Page 1: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

CAT II/III Workshop

Flight Operations View

Page 2: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

CAT II/III Flight Operations View

• General Concepts ICAO/JAA/FAA

• Approval Process– Aircraft Requirements

– Aerodrome Requirements

– Air Operator

Page 3: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

CAT II

• CAT II DH<200 (60m)>=100(30m) and RVR >= 1200ft (350m) (JAA 1000 (300JAA 1000 (300))

• Sufficient visual reference for a manual landing

• Equivalent level of safety by; of safety by;– airborne equipmentairborne equipment– ILS FacilityILS Facility

Page 4: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

CAT II

• Equivalent level of safety by:– visual aids– flight crew training/procedures– ATC procedures– aircraft maintenance– airfield maintenance– criteria for obstacle clearance

Page 5: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

CAT III

• ICAO/FAA - CAT IIIA DH <100(30m) or no DH and RVR >= 700ft (200m) (JAA always DH)

• ICAO/FAA - CAT IIIB DH <50ft (15m) or no DH RVR < 700ft (200m) not <150ft (50m) (JAA 250ft(75m))

• ICAO/FAA - CAT IIIC 0/0 (No JAA)

Page 6: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

CAT III

• Not sufficient references to permit visual landing• Minimum to allow pilot to decide whether aircraft

will land in touchdown zone (CAT IIIA) and ensure safety during roll-out (CAT IIIB)

• Desired level of safety achieved with more stringent requirements

Page 7: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

DH/DA

• Decision altitude/height (DA/H) - is the wheel height above the runway elevation by which a go-around must be initiated unless adequate visual reference has been established and the aircraft position and approach path have been assessed as satisfactory to continue the approach and landing in safety (JAA)

Page 8: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Decision Height

• JAA - for CAT II and CAT IIIA the visual reference to contain not less than a 3 light segment

• JAA - CAT IIIB visual reference to contain one centreline light

Page 9: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Alert Height

• Alert Height - height above runway based on the characteristics of the aeroplane and its fail operational automatic landing system, above which a CAT III approach would be discontinued and a missed approach initiated if a failure occurred in one of the redundant parts of the automatic landing system, or in the relevant ground equipment

Page 10: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Alert Height• Fail-operational automatic landing system - if in

the event of a failure, the approach, flare and landing can be completed by the remaining part of the automatic system.

• Fail-passive automatic landing system - in the event of a failure there is no significant deviation of aeroplane trim, flight path or altitude but the landing will not be completed automatically.

Page 11: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Alert Height

• Go-around above Alert Height for failures (AFM) affecting fail operational system

• Below Alert Height continue except for Autoland warning

• Height evaluated during certification - typically 100 - 200feet

• Operators can select lower Alert Height

Page 12: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

RVR

• Runway Visual Range - range over which a pilot of an aircraft on the centreline of the runway can see the runway surface markings or the lights delineating the runway or identifying its centreline

• Transmissometers strategically located• Three basic portions of runway - the touchdown

zone (TDZ), the mid-runway portion (MID) and the rollout portion or stop end

Page 13: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

RVR

• For CAT II TDZ required

• For CAT III TDZ and Mid required

• For lowest weather FAA requires all

• For CAT III with no DH JAA require only one

• RVR is not the Slant Visual Range (SVR) seen by the pilot

Page 14: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

RVR Minima

• Pilots require 1-3 seconds to establish visual contact• To establish lateral position pilots required to see not

less than three lights• To maintain lateral most pilots require to be able to see a

lateral element of ground pattern• Vertical plane - see a point which has low apparent

movement relative to the aircraft

Page 15: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

RVR Minima

• Establish an RVR to to be associated with that DH to ensure required visual reference is established

• Correlation between visual segment SVR - RVR

• Eye position is important

• Landing lights can obscure required visual reference in CAT III

Page 16: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Minimum Approach Break-off Height

• MABH is the lowest height above ground measured by radio-altimeter such that if a missed approach is initiated without external references:– in normal operation, the aircraft does not touch the

ground during the procedure

– with an engine failure it can be demonstrated that an accident is extremely improbably

Page 17: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Minimum Approach Break-off Height

• Used by JAA but being phased out

• Replaced by minimum DH or indication in AFM of altitude loss during automatic go around - either MABH or altitude loss in AFM can be use to determine minimum DH in CAT III operation

Page 18: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Types of Minima

• Airfield Operating Minima - established in accordance with aerodrome OCH

• Operator Minima - Lowest minima approved by authority for use by an air operator

• Crew Minima - lowest for a crew depending on their qualification/experience

• Aircraft minima - demonstrated during aircraft certification and found in the AFM

