the basement wall and system

    Risk Risk assessment Propose mitigation

    Working inside the excavation basement area

    Confine dark space give minimum space for error. Slight collision between cranes with the stanchions can cause disasters.

    Implement systematic working condition with extra precaution. Space opening must be sufficient for safe mobilization of crane. Limited access and number of workers inside the basement for safety reason.

  • Risk assessment of the basement wall and system

    Risk Risk assessment Propose mitigation

    Cold joint due to the interval concreting.

    Presence of small void which can allow ground water to pass thru the basement wall.

    If the crack is minute, it can be seal with thin layer of concrete sealant. Sump pump need to be installed inside the basement in case if the water intrusion is unstoppable.

  • 4. PILE CAP

    Typical design of pile cap Design of at least 50% of the total

    types of pile cap Risk assessment and integrity of the

    pile cap

  • Typical design of pile cap

    Code used:

    BS 8110: 1997 Structural use of concrete

    BS 5950 Structural steel design

    Truss method

    Check:

    Shear capacity

    Punching shear

  • Typical design of pile cap

    Design criteria: Concrete strength , fcu = 30N/mm

    2

    Reinforcement steel yield strength, fy = 460N/mm2

    Pile capacity = 2129 kN

    Size aggregate = 20mm

    Top and side cover = 50mm

    Bottom cover = 75mm

    Concrete c = 1.5

    Steel s = 1.05

    Concrete density = 24 kN/m3

  • Typical design of pile cap

  • Typical design of pile cap

  • Design of pile cap methodology or construction sequences

    Formwork and reinforcement bar are placed

    Ready mix concrete is transfer into the formwork. Various method of transferring can be done which are by using excavator bucket, specific concrete bucket or boom of pump truck.

    Then the concrete is vibrated using vibrator to reduce the air voids

    The concrete is allowed to harden.

  • Risk assessment and integrity of the pile cap

    Risk Risk assessment Propose mitigation

    Shear failure and punching failure in pile cap.

    This failure can be mitigate if the pile cap have enough thickness and reinforcement inside it.

    Shear and punching failure should be checked and provide sufficient reinforcement bars.

  • Risk assessment and integrity of the pile cap

    Risk Risk assessment Propose mitigation

    Eccentric loads from axial column

    Eccentricity induced moment.

    Column should be checked for verticality during construction.

  • 5. GROUND BEAM AND

    GROUND SLAB

    Typical design of ground tie beam and ground slab

    Design details and types of ground beam and ground slab

    Risk assessment of the designed ground beam and ground slab

  • Typical design of ground tie beam and ground slab

    Code use:

    BS 8110: 1997 Structural use of concrete

    BS 5950 Structural steel design

    Two way suspended slab 8.2m x 8.2m

  • Design details and types of ground beam and ground slab

    Concrete strength = 30N/mm2

    Reinforcement strength = 460 N/mm2

    Slab thickness = 300mm

    Slab area = 8.2m x 8.2m = 67.24m2

    Beam width = 800mm

    Beam thickness = 900mm

    Beam length = 8200m

  • Design details and types of ground beam and ground slab

    Slab reinforcement details:

    X direction = T12-150c/c

    Y direction = T12-150c/c

    Beam reinforcement details:

    Top portion = 3T20

    Bottom portion = 3T25

    Link = 2T8 200c/c

  • Risk assessment of the designed ground beam and ground slab

    Risk Risk assessment Propose mitigation

    The formwork at the bottom of the slab is difficult to remove.

    Due to the weight of beam and friction between soil underneath and beam.

    Provide extra thickness for bottom concrete cover which is 75mm. Eliminate the bottom formwork.

  • 6. OTHER

    CONSIDERATION

    Waterproofing method Cold joint treatment and waterstop Risk mitigation of the chosen

    method

  • Waterproofing method

    High ground water table exert uplift pressure to the basement slab and beam

    Uplift forces = 433,000kN

    Self weight of beam and slab = 154,000kN

    Passive method = diaphragm wall

    Active method = sump pump

  • Waterproofing method

    Sump pump specification Type: Submersible Sump basin dimension: 0.6m

    diameter x 1m depth Individual capacity: 100 liters Service life: 15 years Head pressure: 10m Suction capability: 0.5

    horsepower (400W) Periodic maintenance: annually Daily operation using main

    power supply but has backup battery for power outage

    Additional features: - High water alarm - Automatic operation

  • Waterproofing method

    9 units of sump pumps

    Distance between each sump pump is between 30m to 70m.

    Location of the sump pump

  • Waterproofing method

    Installed along the interior perimeter of the basement wall.

