CDR Report Sample for Civil Engineer PDF - CDR Australia

25
-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------ Welcome To CDRAustralia.org CDR Report Writing Service Provider

Transcript of CDR Report Sample for Civil Engineer PDF - CDR Australia

Page 1: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

Welcome

To

CDRAustralia.org CDR Report Writing Service Provider

Page 2: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

CAREER EPISODE 1

I. Introduction

CE1.1 My first project experience is a project that I did while working at Qatar Building

Company (QBC) when I worked as the Technical Engineer in the Estimation

Department. The project was to prepare a sewer drainage line for the Public Works

Authority, (PWA), also known as ASHGHAL. We had participated in the tendering

process and won the tender. I worked on this project between June 2014 to December

2015.The project was located at Najma District in Doha Qatar in Zone 26. The Project

entailed upgrading of the existing sewerage network in Najma area which involved the

removal and replacement of 19.5km pipelines (200Ø - 1200Ø). My assignment was to

design the project and ensure the sewer was flowing uninterrupted.

II. Background

CE1.2 This project was awarded to rehabilitate the Existing Sewers within Doha by the

ASHGHAL or the Public Works Authority, (PWA), who were the client. The project was

divided into four sections namely Najma-Al Hilal(Package A) Al Arab-Al Kharaib

(Package B).The other section was Najma-Al Hilal Sub (Package C) and Al Arab-Al

Kharaib (Package D). The project involved the design of the main lines and branches to

ensure it was allowing the flow and at the same time it was capable of handling the

volume generated in central Doha. I worked on the design, implementation, and

commissioning of the project.

CE1.3 The goal of this project was to increase the capacity of the existing sewer so that it

could serve several households. It was to replace the current new work with bigger

diameter pipes that could allow the flow through gravitational force. This entailed

excavating the trench and giving it gently gradient to allow the flow of waste water. The

other objective of the project was to ensure the project was completed on time within

the design specifications that was communicated by the ASHGHAL. The last objective of

the project was to carry out the plan and commission it on time since it was overdue

Page 3: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

and it had been delayed previously. Below is the organizational structure that was used

to manage the implementation of this project.

Figure 1: Organization structure.

CE1.4 Below is the statement of my duties as the Technical Engineer.

• Designing of the sewer lines that included determination of the right diameter, the

gradient of the pipe, velocity among other parameters.

• Advice on the best route for the pipeline to serve more areas as much as possible.

• I was responsible for the preparation of the documents and other logistics in the

project to ensure the success.

• I participated in brainstorming of the project after I encountered some challenges.

• I made sure safety, environmental and ethical issues was followed at the site to the

later.

• I interacted with the suppliers on economic issues related to the supply of the raw

materials needed for the site.

Page 4: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

III. Personal Engineering Activity.

CE1.5 After winning the tender to rehabilitate the existing sewer within Doha C763/2, I

started the implementation plan, by review the contract the contract details and

preparing the most important points that were captured in it. I also assembled a strong

team of engineers and technicians who further helped me in the mobilization of the

resources like means of transport, excavator among others. Then I went through the

standards and codes like the BS 5911-1 and BS EN 1916 that were relevant to the use of

the concrete pipes. I organized a meeting with my team before moving to the site ready

to execute the project.

CE1.6 After the start of the project, I collected the information that was essential for the

design work that included the geomorphology and ground topography of the areas

where the sewer was to pass through. The other information that I collected from the

owners of the sewer line was the projected volume of the sewage generated by the

household that was gathered to the line. I organized all the data and came up with the

implementation plan before calling the meeting to discuss the execution plan. I also

reviewed the expectation of the client with my team members regarding the quality of

the work and milestones that were to be delivered.

CE1.7 I started the design work by identifying the best route for the main line followed by

the sublines connecting the households to the main line. I also identified the location of

the Underground obstructions like the power lines and water pipes. I then requested

for the permission from the relevant authorities for the leeway since I didn't want to

interpret existing amenities. The enabled free flow of the waste water through the

pipes, and I designed the suitable gradient that allowed Natural flow. The calculations

that I did during this design was the determination of the gradient or slope.

CE1.8 Also, I determined the cross-sectional are of the pipes that I used for the sewer lines.

The design was to ensure that it was able to a serve the volume generated from the

sources. I used a combination of differential equations to solve this challenge. I used the

Page 5: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

relationship between the cross-sectional area of the pipe, flow velocity, and flow rate. I

further used the Manning equation to determine the speed of flow. Below are the

equations.