Page 19: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Approval Process

Page 20: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aircraft

Flight Crew Air Operator

Aerodrome

Safety

Regulatory Approval

Page 21: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aircraft requirements Airfield requirements

CAT II/III cert ification CAT II/III facilities

Operator’s duties

Crew training

Flight Procedures

Maintenance programme

Airf ield operating minima

FILE

Simulator training

Operational demonstration

Approval

In-line operation Monitoring

Approval Process

Page 22: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Topics

• Aircraft Requirements

• Aerodrome Requirements

• Air Operator

• Approval Process

Page 23: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aeroplane andAeroplane and

EquipmentEquipment

Page 24: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Aircraft requires CAT II/III approval

• Operational approval is required

• JAR AWO section 1 (Autoland), Section 2 CAT II and section 3 (CAT III)

• FAA AC20-57A (autoland), AC 120-29 (CAT II) and AC 120-28D (CAT III)

Aeroplane and Equipment Certification

Page 25: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Equipment listed in AFM to be operative

• MEL indicate status of CAT II/III

• Automatic landing certification requires simulations, assessments and flight test

• Touchdown, roll-out, automatic landing with various configurations and conditions tested

Aeroplane and Equipment Certification

Page 26: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Successful approach– No system failure from 150m

– Speed maintained +/- 5 knots (no turbulence)

– Position of the aircraft between 90m and the DH - deviation of Glide path and Localizer do not exceed the values for excess deviation alerts

Aeroplane and Equipment Certification

Page 27: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome Requirements

• Standards and Recommendations from ICAO Annex 10 (ILS) and ICAO Annex 14 (Aerodrome) are internationally accepted

• Additional requirements/variants may be found in national regulations

• Summary view of typical CAT II/III airfield

Page 28: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome Requirements - Runway

• Runway length - operational requirement• Runway width - normally < 45m• Slope 1st/last quarter < 0.8%• Auto Landing - maximum 2% per 30m in area just before

threshold (60m by 200m)• Objects on runway strip - nil within 60m of centreline

(except frangible)• Taxi-holding positions not < 90m

Page 29: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome Requirements Visual Aids -Aerodrome

• Markings centreline, touchdown, taxiway, taxi-holding position markings

• High intensity threshold, runway end lights, runway touchdown zone lights and runway centreline lights, taxiway centreline lights if <400m visibility, stop bars <400m visibility

Page 30: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome Requirements Visual Aids - Approach

• Approach Lights required for CAT II only

• Extended centreline, side row, crossbar

Page 31: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome RequirementsObstacle Clearance Area

• Obstacle Clearance Altitude/Height (OCH/OCA) - lowest height above threshold (aerodrome) used in establishing compliance with appropriate obstacle clearance criteria

• Minimum DH for CAT II cannot be less than established OCH/A

• OCH/A is a function of aircraft category

Page 32: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome RequirementsObstacle Clearance Area

• Obstacle Free Zone– airspace above inner approach surface, inner

transitional and balked landing surfaces and that portion of the strip

– not penetrated by obstacles except frangible mounted required for air transportation purposes

Page 33: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome RequirementsILS Facility

• Three categories (Annex 10)

– 60m (200ft) for CAT I

– 15m (50ft) for CAT II (acceptable to be used for CAT III with the highest minima (DH not< 50ft)

– Runway surface and along the runway for CAT III

Page 34: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome RequirementsILS Facility

• ILS Critical Area - aircraft/vehicles are excluded during all ILS operations because they will cause disturbances to ILS signal

• ILS Sensitive Area - area extending beyond the critical area where movement and/or parking of aircraft and vehicles is controlled to prevent the possibility

• ILS beam to be protected by longitudinal separation

Page 35: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome RequirementsRVR Measurements

• Number depend on type of operation• Generally 110 to 150m from centreline• Nominally 5m-10m in height

• ICAO recommends readout of 50m increments when RVR less than 800m and 25m increments when RVR less than 150m

• Normally ATC give Mid unless the others lower

Page 36: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome RequirementsMaintenance

• % of unserviceable lights not to exceed 5%

• Recommended not adjacent lights

• Secondary power supply with switchover of maximum of 1 second

• ILS installations ground and flight checked

Page 37: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome RequirementsATC

• Each Aerodrome to develop Low Visibility Procedures to include:– Procedures for ATC to be quickly informed of all

degradations of ILS performance– Procedures for ATC to be quickly informed of

any degradations in visual aids– Procedures for protection of OFZ by control of

ground traffic

Page 38: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aerodrome RequirementsATC

• Each Aerodrome to develop Low Visibility Procedures to include:– Procedures for protection of ILS critical and

sensitive areas and between aircraft– Procedures for met services– Procedures for maintenance– Procedures for security

