Caterpillar 365 KW Generator
for 100-ton rig package
Operation and Maintenance
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
2/15
Purpose
To introduce personnel to the components andperformance capabilities of the 365KW generator
package.
To provide operations guidance for the generator
package.
To provide maintenance and inspection
expectations for the generator package.
To address safety precautions for the generatorpackage.
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
3/15
Components
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
4/15
Generator Control View
1. Electronic ControlModule
2. Control Panel
3. Annuciator Panel(Performance
Readings)
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
5/15
Generator Panels EMC
o Top Row Alarm Level
o Second Row Run/Auto/Stop
Control Panel1. Low Oil Pressure
Override2. Engine Speed3. Emergency STOP4. Generator Engage5. Proper Hertz (50)6. Test Plug7. Alarm8. Generator on9. Generator off
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
6/15
Performance and Capacities
Caterpillar C-15 engine at 373 Kw/500 hp
Kato 365 Kw 220 Volt 50 Hz generator
Impulse circuit board breaker box
Quincy electric air compressor
7.5 Kw , 8.3 bar Webasto coolant heater
Generator house has 4 lift eyes and 4 securing
eyes
Complete generator house 5.5 meter X 2.4 meterat 10 tons
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
7/15
Positioning of the Generator The generator house should be positioned at
least 15 meters from the well bore and the mudpit.
Trailer jack pattern is 10.9 meters X 2.4 meter at
24.3 ton including power swivel. If the power swivel and generator are operated on
the trailer each of the 4 jacks must support 6-tons. Additional matting will be necessary.
The generator house is secured to the trailer with4 transport pins. It may be removed from thetrailer and set independently for operation.
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
8/15
Electrical Safety
The generator should be electrically groundedbefore and during operation to a suitable earth
ground.
WARNING - The circuit breaker for each electrical
outlet must be disconnected/turned off before
connecting or disconnecting electrical cords.
WARNINGNever perform work on any
energized electric circuit. All repairs, additions, or
modifications to electrical circuits must be
performed by a qualified electrician.
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
9/15
Electrical Safety Electrical plugs and
receptacles aresealed for gas orliquids & lock together
locks must beengaged
Electrical splices mustbe performed by anelectrician use ofelectrical tape asinsulation is notpermitted
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
10/15
Starting the engine Generator should be started 1-hour before night fall if
used only at night.
Check all fluid levels engine oil and coolant beforestarting the engine. Fill the fluids to the normaloperating range. Report any contaminated fluid to the
supervisor so that they may be replaced. The engine is equipped with a coolant heating
system. This heating system will preheat the engineand fuel systems. The heating system should beused to preheat the systems when temperatures are
below 5 degrees C. Be certain that all personnel are clear of the engine
before starting the engine.
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
11/15
Daily Maintenance
Check engine oil and coolant fluid levels dailywith the dipsticks or sight glass.
Check to confirm that primary electrical
connections are tight.
Inspect the air cleaner service indicator clean or
replace air cleaner element if indicator is in the
red zone.
Check the fuel/water separator
drain any wateror sediment (drain valve opens countrclockwise).
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
12/15
Monthly Maintenance
Inspect engine and radiator for leaks.
Inspect fan and alternator belts for wear or
deterioration.
Change engine oil and filters every 500 hours of
operation.
Replace the primary fuel filter/water separator
element every 500 hours of operation.
Replace the secondary fuel filter every 500 hoursof operation.
Clean crankcase breather
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
13/15
Welding on or near the generator
WARNING
Welding on the generator or thegenerator house can damage or destroy the
electronic controls unless proper steps are
followed.
Improper grounding can cause damage to drive
train bearings, hydraulic components, and other
equipment.
Clamp the ground cable from the welder to the
component that will be welded.
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
14/15
Welding on EquipmentUse the example here. The current flow
from the welder to the ground clamp of thewelder will not cause damage to any
associated components.
1. Engine
2. Welding electrode
3. Key switch in the OFF position4. Battery disconnect switch in the open
position
5. Disconnected battery cables
6. Battery
7. Electrical/Electronic component
8. Maximize distance between thecomponent that is being welded andany electrical/electronic component.
9. The component that is being welded.
10. Current path of the welder.
11. Ground clamp for the welder.
-
7/29/2019 Caterpillar 365KW Generator Operation and Maint - Copia
15/15
Review of Key Points
The generator should positioned at least 15meters from the well.
Never connect, disconnect, or perform work on a
live electrical circuit.
All electric power cords have locking connections
secure the connections.
Do not weld on the generator or generator house
without following the proper procedure todisconnect electronics and ground the welder
properly.