Q = AV

V = (1.49/n) [(D/4)2/3] (S1/2) (Manning equation) Q = (πD2/4) V = (1.49/n) (πD2/4) [(D/4)2/3] (S1/2).

Where

V= storm water flow velocity

D = storm sewer pipe diameter

S= storm sewer gradient

n = roughness coefficient of pipe

CE1.9 The next design that I did on the project was the determination of the diameter of

the sewerage pipe for the mainline and the connections to the individual households. I

had selected the concrete pipes due to its strength and the ease of installation. I

determined the peak flow rate of the sewer to ensure that it was able to handle

wastewater that was being generated. I used below equations to determine the peak

flow rates

Pmax/min.t=(Pmax/minhr-t-avghr) (Pi-avgd)

Where;

Pmax/minhr-t-avghr=(Qmax/minhr.-tQavg-hr)

(Qmax/minhr.-t) = the average flow during a duration (t) hours

Qavg-hr = the average hourly flow for that day of record.

CE1.10 I encountered the challenge when I was doing the excavation of the trench to lay

down the concrete pipes where I found there was a lot of the underlying cables and the

asbestos pipes. Besides, I discovered that the existing roads in the area where pipes

were passing were not wide enough. Some of the areas were also narrow for the

passage of the excavator that I was using. Therefore, I did analysis and discussed with

my team where I proposed the hand excavation of this areas. The process was slow, but

Page 6: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

at least it was preferable because of the existing infrastructure.

CE1.11 I completed excavation then removed and replaced approximately 2.5km trunk

sewer gravity mains comprising VC pipelines (300mm Ø – 1000mm Ø) and associated

manholes. I also did the replacement of 1km trunk sewer gravity mains that consisted

of the GRP pipelines with diameters of 1000mm and 1200mm and utility holes on this

section. Finally, I did the test run with water before filling back the top soil that I had

excavated with my team I also reinstated the landscaping, paving blocks and asphalt.

CE1.12 To easy the installation work, I innovatively choose reinforced concrete pipes that

were one-meter-long, and it had a socket on one end. This made it easy for installation

and lifting them in place. The assembling method was the socket connections and did

not require any particular joining method as compared if the PVC pipes were used. This

innovative approach reduced the sewer line installation time

CE1.13 The useful software that I used in the project was the AFT Fathom, which is system

modeling and pipe flow analysis software. I used to this software to calculated the flow

distribution and pressure drops in the pipeline. Furthermore, the software was usefully

when I was analyzing the distribution of wastes in the pipe. The software eased my

work and improved on the accuracy of the project.

CE1.14 With other members, I was able to work towards completing this task on time. The

implementation team that I led consisted of both engineers and technicians. I consulted

a senior technical engineer when I encountered some challenges in my projects and

when I was participating in the tendering process. The other person who was worked

closely was the quantity surveyors who were responsible for the BOQ for the project. I

organized meetings on regular basis with the team to review the progress of the

projects.

CE1.15 My other responsibility as the team leader in the project was the preparation of the

projects documentations for records keeping and as the mode of communication. I used

Page 7: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

the English language on this project to avoid language barriers because workers in the

project were from different ethnic background. The documents that I prepared included

the tender documents, project progress reports, weekly reports among others. I also did

the presentation of this documents to my supervisor before it was approved for

circulation.

CE1.16 As the team leader in the project, I participated in making a decision that helped in

reducing the cost of the project or at least working as per the budget. Therefore, from

the start of the project, I developed my budget and came with some ways of reducing

the cost by maximizing the productivity of every worker. This saved on the salaries and

allowance that was paid to the casual Labour on site.

CE1.17 With my project management skills, I was able to ensure all the plans went on

through the project implementation time. I also used the traffic master plan when the

was excavation near the road where the sewer line was passing through. I had

developed the implementation plan that guided me in the budget and the millstones

that were to be achieved at every stage of the project.

CE1.18 At the time of the project implementation, I applied my skills in fluid mechanics to

do the project. I also participated in the training that was offered by the company. The

training was on simulation and how to lay pipes on the trenches using lifting machines.

I also had some discussions with the senior members in the company who they shared

their experiences in piping work. Lastly, I researched on my own whenever I

encountered the challenge that was related to the project.