    Total length is 520m.

    The drainage pipe used is WaterGuard.

    It includes a wall flange that extends up slightly from the drainage system.

    French drain system

  • Cold joint treatment using waterstop

    Hydrophilic waterstop. Exposure to water makes the material expand

    dramatically Enough to create a compression seal Material = chloroprene rubber.

  • Risk mitigation of the chosen method

    Risk Risk assessment Propose mitigation

    Small silt can clog the WaterGuard passage inside the French drain.

    This prevent sump pump from pumping ground water out from the basement.

    Periodic maintenance must be done annually to ensure the system works. Clogged WaterGuard must be replaced with the new one.

  • SUPERSTRUCTURE

  • BS 6399 : part 1 : 1984

  • Loading

    Dead Load

    concrete 2400 kg/m

    Metal deck 13.6 kg/m

    Column Variable depending on type

    Beam Variable depending on type

  • Loading

    Live Load(kn/m)

    General area 2.5

    Balconies 4

    Store 4

    Toilet 2

    Electric Room(AHU) 2

    Stair 4

    Harvesting tank 29.43

  • Typical floor layout

    STAIRS

    AHU SHEAR CORE WALL

    TOILET

    AHU BALCONY

    STORE

    STORE

    STAIRS

    BALCONY

  • Slab System(Bondeck)

  • Bondeck(properties)

    Section properties per m width

    Thickness (mm)

    Grade(mpa) Section modulus area (x10mm/m)

    Cross sectional area (mm/m)

    Second moment (x10^4 mm^4/mm)

    Weight (kg/m)

    1.00 550 16.69 1678 64.08 13.6

    Continous span

    No prop Concrete thickness 2960

    Continuos span 1 prop 150mm

    5930

    Steel conform to BS EN 10147

    Fire resistance up to 120 minutes

  • BONDECK(reinforcement bar)

    Help in supporrting load (longitudinal)

    Shrinkage and temperature effect (transverse)

  • Bondeck(piping)

  • Bondeck(electrical wiring)

  • BEAM

    (Based on BS 5950)

    Universal beam

    1)UB 533 x 210 x 92

    2)UB 610 x 229 x 125

    3)UB 610 x 305 x 149

    4)UB 914 x 305 x 224

    5)UB 1016 x 305 x 314

  • Beam layout

  • UB 533 x 210 x 92

  • UB 610 x 229 x 125

  • UB 610 x 305 x 149

  • UB 914 x 305 x 224

    (Floor 9)

  • UB 1016 x 305 x 314

    (floor 13)

  • Column

    (based on BS 5950)

    Universal column

  • Column (core)

  • Column (critical)

  • Column

    (External)

  • Column

    GROUP

    COLUMN

    FLOOR

    1-5 6-10 11-13

    Core Column 356 X 406 X 467 305 X 305 X 118 254 x 254 x 89

    External Column 356 X 406 X 467 356 X 368 X 177 356 X 368 X 129

    Critical Column 356 X 406 X 467 356 X 406 X 467 356 x 368 x 177

  • Lift shear core

    0.98 kn/m

    Wind load calculated based on MS 1553 2002

    Assumption that the wind load will all be taken by the shear core wall

    Lift motor room load of 7.5kn/m

  • Lift Shear Core dimension

    Lift shear core Length(m) 2.4

    Thickness/ width(m)

    0.4

  • Lift Shear Core Rebar

    4x1T25(corner) x 2x13T25(internal) x 2x6T25(side)

  • Staircase

    Type 1

    Type 2

    Type 2

  • Staircase

    G

    R

    T

    Riser(R) = 166.67 mm Tread(T) = 255 mm Going(G) = 250 mm

  • Staircase

    MAIN REBAR SIZE

    TYPE 1 T12-300 T8-150 SC 1 & 2

    TYPE 2 T12-250 T8-125 SC 6 & 7

  • CONNECTION

  • Base plate to column

    UC 356 x 406 x 467

    Dimension

    = 58 cm x 57 cm

    Thickness = 7 cm

    Bolt grade of 4.6 with 20mm diameter

  • Beam to column

    One example dimension for UB 533 x 210 x 92 9 bolts M22 grade 4.6 o 6 bolts at column o 3 bolts at beam

  • Splice

    Splicing UC 356 x 406 x 467 to same size

    Plate connector length = 450 mm Width connector length = 450 mm Thickness plate = 35mm Web cover plate width = 230 mm 4 no M20, 8.8 grade bolts

