1 CDBG Lead-Based Paint Requirements For Grant Administrators

description

CDBG Lead-Based Paint Requirements. For Grant Administrators. Why do we care?. Harmful to the body Stored in organs and bones Long-lasting physical and neurological problems Children under 6 yrs. and unborn babies most vulnerable. Where is it?. - PowerPoint PPT Presentation

Transcript of CDBG Lead-Based Paint Requirements

Page 1: CDBG Lead-Based Paint Requirements

1

CDBG Lead-Based Paint Requirements

For Grant Administrators

Page 2: CDBG Lead-Based Paint Requirements

2

Why do we care?

• Harmful to the body• Stored in organs and bones• Long-lasting physical and neurological

problems• Children under 6 yrs. and unborn babies

most vulnerable

Page 3: CDBG Lead-Based Paint Requirements

3

Page 4: CDBG Lead-Based Paint Requirements

4

Where is it?

• Toys, fishing equipment, blinds, crayons, water, pottery, lead crystal, solder

• Pre-1978 homes• Higher percentage in pre-1950 homes

Page 5: CDBG Lead-Based Paint Requirements

5

Lead-based paint hazards in a pre-1978 home

• Dust and paint chips• Deteriorated painted / varnished surfaces• Friction surfaces• Impact Surfaces• Chewable surfaces• Soil

Page 6: CDBG Lead-Based Paint Requirements

6

Lead-based paint regs

• New regulations published in 1999• Section 1012 of the Residential Lead-Based

Paint Hazard Reduction Act of 1992• a.k.a Title X Subpart J• 24 CFR Part 35

Page 7: CDBG Lead-Based Paint Requirements

7

Applicability

• If you are doing rehab on a pre-1978 home, and broken painted surfaces exist, or if the work you are doing will break paint, you must address all potential lead hazards, including soil.

Page 8: CDBG Lead-Based Paint Requirements

8

Purpose

• To reduce the threat of childhood lead poisoning in housing owned, assisted, or transferred by the Federal Government.

Page 9: CDBG Lead-Based Paint Requirements

9

Exemptions

• House built after 1-1-78 • Housing exclusively for elderly (unless

children under 6 could be present for prolonged periods of time )

• SROs, efficiency apts, dorms, military barracks

• Certified lead-free property

Page 10: CDBG Lead-Based Paint Requirements

10

Exemptions

• Property where LBP was removed and clearance was achieved

• Unoccupied units that will remain vacant until it is demolished

• Non-residential property • Rehab where a painted surface will not be

disturbed

Page 11: CDBG Lead-Based Paint Requirements

11

Exemptions

• Rehab where only a “de minimis” amount of paint is disturbed

• Emergency repair actions needed to

safeguard against imminent danger or further structural damage

• Emergency housing (e.g. homeless) assistance that lasts less than 100 days per year

• NOTE: All exemptions must be documented

Page 12: CDBG Lead-Based Paint Requirements

12

What you need to do:

DisclosureInspection EvaluationAddress the HazardClearanceNotification

Page 13: CDBG Lead-Based Paint Requirements

13

Disclosure

• Pamphlet: Protect Your Family From Lead in Your Home−http://www.hud.gov/offices/lead/outreach/

• Owners and tenants

Page 14: CDBG Lead-Based Paint Requirements

14

Disclosure

• Evaluation of lead-based paint• Forms

−Owners and renters• Sample forms:

−http://www.hud.gov/offices/lead/disclosurerule/index.cfm

Page 15: CDBG Lead-Based Paint Requirements

15

Inspection

• Inspect the home to determine needed rehab

• Important to identify all repairs needed

Page 16: CDBG Lead-Based Paint Requirements

16

Evaluation

• < $5,000 per unit −Test paint or presume LBP

• >$5,000 per unit−Test paint or presume LBP−Risk assessment

Page 17: CDBG Lead-Based Paint Requirements

17

Evaluation

• When do you presume lead?−Property is in poor condition−Rehab job is small−You have reason to believe lead exists

Pre-1950 building Similar units in the neighborhood

−Work needs to begin immediately

Page 18: CDBG Lead-Based Paint Requirements

18

Pre-Rehab

• Develop estimate• Allocate costs to rehab or LBP• Treatment method based on cost of non-

lead rehab• Determine treatment method

ALWAYS:−Lead-safe work practices by trained personnel−Occupant Protection Plan By Contractor

Page 19: CDBG Lead-Based Paint Requirements

19

TERMS TO KNOW

• Standard Treatments• Interim Controls• Abatement• Lead Safe Work Practices

Page 20: CDBG Lead-Based Paint Requirements

20

Standard Treatments

• Stabilize all deteriorated paint (interior and exterior)

• Create smooth cleanable horizontal surfaces

• Correct dust generating conditions−Friction surfaces−Impact surfaces

• Treat bare soil−To make LBP contaminated soil inaccessible

Page 21: CDBG Lead-Based Paint Requirements

21

Interim Controls

• Acceptable way to reduce exposure to LBP hazards, although not permanent

• Paint stabilization• Treatment of friction & impact surfaces• Treatment of chewable surfaces• Lead-contaminated dust control (24 CFR

35.1330)• Lead-contaminated soil control

Page 22: CDBG Lead-Based Paint Requirements

22

Abatement

• Permanent elimination of lead-based paint hazards

• Remove lead-based paint and its dust• Permanently encapsulate or enclose the

LBP• Replace components that have LBP

Page 23: CDBG Lead-Based Paint Requirements

Abatement

• Remove or permanently cover lead-contaminated soil

• If ordered by enforcement agency

Page 24: CDBG Lead-Based Paint Requirements

24

Lead Safe Work Practices

• Occupant Protection Plan• Done by Contractor• Must include:

