CBP PROJECT MANAGEMENT BOOT CAMP EXAMINATION # of questions - 68 Start Time: - 9:00 am Duration – 90 minutes End Time: 10:30 am 1. Which of the following are examples of projects? Choose all correct answers. A. Marketing department B. An idea C. A new product design D. Managing human resources E. Building a Class A building 2. Which of the following statements explains the difference between project management and other forms of management? Choose all correct answers. A. Project management is focused on doing something specific and new. B. Project management concentrates on the continuous management of project resources. C. Project management concentrates on managing resources on a temporary basis D. Management concentrates on the continuous management of resources. E. Management concentrates on managing resources on a temporary basis. 3. Which of the following are the three basic constraints of most projects? Choose all correct answers. A. Human Resources B. Time C. Cost D. Quality E. Grade F. Duration

Transcript of CBP Questions Practice

Page 1: CBP Questions Practice

CBP PROJECT MANAGEMENT BOOT CAMP EXAMINATION

# of questions - 68 Start Time: - 9:00 am Duration – 90 minutes End Time: 10:30 am

1. Which of the following are examples of projects? Choose all correct answers.

A. Marketing departmentB. An ideaC. A new product designD. Managing human resourcesE. Building a Class A building

2. Which of the following statements explains the difference between project management and other forms of management? Choose all correct answers.

A. Project management is focused on doing something specific and new.B. Project management concentrates on the continuous management of project

resources.C. Project management concentrates on managing resources on a temporary basisD. Management concentrates on the continuous management of resources.E. Management concentrates on managing resources on a temporary basis.

3. Which of the following are the three basic constraints of most projects? Choose all correct answers.

A. Human ResourcesB. TimeC. CostD. QualityE. GradeF. Duration

4. Which stage in a project’s life cycle focuses on determining the scope of work? Choose the correct answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

Page 2: CBP Questions Practice

5. Which stage in a project’s life cycle focuses on determining task descriptions? Choose the best answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

6. Which stage in a project’s life cycle focuses on identifying project stakeholders? Choose the best answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

7. Michelle is responsible for distribution within her company. She has decided that she needs to improve the distribution strategies that the company uses. Would you identify this improvement as a project? Choose the best answer.

8. Jack is committed to developing the world’s first helium powered boat. Jack has already begun manufacturing his product. Would you identify this as a project? Choose the best answer.

9. Which of the following project stages is focused on determining whether to undertake a project or not? Choose the best answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

10. Which one of the following statements best describes the project commissioner? Choose the best answer.

A. The project commissioner is a project manager that has expertise in a particular subject.

B. The project commissioner is the project manager who is charged with the overall responsibility for the project’s success.

C. The project commissioner is any project manager that plays active part in the project.

D. The project commissioner is a senior person or executive with the authority to assign resource and approach the board on behalf of the project.

E. The project commissioner is who brought the need or demand for the project to the attention of stakeholders.

Page 3: CBP Questions Practice

11. What are the five key requirements of all project goals and objectives? Choose all correct answers.

A. Goals should be specificB. Goals should be measurableC. Goals should be agreed uponD. Goals should realisticE. Goals should be time-limitedF. Goals should be relevantG. Goals should be temporaryH. Goals should be unique and create something newI. Goals should be final

12. When presenting the project’s business case what are the three key factors that you should consider to ensure the project’s alignment with the company? Choose all correct answers.

A. MissionB. ValuesC. VisionD. Major goalsE. Critical issues

13. Which of the following is the correct formula for calculating “the expected value” in PERT calculations? Choose the correct answer.

A. The expected value = [optimistic + pessimistic + (4 * most likely)] / 6B. The expected value = [optimistic + pessimistic + (6 * most likely)] / 4C. The expected value = [optimistic + most likely + (6 * pessimistic)] / 4D. The expected value = [optimistic + most likely + (4 * pessimistic)] / 6E. The expected value = [pessimistic + most likely + (6 * optimistic)] / 4

14. Which stage in a project’s life cycle focuses on determining project milestones? Choose the best answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

Page 4: CBP Questions Practice

15. Which stage(s) in a project’s life cycle depends on the “Communication” project management area? Choose all correct answers.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

16. Which stage in a project’s life cycle would you most likely have to take corrective action? Choose the best answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

17. Which stage in a project’s life cycle would you award contracts? Choose the best answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

18. Which stage in a project’s life cycle would you have a formal acceptance of contracts? Choose the best answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

19. Which stage in a project’s life cycle would you disassemble team members? Choose the best answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

20. Which of the following is not an ideal project specification? Choose the best answer.

A. Must be bigB. A volume of 1000 ml is requiredC. A weight of 1 kg is requiredD. Must be redE. A height of 10 centimeters is required

Page 5: CBP Questions Practice

21. Which of the following should be included in the Project Definition Document in the Initiation Stage? Choose all correct answers.