  • Splice

    Splicing UC 356 x 406 x 467 to UC

    305 x 305 x 118 Connector plate length of 320 mm Width of connector plate of 125

    mm Thickness of connector plate of 15

    mm Web cover plate width of 165 mm Use M20, 8.8 grade of bolt

  • Risk assesment

    Risk Risk assesment Mitigation

    Fire

    Affect structural ability

    Danger to human lives

    Intumescent coating that can upstand fire up until 120 minutes

    Corrosion

    Affect structural ability

    Spread more into the member

    Coat with coating such as paint

  • Lintel

  • Lintel

    Height(mm) 60 110 210 Thickness

    (mm) 3.0 3.0 3.0

    UDL can sustained

    (kn/m) 4 8 10

  • INFRASTRUCTURE

  • Source: Perbadanan Urus Air Selangor (PUAS) BHD.

    Main Building (13 Storey Building) : = 29125 m2

    WATER DEMAND

    Normal Usage (Drinking) : (PUAS) = 291 250 L/day = 291. 25 m3/day

    For Hose Reel and Fire Hydrant Usage: (UBBL) = 12133 L/day = 12.133 m3/day

  • STORAGE TANK STORAGE TANK

    DIMENSION : 10000 mm x 8000 mm x 6000 mm

    Designing storage tank for 3 days usage : Normal usage = 873.75 3 Fire Hydrant and Hose Reel = 36. 4 3

    TOTAL VOLUME OF WATER = 910.15 Volume of water per 1 tank = 456 3

    No of tanks : 2

    Using RC storage tank :

    Concrete Plinth : 300 X 500 ( Gap = 1m)

  • STORAGE TANK WATER RECTICULATION

    Standard Code : MS 1058: Part 2: 2002 Dimensioning:

    Source: Hazen-Williams Equation

    Diameter : 110 mm Flow velocity : 0.17 m/s Length : 100 m Pipe head loss : 0.35 Implement pumps to water tank

    --> Hazen Williams Equation

    Type of Pipe = HDPE PIPE

  • SEWERAGE CAPACITY

    Source: Indah Water Konsortium)

    PE calculated: = 1446 person Discharge Produced: = 0.225m3/day.person * 1380 = 310.5m3/day = 3.593 m3/s

  • STORAGE TANK SEWERAGE PIPE Standard Code : MS 1228 : 1991 : MS 1228 C1. 4. 3. 3 (Hydraulic Design)

    Slope (%) 0.4 %

    Sewer Line Diameter (mm) 100

    Source: Indah Water Konsortium ( IWK) Dimension Selection:

    Diameter, Dia = 200 mm Slope, S = 1: 100 Material used: HDPE Pipe

    = where = 3.59

    3 m3/s Peak Factor = 1.164

    = . m3/s

    Using V = 0.45 m/s : From Q= AV A = .

  • STP (1 km from

    the site)

    Project Site

    Manhole: - At every change of direction (at 100m) - No of manhole = 6 - Min diameter = 225 mm

    Sewerage Tapping Point

  • STORAGE TANK DRAINAGE SYSTEM

    OUTER DRAIN

    Minor System Design ARI : 10 years ( 10 = 315.33 mm/ hr)

    Major System Design ARI : 50 years ( 50 = 385.25 mm/ hr)

    ANNUAL RAINFALL INTENSITY (Source : MSMA)

    INNER DRAIN

    =

    360 ------------- Equation 14.7

    Note: C= 0.09

    Area = 1.4 ha

    Q10 = 1.1036 m3/s

    = 38.998 ft3/s

    Q50 = 1.3484 m3/s

    = 47.646 ft3/s

    Area = 0.19 ha

    Q10 = 0.1498 m3/s

    = 5.293 ft3/s

    Q50 = 0.1830 m3/s

    = 6.466 ft3/s

  • Outer Drain Inner Drain

    Width (m) 0.9 0.45

    Height (m) 0.75 0.45

    Freeboard (m) 0.05 0.05

    Flow Capacity ,q (m3/s ) 1.45 0.19

    Velocity (m2/s) 2.29 1.38

    q = A R2/3 S1/2 n

    Drain capacity > Q peak OK

    V = Q A

    Type of Drain : U- Drained Size Material : Concrete Supplier : OKA COOPERATION BHD.