−No entry into worksite−Temporary relocation if necessary−Protect contents of home from LBP contamination

Page 25: CDBG Lead-Based Paint Requirements

25

Temporary Relocation

• Necessary when:−Can’t use kitchen or bath due to rehab work−Can’t close off work area from balance of living

area−Children may be exposed to LBP dust

• NOT necessary when:−Work done in an 8-hour period−Possible to secure worksite−Waiver -- for elderly occupants

Page 26: CDBG Lead-Based Paint Requirements

26

Lead Safe Work Practices

• Worksite Preparation and Containment• Prohibited methods• Worksite Cleanup• One-day training for workers• Not required for de minimis levels of work• 24 CFR 35.140; 35.1350; 35.1345

Page 27: CDBG Lead-Based Paint Requirements

27

Worksite Preparation

• Prevent LBP and dust from leaving worksite• Minimize spread of dust, paint chips, soil and

debris• 6 mil plastic on floors and over doors• Warning signs regarding LBP hazard

reduction activities

Page 28: CDBG Lead-Based Paint Requirements

28

Prohibited Methods of Abatement

• Some methods of paint removal are prohibited because they increase the lead hazard−Open flame burning or torching−Machine sanding or grinding−Abrasive blasting−Paint stripping in poorly ventilated space

• 24 CFR 35.140

Page 29: CDBG Lead-Based Paint Requirements

29

Cleanup and Clearance

• ALL worksites must be cleaned and pass a clearance test that assures the area has been properly cleaned of lead-based paint.

• Clearance Report−Documents results of clearance test−To UGLG, owner, and occupant

• Clearance test NOT done by contractor

Page 30: CDBG Lead-Based Paint Requirements

30

ALWAYS

• Notifications to owner/occupant [24 CFR 35.125]−HUD pamphlet−Evaluations, work to be done, clearance reports

• Lead-safe work practices• Clearance [24 CFR 35.1340]

−Work site−Entire Unit

Page 31: CDBG Lead-Based Paint Requirements

31

Determining Level of Rehab Assistance

• 24 CFR 35.915• Per unit amount of rehab “hard” costs• Federal Funds Only• NOT lead paint related costs• Not “soft” costs

Page 32: CDBG Lead-Based Paint Requirements

32

Determining Level of Rehab Assistance

• Total Rehab Cost Estimate• Subtract identified LBP costs

−Cost of work damaging a painted surface−Cost of work addressing deteriorated paint−Cost of other work components with potential for

LBP impact

• = Level of rehab assistance• Cost Allocation Document to show how level

of rehab was determined

Page 33: CDBG Lead-Based Paint Requirements

33

Getting the work done

• Treatment method is based on the amount of non-lead rehabilitation costs per unit

−< $5,000

−$5,000 - $25,000

−> $25,000

Page 34: CDBG Lead-Based Paint Requirements

34

< $5,000

• Do no harm (to the occupant) • Test paint or Presume• Rehab as usual with Lead Safe Work

Practices• Use Standard Treatments on broken or

deteriorated painted surfaces• Clear the worksite

Page 35: CDBG Lead-Based Paint Requirements

35

> $5,000 - $25,000

• Must Control Lead Hazards

• Test Paint and Do Risk Assessment−Interim Controls

- or-• Presume LBP

−Standard Treatments

• Clear Unit

Page 36: CDBG Lead-Based Paint Requirements

36

> $25,000

• Test Paint and Do Risk Assessment−Abate LBP Hazards−Interim Controls Allowed on Exterior Surfaces not

otherwise disturbed-or-

• Presume LBP −Abate all applicable surfaces

• Clear Unit

Page 37: CDBG Lead-Based Paint Requirements

37

Clearance/Notification

• ALWAYS Do this!• Methods and standards per EPA at 40 CFR

745.227(e)• Must be done by certified clearance

inspector• NOT done by contractor who did the work• Copy of report to owner and occupant• 24 CFR 35.930

Page 38: CDBG Lead-Based Paint Requirements

38

Clearance

• < $5,000 non-lead rehab• Worksite only• Not necessary if work is de minimis

• > $5,000• Clear entire house

Page 39: CDBG Lead-Based Paint Requirements

39

Clearance

• Occupants allowed back on site ONLY after clearance has been achieved

• Don’t pay contractor until clearance has been achieved

Page 40: CDBG Lead-Based Paint Requirements

State Requirements/Resources

Insert State Specific Requirements

Page 41: CDBG Lead-Based Paint Requirements

41

Recordkeeping Requirements

• In each rehab project file:−Documentation of receipt of HUD booklet−Inspection−Risk assessment−Worker certifications−Temporary relocation claims and calculations−Clearance documents

Page 42: CDBG Lead-Based Paint Requirements

42

Resources

• HUD Office of Healthy Homes and Lead Hazard Control −www.hud.gov/offices/lead

• Environmental Protection Agency (EPA)−www.epa.gov/lead

• Occupational Safety and Health Organization (OSHA)−www.osha.gov

Page 43: CDBG Lead-Based Paint Requirements

43

Resources

• Guidance:−http://www.hud.gov/offices/lead/leadsaferule/

LSHRGuidance21June04.pdf

Page 44: CDBG Lead-Based Paint Requirements

44

Handouts

• Summary of Lead-Based Paint Requirements by Activity

• Lead-Based Paint Requirements in CDBG-Assisted Housing Rehabilitation

• Lead-Based Paint Rehabilitation Process• Guidance on HUD/EPA Abatement Letter