RSUD MHAT Kabupaten Kerinci HARGA SATUAN UPAH, BAHAN DAN PERALATAN NO Uraian Satuan Kode Keterangan I. TENAGA KERJA 1 Kepala Tukang oh 75,000.00 2 Mandor oh 65,000.00 3 Mekanik oh 70,000.00 4 Mekanik Pembantu (Asisten Mekanik) oh 50,000.00 5 Operator Terampil oh 70,000.00 6 Operator Kurang Terampil oh 55,000.00 7 Operator Pembantu (Asisten Operator) oh 50,000.00 8 Pekerja oh 50,000.00 9 Penjaga / Satpam oh 50,000.00 10 Sopir Truck / Dumpt Truck oh 55,000.00 11 Sopir Personil oh 55,000.00 12 Sopir Pembantu (Kernet) oh 50,000.00 13 Tukang Batu oh 55,000.00 14 Tukang Besi oh 60,000.00 15 Tukang Cat Semprot oh 60,000.00 16 Tukang Cat oh 60,000.00 17 Tukang Kayu oh 55,000.00 18 Buruh oh 55,000.00 19 Pekerja Profil Arsistik oh 150,000.00 NO Uraian Satuan Kode II. MATERIAL A Material Galian 1 Aspal kg ### 2 Batu Bata Mutu Baik bh 600.00 3 Batu Bata Mutu Sedang bh 400.00 4 Batu Belah ### 5 Batu Kali Bulat ### 6 Batu Pecah (Stone Crusher) 0,5 - 1 Cm ### 7 Batu Pecah (Stone Crusher) 1 - 2 Cm ### 8 Batu Pecah (Stone Crusher) 2 - 3 Cm ### 9 Batu Pecah (Stone Crusher) 3 - 5 Cm ### 10 Batu Pecah (Stone Crusher) 5 - 7 Cm ### 11 Batu Pecah (Stone Crusher) 7 - 10 Cm ### 12 Filler kg 1,126.00 13 Kerikil ### 14 Kerikil Sungai tak diayak/Sirtu ### 15 Pasir Pasangan ### 16 Pasir Timbun / Urug ### 17 Tanah Urug / Timbunan Biasa ### 18 Tanah Urug / Timbunan Pilihan ### B Material Kayu 1 Kayu Bekisting / Mal ### 2 Kayu Klas I ### 3 Kayu Klas II ### 4 Kayu Klas III ### 5 Kayu Perancah ### 6 Kayu Dolken bh ### 7 Kayu Bakar ### Upah Tenaga Kerja (Rp) Harga di Quary (Rp) Jarak Angkut (km) Upah Angkut (Rp) Jumlah Harga (Rp) m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3 m 3

Transcript of CCO 2013c.xls

Page 1: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

HARGA SATUAN UPAH, BAHAN DAN PERALATANNO Uraian Satuan Kode Keterangan

I. TENAGA KERJA1 Kepala Tukang oh 75,000.00

2 Mandor oh 65,000.00

3 Mekanik oh 70,000.00

4 Mekanik Pembantu (Asisten Mekanik) oh 50,000.00

5 Operator Terampil oh 70,000.00

6 Operator Kurang Terampil oh 55,000.00

7 Operator Pembantu (Asisten Operator) oh 50,000.00

8 Pekerja oh 50,000.00

9 Penjaga / Satpam oh 50,000.00

10 Sopir Truck / Dumpt Truck oh 55,000.00

11 Sopir Personil oh 55,000.00

12 Sopir Pembantu (Kernet) oh 50,000.00

13 Tukang Batu oh 55,000.00

14 Tukang Besi oh 60,000.00

15 Tukang Cat Semprot oh 60,000.00

16 Tukang Cat oh 60,000.00

17 Tukang Kayu oh 55,000.00

18 Buruh oh 55,000.00

19 Pekerja Profil Arsistik oh 150,000.00

NO Uraian Satuan Kode Ket

II. MATERIALA Material Galian

1 Aspal kg 10,819.31

2 Batu Bata Mutu Baik bh 600.00

3 Batu Bata Mutu Sedang bh 400.00

4 Batu Belah 189,200.00

5 Batu Kali Bulat 189,200.00

6 Batu Pecah (Stone Crusher) 0,5 - 1 Cm 189,200.00

7 Batu Pecah (Stone Crusher) 1 - 2 Cm 189,200.00

8 Batu Pecah (Stone Crusher) 2 - 3 Cm 189,200.00

9 Batu Pecah (Stone Crusher) 3 - 5 Cm 189,200.00

10 Batu Pecah (Stone Crusher) 5 - 7 Cm 189,200.00

11 Batu Pecah (Stone Crusher) 7 - 10 Cm 189,200.00

12 Filler kg 1,126.00

13 Kerikil 179,000.00

14 Kerikil Sungai tak diayak/Sirtu 111,400.00

15 Pasir Pasangan 170,100.00

16 Pasir Timbun / Urug 42,600.00

17 Tanah Urug / Timbunan Biasa 40,000.00

18 Tanah Urug / Timbunan Pilihan 45,000.00

B Material Kayu

1 Kayu Bekisting / Mal 1,850,000.00

2 Kayu Klas I 3,705,000.00

3 Kayu Klas II 3,087,000.00

4 Kayu Klas III 2,470,000.00

5 Kayu Perancah 1,852,500.00

6 Kayu Dolken bh 24,700.00

7 Kayu Bakar 617,500.00

Upah Tenaga Kerja (Rp)

Harga di Quary (Rp)

Jarak Angkut (km)

Upah Angkut (Rp)

Jumlah Harga (Rp)

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 2: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

NO Uraian Satuan Kode KetHarga di Quary (Rp)

Jarak Angkut (km)

Upah Angkut (Rp)

Jumlah Harga (Rp)

C Material Olahan

1 Batako (Hollow Brick) bh 2,840.50

2 Batako Krawang (Roster) bh 2,700.00

3 Batu Berongga Ekspos bh 2,200.00

4 Gorong-Gorong f 40 cm m 92,316.25

5 Gorong-Gorong f 60 cm m 134,923.75

6 Gorong-Gorong f 80 cm m 216,125.00

7 Gorong-Gorong f 100 cm m 213,037.50

8 Paving Block / Con Block bh 2,250.00

D Material Produk Pertamina

1 Minyak Bensin ltr 5,400.00 on site

2 Minyak Pelumas (Oli) ltr 30,000.00

3 Minyak Solar ltr 5,160.00 on site

4 Minyak Tanah ltr 5,040.00

E Material Toko

1 Amplas lbr 2,627.46

2 Air ltr 320.00

3 Atap Asbes lbr 65,331.50

4 Atap Genteng Metal Multy Roof (40 x 100 cm) lbr 81,664.38

5 Atap Genteng Metal Multy Roof (80 x 100 cm) lbr 106,163.69

6 Atap Nok Atas (C) Genteng Metal Multy Roof lbr 30,109.30

7 Atap Nok Atas (U) Genteng Metal Multy Roof lbr 44,737.88

8 Atap Nok Pinggir (P) Genteng Metal Multy Roof lbr 40,137.50

9 Atap Viber Glass Tipis lbr 49,400.00

10 Atap Viber Glass Medium lbr 74,100.00

11 Atap Vinyl Gelombang (80 x 180 cm) lbr 114,330.13

12 Atap Poly Carbonat tebal= 5mm merk Twinlite 248,540.00

13 Atap Genteng Beton bh 9,941.75

14 Atap Bubungan Genteng Beton bh 122,495.95

15 Atap Metal Okayru Tipe Biasa (73 x 120 cm) bh 75,557.30

16 Bubungan Atap Metal Okayru Tipe Biasa bh 63,627.20

17 Atap Metal Okayru Tipe Kedap Suara /Panas (73 x 120 cm) bh 90,469.93

18 Bubungan Atap Metal Okayru Tipe Kedap Suara /Panas bh 63,698.21

19 Atap Metal Komura Tipe Biasa (76 x 120 cm) bh 105,950.65

20 Bubungan Atap Metal Komura Tipe Biasa bh 63,698.21

21 Atap Metal Komura Tipe Kedap Suara /Panas (76 x 120 cm) bh 105,950.65

22 Bubungan Atap Metal Komura Tipe Kedap Suara /Panas bh 63,698.21

23 Atap Wall Flasing Genteng Metal Multy Roof lbr 105,950.65

24 Bak Air Viber Glass 60 x 60 Cm bh 197,600.00

25 Bak Air Viber Glass 70 x 70 Cm bh 222,300.00

26 Bak Air Viber Glass 80 x 80 Cm bh 247,000.00

27 Batu tempel hitam 175,000.00

28 Baut Begel f 12 mm - 30 cm bh 16,332.88

29 Baut Begel f 12 mm / Sengkang Kuda-kuda kg 12,072.13

30 Besi Beton Polos kg 12,350.00

31 Besi Beton Ulir kg 11,500.00

32 Besi Profil kg 12,075.00

33 Box MCB isi 4 bh 35,506.25

34 Box MCB isi 8 bh 56,810.00

35 Box Zekering Bagus bh 42,607.50

36 Box Zekering Biasa bh 20,995.00

m2

m2

Page 3: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

NO Uraian Satuan Kode KetHarga di Quary (Rp)

Jarak Angkut (km)

Upah Angkut (Rp)

Jumlah Harga (Rp)

37 Cat Aqua Prof bh 35,000.00

38 Cat Besi / Menie Besi kg 15,437.50

39 Cat Kilat / Minyak (isi 0,8 liter) kg 40,137.50

40 Cat Tembok kg 8,645.00

41 Cat Tembok (Merek Dulux dan Sejenisnya) kg 24,000.00

42 Cat Tembok (Merek Metrolite dan Sejenisnya) kg 21,612.50

43 Cat Tembok (Merek Puma dan Sejenisnya) kg 13,492.38

44 Cincin Keramik 10 cm m' 12,072.13

45 Cincin Keramik 20 cm m' 7,410.00

46 Dempul Kayu kg 30,875.00

47 Engsel Jendela 3" Mutu Bagus (Merek SES) bh 18,525.00

48 Engsel Jendela 3" Mutu Sedang (Merek RCH) bh 12,350.00

49 Engsel Pintu 4" Mutu Bagus (Merek SES) bh 24,700.00

50 Engsel Pintu 4" Mutu Sedang (Merek RCH) bh 18,525.00

51 Flange Spigot Dia 2" unit 71,012.50

52 Flange Spigot Dia 3" unit 85,215.00

53 Flange Spigot Dia 4" unit 120,721.25

54 Floor Drain (Bagus) bh 24,854.38

55 Floor Drain (Biasa) bh 11,362.00

56 Formika lbr 85,215.00

57 Granit kg 11,360.00

58 Granit Putih kg 18,463.25

59 Granit Lantai 30 x 30 Cm (Merek Impero & sejenisnya) bh 45,695.00

60 Granit Lantai 40 x 40 Cm (Merek Impero & sejenisnya) bh 51,870.00

61 Grendel Jendela Bagus bh 9,231.63

62 Grendel Jendela Biasa bh 3,550.63

63 Grendel Pintu Biasa bh 9,262.50

64 Grendel Pintu Tanam set 85,215.00

65 Hak Angin bh 32,500.00

66 Ijuk Kg 18,500.00

67 Instalasi Listrik Titik 80,000.00

68 Kaca Bening 3 mm 55,575.00

69 Kaca Bening 5 mm 83,362.50

70 Kaca Blok (Block Glass) bh 24,700.00

71 Kaca Es 3 mm 78,113.75

72 Kaca Es 5 mm 113,620.00

73 Kaca Ray Ban 3 mm 86,450.00

74 Kaca Ray Ban 5 mm 98,800.00

75 Kait Angin Jendela bh 30,875.00

76 Karpet 35,000.00

77 Kawat Beton kg 16,055.00

78 Kawat Las kg 93,860.00

79 Kawat Bronjong f 4 mm Kg 17,290.00

80 Kawat Harmonika (Wire Mes Dia 2,7 mm) 42,607.50

81 Kawat Harmonika (Wire Mes Dia 3 mm) 63,911.25

82 Kawat Nyamuk Uk 90 x 100 cm m 21,612.50

83 Kawat Bronjong kg 20,700.00

84 Keramik 10 x 20 cm (Plint) Merek Ikad & sejenisnya bh 2,130.38

85 Keramik 10 x 30 cm (Plint) Merek Ikad & sejenisnya bh 2,414.43

86 Keramik 20 x 20 Cm (Lantai) Merek Ikad & sejenisnya bh 3,000.00

87 Keramik 20 x 25 Cm (Dinding) Merek Ikad & Sejenisnya bh 4,075.50

88 Keramik 30 x 30 Cm (Lantai) Merek Ikad & sejenisnya bh 5,500.00

89 Plint Keramik 10/30 bh 3,266.58

90 Keramik 40 x 40 Cm (Lantai) Merek Ikad & sejenisnya bh 14,727.38

m2

m2

m2

m2

m2

m2

m2

m2

m2

Page 4: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

NO Uraian Satuan Kode KetHarga di Quary (Rp)

Jarak Angkut (km)

Upah Angkut (Rp)

Jumlah Harga (Rp)

91 Keramik 10 x 40 cm (Plint) Merek Ikad & sejenisnya bh 3,976.70

92 Keramik Artistik bh 15,500.00

93 Kloset Duduk Merk American Standard unit 1,988,350.00

94 Kloset Duduk Merk KIA unit 2,130,375.00

95 Kloset Duduk Merk Toto unit 2,840,500.00

96 Kloset Jongkok Merk American Standart unit 191,733.75

97 Kloset Jongkok Merk Duty unit 160,550.00

98 Kloset Jongkok Merk KIA unit 177,531.25

99 Kloset Jongkok Merk Toto unit 220,000.00

100 Kran Air Biasa bh 14,912.63

101 Kran Air Mutu Bagus bh 38,750.00

102 Kuas Biasa 1" bh 3,976.70

103 Kuas Biasa 2" bh 5,325.94

104 Kuas Biasa 2,5" bh 7,410.00

105 Kuas Biasa 3" bh 8,645.00

106 Kuas Biasa 4" bh 13,585.00

107 Kuas Roda 4" bh 18,525.00

108 Kuas Roda 5" bh 21,612.50

109 Kunci Pintu Bulat bh 78,113.75

110 Kunci Pintu Doble Slag Besar (Merek SES) set 225,000.00

111 Kunci Pintu Doble Slag Kecil (Mutu Sedang) set 113,620.00

112 Lampu Philips Essential (Hemat Energi) 15 - 20 Watt bh 49,708.75

113 Lampu Philips Essential (Hemat Energi) 20 - 40 Watt bh 63,911.25

114 Lampu Pijar 25 Watt 10 - 25 Watt bh 3,705.00

115 Lampu Baret 40 Watt bh 113,620.00

116 Lampu TL Lux Philips (Bambu) 1 x 40 Watt set 248,543.75

117 Lampu TL Lux Philips (Bambu) 2 x 40 Watt set 284,050.00

118 Lampu TL Philips 2 x 20 Watt set 142,025.00

119 Lampu TL Philips 2 x 40 Watt set 177,531.25

120 Lampu TL Philips 20 Watt set 78,113.75

121 Lampu TL Philips 40 Watt set 92,316.25

122 Lem Aica Aibon isi 1 kg klg 43,225.00

123 Lem Kayu Merk FOX kg 24,854.38

124 Lem Pipa PVC kg 56,810.00

125 List Kayu 1x4 cm dirouter m 9,880.00

126 List Profil Kayu 2x2 cm m 9,880.00

127 List Profil Kayu 3x3 cm m 11,115.00

128 List Profil Kayu 4x4 cm m 12,350.00

129 List Profil Gipsum m 21,000.00

130 MCB bh 13,492.38

131 Minyak Cat / Menie Kayu ltr 18,525.00

132 Multiplek 9 mm lbr 209,950.00

133 Paku Asbes kg 24,700.00

134 Paku Atap Genteng Metal / Aluminium kg 32,665.75

135 Paku Biasa 1 - 2" kg 16,055.00

136 Paku Biasa 2 - 5" kg 16,055.00

137 Paku Seng kg 21,303.75

138 Paku Skrup kg 34,000.00

139 Paku Triplek kg 17,290.00

140 Papan Gipsum Lbr 113,620.00

141 Papan Lambisering 8 cm x 4 m (Kayu Marsawa & Sejenis) m3 3,859,375.00

142 Papan Lambisering 8 cm x 4 m (Kayu Meranti) m3 3,698,569.00

143 Pipa Stainless Steel Dia 0,5" tebal =1 mm m 19,599.45

144 Pipa Stainless Steel Dia 0,75" tebal =1 mm m 32,665.75

Page 5: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

NO Uraian Satuan Kode KetHarga di Quary (Rp)

Jarak Angkut (km)

Upah Angkut (Rp)

Jumlah Harga (Rp)

145 Pipa Stainless Steel Dia 1" tebal =1 mm m 48,998.63

146 Pipa Stainless Steel Dia 1,25" tebal =1 mm m 65,331.50

147 Pipa Stainless Steel Dia 1,5" tebal =1 mm m 72,432.75

148 Pipa Stainless Steel Dia 1,5" tebal =1,22 mm m 78,113.75

149 Pipa Stainless Steel Dia 2" tebal =1,2 mm m 85,215.00

150 Pipa Stainless Steel Dia 2,5" tebal =1,2 mm m 99,417.50

151 Pipa Galvanis (Medium/Tebal) Dia 0,5" m 18,525.00

152 Pipa Galvanis (Medium/Tebal) Dia 1" m 32,110.00

153 Pipa Galvanis (Medium/Tebal) Dia 1,25" m 39,056.88

154 Pipa Galvanis (Medium/Tebal) Dia 1,5" m 49,708.75

155 Pipa Galvanis (Medium/Tebal) Dia 2" m 92,316.25

156 Pipa Galvanis (Medium/Tebal) Dia 3" m 92,625.00

157 Pipa Galvanis (Medium/Tebal) Dia 3/4" m 22,230.00

158 Pipa Galvanis (Medium/Tebal) Dia 4" m 156,227.50

159 Pipa Besi Dia 6" m 206,245.00

160 Pipa PVC SII Dia 0,5" m 8,450.49

161 Pipa PVC SII Dia 3/4" m 11,788.08

162 Pipa PVC SII Dia 1" m 16,048.83

163 Pipa PVC SII Dia 1.5" m 28,902.09

164 Pipa PVC SII Dia 2" m 36,571.44

165 Pipa PVC SII Dia 3" m 71,225.54

166 Pipa PVC SII Dia 4" m 35,506.25

167 Pipa PVC AW Dia 0,5" m 7,000.00

168 Pipa PVC AW Dia 3/4" m 10,012.76

169 Pipa PVC AW Dia 1" m 13,563.39

170 Pipa PVC AW Dia 1.5" m 24,428.30

171 Pipa PVC AW Dia 2" m 30,000.00

172 Pipa PVC AW Dia 3" m 60,218.60

173 Pipa PVC AW Dia 4" m 80,000.00

174 Pipa AW Dia 6" m 102,000.00

175 Plamour Tembok kg 24,700.00

176 Pelat Stainless steel t=1,2 mm 653,315.00

177 Plitur Impra Bening kg 43,225.00

178 Plitur Impra Warna kg 48,288.50

179 Plywood Lbr 81,650.00

180 Residu Ltr 9,880.00

181 Saklar Seri Putih bh 18,525.00

182 Saklar Seri Warna bh 28,405.00

183 Saklar Tunggal Putih bh 16,055.00

184 Saklar Tunggal Warna bh 22,724.00

185 Sarang Lampu Down Light bh 50,000.00

186 Semen Portlant kg 1,276.00

187 Semen Putih kg 2,070.00

188 Semen Warna kg 6,325.00

189 Seng Gelombang BJLS 20 lbr 42,000.00

190 Seng Gelombang BJLS 20 Warna lbr 67,925.00

191 Seng Plat BJLS 20 Biasa lbr 52,487.50

192 Seng Plat BJLS 20 Warna lbr 73,142.88

193 Sirlak kg 39,767.00

194 Spirtus ltr 9,231.63

195 Stop Kontak Biasa (Merek Voltama) bh 18,525.00

196 Stop Kontak Warna (Merek Voltama) bh 22,724.00

197 Tarikan Jendela Set 7,000.00

198 Teak Wood 2,6 mm lbr 93,860.00

m2

Page 6: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

NO Uraian Satuan Kode KetHarga di Quary (Rp)

Jarak Angkut (km)

Upah Angkut (Rp)

Jumlah Harga (Rp)

199 Teak Wood 3,6 mm lbr 99,417.50

200 Tegel Lantai 20 x 20 cm bh 2,130.38

201 Tegel Plint 10 x 20 cm bh 1,420.28

202 Tepung Mill kg 18,463.25

203 Tepung Gipsum kg 15,200.00

204 Thiner ltr 24,700.00

205 Triplek 2,6 mm lbr 45,000.00

206 Triplek 3,6 mm lbr 55,000.00

207 Valve Dia 2" unit 596,505.00

208 Valve Dia 3" unit 752,732.50

209 Valve Dia 4" unit 1,107,795.00

210 Valve Dia 6" merk AW unit 1,562,275.00

211 Wastafel Aluminium bh 355,062.50

212 Wastafel Keramik (Merk American Standard) bh 639,112.50

213 Wastafel Keramik (Merk KIA) bh 852,150.00

214 Wastafel Keramik (Merk Toto) bh 710,123.00

215 Pagar Besi Berprofil m2 250,000.00

216 Pagar Besi Pipa m2 280,000.00

217 Pagar Besi U m2 395,000.00

218 Cerucuk Bambu bh 8,750.00

219 GRC lbr 85,000.00

220 Aluminium btg 70,000.00

Catatan : Harga Sudah Termasuk Pajak Galian C, Pph , dan

Upah angkut

Page 7: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

ANALISA HARGA SATUAN PEKERJAANNo. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

PEKERJAAN PERSIAPAN 100.00 Pekerjaan Pengukuran

8.0000 org Pekerja @ Rp. 50,000.00 400,000.00

2.0000 org Mandor @ Rp. 65,000.00 130,000.00

0.5000 org Pengawas @ Rp. 75,000.00 37,500.00

2.0000 org Asisten Ahli Ukur @ Rp. 65,000.00 130,000.00

1.0000 hr Sewa alat ukur @ Rp. 150,000.00 150,000.00

JUMLAH ( BELUM PPN ) 847,500.00 847,500.00

OVERHEAD 10 % 84,750.00 84,750.00

JUMLAH 932,250.00 932,250.00

DIBULATKAN 932,250.00 932,250.00

1.0000 Pekerjaan Pengukuran

0.01 x 932,250.00 9,322.50 9,322.50

1.0000 Pemasangan bouwplank

0.0120 Kayu Kelas II 5/7 @ Rp. 3,087,000.00 37,044.00

0.0200 kg Paku reng @ Rp. 16,055.00 321.10

0.0070 Kayu kelas II papan 3/20 @ Rp. 3,087,000.00 21,609.00

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang kayu @ Rp. 75,000.00 750.00

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

0.0050 org Mandor @ Rp. 65,000.00 325.00

JUMLAH ( BELUM PPN ) 11,575.00 58,974.10 70,549.10

OVERHEAD 10 % 1,157.50 5,897.41 7,054.91

JUMLAH 12,732.50 64,871.51 77,604.01

DIBULATKAN 12,732.00 64,871.00 77,604.00

1.0000 Membersihkan lapangan/ lokasi pekerjaan

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

0.0500 org Mandor @ Rp. 65,000.00 3,250.00

JUMLAH ( BELUM PPN ) 8,250.00 8,250.00

OVERHEAD 10 % 825.00 825.00

JUMLAH 9,075.00 9,075.00

DIBULATKAN 9,075.00 9,075.00

PEKERJAAN TANAH 1.0000 Galian tanah biasa sedalam sampai 1 meter

0.7500 org Pekerja @ Rp. 50,000.00 37,500.00

0.0250 org Mandor @ Rp. 65,000.00 1,625.00

JUMLAH ( BELUM PPN ) 39,125.00 39,125.00

OVERHEAD 10 % 3,912.50 3,912.50

JUMLAH 43,037.50 43,037.50

DIBULATKAN 43,037.00 43,037.00

1.0000 Galian tanah biasa sedalam 1 - 2 meter

0.9000 org Pekerja @ Rp. 50,000.00 45,000.00

0.0450 org Mandor @ Rp. 65,000.00 2,925.00

JUMLAH ( BELUM PPN ) 47,925.00 47,925.00

OVERHEAD 10 % 4,792.50 4,792.50

JUMLAH 52,717.50 52,717.50

m2

m2

m1

m3

m3

m2

m3

m3

Page 8: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

DIBULATKAN 52,717.00 52,717.00

1.0000 Galian tanah biasa sedalam 2 - 3 meter

1.0500 org Pekerja @ Rp. 50,000.00 52,500.00

0.0670 org Mandor @ Rp. 65,000.00 4,355.00

JUMLAH ( BELUM PPN ) 56,855.00 56,855.00

OVERHEAD 10 % 5,685.50 5,685.50

JUMLAH 62,540.50 62,540.50

DIBULATKAN 62,540.00 62,540.00

1.0000 Galian tanah keras sedalam sampai 1 meter

1.0000 org Pekerja @ Rp. 50,000.00 50,000.00

0.0320 org Mandor @ Rp. 65,000.00 2,080.00

JUMLAH ( BELUM PPN ) 52,080.00 52,080.00

OVERHEAD 10 % 5,208.00 5,208.00

JUMLAH 57,288.00 57,288.00

DIBULATKAN 57,288.00 57,288.00

1.0000 Galian tanah cadas sedalam sampai 1 meter

1.5000 org Pekerja @ Rp. 50,000.00 75,000.00

0.0600 org Mandor @ Rp. 65,000.00 3,900.00

JUMLAH ( BELUM PPN ) 78,900.00 78,900.00

OVERHEAD 10 % 7,890.00 7,890.00

JUMLAH 86,790.00 86,790.00

DIBULATKAN 86,790.00 86,790.00

1.0000 Galian tanah lumpur sedalam 1 meter

1.2000 org Pekerja @ Rp. 50,000.00 60,000.00

0.0450 org Mandor @ Rp. 65,000.00 2,925.00

JUMLAH ( BELUM PPN ) 62,925.00 62,925.00

OVERHEAD 10 % 6,292.50 6,292.50

JUMLAH 69,217.50 69,217.50

DIBULATKAN 69,217.00 69,217.00

Mod. SNI 6.3 1.0000 Membuat sumur

2.0000 bh Buis beton D. 80 cm @ Rp. 216,125.00 432,250.00

1.0000 org Tukang gali sumur @ Rp. 55,000.00 55,000.00

0.7350 org Pekerja @ Rp. 50,000.00 36,750.00

0.0735 org Mandor @ Rp. 65,000.00 4,777.50

JUMLAH ( BELUM PPN ) 96,527.50 432,250.00 528,777.50

OVERHEAD 10 % 9,652.75 43,225.00 52,877.75

JUMLAH 106,180.25 475,475.00 581,655.25

DIBULATKAN 106,180.00 475,475.00 581,655.00

A6 1.0000 Mengangkut tanah sejauh 30 meter

0.3300 org Pekerja @ Rp. 50,000.00 16,500.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 17,150.00 17,150.00

OVERHEAD 10 % 1,715.00 1,715.00

JUMLAH 18,865.00 18,865.00

DIBULATKAN 18,865.00 18,865.00

1.0000 Pembuangan tanah sejauh 15 meter

0.3300 org Pekerja @ Rp. 50,000.00 16,500.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

m3

m3

m3

m3

m1

m3

m3

Page 9: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

JUMLAH ( BELUM PPN ) 17,150.00 17,150.00

OVERHEAD 10 % 1,715.00 1,715.00

JUMLAH 18,865.00 18,865.00

DIBULATKAN 18,865.00 18,865.00

A14 1.0000 Membuang tanah dengan menghampar

0.2500 org Pekerja @ Rp. 50,000.00 12,500.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 13,150.00 13,150.00

OVERHEAD 10 % 1,315.00 1,315.00

JUMLAH 14,465.00 14,465.00

DIBULATKAN 14,465.00 14,465.00

1.0000 Urug kembali bekas galian

1/3 x 43,037.00 14,345.67 - 14,345.67

1.0000 Memadatkan tanah (per 20 cm)

0.5000 org Pekerja @ Rp. 50,000.00 25,000.00

0.0500 org Mandor @ Rp. 65,000.00 3,250.00

JUMLAH ( BELUM PPN ) 28,250.00 28,250.00

OVERHEAD 10 % 2,825.00 2,825.00

JUMLAH 31,075.00 31,075.00

DIBULATKAN 31,075.00 31,075.00

1.0000 Urug pasir

1.2000 Pasir urug @ Rp. 170,100.00 204,120.00

0.3000 org Pekerja @ Rp. 50,000.00 15,000.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 15,650.00 204,120.00 219,770.00

OVERHEAD 10 % 1,565.00 20,412.00 21,977.00

JUMLAH 17,215.00 224,532.00 241,747.00

DIBULATKAN 17,215.00 224,532.00 241,747.00

1.0000 Urug tanah mendatangkan

1.2000 Tanah urug @ Rp. 40,000.00 48,000.00

0.3000 org Pekerja @ Rp. 50,000.00 15,000.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 15,650.00 48,000.00 63,650.00

OVERHEAD 10 % 1,565.00 4,800.00 6,365.00

JUMLAH 17,215.00 52,800.00 70,015.00

DIBULATKAN 17,215.00 52,800.00 70,015.00

1.0000 Urugan sirtu

1.2000 Sirtu @ Rp. 111,400.00 133,680.00

0.2500 org Pekerja @ Rp. 50,000.00 12,500.00

0.0250 org Mandor @ Rp. 65,000.00 1,625.00

JUMLAH ( BELUM PPN ) 14,125.00 133,680.00 147,805.00

OVERHEAD 10 % 1,412.50 13,368.00 14,780.50

JUMLAH 15,537.50 147,048.00 162,585.50

DIBULATKAN 15,537.00 147,048.00 162,585.00

1.0000 Pemasangan lapisan ijuk

m3

m3

m2

m3

m3

m3

m3

m3

m3

m3

Page 10: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

1.2000 Ijuk @ Rp. 160,000.00 192,000.00

0.2500 org Pekerja @ Rp. 50,000.00 12,500.00

0.0250 org Mandor @ Rp. 65,000.00 1,625.00

JUMLAH ( BELUM PPN ) 14,125.00 192,000.00 206,125.00

OVERHEAD 10 % 1,412.50 19,200.00 20,612.50

JUMLAH 15,537.50 211,200.00 226,737.50

DIBULATKAN 15,537.00 211,200.00 226,737.00

PEKERJAAN PASANGAN

1.0000 Pasangan pondasi batu kosong

1.2000 Batu belah 15/20 cm @ Rp. 189,200.00 227,040.00

0.4320 Pasir urug @ Rp. 170,100.00 73,483.20

0.3900 org Tukang batu @ Rp. 55,000.00 21,450.00

0.0390 org Kepala tukang batu @ Rp. 75,000.00 2,925.00

0.7800 org Pekerja @ Rp. 50,000.00 39,000.00

0.0390 org Mandor @ Rp. 65,000.00 2,535.00

JUMLAH ( BELUM PPN ) 65,910.00 300,523.20 366,433.20

OVERHEAD 10 % 6,591.00 30,052.32 36,643.32

JUMLAH 72,501.00 330,575.52 403,076.52

DIBULATKAN 72,501.00 330,575.00 403,076.00

1.0000 Pasangan pondasi 1 Pc : 4 Ps

1.2000 Batu belah 15/20 cm @ Rp. 189,200.00 227,040.00

163.0000 kg PC @ Rp. 1,276.00 207,988.00

0.5200 Pasir pasang @ Rp. 170,100.00 88,452.00

0.7500 org Tukang batu @ Rp. 55,000.00 41,250.00

0.0750 org Kepala tukang batu @ Rp. 75,000.00 5,625.00

1.5000 org Pekerja @ Rp. 50,000.00 75,000.00

0.0750 org Mandor @ Rp. 65,000.00 4,875.00

JUMLAH ( BELUM PPN ) 126,750.00 523,480.00 650,230.00

OVERHEAD 10 % 12,675.00 52,348.00 65,023.00

JUMLAH 139,425.00 575,828.00 715,253.00

DIBULATKAN 139,425.00 575,828.00 715,253.00

1.0000 Pasangan pondasi 1 Pc : 3 Ps

1.2000 Batu belah 15/20 cm @ Rp. 189,200.00 227,040.00

202.0000 kg PC @ Rp. 1,276.00 257,752.00

0.4850 Pasir pasang @ Rp. 170,100.00 82,498.50

0.7500 org Tukang batu @ Rp. 55,000.00 41,250.00

0.0750 org Kepala tukang batu @ Rp. 75,000.00 5,625.00

1.5000 org Pekerja @ Rp. 50,000.00 75,000.00

0.0750 org Mandor @ Rp. 65,000.00 4,875.00

JUMLAH ( BELUM PPN ) 126,750.00 567,290.50 694,040.50

OVERHEAD 10 % 12,675.00 56,729.05 69,404.05

JUMLAH 139,425.00 624,019.55 763,444.55

DIBULATKAN 139,425.00 624,019.00 763,444.00

1.0000 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps

m3

m3

m3

m3

m3

m3

m3

m3

m3

m3

m2

Page 11: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

70.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 600.00 42,000.00

11.5000 kg PC @ Rp. 1,276.00 14,674.00

0.0430 Pasir pasang @ Rp. 170,100.00 7,314.30

0.1000 org Tukang batu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang batu @ Rp. 75,000.00 750.00