CE1.19 I understood the importance of taking safety while implementing the project

because it could cause adverse impacts to both implementation team, environment, and

tools. We used the lift tools instead of manually lifting because of dangers in the back

injuries. The other safety precaution that I took was to use protective equipment like

safety boots and gloves. I also followed the user operation manuals for the lifting tools

Page 8: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

that we were using at the site to avoid damages and associated injuries.

IV. Summary

CE1.20 I completed this project on time and gained tremendous engineering experiences

concerning team leadership and technical knowledge. I managed to lead the

implementation team from beginning up to completion. Therefore, I achieved the goals

of the project that included upgrading of the pipeline and completing it within the

planned time. I played a significant role in the project from the beginning where I did

the design, coordinated the implementation and commissioning. In the end, all the

members of my team and management were happy with the way I implemented the

project successfully.

CAREER EPISODE 2

I. Introduction

CE2.1 The second project discussion is my Engineering experience that I acquired while working

as the Technical Engineer at Qatar Building Company (QBC). This project was the participation

in the construction of the Al Otouriyah / Al Jemailya / Al Shihaniyah Road (P019) where I

performed the Soil test that I will elaborate on the project. I worked and delivered this project

within 18 months between November 2014 to May 2016.The project was located in the central

region of the Qatar, where 28.7km of Rural Arterial road from Al Shihaniyah to Al Jemailya via

Al Otouriyah. My responsibility was to perform the soil test that enables the determination of

the amount of compaction and the to check whether the soil was able to current the maximum

required loads.

II. Background

CE2.2 Qatar Building Company (QBC) is the market leader in civil engineering and building, and it

was awarded the contracted to construct by road by ASHGHAL or the Public Works Authority of

Qatar government, (PWA). The project was the design, and its implementation monitor by

ASHGHAL. The road was divided into two sections namely 18.8 Km between Al Otouriyah and

Al Jemailya. The second section was the 12.6Km between Al Shihaniyah to Al Otouriyah. The

Page 9: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

project that I did this construction work was the earthwork where I perform the various soil

test to ensure compaction was done well. I implemented the project and made

recommendations as per the test results.

CE2.3 The goal of my engagement on this project was to upgrade the existing two-lane single

carriageway (1+1) to a four-lane dual carriageway (2+2). There was also a provision of the

cycle lanes that was reserved for future expansion to six carriageways (3+3) lanes. Because of

the scope of the project, I participated in the earthworks that involved compaction and testing

the strength. The objectives of the compaction soil test were to verify the strength of the road

base the before the paving to make sure it was able to carry design loads. The other aim was to

advise on the mixing combination in areas that did not yield the required test. The last goal of

the project was to make sure the road was done as per the codes and standards that were

mentioned in the project contract.

Figure 1: The organization chart used

CE2.4 Below are the roles and responsibilities that I was assigned as the Technical Engineer.

Participated in the design of the road especially the stabilization of the base foundation.

Page 10: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

I did the soil compaction test and advice the earthworks team where necessary.

I was part of the project planning team where I came with the implementation plans and ways

of mitigating challenges that I encountered in my line of duty.

I did the compaction test calculations where I was able to determine important test parameters

that helped me in making the informed decision.

As the team leader in the soil compaction test, I prepared and presented various documents to

the stakeholders.

I ensured safety was maintained at the workstation and ensured the dust was not affecting the

surrounding environment.

III. Personal Engineering Activity.

CE2.5 We moved to the site after the company won the contract and after completing all the

logistics work. To understand the project, I went through the contract that specified the scope

and the timeframe for the project. Besides, I went through the applicable codes and standards

that were mentioned in the contract that includes the standards as per ASHGHAL. Also, the

California Bearing Ratio (CBR) that I did was as per the AASHTO T193, D4429 and D1883-05.

After assembly my team I met with the Engineering manager who we discussed what was

expected of me as the person who was responsible for the soil compaction testing.

CE2.6 Before I started the project, I listed down the details of the information that I wanted to

initiate the implementation of the project. Some of the information was the test method that

was expected, the reporting structure concerning conveying data for the purpose of action

among other. The technician whom we worked together collected samples randomly from the

road sections that had been compacted. Lastly, I organized meeting with my team members

who we discussed the testing procedure that I adopted.

CE2.7 The first Engineering work that I did while constructing the road was to ensure the road

foundation was done correctly. The road foundation was done by mixing deferent soil mixture

and compacting using a roller to form layers. To ensure that the compaction was done properly

I did the soil test using various methods. I instructed compaction to be done until the required

compacted soil was achieved. The soil compaction test that I used were sand cone method,

California Bearing Ratio, and the Soil Permeability.

