CDF Analysis Diskpool Status
Doug Benjamin and Dave Ambrose
with help from Alexei Varganov
•Use Case analysis•Analysis of Billing and door DB’s
•System tests• fileserver rate tests•Pnfs database rate tests•New hardware (CMS Sataboy on loan)
•Plans
![Page 2: CDF Analysis Diskpool Status](https://reader036.fdocuments.net/reader036/viewer/2022062422/56812c2a550346895d90a186/html5/thumbnails/2.jpg)
GDM April 18 2006 CDF Analysis diskpool status - D Benjamin
Daily diskpool usage
D. Ambrose
![Page 3: CDF Analysis Diskpool Status](https://reader036.fdocuments.net/reader036/viewer/2022062422/56812c2a550346895d90a186/html5/thumbnails/3.jpg)
GDM April 18 2006 CDF Analysis diskpool status - D Benjamin
jobs by user (Total/write/read)
D. Ambrose
![Page 4: CDF Analysis Diskpool Status](https://reader036.fdocuments.net/reader036/viewer/2022062422/56812c2a550346895d90a186/html5/thumbnails/4.jpg)
GDM April 18 2006 CDF Analysis diskpool status - D Benjamin
Example user profile
• Most prolific user• Reading only• ntuples
D Ambrose
![Page 5: CDF Analysis Diskpool Status](https://reader036.fdocuments.net/reader036/viewer/2022062422/56812c2a550346895d90a186/html5/thumbnails/5.jpg)
GDM April 18 2006 CDF Analysis diskpool status - D Benjamin
Example user profile
• Most prolific writer• Writing ntuples• Reading ntuples
D Ambrose
![Page 6: CDF Analysis Diskpool Status](https://reader036.fdocuments.net/reader036/viewer/2022062422/56812c2a550346895d90a186/html5/thumbnails/6.jpg)
GDM April 18 2006 CDF Analysis diskpool status - D Benjamin
System testing• Fileserver read
performance– By server– Agregate rate
• PNFS database performance testing– Initial results
“interesting”– More work needed to
understand the results
A Varganov
![Page 7: CDF Analysis Diskpool Status](https://reader036.fdocuments.net/reader036/viewer/2022062422/56812c2a550346895d90a186/html5/thumbnails/7.jpg)
GDM April 18 2006 CDF Analysis diskpool status - D Benjamin
Various fileservers
30 jobs 100 jobs
120 MB/s
0 MB/s
0 MB/s
120 MB/s
A Varganov
D Ambrose
![Page 8: CDF Analysis Diskpool Status](https://reader036.fdocuments.net/reader036/viewer/2022062422/56812c2a550346895d90a186/html5/thumbnails/8.jpg)
GDM April 18 2006 CDF Analysis diskpool status - D Benjamin
Plans/Conclusions
• Finish User use case profiles in 1-2 weeks (including interviews)
• Finish hardware testing 1-2 weeks– Including borrowed CMS hardware– Summarize results
• Plan for first formal preproduction readiness review week of 15-May