    Slope of Drain = 0.005

  • STORAGE TANK HARVESTING TANK

    2 harvesting tank Dimension : 3000 x 3000 x 3000

    Volume Capacity = 273 x 2 tanks = 54 3 Maximum volume of rain water collected = 32.19m3 < 54 3

    OK

  • PAVEMENT

  • PARKING LOT PAVEMENT

    Pavement type: Asphalt Concrete Base Pavement

    Subgrade class: moderate

    4cm

    9cm

  • DCA REQUIREMENT

  • AIRPORT REQUIREMENT

    2.96km

    3.5km

    Inner horizontal surface

  • AIRPORT REQUIREMENT

    Elevation of Inner Horizontal Surface: 27m MSL

    Requirement for obstacles height: 45m

    PL

    Inner Horizontal Surface

    Height requirement

    Height : 53.5m

    MSL

    27m

    45m

    17.8m

  • ASSESSMENT

  • TRAFFIC IMPACT ASSESSMENT (TIA)

    Year Volume (veh/hr) LOS

    2010 8 233 C

    2012 9 283 D

    2015 11 113 D

    2020 15 000 E

    Census Station : Kuala Lumpur-Subang Airport (BR802)

    Mitigation for year 2020: Add one lane per

    direction. AND Increase lane width LOS : D

  • ENVIRONMENTAL IMPACT

    ASSESSMENT (EIA)

    Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 1987.

    Required area: 500 000 squared-metre

    Area of project: 14 030 squared-meter

    No EIA is required

  • ENVIRONMENTAL IMPACT

    ASSESSMENT (EIA)

  • MATERIALS USED

  • STEEL FRAME

    Advantages

    Shorter build times

    Reduced site labour

    Superior quality

    Reduced environment disruption to site.

  • LYSAGHT BONDEK

    Excellent spanning capacities for greater strength and less deflection

    Acts as permanent formwork with minimal propping and no stripping of formwork is required

    Fast and easy to install with less handling required

    Works as composite slab saving on concrete and reinforcement costs

    Ribs at 200mm centres creating a safe working platform with slip resistant embossments

    Advanced design for fire resistance

  • HOMOGENEOUS TILES

    Tougher tile because lower water absorption rate & higher density.

    Use in:-

    Staircase

    Balconies

    Toilets

  • GRANITE TILES

    Easily remove stains

    Wide availability in market

    Use in:-

    Staircase

    Floor outside the lift

  • CEMENT RENDER

    Solid plastering

    Often textured, colored, painted after application.

    Use in:-

    AHU

    Store

  • FLOOR SCREEDS/CARPET

    Screed directly bonded to base

    Carpet offering warmth

    Use in:-

    Office area

  • FLOOR DROPS

    To avoid water flow out to other area in building.

    Examples:

    Toilets (50mm drop)

    Balconies (100mm drop)

  • BUILDING SET-BACK

    Required distance that a building must be located away from the streets, easements, and other structures.

    3500mm setback

  • SCHEDULING

  • CED 1

  • CED 2

  • SUBMISSION SCHEDULE

  • CONSTRUCTION SCHEDULE

  • MINIMIZED

    WASTAGES IN

    CONSTRUCTION

    PROJECT

  • Construction Waste

  • Construction Waste

    A waste allowance is generally included within the order to account for design waste and construction process waste.

    Construction waste categories:

    Generated by design activities.

    Generated by construction activities.

  • Typical Malaysian Contractors Material Wastage Allowance

    Material Wastage Allowance

    Concrete 7%

    Rebar up to 16mm 8%

    Rebar more than 16mm 15%

    Formwork 12%

    Cement screed 30%

    Red bricks wall 12%

    Metal roofing 5%

    Tiling 8%

  • MINIMIZE CONSTRUCTION WASTE

    An effective effort in minimizing wastage in construction can:

    Make significant savings

    to the client, contractors and the environment

    Divert a high percentage of all construction waste materials from the landfill and recycled into new products.

  • BUILDING ECONOMICS

  • BUILDING COSTING (June 2012) SECTIONS COST (RM)

    Steel beam RM6,338,588.26

    Steel Column RM 75,232,858.80

    Lysaght Bondex RM 497,605.45

    Spun Pile RM 824,100.00

    Pile Cap RM 90,159.00

    Water tank RM20,875.20

    Harvesting Tank RM2,635.20

    Water Reticulation Pipe RM 2,300.00

    TOTAL RM83,009,121.91

    MAIN TOWER ONLY:-

    WHOLE PROJECT AREA MAIN TOWER AREA

    SECTIONS COST (RM) COST (RM)

    Basement walls RM3,763,327.71 -

    Excavation RM11,245,045.00 RM1,697,152.21

    TOTAL RM14,571,572.71 RM1,697,152.21

    MAIN TOWER & WHOLE AREA:-

  • BUILDING COSTING (June 2012)

    ESTIMATION TOTAL COST OF MAIN BUILDING:-

    RM140,000,000

  • THANK YOU

    By Consultant :-

    For Client :-