CE2.8 While doing the California Bearing Ratio, I determined the quality of strength of the soil that

was to form the base of the soil. I also measured the thickness of the base compacted soil and

Page 11: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

the layer. I performed this test by using a plunger with the standard area and measuring the

pressure required to penetrate the soil. I then divided the measured pressure with the required

pressure to achieve equal penetration on the norm crushed rock material. Below is the formula

CBR = F/Fo

where

F = force needed to penetrate a soil mass.

F0 = force necessary for the penetration as per the standard material.

CE2.9 The other test that I did was the sand cone method and the Soil Permeability to ensure that

the compaction process was done well. The purpose of the sand cone method was to determine

the field density. For the ground permeability test, I used Darcy’s law as shown below.

V = kiA

where

V = Flow rate cm3 /s,

A = cross-sectional area of soil conveying flow, cm2

k = permeability Coefficient

CE2.10 After completion of the compaction of the base soil, and ensuring the road could sustain the

design loads. We lay down the asphalt pavement in that contained approximately 313200-ton

asphaltic concrete followed by 244,224-ton Polymer Modified Bitumen asphalt in various layer

thicknesses. The other part of the road that we did was the pavement where interlocking blocks

was used. Besides, the streets light was erected. We also made the road making and built the

road signs to guide drivers while navigating the new path. We commissioned the project with

my team and client after completing all the work that was stated in the contract.

CE2.11 I encountered a technical challenge when I was preparing the granular road base layers and

sub base whereby on doing the laboratory test I found that the materials did not meet the

stipulated sand equivalent ratio that was 25. After researching for the best solution, I discussed

with the quality manager and agreed to do different mix gradations, and I also added the

Gabbro aggregate fines that helped in meeting the proposed mix in of sand equivalent ratio. In

the end, I managed to achieve the equivalent sand ratio of 32 that was good enough for the

project.

Page 12: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

CE2.12 To improve the quality delivery, I tried to be creative by following the company IMS Policy

when I was working with subcontractors’ also followed the Quality & HSE to ensure the quality

was maintained. On the design work, I made the decision to use three different compaction test

methods to improve the reliability of the results and reduce the chances of the errors that are

associated with soil compaction test. I also did the test on the rolling basis to ensure we deliver

results on time without any delay.

CE2.13 I leveraged on latest technology during the execution of this project regarding tools that I

was using. For example, I used GEOSYSTEM programs software that helped me in plotting

boring log, and the test pit logs that helped me in reducing the time taken in reporting test

results for the geotechnical test. The software also helped me in the analysis of the cement

products and concrete test results. This program supported the AASHTO, ASTM, and ACI

standards.

CE2.14 I was a member of a team during the implementation of the roads construction works, and I

was appointed the team leader when we were doing the road compaction test. As the team

leader, I helped in guiding the technicians on how the test was performed. As the team leader, I

maintained the flow of communication and gave the feedback to the management who lead the

road construction works. We also worked together with subcontractors who were suppliers of

the raw materials where we regularly discussed on the delivery lead times.

CE2.15 As the team leader in the compaction soil test, I was tasked with the production of different

types of reports that I share with the client and the company head office. These reports were

important because it determined the compaction required which is normally associated with

the cost. The other documents that I prepared with my team included the analysis reports,

weekly progress report among others. The language that I used on this documents was English

since that was the official communication language at the site.

CE2.16 I made the economical decision during the implementation of this project because I always

interacted with the suppliers of the soil compaction equipment. I always when for the most

affordable but reliable option regarding hardware and test. Besides, as the team leader, I

negotiated the project manager to allow my time work extra few hours to cover lost time. This

reduced the overall cost of the project since it was billed as per the number of days spent at the

site.

Page 13: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

CE2.17 Project management was a core part of the project because without it tracking of the

progress could not have been possible. There with my skills in project management, I was able

to plan the section that I was working on in the road project. I came with the work breakdown

structure where I disintegrated all the soil testing procedure into subtask that I allocated my

team members enabling me to monitor and track the progress well.

CE2.18 To enhance my work delivery, I participated in self-study by studying various methods used

in geotechnical test and their advantages and disadvantages. Also, I applied my knowledge that

I acquired in university in areas like the soil mechanics for geotechnical investigation and

analysis. The other skills that I used were the engineering soil properties that gave me

knowledge in the standard soil test methods. The last application of knowledge that I involved

in the project was the different road profiles that I learn during the study of the construction

drawings in my undergraduate degree.