A. The Product DescriptionB. The WBSC. The Project MilestonesD. The Business Case DocumentE. The Project AssumptionsF. The Project Calendar

22. Which of the following can be found at Level 2 in a single project Work Breakdown Structure? Choose all correct answers.

A. ProjectB. DeliverablesC. TasksD. SubtasksE. All of the above

23. Which of the following can be found at Level 4 in a single project Work Breakdown Structure? Choose all correct answers.

A. ProjectB. DeliverablesC. TasksD. SubtasksE. All of the above

24. Which of the following best describes the use of Unique WBS Identifiers? Choose all correct answers.

A. WBS Identifiers are used t o identify and track each task within the WBS structure.

B. WBS Identifiers are used for accountingC. WBS Identifiers are used for Earn Value calculationsD. WBS Identifiers are used to determine precise PERT valuesE. WBS Identifiers are used to locate a particular task.

25. Which of the following should be included when defining task descriptions? Choose all correct answers.

A. A general task descriptionB. Task-specific specificationsC. Deliverable-specific task listD. MilestonesE. The populated WBS

Page 6: CBP Questions Practice

26. Using the Quantitative method, what will be the time estimate for 40 building bicycles if it takes 12 hr to build one bicycles? Choose the correct answer.

A. 19 daysB. 20 daysC. 21 daysD. 22 days E. 23 days

27. Which of the following is the correct formula for determining Standard Deviation in PERT calculations? Choose the correct answer.

A. Standard Deviation = [pessimistic – optimistic]/6B. Standard Deviation = [pessimistic – optimistic]/4C. Standard Deviation = [optimistic – pessimistic]/6D. Standard Deviation = [pessimistic – most likely] /6E. Standard Deviation = [optimistic – most likely]/6

28. Given the following values calculate the expected value.Optimistic = 14 daysPessimistic = 18 daysMost likely = 16 days

Choose the correct answer.

A. 5 daysB. 12 daysC. 6 daysD. 16 daysE. 18 daysF. 20 days

29. Given the following values calculate the Standard Deviation.Optimistic = 14 daysPessimistic = 18 daysMost likely = 16 days

Choose the correct answer.

A. 1 dayB. 0.67 daysC. 1.67 daysD. 2 daysE. 6 daysF. None of the above

Page 7: CBP Questions Practice

30. Given the following values calculate the time range for 95.44% accuracy.

Expected Value = 20Standard Deviation = 2

Choose the correct answer.

A. Between 20 – 22 daysB. Between 16 – 24 daysC. Between 18 – 22 daysD. Between 4 – 16 daysE. Between 2 – 4 days

31. Given the following values calculate the time range for 68.26% accuracy.

Expected Value = 20Standard Deviation = 3.5

Choose the correct answer.

A. Between 16.5 to 23.5 daysB. Between 13 – 27 daysC. Between 3.5 – 7 daysD. Between 16 – 24 daysE. Between 23.5 – 27 days

32. Given the following values calculate the time range for 99.73% accuracy.

Expected Value = 35Standard Deviation = 0.9

Choose the correct answer.

A. Between 34.4 to 35.6 daysB. Between 33.8 to 36.2 daysC. Between 32.3 to 37.7 daysD. Between 32 to 38 daysE. Between 0.6 to 1.89 days

Page 8: CBP Questions Practice

33. Given the following values calculate the total expected value for Deliverable 1.

Activity Description Optimistic Pessimistic

Most Likely

Expected Value

Standard Dev

SD Squar

ed

Deliverable1

Task 1 13 15 14 14.00 0.33 0.11

Task 2 25 30 27 27.17 0.83 0.69

Task 3 4 7 5 5.17 0.50 0.25

Task 4 3 5 4 4.00 0.33 0.11

Task 5 5 7 5 5.33 0.33 0.11

Calculate the total expected value:

A. 55.67B. 53.57C. 60D. 9.28E. 3099.15

34. Given the following values calculate the Standard Deviation for Deliverable 1.

Activity Description Optimistic Pessimistic

Most Likely

Expected Value

Standard Dev

SD Squar

ed

Deliverable1

Task 1 13 15 14 14.00 0.33 0.11

Task 2 25 30 27 27.17 0.83 0.69

Task 3 4 7 5 5.17 0.50 0.25

Task 4 3 5 4 4.00 0.33 0.11

Task 5 5 7 5 5.33 0.33 0.11

Calculate the Standard Deviation to be used in time range calculations for Deliverable 1:

A. 1.13B. 1.28C. 1.64D. 2.33E. None of the above

Page 9: CBP Questions Practice

35. Which of the following procurement methods provide no form of ownership? Choose all correct answers.

A. OutsourceB. LicenseC. BuyD. RentalE. Make

36. Which of the following statements clarifies the difference between Management and Leadership? Choose all that apply.

A. Leadership is focused on controlling resources.B. Management is focused on structure.C. Leaders are focused on accomplishing a vision.D. Leaders have a short range perspective.E. Managers have a short range perspective.

