CCOS Status Report
February 6, 2004
Policy Committee Meeting
CCOS Funding Status
Available and Committed FundsCash and Commitments Available (per CCOS financial Report of December 2003) $1,614,592.792003 EPA Money at ARB $894,200.00Total Available $2,508,792.79
Commitments Secured during the last Fundraising EffortEPA/HUD (reliable standard pathway, three to six months to transfer) $500,000.00 $500,000.00 $500,000.00US Department of Transportation (requires complex transfer processing) $250,000.00 $250,000.00US Department of Agriculture (may be directed to University research) $384,000.00Total Secured Commitments $500,000.00 $750,000.00 $1,134,000.00
Total Available Funds and Secured Commitments $3,008,792.79 $3,258,792.79 $3,642,792.79
Total expenditure to complete identified CCOS Phase III tasks $3,065,000.00 $3,065,000.00 $3,065,000.00
Balance ($56,207.21) $193,792.79 $577,792.79
CCOS Funding Needs
Funds Needed to Complete Current Table 1 Category III ProjectsTable 1 Category III Phase I estimate $770,000Table 1 Category III Phase I contingency $200,000Table 1 Category III Phase 2 estimate $1,260,000 2004 - 100k+40k+100k+150k+100k+80k Projects III-2, 6, 11-a, 16, 17, 18 2005 - 50k+200k+200k Project III-10b, 11b, 13b 2006 - 150k+60k+30k Projects III-19, 20, 21Total Needed for Current Table 1 Category III $2,230,000
Other expenditures to be added to Table 1Category IIIDatabase Management for three years ($50kx3) $150,000Database Improvements $150,000NOAA funding for a year (including three profilers) $250,000Augmentation of 01-02CCOS $30,000Design of a Technical Study for a future Deposition Study $75,000Design of a long-term Enhanced Monitoring Network $100,000CCOS Conference, publications, and final synthesis document (add to III-21) $80,000Total additional expenditure $835,000
Total expenditure to complete identified CCOS Category III tasks $3,065,000
Category IV Long term projectsPreliminary Estimate $13,850,000
Table I - Changes
• Per PC request, TC reprioritized Category III projects
• Identified projects to be initiated in 2004, 2005, 2006
• Changed title/scope of III-3 from ‘Ground-Truth the Roadway Network’ to ‘Update Intregated Transportation Network.’
Table 1 - Additions• Added 7 new projects (total $835k)
• Basic Database support on consent calendar. Future improvements still under consideration
• Replacement of NOAA earmark is consent calendar item
• Need for further validation of meteorological models identified and placed on consent calendar
• For Deposition Study and Long-Term Measurement Network, contracting out designs and cost estimates recommended. Request approval to develop RFP/RFQ
• Enhanced funding for conferences/publications proposed
Informational Items
• Processing of Seasonal Ozone Modeling contract on hold until NOAA funding issue resolved
• TC may recommend termination of one CCOS contract
• TC feels US EPA should include California specific items in their research agenda. This would require future fundraising (CCOS earmarks for EPA)
• There are sufficient funds to complete current CCOS projects. However, TC remains willing and enthusiastic to carry CCOS process further depending on availability of future funding.
CCOS Modeling Update• Of the three CCOS episodes, July-August 2000 is only
modeled episode currently available for SIPs
• Of several modeling efforts, only ARB modeling results for that episode satisfy EPA requirements
• Modeling of September 2000 episode by Alpine Geophysics (03-01CCOS) unsuccessful so far
• Modeling of June 2000 episode not currently active
• ARB modeling of non-CCOS July 1999 episode shows promise, but it’s unclear if acceptable modeling will be available in time for current SIP development