CE2.19 Safety and sustainability were a paramount part of the project because it was the best way

of mitigating the dangers associated with Road construction. For safety reasons, I protected and

stored all the test samples in the secured place to ensure there was no contamination. I also

used protective gear during the execution of the project by wearing safety boots, helmet, and

gloves. I also considered the environmental hazards associated with roads construction by

spraying water regularly to the excavated earth to suppress dust. Lastly, as an ethical engineer,

we maintained good working relationship with everyone in the project and the neighborhood

where we organized football games with the young kid in the surrounding.

IV. Summary

CE2.20 The scope of the project was huge, but I leveraged on teamwork and my good research

skills. The project gave me a lot of experience in road construction and tested my ability as the

team leader. I completed my project after successfully meeting the objectives of the project and

after completion of the road construction work. The project met with the international roads

standards, and the law stated in Qatar and Ashghal requirements. My contribution was

significant as per the statement of my responsibilities and the quality of the work that i did with

my team.

Page 14: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

CAREER EPISODE 3

I. Introduction

CE3.1 My third project discussion is the experience that I acquired while working on the extension

of Highway 55 temporary truck route section B and A. At the time of this project I was working

for Qatar Building Company (QBC) as the Technical Engineer. This project consisted of the

constructing 22.7 KM dual carriageways with four bridges, seven roundabouts and other

associated amenities like diversions that ensured the flow of traffic. I worked on this project

between November 2013 and January 2015 at west and north of Doha City. The work was

divided into Sections A and B for Route 55 Temporary Truck Route (TTR). As the Technical

Background

CE3.2 QBC was established as a private civil engineer contractor in 1971 as a private civil

engineering contractor in Qatar. It has cemented its position as the Civil engineering contractor,

and it further introduced a new line of service called the Qatar Building Company Heavy

Equipment Division that deals with construction equipment. This project was as a result of the

tender that QBC had won after it was selected by the Ashghal to construct the road extension

of the Highway 55 Temporary Truck Route of sections B and A. The project involved the supply

of the civil engineering raw material and implementation of the traffic management plan. The

other work included the re-routing of the power lines that was on the construction site and the

design and construction of the Asphalt paved road. The other work that I did on the project was

the design of the bridges and the drainage systems along the roads. After every section during

the compaction of the base foundation, I did both penetration and compaction test to make sure

the road was able to carry the design loads.

CE3.3 The aim of the project was to extend the Highway 55 and construct the Temporary Truck

Route through Section A and B. With my civil engineering skills, and I ensured the project was

implemented within the standards. I made sure the raw material used were acceptable. I also

performed random penetration and compaction test to ensure the road was done as per the

standards applicable in Qatar. The other objective of the project was to provide the basic

outline of the resources that was required to implement the project. The design was also to

allow the smooth flow of the traffic. Thus I introduced some roundabouts to enable vehicles to

Page 15: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

move from one side to another without creating some congestion. The last objective of the

project was to design and construct Bridge that was able to withstand all the loadings acting on

it.

Figure 1: Organization Chart

CE3.4 As the project technical civil engineer, I was assigned the following roles and

responsibilities.

I participated in the design of the road constructions, such as coming with the specifications

like the compaction pressure, the number of roller passes, the thickness of the pavement

layers, the excavation and fill volume among others.

I performed the both compaction and penetration test followed by calculations so as to

ensure the road was done to the design specifications and was able to carry the design

loads.

I enforced the Roads constructions standards that were necessary for Qatar approval.

Page 16: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

I optimized my designs by using the latest civil engineering software.

I was the team leader who made sure that the members were doing the right things. I also

implemented safety on behave of the client.

I managed the project through planning, implementation, monitoring coordination among

other areas.

II. Personal Engineering Activity

CE3.5 As the Technical Engineer and after being appointed to be part of this project, I started by

reviewing the contract to understand the project details like the scope of the work and

responsibilities of every contractor in the work. I also went through the road design and the

specifications to acquaint myself. Then I took two weeks to move to the site and set the base

and to assemble my team that consisted of Civil engineers and other technicians who were

experts in road construction. I also went through the standards and codes that I followed in the

project to meet the international standards such as the Qatar National Construction Standards

2010, ASTM Standards D1883-05, AASHTO T193, and BS 1377. I then held meetings with the

Project Engineer who we had the last briefing.