0.3000 org Pekerja @ Rp. 50,000.00 15,000.00

0.0150 org Mandor @ Rp. 65,000.00 975.00

JUMLAH ( BELUM PPN ) 22,225.00 63,988.30 86,213.30

OVERHEAD 10 % 2,222.50 6,398.83 8,621.33

JUMLAH 24,447.50 70,387.13 94,834.63

DIBULATKAN 24,447.00 70,387.00 94,834.00

1.0000 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps

140.0000 bh Bata merah 5 x 11 x 22 cm @ Rp. 600.00 84,000.00

26.5500 kg PC @ Rp. 1,276.00 33,877.80

0.0930 Pasir pasang @ Rp. 170,100.00 15,819.30

0.2000 org Tukang batu @ Rp. 55,000.00 11,000.00

0.0200 org Kepala tukang batu @ Rp. 75,000.00 1,500.00

0.6000 org Pekerja @ Rp. 50,000.00 30,000.00

0.0300 org Mandor @ Rp. 65,000.00 1,950.00

JUMLAH ( BELUM PPN ) 44,450.00 133,697.10 178,147.10

OVERHEAD 10 % 4,445.00 13,369.71 17,814.71

JUMLAH 48,895.00 147,066.81 195,961.81

DIBULATKAN 48,895.00 147,066.00 195,961.00

SNI 1.0000 Pasangan dinding bataco

6.18 12.5000 bh Bataco @ Rp. 2,840.50 35,506.25

12.5000 kg PC @ Rp. 1,276.00 15,950.00

0.0400 Pasir pasang @ Rp. 170,100.00 6,804.00

0.1000 org Tukang batu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang batu @ Rp. 75,000.00 750.00

0.5000 org Pekerja @ Rp. 50,000.00 25,000.00

0.0250 org Mandor @ Rp. 65,000.00 1,625.00

JUMLAH ( BELUM PPN ) 32,875.00 58,260.25 91,135.25

OVERHEAD 10 % 3,287.50 5,826.03 9,113.53

JUMLAH 36,162.50 64,086.28 100,248.78

DIBULATKAN 36,162.00 64,086.00 100,248.00

SNI 1.0000 Pasangan roster 25/25 cm

6.19 16.0000 bh Roster 25/25 cm @ Rp. 2,700.00 43,200.00

12.5000 kg PC @ Rp. 1,276.00 15,950.00

0.0400 Pasir pasang @ Rp. 170,100.00 6,804.00

0.1000 org Tukang batu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang batu @ Rp. 75,000.00 750.00

0.5000 org Pekerja @ Rp. 50,000.00 25,000.00

0.0250 org Mandor @ Rp. 65,000.00 1,625.00

JUMLAH ( BELUM PPN ) 32,875.00 65,954.00 98,829.00

OVERHEAD 10 % 3,287.50 6,595.40 9,882.90

JUMLAH 36,162.50 72,549.40 108,711.90

DIBULATKAN 36,162.00 72,549.00 108,711.00

SNI 1.0000 Pasangan paving block/conblock

6.20 1.0000 bh Paving block/conblock @ Rp. 2,250.00 2,250.00

0.0400 Urug pasir @ Rp. 42,600.00 1,704.00

0.1000 org Tukang batu @ Rp. 75,000.00 7,500.00

m3

m2

m3

m2

m3

m2

m3

m2

m3

Page 12: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

0.0100 org Kepala tukang batu @ Rp. 50,000.00 500.00

0.2000 org Pekerja @ Rp. 65,000.00 13,000.00

0.0250 org Mandor @ Rp. 65,000.00 1,625.00

JUMLAH ( BELUM PPN ) 22,625.00 3,954.00 26,579.00

OVERHEAD 10 % 2,262.50 395.40 2,657.90

JUMLAH 24,887.50 4,349.40 29,236.90

DIBULATKAN 24,887.00 4,349.00 29,236.00

PEKERJAAN BETON 1.0000 Membuat beton dengan mutu K 225

371.0000 kg PC @ Rp. 1,276.00 473,396.00

0.6500 Pasir beton @ Rp. 170,100.00 110,565.00

0.6980 Kerikil beton @ Rp. 179,000.00 124,942.00

0.2750 org Tukang batu @ Rp. 55,000.00 15,125.00

0.0280 org Kepala tukang batu @ Rp. 75,000.00 2,100.00

1.6500 org Pekerja @ Rp. 50,000.00 82,500.00

0.0830 org Mandor @ Rp. 65,000.00 5,395.00

JUMLAH ( BELUM PPN ) 105,120.00 708,903.00 814,023.00

OVERHEAD 10 % 10,512.00 70,890.30 81,402.30

JUMLAH 115,632.00 779,793.30 895,425.30

DIBULATKAN 115,632.00 779,793.00 895,425.00

SNI 1.0000 Membuat beton dengan mutu K 275

6.36 406.0000 kg PC @ Rp. 1,276.00 518,056.00

0.6840 Pasir beton @ Rp. 170,100.00 116,348.40

1.0260 Kerikil beton @ Rp. 179,000.00 183,654.00

0.2750 org Tukang batu @ Rp. 55,000.00 15,125.00

0.0280 org Kepala tukang batu @ Rp. 75,000.00 2,100.00

1.6500 org Pekerja @ Rp. 50,000.00 82,500.00

0.0830 org Mandor @ Rp. 65,000.00 5,395.00

JUMLAH ( BELUM PPN ) 105,120.00 818,058.40 923,178.40

OVERHEAD 10 % 10,512.00 81,805.84 92,317.84

JUMLAH 115,632.00 899,864.24 1,015,496.24

DIBULATKAN 115,632.00 899,864.00 1,015,496.00

1.0000 Membuat beton dengan mutu K 300

413.0000 kg PC @ Rp. 1,276.00 526,988.00

0.6810 Pasir beton @ Rp. 170,100.00 115,838.10

1.0210 Kerikil beton @ Rp. 179,000.00 182,759.00

0.2750 org Tukang batu @ Rp. 55,000.00 15,125.00

0.0280 org Kepala tukang batu @ Rp. 75,000.00 2,100.00

1.6500 org Pekerja @ Rp. 50,000.00 82,500.00

0.0830 org Mandor @ Rp. 65,000.00 5,395.00

JUMLAH ( BELUM PPN ) 105,120.00 825,585.10 930,705.10

OVERHEAD 10 % 10,512.00 82,558.51 93,070.51

JUMLAH 115,632.00 908,143.61 1,023,775.61

DIBULATKAN 115,632.00 908,143.00 1,023,775.00

1.0000 kg Pembesian dengan besi polos

1.0500 kg Besi beton polos @ Rp. 12,350.00 12,967.50

0.0150 kg Kawat beton @ Rp. 16,055.00 240.83

0.0070 org Tukang besi @ Rp. 55,000.00 385.00

0.0007 org Kepala tukang besi @ Rp. 75,000.00 52.50

0.0070 org Pekerja @ Rp. 50,000.00 350.00

0.0003 org Mandor @ Rp. 65,000.00 19.50

JUMLAH ( BELUM PPN ) 807.00 13,208.33 14,015.33

m3

m3

m3

m3

m3

m3

m3

m3

m3

Page 13: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

OVERHEAD 10 % 80.70 1,320.83 1,401.53

JUMLAH 887.70 14,529.16 15,416.86

DIBULATKAN 887.00 14,529.00 15,416.00

1.0000 kg Pembesian dengan besi ulir

1.0500 kg Besi beton ulir @ Rp. 11,500.00 12,075.00

0.0150 kg Kawat beton @ Rp. 16,055.00 240.83

0.0070 org Tukang besi @ Rp. 55,000.00 385.00

0.0007 org Kepala tukang besi @ Rp. 75,000.00 52.50

0.0070 org Pekerja @ Rp. 50,000.00 350.00

0.0003 org Mandor @ Rp. 65,000.00 19.50

JUMLAH ( BELUM PPN ) 807.00 12,315.83 13,122.83

OVERHEAD 10 % 80.70 1,231.58 1,312.28

JUMLAH 887.70 13,547.41 14,435.11

DIBULATKAN 887.00 13,547.00 14,435.00

1.0000 Membuat 1m³ Pondasi Beton Bertulang (150 Kg Besi + Bekisting)

5.3000 HO Pekerja @ Rp. 50,000.00 265,000.00

0.2650 HO Mandor @ Rp. 65,000.00 17,225.00

1.3000 HO Tukang Kayu @ Rp. 55,000.00 71,500.00

0.2750 HO Tukang Batu @ Rp. 55,000.00 15,125.00

1.0500 HO Tukang Besi @ Rp. 55,000.00 57,750.00

0.2620 HO Kepala Tukang @ Rp. 75,000.00 19,650.00

0.2000 M³ Kayu Bekisting @ Rp. 1,850,000.00 370,000.00

1.5000 Kg Paku @ Rp. 16,055.00 24,082.50

0.4000 Liter Minyak Bekisting @ Rp. 18,525.00 7,410.00

157.5000 Kg Besi Beton Polos @ Rp. 12,350.00 1,945,125.00

2.2500 Kg Kawat Beton @ Rp. 16,055.00 36,123.75

336.0000 Kg Semen Portland @ Rp. 1,276.00 428,736.00

0.5400 M³ Pasir Beton @ Rp. 170,100.00 91,854.00

0.8100 M³ Kerikil @ Rp. 179,000.00 144,990.00

JUMLAH ( BELUM PPN ) 446,250.00 3,048,321.25 3,494,571.25

OVERHEAD 10 % 44,625.00 304,832.13 349,457.13

JUMLAH 490,875.00 3,353,153.38 3,844,028.38

DIBULATKAN 490,875.00 3,353,153.00 3,844,028.00

1.0000 Membuat 1m³ Sloof Beton Bertulang (200 Kg Besi + Bekisting)

5.6500 HO Pekerja @ Rp. 50,000.00 282,500.00

0.2830 HO Mandor @ Rp. 65,000.00 18,395.00

1.5600 HO Tukang Kayu @ Rp. 55,000.00 85,800.00

0.2750 HO Tukang Batu @ Rp. 55,000.00 15,125.00

1.4000 HO Tukang Besi @ Rp. 55,000.00 77,000.00

0.3230 HO Kepala Tukang @ Rp. 75,000.00 24,225.00

0.2700 M³ Kayu Bekisting @ Rp. 1,850,000.00 499,500.00

2.0000 Kg Paku @ Rp. 16,055.00 32,110.00

0.6000 Liter Minyak Bekisting @ Rp. 18,525.00 11,115.00

210.0000 Kg Besi Beton Polos @ Rp. 12,350.00 2,593,500.00

3.0000 Kg Kawat Beton @ Rp. 16,055.00 48,165.00

336.0000 Kg Semen Portland @ Rp. 1,276.00 428,736.00

0.5400 M³ Pasir Beton @ Rp. 170,100.00 91,854.00

0.8100 M³ Kerikil @ Rp. 179,000.00 144,990.00

JUMLAH ( BELUM PPN ) 503,045.00 3,849,970.00 4,353,015.00

OVERHEAD 10 % 50,304.50 384,997.00 435,301.50

JUMLAH 553,349.50 4,234,967.00 4,788,316.50

DIBULATKAN 553,349.00 4,234,967.00 4,788,316.00

m3

m3

Page 14: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

1.0000 Membuat 1m³ Kolom Beton Bertulang (200 Kg Besi + Bekisting)

7.0500 HO Pekerja @ Rp. 50,000.00 352,500.00

0.3530 HO Mandor @ Rp. 65,000.00 22,945.00

1.6500 HO Tukang Kayu @ Rp. 55,000.00 90,750.00

0.2750 HO Tukang Batu @ Rp. 55,000.00 15,125.00

2.1000 HO Tukang Besi @ Rp. 55,000.00 115,500.00

0.4030 HO Kepala Tukang @ Rp. 75,000.00 30,225.00

0.4000 M³ Kayu Bekisting @ Rp. 1,850,000.00 740,000.00

4.0000 Kg Paku @ Rp. 16,055.00 64,220.00

2.0000 Liter Minyak Bekisting @ Rp. 18,525.00 37,050.00

210.0000 Kg Besi Beton Polos @ Rp. 12,350.00 2,593,500.00

3.0000 Kg Kawat Beton @ Rp. 16,055.00 48,165.00

336.0000 Kg Semen Portland @ Rp. 1,276.00 428,736.00

0.5400 M³ Pasir Beton @ Rp. 170,100.00 91,854.00

0.8100 M³ Kerikil @ Rp. 179,000.00 144,990.00

0.1500 M³ Balok Bekisting @ Rp. 1,850,000.00 277,500.00

3.5000 Lbr Plywood @ Rp. 81,650.00 285,775.00

20.0000 Btg Dolken Kayu Galam, Ø (8-10) cm, Panjang 4 m @ Rp. 24,700.00 494,000.00

JUMLAH ( BELUM PPN ) 627,045.00 5,205,790.00 5,832,835.00

OVERHEAD 10 % 62,704.50 520,579.00 583,283.50

JUMLAH 689,749.50 5,726,369.00 6,416,118.50

DIBULATKAN 689,749.00 5,726,369.00 6,416,118.00

1.0000 Membuat 1m³ Kolom Beton Bertulang (100 Kg Besi + Bekisting)

7.0500 HO Pekerja @ Rp. 50,000.00 352,500.00

0.3530 HO Mandor @ Rp. 65,000.00 22,945.00

1.6500 HO Tukang Kayu @ Rp. 55,000.00 90,750.00

0.2750 HO Tukang Batu @ Rp. 55,000.00 15,125.00

2.1000 HO Tukang Besi @ Rp. 55,000.00 115,500.00

0.4030 HO Kepala Tukang @ Rp. 75,000.00 30,225.00

0.4000 M³ Kayu Bekisting @ Rp. 1,850,000.00 740,000.00

4.0000 Kg Paku @ Rp. 16,055.00 64,220.00

2.0000 Liter Minyak Bekisting @ Rp. 18,525.00 37,050.00

105.0000 Kg Besi Beton Polos @ Rp. 12,350.00 1,296,750.00

1.5000 Kg Kawat Beton @ Rp. 16,055.00 24,082.50

336.0000 Kg Semen Portland @ Rp. 1,276.00 428,736.00

0.5400 M³ Pasir Beton @ Rp. 170,100.00 91,854.00

0.8100 M³ Kerikil @ Rp. 179,000.00 144,990.00

0.1500 M³ Balok Bekisting @ Rp. 1,850,000.00 277,500.00

3.5000 Lbr Plywood @ Rp. 81,650.00 285,775.00

20.0000 Btg Dolken Kayu Galam, Ø (8-10) cm, Panjang 4 m @ Rp. 24,700.00 494,000.00

JUMLAH ( BELUM PPN ) 627,045.00 3,884,957.50 4,512,002.50

OVERHEAD 10 % 62,704.50 388,495.75 451,200.25

JUMLAH 689,749.50 4,273,453.25 4,963,202.75

DIBULATKAN 689,749.00 4,273,453.00 4,963,202.00

1.0000 Membuat 1m³ Balok Beton Bertulang (200 Kg Besi + Bekisting)

6.3500 HO Pekerja @ Rp. 50,000.00 317,500.00

0.3180 HO Mandor @ Rp. 65,000.00 20,670.00

1.6500 HO Tukang Kayu @ Rp. 55,000.00 90,750.00

0.2750 HO Tukang Batu @ Rp. 55,000.00 15,125.00

1.4000 HO Tukang Besi @ Rp. 55,000.00 77,000.00

0.3330 HO Kepala Tukang @ Rp. 75,000.00 24,975.00

0.3200 M³ Kayu Bekisting @ Rp. 1,850,000.00 592,000.00

m3

m3

m3

Page 15: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

3.2000 Kg Paku @ Rp. 16,055.00 51,376.00

1.6000 Liter Minyak Bekisting @ Rp. 18,525.00 29,640.00

210.0000 Kg Besi Beton Polos @ Rp. 12,350.00 2,593,500.00

3.0000 Kg Kawat Beton @ Rp. 16,055.00 48,165.00

336.0000 Kg Semen Portland @ Rp. 1,276.00 428,736.00

0.5400 M³ Pasir Beton @ Rp. 170,100.00 91,854.00

0.8100 M³ Kerikil @ Rp. 179,000.00 144,990.00

0.1400 M³ Balok Bekisting @ Rp. 1,850,000.00 259,000.00

2.8000 Lbr Plywood @ Rp. 81,650.00 228,620.00

16.0000 Btg Dolken Kayu Galam, Ø (8-10) cm, Panjang 4 m @ Rp. 24,700.00 395,200.00

JUMLAH ( BELUM PPN ) 546,020.00 4,863,081.00 5,409,101.00

OVERHEAD 10 % 54,602.00 486,308.10 540,910.10

JUMLAH 600,622.00 5,349,389.10 5,950,011.10

DIBULATKAN 600,622.00 5,349,389.00 5,950,011.00

1.0000 Membuat 1m³ Plat Beton Bertulang (150 Kg Besi + Bekisting)

5.3000 HO Pekerja @ Rp. 50,000.00 265,000.00

0.2650 HO Mandor @ Rp. 65,000.00 17,225.00

1.3000 HO Tukang Kayu @ Rp. 55,000.00 71,500.00

0.2750 HO Tukang Batu @ Rp. 55,000.00 15,125.00

1.0500 HO Tukang Besi @ Rp. 55,000.00 57,750.00

0.2650 HO Kepala Tukang @ Rp. 75,000.00 19,875.00

0.3200 M³ Kayu Bekisting @ Rp. 1,850,000.00 592,000.00

3.2000 Kg Paku @ Rp. 16,055.00 51,376.00

1.6000 Liter Minyak Bekisting @ Rp. 18,525.00 29,640.00

157.5000 Kg Besi Beton Polos @ Rp. 12,350.00 1,945,125.00

2.2500 Kg Kawat Beton @ Rp. 16,055.00 36,123.75

336.0000 Kg Semen Portland @ Rp. 1,276.00 428,736.00

0.5400 M³ Pasir Beton @ Rp. 170,100.00 91,854.00

0.8100 M³ Kerikil @ Rp. 179,000.00 144,990.00

0.1200 M³ Balok Bekisting @ Rp. 1,850,000.00 222,000.00

2.8000 Lbr Plywood @ Rp. 81,650.00 228,620.00

32.0000 Btg Dolken Kayu Galam, Ø (8-10) cm, Panjang 4 m @ Rp. 24,700.00 790,400.00

JUMLAH ( BELUM PPN ) 446,475.00 4,560,864.75 5,007,339.75

OVERHEAD 10 % 44,647.50 456,086.48 500,733.98

JUMLAH 491,122.50 5,016,951.23 5,508,073.73

DIBULATKAN 491,122.00 5,016,951.00 5,508,073.00

1.0000 Membuat 1m' Kolom Praktis Beton Bertulang (11 x 11)

0.1800 HO Pekerja @ Rp. 50,000.00 9,000.00

0.0090 HO Mandor @ Rp. 65,000.00 585.00

0.0200 HO Tukang Kayu @ Rp. 55,000.00 1,100.00

0.0200 HO Tukang Batu @ Rp. 55,000.00 1,100.00

0.0200 HO Tukang Besi @ Rp. 55,000.00 1,100.00

0.0060 HO Kepala Tukang @ Rp. 75,000.00 450.00

0.0020 M³ Kayu Bekisting @ Rp. 1,850,000.00 3,700.00

0.0100 Kg Paku @ Rp. 16,055.00 160.55

3.0000 Kg Besi Beton Polos @ Rp. 12,350.00 37,050.00

0.0450 Kg Kawat Beton @ Rp. 16,055.00 722.48

4.0000 Kg Semen Portland @ Rp. 1,276.00 5,104.00

0.0060 M³ Pasir Beton @ Rp. 170,100.00 1,020.60

0.0090 M³ Kerikil @ Rp. 179,000.00 1,611.00

JUMLAH ( BELUM PPN ) 13,335.00 49,368.63 62,703.63

OVERHEAD 10 % 1,333.50 4,936.86 6,270.36

JUMLAH 14,668.50 54,305.49 68,973.99

m3

m1

Page 16: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

DIBULATKAN 14,668.00 54,305.00 68,973.00

1.0000 Membuat 1m' Ring Balok Beton Bertulang (10 x 15)

0.2970 HO Pekerja @ Rp. 50,000.00 14,850.00

0.0150 HO Mandor @ Rp. 65,000.00 975.00

0.0330 HO Tukang Kayu @ Rp. 55,000.00 1,815.00

0.0330 HO Tukang Batu @ Rp. 55,000.00 1,815.00

0.0330 HO Tukang Besi @ Rp. 55,000.00 1,815.00

0.0100 HO Kepala Tukang @ Rp. 75,000.00 750.00

0.0030 M³ Kayu Bekisting @ Rp. 1,850,000.00 5,550.00

0.0200 Kg Paku @ Rp. 16,055.00 321.10

3.6000 Kg Besi Beton Polos @ Rp. 12,350.00 44,460.00

0.0500 Kg Kawat Beton @ Rp. 16,055.00 802.75

5.5000 Kg Semen Portland @ Rp. 1,276.00 7,018.00

0.0090 M³ Pasir Beton @ Rp. 170,100.00 1,530.90

0.0150 M³ Kerikil @ Rp. 179,000.00 2,685.00

JUMLAH ( BELUM PPN ) 22,020.00 62,367.75 84,387.75

OVERHEAD 10 % 2,202.00 6,236.78 8,438.78

JUMLAH 24,222.00 68,604.53 92,826.53

DIBULATKAN 24,222.00 68,604.00 92,826.00

PEKERJAAN PELESTERAN

1.0000 Plesteran 1 Pc : 4 Ps, tebal 15 mm

6.2400 kg PC @ Rp. 1,276.00 7,962.24

0.0240 Pasir pasang @ Rp. 170,100.00 4,082.40

0.1500 org Tukang batu @ Rp. 55,000.00 8,250.00

0.0150 org Kepala tukang batu @ Rp. 75,000.00 1,125.00

0.3000 org Pekerja @ Rp. 50,000.00 15,000.00

0.0150 org Mandor @ Rp. 65,000.00 975.00

JUMLAH ( BELUM PPN ) 25,350.00 12,044.64 37,394.64

OVERHEAD 10 % 2,535.00 1,204.46 3,739.46

JUMLAH 27,885.00 13,249.10 41,134.10

DIBULATKAN 27,885.00 13,249.00 41,134.00

1.0000 Plesteran beton 1 Pc : 3 Ps, tebal 15 mm

7.7760 kg PC @ Rp. 1,276.00 9,922.18

0.0230 Pasir pasang @ Rp. 170,100.00 3,912.30

0.1500 org Tukang batu @ Rp. 55,000.00 8,250.00

0.0150 org Kepala tukang batu @ Rp. 75,000.00 1,125.00

0.3000 org Pekerja @ Rp. 50,000.00 15,000.00

0.0150 org Mandor @ Rp. 65,000.00 975.00

JUMLAH ( BELUM PPN ) 25,350.00 13,834.48 39,184.48

OVERHEAD 10 % 2,535.00 1,383.45 3,918.45

JUMLAH 27,885.00 15,217.92 43,102.92

DIBULATKAN 27,885.00 15,217.00 43,102.00

1.0000 Plesteran beton 1 Pc : 2 Ps, tebal 15 mm

10.2240 kg PC @ Rp. 1,276.00 13,045.82

0.0200 Pasir pasang @ Rp. 170,100.00 3,402.00

0.1500 org Tukang batu @ Rp. 55,000.00 8,250.00

0.0150 org Kepala tukang batu @ Rp. 75,000.00 1,125.00

0.3000 org Pekerja @ Rp. 50,000.00 15,000.00

0.0150 org Mandor @ Rp. 65,000.00 975.00

JUMLAH ( BELUM PPN ) 25,350.00 16,447.82 41,797.82

m1

m2

m3

m2

m3

m2

m3

Page 17: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

OVERHEAD 10 % 2,535.00 1,644.78 4,179.78

JUMLAH 27,885.00 18,092.61 45,977.61

DIBULATKAN 27,885.00 18,092.00 45,977.00

1.0000 Plesteran Ciprat, 1 Pc : 2 Ps

4.3200 kg PC @ Rp. 1,276.00 5,512.32

0.0060 Pasir pasang @ Rp. 170,100.00 1,020.60

0.1000 org Tukang batu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang batu @ Rp. 75,000.00 750.00

0.3000 org Pekerja @ Rp. 50,000.00 15,000.00

0.0150 org Mandor @ Rp. 65,000.00 975.00

JUMLAH ( BELUM PPN ) 22,225.00 6,532.92 28,757.92

OVERHEAD 10 % 2,222.50 653.29 2,875.79

JUMLAH 24,447.50 7,186.21 31,633.71

DIBULATKAN 24,447.00 7,186.00 31,633.00

1.0000 Acian

3.2500 kg PC @ Rp. 1,276.00 4,147.00

0.1000 org Tukang batu @ Rp. 55,000.00 5,500.00

0.0100 org Kep. Tk. Batu @ Rp. 75,000.00 750.00

0.2000 org Pekerja @ Rp. 50,000.00 10,000.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 16,900.00 4,147.00 21,047.00