37. Which of the following statements clarify the difference between Teams and Groups? Choose all that apply.

A. Teams are an administrative classification of individuals.B. Groups are a collection of people focused on contributing towards shared

goals and objectives.C. Groups are a functional classification of individuals.D. Teams empower people to develop individual skills.E. Groups are assigned tasks and are told what course of action to take.F. Groups are a collection of people who tend to work independently from each

other.

38. Which of the following statements describes the major difference between groups and teams? Choose the best answer.

A. Teams do not have budget constraints.B. Teams have recognized their interdependence.C. Groups are used as an organizational unit.D. Member of a group use similar resources.E. Teams can comprise of a group or groups of people.

39. Identify the benefits of building teams. Choose all correct answers.

A. OwnershipB. AccountabilityC. AcceptanceD. Resource ManagementE. Organization

Page 10: CBP Questions Practice

40. Understanding the difference between management and leadership is important to ensure a company’s success at empowering their workforce. Which of the following statements accurately describes this difference? Choose all correct answers.

A. Management is focused on controlling resourcesB. Management is focused on empowering peopleC. Management manages people as employeesD. Leadership is focused on peopleE. Leaders are focused on a specific task

41. What are the 4 basic needs for creating a learning environment? Choose the four correct answers.

A. Need for fulfillmentB. Need for relevancyC. Need for securityD. Need for belongingE. Need for continuityF. Need for autonomy

42. Which of the following statements best describes the need for autonomy? Choose the best answer.

A. Autonomy refers to the need to do something important.B. Autonomy refers to the need to act independently and be self directing.C. Autonomy refers to the need to work in environment free from threatD. Autonomy refers to the need for support and dependence.E. Autonomy refers to the need to be part of something.

43. Given the following values calculate the Cost Variance.

Budgeted Cost of Work Scheduled (BCWS) = $12,100Budgeted Cost of Work Performed (BCWP) = $12,995Actual Cost of Work Performed (ACWP) = $12,850

Choose the correct answer.

A. (896)B. (750)C. 895D. 145E. 750F. (145)

Page 11: CBP Questions Practice

44. Given the following values calculate the Schedule Variance.

Budgeted Cost of Work Scheduled (BCWS) = $12,100Budgeted Cost of Work Performed (BCWP) = $12,995Actual Cost of Work Performed (ACWP) = $12,850

Choose the correct answer.

A. (896)B. (750)C. 895D. 145E. 750F. (145)

45. Given the following values calculate the Schedule Variance Index.

Budgeted Cost of Work Scheduled (BCWS) = $12,100Budgeted Cost of Work Performed (BCWP) = $12,995Actual Cost of Work Performed (ACWP) = $12,850

Choose the correct answer.

A. (0.06)B. 0.07C. 0.01D. 0.06E. (0.01)

46. Given the following values calculate the Cost Variance Index.

Budgeted Cost of Work Scheduled (BCWS) = $12,100Budgeted Cost of Work Performed (BCWP) = $12,995Actual Cost of Work Performed (ACWP) = $12,850

Choose the correct answer.

A. (0.07)B. (0.06)C. 0.07D. 0.01E. (0.06)

Page 12: CBP Questions Practice

47. Given the following values calculate the Cost Performance Index.

Budgeted Cost of Work Scheduled (BCWS) = $2,500Budgeted Cost of Work Performed (BCWP) = $2,000Actual Cost of Work Performed (ACWP) = $3,000

Choose the correct answer.

A. 1.25B. 0.83C. 0.67D. 1.50E. 1.20

48. Given the following values calculate the Schedule Performance Index.

Budgeted Cost of Work Scheduled (BCWS) = $2,500Budgeted Cost of Work Performed (BCWP) = $2,000Actual Cost of Work Performed (ACWP) = $3,000

Choose the correct answer.

A. 0.80B. 1.00C. 1.20D. 1.25E. 0.83

49. Given the following values calculate the Cost Schedule Index.

Budgeted Cost of Work Scheduled (BCWS) = $2,500Budgeted Cost of Work Performed (BCWP) = $2,000Actual Cost of Work Performed (ACWP) = $3,000

Choose the correct answer.

A. 0.53B. 0.83C. 0.80D. 1.88E. 1.00

Page 13: CBP Questions Practice

50. Given the following values calculate the Estimate at Completion.

Budgeted Cost of Work Scheduled (BCWS) = $2,500Budgeted Cost of Work Performed (BCWP) = $2,000Actual Cost of Work Performed (ACWP) = $3,000Budget at Completion (BAC) = $10,000

Choose the correct answer.