CE3.6 I started the project by collecting the information that helped me in the implementation

process. The data that I gathered on this particular project included the compaction passes that

was to be used, the paving raw materials and the procedure used to test and analyze the road to

ensure it was done correctly. I also collected information such as the mass of the sample, the

volume of the mold and the water content in the sample that helped me when I was doing the

compaction test for the samples that I had collected from the site. Then I came up with the

implementation plan where I determine the key performance indicators, roles, and

responsibilities of everyone, budget and the millstones that were to be achieved at every

particular time.

CE3.7 I reviewed the tender documents to make sure that I considered all the requirements on the

project such as the design, implementations, materials used and tests to check the quality of the

work. I made the approvals of all the materials on time to avoid the delays that could have

happened to the project especially for the material with long lead times like the retaining wall

face panels and the bridge deck. I issued various site instructions to the members of my team

during the excavation, filling, compaction and paving using the bitumen. I did multiple tests on

random sections of the road during every stage of the project implementation and determined

their parameters through calculations followed by comparison with internationals standards.

Page 17: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

CE3.8 The other duty that I was assigned during the implementation of this project was

performing the penetration test to determine mechanical strength of the new carriageway

constructedto ensured that it was able to carry the design loads. I did this important test called

the California bearing ratio(CBR) by measuring the pressure that was able to penetrate the

tarmacked road using a plunger of the given area. I did this test under the ASTM Standards

D1883-05, AASHTO T193 and thein BS 1377. During this test, I did the calculations that helped

in the determination of the CBR using below formula.

p= measured pressure for site soils [N/mm²]

ps= pressure to achieve equal penetration on standard soil [N/mm²]

CE3.9 I also calculated compaction density for the already paved road to ensure that it was able to

carry the loads from the vehicles moving on it. I used the information that I collected with

below formula to determine the densities that were important in the determination of the road

compaction.

Bulk density, P=M/V

Dry Density, Pd= P/(1+W)

Where;

M=Mass of the sample(grams)

V=Volume of the mold(ml)

W=water content of the sub-samples

CE3.10 The difficulty that I encountered during the implementation of this project was when I

realized the CBR value on the proposed existing road ground was less than 15% that I

measured at 95% of MDD. As per the Qatar Standard Specifications, the values of the CBR for

the existing ground ought to be higher than 15% so as to receive permanent road layers. To

solve this technical challenge, I researched online and consulted my friends and senior

members of the company and came with the suggestion of excavating some portion. Therefore, I

excavated 300mm thickness of weak topsoil and filled it before doing the compaction of the

layers less than 150mm thickness so as to meet the requirements of the CBR value.

Page 18: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

CE3.11 After completion of the compaction and penetration tests on every section of the road and

at different stages, I prepared short reports that I shared with the project engineer who was

heading the project. I also kept the test samples with the name tags for future references. Lastly,

I held discussion with the implementation team to ensure that the compaction and ingredients

mixing was done correctly.

CE3.12 I embraced the innovative technique, in the way, I implemented the project, for example, I

discussed with other engineers, and they agreed to work on sections until it was completed

then move to another section. This prevented the suffering of the motorist who needed only to

pass through diversions. The other innovation that I introduced was the use of the softwares

that tremendously improved on the design accuracy.

CE3.13 As an engineer who values new technologies, I adopted the application of engineering

software during the implementations of my road design and construction project. The software

that I leveraged on is AutoCAD Civil 3D, Micro station, and the AutoTurn. This softwares gave

me the edge during the implementation process because I was able to cut the delivery time and

I was also able to do the design optimization.

CE3.14 As shown by the scope of the project, there was a lot of work; therefore, teamwork at the

site provided the solution. Therefore, I organized a team consisting of technicians and engineers

who we worked together. I discussed and reviewed the site progressed with my team members.

As the team head, I tasked every technicians and engineer who were working under me.

CE3.15 I created various documents at different stages of the project for the purpose of records

keeping and channeling information to other stakeholders. For example, after compaction and

penetration tests, I documented the procedure that I used plus the outcome results. The other

documents that I prepared include the progress reports, weekly reports, and monthly reports. I

used the language that was understood by everyone at the site thus I avoided the language

barriers.

CE3.16 I interacted with the suppliers of all the raw materials that was used at the site; thus I was

able to make economic decision based on the goods that was purchased. For example, I

negotiated for the discount since I instructed the procurement department to buy the materials

in bulk thus we were given discounts. There other are that I made an economic decision was

when I requested and negotiated with the client to allow us to work for extra one hour every

day and shorten the delivery time. This saved some money since the payment was pegged on

the number of days worked and not the hours.