OVERHEAD 10 % 1,690.00 414.70 2,104.70

JUMLAH 18,590.00 4,561.70 23,151.70

DIBULATKAN 18,590.00 4,561.00 23,151.00

SNI 1.0000 Pasang dinding batu hias tempel

6.74 1.0500 Batu tempel hitam @ Rp. 175,000.00 183,750.00

11.7500 kg PC @ Rp. 1,276.00 14,993.00

0.0350 Pasir pasang @ Rp. 170,100.00 5,953.50

0.2000 org Tukang batu @ Rp. 55,000.00 11,000.00

0.0350 org Kepala tukang batu @ Rp. 75,000.00 2,625.00

0.2000 org Pekerja @ Rp. 50,000.00 10,000.00

0.0300 org Mandor @ Rp. 65,000.00 1,950.00

JUMLAH ( BELUM TERMASUK PPN ) 25,575.00 204,696.50 230,271.50

OVERHEAD 10 % 2,557.50 20,469.65 23,027.15

JUMLAH 28,132.50 225,166.15 253,298.65

DIBULATKAN 28,132.00 225,166.00 253,298.00

PEKERJAAN KERAMIK 1.0000 Pasang keramik 20/20

11.8700 bh keramik 30/30 @ Rp. 5,500.00 65,285.00

10.0000 kg PC @ Rp. 1,276.00 12,760.00

0.0450 Pasir pasang @ Rp. 170,100.00 7,654.50

1.5000 kg Semen warna @ Rp. 6,325.00 9,487.50

0.3500 org Tukang batu @ Rp. 55,000.00 19,250.00

0.0350 org Kep. Tk. Batu @ Rp. 75,000.00 2,625.00

0.7000 org Pekerja @ Rp. 50,000.00 35,000.00

0.0350 org Mandor @ Rp. 65,000.00 2,275.00

JUMLAH ( BELUM PPN ) 59,150.00 95,187.00 154,337.00

OVERHEAD 10 % 5,915.00 9,518.70 15,433.70

JUMLAH 65,065.00 104,705.70 169,770.70

DIBULATKAN 65,065.00 104,705.00 169,770.00

m2

m3

m2

m2

m2

m3

m2

m3

Page 18: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

1.0000 Pasang keramik 30/30

26.5000 bh keramik 20/20 @ Rp. 3,000.00 79,500.00

10.4000 kg PC @ Rp. 1,276.00 13,270.40

0.0450 Pasir pasang @ Rp. 170,100.00 7,654.50

1.6200 kg Semen warna @ Rp. 6,325.00 10,246.50

0.3500 org Tukang batu @ Rp. 55,000.00 19,250.00

0.0350 org Kep. Tk. Batu @ Rp. 75,000.00 2,625.00

0.7000 org Pekerja @ Rp. 50,000.00 35,000.00

0.0350 org Mandor @ Rp. 65,000.00 2,275.00

JUMLAH ( BELUM PPN ) 59,150.00 110,671.40 169,821.40

OVERHEAD 10 % 5,915.00 11,067.14 16,982.14

JUMLAH 65,065.00 121,738.54 186,803.54

DIBULATKAN 65,065.00 121,738.00 186,803.00

1.0000 Pasang keramik 40/40

6.6300 bh keramik 40/40 @ Rp. 14,727.38 97,642.53

9.8000 kg PC @ Rp. 1,276.00 12,504.80

0.0450 Pasir pasang @ Rp. 170,100.00 7,654.50

1.3800 kg Semen warna @ Rp. 6,325.00 8,728.50

0.3500 org Tukang batu @ Rp. 55,000.00 19,250.00

0.0350 org Kep. Tk. Batu @ Rp. 75,000.00 2,625.00

0.7000 org Pekerja @ Rp. 50,000.00 35,000.00

0.0350 org Mandor @ Rp. 65,000.00 2,275.00

JUMLAH ( BELUM PPN ) 59,150.00 126,530.33 185,680.33

OVERHEAD 10 % 5,915.00 12,653.03 18,568.03

JUMLAH 65,065.00 139,183.36 204,248.36

DIBULATKAN 65,065.00 139,183.00 204,248.00

SNI 1.0000 Pasang plint keramik ukuran 10 x 40 cm

6.24 0.2300 Keramik 40/40 @ Rp. 14,727.38 3,387.30

1.2000 kg PC @ Rp. 1,276.00 1,531.20

0.0030 Pasir pasang @ Rp. 170,100.00 510.30

0.1000 kg Semen warna @ Rp. 6,325.00 632.50

0.0300 org Tukang batu @ Rp. 55,000.00 1,650.00

0.0030 org Kepala tukang batu @ Rp. 75,000.00 225.00

0.0600 org Pekerja @ Rp. 50,000.00 3,000.00

0.0030 org Mandor @ Rp. 65,000.00 195.00

JUMLAH ( BELUM TERMASUK PPN ) 5,070.00 6,061.30 11,131.30

OVERHEAD 10 % 507.00 606.13 1,113.13

JUMLAH 5,577.00 6,667.43 12,244.43

DIBULATKAN 5,577.00 6,667.00 12,244.00

SNI 1.0000 Pasang plint keramik ukuran 10 x 30 cm

6.25 0.1800 Keramik 30/30 @ Rp. 5,500.00 990.00

1.6500 kg PC @ Rp. 1,276.00 2,105.40

0.0032 Pasir pasang @ Rp. 170,100.00 544.32

0.1000 kg Semen warna @ Rp. 6,325.00 632.50

0.0300 org Tukang batu @ Rp. 55,000.00 1,650.00

0.0030 org Kepala tukang batu @ Rp. 75,000.00 225.00

0.0600 org Pekerja @ Rp. 50,000.00 3,000.00

0.0030 org Mandor @ Rp. 65,000.00 195.00

JUMLAH ( BELUM TERMASUK PPN ) 5,070.00 4,272.22 9,342.22

OVERHEAD 10 % 507.00 427.22 934.22

JUMLAH 5,577.00 4,699.44 10,276.44

DIBULATKAN 5,577.00 4,699.00 10,276.00

m2

m3

m2

m3

m1

m2

m3

m1

m2

m3

Page 19: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

1.0000 Pasang list keramik dinding 5/20

5.0000 bh List keramik dinding motif @ Rp. 6,500.00 32,500.00

0.4080 kg PC @ Rp. 1,276.00 520.61

0.0009 Pasir @ Rp. 170,100.00 153.09

0.0600 kg Semen putih @ Rp. 6,325.00 379.50

0.1000 org Tukang batu @ Rp. 55,000.00 5,500.00

0.0100 org Kep. Tk. Batu @ Rp. 75,000.00 750.00

0.0500 org Pekerja @ Rp. 50,000.00 2,500.00

0.0025 org Mandor @ Rp. 65,000.00 162.50

JUMLAH ( BELUM PPN ) 8,912.50 33,553.20 42,465.70

OVERHEAD 10 % 891.25 3,355.32 4,246.57

JUMLAH 9,803.75 36,908.52 46,712.27

DIBULATKAN 9,803.00 36,908.00 46,712.00

1.0000 Pasang keramik dinding 20/25

20.0000 Tegel keramik 20/25 @ Rp. 4,075.50 81,510.00

9.3000 kg PC @ Rp. 1,276.00 11,866.80

0.0180 Pasir pasang @ Rp. 170,100.00 3,061.80

1.5000 kg Semen putih @ Rp. 6,325.00 9,487.50

0.6500 org Tukang batu @ Rp. 55,000.00 35,750.00

0.0650 org Kep. Tk. Batu @ Rp. 75,000.00 4,875.00

0.3200 org Pekerja @ Rp. 50,000.00 16,000.00

0.0160 org Mandor @ Rp. 65,000.00 1,040.00

JUMLAH ( BELUM PPN ) 57,665.00 105,926.10 163,591.10

OVERHEAD 10 % 5,766.50 10,592.61 16,359.11

JUMLAH 63,431.50 116,518.71 179,950.21

DIBULATKAN 63,431.00 116,518.00 179,950.00

PEKERJAAN RANGKA ATAP

SNI 1.0000 Pasang kuda-kuda baja ringan

03-3434-2001 0.4000 kg Besi chanel @ Rp. 70,000.00 28,000.00

15.0000 bh Sekrup atap @ Rp. 250.00 3,750.00

5.6000 kg Reng @ Rp. 10,000.00 56,000.00

0.5000 org Kepala tukang @ Rp. 65,000.00 32,500.00

0.4000 org Pekerja @ Rp. 50,000.00 20,000.00

0.2000 org Mandor @ Rp. 65,000.00 13,000.00

JUMLAH ( BELUM PPN ) 121,500.00 31,750.00 153,250.00

OVERHEAD 10 % 12,150.00 3,175.00 15,325.00

JUMLAH 133,650.00 34,925.00 168,575.00

DIBULATKAN 133,650.00 34,925.00 168,575.00

1.0000 Membuat kuda-kuda kayu kelas II

1.1000 Kayu Kelas II @ Rp. 3,087,000.00 3,395,700.00

15.0000 kg Besi strip @ Rp. 12,072.13 181,081.95

5.6000 kg Paku biasa 2" - 5" @ Rp. 16,055.00 89,908.00

12.0000 org Tukang kayu @ Rp. 55,000.00 660,000.00

1.2000 org Kepala tukang kayu @ Rp. 75,000.00 90,000.00

4.0000 org Pekerja @ Rp. 50,000.00 200,000.00

0.2000 org Mandor @ Rp. 65,000.00 13,000.00

JUMLAH ( BELUM PPN ) 963,000.00 3,666,689.95 4,629,689.95

OVERHEAD 10 % 96,300.00 366,669.00 462,969.00

JUMLAH 1,059,300.00 4,033,358.95 5,092,658.95

DIBULATKAN 1,059,300.00 4,033,358.00 5,092,658.00

m1

m3

m2

m2

m3

m2

m3

m3

Page 20: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

SNI 1.0000 Pasang kuda-kuda kayu lama

03-3434-2002 15.0000 kg Besi strip @ Rp. 12,072.13 181,081.95

0.8000 kg Paku biasa 2" - 5" @ Rp. 16,055.00 12,844.00

12.0000 org Tukang kayu @ Rp. 55,000.00 660,000.00

1.2000 org Kepala tukang kayu @ Rp. 75,000.00 90,000.00

4.0000 org Pekerja @ Rp. 50,000.00 200,000.00

0.2000 org Mandor @ Rp. 65,000.00 13,000.00

JUMLAH ( BELUM PPN ) 963,000.00 193,925.95 1,156,925.95

OVERHEAD 10 % 96,300.00 19,392.59 115,692.60

JUMLAH 1,059,300.00 213,318.54 1,272,618.55

DIBULATKAN 1,059,300.00 213,318.00 1,272,618.00

1.0000 Pasang Nook,Goording dan Jurai kayu Kelas II

1.1000 Kayu Kelas II @ Rp. 3,087,000.00 3,395,700.00

15.0000 kg Besi strip @ Rp. 12,072.13 181,081.95

3.0000 kg Paku biasa 2" - 5" @ Rp. 16,055.00 48,165.00

7.2000 org Tukang kayu @ Rp. 55,000.00 396,000.00

0.7200 org Kepala tukang kayu @ Rp. 75,000.00 54,000.00

2.4000 org Pekerja @ Rp. 50,000.00 120,000.00

0.1200 org Mandor @ Rp. 65,000.00 7,800.00

JUMLAH ( BELUM PPN ) 577,800.00 3,624,946.95 4,202,746.95

OVERHEAD 10 % 57,780.00 362,494.70 420,274.70

JUMLAH 635,580.00 3,987,441.65 4,623,021.65

DIBULATKAN 635,580.00 3,987,441.00 4,623,021.00

SNI 1.0000 Pasang Goording Lama

0.8000 kg Paku biasa 2" - 5" @ Rp. 16,055.00 12,844.00

12.0000 org Tukang kayu @ Rp. 55,000.00 660,000.00

1.2000 org Kepala tukang kayu @ Rp. 75,000.00 90,000.00

4.0000 org Pekerja @ Rp. 50,000.00 200,000.00

0.2000 org Mandor @ Rp. 65,000.00 13,000.00

JUMLAH ( BELUM PPN ) 963,000.00 12,844.00 975,844.00

OVERHEAD 10 % 96,300.00 1,284.40 97,584.40

JUMLAH 1,059,300.00 14,128.40 1,073,428.40

DIBULATKAN 1,059,300.00 14,128.00 1,073,428.00

F.16 1.0000 Pasang usuk 5/7, reng 2/3 lama

0.1500 kg Paku usuk @ Rp. 16,055.00 2,408.25

0.1000 kg Paku reng @ Rp. 16,055.00 1,605.50

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kep. Tk. Kayu @ Rp. 75,000.00 750.00

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

0.0025 org Mandor @ Rp. 65,000.00 162.50

JUMLAH ( BELUM PPN ) 11,412.50 4,013.75 15,426.25

OVERHEAD 10 % 1,141.25 401.38 1,542.63

JUMLAH 12,553.75 4,415.13 16,968.88

DIBULATKAN 12,553.00 4,415.00 16,968.00

F.16 1.0000 Pasang usuk 5/7, reng 2/3 kayu kelas II

2.2000 Usuk kayu 5/7 @ Rp. 24,700.00 54,340.00

5.0000 Reng 2/3 @ Rp. 24,700.00 123,500.00

0.1500 kg Paku usuk @ Rp. 16,055.00 2,408.25

m3

m3

m3

m3

m2

m2

m1

m1

Page 21: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

0.1000 kg Paku reng @ Rp. 16,055.00 1,605.50

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kep. Tk. Kayu @ Rp. 75,000.00 750.00

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

0.0025 org Mandor @ Rp. 65,000.00 162.50

JUMLAH ( BELUM PPN ) 11,412.50 181,853.75 193,266.25

OVERHEAD 10 % 1,141.25 18,185.38 19,326.63

JUMLAH 12,553.75 200,039.13 212,592.88

DIBULATKAN 12,553.00 200,039.00 212,592.00

PEKERJAAN PINTU DAN JENDELA 1.0000 Membuat kusen pintu / jendela aluminium

1.0000 Aluminium @ Rp. 70,000.00 70,000.00

4.0000 bh Skrup @ Rp. 250.00 1,000.00

0.2000 org Tukang aluminium @ Rp. 55,000.00 11,000.00

0.1000 org Kepala tukang aluminium @ Rp. 75,000.00 7,500.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 19,150.00 71,000.00 90,150.00

OVERHEAD 10 % 1,915.00 7,100.00 9,015.00

JUMLAH 21,065.00 78,100.00 99,165.00

DIBULATKAN 21,065.00 78,100.00 99,165.00

1.0000 Membuat kusen pintu / jendela kayu Surian

1.1000 Kayu Surian @ Rp. 3,705,000.00 4,075,500.00

1.2500 kg Paku @ Rp. 16,055.00 20,068.75

1.0000 kg Lem kayu @ Rp. 24,854.38 24,854.38

18.0000 org Tukang kayu @ Rp. 55,000.00 990,000.00

1.8000 org Kepala tukang kayu @ Rp. 75,000.00 135,000.00

6.0000 org Pekerja @ Rp. 50,000.00 300,000.00

0.3000 org Mandor @ Rp. 65,000.00 19,500.00

JUMLAH ( BELUM PPN ) 1,444,500.00 4,120,423.13 5,564,923.13

OVERHEAD 10 % 144,450.00 412,042.31 556,492.31

JUMLAH 1,588,950.00 4,532,465.44 6,121,415.44

DIBULATKAN 1,588,950.00 4,532,465.00 6,121,415.00

1.0000 Pasang pintu panel kayu surian

0.0400 Kayu surian papan @ Rp. 3,705,000.00 148,200.00

0.5000 kg Lem kayu @ Rp. 24,854.38 12,427.19

3.0000 org Tukang kayu @ Rp. 55,000.00 165,000.00

0.3000 org Kepala tukang kayu @ Rp. 75,000.00 22,500.00

1.0000 org Pekerja @ Rp. 50,000.00 50,000.00

0.0500 org Mandor @ Rp. 65,000.00 3,250.00

JUMLAH ( BELUM PPN ) 240,750.00 160,627.19 401,377.19

OVERHEAD 10 % 24,075.00 16,062.72 40,137.72

JUMLAH 264,825.00 176,689.91 441,514.91

DIBULATKAN 264,825.00 176,689.00 441,514.00

1.0000 Pasang pintu dan jendela kaca kayu surian

0.0240 Kayu surian papan @ Rp. 3,705,000.00 88,920.00

0.3000 kg Lem kayu @ Rp. 24,854.38 7,456.31

2.4000 org Tukang kayu @ Rp. 55,000.00 132,000.00

0.2400 org Kepala tukang kayu @ Rp. 75,000.00 18,000.00

0.8000 org Pekerja @ Rp. 50,000.00 40,000.00

0.0400 org Mandor @ Rp. 65,000.00 2,600.00

m1

m1

m3

m3

m2

m3

m2

m3

Page 22: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

JUMLAH ( BELUM PPN ) 192,600.00 96,376.31 288,976.31

OVERHEAD 10 % 19,260.00 9,637.63 28,897.63

JUMLAH 211,860.00 106,013.95 317,873.95

DIBULATKAN 211,860.00 106,013.00 317,873.00

1.0000 Pasang jalusi kusen kayu surian

0.0600 Kayu surian papan @ Rp. 3,705,000.00 222,300.00

0.1500 kg Paku @ Rp. 24,854.38 3,728.16

2.0000 org Tukang kayu @ Rp. 55,000.00 110,000.00

0.2000 org Kepala tukang kayu @ Rp. 75,000.00 15,000.00

0.6700 org Pekerja @ Rp. 50,000.00 33,500.00

0.3350 org Mandor @ Rp. 65,000.00 21,775.00

JUMLAH ( BELUM PPN ) 180,275.00 226,028.16 406,303.16

OVERHEAD 10 % 18,027.50 22,602.82 40,630.32

JUMLAH 198,302.50 248,630.97 446,933.47

DIBULATKAN 198,302.00 248,630.00 446,933.00

PEKERJAAN PLAFOND 1.0000 Pasang rangka langit-langit (60 x 120) m, kayu kelas II

0.0130 Kayu kayu kelas II @ Rp. 3,087,000.00 40,131.00

0.1200 kg Paku @ Rp. 16,055.00 1,926.60

0.2700 org Tukang kayu @ Rp. 55,000.00 14,850.00

0.0270 org Kepala tukang kayu @ Rp. 75,000.00 2,025.00

0.1700 org Pekerja @ Rp. 50,000.00 8,500.00

0.0085 org Mandor @ Rp. 65,000.00 552.50

JUMLAH ( BELUM PPN ) 25,927.50 42,057.60 67,985.10

OVERHEAD 10 % 2,592.75 4,205.76 6,798.51

JUMLAH 28,520.25 46,263.36 74,783.61

DIBULATKAN 28,520.00 46,263.00 74,783.00

1.0000 Pasang langit-langit triplek (60 x 120) m, tebal 4 mm

0.3750 Lbr GRC @ Rp. 85,000.00 31,875.00

0.0300 kg Paku @ Rp. 16,055.00 481.65

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang kayu @ Rp. 75,000.00 750.00

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

0.0050 org Mandor @ Rp. 65,000.00 325.00

JUMLAH ( BELUM PPN ) 11,575.00 32,356.65 43,931.65

OVERHEAD 10 % 1,157.50 3,235.67 4,393.17

JUMLAH 12,732.50 35,592.32 48,324.82

DIBULATKAN 12,732.00 35,592.00 48,324.00

SNI 1.0000 List langit-langit kayu profil

6.19 1.1000 List kayu profil @ Rp. 12,350.00 13,585.00

03-2838-2002 0.0100 kg Paku @ Rp. 16,055.00 160.55

0.0500 org Tukang kayu @ Rp. 55,000.00 2,750.00

0.0050 org Kepala tukang kayu @ Rp. 75,000.00 375.00

0.0500 org Pekerja @ Rp. 50,000.00 2,500.00

0.0030 org Mandor @ Rp. 65,000.00 195.00

JUMLAH ( BELUM PPN ) 5,820.00 13,745.55 19,565.55

OVERHEAD 10 % 582.00 1,374.56 1,956.56

JUMLAH 6,402.00 15,120.11 21,522.11

DIBULATKAN 6,402.00 15,120.00 21,522.00

m2

m3

m2

m3

m2

m1

m1

Page 23: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

PEKERJAAN LISPLANG 1.0000 Pasang lisplank ukuran (2 x 20) cm, kayu surian

0.0048 Kayu surian papan @ Rp. 3,705,000.00 17,784.00

0.0600 kg Paku biasa 2" - 5" @ Rp. 24,854.38 1,491.26

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang kayu @ Rp. 75,000.00 750.00

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

0.0050 org Mandor @ Rp. 65,000.00 325.00

JUMLAH ( BELUM PPN ) 11,575.00 19,275.26 30,850.26

OVERHEAD 10 % 1,157.50 1,927.53 3,085.03

JUMLAH 12,732.50 21,202.79 33,935.29

DIBULATKAN 12,732.00 21,202.00 33,935.00

1.0000 Mengerjakan papan ruiter kayu kelas II 2/20

0.0040 Kayu kelas II papan @ Rp. 3,087,000.00 12,348.00

0.0200 kg Paku biasa 2" - 5" @ Rp. 16,055.00 321.10

0.0800 org Tukang kayu @ Rp. 55,000.00 4,400.00

0.0080 org Kepala tukang kayu @ Rp. 75,000.00 600.00

0.0280 org Pekerja @ Rp. 50,000.00 1,400.00

0.0014 org Mandor @ Rp. 65,000.00 91.00

JUMLAH 6,491.00 12,669.10 19,160.10

OVERHEAD 10 % 649.10 1,266.91 1,916.01

JUMLAH 7,140.10 13,936.01 21,076.11

DIBULATKAN 7,140.00 13,936.00 21,076.00

PEKERJAAN TALANG SNI 1.0000 Pasang talang datar, seng BJLS 20, papan kayu kelas II

6.18 0.5000 lbr Seng plat 3' x 6' BJLS 20 @ Rp. 52,487.50 26,243.75

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 16,055.00 240.83

0.0096 Kayu kelas II papan @ Rp. 3,087,000.00 29,635.20

0.2500 kg Flincoat @ Rp. 120,721.25 30,180.31

0.4000 org Tukang kayu @ Rp. 55,000.00 22,000.00

0.0250 org Kepala tukang kayu @ Rp. 75,000.00 1,875.00

0.1500 org Pekerja @ Rp. 50,000.00 7,500.00

0.0013 org Mandor @ Rp. 65,000.00 81.25

JUMLAH ( BELUM PPN ) 31,456.25 86,300.09 117,756.34

OVERHEAD 10 % 3,145.63 8,630.01 11,775.63

JUMLAH 34,601.88 94,930.10 129,531.97

DIBULATKAN 34,601.00 94,930.00 129,531.00

SNI 1.0000 Pasang talang miring, seng BJLS 20, papan kayu kelas II

6.19 0.5000 lbr Seng plat 3' x 6' BJLS 20 @ Rp. 52,487.50 26,243.75

0.0150 kg Paku biasa 1/2" - 1" @ Rp. 16,055.00 240.83

0.0190 Kayu kelas II papan @ Rp. 3,087,000.00 58,653.00

0.2500 kg Flincoat @ Rp. 120,721.25 30,180.31

0.4000 org Tukang kayu @ Rp. 55,000.00 22,000.00

0.0250 org Kepala tukang kayu @ Rp. 75,000.00 1,875.00

0.0400 org Pekerja @ Rp. 50,000.00 2,000.00

0.0013 org Mandor @ Rp. 65,000.00 81.25

JUMLAH ( BELUM PPN ) 25,956.25 115,317.89 141,274.14

OVERHEAD 10 % 2,595.63 11,531.79 14,127.41

JUMLAH 28,551.88 126,849.68 155,401.55

DIBULATKAN 28,551.00 126,849.00 155,401.00

m1

m3

m1

m3

m1

m3

m1

m3

Page 24: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

PEKERJAAN ATAP 1.0000 Pasang gentang metal

1.2000 bh Genteng metal @ Rp. 50,000.00 60,000.00

4.0000 bh Skrup @ Rp. 250.00 1,000.00

0.2000 org Tukang batu @ Rp. 55,000.00 11,000.00

0.2000 org Pekerja @ Rp. 50,000.00 10,000.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 21,650.00 61,000.00 82,650.00

OVERHEAD 10 % 2,165.00 6,100.00 8,265.00

JUMLAH 23,815.00 67,100.00 90,915.00

DIBULATKAN 23,815.00 67,100.00 90,915.00

1.0000 Pasang bubungan genteng metal

1.0000 stel Bubungan genteng metal @ Rp. 25,000.00 25,000.00

0.2500 kg Paku @ Rp. 250.00 62.50

0.2000 org Tukang batu @ Rp. 55,000.00 11,000.00

0.0200 org Kep. Tk. Batu @ Rp. 75,000.00 1,500.00

0.4000 org Pekerja @ Rp. 50,000.00 20,000.00

JUMLAH ( BELUM PPN ) 32,500.00 25,062.50 57,562.50

OVERHEAD 10 % 3,250.00 2,506.25 5,756.25

JUMLAH 35,750.00 27,568.75 63,318.75

DIBULATKAN 35,750.00 27,568.00 63,318.00

1.0000 Pasang seng multy colour

0.7000 lmbr Seng multy colour @ Rp. 73,142.88 51,200.02

0.1000 kg Paku @ Rp. 250.00 25.00

0.2000 org Tukang batu @ Rp. 55,000.00 11,000.00

0.0200 org Kep. Tk. Batu @ Rp. 75,000.00 1,500.00

0.1500 org Pekerja @ Rp. 50,000.00 7,500.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 20,650.00 51,225.02 71,875.02

OVERHEAD 10 % 2,065.00 5,122.50 7,187.50

JUMLAH 22,715.00 56,347.52 79,062.52

DIBULATKAN 22,715.00 56,347.00 79,062.00

1.0000 Pasang bubungan seng multy colour

0.5000 lmr Bubungan seng multy colour @ Rp. 73,142.88 36,571.44

0.1000 kg Paku @ Rp. 250.00 25.00

0.3200 org Tukang batu @ Rp. 55,000.00 17,600.00

0.0300 org Kep. Tk. Batu @ Rp. 75,000.00 2,250.00

0.7500 org Pekerja @ Rp. 50,000.00 37,500.00

JUMLAH ( BELUM PPN ) 57,350.00 36,596.44 93,946.44

OVERHEAD 10 % 5,735.00 3,659.64 9,394.64

JUMLAH 63,085.00 40,256.08 103,341.08

DIBULATKAN 63,085.00 40,256.00 103,341.00

1.0000 Pasang seng gelombang

0.8597 lmbr Seng gelombang BJLS 20 @ Rp. 42,000.00 36,107.40

0.0370 kg Paku @ Rp. 250.00 9.25

0.2000 org Tukang batu @ Rp. 55,000.00 11,000.00

0.0200 org Kep. Tk. Batu @ Rp. 75,000.00 1,500.00

0.1100 org Pekerja @ Rp. 50,000.00 5,500.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 18,650.00 36,116.65 54,766.65

m2

m1

m2

m1

m2

Page 25: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

OVERHEAD 10 % 1,865.00 3,611.67 5,476.67

JUMLAH 20,515.00 39,728.32 60,243.32

DIBULATKAN 20,515.00 39,728.00 60,243.00

1.0000 Pasang bubungan seng

0.5780 lmr Seng plat BJLS 20 @ Rp. 52,487.50 30,337.77

0.0216 kg Paku @ Rp. 250.00 5.40

0.0250 org Tukang batu @ Rp. 55,000.00 1,375.00

0.0250 org Kep. Tk. Batu @ Rp. 75,000.00 1,875.00

0.2500 org Pekerja @ Rp. 50,000.00 12,500.00

JUMLAH ( BELUM PPN ) 15,750.00 30,343.18 46,093.18

OVERHEAD 10 % 1,575.00 3,034.32 4,609.32

JUMLAH 17,325.00 33,377.49 50,702.49

DIBULATKAN 17,325.00 33,377.00 50,702.00

PEKERJAAN PENGECATAN 1.0000 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup

0.2000 kg Cat meni @ Rp. 15,437.50 3,087.50

0.1500 kg Plamir @ Rp. 24,700.00 3,705.00

0.1700 kg Cat dasar @ Rp. 24,000.00 4,080.00

0.2600 kg Cat penutup @ Rp. 24,000.00 6,240.00

0.3750 org Tukang cat @ Rp. 55,000.00 20,625.00

0.0375 org Kepala tukang cat @ Rp. 75,000.00 2,812.50

0.2500 org Pekerja @ Rp. 50,000.00 12,500.00

0.0150 org Mandor @ Rp. 65,000.00 975.00

JUMLAH ( BELUM PPN ) 36,912.50 17,112.50 54,025.00

OVERHEAD 10 % 3,691.25 1,711.25 5,402.50

JUMLAH 40,603.75 18,823.75 59,427.50

DIBULATKAN 40,603.00 18,823.00 59,427.00

SNI 1.0000 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup

6.9 0.2000 kg Cat meni @ Rp. 15,437.50 3,087.50

0.1500 kg Plamir @ Rp. 24,700.00 3,705.00

0.1700 kg Cat dasar @ Rp. 24,000.00 4,080.00

0.3500 kg Cat penutup @ Rp. 24,000.00 8,400.00

0.3750 org Tukang cat @ Rp. 55,000.00 20,625.00

0.0375 org Kepala tukang cat @ Rp. 75,000.00 2,812.50

0.2500 org Pekerja @ Rp. 50,000.00 12,500.00

0.0150 org Mandor @ Rp. 65,000.00 975.00

JUMLAH ( BELUM PPN ) 36,912.50 19,272.50 56,185.00

OVERHEAD 10 % 3,691.25 1,927.25 5,618.50

JUMLAH 40,603.75 21,199.75 61,803.50

DIBULATKAN 40,603.00 21,199.00 61,803.00

SNI 1.0000 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)

6.14 0.1600 kg Plamir tembok @ Rp. 24,700.00 3,952.00

0.1600 kg Cat dasar @ Rp. 24,000.00 3,840.00

0.2600 kg Cat penutup 2 x @ Rp. 24,000.00 6,240.00

0.2000 org Tukang cat @ Rp. 55,000.00 11,000.00

0.0200 org Kepala tukang cat @ Rp. 75,000.00 1,500.00

0.2000 org Pekerja @ Rp. 50,000.00 10,000.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 23,150.00 14,032.00 37,182.00

OVERHEAD 10 % 2,315.00 1,403.20 3,718.20

JUMLAH 25,465.00 15,435.20 40,900.20

m1

m2

m2

m2

Page 26: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

DIBULATKAN 25,465.00 15,435.00 40,900.00

SNI 1.0000 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)

6.15 0.1200 kg Cat dasar @ Rp. 24,700.00 2,964.00

0.1800 kg Cat penutup 2 x @ Rp. 24,000.00 4,320.00

0.2000 org Tukang cat @ Rp. 55,000.00 11,000.00

0.0200 org Kepala tukang cat @ Rp. 75,000.00 1,500.00

0.2000 org Pekerja @ Rp. 50,000.00 10,000.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 23,150.00 7,284.00 30,434.00

OVERHEAD 10 % 2,315.00 728.40 3,043.40

JUMLAH 25,465.00 8,012.40 33,477.40

DIBULATKAN 25,465.00 8,012.00 33,477.00

SNI 1.0000 Pengecatan tembok tidak terlindung dari panas dan hujan

6.14 0.1000 kg Cat alkali resisting primer @ Rp. 24,700.00 2,470.00

0.3600 kg Cat ICI Weathershield @ Rp. 35,000.00 12,600.00

0.0630 org Tukang cat @ Rp. 55,000.00 3,465.00

0.0063 org Kepala tukang cat @ Rp. 75,000.00 472.50

0.0200 org Pekerja @ Rp. 50,000.00 1,000.00

0.0025 org Mandor @ Rp. 65,000.00 162.50

JUMLAH ( BELUM PPN ) 5,100.00 15,070.00 20,170.00

OVERHEAD 10 % 510.00 1,507.00 2,017.00

JUMLAH 5,610.00 16,577.00 22,187.00

DIBULATKAN 5,610.00 16,577.00 22,187.00

SNI 1.0000 Pengecatan bidang besi ( 3 x )

