Project Coordination Committee MeetingComprehensive Disaster Management Programme Phase II
Ministry of Disaster Management and Relief
13 May 2013
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 2/12
Overall Key Results
Post-2015 DRR Framework completed through nationalconsultation
National textbooks with DRR & CCA content for the primaryand Secondary schools were launched
Continued LDRRF through direct implementationagreement with local DMCs
Interactive Voice Response is launched
Climate change parameter studies completed
Management: A senior programme adviser deployed
Clarified Logframe, RRF, MYP
Filling up remaining vacancies
Joint planning and ‘coupling’ with DDM
1st Quarter Highlight
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 3/12
Professionalising DM System
Bangladesh participation in international forums: Asian Advisory Group of Parliamentarians for DRR (AAGPDRR), Incheon, Korea RCC Ulaanbaatar, Mongolia 4th GPDRR 2013 (preparation), Geneva International Conference on Local Government: Mainstreaming DRR & CCA in urban
local governance
National Disaster Preparedness Day 2013 Nationwide school safety drill, national seminar, booklet for schools, newspaper article
and supplements
Completion of Post 2015 HFA DRR agenda
Development of Community Radio (C.R.) Listeners Group
Launch of Masters programmes with BUP
Outcome -1: 1st Quarter Highlight
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 4/12
Rural Risk Reduction
LDRRF:
FTRA/RRAP at 29 Unions in 10 Upazilas in 6 districts.
Implemented: 92 schemes; at USD 2.98 millions,
benefitting 0.2 million people.
Disbursed USD 2.15 millions
Plans for Training of local DMCs are revisited
Outcome -2: 1st Quarter Highlights
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 5/12
Urban Risk Reduction
Seismic fault mapping completed, leading to: Urban Contingency Planning : bldg inventory 45 Wards , risk profile 18 wards
City planning for Mymensignh with UDD
Retrofitting assessment initiated - commissioned the
seismic retrofitting assessments of three major buildings to ADPC
1st batch of Safer City training with UN-ISDR / MAB
Training of construction workers – 240 masons and bar binders
in this quarter, total 1540
Urban LDRRF interventions:
with city governments of Sylhet, Mymensingh, Chittagong
With communities at Chittagong
Outcome 3: 1st Quarter Highlight
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 6/12
Preparedness
Official Launch of the IVR by 6 mobile operators
DMIC dissemination 16 Sitreps
Safer school programme – 30 secondary school teachers identified as Master Trainers
nation-wide safe school drills during NDPD,
school drill model in Shahin School
Outcome 4: 1st Quarter Highlight
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 7/12
Mainstreaming DRR across sectors National Curricula Textbook Board (NCTB):
Textbooks disseminated
Supplementary learning materials and ToT manual for engineers
Bangladesh Meteorological Department (BMD): Meteorologists are trained on computerised weather date processing Others received training on GIS and remote sensing software
Flood Forecasting and Warning Centre (FFWC): Main Meteorological Office computer is updated
42 professionals received training
Geological Survey of Bangladesh (GSB): Seismic assessment for 6 cities ongoing, active fault mapping
Department of Agricultural Extension (DAE): Rabi/2013 demonstration is completed
Technology dissemination: Dry Seedbed; Mushroom planitng, demo plots
Department of Fisheries (DoF Climate impact assessment and CCA mainstreaming guideline developed
Outcome 5: 1st Quarter Highlight
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 8/12
Mainstreaming DRR across sectors
Department of Livestock Services (DLS): draft action plan on disaster and climate risk management in livestock sector
Department of Environment (DoE): DRR&CCA integration in Fisheries and Livestock Sectors,
Publications for the Climate Change Knowledge Network Directorate General of Health Services (DGHS):
Guidelines for: post-earthquake action plan; Non-structural vulnerability asmnt
A National Health Crisis Management and Archive Centre established.
Fire Service and Civil Defence (FSCD): 1,500 urban volunteers in 38 batches bringing up 16,373
100 professioals trained in 2 batches bringing up to 1,415
Department of Women Affairs (DWA): DRR Action Plan was submitted for approval to ministry.
Outcome 5: 1st Quarter Highlight
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 9/12
Community Level CCA
Publication of Climate Change Studies: 4 reports finalised
Internal Displacement study: Consulted to national expert
Translation to adaptation techniques: Findings of studies
are shared with potential users and partner agencies
Capacity building: capacity building consulted with government
departments, training/academic institutes, I/NGOs.
Outcome 6: 1st Quarter’s Highlight
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 10/12
Outcome AWP for2013
(version-A)
Progress of Q1 Total Exp. Upto March 2013
% against AWP
Planned for Q1(Jan-Mar'13)
Exp. for Q1(Jan-Mar'13)
% AgainstQ1
A C D E F G
Outcome 1 454,215 110,924 142,654 129% 142,654 31%
Outcome 2-
13,409,240 2,768,606 2,200,358 79% 2,200,358 16%
Outcome 3 4,092,942 588,534 842,884 143% 842,884 21%
Outcome 4 3,032,915 632,500 149,040 24% 149,040 5%
Outcome 5 3,010,744 2,900 0% - 0%
Outcome 6- 661,260 99,500 77,691.25 78% 77,691 12%
Outcome 7 1,721,872 331,202 336,090 101% 336,090 20%
TOTAL 26,383,187 4,534,165 3,748,718 83% 3,748,718 14%
Summary of Financial Progress for 1st Quarter 2013
Reporting Period: January -Mach 2013 Figures in USD
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 11/12
M&E M&E data collection plan for 2013 and 2014
100-Unions Survey ongoing Disaster Management Committee functionality assessment
CPP functionality assessment,
Community and household level disaster preparedness LDRRF intervention results survey
School safety preparedness assessment
Baseline production: MoU with BBS for Baseline for Assessment &Union Vuln./Resilience Index
Assessments Completed: Urban Volunteers; DMIC users and beneficiaries
Pipeline: Landslide volunteers & Resilient Habitat Approaches
7/16/2019 CDMP-1st Quarter Progress Report 2013
http://slidepdf.com/reader/full/cdmp-1st-quarter-progress-report-2013 12/12
Way forward Challenges:
High delivery targets vs. political instability
Capacity constraints of DMCs / NGOs gravitate to conventional interventions
Urban LDRRF projects require intensive supervision Lessons:
Broader academic opportunities
Urban projects boosted LDRRF gaining momentum
More confident partner department
Priorities for Q2: Business continuity plan to work during hartals
Fewer LDRRF projects with larger nominal values
Intensive capacity building of DMCs, officials and planning cadres