Page 19: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

CE3.17 With my skills in project management, I was able to track the project progress using the MS

project where I was able to come up with the work breakdown structures (WBS). With this

skill, I managed my project very well and planned accordingly especially for the task that was

dependent on others. With this knowledge and expertise, I was able to monitor the project

implementation process that led to cost minimization. Besides, I was able to develop Gantt chart

that I used to illustrate the project schedule that was easy to be followed by my team.

CE3.18 During the implementation of this project, I took some initiative to improve my skills in the

delivery of this project apart from the skills that I acquired in my engineering school. For

example, I did self-study and research online on the various methods of performing the

compaction test in the tarmacked road like this project. Apart from that, I applied the

knowledge that I acquired in my undergraduate degrees such as the Highway and Pavement

Design, Transportation Engineering, Soil Mechanics, and Design of bridge structures.

CE3.19 I put safety in the forefront in all the activities that I did at the site to avoid any form of

accidents that could have jeopardized the project implementation. Therefore, I ensured all the

workers were supplied with the protective gears like the safety boots, coverall, and helmets.

Besides, I followed the correct operation procedures for the tools and equipment to avoid any

breakage. Lastly, I protected the environment and ensured the project was sustainable by

preventing pollution.

III. Summary

CE3.20 In my view, the project gave me valuable experience and improved my engineering

knowledge because I was able to lead the design team. I was also able to make decisions and

research on the project when I encountered some challenges. The project was successful

despite the technical problems that I faced. The project was completed on time and within the

standards that was agreed from the beginning. As the team leader in the project, my

contribution was enormous since I came up with the construction plan, time management,

resources management among other duties.

SUMMARY STATEMENT FOR PROFESSIONAL ENGINEER

Competency Element A brief summary of how you have applied

the element

Paragraph in the career

episode(s) where the

element is addressed

PE1 KNOWLEDGE AND SKILL BASE

Page 20: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

PE1.1 Comprehensive, theory-

based understanding of the

underpinning natural and physical

sciences and the engineering

fundamentals applicable to the

engineering discipline

a) I use my knowledge in physical

science and natural science to

understand and implement the

project as per the codes and

standards in my projects

CE1.5, CE1.8, CE1.9,

CE1.10

CE2.5, CE2.7, CE2.8,

CE2.9, CE2.10,

CE3.5, CE3.7, CE3.8,CE3.9, CE3.10,

PE1.2 Conceptual understanding of

the mathematics, numerical

analysis, statistics and computer

and information sciences which

underpin the engineering discipline

a) I did mathematical calculations that

helped me in determination of

important engineering parameters

like flow rate, density among others.

b) I used Civil Engineering softwares to

model and analyze my designs for

optimization.

c) The basis of my design work was the

information that I collected from the

beginning of the project.

CE1.8, CE1.9

CE2.8, CE2.9

CE3.8, CE3.9

CE1.13

CE2.13

CE3.13 CE1.6

CE2.6

CE3.6

PE1.3 In-depth understanding of

specialist bodies of knowledge

within the engineering discipline

a) I leveraged on my skills in the data

management to gather the

information that was important during

the design.

b) I used my calculation skills in Civil

engineering to determine the

parameters that I used in

implementing the project.

c) I introduced the engineering

softwares as the way of introducing

new implementation procedures in

my project.

CE1.6

CE2.6

CE3.6

CE1.8, CE1.9

CE2.8, CE2.9

CE3.8, CE3.9

CE1.13

CE2.13

CE3.13

PE1.4 Discernment of knowledge

development and research

directions within the engineering

discipline

a) I participated in trainings during my

project implementation to improve

my knowledge.

CE1.18, CE2.18,

CE3.18,

Page 21: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

b) I used the method of research to find

solution to the challenges that I

encountered.

c) I reviewed the information in both

online and off line to understand the

project well.