6.9 0.1670 kg Cat meni besi @ Rp. 15,437.50 2,578.06

0.2000 kg Cat besi @ Rp. 15,437.50 3,087.50

0.1500 ltr Thinner @ Rp. 24,700.00 3,705.00

0.1050 org Tukang cat @ Rp. 55,000.00 5,775.00

0.0040 org Kepala tukang cat @ Rp. 75,000.00 300.00

0.0700 org Pekerja @ Rp. 50,000.00 3,500.00

0.0025 org Mandor @ Rp. 65,000.00 162.50

JUMLAH ( BELUM PPN ) 9,737.50 9,370.56 19,108.06

OVERHEAD 10 % 973.75 937.06 1,910.81

JUMLAH 10,711.25 10,307.62 21,018.87

DIBULATKAN 10,711.00 10,307.00 21,018.00

PEKERJAAN BONGKARAN

AK 1.0000 Membongkar pasangan batu kali

4.0000 org Tukang batu @ Rp. 55,000.00 220,000.00

0.4000 org Pekerja @ Rp. 50,000.00 20,000.00

JUMLAH ( BELUM PPN ) 240,000.00 - 240,000.00

OVERHEAD 10 % 24,000.00 - 24,000.00

JUMLAH 264,000.00 - 264,000.00

DIBULATKAN 264,000.00 - 264,000.00

AK 1.0000 Membongkar pasangan batu merah dan membersihkan

2.0000 org Tukang batu @ Rp. 55,000.00 110,000.00

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

JUMLAH ( BELUM PPN ) 115,000.00 - 115,000.00

OVERHEAD 10 % 11,500.00 - 11,500.00

JUMLAH 126,500.00 - 126,500.00

DIBULATKAN 126,500.00 - 126,500.00

m2

m2

m2

m3

m3

Page 27: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

AK 1.0000 Membongkar beton bertulang dan membersihkan

0.2000 org Tukang batu @ Rp. 55,000.00 11,000.00

8.0000 org Pekerja @ Rp. 50,000.00 400,000.00

0.1000 org Mandor @ Rp. 65,000.00 6,500.00

JUMLAH ( BELUM PPN ) 417,500.00 - 417,500.00

OVERHEAD 10 % 41,750.00 - 41,750.00

JUMLAH 459,250.00 - 459,250.00

DIBULATKAN 459,250.00 - 459,250.00

AK 10.0000 Pekerjaan bongkar lantai tegel untuk dipergunakan lagi

2.0000 org Pekerja @ Rp. 55,000.00 110,000.00

0.1000 org Mandor @ Rp. 50,000.00 5,000.00

JUMLAH ( BELUM PPN ) 115,000.00 - 115,000.00

TIAP 1M2 ( BELUM PPN ) 11,500.00 - 11,500.00

OVERHEAD 10 % 1,150.00 - 1,150.00

JUMLAH 12,650.00 - 12,650.00

DIBULATKAN 12,650.00 - 12,650.00

I.6 10.0000 Mengupas plesteran lama

1.2500 org Pekerja @ Rp. 55,000.00 68,750.00

0.1250 org Mandor @ Rp. 50,000.00 6,250.00

JUMLAH ( BELUM PPN ) 75,000.00 - 75,000.00

TIAP 1M2 ( BELUM PPN ) 7,500.00 - 7,500.00

OVERHEAD 10 % 750.00 - 750.00

JUMLAH 8,250.00 - 8,250.00

DIBULATKAN 8,250.00 - 8,250.00

I.7 10.0000 Membongkar genteng / sirap untuk dipergunakan lagi

2.0000 org Pekerja @ Rp. 55,000.00 110,000.00

0.1000 org Mandor @ Rp. 50,000.00 5,000.00

JUMLAH ( BELUM PPN ) 115,000.00 - 115,000.00

TIAP 1M2 ( BELUM PPN ) 11,500.00 - 11,500.00

OVERHEAD 10 % 1,150.00 - 1,150.00

JUMLAH 12,650.00 - 12,650.00

DIBULATKAN 12,650.00 - 12,650.00

I.8 10.0000 Membongkar atap seng

0.5000 org Tukang besi @ Rp. 55,000.00 27,500.00

1.0000 org Pekerja @ Rp. 50,000.00 50,000.00

JUMLAH ( BELUM PPN ) 77,500.00 - 77,500.00

TIAP 1M2 ( BELUM PPN ) 7,750.00 - 7,750.00

OVERHEAD 10 % 775.00 - 775.00

JUMLAH 8,525.00 - 8,525.00

DIBULATKAN 8,525.00 - 8,525.00

I.9 10.0000 Membongkar usuk / reng dipakai lagi

0.6000 org Tukang kayu @ Rp. 55,000.00 33,000.00

0.0600 org Kep. Tk. Kayu @ Rp. 75,000.00 4,500.00

m3

m2

m2

m2

m2

m2

Page 28: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

2.0000 org Pekerja @ Rp. 50,000.00 100,000.00

0.1000 org Mandor @ Rp. 65,000.00 6,500.00

JUMLAH ( BELUM PPN ) 144,000.00 - 144,000.00

TIAP 1M2 ( BELUM PPN ) 14,400.00 - 14,400.00

OVERHEAD 10 % 1,440.00 - 1,440.00

JUMLAH 15,840.00 - 15,840.00

DIBULATKAN 15,840.00 - 15,840.00

10.0000 Membongkar usuk / reng tidak dipakai lagi

2.0000 org Pekerja @ Rp. 50,000.00 100,000.00

0.1000 org Mandor @ Rp. 65,000.00 6,500.00

JUMLAH ( BELUM PPN ) 106,500.00 - 106,500.00

TIAP 1M2 ( BELUM PPN ) 10,650.00 - 10,650.00

OVERHEAD 10 % 1,065.00 - 1,065.00

JUMLAH 11,715.00 - 11,715.00

DIBULATKAN 11,715.00 - 11,715.00

L.12 1.0000 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi

6.0000 org Tukang kayu @ Rp. 55,000.00 330,000.00

0.6000 org Kep. Tk. Kayu @ Rp. 75,000.00 45,000.00

4.0000 org Pekerja @ Rp. 50,000.00 200,000.00

0.2000 org Mandor @ Rp. 65,000.00 13,000.00

JUMLAH ( BELUM PPN ) 588,000.00 - 588,000.00

OVERHEAD 10 % 58,800.00 - 58,800.00

JUMLAH 646,800.00 - 646,800.00

DIBULATKAN 646,800.00 - 646,800.00

1.0000 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi

1.0000 org Pekerja @ Rp. 50,000.00 50,000.00

0.2000 org Mandor @ Rp. 65,000.00 13,000.00

JUMLAH ( BELUM PPN ) 63,000.00 - 63,000.00

OVERHEAD 10 % 6,300.00 - 6,300.00

JUMLAH 69,300.00 - 69,300.00

DIBULATKAN 69,300.00 - 69,300.00

L.14 1.0000 Mengerjakan kembali bangunan kayu yang telah dibongkar

12.0000 org Tukang kayu @ Rp. 55,000.00 660,000.00

1.2000 org Kep. Tk. Kayu @ Rp. 75,000.00 90,000.00

4.0000 org Pekerja @ Rp. 50,000.00 200,000.00

0.2000 org Mandor @ Rp. 65,000.00 13,000.00

JUMLAH ( BELUM PPN ) 963,000.00 - 963,000.00

OVERHEAD 10 % 96,300.00 - 96,300.00

JUMLAH 1,059,300.00 - 1,059,300.00

DIBULATKAN 1,059,300.00 - 1,059,300.00

PEKERJAAN SANITASI SNI 1.0000 bh Memasang kloset duduk/monoblock

1.0000 bh Kloset duduk / monoblock @ Rp. 1,988,350.00 1,988,350.00

6.1 6% x Harga kloset (Perlengkapan) @ Rp. 1,988,350.00 119,301.00

1.1000 org Tukang batu @ Rp. 55,000.00 60,500.00

0.0010 org Kepala tukang batu @ Rp. 75,000.00 75.00

m2

m3

m3

m3

Page 29: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

3.3000 org Pekerja @ Rp. 50,000.00 165,000.00

0.1600 org Mandor @ Rp. 65,000.00 10,400.00

JUMLAH ( BELUM PPN ) 235,975.00 2,107,651.00 2,343,626.00

OVERHEAD 10 % 23,597.50 210,765.10 234,362.60

JUMLAH 259,572.50 2,318,416.10 2,577,988.60

DIBULATKAN 259,572.00 2,318,416.00 2,577,988.00

SNI 1.0000 bh Memasang kloset jongkok

1.0000 bh Kloset jongkok porselen @ Rp. 191,733.75 191,733.75

6.2 6.0000 kg PC @ Rp. 1,276.00 7,656.00

0.0100 Pasir pasang @ Rp. 170,100.00 1,701.00

1.5000 org Tukang batu @ Rp. 55,000.00 82,500.00

1.5000 org Kepala tukang batu @ Rp. 75,000.00 112,500.00

1.0000 org Pekerja @ Rp. 50,000.00 50,000.00

0.1600 org Mandor @ Rp. 65,000.00 10,400.00

JUMLAH ( BELUM PPN ) 255,400.00 201,090.75 456,490.75

OVERHEAD 10 % 25,540.00 20,109.08 45,649.08

JUMLAH 280,940.00 221,199.83 502,139.83

DIBULATKAN 280,940.00 221,199.00 502,139.00

SNI 1.0000 bh Memasang urinoir

1.0000 bh Urinoir @ Rp. 1,200,000.00 1,200,000.00

6.4 30% x Harga urinoir (Perlengkapan) @ Rp. 1,200,000.00 360,000.00

6.0000 kg PC @ Rp. 1,276.00 7,656.00

0.0100 Pasir pasang @ Rp. 170,100.00 1,701.00

1.0000 org Tukang batu @ Rp. 55,000.00 55,000.00

0.1000 org Kepala tukang batu @ Rp. 75,000.00 7,500.00

1.0000 org Pekerja @ Rp. 50,000.00 50,000.00

0.1000 org Mandor @ Rp. 65,000.00 6,500.00

JUMLAH ( BELUM PPN ) 119,000.00 1,569,357.00 1,688,357.00

OVERHEAD 10 % 11,900.00 156,935.70 168,835.70

JUMLAH 130,900.00 1,726,292.70 1,857,192.70

DIBULATKAN 130,900.00 1,726,292.00 1,857,192.00

SNI 1.0000 bh Memasang wastafel

1.0000 bh Wastafel @ Rp. 639,112.50 639,112.50

6.5 12% x Harga wastafel (Perlengkapan) @ Rp. 639,112.50 76,693.50

6.0000 kg PC @ Rp. 1,276.00 7,656.00

0.0100 Pasir pasang @ Rp. 170,100.00 1,701.00

1.4500 org Tukang batu @ Rp. 55,000.00 79,750.00

0.1500 org Kepala tukang batu @ Rp. 75,000.00 11,250.00

1.2000 org Pekerja @ Rp. 50,000.00 60,000.00

0.1000 org Mandor @ Rp. 65,000.00 6,500.00

JUMLAH ( BELUM PPN ) 157,500.00 725,163.00 882,663.00

OVERHEAD 10 % 15,750.00 72,516.30 88,266.30

JUMLAH 173,250.00 797,679.30 970,929.30

DIBULATKAN 173,250.00 797,679.00 970,929.00

SNI 1.0000 bh Memasang bak mandi fiberglass 60 x 60

1.0000 bh Bak fiberglass @ Rp. 197,600.00 197,600.00

6.7 18% x Harga bak(Perlengkapan) @ Rp. 197,600.00 35,568.00

2.7000 org Tukang batu @ Rp. 55,000.00 148,500.00

0.5400 org Kepala tukang batu @ Rp. 75,000.00 40,500.00

1.8000 org Pekerja @ Rp. 50,000.00 90,000.00

0.1100 org Mandor @ Rp. 65,000.00 7,150.00

m3

m3

m3

Page 30: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

JUMLAH ( BELUM PPN ) 286,150.00 233,168.00 519,318.00

OVERHEAD 10 % 28,615.00 23,316.80 51,931.80

JUMLAH 314,765.00 256,484.80 571,249.80

DIBULATKAN 314,765.00 256,484.00 571,249.00

SNI 1.0000 bh Memasang bak fiberglass 70 x 70

1.0000 bh Bak fiberglass @ Rp. 222,300.00 222,300.00

6.11 12% x Harga bak (Perlengkapan) @ Rp. 222,300.00 26,676.00

4.5000 org Tukang batu @ Rp. 55,000.00 247,500.00

0.9000 org Kepala tukang batu @ Rp. 75,000.00 67,500.00

3.0000 org Pekerja @ Rp. 50,000.00 150,000.00

0.9000 org Mandor @ Rp. 65,000.00 58,500.00

JUMLAH ( BELUM PPN ) 523,500.00 248,976.00 772,476.00

OVERHEAD 10 % 52,350.00 24,897.60 77,247.60

JUMLAH 575,850.00 273,873.60 849,723.60

DIBULATKAN 575,850.00 273,873.00 849,723.00

SNI 1.0000 Memasang pipa beton, diameter 15 cm - 20 cm

1.1000 bh Pipa beton @ Rp. 74,000.00 81,400.00

6.14 16.0000 bh Batu bata @ Rp. 600.00 9,600.00

3.9200 kg PC @ Rp. 1,276.00 5,001.92

0.0560 Pasir pasang @ Rp. 170,100.00 9,525.60

0.0240 Pasir urug @ Rp. 170,100.00 4,082.40

0.0700 org Tukang batu @ Rp. 55,000.00 3,850.00

0.0070 org Kepala tukang batu @ Rp. 75,000.00 525.00

0.1400 org Pekerja @ Rp. 50,000.00 7,000.00

0.0070 org Mandor @ Rp. 65,000.00 455.00

JUMLAH ( BELUM PPN ) 11,830.00 109,609.92 121,439.92

OVERHEAD 10 % 1,183.00 10,960.99 12,143.99

JUMLAH 13,013.00 120,570.91 133,583.91

DIBULATKAN 13,013.00 120,570.00 133,583.00

SNI 1.0000 Memasang pipa beton, diameter 30 cm - 100 cm

1.1000 bh Pipa beton @ Rp. 100,000.00 110,000.00

6.15 330.0000 bh Batu bata @ Rp. 600.00 198,000.00

10.3000 kg PC @ Rp. 1,276.00 13,142.80

0.0610 Pasir pasang @ Rp. 170,100.00 10,376.10

0.0690 Pasir urug @ Rp. 170,100.00 11,736.90

0.1900 org Tukang batu @ Rp. 55,000.00 10,450.00

0.0190 org Kepala tukang batu @ Rp. 75,000.00 1,425.00

0.3800 org Pekerja @ Rp. 50,000.00 19,000.00

0.0190 org Mandor @ Rp. 65,000.00 1,235.00

JUMLAH ( BELUM PPN ) 32,110.00 343,255.80 375,365.80

OVERHEAD 10 % 3,211.00 34,325.58 37,536.58

JUMLAH 35,321.00 377,581.38 412,902.38

DIBULATKAN 35,321.00 377,581.00 412,902.00

SNI 1.0000 Memasang pipa galvanis diameter 1/2"

1.2000 Pipa galvanis @ Rp. 18,525.00 22,230.00

6.19 35% x Harga pipa (Perlengkapan) @ Rp. 18,525.00 6,483.75

0.0900 org Tukang batu @ Rp. 55,000.00 4,950.00

0.0090 org Kepala tukang batu @ Rp. 75,000.00 675.00

0.0540 org Pekerja @ Rp. 50,000.00 2,700.00

m1

m3

m3

m1

m3

m3

m1

m1

Page 31: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

0.0270 org Mandor @ Rp. 65,000.00 1,755.00

JUMLAH ( BELUM PPN ) 10,080.00 28,713.75 38,793.75

OVERHEAD 10 % 1,008.00 2,871.38 3,879.38

JUMLAH 11,088.00 31,585.13 42,673.13

DIBULATKAN 11,088.00 31,585.00 42,673.00

SNI 1.0000 Memasang pipa galvanis diameter 3/4"

1.2000 Pipa galvanis @ Rp. 22,230.00 26,676.00

6.20 35% x Harga pipa (Perlengkapan) @ Rp. 22,230.00 7,780.50

0.0900 org Tukang batu @ Rp. 55,000.00 4,950.00

0.0090 org Kepala tukang batu @ Rp. 75,000.00 675.00

0.0540 org Pekerja @ Rp. 50,000.00 2,700.00

0.0270 org Mandor @ Rp. 65,000.00 1,755.00

JUMLAH ( BELUM PPN ) 10,080.00 34,456.50 44,536.50

OVERHEAD 10 % 1,008.00 3,445.65 4,453.65

JUMLAH 11,088.00 37,902.15 48,990.15

DIBULATKAN 11,088.00 37,902.00 48,990.00

SNI 1.0000 Memasang pipa galvanis diameter 1"

1.2000 Pipa galvanis @ Rp. 32,110.00 38,532.00

6.21 35% x Harga pipa (Perlengkapan) @ Rp. 32,110.00 11,238.50

0.0900 org Tukang batu @ Rp. 55,000.00 4,950.00

0.0090 org Kepala tukang batu @ Rp. 75,000.00 675.00

0.0540 org Pekerja @ Rp. 50,000.00 2,700.00

0.0270 org Mandor @ Rp. 65,000.00 1,755.00

JUMLAH ( BELUM PPN ) 10,080.00 49,770.50 59,850.50

OVERHEAD 10 % 1,008.00 4,977.05 5,985.05

JUMLAH 11,088.00 54,747.55 65,835.55

DIBULATKAN 11,088.00 54,747.00 65,835.00

SNI 1.0000 Memasang pipa galvanis diameter 1 1/2"

1.2000 Pipa galvanis @ Rp. 49,708.75 59,650.50

6.22 35% x Harga pipa (Perlengkapan) @ Rp. 49,708.75 17,398.06

0.1800 org Tukang batu @ Rp. 55,000.00 9,900.00

0.0180 org Kepala tukang batu @ Rp. 75,000.00 1,350.00

0.1080 org Pekerja @ Rp. 50,000.00 5,400.00

0.0054 org Mandor @ Rp. 65,000.00 351.00

JUMLAH ( BELUM PPN ) 17,001.00 77,048.56 94,049.56

OVERHEAD 10 % 1,700.10 7,704.86 9,404.96

JUMLAH 18,701.10 84,753.42 103,454.52

DIBULATKAN 18,701.00 84,753.00 103,454.00

SNI 1.0000 Memasang pipa PVC tipe AW diameter 1/2"

1.2000 Pipa PVC @ Rp. 7,000.00 8,400.00

6.25 35% x Harga pipa (Perlengkapan) @ Rp. 7,000.00 2,450.00

0.0600 org Tukang batu @ Rp. 55,000.00 3,300.00

0.0060 org Kepala tukang batu @ Rp. 75,000.00 450.00

0.0360 org Pekerja @ Rp. 50,000.00 1,800.00

0.0018 org Mandor @ Rp. 65,000.00 117.00

JUMLAH ( BELUM PPN ) 5,667.00 10,850.00 16,517.00

OVERHEAD 10 % 566.70 1,085.00 1,651.70

JUMLAH 6,233.70 11,935.00 18,168.70

DIBULATKAN 6,233.00 11,935.00 18,168.00

SNI 1.0000 Memasang pipa PVC tipe AW diameter 3/4"

m1

m1

m1

m1

m1

m1

m1

m1

m1

Page 32: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

1.2000 Pipa PVC @ Rp. 10,012.76 12,015.31

6.26 35% x Harga pipa (Perlengkapan) @ Rp. 10,012.76 3,504.47

0.0600 org Tukang batu @ Rp. 55,000.00 3,300.00

0.0060 org Kepala tukang batu @ Rp. 75,000.00 450.00

0.0360 org Pekerja @ Rp. 50,000.00 1,800.00

0.0018 org Mandor @ Rp. 65,000.00 117.00

JUMLAH ( BELUM PPN ) 5,667.00 15,519.78 21,186.78

OVERHEAD 10 % 566.70 1,551.98 2,118.68

JUMLAH 6,233.70 17,071.76 23,305.46

DIBULATKAN 6,233.00 17,071.00 23,305.00

SNI 1.0000 Memasang pipa PVC tipe AW diameter 1"

1.2000 Pipa PVC @ Rp. 13,563.39 16,276.07

6.27 35% x Harga pipa (Perlengkapan) @ Rp. 13,563.39 4,747.19

0.0600 org Tukang batu @ Rp. 55,000.00 3,300.00

0.0060 org Kepala tukang batu @ Rp. 75,000.00 450.00

0.0360 org Pekerja @ Rp. 50,000.00 1,800.00

0.0018 org Mandor @ Rp. 65,000.00 117.00

JUMLAH ( BELUM PPN ) 5,667.00 21,023.25 26,690.25

OVERHEAD 10 % 566.70 2,102.33 2,669.03

JUMLAH 6,233.70 23,125.58 29,359.28

DIBULATKAN 6,233.00 23,125.00 29,359.00

SNI 1.0000 Memasang pipa PVC tipe AW diameter 1 1/2"

1.2000 Pipa PVC @ Rp. 24,428.30 29,313.96

6.28 35% x Harga pipa (Perlengkapan) @ Rp. 24,428.30 8,549.90

0.0600 org Tukang batu @ Rp. 55,000.00 3,300.00

0.0060 org Kepala tukang batu @ Rp. 75,000.00 450.00

0.0360 org Pekerja @ Rp. 50,000.00 1,800.00

0.0018 org Mandor @ Rp. 65,000.00 117.00

JUMLAH ( BELUM PPN ) 5,667.00 37,863.87 43,530.87

OVERHEAD 10 % 566.70 3,786.39 4,353.09

JUMLAH 6,233.70 41,650.25 47,883.95

DIBULATKAN 6,233.00 41,650.00 47,883.00

SNI 1.0000 Memasang pipa PVC tipe AW diameter 2"

1.2000 Pipa PVC @ Rp. 30,000.00 36,000.00

6.29 35% x Harga pipa (Perlengkapan) @ Rp. 30,000.00 10,500.00

0.0900 org Tukang batu @ Rp. 55,000.00 4,950.00

0.0090 org Kepala tukang batu @ Rp. 75,000.00 675.00

0.0544 org Pekerja @ Rp. 50,000.00 2,720.00

0.0027 org Mandor @ Rp. 65,000.00 175.50

JUMLAH ( BELUM PPN ) 8,520.50 46,500.00 55,020.50

OVERHEAD 10 % 852.05 4,650.00 5,502.05

JUMLAH 9,372.55 51,150.00 60,522.55

DIBULATKAN 9,372.00 51,150.00 60,522.00

SNI 1.0000 Memasang pipa PVC tipe AW diameter 2 1/2"

1.2000 Pipa PVC @ Rp. 60,218.60 72,262.32

6.30 35% x Harga pipa (Perlengkapan) @ Rp. 60,218.60 21,076.51

0.0600 org Tukang batu @ Rp. 55,000.00 3,300.00

0.0060 org Kepala tukang batu @ Rp. 75,000.00 450.00

0.0360 org Pekerja @ Rp. 50,000.00 1,800.00

0.0018 org Mandor @ Rp. 65,000.00 117.00

JUMLAH ( BELUM PPN ) 5,667.00 93,338.83 99,005.83

m1

m1

m1

m1

m1

m1

m1

m1

m1

Page 33: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

OVERHEAD 10 % 566.70 9,333.88 9,900.58

JUMLAH 6,233.70 102,672.71 108,906.41

DIBULATKAN 6,233.00 102,672.00 108,906.00

SNI 1.0000 Memasang pipa PVC tipe AW diameter 3"

1.2000 Pipa PVC @ Rp. 60,218.60 72,262.32

6.31 35% x Harga pipa (Perlengkapan) @ Rp. 60,218.60 21,076.51

0.1350 org Tukang batu @ Rp. 55,000.00 7,425.00

0.0135 org Kepala tukang batu @ Rp. 75,000.00 1,012.50

0.0810 org Pekerja @ Rp. 50,000.00 4,050.00

0.0410 org Mandor @ Rp. 65,000.00 2,665.00

JUMLAH ( BELUM PPN ) 15,152.50 93,338.83 108,491.33

OVERHEAD 10 % 1,515.25 9,333.88 10,849.13

JUMLAH 16,667.75 102,672.71 119,340.46

DIBULATKAN 16,667.00 102,672.00 119,340.00

SNI 1.0000 Memasang pipa PVC tipe AW diameter 4"

1.2000 Pipa PVC @ Rp. 80,000.00 96,000.00

6.32 35% x Harga pipa (Perlengkapan) @ Rp. 80,000.00 28,000.00

0.1350 org Tukang batu @ Rp. 55,000.00 7,425.00

0.0135 org Kepala tukang batu @ Rp. 75,000.00 1,012.50

0.0810 org Pekerja @ Rp. 50,000.00 4,050.00

0.0410 org Mandor @ Rp. 65,000.00 2,665.00

JUMLAH ( BELUM PPN ) 15,152.50 124,000.00 139,152.50

OVERHEAD 10 % 1,515.25 12,400.00 13,915.25

JUMLAH 16,667.75 136,400.00 153,067.75

DIBULATKAN 16,667.00 136,400.00 153,067.00

SNI 1.0000 bh Memasang bak cuci piring stainless steel

1.0000 bh Bak cuci stainless steel @ Rp. 355,062.50 355,062.50

6.33 1.0000 set Water drain + asesories @ Rp. 125,000.00 125,000.00

0.3000 org Tukang batu @ Rp. 55,000.00 16,500.00

0.0300 org Kepala tukang batu @ Rp. 75,000.00 2,250.00

0.0300 org Pekerja @ Rp. 50,000.00 1,500.00

0.0015 org Mandor @ Rp. 65,000.00 97.50

JUMLAH ( BELUM PPN ) 20,347.50 480,062.50 500,410.00

OVERHEAD 10 % 2,034.75 48,006.25 50,041.00

JUMLAH 22,382.25 528,068.75 550,451.00

DIBULATKAN 22,382.00 528,068.00 550,451.00

SNI 1.0000 bh Memasang kran diameter 3/4" atau 1/2"

1.0000 bh Kran air @ Rp. 38,750.00 38,750.00

6.35 0.0250 bh Seal tape @ Rp. 7,000.00 175.00

0.1000 org Tukang batu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang batu @ Rp. 75,000.00 750.00

0.0100 org Pekerja @ Rp. 50,000.00 500.00

0.0050 org Mandor @ Rp. 65,000.00 325.00

JUMLAH ( BELUM PPN ) 7,075.00 38,925.00 46,000.00

OVERHEAD 10 % 707.50 3,892.50 4,600.00

JUMLAH 7,782.50 42,817.50 50,600.00

DIBULATKAN 7,782.00 42,817.00 50,600.00

SNI 1.0000 bh Memasang floor drain

1.0000 bh Floor drain @ Rp. 24,854.38 24,854.38

6.35 0.1000 org Tukang batu @ Rp. 55,000.00 5,500.00

m1

m1

m1

m1

Page 34: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

0.0100 org Kepala tukang batu @ Rp. 75,000.00 750.00

0.0100 org Pekerja @ Rp. 50,000.00 500.00

0.0050 org Mandor @ Rp. 65,000.00 325.00

JUMLAH ( BELUM PPN ) 7,075.00 24,854.38 31,929.38

OVERHEAD 10 % 707.50 2,485.44 3,192.94

JUMLAH 7,782.50 27,339.82 35,122.32

DIBULATKAN 7,782.00 27,339.00 35,122.00

PEKERJAAN BESI DAN ALUMUNIUM SNI 1.0000 Pasang pintu gulung besi

1.0000 Pintu gulung besi @ Rp. 450,000.00 450,000.00

6.5 1.2000 org Tukang besi konstruksi @ Rp. 55,000.00 66,000.00

0.1200 org Kepala tukang besi @ Rp. 75,000.00 9,000.00

1.2000 org Pekerja @ Rp. 50,000.00 60,000.00

0.0060 org Mandor @ Rp. 65,000.00 390.00

JUMLAH ( BELUM PPN ) 135,390.00 450,000.00 585,390.00

OVERHEAD 10 % 13,539.00 45,000.00 58,539.00

JUMLAH 148,929.00 495,000.00 643,929.00

DIBULATKAN 148,929.00 495,000.00 643,929.00

SNI 1.0000 Pasang pintu lipat

1.0000 Pintu lipat @ Rp. 450,000.00 450,000.00

6.6 1.0500 org Tukang besi konstruksi @ Rp. 55,000.00 57,750.00

0.1050 org Kepala tukang besi @ Rp. 75,000.00 7,875.00

1.0500 org Pekerja @ Rp. 50,000.00 52,500.00

0.0052 org Mandor @ Rp. 65,000.00 338.00

JUMLAH ( BELUM PPN ) 118,463.00 450,000.00 568,463.00

OVERHEAD 10 % 11,846.30 45,000.00 56,846.30

JUMLAH 130,309.30 495,000.00 625,309.30

DIBULATKAN 130,309.00 495,000.00 625,309.00

SNI 1.0000 Pasang Rolling door

1.0000 Roll door @ Rp. 450,000.00 450,000.00

6.8 1.5000 org Tukang besi konstruksi @ Rp. 55,000.00 82,500.00

0.1050 org Kepala tukang besi @ Rp. 75,000.00 7,875.00

1.0500 org Pekerja @ Rp. 50,000.00 52,500.00

0.0052 org Mandor @ Rp. 65,000.00 338.00

JUMLAH ( BELUM PPN ) 143,213.00 450,000.00 593,213.00

OVERHEAD 10 % 14,321.30 45,000.00 59,321.30

JUMLAH 157,534.30 495,000.00 652,534.30

DIBULATKAN 157,534.00 495,000.00 652,534.00

SNI 1.0000 Pasang pintu/jendela alumunium

1.0000 Pintu alumunium @ Rp. 700,000.00 700,000.00

6.9 1.0500 org Tukang besi konstruksi @ Rp. 55,000.00 57,750.00

0.1050 org Kepala tukang besi @ Rp. 75,000.00 7,875.00

0.0052 org Mandor @ Rp. 65,000.00 338.00

JUMLAH ( BELUM PPN ) 65,963.00 700,000.00 765,963.00

OVERHEAD 10 % 6,596.30 70,000.00 76,596.30

JUMLAH 72,559.30 770,000.00 842,559.30

DIBULATKAN 72,559.00 770,000.00 842,559.00

SNI 1.0000 Pasang teralis besi

11.5000 Baja strip 2 x 3 @ Rp. 16,332.88 187,828.12

m2

m2

m2

m2

m2

m2

m2

m2

m2

m1

Page 35: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

6.12 1.2000 org Tukang las @ Rp. 55,000.00 66,000.00

0.0120 org Kepala tukang las @ Rp. 75,000.00 900.00

1.2000 org Pekerja @ Rp. 50,000.00 60,000.00

0.0006 org Mandor @ Rp. 65,000.00 39.00

JUMLAH ( BELUM PPN ) 126,939.00 187,828.12 314,767.12

OVERHEAD 10 % 12,693.90 18,782.81 31,476.71

JUMLAH 139,632.90 206,610.93 346,243.83

DIBULATKAN 139,632.00 206,610.00 346,243.00

SNI 1.0000 Pasang kawat harmonika

1.1000 Kawat harmonika @ Rp. 63,911.25 70,302.38

6.13 0.0200 kg Paku biasa 1/2" - 1" @ Rp. 16,055.00 321.10

0.0018 Kayu kelas II papan @ Rp. 3,087,000.00 5,556.60

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang kayu @ Rp. 75,000.00 750.00

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

0.0005 org Mandor @ Rp. 65,000.00 32.50

JUMLAH ( BELUM PPN ) 11,282.50 76,180.08 87,462.58

OVERHEAD 10 % 1,128.25 7,618.01 8,746.26

JUMLAH 12,410.75 83,798.08 96,208.83

DIBULATKAN 12,410.00 83,798.00 96,208.00

SNI 1.0000 Pasang kawat nyamuk

1.1000 Kawat nyamuk @ Rp. 21,612.50 23,773.75

6.14 0.0200 kg Paku biasa 1/2" - 1" @ Rp. 16,055.00 321.10

0.0018 Kayu kelas II papan @ Rp. 3,087,000.00 5,556.60

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang kayu @ Rp. 75,000.00 750.00

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

0.0005 org Mandor @ Rp. 65,000.00 32.50

JUMLAH ( BELUM PPN ) 11,282.50 29,651.45 40,933.95

OVERHEAD 10 % 1,128.25 2,965.15 4,093.40

JUMLAH 12,410.75 32,616.60 45,027.35

DIBULATKAN 12,410.00 32,616.00 45,027.00

SNI 1.0000 Pasang kawat kassa

1.1000 Kawat kassa @ Rp. 21,612.50 23,773.75

6.15 0.0200 kg Paku biasa 1/2" - 1" @ Rp. 16,055.00 321.10

0.0018 Kayu kelas II papan @ Rp. 3,087,000.00 5,556.60

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang kayu @ Rp. 75,000.00 750.00

0.1000 org Pekerja @ Rp. 50,000.00 5,000.00

0.0005 org Mandor @ Rp. 65,000.00 32.50

JUMLAH ( BELUM PPN ) 11,282.50 29,651.45 40,933.95

OVERHEAD 10 % 1,128.25 2,965.15 4,093.40

JUMLAH 12,410.75 32,616.60 45,027.35

DIBULATKAN 12,410.00 32,616.00 45,027.00

SNI 1.0000 Pasang jendela nako & tralis

1.1000 Jendela nako @ Rp. 113,620.00 124,982.00

6.17 0.0200 kg Paku skrup @ Rp. 34,000.00 680.00

0.0250 Besi strip @ Rp. 12,072.13 301.80

0.2000 org Tukang kayu @ Rp. 55,000.00 11,000.00

0.0200 org Kepala tukang kayu @ Rp. 75,000.00 1,500.00

0.2000 org Pekerja @ Rp. 50,000.00 10,000.00

m2

m2

m3

m2

m2

m3

m2

m2

m3

m2

m2

m2

Page 36: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

0.0010 org Mandor @ Rp. 65,000.00 65.00

JUMLAH ( BELUM PPN ) 22,565.00 125,963.80 148,528.80

OVERHEAD 10 % 2,256.50 12,596.38 14,852.88

JUMLAH 24,821.50 138,560.18 163,381.68

DIBULATKAN 24,821.00 138,560.00 163,381.00

PEKERJAAN KUNCI DAN KACA

6.1 1.0000 bh Pasang kunci pintu merk SES

1.0000 bh Kunci pintu Double slag merk SES @ Rp. 225,000.00 225,000.00

0.6000 org Tukang kayu @ Rp. 55,000.00 33,000.00

0.0600 org Kepala tukang kayu @ Rp. 75,000.00 4,500.00

0.0600 org Pekerja @ Rp. 50,000.00 3,000.00

0.0030 org Mandor @ Rp. 65,000.00 195.00

JUMLAH ( BELUM PPN ) 40,695.00 225,000.00 265,695.00

OVERHEAD 10 % 4,069.50 22,500.00 26,569.50

JUMLAH 44,764.50 247,500.00 292,264.50

DIBULATKAN 44,764.00 247,500.00 292,264.00

6.2 1.0000 bh Pasang handle pintu

1.0000 bh handle pintu @ Rp. 115,000.00 115,000.00

0.5000 org Tukang kayu @ Rp. 55,000.00 27,500.00

0.0100 org Kepala tukang kayu @ Rp. 75,000.00 750.00

0.0100 org Pekerja @ Rp. 50,000.00 500.00

0.0050 org Mandor @ Rp. 65,000.00 325.00

JUMLAH ( BELUM PPN ) 29,075.00 115,000.00 144,075.00

OVERHEAD 10 % 2,907.50 11,500.00 14,407.50

JUMLAH 31,982.50 126,500.00 158,482.50

DIBULATKAN 31,982.00 126,500.00 158,482.00

6.3 1.0000 bh Pasang kunci tanam kamar mandi

1.0000 bh Kunci tanam kamar mandi @ Rp. 50,000.00 50,000.00

0.5000 org Tukang kayu @ Rp. 55,000.00 27,500.00

0.0050 org Kepala tukang kayu @ Rp. 75,000.00 375.00

0.0050 org Pekerja @ Rp. 50,000.00 250.00

0.0025 org Mandor @ Rp. 65,000.00 162.50

JUMLAH ( BELUM PPN ) 28,287.50 50,000.00 78,287.50

OVERHEAD 10 % 2,828.75 5,000.00 7,828.75

JUMLAH 31,116.25 55,000.00 86,116.25

DIBULATKAN 31,116.00 55,000.00 86,116.00

6.4 1.0000 bh Pasang kunci tanam silinder

1.0000 bh Kunci silinder @ Rp. #REF! #REF!

0.5000 org Tukang kayu @ Rp. 55,000.00 27,500.00

0.0050 org Kepala tukang kayu @ Rp. 75,000.00 375.00

0.0050 org Pekerja @ Rp. 50,000.00 250.00

0.0003 org Mandor @ Rp. 65,000.00 16.25

JUMLAH ( BELUM PPN ) 28,141.25 #REF! #REF!

OVERHEAD 10 % 2,814.13 #REF! #REF!

JUMLAH 30,955.38 #REF! #REF!

DIBULATKAN 30,955.00 #REF! #REF!