A. $11,000B. $10,500C. $9,000D. $9,500E. $10,000

51. Given the following values calculate the Estimate to Completion.

Budgeted Cost of Work Scheduled (BCWS) = $2,500Budgeted Cost of Work Performed (BCWP) = $2,000Actual Cost of Work Performed (ACWP) = $3,000Budget at Completion (BAC) = $10,000

Choose the correct answer.

A. $8,000B. $7,500C. $6,000D. $6,500E. $7,000F. $14,000G. $13,000

52. The Schedule Performance Index for a particular project is 1.95. What does this SPI value indicate? Choose the best answer.

A. The project is ahead of schedule.B. The project is behind schedule.C. The project is on schedule.D. The project cannot be brought back on track.E. The project can easily be brought back on track.F. The project is over budget.

Page 14: CBP Questions Practice

53. The Cost Performance Index for a particular project is 0.63. What does this CPI value indicate? Choose the best answer.

A. The project is presently at a cost savings.B. The project is over its budget.C. The project is behind schedule.D. The project cannot be brought back on track.E. The project can easily be brought back on track.F. The project is on budget.

54. The Schedule Performance Index for a particular project is 1. What does this SPI value indicate? Choose the best answer.

A. The project is ahead of schedule.B. The project is behind schedule.C. The project is on schedule.D. The project cannot be brought back on track.E. The project can easily be brought back on track.F. The project is over budget.

55. The Schedule Variance of a particular project is 320. What does this SV value indicate? Choose the best answer.

A. The project is ahead of schedule.B. The project is behind schedule.C. The project is on schedule.D. The project cannot be brought back on track.E. The project can easily be brought back on track.F. The project is over budget.

56. The Cost Variance of a particular project is (995). What does this CV value indicate? Choose the best answer.

A. The project is presently at a cost savings.B. The project is over its budget.C. The project is behind schedule.D. The project cannot be brought back on track.E. The project can easily be brought back on track.F. The project is on budget.

Page 15: CBP Questions Practice

57. Which of the following statements the use of the Cost Schedule Index? Choose the best answer.

A. The Cost Schedule Index indicates the likelihood of a project being brought back on track.

B. The Cost Schedule Index indicates the relative extent to which a project is ahead or behind schedule.

C. The Cost Schedule Index indicates the relative extent to which a project is over or under budget.

D. The Cost Schedule Index is used to quantify performance when compared to the original estimates.

E. The Cost Schedule Index is provides a combination of Cost and Schedule estimates.

58. Which of the following can be used as a cost estimation method? Choose all correct answers

A. Cost Schedule IndexB. Cost VarianceC. Personal ExperienceD. Previous ProjectsE. Quantitative Methods

59. Which of the following project management areas are required in the Implementation Stage? Choose all correct answers.

A. Quality ControlB. CommunicationC. Change ManagementD. LeadershipE. Creating Work Breakdown Structure

60. Which stage in a project’s life cycle would you define the Project Calendar? Choose the best answer.

A. The Initiation StageB. The Planning StageC. The Implementation StageD. The Closing Stage

61. Identify the two important factors when planning the quality element of a project. Choose the two correct answers.

A. GradeB. QualityC. PERT calculationsD. ISO StandardsE. Gantt Charts

Page 16: CBP Questions Practice

62. Which of the following are key requirements of the Implementation Stage? Choose all correct answers.

A. Ensure that tasks are completed according to schedule.B. Ensure that tasks are completed within budget.C. Ensure that all deliverable-specific task lists are developed.D. Build the project plan.E. Ensure that all resources have been identified.

63. Which of the following are standard documents that are used during the procurement process? Choose all correct answers.

A. RFPB. RFBC. RFID. IFTE. RFQ

64. Which one of the following solutions would be a last resort when a project’s cost constraints have been surpassed? Choose the correct answer.

A. Adjust project specifications or the scope of workB. Increase the project budgetC. Reduce tasks durationsD. Expand the project calendarE. None of the above

65. Which one of the following is used when negotiating during the procurement process? Choose the best answer.

A. Vendor Evaluation MatrixB. Gantt ChartsC. Decision Making MatrixD. Earned Value ChartsE. Project Selection Criteria

66. Which of the following are needed when determining the Project Schedule? Choose all correct answers.

A. Project calendarB. Resource scheduleC. Task durationsD. Task specificationsE. Project costs assumptions

Page 17: CBP Questions Practice

67. Which one of the following impacts directly on the Project’s Quality Element? Choose the best answer.

A. Project SpecificationsB. Project DeliverablesC. Project ScheduleD. Human ResourcesE. Procurement Plan

68. Which one of the following documents is submitted to the Project Selection Committee for project initiation? Choose the best answer.

A. The Project Definition DocumentB. The Project PlanC. The Project WBSD. The Project Business Case DocumentE. All of the above