CE1.10, CE2.11,

CE3.10, CE1.5

CE2.5

CE3.5

PE1.5 Knowledge of contextual

factors impacting the engineering

discipline

a) I understood the impact of

teamwork, because without it the

delivery could not have been

possible.

b) I knew the impacts of not following

safety precaution, therefore I

followed it to the later.

c) I avoided language barriers at the

site by using the official language

that was English

CE1.14

CE2.14,

CE3.14, CE1.19 CE2.19 CE3.19

CE1.15

CE2.15

CE3.15

PE1.6 Understanding of the scope,

principles, norms, accountabilities

and bounds of contemporary

engineering practice in the specific

discipline

a) I made economic decisions that

helped in cutting the cost

b) I was aware of my roles and

responsibilities that was necessary to

implement the project.

c) I implemented the project as per the

codes and standards in Civil

Engineering

CE1.16 CE2.16,

CE3.16, CE1.4

CE2.4

CE3.4

CE1.5 CE2.5 CE3.5

PE2 ENGINEERING APPLICATION ABILITY

PE2.1 Application of established

engineering methods to complex

engineering problem solving

a) I used my research skills in civil

Engineering to find solution to the

challenges that I encountered.

b) I did the mathematical calculation

CE1.10

CE2.11,

CE3.10,

CE1.8, CE1.9

CE2.8, CE2.9

Page 22: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

that was paramount in design

progress.

c) I followed standards and codes that

was set by the ASHGHAL

CE3.8, CE3.9 CE1.5, CE2.5 CE3.5

PE2.2 Fluent application of

engineering techniques, tools and

resources

a) I used the latest technology tools to

implement my project like the

softwares.

b) I used the resources that was

available to ensure the safety of

every person in my project was

taken care of.

c) I used the available information to

design different parts of my project.

CE1.13 CE2.13,

CE3.13 CE1.19 CE2.19 CE3.19 CE1.6 CE2.6 CE3.6

PE2.3 Application of systematic

engineering synthesis and design

processes

d) I used civil engineering softwares to

optimize my design work.

e) I follow the project objectives to

make sure I was not deviating from

the course.

f) I made the progress documents that

helped me in recording everything

that I did at the site.

CE1.13

CE2.13

CE3.13 CE1.3

CE2.3

CE3.3

CE1.15 CE2.15 CE3.15

PE2.4 Application of systematic

approaches to the conduct and

management of engineering

projects

a) I used my project management skills

to plan, coordinate and implement

the project.

b) I managed the cost associated with

the project by make economic

decisions.

c) I was a good team manager in all

CE1.18, CE2.17 CE3.17, CE1.16, CE2.16, CE3.16 CE1.14 CE2.14,

Page 23: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

my projects. CE3.14

PE3 PROFESSIONAL AND PERSONAL ATTRIBUTES

PE3.1 Ethical conduct and

professional accountability

a) As an ethical civil engineer, I

observed environmental safety,

safety of workforce and tools.

b) I had good working relationships with

my team members that avoided any

frictions.

c) The guiding principle in all my

projects was the relevant standards

and codes that I studied in the start

CE1.19, CE2.19, CE3.19, CE1.15, CE2.14, CE3.14 CE1.5

CE2.5

CE3.5

PE3.2 Effective oral and written

communication in professional and

lay domains

a) I communicated well through written

documents that I prepared and share

within the company.

b) I held meetings before the start of

the project with stakeholders to

discuss the implementation plan.

CE1.15

CE2.15

CE3.15

CE1.5, CE2.5, CE3.5

PE3.3 Creative innovative and

proactive demeanor

a) I adopted innovative methods in

implementing my projects

b) I used the latest engineering

softwares to optimize my designs

CE1.12 CE2.12 CE3.12 CE1.13

CE2.13

CE3.13

PE3.4 Professional use and

management of information

a) I used my skills in information

management to collect the relevant

project data.

b) I review all the information that was

available the project contract.

CE1.6

CE2.6

CE3.6

CE1.5

CE2.5,

CE3.5

Page 24: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

PE3.5 Orderly management of self,

and professional conduct

a) I managed myself well through the

use of project management skills to

track the progress.

b) I start the projects by having

objectives in place, that helped me in

determining whether the project was

successful or not.

c) I followed the guide of standards and

codes to execute my projects and

gained acceptance.

CE1.18 CE2.17 CE3.17

CE1.3

CE2.3

CE3.3

CE1.5 CE2.5 CE3.5

PE3.6 Effective team membership

and team leadership

a) As a team leader, I worked well with

every person in the project and I was

the unified the team members.

.

CE1.16,

CE2.14,

CE3.14

Page 25: CDR Report Sample for Civil Engineer PDF - CDR Australia

-------------------Reach us to get your cdr report to be done at CDRAustralia.org------------------

Reach to our executive for your report to be done at below Details: Web: www.cdraustralia.org Email: [email protected]