6.5 1.0000 bh Pasang engsel pintu

1.0000 bh Engsel pintu @ Rp. 24,700.00 24,700.00

Page 37: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

0.1500 org Tukang kayu @ Rp. 55,000.00 8,250.00

0.0150 org Kepala tukang kayu @ Rp. 75,000.00 1,125.00

0.0150 org Pekerja @ Rp. 50,000.00 750.00

0.0008 org Mandor @ Rp. 65,000.00 48.75

JUMLAH ( BELUM PPN ) 10,173.75 24,700.00 34,873.75

OVERHEAD 10 % 1,017.38 2,470.00 3,487.38

JUMLAH 11,191.13 27,170.00 38,361.13

DIBULATKAN 11,191.00 27,170.00 38,361.00

6.6 1.0000 bh Pasang engsel jendela kupu-kupu

1.0000 bh Engsel jendela @ Rp. 18,525.00 18,525.00

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang kayu @ Rp. 75,000.00 750.00

0.0100 org Pekerja @ Rp. 50,000.00 500.00

0.0050 org Mandor @ Rp. 65,000.00 325.00

JUMLAH ( BELUM PPN ) 7,075.00 18,525.00 25,600.00

OVERHEAD 10 % 707.50 1,852.50 2,560.00

JUMLAH 7,782.50 20,377.50 28,160.00

DIBULATKAN 7,782.00 20,377.00 28,160.00

6.7 1.0000 bh Pasang engsel angin

1.0000 bh Engsel angin @ Rp. 18,525.00 18,525.00

0.2000 org Tukang kayu @ Rp. 55,000.00 11,000.00

0.0200 org Kepala tukang kayu @ Rp. 75,000.00 1,500.00

0.0200 org Pekerja @ Rp. 50,000.00 1,000.00

0.0100 org Mandor @ Rp. 65,000.00 650.00

JUMLAH ( BELUM PPN ) 14,150.00 18,525.00 32,675.00

OVERHEAD 10 % 1,415.00 1,852.50 3,267.50

JUMLAH 15,565.00 20,377.50 35,942.50

DIBULATKAN 15,565.00 20,377.00 35,942.00

6.8 1.0000 bh Pasang spring knip

1.0000 bh Spring knip @ Rp. 35,000.00 35,000.00

0.1500 org Tukang kayu @ Rp. 55,000.00 8,250.00

0.0150 org Kepala tukang kayu @ Rp. 75,000.00 1,125.00

0.0150 org Pekerja @ Rp. 50,000.00 750.00

0.0008 org Mandor @ Rp. 65,000.00 48.75

JUMLAH ( BELUM PPN ) 10,173.75 35,000.00 45,173.75

OVERHEAD 10 % 1,017.38 3,500.00 4,517.38

JUMLAH 11,191.13 38,500.00 49,691.13

DIBULATKAN 11,191.00 38,500.00 49,691.00

6.9 1.0000 bh Pasang kait angin

1.0000 bh Kait angin @ Rp. 30,875.00 30,875.00

0.1500 org Tukang kayu @ Rp. 55,000.00 8,250.00

0.0150 org Kepala tukang kayu @ Rp. 75,000.00 1,125.00

0.0150 org Pekerja @ Rp. 50,000.00 750.00

0.0008 org Mandor @ Rp. 65,000.00 48.75

JUMLAH ( BELUM PPN ) 10,173.75 30,875.00 41,048.75

OVERHEAD 10 % 1,017.38 3,087.50 4,104.88

JUMLAH 11,191.13 33,962.50 45,153.63

DIBULATKAN 11,191.00 33,962.00 45,153.00

6.10 1.0000 bh Pasang door closer

1.0000 bh Door closer @ Rp. 200,000.00 200,000.00

Page 38: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

0.5000 org Tukang kayu @ Rp. 55,000.00 27,500.00

0.0500 org Kepala tukang kayu @ Rp. 75,000.00 3,750.00

0.0500 org Pekerja @ Rp. 50,000.00 2,500.00

0.0025 org Mandor @ Rp. 65,000.00 162.50

JUMLAH ( BELUM PPN ) 33,912.50 200,000.00 233,912.50

OVERHEAD 10 % 3,391.25 20,000.00 23,391.25

JUMLAH 37,303.75 220,000.00 257,303.75

DIBULATKAN 37,303.00 220,000.00 257,303.00

6.11 1.0000 bh Pasang kunci selot

1.0000 bh Kunci selot @ Rp. 75,000.00 75,000.00

0.2000 org Tukang kayu @ Rp. 55,000.00 11,000.00

0.0200 org Kepala tukang kayu @ Rp. 75,000.00 1,500.00

0.0200 org Pekerja @ Rp. 50,000.00 1,000.00

0.0010 org Mandor @ Rp. 65,000.00 65.00

JUMLAH ( BELUM PPN ) 13,565.00 75,000.00 88,565.00

OVERHEAD 10 % 1,356.50 7,500.00 8,856.50

JUMLAH 14,921.50 82,500.00 97,421.50

DIBULATKAN 14,921.00 82,500.00 97,421.00

6.12 1.0000 bh Pasang pegangan pintu / door holder

1.0000 bh Door holder @ Rp. 50,000.00 50,000.00

0.5000 org Tukang kayu @ Rp. 55,000.00 27,500.00

0.0500 org Kepala tukang kayu @ Rp. 75,000.00 3,750.00

0.0500 org Pekerja @ Rp. 50,000.00 2,500.00

0.0025 org Mandor @ Rp. 65,000.00 162.50

JUMLAH ( BELUM PPN ) 33,912.50 50,000.00 83,912.50

OVERHEAD 10 % 3,391.25 5,000.00 8,391.25

JUMLAH 37,303.75 55,000.00 92,303.75

DIBULATKAN 37,303.00 55,000.00 92,303.00

6.13 1.0000 bh Pasang door stop

1.0000 bh Door stop @ Rp. 50,000.00 50,000.00

0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00

0.0100 org Kepala tukang kayu @ Rp. 75,000.00 750.00

0.0100 org Pekerja @ Rp. 50,000.00 500.00

0.0005 org Mandor @ Rp. 65,000.00 32.50

JUMLAH ( BELUM PPN ) 6,782.50 50,000.00 56,782.50

OVERHEAD 10 % 678.25 5,000.00 5,678.25

JUMLAH 7,460.75 55,000.00 62,460.75

DIBULATKAN 7,460.00 55,000.00 62,460.00

6.14 1.0000 bh Pasang rel pintu dorong

1.0000 bh Rel pintu dorong @ Rp. 350,000.00 350,000.00

0.6000 org Tukang kayu @ Rp. 55,000.00 33,000.00

0.0600 org Kepala tukang kayu @ Rp. 75,000.00 4,500.00

0.0600 org Pekerja @ Rp. 50,000.00 3,000.00

0.0030 org Mandor @ Rp. 65,000.00 195.00

JUMLAH ( BELUM PPN ) 40,695.00 350,000.00 390,695.00

OVERHEAD 10 % 4,069.50 35,000.00 39,069.50

JUMLAH 44,764.50 385,000.00 429,764.50

DIBULATKAN 44,764.00 385,000.00 429,764.00

6.15 1.0000 bh Pasang kunci lemari

1.0000 bh Kunci lemari @ Rp. 25,000.00 25,000.00

Page 39: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

0.2500 org Tukang kayu @ Rp. 55,000.00 13,750.00

0.0250 org Kepala tukang kayu @ Rp. 75,000.00 1,875.00

0.0250 org Pekerja @ Rp. 50,000.00 1,250.00

0.0013 org Mandor @ Rp. 65,000.00 81.25

JUMLAH ( BELUM PPN ) 16,956.25 25,000.00 41,956.25

OVERHEAD 10 % 1,695.63 2,500.00 4,195.63

JUMLAH 18,651.88 27,500.00 46,151.88

DIBULATKAN 18,651.00 27,500.00 46,151.00

6.16 1.0000 Pasang kaca, tebal 3 mm

1.1000 Kaca polos @ Rp. 78,113.75 85,925.13

0.1500 org Tukang kayu @ Rp. 55,000.00 8,250.00

0.0150 org Kepala tukang kayu @ Rp. 75,000.00 1,125.00

0.0150 org Pekerja @ Rp. 50,000.00 750.00

0.0008 org Mandor @ Rp. 65,000.00 48.75

JUMLAH ( BELUM PPN ) 10,173.75 85,925.13 96,098.88

OVERHEAD 10 % 1,017.38 8,592.51 9,609.89

JUMLAH 11,191.13 94,517.64 105,708.76

DIBULATKAN 11,191.00 94,517.00 105,708.00

6.17 1.0000 Pasang kaca, tebal 5 mm

1.0000 Kaca polos @ Rp. 83,362.50 83,362.50

0.0080 org Pekerja @ Rp. 50,000.00 400.00

0.0008 org Mandor @ Rp. 65,000.00 48.75

JUMLAH ( BELUM PPN ) 448.75 83,362.50 83,811.25

OVERHEAD 10 % 44.88 8,336.25 8,381.13

JUMLAH 493.63 91,698.75 92,192.38

DIBULATKAN 493.00 91,698.00 92,192.00

6.18 1.0000 Pasang kaca cermin, tebal 5 mm

1.1000 Kaca cermin @ Rp. 130,000.00 143,000.00

0.1500 org Tukang kayu @ Rp. 55,000.00 8,250.00

0.0150 org Kepala tukang kayu @ Rp. 75,000.00 1,125.00

0.0150 org Pekerja @ Rp. 50,000.00 750.00

0.0008 org Mandor @ Rp. 65,000.00 48.75

JUMLAH ( BELUM PPN ) 10,173.75 143,000.00 153,173.75

OVERHEAD 10 % 1,017.38 14,300.00 15,317.38

JUMLAH 11,191.13 157,300.00 168,491.13

DIBULATKAN 11,191.00 157,300.00 168,491.00

6.19 1.0000 Pasang kaca patri, tebal 5 mm

1.1000 Kaca patri @ Rp. 500,000.00 550,000.00

0.1500 org Tukang kayu @ Rp. 55,000.00 8,250.00

0.0150 org Kepala tukang kayu @ Rp. 75,000.00 1,125.00

0.0150 org Pekerja @ Rp. 50,000.00 750.00

0.0008 org Mandor @ Rp. 65,000.00 48.75

JUMLAH ( BELUM PPN ) 10,173.75 550,000.00 560,173.75

OVERHEAD 10 % 1,017.38 55,000.00 56,017.38

JUMLAH 11,191.13 605,000.00 616,191.13

DIBULATKAN 11,191.00 605,000.00 616,191.00

m2

m2

m2

m2

m2

m2

m2

m2

Page 40: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Upah Bahan Jumlah

(1) (2) (3) (4) (5)

6.20 1.0000 Pasang kusen alumunium

1.1000 Kusen alumunium @ Rp. 85,000.00 93,500.00

15% x Harga kusen (Perlengkapan) @ Rp. 85,000.00 12,750.00

0.1500 oh Tukang alumunium @ Rp. 55,000.00 8,250.00

0.0150 oh Kepala tukang @ Rp. 75,000.00 1,125.00

0.0150 oh Pekerja @ Rp. 50,000.00 750.00

0.0008 oh Mandor @ Rp. 65,000.00 48.75

JUMLAH ( BELUM PPN ) 10,173.75 106,250.00 116,423.75

OVERHEAD 10 % 1,017.38 10,625.00 11,642.38

JUMLAH 11,191.13 106,250.00 117,441.13

DIBULATKAN 11,191.00 106,250.00 117,441.00

m1

m1

Page 41: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

DAFTAR HARGA SATUAN PEKERJAANNo. Macam Pekerjaan Harga

(1) (2) (3)

PEKERJAAN PERSIAPAN 1.0000 m2 Pekerjaan Pengukuran @Rp. 9,322.50

1.0000 m1 Pemasangan bouwplank @Rp. 77,604.00

1.0000 m2 Membersihkan lapangan/ lokasi pekerjaan @Rp. 9,075.00

PEKERJAAN TANAH 1.0000 m3 Galian tanah biasa sedalam sampai 1 meter @Rp. 43,037.00

1.0000 m3 Galian tanah biasa sedalam 1 - 2 meter @Rp. 52,717.00

1.0000 m3 Galian tanah biasa sedalam 2 - 3 meter @Rp. 62,540.00

1.0000 m3 Galian tanah keras sedalam sampai 1 meter @Rp. 57,288.00

1.0000 m3 Galian tanah cadas sedalam sampai 1 meter @Rp. 86,790.00

1.0000 m3 Galian tanah lumpur sedalam 1 meter @Rp. 69,217.00

1.0000 m1 Membuat sumur @Rp. 581,655.00

1.0000 m3 Mengangkut tanah sejauh 30 meter @Rp. 18,865.00

1.0000 m3 Pembuangan tanah sejauh 15 meter @Rp. 18,865.00

1.0000 m3 Membuang tanah dengan menghampar @Rp. 14,465.00

1.0000 m3 Urug kembali bekas galian @Rp. 14,345.67

1.0000 m2 Memadatkan tanah (per 20 cm) @Rp. 31,075.00

1.0000 m3 Urug pasir @Rp. 241,747.00

1.0000 m3 Urug tanah mendatangkan @Rp. 70,015.00

1.0000 m3 Urugan sirtu @Rp. 162,585.00

1.0000 m3 Pemasangan lapisan ijuk @Rp. 226,737.00

PEKERJAAN PASANGAN 1.0000 m3 Pasangan pondasi batu kosong @Rp. 403,076.00

1.0000 m3 Pasangan pondasi 1 Pc : 4 Ps @Rp. 715,253.00

1.0000 m3 Pasangan pondasi 1 Pc : 3 Ps @Rp. 763,444.00

1.0000 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps @Rp. 94,834.00

1.0000 m2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps @Rp. 195,961.00

1.0000 m2 Pasangan dinding bataco @Rp. 100,248.00

1.0000 m2 Pasangan roster 25/25 cm @Rp. 108,711.00

1.0000 m2 Pasangan paving block/conblock @Rp. 29,236.00

PEKERJAAN BETON 1.0000 m3 Membuat beton dengan mutu K 225 @Rp. 895,425.00

1.0000 m3 Membuat beton dengan mutu K 275 @Rp. 1,015,496.00

1.0000 m3 Membuat beton dengan mutu K 300 @Rp. 1,023,775.00

1.0000 kg Pembesian dengan besi polos @Rp. 15,416.00

1.0000 kg Pembesian dengan besi ulir @Rp. 14,435.00

1.0000 m3 Membuat 1m³ Pondasi Beton Bertulang (150 Kg Besi + Bekisting) @Rp. 3,844,028.00

1.0000 m3 Membuat 1m³ Sloof Beton Bertulang (200 Kg Besi + Bekisting) @Rp. 4,788,316.00

1.0000 m3 Membuat 1m³ Kolom Beton Bertulang (200 Kg Besi + Bekisting) @Rp. 6,416,118.00

1.0000 m3 Membuat 1m³ Kolom Beton Bertulang (100 Kg Besi + Bekisting) @Rp. 4,963,202.00

1.0000 m3 Membuat 1m³ Balok Beton Bertulang (200 Kg Besi + Bekisting) @Rp. 5,950,011.00

1.0000 m3 Membuat 1m³ Plat Beton Bertulang (150 Kg Besi + Bekisting) @Rp. 5,508,073.00

1.0000 m1 Membuat 1m' Kolom Praktis Beton Bertulang (11 x 11) @Rp. 68,973.00

1.0000 m1 Membuat 1m' Ring Balok Beton Bertulang (10 x 15) @Rp. 92,826.00

PEKERJAAN PELESTERAN 1.0000 m2 Plesteran 1 Pc : 4 Ps, tebal 15 mm @Rp. 41,134.00

Page 42: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Harga

(1) (2) (3)

1.0000 m2 Plesteran beton 1 Pc : 3 Ps, tebal 15 mm @Rp. 43,102.00

1.0000 m2 Plesteran beton 1 Pc : 2 Ps, tebal 15 mm @Rp. 45,977.00

1.0000 m2 Plesteran Ciprat, 1 Pc : 2 Ps @Rp. 31,633.00

1.0000 m2 Acian @Rp. 23,151.00

1.0000 m2 Pasang dinding batu hias tempel @Rp. 253,298.00

PEKERJAAN KERAMIK 1.0000 m2 Pasang keramik 20/20 @Rp. 169,770.00

1.0000 m2 Pasang keramik 30/30 @Rp. 186,803.00

1.0000 m2 Pasang keramik 40/40 @Rp. 204,248.00

1.0000 m1 Pasang plint keramik ukuran 10 x 40 cm @Rp. 12,244.00

1.0000 m1 Pasang plint keramik ukuran 10 x 30 cm @Rp. 10,276.00

1.0000 m1 Pasang list keramik dinding 5/20 @Rp. 46,712.00

1.0000 m2 Pasang keramik dinding 20/25 @Rp. 179,950.00

PEKERJAAN RANGKA ATAP 1.0000 m2 Pasang kuda-kuda baja ringan @Rp. 168,575.00

1.0000 m3 Membuat kuda-kuda kayu kelas II @Rp. 5,092,658.00

1.0000 m3 Pasang kuda-kuda kayu lama @Rp. 1,272,618.00

1.0000 m3 Pasang Nook,Goording dan Jurai kayu Kelas II @Rp. 4,623,021.00

1.0000 m3 Pasang Goording Lama @Rp. 1,073,428.00

1.0000 m2 Pasang usuk 5/7, reng 2/3 lama @Rp. 16,968.00

1.0000 m2 Pasang usuk 5/7, reng 2/3 kayu kelas II @Rp. 212,592.00

PEKERJAAN PINTU DAN JENDELA 1.0000 m3 Membuat kusen pintu / jendela kayu Surian @Rp. 6,121,415.00

1.0000 m2 Pasang pintu panel kayu surian @Rp. 441,514.00

1.0000 m2 Pasang pintu dan jendela kaca kayu surian @Rp. 317,873.00

1.0000 m2 Pasang jalusi kusen kayu surian @Rp. 446,933.00

PEKERJAAN PLAFOND 1.0000 m2 Pasang rangka langit-langit (60 x 120) m, kayu kelas II @Rp. 74,783.00

1.0000 m2 Pasang langit-langit triplek (60 x 120) m, tebal 4 mm @Rp. 48,324.00

1.0000 m1 List langit-langit kayu profil @Rp. 21,522.00

PEKERJAAN LISPLANG 1.0000 m1 Pasang lisplank ukuran (2 x 20) cm, kayu surian @Rp. 33,935.00

1.0000 m1 Mengerjakan papan ruiter kayu kelas II 2/20 @Rp. 21,076.00

PEKERJAAN TALANG 1.0000 m1 Pasang talang datar, seng BJLS 20, papan kayu kelas II @Rp. 129,531.00

1.0000 m1 Pasang talang miring, seng BJLS 20, papan kayu kelas II @Rp. 155,401.00

PEKERJAAN ATAP 1.0000 m2 Pasang gentang metal @Rp. 90,915.00

1.0000 m1 Pasang bubungan genteng metal @Rp. 63,318.00

1.0000 m2 Pasang seng multy colour @Rp. 79,062.00

1.0000 m1 Pasang bubungan seng multy colour @Rp. 103,341.00

1.0000 m2 Pasang seng gelombang @Rp. 60,243.00

1.0000 m1 Pasang bubungan seng @Rp. 50,702.00

PEKERJAAN PENGECATAN 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup @Rp. 59,427.00

Page 43: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Harga

(1) (2) (3)

1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup @Rp. 61,803.00

1.0000 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) @Rp. 40,900.00

1.0000 m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) @Rp. 33,477.00

1.0000 m2 Pengecatan tembok tidak terlindung dari panas dan hujan @Rp. 22,187.00

1.0000 m2 Pengecatan bidang besi ( 3 x ) @Rp. 21,018.00

PEKERJAAN BONGKARAN 1.0000 m3 Membongkar pasangan batu kali @Rp. 264,000.00

1.0000 m3 Membongkar pasangan batu merah dan membersihkan @Rp. 126,500.00

1.0000 m3 Membongkar beton bertulang dan membersihkan @Rp. 459,250.00

10.0000 m2 Pekerjaan bongkar lantai tegel untuk dipergunakan lagi @Rp. 12,650.00

10.0000 m2 Mengupas plesteran lama @Rp. 8,250.00

10.0000 m2 Membongkar atap seng @Rp. 8,525.00

10.0000 m2 Membongkar usuk / reng dipakai lagi @Rp. 15,840.00

10.0000 m2 Membongkar usuk / reng tidak dipakai lagi @Rp. 11,715.00

1.0000 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi @Rp. 646,800.00

1.0000 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi @Rp. 69,300.00

1.0000 m3 Mengerjakan kembali bangunan kayu yang telah dibongkar @Rp. 1,059,300.00

PEKERJAAN SANITASI 1.0000 bh Memasang kloset duduk/monoblock @Rp. 2,577,988.00

1.0000 bh Memasang kloset jongkok @Rp. 502,139.00

1.0000 bh Memasang urinoir @Rp. 1,857,192.00

1.0000 bh Memasang wastafel @Rp. 970,929.00

1.0000 bh Memasang bak mandi fiberglass 60 x 60 @Rp. 571,249.00

1.0000 bh Memasang bak fiberglass 70 x 70 @Rp. 849,723.00

1.0000 m1 Memasang pipa beton, diameter 15 cm - 20 cm @Rp. 133,583.00

1.0000 m1 Memasang pipa beton, diameter 30 cm - 100 cm @Rp. 412,902.00

1.0000 m1 Memasang pipa galvanis diameter 1/2" @Rp. 42,673.00

1.0000 m1 Memasang pipa galvanis diameter 3/4" @Rp. 48,990.00

1.0000 m1 Memasang pipa galvanis diameter 1" @Rp. 65,835.00

1.0000 m1 Memasang pipa galvanis diameter 1 1/2" @Rp. 103,454.00

1.0000 m1 Memasang pipa PVC tipe AW diameter 1/2" @Rp. 18,168.00

1.0000 m1 Memasang pipa PVC tipe AW diameter 3/4" @Rp. 23,305.00

1.0000 m1 Memasang pipa PVC tipe AW diameter 1" @Rp. 29,359.00

1.0000 m1 Memasang pipa PVC tipe AW diameter 1 1/2" @Rp. 47,883.00

1.0000 m1 Memasang pipa PVC tipe AW diameter 2" @Rp. 60,522.00

1.0000 m1 Memasang pipa PVC tipe AW diameter 2 1/2" @Rp. 108,906.00

1.0000 m1 Memasang pipa PVC tipe AW diameter 3" @Rp. 119,340.00

1.0000 m1 Memasang pipa PVC tipe AW diameter 4" @Rp. 153,067.00

1.0000 bh Memasang bak cuci piring stainless steel @Rp. 550,451.00

1.0000 bh Memasang kran diameter 3/4" atau 1/2" @Rp. 50,600.00

1.0000 bh Memasang floor drain @Rp. 35,122.00

PEKERJAAN BESI DAN ALUMUNIUM 1.0000 m2 Pasang pintu gulung besi @Rp. 643,929.00

1.0000 m2 Pasang pintu lipat @Rp. 625,309.00

1.0000 m2 Pasang Rolling door @Rp. 652,534.00

1.0000 m2 Pasang pintu/jendela alumunium @Rp. 842,559.00

1.0000 m2 Pasang teralis besi @Rp. 346,243.00

1.0000 m2 Pasang kawat harmonika @Rp. 96,208.00

Page 44: CCO 2013c.xls

RSUD MHAT Kabupaten Kerinci

No. Macam Pekerjaan Harga

(1) (2) (3)

1.0000 m2 Pasang kawat nyamuk @Rp. 45,027.00

1.0000 m2 Pasang kawat kassa @Rp. 45,027.00

1.0000 m2 Pasang jendela nako & tralis @Rp. 163,381.00

PEKERJAAN KUNCI DAN KACA 1.0000 bh Pasang kunci pintu merk SES @Rp. 292,264.00

1.0000 bh Pasang kunci tanam kamar mandi @Rp. 86,116.00

1.0000 bh Pasang engsel pintu @Rp. 38,361.00

1.0000 bh Pasang engsel jendela kupu-kupu @Rp. 28,160.00

1.0000 bh Pasang engsel angin @Rp. 35,942.00

1.0000 bh Pasang spring knip @Rp. 49,691.00

1.0000 bh Pasang kait angin @Rp. 45,153.00

1.0000 bh Pasang door closer @Rp. 257,303.00

1.0000 bh Pasang kunci selot @Rp. 97,421.00

1.0000 bh Pasang pegangan pintu / door holder @Rp. 92,303.00

1.0000 bh Pasang door stop @Rp. 62,460.00

1.0000 bh Pasang kunci lemari @Rp. 46,151.00

1.0000 m2 Pasang kaca, tebal 3 mm @Rp. 105,708.00

1.0000 m2 Pasang kaca, tebal 5 mm @Rp. 92,192.00

1.0000 m2 Pasang kaca patri, tebal 5 mm @Rp. 616,191.00

1.0000 m1 Pasang kusen alumunium @Rp. 117,441.00

Page 45: CCO 2013c.xls

RSUD HMAT Kabupaten Kerinci

RENCANA ANGGARAN BIAYA (RAB)OWNER ESTIMATE (OE)

KEGIATAN : PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKITPEKERJAAN : PEMBANGUNAN GEDUNG GENERAL CHECK UPLOKASI : RSU MAYJEN H. A. THALIB - KERINCIVOLUME : 1 (SATU) PAKETTAHUN ANGGARA : 2013

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN 1 Pek. Pekerjaan Pengukuran 1.00 Ls @Rp. 1,000,000.00 Rp. 1,000,000.00

2 Pek. Pemasangan bouwplank 1.00 Ls @Rp. 500,000.00 Rp. 500,000.00

3 Pek. Pemasangan papan nama proyek 1.00 Ls @Rp. 300,000.00 Rp. 300,000.00

4 Pek. Pembongkaran 1.00 Ls @Rp. 2,500,000.00 Rp. 2,500,000.00

Rp. 4,300,000.00

II PEKERJAAN PONDASI 1 Pek. Galian tanah pondasi 35.00 m3 @Rp. 43,037.00 Rp. 1,506,295.00

2 Pek. Urug kembali bekas galian 11.67 m3 @Rp. 14,345.67 Rp. 167,366.11

3 Pek. Pondasi Batu Kali 32.64 m3 @Rp. 715,253.00 Rp. 23,345,857.92

4 Pek. Urugan Pasir (Anstampang) 1.36 m3 @Rp. 241,747.00 Rp. 328,775.92

Rp. 25,348,294.95

III PEKERJAAN STRUKTUR 1 Pek. Sloof beton bertulang 15/20 1.02 m3 @Rp. 4,788,316.00 Rp. 4,884,082.32

2 Pek. Kolom beton bertulang 15/25 1.43 m3 @Rp. 6,416,118.00 Rp. 9,142,968.15

3 Pek. Kolom + Balok Pinggang 12/12 0.67 m3 @Rp. 5,032,175.00 Rp. 3,371,557.25

4 Pek. Ring balok 15/20 1.17 m3 @Rp. 4,788,316.00 Rp. 5,602,329.72

5 Pek. Plat atap teras T = 12 cm 0.30 m3 @Rp. 5,508,073.00 Rp. 1,652,421.90

6 Pek. Plat Overstek T = 12 cm 3.64 m3 @Rp. 895,425.00 Rp. 3,259,347.00

Rp. 27,912,706.34

IV PEKERJAAN LANTAI 1 Pek. Timbunana Tanah Bawah Lantai 14.00 m3 @Rp. 241,747.00 Rp. 3,384,458.00

2 Pek. Urugan Pasir Bawah Lantai 3.60 m3 @Rp. 241,747.00 Rp. 870,289.20

3 Pek. Cor Lantai 1 : 3 : 5 7.20 m3 @Rp. 895,425.00 Rp. 6,447,060.00

4 Pek. Lantai Keramik 40 x 40 44.00 m2 @Rp. 204,248.00 Rp. 8,986,912.00

5 Pek. Lantai Keramik 30 x 30 28.00 m2 @Rp. 169,770.00 Rp. 4,753,560.00

Rp. 24,442,279.20

V PEKERJAAN DINDING DAN PLESTERAN 1 Pek. Pasangan Dinding Bata 1 : 3 106.36 m2 @Rp. 94,834.00 Rp. 10,086,544.24

2 Pek. Plesteran Dinding 1 : 3 212.72 m2 @Rp. 45,977.00 Rp. 9,780,227.44

Rp. 19,866,771.68

VI PEKERJAAN ATAP 1 Pek. Membuat kuda-kuda/ rangka atap baja ringan 84.2000 m2 @Rp. 168,575.00 Rp. 14,194,015.00

2 Pek. Atap Genteng Metal 84.2000 m2 @Rp. 90,915.00 Rp. 7,655,043.00

3 Pek. Perabung Genteng Metal 10.0000 m1 @Rp. 63,318.00 Rp. 633,180.00

4 Pek. Lisplank Papan 2/20 36.8400 m1 @Rp. 33,935.00 Rp. 1,250,165.40

Rp. 23,732,403.40

VII PEKERJAAN PLAFOND 1 Pek. Plafond GRC + Rangka 70.00 m2 @Rp. 123,107.00 Rp. 8,617,490.00

2 Pek. List Plafond GRC 50.00 m1 @Rp. 28,000.00 Rp. 1,400,000.00

Rp. 10,017,490.00

Page 46: CCO 2013c.xls

RSUD HMAT Kabupaten Kerinci

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

VIII PEKERJAAN PAS. DAUN PINTU, JENDELA DAN VENTILASI 1 Pek. Pas. Pintu Panel 2 Pintu Terpasang + Kunci 2.52 m2 @Rp. 1,134,823.00 Rp. 2,859,753.96

2 Pek. Pas. Pintu Panel 1 Pintu Terpasang + Kunci 1.68 m2 @Rp. 1,134,823.00 Rp. 1,906,502.64

3 Pek. Pas. Jendela + Grendel 6.09 m2 @Rp. 842,559.00 Rp. 5,131,184.31

Rp. 9,897,440.91

IX PEKERJAAN PENGECATAN 1 Pek. Cat Tembok 212.72 m2 @Rp. 40,900.00 Rp. 8,700,248.00

2 Pek. Cat Plafond 70.00 m2 @Rp. 40,900.00 Rp. 2,863,000.00

3 Pek. Cat Minyak 20.00 m2 @Rp. 61,803.00 Rp. 1,236,060.00

Rp. 12,799,308.00

X PEKERJAAN DRENASE 1 Pek. Galian 17.2800 m3 @Rp. 43,037.00 Rp. 743,679.36

2 Pek. Pasangan Bata 50.4000 m2 @Rp. 94,834.00 Rp. 4,779,633.60

3 Pek. Plesteran 80.0000 m2 @Rp. 45,977.00 3,678,160.00

4 Pek. Cor Beton 3.2400 m3 @Rp. 895,425.00 Rp. 2,901,177.00

Rp. 12,102,649.96

XI PEKERJAAN INSTALASI LISTRIK 1 Pek. Instalasi Titik Lampu 17.00 Ttk @Rp. 80,000.00 Rp. 1,360,000.00

2 Pek. Stop Kontak 7.00 bh @Rp. 22,724.00 Rp. 159,068.00

3 Pek. Lampu SL 40 Watt 11.00 bh @Rp. 63,911.25 Rp. 703,023.75

4 Pek. Saklar Ganda 2.00 bh @Rp. 28,405.00 Rp. 56,810.00

5 Pek. Saklar Tunggal 1.00 bh @Rp. 22,724.00 Rp. 22,724.00

6 Pek. Zekering / MCB 1.00 Unit @Rp. 2,500,000.00 Rp. 2,500,000.00

Rp. 4,801,625.75

XII PEKERJAAN PENYELESAIAN 1 Pek. Pembuatan Laporan dan As-builtdrawing 1.00 ls @Rp. 2,500,000.00 Rp. 2,500,000.00

2 Pek. Foto dan dokumentasi 1.00 ls @Rp. 300,000.00 Rp. 300,000.00

Rp. 2,800,000.00

(A). JUMLAH HARGA PEKERJAAN Rp. 178,020,970.19 (B). PPN = 10 % x (A) Rp. 17,802,097.02 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 195,823,067.21 (D). DIBULATKAN Rp. 195,823,000.00

(E). TERBILANG Seratus Sembilan Puluh Lima Juta Delapan Ratus Dua Puluh Tiga Rupiah

Sungai Penuh, Februari 2013 Disetujui oleh : Dibuat oleh :

Pejabat Pembuat Komitmen (PPK) CV. IKA PUTRA CONSULTANT

JON EFENDI,Spd FANTONI, ST

NIP.196604071999031009 Arsitek

Page 47: CCO 2013c.xls

RSUD HMAT Kabupaten Kerinci

REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)OWNER ESTIMATE (OE)

KEGIATAN : PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKITPEKERJAAN : PEMBANGUNAN GEDUNG GENERAL CHECK UPLOKASI : RSU MAYJEN H. A. THALIB - KERINCIVOLUME : 1 (SATU) PAKETTAHUN ANGGARA : 2013

NO MACAM PEKERJAAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN Rp. 4,300,000.00

II PEKERJAAN PONDASI Rp. 25,348,294.95

III PEKERJAAN STRUKTUR Rp. 27,912,706.34

IV PEKERJAAN LANTAI Rp. 24,442,279.20

V PEKERJAAN DINDING DAN PLESTERAN Rp. 19,866,771.68

VI PEKERJAAN ATAP Rp. 23,732,403.40

VII PEKERJAAN PLAFOND Rp. 10,017,490.00

VIII PEKERJAAN PAS. DAUN PINTU, JENDELA DAN VENTILASI Rp. 9,897,440.91

IX PEKERJAAN PENGECATAN Rp. 12,799,308.00

X PEKERJAAN DRENASE Rp. 12,102,649.96

XI PEKERJAAN INSTALASI LISTRIK Rp. 4,801,625.75

XII PEKERJAAN PENYELESAIAN Rp. 2,800,000.00

(A). JUMLAH HARGA PEKERJAAN Rp. 178,020,970.19 (B). PPN = 10 % x (A) Rp. 17,802,097.02 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 195,823,067.21 (D). DIBULATKAN Rp. 195,823,000.00

(E). TERBILANG Seratus Sembilan Puluh Lima Juta Delapan Ratus Dua Puluh Tiga Rupiah

Sungai Penuh, Februari 2013Disetujui oleh : Dibuat oleh :

Pejabat Pembuat Komitmen (PPK) CV. IKA PUTRA CONSULTANT

JON EFENDI,Spd FANTONI, ST

NIP.196604071999031009 Arsitek

Page 48: CCO 2013c.xls

DINAS KESEHATAN KOTA SUNGAI PENUH Jalan Jenderal Sudirman No. 24 Sungai Penuh Telp. (0748) 21052 Fax. (0748) 21052

KEGIATAN PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKIT

PEKERJAAN PEMBANGUNAN GEDUNG GENERAL CHECK UP

LOKASI RSU MAYJEN H. A. THALIB - KERINCI

VOLUME 1 (SATU) PAKET

TAHUN ANGGARAN 2012

R A BRENCANA ANGGARAN BIAYA

Konsultan Perencana 1

Page 49: CCO 2013c.xls

CV. BOSCO CONSULTANT 1

Page 50: CCO 2013c.xls

DINAS KESEHATAN KOTA SUNGAI PENUH Jalan Jenderal Sudirman No. 24 Sungai Penuh Telp. (0748) 21052 Fax. (0748) 21052

KEGIATAN PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKIT

PEKERJAAN PEMBANGUNAN GEDUNG GENERAL CHECK UP

LOKASI RSU MAYJEN H. A. THALIB - KERINCI

VOLUME 1 (SATU) PAKET

TAHUN ANGGARAN 2012

GAMBAR KERJA Konsultan Perencana 1 CV. BOSCO CONSULTANT

Page 51: CCO 2013c.xls

DINAS KESEHATAN KOTA SUNGAI PENUH Jalan Jenderal Sudirman No. 24 Sungai Penuh Telp. (0748) 21052 Fax. (0748) 21052

#REF!#REF!

#REF!#REF!

#REF!#REF!

#REF!#REF!

#REF!2012

R A BRENCANA ANGGARAN BIAYA

Konsultan Perencana 2

Page 52: CCO 2013c.xls

CV. NAWRIZZA CIPTA CONSULTANT 2

Page 53: CCO 2013c.xls

Dinas Kesehatan Kota Sungai Penuh 53

ENGINEER ESTIMATE (EE)

KEGIATAN : PENGADAAN, PENINGKATAN DAN PERBAIKAN SARANA & PRASARANA PUSKESMAS DAN JARINGANNYAPEKERJAAN : PENINGKATAN PUSKESMAS MENJADI PUSKESMAS RAWAT INAP PERSALINAN KOTO BARULOKASI : KECAMATAN PESISIR BUKITVOLUME : 1 (SATU) UNITTAHUN ANGGARA : 2012

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN 1 Pek. Pekerjaan Pengukuran 170.0000 m2 @Rp. 9,322.50 Rp. 1,584,825.00

2 Pek. Pemasangan bouwplank 56.0000 m1 @Rp. 77,604.00 Rp. 4,345,824.00

3 Pek. Membersihkan lapangan/ lokasi pekerjaan 170.0000 m2 @Rp. 9,075.00 Rp. 1,542,750.00

4 Pek. Pemasangan papan nama proyek 1.0000 ls @Rp. 250,000.00 Rp. 250,000.00

5 Pek. Pembuatan/ sewa direksi keet 1.0000 ls @Rp. 2,500,000.00 Rp. 2,500,000.00

Rp. 10,223,399.00

I PEKERJAAN PEMBONGKARAN 1 Pek. #REF! 30.0000 #REF! @Rp. #REF! Rp. #REF!

2 Pek. #REF! 0.4320 #REF! @Rp. #REF! Rp. #REF!

3 Pek. #REF! 0.9000 #REF! @Rp. #REF! Rp. #REF!

4 Pek. #REF! 6.6000 #REF! @Rp. #REF! Rp. #REF!

Rp. #REF!

II PEKERJAAN TANAH DAN PASIR 1 Pek. Galian tanah pondasi 100.8000 m3 @Rp. 43,037.00 Rp. 4,338,129.60

2 Pek. Urug kembali bekas galian 33.6000 m3 @Rp. 14,345.67 Rp. 482,014.40

3 Pek. Timbunan tanah didatangkan 21.6000 m3 @Rp. 70,015.00 Rp. 1,512,324.00

4 Pek. Urugan pasir bawah pondasi 3.3600 m3 @Rp. 241,747.00 Rp. 812,269.92

5 Pek. Urugan pasir bawah lantai 5.4000 m3 @Rp. 241,747.00 Rp. 1,305,433.80

Rp. 8,450,171.72

III PEKERJAAN PONDASI DAN BETON 1 Pek. Pasangan pondasi batu kosong 10.0800 m3 @Rp. 403,076.00 Rp. 4,063,006.08

2 Pek. Pasangan pondasi 1 Pc : 4 Ps 74.9775 m3 @Rp. 715,253.00 Rp. 53,627,881.81

3 Pek. Sloof beton bertulang 15/20 2.3070 m3 @Rp. 4,788,316.00 Rp. 11,046,645.01

Page 54: CCO 2013c.xls

Dinas Kesehatan Kota Sungai Penuh 54

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

4 Pek. Kolom beton bertulang 15/15 1.2622 m3 @Rp. 4,963,202.00 Rp. 6,264,801.72

5 Pek. Kolom praktis 11/11 42.9000 m1 @Rp. 68,973.00 Rp. 2,958,941.70

6 Pek. Ring balok praktis 10/15 158.7000 m1 @Rp. 92,826.00 Rp. 14,731,486.20

7 Pek. Dak beton/ pet jendela beton 1.5680 m3 @Rp. 5,508,073.00 Rp. 8,636,658.46

8 Pek. Profil beton 35.4000 m1 @Rp. 150,000.00 Rp. 5,310,000.00

9 Pek. Plat beton meja dapur 0.1250 m3 @Rp. 5,508,073.00 Rp. 688,509.13

Rp. 107,327,930.11

IV PEKERJAAN DINDING DAN PLESTERAN 1 Pek. Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps 245.2250 m2 @Rp. 94,834.00 Rp. 23,255,667.65

2 Pek. Plesteran 1 Pc : 4 Ps, tebal 15 mm 490.4500 m2 @Rp. 41,134.00 Rp. 20,174,170.30

Rp. 43,429,837.95

V PEKERJAAN KUSEN, PINTU, JENDELA DAN VENTILASI 1 Pek. Membuat kusen pintu / jendela kayu Surian 1.1461 m3 @Rp. 6,121,415.00 Rp. 7,015,949.62

2 Pek. Pasang pintu panel kayu surian 15.9600 m2 @Rp. 441,514.00 Rp. 7,046,563.44

3 Pek. Pasang pintu dan jendela kaca kayu surian 14.4000 m2 @Rp. 317,873.00 Rp. 4,577,371.20

4 Pek. Pasang jalusi kusen kayu surian 4.7100 m2 @Rp. 446,933.00 Rp. 2,105,054.43

Rp. 20,744,938.69

VI PEKERJAAN ATAP 1 Pek. Membuat kuda-kuda/ rangka atap baja ringan 194.6420 m3 @Rp. 225,000.00 Rp. 43,794,457.27

4 Pek. Pasang lisplank ukuran (2 x 20) cm, kayu surian 56.0000 m1 @Rp. 33,935.00 Rp. 1,900,360.00

5 Pek. Pasang gentang metal 194.6420 m2 @Rp. 90,915.00 Rp. 17,695,880.37

6 Pek. Pasang bubungan genteng metal 8.0000 m1 @Rp. 63,318.00 Rp. 506,544.00

Rp. 63,897,241.64

VII PEKERJAAN PLAFOND 1 Pek. Pasang rangka langit-langit (60 x 120) m, kayu kelas II 127.9600 m2 @Rp. 74,783.00 Rp. 9,569,232.68

2 Pek. Pasang langit-langit triplek (60 x 120) m, tebal 4 mm 127.9600 m2 @Rp. 48,324.00 Rp. 6,183,539.04

3 Pek. List langit-langit kayu profil 169.1800 m1 @Rp. 21,522.00 Rp. 3,641,091.96

Rp. 19,393,863.68

VIII PEKERJAAN LANTAI 1 Pek. Rabat beton lantai 12.7960 m3 @Rp. 895,425.00 Rp. 11,457,858.30

2 Pek. Pasang keramik 20/20 124.9600 m2 @Rp. 169,770.00 Rp. 21,214,459.20

Page 55: CCO 2013c.xls

Dinas Kesehatan Kota Sungai Penuh 55

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

3 Pek. Pasang plint keramik ukuran 10 x 30 cm 153.8000 m1 @Rp. 10,276.00 Rp. 1,580,448.80

4 Pek. Pasang keramik dinding 20/25 13.6200 m2 @Rp. 179,950.00 Rp. 2,450,919.00

5 Pek. Pasang keramik 30/30 3.0000 m2 @Rp. 186,803.00 Rp. 560,409.00

6 Pek. Pasang list keramik dinding 5/20 10.2000 m1 @Rp. 46,712.00 Rp. 476,462.40

Rp. 37,740,556.70

IX PEKERJAAN KUNCI DAN KACA 1 Pek. Pasang kunci pintu merk SES 8.0000 bh @Rp. 292,264.00 Rp. 2,338,112.00

2 Pek. Pasang engsel pintu 24.0000 bh @Rp. 38,361.00 Rp. 920,664.00

3 Pek. Pasang engsel jendela kupu-kupu 22.0000 bh @Rp. 28,160.00 Rp. 619,520.00

4 Pek. Pasang pegangan pintu / door holder 10.0000 bh @Rp. 92,303.00 Rp. 923,030.00

5 Pek. Pasang kait angin 11.0000 bh @Rp. 45,153.00 Rp. 496,683.00

6 Pek. Pasang kunci selot 22.0000 bh @Rp. 97,421.00 Rp. 2,143,262.00

7 Pek. Pasang kaca, tebal 5 mm 14.4000 m2 @Rp. 92,192.00 Rp. 1,327,564.80

Rp. 8,768,835.80

X PEKERJAAN INSTALASI LISTRIK 1 Pek. Lampu Philips Essential (Hemat Energi) 20 - 40 Watt 16.0000 bh @Rp. 63,911.25 Rp. 1,022,580.00

2 Pek. Lampu Philips Essential (Hemat Energi) 15 - 20 Watt 2.0000 bh @Rp. 49,708.75 Rp. 99,417.50

3 Pek. Stop Kontak Warna (Merek Voltama) 7.0000 bh @Rp. 22,724.00 Rp. 159,068.00

4 Pek. Saklar Seri Putih 3.0000 bh @Rp. 18,525.00 Rp. 55,575.00

5 Pek. Saklar Tunggal Putih 6.0000 bh @Rp. 16,055.00 Rp. 96,330.00

6 Pek. Instalasi listrik 18.0000 ttk @Rp. 75,000.00 Rp. 1,350,000.00

7 Pek. Pemasukan PLN 1.0000 ttk @Rp. 3,500,000.00 Rp. 3,500,000.00

Rp. 6,282,970.50

XI PEKERJAAN SANITASI 1 Pek. Memasang kloset jongkok 2.0000 bh @Rp. 502,139.00 Rp. 1,004,278.00

2 Pek. Memasang bak cuci piring stainless steel 1.0000 bh @Rp. 550,451.00 Rp. 550,451.00

3 Pek. Memasang bak fiberglass 70 x 70 2.0000 bh @Rp. 849,723.00 Rp. 1,699,446.00

4 Pek. Memasang kran diameter 3/4" atau 1/2" 3.0000 bh @Rp. 50,600.00 Rp. 151,800.00

5 Pek. Memasang floor drain 2.0000 bh @Rp. 35,122.00 Rp. 70,244.00

6 Pek. Memasang pipa PVC tipe AW diameter 1/2" 25.0000 m1 @Rp. 18,168.00 Rp. 454,200.00

7 Pek. Memasang pipa PVC tipe AW diameter 3" 8.0000 m1 @Rp. 119,340.00 Rp. 954,720.00

8 Pek. Memasang pipa PVC tipe AW diameter 4" 16.0000 m1 @Rp. 153,067.00 Rp. 2,449,072.00

9 Pek. Memasang septictank 2.0000 ls @Rp. 1,500,000.00 Rp. 3,000,000.00

10 Pek. Pemasukan PDAM 1.0000 ls @Rp. 2,000,000.00 Rp. 2,000,000.00

Page 56: CCO 2013c.xls

Dinas Kesehatan Kota Sungai Penuh 56

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

Rp. 12,334,211.00

XII PEKERJAAN PENGECATAN 1 Pek. Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis ca 490.4500 m2 @Rp. 59,427.00 Rp. 29,145,972.15

2 Pek. Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 la 47.0208 m2 @Rp. 40,900.00 Rp. 1,923,150.72

3 Pek. Pengecatan Plafond 127.9600 m2 @Rp. 59,427.00 Rp. 7,604,278.92

Rp. 38,673,401.79

XIII PEKERJAAN SALURAN AIR HUJAN 1 Pek. Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps 52.8000 m2 @Rp. 94,834.00 Rp. 5,007,235.20

2 Pek. Plesteran 1 Pc : 4 Ps, tebal 15 mm 105.6000 m2 @Rp. 41,134.00 Rp. 4,343,750.40

3 Pek. Rabat beton lantai 2.6400 m3 @Rp. 895,425.00 Rp. 2,363,922.00

Rp. 11,714,907.60

XIV PEKERJAAN PENYELESAIAN 1 Pek. Pembuatan Laporan dan As-builtdrawing 1.0000 ls @Rp. 1,500,000.00 Rp. 1,500,000.00

2 Pek. Foto dan dokumentasi 1.0000 ls @Rp. 1,000,000.00 Rp. 1,000,000.00

3 Pek. Tendon air dan dudukannya 1.0000 ls @Rp. 4,000,000.00 Rp. 4,000,000.00

4 Pek. Besi teralis jendela 14.4000 m2 @Rp. 346,243.00 Rp. 4,985,899.20

Rp. 11,485,899.20

(A). JUMLAH HARGA PEKERJAAN Rp. 400,468,165.38 (B). PPN = 10 % x (A) Rp. 40,046,816.54 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 440,514,981.92 (D). DIBULATKAN Rp. 440,515,000.00

(E). TERBILANG Seratus delapan puluh sembilan juta rupiah

Sungai Penuh, 03 April 2012Disetujui oleh : Dibuat oleh :

Pejabat Pembuat Komitmen (PPK) Konsultan PerencanaDinas Kesehatan Kota Sungai Penuh CV. BOSCO CONSULTANT

WQ

Page 57: CCO 2013c.xls

Dinas Kesehatan Kota Sungai Penuh 57

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

H. JOSRIZAL HELMAN, S.Si, Apt DEDI ASMADI

NIP. 19680629 199905 1 002

Mengetahui : Kepala Dinas Kesehatan Kota Sungai Penuh

H. ZAMRIN, AMK, S.pd

NIP. 140 125 225

Page 58: CCO 2013c.xls

Dinas Kesehatan Kota Sungai Penuh 58

REKAPITULASI ENGINEER ESTIMATE (EE)

KEGIATAN : PENGADAAN, PENINGKATAN DAN PERBAIKAN SARANA & PRASARANA PUSKESMAS DAN JARINGANNYAPEKERJAAN : PENINGKATAN PUSKESMAS MENJADI PUSKESMAS RAWAT INAP PERSALINAN KOTO BARULOKASI : KECAMATAN PESISIR BUKITVOLUME : 1 (SATU) UNITTAHUN ANGGARA : 2012

NO MACAM PEKERJAAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN Rp. 10,223,399.00

II PEKERJAAN PONDASI Rp. 8,450,171.72

III PEKERJAAN STRUKTUR Rp. 107,327,930.11

V PEKERJAAN DINDING DAN PLESTERAN Rp. 43,429,837.95

VIII PEKERJAAN PAS. DAUN PINTU, JENDELA DAN VENTILASI Rp. 20,744,938.69

VI PEKERJAAN ATAP Rp. 63,897,241.64

VII PEKERJAAN PLAFOND Rp. 19,393,863.68

#REF! #REF! Rp. 37,740,556.70

#REF! #REF! Rp. 8,768,835.80

XI PEKERJAAN INSTALASI LISTRIK Rp. 6,282,970.50

#REF! #REF! Rp. 12,334,211.00

IX PEKERJAAN PENGECATAN Rp. 38,673,401.79

XIII PEKERJAAN SALURAN AIR HUJAN Rp. 11,714,907.60

XIV PEKERJAAN PENYELESAIAN Rp. 11,485,899.20

(A). JUMLAH HARGA PEKERJAAN Rp. 400,468,165.38 (B). PPN = 10 % x (A) Rp. 40,046,816.54 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 440,514,981.92 (D). DIBULATKAN Rp. 440,515,000.00

(E). TERBILANG Seratus Sembilan Puluh Lima Juta Delapan Ratus Dua Puluh Tiga Rupiah

Page 59: CCO 2013c.xls

Dinas Kesehatan Kota Sungai Penuh 59

NO MACAM PEKERJAAN JUMLAH HARGA

Sungai Penuh, 03 April 2012Disetujui oleh : Dibuat oleh :

Pejabat Pembuat Komitmen (PPK) Konsultan PerencanaDinas Kesehatan Kota Sungai Penuh -

H. JOSRIZAL HELMAN, S.Si, Apt DEDI ASMADI

NIP. 19680629 199905 1 002

Mengetahui : Kepala Dinas Kesehatan Kota Sungai Penuh

H. ZAMRIN, AMK, S.pd

NIP. 140 125 225

Page 60: CCO 2013c.xls

DINAS KESEHATAN KOTA SUNGAI PENUH Jalan Jenderal Sudirman No. 24 Sungai Penuh Telp. (0748) 21052 Fax. (0748) 21052

KEGIATAN

PEKERJAAN AS MENJADI PUSKESMAS RAWAT INAP PERSALINAN KOTO BARU

LOKASI KECAMATAN PESISIR BUKIT

VOLUME 1 (SATU) UNIT

TAHUN ANGGARAN 2012

R A BRENCANA ANGGARAN BIAYA

Konsultan Perencana 3

PENGADAAN, PENINGKATAN DAN PERBAIKAN SARANA &

PRASARANA PUSKESMAS DAN JARINGANNYA

Page 61: CCO 2013c.xls

CV. NAWRIZZA CIPTA CONSULTANT 3

Page 62: CCO 2013c.xls

DINAS KESEHATAN KOTA SUNGAI PENUH Jalan Jenderal Sudirman No. 24 Sungai Penuh Telp. (0748) 21052 Fax. (0748) 21052

#REF!#REF!

#REF!#REF!

#REF!#REF!

#REF!#REF!

#REF!2012

R A BRENCANA ANGGARAN BIAYA

Konsultan Perencana 3

Page 63: CCO 2013c.xls

CV. NAWRIZZA CIPTA CONSULTANT 3

Page 64: CCO 2013c.xls

DINAS KESEHATAN KOTA SUNGAI PENUH Jalan Jenderal Sudirman No. 24 Sungai Penuh Telp. (0748) 21052 Fax. (0748) 21052

#REF!#REF!

#REF!

#REF!

#REF!#REF!

#REF!#REF!

#REF! 2012

R A BRENCANA ANGGARAN BIAYA

Konsultan Perencana 3

Page 65: CCO 2013c.xls

CV. BOSCO CONSULTANT 3

Page 66: CCO 2013c.xls

DINAS KESEHATAN KOTA SUNGAI PENUH Jalan Jenderal Sudirman No. 24 Sungai Penuh Telp. (0748) 21052 Fax. (0748) 21052

KEGIATAN PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKIT

PEKERJAAN #REF!

LOKASI #REF!

VOLUME 1 (SATU) PAKET

TAHUN ANGGARAN 2012

GAMBAR KERJA Konsultan Perencana 2 CV. BOSCO CONSULTANT

Page 67: CCO 2013c.xls

DINAS KESEHATAN KOTA SUNGAI PENUH Jalan Jenderal Sudirman No. 24 Sungai Penuh Telp. (0748) 21052 Fax. (0748) 21052

#REF!#REF!

#REF!

#REF!

#REF!#REF!

#REF!#REF!

#REF!2012

R A BRENCANA ANGGARAN BIAYA

Page 68: CCO 2013c.xls

Konsultan Perencana 4 CV. BOSCO CONSULTANT

Page 69: CCO 2013c.xls

DINAS KESEHATAN KOTA SUNGAI PENUH Jalan Jenderal Sudirman No. 24 Sungai Penuh Telp. (0748) 21052 Fax. (0748) 21052

#REF!#REF!

#REF!

#REF!

#REF!#REF!

#REF!#REF!

#REF!2012

### Konsultan Perencana 4

Page 70: CCO 2013c.xls

CV. BOSCO CONSULTANT 4

Page 71: CCO 2013c.xls

RSUD MAYJEN H. A. THA KABUPATEN KERINCI

KEGIATAN PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKIT

PEKERJAAN

PEMBANGUNAN GEDUNG GENERAL CHECK UP

LOKASI RSU MAYJEN H. A. THALIB - KERINCI

VOLUME 1 (SATU) PAKET

TAHUN ANGGARAN 2013

OEOWNER ESTIMATE

Page 72: CCO 2013c.xls

RSUD HMAT Kabupaten Kerinci

RENCANA ANGGARAN BIAYA (RAB)OWNER ESTIMATE (OE)

KEGIATAN : PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKITPEKERJAAN : PEMASANGAN CONBLOCK PARKIR DAN PENATAAN TAMAN RAWAT JALAN RSULOKASI : RSU MAYJEN H. A. THALIB - KERINCIVOLUME : 1 (SATU) PAKETTAHUN ANGGARA : 2013

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PAGAR 1 Pek. Pengukuran 1.00 ls @Rp. 1,000,000.00 Rp. 1,000,000.00

2 Pek. Galian pondasi pagar 1.80 m3 @Rp. 52,717.00 Rp. 94,890.60

3 Pek. Pas. Pondasi pagar 0.54 m3 @Rp. 715,253.00 Rp. 386,236.62

4 Pek. Pas. Pagar besi 54.56 m2 @Rp. 346,243.00 Rp. 18,891,018.08

Rp. 20,372,145.30

II PEKERJAAN AIR MANCUR 1 Pek. Pembongkaran 1.00 ls @Rp. 2,626,000.00 Rp. 2,626,000.00

2 Pek. Timbunan 1.50 m3 @Rp. 70,015.00 Rp. 105,022.50

3 Pek. Cor lantai kolam 1.50 m3 @Rp. 895,425.00 Rp. 1,343,137.50

4 Pek. Pas. Dinding kolam 81.12 m2 @Rp. 195,961.00 Rp. 15,896,356.32

5 Pek. Batu alam area kolam 12.56 m3 @Rp. 253,298.00 Rp. 3,181,422.88

6 Pek. Batu alam dinding luar 43.20 m2 @Rp. 253,298.00 Rp. 10,942,473.60

7 Pek. Pas. Besi grill 56.52 m1 @Rp. 78,113.75 Rp. 4,414,989.15

8 Pek. Pas. Koral 16.95 m2 @Rp. 162,585.00 Rp. 2,755,815.75

9 Pek. Tiang hias kolam / besi plat bolong 8.00 ls @Rp. 1,000,000.00 Rp. 8,000,000.00

10 Pek. Besi plat kolam 3.00 ls @Rp. 750,000.00 Rp. 2,250,000.00

Rp. 51,515,217.70

III PEKERJAAN PAVING BLOCK + TEMPAT DUDUK 1 Pek. Beton pembatas paving block baru 2.51 m3 @Rp. 895,425.00 Rp. 2,247,516.75

2 Pek. Timbunan tanah T = 20 cm 68.10 m3 @Rp. 70,015.00 Rp. 4,768,021.50

3 Pek. Urugan pasir T = 10 cm 34.05 m3 @Rp. 241,747.00 Rp. 8,231,485.35

4 Pek. Paving block 340.50 m2 @Rp. 29,236.00 Rp. 9,954,858.00

5 Pek. Cor beton area tempat duduk 2.60 m3 @Rp. 1,023,775.00 Rp. 2,661,815.00

6 Pek. Acian kasar area tempat duduk 2.60 m3 @Rp. 45,977.00 Rp. 119,540.20

7 Pek. Tempat duduk 16.00 m2 @Rp. 1,023,775.00 Rp. 16,380,400.00

8 Pek. Besi pipa 60.00 m1 @Rp. 346,243.00 Rp. 20,774,580.00

9 Pek. Tiang lampu hias (cor beton) 1.60 m3 @Rp. 4,963,202.00 Rp. 7,941,123.20

10 Pek. Batu alam andesit (untuk tiang lampu hias) 1.60 m2 @Rp. 253,298.00 Rp. 405,276.80

Rp. 73,484,616.80

IV PEKERJAAN INSTALASI 1 Pek. Pipa 2 inc 5.00 m1 @Rp. 60,522.00 Rp. 302,610.00

2 Pek. Pipa 1 inc 25.00 m1 @Rp. 29,359.00 Rp. 733,975.00

3 Pek. Instalasi listrik 50.00 m1 @Rp. 80,000.00 Rp. 4,000,000.00

4 Pek. Titik lampu 27.00 ttk @Rp. 80,000.00 Rp. 2,160,000.00

5 Pek. Lampu area air mancur 22.00 bh @Rp. 233,000.00 Rp. 5,126,000.00

6 Pek. Pompa air 1.00 bh @Rp. 1,200,000.00 Rp. 1,200,000.00

7 Pek. Lampu hias 5.00 bh @Rp. 500,000.00 Rp. 2,500,000.00

Rp. 16,022,585.00

Page 73: CCO 2013c.xls

RSUD HMAT Kabupaten Kerinci

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

V PEKERJAAN PENYELESAIAN 1 Pek. Pembuatan Laporan dan As-builtdrawing 1.00 ls @Rp. 2,000,000.00 Rp. 2,000,000.00

2 Pek. Foto dan dokumentasi 1.00 ls @Rp. 300,000.00 Rp. 300,000.00

Rp. 2,300,000.00

(A). JUMLAH HARGA PEKERJAAN Rp. 163,694,564.80 (B). PPN = 10 % x (A) Rp. 16,369,456.48 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 180,064,021.28 (D). DIBULATKAN Rp. 180,064,000.00

(E). TERBILANG Seratus Delapan Puluh Empat Juta Dua Puluh Ribu Rupiah

Sungai Penuh, Februari 2013 Disetujui oleh : Dibuat oleh :

Pejabat Pembuat Komitmen (PPK) CV. IKA PUTRA CONSULTANT

JON EFENDI,Spd FANTONI, ST

NIP.196604071999031009 Arsitek

Page 74: CCO 2013c.xls

RSUD HMAT Kabupaten Kerinci

REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)OWNER ESTIMATE (OE)

KEGIATAN : PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKITPEKERJAAN : PEMASANGAN CONBLOCK PARKIR DAN PENATAAN TAMAN RAWAT JALAN RSULOKASI : RSU MAYJEN H. A. THALIB - KERINCIVOLUME : 1 (SATU) PAKETTAHUN ANGGARA : 2013

NO MACAM PEKERJAAN JUMLAH HARGA

I PEKERJAAN PAGAR Rp. 20,372,145.30

II PEKERJAAN AIR MANCUR Rp. 51,515,217.70

III PEKERJAAN PAVING BLOCK + TEMPAT DUDUK Rp. 73,484,616.80

IV PEKERJAAN INSTALASI Rp. 16,022,585.00

V PEKERJAAN PENYELESAIAN Rp. 2,300,000.00

(A). JUMLAH HARGA PEKERJAAN Rp. 163,694,564.80 (B). PPN = 10 % x (A) Rp. 16,369,456.48 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 180,064,021.28 (D). DIBULATKAN Rp. 180,064,000.00

(E). TERBILANG Seratus Delapan Puluh Empat Juta Dua Puluh Ribu Rupiah

Sungai Penuh, Februari 2013Disetujui oleh : Dibuat oleh :

Pejabat Pembuat Komitmen (PPK) CV. IKA PUTRA CONSULTANT

JON EFENDI,Spd FANTONI, ST

NIP.196604071999031009 Arsitek

Page 75: CCO 2013c.xls

RSUD MAYJEN H. A. THA KABUPATEN KERINCI

KEGIATAN PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKIT

PEKERJAAN

LOKASI RSU MAYJEN H. A. THALIB - KERINCI

VOLUME 1 (SATU) PAKET

TAHUN ANGGARAN 2013

OEOWNER ESTIMATE

PEMASANGAN CONBLOCK PARKIR DAN PENATAAN TAMAN RAWAT JALAN RSU

Page 76: CCO 2013c.xls

RSUD HMAT Kabupaten Kerinci

RENCANA ANGGARAN BIAYA (RAB)OWNER ESTIMATE (OE)

KEGIATAN : PENGADAAN, PENINGKATAN DAN PERBAIKAN SARANA & PRASARANA DAN JARINGANNYAPEKERJAAN : REHABILITASI RUANG OKALOKASI : RSU MAYJEN H. A. THALIB - KERINCIVOLUME : 1 (SATU) UNITTAHUN ANGGARA : 2013

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN 1 Pek. Pengukuran 1.00 Ls @Rp. 1,000,000.00 Rp. 1,000,000.00

2 Pek. Pasang bouwpalnk 25.00 m1 @Rp. 77,604.00 Rp. 1,940,100.00

3 Pek. Pemasangan papan nama proyek 1.00 Ls @Rp. 300,000.00 Rp. 300,000.00

4 Pek. Pembongkaran dinding 1.00 Ls @Rp. 750,000.00 Rp. 750,000.00

5 Pek. Rehab garbarata 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00

Rp. 5,990,100.00

A PEKERJAAN RUANG OKA I PEKERJAAN PONDASI 1 Pek. Galian tanah pondasi 12.00 m3 @Rp. 43,037.00 Rp. 516,444.00

2 Pek. Urug kembali bekas galian 4.00 m3 @Rp. 14,345.67 Rp. 57,382.67

3 Pek. Pondasi Batu Kali 9.00 m3 @Rp. 715,253.00 Rp. 6,437,277.00

4 Pek. Urugan Pasir 6.40 m3 @Rp. 241,747.00 Rp. 1,547,180.80

Rp. 8,558,284.47

II PEKERJAAN STRUKTUR 1 Pek. Sloof beton bertulang 15/20 0.75 m3 @Rp. 4,788,316.00 Rp. 3,591,237.00

2 Pek. Kolom beton bertulang 15/25 2.10 m3 @Rp. 5,032,175.00 Rp. 10,567,567.50

3 Pek. Kolom + Balok Pinggang 12/12 0.20 m3 @Rp. 5,032,175.00 Rp. 1,006,435.00

4 Pek. Ring balok 15/20 0.75 m3 @Rp. 4,788,316.00 Rp. 3,591,237.00

5 Pek. Plat atap teras T = 12 cm 0.36 m3 @Rp. 5,508,073.00 Rp. 1,982,906.28

6 Pek. Plat Overstek T = 12 cm 0.85 m3 @Rp. 5,508,073.00 Rp. 4,681,862.05

7 Pek. Plat atap samping 0.60 m3 @Rp. 5,508,073.00 Rp. 3,304,843.80

Rp. 28,726,088.63

III PEKERJAAN LANTAI 1 Pek. Timbunana Tanah Bawah Lantai 19.55 m3 @Rp. 70,015.00 Rp. 1,368,793.25

2 Pek. Urugan Pasir Bawah Lantai 48.87 m3 @Rp. 241,747.00 Rp. 11,814,175.89

3 Pek. Cor Lantai 1 : 3 : 5 9.77 m3 @Rp. 895,425.00 Rp. 8,748,302.25

4 Pek. Lantai Keramik 40 x 40 32.00 m2 @Rp. 204,248.00 Rp. 6,535,936.00

5 Pek. Lantai Keramik KM 30 x 30 7.50 m2 @Rp. 186,803.00 Rp. 1,401,022.50

6 Pek. Lantai Keramik Selasar 30 x 30 15.00 m2 @Rp. 186,803.00 Rp. 2,802,045.00

7 Pek. Lantai Keramik Teras 30 x 30 3.00 m2 @Rp. 186,803.00 Rp. 560,409.00

8 Pek. Dinding kamar mandi 30 x 30 14.40 m2 @Rp. 186,803.00 Rp. 2,689,963.20

Rp. 35,920,647.09

IV PEKERJAAN DINDING DAN PLESTERAN 1 Pek. Pasangan Dinding Bata 1 : 3 38.20 m2 @Rp. 94,834.00 Rp. 3,622,658.80

2 Pek. Plesteran Dinding 1 : 3 76.40 m2 @Rp. 45,977.00 Rp. 3,512,642.80

3 Pek. Batu alam diatas bak air 24.00 m2 @Rp. 253,298.00 Rp. 6,079,152.00

Rp. 13,214,453.60

V PEKERJAAN ATAP 1 Pek. Membuat kuda-kuda/ rangka atap baja ringan 42.0000 m2 @Rp. 168,575.00 Rp. 7,080,150.00

2 Pek. Atap seng multi colour + bubungan 42.0000 m2 @Rp. 182,403.00 Rp. 7,660,926.00

3 Pek. Lisplank Papan 2/20 10.0000 m1 @Rp. 33,935.00 Rp. 339,350.00

Rp. 15,080,426.00

VI PEKERJAAN PLAFOND 1 Pek. Plafond GRC + Rangka 39.50 m2 @Rp. 123,107.00 Rp. 4,862,726.50

2 Pek. List Plafond 30.00 m1 @Rp. 28,000.00 Rp. 840,000.00

Rp. 5,702,726.50

Page 77: CCO 2013c.xls

RSUD HMAT Kabupaten Kerinci

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

VII PEKERJAAN PAS. DAUN PINTU, JENDELA DAN VENTILASI 1 Pek. Pas. Pintu Panel 2 Pintu Terpasang + Kunci 1.00 Unit @Rp. 1,134,823.00 Rp. 1,134,823.00

2 Pek. Pas. Pintu fiber KM/WC Terpasang + Kunci 2.00 Unit @Rp. 436,116.00 Rp. 872,232.00

3 Pek. Pas. Jendela terpasang + Grendel + hak angin + handle 11.00 m2 @Rp. 842,559.00 Rp. 9,268,149.00

4 Pek. Pas. Kaca ventilasi terpasang 2.00 Unit @Rp. 92,192.00 Rp. 184,384.00

5 Pek. Kisi - kisi besi 1.00 Unit @Rp. 2,500,000.00 Rp. 2,500,000.00

Rp. 13,959,588.00

VIII PEKERJAAN PENGECATAN 1 Pek. Cat Tembok 76.40 m2 @Rp. 40,900.00 Rp. 3,124,760.00

2 Pek. Cat Minyak 15.00 m2 @Rp. 61,803.00 Rp. 927,045.00

Rp. 4,051,805.00

IX PEKERJAAN SANITASI 1 Pek. Klosed jongkok 2.00 Unit @Rp. 502,139.00 Rp. 1,004,278.00

2 Pek. Bak fiber 2.00 Unit @Rp. 849,723.00 Rp. 1,699,446.00

3 Pek. Floor drain 2.00 bh @Rp. 24,854.38 Rp. 49,708.76

4 Pek. Kran air 2.00 bh @Rp. 38,750.00 Rp. 77,500.00

5 Pek. Memasang pipa PVC tipe AW diameter 1/2" 25.00 m1 @Rp. 18,168.00 Rp. 454,200.00

6 Pek. Memasang pipa PVC tipe AW diameter 4" 15.00 m1 @Rp. 153,067.00 Rp. 2,296,005.00

7 Pek. Septick tank + resapan 1.00 unit @Rp. 2,000,000.00 Rp. 2,000,000.00

Rp. 7,581,137.76

X PEKERJAAN INSTALASI LISTRIK 1 Pek. Instalasi Titik Lampu 15.00 Ttk @Rp. 80,000.00 Rp. 1,200,000.00

2 Pek. Stop Kontak 3.00 bh @Rp. 22,724.00 Rp. 68,172.00

3 Pek. Sarang lampu downlight 6.00 bh @Rp. 50,000.00 Rp. 300,000.00

4 Pek. Lampu SL 40 Watt 11.00 bh @Rp. 63,911.25 Rp. 703,023.75

5 Pek. Saklar Ganda 4.00 bh @Rp. 28,405.00 Rp. 113,620.00

6 Pek. Saklar Tunggal 6.00 bh @Rp. 22,724.00 Rp. 136,344.00

7 Pek. Lampu pijar 2.00 bh @Rp. 3,705.00 Rp. 7,410.00

Rp. 2,528,569.75

B PEKERJAAN GUDANG 1 Pek. Pasangan Dinding 1 : 4 30.90 m2 @Rp. 94,834.00 Rp. 2,930,370.60

2 Pek. Plesteran 1 : 4 61.80 m2 @Rp. 45,977.00 Rp. 2,841,378.60

3 Pek. Plafond Triplek + rangka + list 9.00 m2 @Rp. 144,629.00 Rp. 1,301,661.00

4 Pek. Pondasi batu kali 0.225 m3 @Rp. 715,253.00 Rp. 160,931.93

5 Pek. Kusen + Pintu Kayu 1.000 bh @Rp. 1,000,000.00 Rp. 1,000,000.00

Rp. 8,234,342.13

C PEKERJAAN PENYELESAIAN 1 Pek. Pembuatan Laporan dan As-builtdrawing 1.00 ls @Rp. 2,000,000.00 Rp. 2,000,000.00

2 Pek. Foto dan dokumentasi 1.00 ls @Rp. 500,000.00 Rp. 500,000.00

Rp. 2,500,000.00

(A). JUMLAH HARGA PEKERJAAN Rp. 152,048,168.92 (B). PPN = 10 % x (A) Rp. 15,204,816.89 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 167,252,985.81 (D). DIBULATKAN Rp. 167,253,000.00

(E). TERBILANG Seratus Enam Puluh Delapan Juta Sembilan Ratus Delapan Ribu Rupiah

Sungai Penuh, Februari 2013 Disetujui oleh : Dibuat oleh :

CV. IKA PUTRA CONSULTANT Pejabat Pembuat Komitmen (PPK)

JON EFENDI,Spd FANTONI, ST

NIP.196604071999031009 Arsitek

Page 78: CCO 2013c.xls

RSUD HMAT Kabupaten Kerinci

REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)OWNER ESTIMATE (OE)

KEGIATAN : PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKITPEKERJAAN : REHABILITASI RUANG OKALOKASI : RSU MAYJEN H. A. THALIB - KERINCIVOLUME : 1 (SATU) UNITTAHUN ANGGARA : 2013

NO MACAM PEKERJAAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN Rp. 5,990,100.00

A PEKERJAAN RUANG OKA I PEKERJAAN PONDASI Rp. 8,558,284.47

II PEKERJAAN STRUKTUR Rp. 28,726,088.63

III PEKERJAAN LANTAI Rp. 35,920,647.09

IV PEKERJAAN DINDING DAN PLESTERAN Rp. 13,214,453.60

V PEKERJAAN ATAP Rp. 15,080,426.00

VI PEKERJAAN PLAFOND Rp. 5,702,726.50

VII PEKERJAAN PAS. DAUN PINTU, JENDELA DAN VENTILASI Rp. 13,959,588.00

VIII PEKERJAAN PENGECATAN Rp. 4,051,805.00

IX PEKERJAAN SANITASI Rp. 7,581,137.76

X PEKERJAAN INSTALASI LISTRIK Rp. 2,528,569.75

B PEKERJAAN GUDANG Rp. 8,234,342.13

C PEKERJAAN PENYELESAIAN Rp. 2,500,000.00

(A). JUMLAH HARGA PEKERJAAN Rp. 152,048,168.92 (B). PPN = 10 % x (A) Rp. 15,204,816.89 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 167,252,985.81 (D). DIBULATKAN Rp. 167,253,000.00

(E). TERBILANG Seratus Enam Puluh Delapan Juta Sembilan Ratus Delapan Ribu Rupiah

Sungai Penuh, Februari 2013Disetujui oleh : Dibuat oleh :

### CV. IKA PUTRA CONSULTANTDinas Kesehatan Kota Sungai Penuh

JON EFENDI,Spd FANTONI, ST

NIP.196604071999031009 Arsitek

Page 79: CCO 2013c.xls

RSUD MAYJEN H. A. THA KABUPATEN KERINCI

KEGIATAN PENDUKUNG PENINGKATAN PELAYANAN RUMAH SAKIT

PEKERJAAN

REHABILITASI RUANG OKA

LOKASI RSU MAYJEN H. A. THALIB - KERINCI

VOLUME 1 (SATU) PAKET

TAHUN ANGGARAN 2013

EEENGINEER ESTIMATE

Page 80: CCO 2013c.xls

RENCANA ANGGARAN BIAYA (RAB) CONTRACT CHANGE ORDER (CCO)

KEGIATAN : PENIGKATAN SARANA DAN PRASARANA RUMAH SAKIT (DAK)PEKERJAAN : PEMBANGUNAN GEDUNG KELAS III RSUD MHATLOKASI : RSUD MAYJEN H. A. THALIB - KERINCIVOLUME : 1 (SATU) PaketTAHUN ANGGARA : 2013

KONTRAK REALISASI PEKERJAAN LAPANGAN VOLUME PEKERJAAN TAMBAH VOLUME PEKERJAAN KURANG

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA

A PEKERJAAN PERSIAPAN 1 Pek. Papan Nama Proyek 1.00 Ls @Rp. 500,000.00 Rp. 500,000.00 1.00 Ls @Rp. 500,000.00 Rp. 500,000.00 Rp. -

2 Pek. Pas. Bowplank dan Pengukuran 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00 Rp. -

3 Pek. Sewa Barak Kerja 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00 Rp. -

4 Pek. IMB dan HO 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00 Rp. -

5 Pek. Dokumentasi dan Pelaporan 1.00 Ls @Rp. 4,000,000.00 Rp. 4,000,000.00 1.00 Ls @Rp. 4,000,000.00 Rp. 4,000,000.00 Rp. -

6 Pek. Pematangan lahan + pengangkutan tanah 300.00 m3 @Rp. 81,405.00 Rp. 24,421,500.00 300.00 m3 @Rp. 81,405.00 Rp. 24,421,500.00 Rp. -

Rp. 34,921,500.00 Rp. 34,921,500.00 Rp. -

B PEKERJAAN LANTAI I

I PEKERJAAN TANAH DAN PASIR 1 Pek. Galian tanah pondasi 46.80 m3 @Rp. 62,540.00 Rp. 2,926,872.00 113.18 m3 @Rp. 62,540.00 Rp. 7,078,277.20 66.38 m3 @Rp. 62,540.00 Rp. 4,151,405.20 Rp. -

2 Pek. Urug kembali bekas galian 15.30 m3 @Rp. 63,387.00 Rp. 969,821.10 51.82 m3 @Rp. 63,387.00 Rp. 3,284,714.34 36.52 m3 @Rp. 63,387.00 Rp. 2,314,893.24 Rp. -

3 Pek. Urugan pasir bawah lantai dan pondasi 15.00 m3 @Rp. 213,607.00 Rp. 3,204,105.00 14.90 m3 @Rp. 213,607.00 Rp. 3,182,744.30 Rp. - 0.10 m3 @Rp. 213,607.00 Rp. 21,360.70

4 Pek. Urugan tanah lantai dipadatkan 120.00 m3 @Rp. 144,157.00 Rp. 17,298,840.00 104.38 m3 @Rp. 144,157.00 Rp. 15,047,107.66 Rp. - 15.62 m3 @Rp. 144,157.00 Rp. 2,251,732.34

Rp. 24,399,638.10 Rp. 28,592,843.50 Rp. 6,466,298.44 Rp. 2,273,093.04

II PEKERJAAN PASANGAN DAN BETON 1 Pek. Pasangan pondasi 1 Pc : 4 Ps 88.60 m3 @Rp. 685,240.00 Rp. 60,710,979.18 88.60 m3 @Rp. 685,240.00 Rp. 60,710,979.18 - m3 @Rp. 685,240.00 Rp. - Rp. -

2 Pek. Beton bertulang Pondasi 13.66 m3 @Rp. 3,423,801.00 Rp. 46,769,121.66 15.01 m3 @Rp. 3,423,801.00 Rp. 51,391,253.01 1.35 m3 @Rp. 3,423,801.00 Rp. 4,622,131.35 Rp. -

3 Pek. Beton bertulang sloof 20/35 14.78 m3 @Rp. 4,257,578.00 Rp. 62,927,002.84 10.53 m3 @Rp. 4,257,578.00 Rp. 44,832,296.34 Rp. - 4.25 m3 @Rp. 4,257,578.00 Rp. 18,094,706.50

4 Pek. Beton bertulang kolom 30/30 7.72 m3 @Rp. 5,698,473.00 Rp. 43,992,211.56 8.10 m3 @Rp. 5,698,473.00 Rp. 46,157,631.30 0.38 m3 @Rp. 5,698,473.00 Rp. 2,165,419.74 Rp. -

5 Pek. Beton bertulang kolom praktis 12/12 0.80 m3 @Rp. 5,279,610.00 Rp. 4,223,688.00 0.60 m3 @Rp. 5,279,610.00 Rp. 3,167,766.00 Rp. - 0.20 m3 @Rp. 5,279,610.00 Rp. 1,055,922.00

6 Pek. Beton bertulang kolom teras 1.23 m1 @Rp. 4,427,641.00 Rp. 5,445,998.43 2.07 m1 @Rp. 4,427,641.00 Rp. 9,165,216.87 0.84 m1 @Rp. 4,427,641.00 Rp. 3,719,218.44 Rp. -

7 Pek. Beton bertulang Kanopi dan plat teras 1.90 m3 @Rp. 4,879,334.00 Rp. 9,270,734.60 4.93 m3 @Rp. 4,879,334.00 Rp. 24,055,116.62 3.03 m3 @Rp. 4,879,334.00 Rp. 14,784,382.02 Rp. -

8 Pek. Pas. Dinding bata 1 : 4 330.37 m3 @Rp. 86,013.00 Rp. 28,416,114.81 330.37 m3 @Rp. 86,013.00 Rp. 28,416,114.81 Rp. - Rp. -

9 Pek. Plesteran + acian 1 : 4 660.74 m3 @Rp. 41,195.00 Rp. 27,219,184.30 660.74 m3 @Rp. 41,195.00 Rp. 27,219,184.30 Rp. - Rp. -

10 Pek. Batu alam andesit 109.60 m2 @Rp. 225,080.00 Rp. 24,668,768.00 109.60 m2 @Rp. 225,080.00 Rp. 24,668,768.00 Rp. - Rp. -

11 Pek. acian lantai (langit-langit) m2 @Rp. Rp. - 175.20 m2 @Rp. 26,000.00 Rp. 4,555,200.00 175.20 m2 @Rp. 26,000.00 Rp. 4,555,200.00 Rp. -

313,643,803.38 324,339,526.43 29,846,351.55 19,150,628.50

III PEKERJAAN LANTAI DAN KERAMIK 1 Pek. Cor lantai dan selasar 32.78 m2 @Rp. 797,699.00 Rp. 26,148,573.22 29.82 m2 @Rp. 797,699.00 Rp. 23,787,384.18 Rp. - 2.96 m2 @Rp. 797,699.00 Rp. 2,361,189.04

2 Pek. Pas. Lantai keramik KM/WC 30x30 16.80 m2 @Rp. 171,546.00 Rp. 2,881,972.80 18.00 m2 @Rp. 171,546.00 Rp. 3,087,828.00 1.20 m2 @Rp. 171,546.00 Rp. 205,855.20 Rp. -

3 Pek. Pas. Lantai keramik 40x40 ( BERMOTIF ) 228.00 m2 @Rp. 186,805.00 Rp. 42,591,540.00 223.75 m2 @Rp. 186,805.00 Rp. 41,797,618.75 Rp. - 4.25 m2 @Rp. 186,805.00 Rp. 793,921.25

4 Pek. Pas. Teras keramik 40x40 (BERMOTIF ) 49.56 m2 @Rp. 186,805.00 Rp. 9,258,055.80 48.50 m2 @Rp. 186,805.00 Rp. 9,060,042.50 Rp. - 1.06 m2 @Rp. 186,805.00 Rp. 198,013.30

5 Pek. Pas. Dinding keramik KM/WC 30x30 T=1.2 m 8.00 m2 @Rp. 171,546.00 Rp. 1,372,368.00 65.16 m2 @Rp. 171,546.00 Rp. 11,177,937.36 57.16 m2 @Rp. 171,546.00 Rp. 9,805,569.36 Rp. -

Rp. 82,252,509.82 Rp. 88,910,810.79 Rp. 10,011,424.56 Rp. 3,353,123.59

IV PEKERJAAN KUSEN PINTU DAN JENDELA 1 Pek. Kusen pintu dan jendela 2.39 m3 @Rp. 5,553,393.00 Rp. 13,261,502.48 1.87 m3 @Rp. 5,553,393.00 Rp. 10,384,844.91 Rp. - 0.52 m3 @Rp. 5,553,393.00 Rp. 2,876,657.57

2 Pek. Pintu Kaca - 2.00 unit @Rp. 11,750,000.00 Rp. 23,500,000.00 2.00 unit @Rp. 11,750,000.00 Rp. 23,500,000.00

3 Pek. Pas. Pintu Panel 2 Pintu Terpasang + Kunci 1.00 unit @Rp. 1,103,806.00 Rp. 1,103,806.00 - - @Rp. - Rp. - Rp. - 1.00 unit @Rp. 1,103,806.00 Rp. 1,103,806.00

4 Pek. Daun pintu panil 7.00 Bh @Rp. 838,742.00 Rp. 5,871,194.00 17.00 Bh @Rp. 838,742.00 Rp. 14,258,614.00 10.00 Bh @Rp. 838,742.00 Rp. 8,387,420.00 Rp. -

5 Pek. Daun jendela kaca 5 mm 18.00 Bh @Rp. 385,287.00 Rp. 6,935,166.00 23.00 Bh @Rp. 385,287.00 Rp. 8,861,601.00 5.00 Bh @Rp. 385,287.00 Rp. 1,926,435.00 Rp. -

6 Pek. Jendela Aluminium Area Lobby 47.20 M2 @Rp. 842,559.00 Rp. 39,768,784.80 46.26 M2 @Rp. 842,559.00 Rp. 38,976,779.34 Rp. - 0.94 M2 @Rp. 842,559.00 Rp. 792,005.46

7 Pek. Ventilasi 6.00 Bh @Rp. 415,774.00 Rp. 2,494,644.00 6.00 Bh @Rp. 415,774.00 Rp. 2,494,644.00 Rp. - Rp. -

8 Pek. Kaca Mati 52.00 Bh @Rp. 86,418.10 Rp. 4,493,741.10 45.00 Bh @Rp. 86,418.10 Rp. 3,888,814.50 Rp. - 7.00 Bh @Rp. 86,418.10 Rp. 604,926.70

Rp. 73,928,838.38 Rp. 102,365,297.75 Rp. 33,813,855.00 Rp. 5,377,395.73

Page 81: CCO 2013c.xls

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA

Page 82: CCO 2013c.xls

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA

V PEKERJAAN GANTUNGAN DAN KUNCI 1 Pek. Kunci pintu double slaag 7.00 Unit @Rp. 261,247.00 Rp. 1,828,729.00 13.00 Unit @Rp. 261,247.00 Rp. 3,396,211.00 6.00 Unit @Rp. 261,247.00 Rp. 1,567,482.00 Rp. -

2 Pek. Engsel pintu 21.00 Unit @Rp. 34,956.00 Rp. 734,076.00 39.00 Unit @Rp. 34,956.00 Rp. 1,363,284.00 18.00 Unit @Rp. 34,956.00 Rp. 629,208.00 Rp. -

3 Pek. Grendel pintu 14.00 Unit @Rp. 25,000.00 Rp. 350,000.00 26.00 Unit @Rp. 25,000.00 Rp. 650,000.00 12.00 Unit @Rp. 25,000.00 Rp. 300,000.00 Rp. -

4 Pek. Engsel jendela 36.00 Unit @Rp. 25,606.00 Rp. 921,816.00 46.00 Unit @Rp. 25,606.00 Rp. 1,177,876.00 10.00 Unit @Rp. 25,606.00 Rp. 256,060.00 Rp. -

5 Pek. Grendel jendela 36.00 Unit @Rp. 25,000.00 Rp. 900,000.00 46.00 Unit @Rp. 25,000.00 Rp. 1,150,000.00 10.00 Unit @Rp. 25,000.00 Rp. 250,000.00 Rp. -

6 Pek. Hak angin 36.00 Unit @Rp. 40,897.00 Rp. 1,472,292.00 46.00 Unit @Rp. 40,897.00 Rp. 1,881,262.00 10.00 Unit @Rp. 40,897.00 Rp. 408,970.00 Rp. -

7 Pek. Tarikan jendela 18.00 Unit @Rp. 25,606.00 Rp. 460,908.00 23.00 Unit @Rp. 25,606.00 Rp. 588,938.00 5.00 Unit @Rp. 25,606.00 Rp. 128,030.00 Rp. -

Rp. 6,667,821.00 Rp. 10,207,571.00 Rp. 3,539,750.00 Rp. -

XI PEKERJAAN PENGECATAN 1 Pek. Cat dinding 660.74 m2 @Rp. 38,965.00 Rp. 25,745,734.10 660.74 m2 @Rp. 38,965.00 Rp. 25,745,734.10 Rp. - Rp. -

2 Pek. Cat kusen pintu dan jendela 100.00 m2 @Rp. 57,068.00 Rp. 5,706,800.00 102.44 m2 @Rp. 57,068.00 Rp. 5,846,045.92 2.44 m2 @Rp. 57,068.00 Rp. 139,245.92 Rp. -

3 Pek. Cat langit-langit Rp. - 175.20 m2 @Rp. 38,965.00 Rp. 6,826,668.00 175.20 m2 @Rp. 38,965.00 Rp. 6,826,668.00 Rp. -

Rp. 31,452,534.10 Rp. 38,418,448.02 Rp. 6,965,913.92 Rp. -

IX PEKERJAAN INSTALASI LISTRIK 1 Pek. Pemasukan PLN 1.00 Ls @Rp. 2,500,000.00 Rp. 2,500,000.00 Rp. - Rp. - 1.00 Ls @Rp. 2,500,000.00 Rp. 2,500,000.00

2 Pek. Pemasukan Arus - 1.00 Ls @Rp. 1,500,000.00 Rp. 1,500,000.00 1.00 Ls @Rp. 1,500,000.00 Rp. 1,500,000.00

3 Pek. Instalasi listrik 35.00 ttk @Rp. 80,000.00 Rp. 2,800,000.00 53.00 ttk @Rp. 80,000.00 Rp. 4,240,000.00 18.00 ttk @Rp. 80,000.00 Rp. 1,440,000.00 Rp. -

4 Pek. Lampu philips essential (Hemat energi) 20 - 45 watt 17.00 bh @Rp. 43,479.11 Rp. 739,144.80 42.00 bh @Rp. 43,479.11 Rp. 1,826,122.62 25.00 bh @Rp. 43,479.11 Rp. 1,086,977.75 Rp. -

5 Pek. Lampu pijar 25 watt 7.00 bh @Rp. 3,240.68 Rp. 22,684.75 - - @Rp. - Rp. - Rp. - 7.00 bh @Rp. 3,240.68 Rp. 22,684.76

7 Pek. Saklar ganda 7.00 bh @Rp. 24,845.20 Rp. 173,916.42 6.00 bh @Rp. 24,845.20 Rp. 149,071.20 Rp. - 1.00 bh @Rp. 24,845.20 Rp. 24,845.20

8 Pek. Saklar tunggal 8.00 bh @Rp. 19,876.16 Rp. 159,009.30 8.00 bh @Rp. 19,876.16 Rp. 159,009.28 Rp. - Rp. -

9 Pek. Stop kontak 11.00 bh @Rp. 19,876.16 Rp. 218,637.79 11.00 bh @Rp. 19,876.16 Rp. 218,637.76 Rp. - Rp. -

Rp. 6,613,393.06 Rp. 8,092,840.86 Rp. 4,026,977.75 Rp. 2,547,529.96

X PEKERJAAN SANITASI DAN AIR BERSIH 1 Pek. Pemasukan PDAM 1.00 ls @Rp. 2,000,000.00 Rp. 2,000,000.00 Rp. - Rp. - 1.00 ls @Rp. 2,000,000.00 Rp. 2,000,000.00

2 Pek. Sumur Gali (lengkap mesin pompa otomatis) - 1.00 unit @Rp. 10,500,000.00 Rp. 10,500,000.00 1.00 unit @Rp. 10,500,000.00 Rp. 10,500,000.00

3 Pek. Klosed jongkok 6.00 Unit @Rp. 474,418.00 Rp. 2,846,508.00 6.00 Unit @Rp. 474,418.00 Rp. 2,846,508.00 Rp. - Rp. -

4 Pek. Bak fiber 7.00 Unit @Rp. 194,440.72 Rp. 1,361,085.04 6.00 Unit @Rp. 194,440.72 Rp. 1,166,644.32 Rp. - 1.00 Unit @Rp. 194,440.72 Rp. 194,440.72

5 Pek. Pintu KM/WC fiber 6.00 Unit @Rp. 194,440.72 Rp. 1,166,644.32 6.00 Unit @Rp. 194,440.72 Rp. 1,166,644.32 Rp. - Rp. -

6 Pek. Floor drain 7.00 bh @Rp. 31,696.00 Rp. 221,872.00 6.00 bh @Rp. 31,696.00 Rp. 190,176.00 Rp. - 1.00 bh @Rp. 31,696.00 Rp. 31,696.00

7 Pek. Septik tank dan peresapan 1,5 x 2,5 x 1,5 2.00 Unit @Rp. 2,538,000.00 Rp. 5,076,000.00 1.00 Unit @Rp. 2,538,000.00 Rp. 2,538,000.00 Rp. - 1.00 Unit @Rp. 2,538,000.00 Rp. 2,538,000.00

8 Pek. Pas. Pipa PVC dia 1/2" 70.00 m1 @Rp. 18,800.00 Rp. 1,316,000.00 70.00 m1 @Rp. 18,800.00 Rp. 1,316,000.00 Rp. - Rp. -

9 Pek. Pas. Pipa PVC dia 4" 30.00 m1 @Rp. 135,973.00 Rp. 4,079,190.00 30.00 m1 @Rp. 135,973.00 Rp. 4,079,190.00 Rp. - Rp. -

10 Pek. Pas. Pipa PVC dia 2" 30.00 m1 @Rp. 54,112.00 Rp. 1,623,360.00 30.00 m1 @Rp. 54,112.00 Rp. 1,623,360.00 Rp. - Rp. -

Rp. 19,690,659.37 Rp. 25,426,522.64 Rp. 10,500,000.00 Rp. 4,764,136.72

C PEKERJAAN LANTAI II

I PEKERJAAN BETON 1 Pek. Plat beton bertulang + area tangga + atap lobby 26.84 m3 @Rp. 4,879,334.00 Rp. 130,961,324.56 32.18 m3 @Rp. 4,879,334.00 Rp. 157,016,968.12 5.34 m3 @Rp. 4,879,334.00 Rp. 26,055,643.56 Rp. -

2 Pek. Beton bertulang balok lantai 25/35 16.10 m3 @Rp. 4,427,641.00 Rp. 71,285,020.10 8.37 m3 @Rp. 4,427,641.00 Rp. 37,059,355.17 Rp. - 7.73 m3 @Rp. 4,427,641.00 Rp. 34,225,664.93

3 Pek. Beton bertulang kolom30/30 7.72 m3 @Rp. 5,698,473.00 Rp. 43,992,211.56 8.91 m3 @Rp. 5,698,473.00 Rp. 50,773,394.43 1.19 m3 @Rp. 5,698,473.00 Rp. 6,781,182.87 Rp. -

4 Pek. Beton bertulang kolom praktis 12/12 0.80 m3 @Rp. 5,279,610.00 Rp. 4,223,688.00 0.60 m3 @Rp. 5,279,610.00 Rp. 3,167,766.00 Rp. - 0.20 m3 @Rp. 5,279,610.00 Rp. 1,055,922.00

5 Pek. Beton bertulang ring balok 20/30 14.00 m3 @Rp. 4,427,641.00 Rp. 61,986,974.00 9.87 m3 @Rp. 4,427,641.00 Rp. 43,700,816.67 Rp. - 4.13 m3 @Rp. 4,427,641.00 Rp. 18,286,157.33

6 Pek. Beton bertulang Kanopi jendela 3.10 m3 @Rp. 4,879,334.00 Rp. 15,125,935.40 5.54 m3 @Rp. 4,879,334.00 Rp. 27,031,510.36 2.44 m3 @Rp. 4,879,334.00 Rp. 11,905,574.96 Rp. -

7 Pek. Pas. Dinding bata 1 : 4 325.00 m2 @Rp. 86,013.00 Rp. 27,954,225.00 360.63 m2 @Rp. 86,013.00 Rp. 31,018,868.19 35.63 m2 @Rp. 86,013.00 Rp. 3,064,643.19 Rp. -

8 Pek. Plesteran + acian 1 : 4 650.00 m2 @Rp. 41,195.00 Rp. 26,776,750.00 721.26 m2 @Rp. 41,195.00 Rp. 29,712,305.70 71.26 m2 @Rp. 41,195.00 Rp. 2,935,555.70 Rp. -

382,306,128.62 379,480,984.64 50,742,600.28 53,567,744.26

Page 83: CCO 2013c.xls

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA

II PEKERJAAN LANTAI DAN KERAMIK 1 Pek. Pas. Lantai keramik KM/WC 30 x 30 (Kasar) 14.40 m2 @Rp. 171,546.00 Rp. 2,470,262.40 14.40 m2 @Rp. 171,546.00 Rp. 2,470,262.40 Rp. - Rp. -

2 Pek. Pas. Lantai keramik 40 x 40 (BERMOTIF) 212.00 m2 @Rp. 186,805.00 Rp. 39,602,660.00 166.00 m2 @Rp. 186,805.00 Rp. 31,009,630.00 Rp. - 46.00 m2 @Rp. 186,805.00 Rp. 8,593,030.00

3 Pek. Pas. Dinding keramik 30m x 30 T=1.2 m 42.48 m2 @Rp. 171,546.00 Rp. 7,287,274.08 65.16 m2 @Rp. 171,546.00 Rp. 11,177,937.36 Rp. - (22.68) m2 @Rp. 171,546.00 Rp. (3,890,663.28)

4 Pek. Pas. Keramik selasar 40m x 40 T=1.2 m Rp. - 25.00 m2 @Rp. 186,805.00 Rp. 4,670,125.00 25.00 m2 @Rp. 186,805.00 Rp. 4,670,125.00 Rp. -

5 Pek. Pas. Keramik tangga pasien 40m x 40 T=1.2 m( kasar) Rp. - 20.36 m2 @Rp. 186,805.00 Rp. 3,802,415.78 20.36 m2 @Rp. 186,805.00 Rp. 3,802,415.78 Rp. -

6 Pek. Pas. Keramik tangga 30m x 25 T=1.2 m( kasar) Rp. - 13.50 m2 @Rp. 171,546.00 Rp. 2,315,871.00 13.50 m2 @Rp. 171,546.00 Rp. 2,315,871.00 Rp. -

Rp. 49,360,196.48 Rp. 55,446,241.54 Rp. 10,788,411.78 Rp. 4,702,366.72

III PEKERJAAN KUSEN PINTU DAN JENDELA 1 Pek. Kusen pintu dan jendela 2.60 m3 @Rp. 5,553,393.00 Rp. 14,411,054.84 1.83 m3 @Rp. 5,553,393.00 Rp. 10,162,709.19 Rp. - 0.77 m3 @Rp. 5,553,393.00 Rp. 4,248,345.65

2 Pek. Daun pintu panil 6.00 Bh @Rp. 838,742.00 Rp. 5,032,452.00 6.00 Bh @Rp. 838,742.00 Rp. 5,032,452.00 Rp. - Rp. -

3 Pek. Daun jendela kaca 5 mm 20.00 Bh @Rp. 385,287.00 Rp. 7,705,740.00 23.00 Bh @Rp. 385,287.00 Rp. 8,861,601.00 3.00 Bh @Rp. 385,287.00 Rp. 1,155,861.00 Rp. -

4 Pek. Jendela kaca mati 5 mm 52.00 Bh @Rp. 86,418.10 Rp. 4,493,741.10 45.00 Bh @Rp. 86,418.10 Rp. 3,888,814.50 Rp. - 7.00 Bh @Rp. 86,418.10 Rp. 604,926.70

5 Pek. Ventilasi 6.00 Bh @Rp. 80,700.00 Rp. 484,200.00 6.00 Bh @Rp. 80,700.00 Rp. 484,200.00 Rp. - Rp. -

5 Pek. Jendela Aluminium Rp. - 4.10 M2 @Rp. 842,559.00 Rp. 3,454,491.90 4.10 M2 @Rp. 842,559.00 Rp. 3,454,491.90 Rp. -

Rp. 32,127,187.94 Rp. 31,884,268.59 Rp. 1,155,861.00 Rp. 4,853,272.35

IV PEKERJAAN ATAP 1 Pek. Kuda-kuda (rangka baja ringan) 488.18 m2 @Rp. 168,575.00 Rp. 82,294,943.50 355.34 m2 @Rp. 168,575.00 Rp. 59,901,440.50 Rp. - 132.84 m2 @Rp. 168,575.00 Rp. 22,393,503.00

2 Pek. Atap T 0,35 mm uk. 70x80 488.18 m2 @Rp. 90,915.00 Rp. 44,382,884.70 355.34 m2 @Rp. 90,915.00 Rp. 32,305,736.10 Rp. - 132.84 m2 @Rp. 90,915.00 Rp. 12,077,148.60

3 Pek. Bubungan atap 32.00 m1 @Rp. 63,318.00 Rp. 2,026,176.00 33.20 m1 @Rp. 63,318.00 Rp. 2,102,157.60 1.20 m1 @Rp. 63,318.00 Rp. 75,981.60 Rp. -

4 Pek. Rangka plafond 212.00 m2 @Rp. 68,985.00 Rp. 14,624,820.00 252.02 m2 @Rp. 68,985.00 Rp. 17,385,599.70 40.02 m2 @Rp. 68,985.00 Rp. 2,760,779.70 Rp. -

5 Pek. Plafond triplek 212.00 m2 @Rp. 43,864.00 Rp. 9,299,168.00 252.02 m2 @Rp. 43,864.00 Rp. 11,054,605.28 40.02 m2 @Rp. 43,864.00 Rp. 1,755,437.28 Rp. -

6 Pek. Plafond gipsum Rp. - 25.00 m2 @Rp. 43,864.00 Rp. 1,096,600.00 25.00 m2 @Rp. 43,864.00 Rp. 1,096,600.00 Rp. -

7 Pek. rangka Plafond gipsum Rp. - 25.00 m2 @Rp. 68,985.00 Rp. 1,724,625.00 25.00 m2 @Rp. 68,985.00 Rp. 1,724,625.00 Rp. -

8 Pek. Lisplank kayu 3/25 72.76 m1 @Rp. 31,278.00 Rp. 2,275,787.28 - - @Rp. - Rp. - Rp. - 72.76 m1 @Rp. 31,278.00 Rp. 2,275,787.28

9 Pek. Lisplank GRC 71.40 m1 @Rp. 45,000.00 Rp. 3,213,000.00 71.40 m1 @Rp. 45,000.00 Rp. 3,213,000.00 Rp. -

10 Pek. List plafond profil 410.00 m1 @Rp. 19,627.00 Rp. 8,047,070.00 352.00 m1 @Rp. 19,627.00 Rp. 6,908,704.00 Rp. - 58.00 m1 @Rp. 19,627.00 Rp. 1,138,366.00

11 Pek. tedeng layar GRC @Rp. Rp. - 24.00 M2 @Rp. 45,000.00 Rp. 1,080,000.00 24.00 M2 @Rp. 45,000.00 Rp. 1,080,000.00 Rp. -

12 Pek. rangka tedeng layar GRC @Rp. Rp. - 24.00 M2 @Rp. 68,985.00 Rp. 1,655,640.00 24.00 M2 @Rp. 68,985.00 Rp. 1,655,640.00 Rp. -

Rp. 162,950,849.48 Rp. 138,428,108.18 Rp. 13,362,063.58 Rp. 37,884,804.88

V PEKERJAAN GANTUNGAN DAN KUNCI 1 Pek. Kunci pintu double slaag 6.00 Unit @Rp. 261,247.00 Rp. 1,567,482.00 12.00 Unit @Rp. 261,247.00 Rp. 3,134,964.00 6.00 Unit @Rp. 261,247.00 Rp. 1,567,482.00 Rp. -

2 Pek. Engsel pintu 18.00 Unit @Rp. 34,956.00 Rp. 629,208.00 36.00 Unit @Rp. 34,956.00 Rp. 1,258,416.00 18.00 Unit @Rp. 34,956.00 Rp. 629,208.00 Rp. -

3 Pek. Grendel pintu 2.00 Unit @Rp. 25,000.00 Rp. 50,000.00 24.00 Unit @Rp. 25,000.00 Rp. 600,000.00 22.00 Unit @Rp. 25,000.00 Rp. 550,000.00 Rp. -

4 Pek. Engsel jendela 40.00 Unit @Rp. 25,606.00 Rp. 1,024,240.00 44.00 Unit @Rp. 25,606.00 Rp. 1,126,664.00 4.00 Unit @Rp. 25,606.00 Rp. 102,424.00 Rp. -

5 Pek. Grendel jendela 40.00 Unit @Rp. 25,000.00 Rp. 1,000,000.00 44.00 Unit @Rp. 25,000.00 Rp. 1,100,000.00 4.00 Unit @Rp. 25,000.00 Rp. 100,000.00 Rp. -

6 Pek. Hak angin 40.00 Unit @Rp. 40,897.00 Rp. 1,635,880.00 44.00 Unit @Rp. 40,897.00 Rp. 1,799,468.00 4.00 Unit @Rp. 40,897.00 Rp. 163,588.00 Rp. -

7 Pek. Tarikan jendela 20.00 Unit @Rp. 25,606.00 Rp. 512,120.00 22.00 Unit @Rp. 25,606.00 Rp. 563,332.00 2.00 Unit @Rp. 25,606.00 Rp. 51,212.00 Rp. -

Rp. 6,418,930.00 Rp. 9,582,844.00 Rp. 3,163,914.00 Rp. -

VI PEKERJAAN PENGECATAN 1 Pek. Cat dinding 650.00 m2 @Rp. 38,965.00 Rp. 25,327,250.00 721.26 m2 @Rp. 38,965.00 Rp. 28,103,895.90 71.26 m2 @Rp. 38,965.00 Rp. 2,776,645.90 Rp. -

2 Pek. Cat kusen pintu dan jendela 100.00 m2 @Rp. 57,068.00 Rp. 5,706,800.00 101.50 m2 @Rp. 38,965.00 Rp. 3,954,947.50 1.50 m2 @Rp. 38,965.00 Rp. 58,447.50 Rp. -

Rp. 31,034,050.00 Rp. 32,058,843.40 Rp. 2,835,093.40 Rp. -

VII PEKERJAAN INSTALASI LISTRIK 1 Pek. Instalasi listrik 51.00 ttk @Rp. 80,000.00 Rp. 4,080,000.00 36.00 ttk @Rp. 80,000.00 Rp. 2,880,000.00 Rp. - 15.00 ttk @Rp. 80,000.00 Rp. 1,200,000.00

2 Pek. Lampu philips essential (Hemat energi) 20 - 45 watt 17.00 bh @Rp. 43,479.11 Rp. 739,144.80 24.00 bh @Rp. 43,479.11 Rp. 1,043,498.64 7.00 bh @Rp. 43,479.11 Rp. 304,353.77 Rp. -

3 Pek. Lampu pijar 25 watt 6.00 bh @Rp. 3,240.68 Rp. 19,444.07 - - @Rp. - Rp. - Rp. - 6.00 bh @Rp. 3,240.68 Rp. 19,444.08

4 Pek. Lampu hias 1.00 bh @Rp. 500,000.00 Rp. 500,000.00 - - @Rp. - Rp. - Rp. - 1.00 bh @Rp. 500,000.00 Rp. 500,000.00

4 Pek. Lampu hias gantung (dia 60 cm ) Rp. - 1.00 bh @Rp. 5,000,000.00 Rp. 5,000,000.00 1.00 bh @Rp. 5,000,000.00 Rp. 5,000,000.00 Rp. -

5 Pek. Sarang lampu downlight 28.00 bh @Rp. 43,733.86 Rp. 1,224,547.95 - - @Rp. - Rp. - Rp. - 28.00 bh @Rp. 43,733.86 Rp. 1,224,548.08

6 Pek. Saklar ganda 8.00 bh @Rp. 24,845.20 Rp. 198,761.63 8.00 bh @Rp. 24,845.20 Rp. 198,761.60 Rp. - Rp. -

7 Pek. Saklar tunggal 6.00 bh @Rp. 19,876.16 Rp. 119,256.98 6.00 bh @Rp. 19,876.16 Rp. 119,256.96 Rp. - Rp. -

8 Pek. Stop kontak 11.00 bh @Rp. 19,876.16 Rp. 218,637.79 11.00 bh @Rp. 19,876.16 Rp. 218,637.76 Rp. - Rp. -

Rp. 7,099,793.21 Rp. 9,460,154.96 Rp. 5,304,353.77 Rp. 2,943,992.16

Page 84: CCO 2013c.xls

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA VOLUME SAT HARGA SATUAN JUMLAH HARGA

VIII PEKERJAAN SANITASI DAN AIR BERSIH 1 Pek. Klosed jongkok 6.00 Unit @Rp. 474,418.00 Rp. 2,846,508.00 6.00 Unit @Rp. 474,418.00 Rp. 2,846,508.00 Rp. - Rp. -

2 Pek. Bak fiber 6.00 bh @Rp. 194,440.72 Rp. 1,166,644.32 6.00 bh @Rp. 194,440.72 Rp. 1,166,644.32 Rp. - Rp. -

3 Pek. Pintu KM/WC fiber 6.00 Unit @Rp. 194,440.72 Rp. 1,166,644.32 6.00 Unit @Rp. 194,440.72 Rp. 1,166,644.32 Rp. - Rp. -

4 Pek. Floor drain 6.00 bh @Rp. 31,696.00 Rp. 190,176.00 6.00 bh @Rp. 31,696.00 Rp. 190,176.00 Rp. - Rp. -

5 Pek. Pas. Pipa PVC dia 1/2" 100.00 m1 @Rp. 18,800.00 Rp. 1,880,000.00 100.00 m1 @Rp. 18,800.00 Rp. 1,880,000.00 Rp. - Rp. -

6 Pek. Pas. Pipa PVC dia 4" 80.00 m1 @Rp. 135,973.00 Rp. 10,877,840.00 80.00 m1 @Rp. 135,973.00 Rp. 10,877,840.00 Rp. - Rp. -

7 Pek. Pas. Pipa PVC dia 2" 80.00 m1 @Rp. 54,112.00 Rp. 4,328,960.00 80.00 m1 @Rp. 54,112.00 Rp. 4,328,960.00 Rp. - Rp. -

Rp. 22,456,772.65 Rp. 22,456,772.64 Rp. - Rp. -

D PEKERJAAN FINISHING 1 Pek. Pembersihan akhir 1.00 ls @Rp. 1,338,000.00 Rp. 1,338,000.00 1.00 ls @Rp. 1,338,000.00 Rp. 1,338,000.00 Rp. - Rp. -

2 Pek. Asbuilt drawing 1.00 ls @Rp. 3,000,000.00 Rp. 3,000,000.00 1.00 ls @Rp. 3,000,000.00 Rp. 3,000,000.00 Rp. - Rp. -

3 Pek. Reling besi 30.50 m1 @Rp. 450,000.00 Rp. 13,725,000.00 - - - Rp. - Rp. - 30.50 m1 @Rp. 450,000.00 Rp. 13,725,000.00

4 Pek. Relief Bangunan Rp. - 188 m1 @Rp. 125,000.00 Rp. 23,500,000.00

5 Pek. Cor Saluran Keliling Bangungan Rp. - 8.05 m3 @Rp. 797,699.00 Rp. 6,421,476.95 8.05 m3 @Rp. 797,699.00 Rp. 6,421,476.95

6 Pek. Reling relling tangga stenlies Rp. - 23.50 m1 @Rp. 1,050,000.00 Rp. 24,675,000.00 23.50 m1 @Rp. 1,050,000.00 Rp. 24,675,000.00 Rp. -

Rp. 18,063,000.00 Rp. 58,934,476.95 Rp. 31,096,476.95 Rp. 13,725,000.00

(A). JUMLAH HARGA PEKERJAAN Rp. 1,305,387,605.58 Rp. 1,399,008,055.88 Rp. 223,619,345.98 Rp. 155,143,087.91 (B). PPN = 10 % x (A) Rp. 130,538,760.56 Rp. 139,900,805.59 Rp. 22,361,934.60 Rp. 15,514,308.79 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 1,435,926,366.14 Rp. 1,538,908,861.47 Rp. 245,981,280.57 Rp. 170,657,396.70 (D). DIBULATKAN Rp. 1,435,926,000.00 Rp. 1,538,908,000.00 Rp. 245,981,000.00 Rp. 170,657,000.00

(E).SELISIH HARGA REALISASI DENGAN KONTRAK 102,982,000.00

Page 85: CCO 2013c.xls

RENCANA ANGGARAN BIAYA (RAB)OWNER ESTIMATE (OE)

KEGIATAN : PENIGKATAN SARANA DAN PRASARANA RUMAH SAKIT (DAK)PEKERJAAN : PEMBANGUNAN GEDUNG KELAS III RSUD MHATLOKASI : RSUD MAYJEN H. A. THALIB - KERINCIVOLUME : 1 (SATU) PaketTAHUN ANGGARA : 2013

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

A PEKERJAAN PERSIAPAN 1 Pek. Papan Nama Proyek 1.00 Ls @Rp. 500,000.00 Rp. 500,000.00

2 Pek. Pas. Bowplank dan Pengukuran 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00

3 Pek. Sewa Barak Kerja 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00

4 Pek. IMB dan HO 1.00 Ls @Rp. 2,000,000.00 Rp. 2,000,000.00

5 Pek. Dokumentasi dan Pelaporan 1.00 Ls @Rp. 4,000,000.00 Rp. 4,000,000.00

6 Pek. Pematangan lahan + pengangkutan tanah 300.00 m3 @Rp. 81,405.00 Rp. 24,421,500.00

Rp. 34,921,500.00

B PEKERJAAN LANTAI I

I PEKERJAAN TANAH DAN PASIR 1 Pek. Galian tanah pondasi 46.80 m3 @Rp. 62,540.00 Rp. 2,926,872.00

2 Pek. Urug kembali bekas galian 15.30 m3 @Rp. 70,015.00 Rp. 1,071,229.50

4 Pek. Urugan pasir bawah lantai dan pondasi 15.00 m3 @Rp. 241,747.00 Rp. 3,626,205.00

5 Pek. Urugan tanah lantai dipadatkan 120.00 m3 @Rp. 162,585.00 Rp. 19,510,200.00

Rp. 27,134,506.50

II PEKERJAAN PASANGAN DAN BETON 1 Pek. Pasangan pondasi 1 Pc : 4 Ps 62.64 m3 @Rp. 763,444.00 Rp. 47,822,132.16

2 Pek. Beton bertulang Pondasi 13.66 m3 @Rp. 3,844,028.00 Rp. 52,509,422.48

3 Pek. Beton bertulang sloof 20/35 14.78 m3 @Rp. 4,788,316.00 Rp. 70,771,310.48

4 Pek. Beton bertulang kolom 30/30 7.72 m3 @Rp. 6,416,118.00 Rp. 49,532,430.96

5 Pek. Beton bertulang kolom praktis 12/12 0.80 m3 @Rp. 5,950,011.00 Rp. 4,760,008.80

6 Pek. Beton bertulang kolom teras 1.23 m1 @Rp. 4,963,202.00 Rp. 6,104,738.46

7 Pek. Beton bertulang Kanopi dan plat teras 1.90 m3 @Rp. 5,508,073.00 Rp. 10,465,338.70

8 Pek. Pas. Dinding bata 1 : 4 330.37 m3 @Rp. 94,834.00 Rp. 31,330,308.58

9 Pek. Plesteran + acian 1 : 4 660.74 m3 @Rp. 43,102.00 Rp. 28,479,215.48

10 Pek. Batu alam andesit 109.60 m2 @Rp. 253,298.00 Rp. 27,761,460.80

329,536,366.90

III PEKERJAAN LANTAI DAN KERAMIK 1 Pek. Cor lantai dan selasar 32.78 m2 @Rp. 895,425.00 Rp. 29,352,031.50

2 Pek. Pas. Lantai keramik KM/WC 30x30 16.80 m2 @Rp. 186,803.00 Rp. 3,138,290.40

3 Pek. Pas. Lantai keramik 40x40 ( BERMOTIF ) 228.00 m2 @Rp. 204,248.00 Rp. 46,568,544.00

4 Pek. Pas. Teras keramik 40x40 (BERMOTIF ) 49.56 m2 @Rp. 204,248.00 Rp. 10,122,530.88

5 Pek. Pas. Dinding keramik KM/WC 30x30 T=1.2 m 8.00 m2 @Rp. 186,803.00 Rp. 1,494,424.00

Rp. 90,675,820.78

IV PEKERJAAN KUSEN PINTU DAN JENDELA 1 Pek. Kusen pintu dan jendela 2.39 m3 @Rp. 6,121,415.00 Rp. 14,617,939.02

2 Pek. Pas. Pintu Panel 2 Pintu Terpasang + Kunci 1.00 unit @Rp. 1,134,823.00 Rp. 1,134,823.00

3 Pek. Daun pintu panil 7.00 Bh @Rp. 883,028.00 Rp. 6,181,196.00

4 Pek. Daun jendela kaca 5 mm 18.00 Bh @Rp. 410,065.00 Rp. 7,381,170.00

5 Pek. Jendela Aluminium Area Lobby 47.20 M2 @Rp. 842,559.00 Rp. 39,768,784.80

6 Pek. Ventilasi 6.00 Bh @Rp. 446,933.00 Rp. 2,681,598.00

6 Pek. Kaca Mati 52.00 Bh @Rp. 98,800.00 Rp. 5,137,600.00

Rp. 76,903,110.82

Page 86: CCO 2013c.xls

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

V PEKERJAAN GANTUNGAN DAN KUNCI 1 Pek. Kunci pintu double slaag 7.00 Unit @Rp. 292,264.00 Rp. 2,045,848.00

2 Pek. Engsel pintu 21.00 Unit @Rp. 38,361.00 Rp. 805,581.00

3 Pek. Grendel pintu 14.00 Unit @Rp. 25,000.00 Rp. 350,000.00

4 Pek. Engsel jendela 36.00 Unit @Rp. 28,160.00 Rp. 1,013,760.00

5 Pek. Grendel jendela 36.00 Unit @Rp. 25,000.00 Rp. 900,000.00

6 Pek. Hak angin 36.00 Unit @Rp. 45,153.00 Rp. 1,625,508.00

7 Pek. Tarikan jendela 18.00 Unit @Rp. 28,160.00 Rp. 506,880.00

Rp. 7,247,577.00

XI PEKERJAAN PENGECATAN 1 Pek. Cat dinding 660.74 m2 @Rp. 40,900.00 Rp. 27,024,266.00

2 Pek. Cat kusen pintu dan jendela 100.00 m2 @Rp. 59,427.00 Rp. 5,942,700.00

Rp. 32,966,966.00

IX PEKERJAAN INSTALASI LISTRIK 1 Pek. Pemasukan PLN 1.00 Ls @Rp. 2,500,000.00 Rp. 2,500,000.00

2 Pek. Instalasi listrik 35.00 ttk @Rp. 80,000.00 Rp. 2,800,000.00

3 Pek. Lampu philips essential (Hemat energi) 20 - 45 watt 17.00 bh @Rp. 49,708.75 Rp. 845,048.75

4 Pek. Lampu pijar 25 watt 7.00 bh @Rp. 3,705.00 Rp. 25,935.00

5 Pek. Saklar ganda 7.00 bh @Rp. 28,405.00 Rp. 198,835.00

6 Pek. Saklar tunggal 8.00 bh @Rp. 22,724.00 Rp. 181,792.00

7 Pek. Stop kontak 11.00 bh @Rp. 22,724.00 Rp. 249,964.00

Rp. 6,801,574.75

X PEKERJAAN SANITASI DAN AIR BERSIH 1 Pek. Pemasukan PDAM 1.00 ls @Rp. 2,000,000.00 Rp. 2,000,000.00

2 Pek. Klosed jongkok 6.00 Unit @Rp. 502,139.00 Rp. 3,012,834.00

3 Pek. Bak fiber 7.00 Unit @Rp. 222,300.00 Rp. 1,556,100.00

4 Pek. Pintu KM/WC fiber 6.00 Unit @Rp. 222,300.00 Rp. 1,333,800.00

5 Pek. Floor drain 7.00 bh @Rp. 35,122.00 Rp. 245,854.00

6 Pek. Septik tank dan peresapan 1,5 x 2,5 x 1,5 2.00 Unit @Rp. 2,538,000.00 Rp. 5,076,000.00

7 Pek. Pas. Pipa PVC dia 1/2" 70.00 m1 @Rp. 18,800.00 Rp. 1,316,000.00

8 Pek. Pas. Pipa PVC dia 4" 30.00 m1 @Rp. 153,067.00 Rp. 4,592,010.00

9 Pek. Pas. Pipa PVC dia 2" 30.00 m1 @Rp. 60,522.00 Rp. 1,815,660.00

Rp. 20,948,258.00

C PEKERJAAN LANTAI II

I PEKERJAAN BETON 1 Pek. Plat beton bertulang + area tangga + atap lobby 26.84 m3 @Rp. 5,508,073.00 Rp. 147,836,679.32

2 Pek. Beton bertulang balok lantai 25/35 16.10 m3 @Rp. 4,963,202.00 Rp. 79,907,552.20

3 Pek. Beton bertulang kolom30/30 7.72 m3 @Rp. 6,416,118.00 Rp. 49,532,430.96

4 Pek. Beton bertulang kolom praktis 12/12 0.80 m3 @Rp. 5,950,011.00 Rp. 4,760,008.80

5 Pek. Beton bertulang ring balok 20/30 14.00 m3 @Rp. 4,963,202.00 Rp. 69,484,828.00

6 Pek. Beton bertulang Kanopi jendela 3.10 m3 @Rp. 5,508,073.00 Rp. 17,075,026.30

7 Pek. Pas. Dinding bata 1 : 4 325.00 m2 @Rp. 94,834.00 Rp. 30,821,050.00

8 Pek. Plesteran + acian 1 : 4 650.00 m2 @Rp. 43,102.00 Rp. 28,016,300.00

427,433,875.58

Page 87: CCO 2013c.xls

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

II PEKERJAAN LANTAI DAN KERAMIK 1 Pek. Pas. Lantai keramik KM/WC 30 x 30 (Kasar) 14.40 m2 @Rp. 186,803.00 Rp. 2,689,963.20

2 Pek. Pas. Lantai keramik 40 x 40 (BERMOTIF) 212.00 m2 @Rp. 204,248.00 Rp. 43,300,576.00

3 Pek. Pas. Dinding keramik 30m x 30 T=1.2 m 42.48 m2 @Rp. 186,803.00 Rp. 7,935,391.44

Rp. 53,925,930.64

III PEKERJAAN KUSEN PINTU DAN JENDELA 1 Pek. Kusen pintu dan jendela 2.60 m3 @Rp. 6,121,415.00 Rp. 15,885,071.93

2 Pek. Daun pintu panil 6.00 Bh @Rp. 883,028.00 Rp. 5,298,168.00

3 Pek. Daun jendela kaca 5 mm 20.00 Bh @Rp. 410,065.00 Rp. 8,201,300.00

4 Pek. Jendela kaca mati 5 mm 52.00 Bh @Rp. 98,800.00 Rp. 5,137,600.00

5 Pek. Ventilasi 6.00 Bh @Rp. 92,192.00 Rp. 553,152.00

Rp. 35,075,291.93

IV PEKERJAAN ATAP 1 Pek. Kuda-kuda (rangka baja ringan) 488.18 m2 @Rp. 168,575.00 Rp. 82,294,943.50

2 Pek. Atap T 0,35 mm uk. 70x80 488.18 m2 @Rp. 90,915.00 Rp. 44,382,884.70

3 Pek. Bubungan atap 32.00 m1 @Rp. 63,318.00 Rp. 2,026,176.00

4 Pek. Rangka plafond 212.00 m2 @Rp. 74,783.00 Rp. 15,853,996.00

5 Pek. Plafond triplek 212.00 m2 @Rp. 48,324.00 Rp. 10,244,688.00

6 Pek. Lisplank kayu 3/25 72.76 m1 @Rp. 33,935.00 Rp. 2,469,110.60

7 Pek. List plafond profil 410.00 m1 @Rp. 21,522.00 Rp. 8,824,020.00

Rp. 166,095,818.80

V PEKERJAAN GANTUNGAN DAN KUNCI 1 Pek. Kunci pintu double slaag 6.00 Unit @Rp. 292,264.00 Rp. 1,753,584.00

2 Pek. Engsel pintu 18.00 Unit @Rp. 38,361.00 Rp. 690,498.00

3 Pek. Grendel pintu 2.00 Unit @Rp. 25,000.00 Rp. 50,000.00

4 Pek. Engsel jendela 40.00 Unit @Rp. 28,160.00 Rp. 1,126,400.00

5 Pek. Grendel jendela 40.00 Unit @Rp. 25,000.00 Rp. 1,000,000.00

6 Pek. Hak angin 40.00 Unit @Rp. 45,153.00 Rp. 1,806,120.00

7 Pek. Tarikan jendela 20.00 Unit @Rp. 28,160.00 Rp. 563,200.00

Rp. 6,989,802.00

XI PEKERJAAN PENGECATAN 1 Pek. Cat dinding 650.00 m2 @Rp. 40,900.00 Rp. 26,585,000.00

2 Pek. Cat kusen pintu dan jendela 100.00 m2 @Rp. 59,427.00 Rp. 5,942,700.00

Rp. 32,527,700.00

VI PEKERJAAN INSTALASI LISTRIK 1 Pek. Instalasi listrik 51.00 ttk @Rp. 80,000.00 Rp. 4,080,000.00

2 Pek. Lampu philips essential (Hemat energi) 20 - 45 watt 17.00 bh @Rp. 49,708.75 Rp. 845,048.75

3 Pek. Lampu pijar 25 watt 6.00 bh @Rp. 3,705.00 Rp. 22,230.00

4 Pek. Lampu hias 1.00 bh @Rp. 500,000.00 Rp. 500,000.00

5 Pek. Sarang lampu downlight 28.00 bh @Rp. 50,000.00 Rp. 1,400,000.00

6 Pek. Saklar ganda 8.00 bh @Rp. 28,405.00 Rp. 227,240.00

7 Pek. Saklar tunggal 6.00 bh @Rp. 22,724.00 Rp. 136,344.00

8 Pek. Stop kontak 11.00 bh @Rp. 22,724.00 Rp. 249,964.00

Rp. 7,460,826.75

Page 88: CCO 2013c.xls

NO MACAM PEKERJAAN VOLUME SAT HARGA SATUAN JUMLAH HARGA

VII PEKERJAAN SANITASI DAN AIR BERSIH 1 Pek. Klosed jongkok 6.00 Unit @Rp. 502,139.00 Rp. 3,012,834.00

2 Pek. Bak fiber 6.00 bh @Rp. 222,300.00 Rp. 1,333,800.00

3 Pek. Pintu KM/WC fiber 6.00 Unit @Rp. 222,300.00 Rp. 1,333,800.00

4 Pek. Floor drain 6.00 bh @Rp. 35,122.00 Rp. 210,732.00

5 Pek. Pas. Pipa PVC dia 1/2" 100.00 m1 @Rp. 18,800.00 Rp. 1,880,000.00

6 Pek. Pas. Pipa PVC dia 4" 80.00 m1 @Rp. 153,067.00 Rp. 12,245,360.00

7 Pek. Pas. Pipa PVC dia 2" 80.00 m1 @Rp. 60,522.00 Rp. 4,841,760.00

Rp. 24,858,286.00

D PEKERJAAN FINISHING 1 Pek. Pembersihan akhir 1.00 ls @Rp. 1,338,000.00 Rp. 1,338,000.00

2 Pek. Asbuilt drawing 1.00 ls @Rp. 3,000,000.00 Rp. 3,000,000.00

3 Pek. Reling besi 30.50 m1 @Rp. 450,000.00 Rp. 13,725,000.00

Rp. 18,063,000.00

(A). JUMLAH HARGA PEKERJAAN Rp. 1,399,566,212.45 (B). PPN = 10 % x (A) Rp. 139,956,621.24 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 1,539,522,833.69 (D). DIBULATKAN Rp. 1,539,522,000.00

(E). TERBILANG Satu Milyar Lima Ratus Tiga Puluh Sembilan Juta Lima Ratus Dua Puluh Dua Ribu Rupiah

Sungai Penuh, Februari 2013 Disetujui oleh : Dibuat oleh :

Pejabat Pembuat Komitmen (PPK) CV. IKA PUTRA CONSULTANT Peningkatan Sarana dan Prasarana RS (DAK)

JON EFENDI,Spd FANTONI, ST

NIP.196604071999031009 Arsitek

Page 89: CCO 2013c.xls

REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)OWNER ESTIMATE (OE)

KEGIATAN : PENIGKATAN SARANA DAN PRASARANA RUMAH SAKIT (DAK)PEKERJAAN : PEMBANGUNAN GEDUNG KELAS III RSUD MHATLOKASI : RSUD MAYJEN H. A. THALIB - KERINCIVOLUME : 1 (SATU) UNITTAHUN ANGGARA : 2013

NO MACAM PEKERJAAN JUMLAH HARGA

A PEKERJAAN PERSIAPAN Rp. 34,921,500.00

B PEKERJAAN LANTAI I

I PEKERJAAN TANAH DAN PASIR Rp. 27,134,506.50

II PEKERJAAN PASANGAN DAN BETON Rp. 329,536,366.90

III PEKERJAAN LANTAI DAN KERAMIK Rp. 90,675,820.78

IV PEKERJAAN KUSEN PINTU DAN JENDELA Rp. 76,903,110.82

V PEKERJAAN GANTUNGAN DAN KUNCI Rp. 7,247,577.00

XI PEKERJAAN PENGECATAN Rp. 32,966,966.00

IX PEKERJAAN INSTALASI LISTRIK Rp. 6,801,574.75

X PEKERJAAN SANITASI DAN AIR BERSIH Rp. 20,948,258.00

C PEKERJAAN LANTAI II

I PEKERJAAN BETON Rp. 427,433,875.58

II PEKERJAAN LANTAI DAN KERAMIK Rp. 53,925,930.64

III PEKERJAAN KUSEN PINTU DAN JENDELA Rp. 35,075,291.93

IV PEKERJAAN ATAP Rp. 166,095,818.80

V PEKERJAAN GANTUNGAN DAN KUNCI Rp. 6,989,802.00

XI PEKERJAAN PENGECATAN Rp. 32,527,700.00

VI PEKERJAAN INSTALASI LISTRIK Rp. 7,460,826.75

VII PEKERJAAN SANITASI DAN AIR BERSIH Rp. 24,858,286.00

D PEKERJAAN FINISHING Rp. 18,063,000.00

(A). JUMLAH HARGA PEKERJAAN Rp. 1,399,566,212.45 (B). PPN = 10 % x (A) Rp. 139,956,621.24 (C). TOTAL HARGA PEKERJAAN = (A) + (B) Rp. 1,539,522,833.69 (D). DIBULATKAN Rp. 1,539,522,000.00

(E). TERBILANG Satu MilyarLima Ratus Tiga Puluh Sembilan Juta Lima Ratus Dua Puluh Dua Ribu Rupiah

Sungai Penuh, Februari 2013 Disetujui oleh : Dibuat oleh :

Pejabat Pembuat Komitmen (PPK) CV. IKA PUTRA CONSULTANT Peningkatan Sarana dan Prasarana RS (DAK)

JON EFENDI,Spd FANTONI, ST

NIP.196604071999031009 Arsitek

Page 90: CCO 2013c.xls

RSUD MAYJEN H. A. THA KABUPATEN KERINCI

KEGIATAN PENINGKATAN SARANA DAN PRASARANA RUMAH SAKIT (DAK)

PEKERJAAN

PEMBANGUNAN GEDUNG KELAS III RSUD MHAT

LOKASI RSU MAYJEN H. A. THALIB - KERINCI

VOLUME 1 (SATU) PAKET

TAHUN ANGGARAN 2013

OEOWNER ESTIMATE