Page 39: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Air Operator Approval

Page 40: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Aircraft type - AFM (Certification)• Aerodrome equipment - qualify• Aerodrome Operating Minima• Flight Crew Training• Flight Crew Procedures• Maintenance Program• Operational Demonstration

Air Operator Approval

Page 41: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Operator take account of:– aircraft performance– composition of flight crew– runway which may be used– adequacy of visual and non-visual aids– aircraft navigation equipment– obstacle clearance height– availability of met reports

Air Operator Approval Minima

Page 42: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Air Operator to ensure DH not lower than:– DH specified in the AFM– Minimum DH to which precision approach can

be used– The OCH for category of aircraft– The DH for which the flight crew is authorised– 100ft(30m)

Air Operator Approval CAT II DH

Page 43: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• An air operator to ensure that DH not lower than:– Minimum DH in the AFM

– Minimum DH to which the precision approach can be used

– The DH to which the crew is authorised

Air Operator Approval CAT III DH

Page 44: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

– ICAO/JAA/FAA slight differences

– RVR Minimum related to DH

– Increase DH Increase RVR

– For RVR values less than 300m a go-around is assumed in event of auto-pilot failure

Air Operator Approval CAT II/III RVR

Page 45: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Air Operator ApprovalFlight Crew Procedures

• Satisfactory check of aircraft equipment• Effect on minima of failures - aircraft and ground• Procedures for approach, flare and roll-out• Procedures for failures/warnings• Minimum visual reference• Importance of correct seating eye position• Action to take if visibility deteriorates

Page 46: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Air Operator ApprovalFlight Crew Procedures

• Allocation of crew duties to permit PIC to devote himself to supervision/decision making

• Calls below 200ft - one pilot on instruments at all times

• Requirement for localizer area to be protected

• Use of information relating to wind, turbulence

• Procedures to use for practice approaches• Information on maximum deviation allowed

Page 47: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Air Operator ApprovalFlight Crew Procedures

• Flight preparation procedures

• Approach preparation procedures

• Approach Procedures

• Failures and associated actions– Continue– Revert to higher minimum– Go Around and reassess

Page 48: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Air Operator ApprovalFlight Crew Procedures

• Failures - Continue/Revert/Go Around– > 1000 Continue with higher DH if conditions met– < 1000 Go around and reassessment– Below AH go around required for autoland warning

• Abnormal Procedures– Provided in AFM– Simplified procedures found in FCOM

Page 49: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Air Operator ApprovalFlight Crew Training

• CAA requirements to be met– Ground training requirements

– Simulator Training requirements

– Initial, recurrent, conversion training/checking

– Type and command experience

Page 50: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Airbus aircraft CAT II/III inherent functions

• Air operator required to seek approval from CAA

• Specific maintenance program

• Reliability program to be extended to monitor, track and control - > 95%

Air Operator ApprovalMaintenance

Page 51: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Procedures to govern the capability of aircraft• Upgrading/downgrading procedure to be defined• Dispatch policy based on MEL• Dispatch criteria and status recorded in the

Technical Log • Requirements for tests to verify the CAT III

capability to be established

Air Operator ApprovalMaintenance

Page 52: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• To establish that the air operator can carry out CAT II/III with the appropriate success rate and level of safety

• Performance and reliability meet airworthiness certification

• Attention given to flight and maintenance procedures

Air Operator ApprovalOperational Demonstration

Page 53: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Flight reports and/or recordings

• Recordings required for DH < 50ft

• Resulting approach/landing success rate

• Unsuccessful approaches due to ATC factors and/or ground facility difficulties may be excluded if proofs provided

Air Operator ApprovalOperational Demonstration

Page 54: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Data Collection Crew Report:– airfield and runway used– weather conditions– time, adequacy of speed control– out of trim– capability of information (FD, AFCS, raw)– position through 100 ft and at touchdown– reason for failure if approach aborted

Air Operator ApprovalOperational Demonstration

Page 55: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• New Type:– 6 months at 200ft with procedures for lower

limits in place– Summary report to indicate to 90% confidence

level that 95% would be successful– No failure for 30 approaches– then 6 months at 50 ft with procedures for

lower limits in place

Air Operator ApprovalOperational Demonstration

Page 56: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• New Type:– then 6 months at 50 ft with procedures for

lower limits in place– summary report to indicate to 90% confidence

level that deviations are not worse than recorded during the certification programme

– typically 100 landings– sources of data distributed evenly

Air Operator ApprovalOperational Demonstration

Page 57: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Continue to provide reports of service

• Number of approaches, by type where CAT II or III equipment was utilised to make satisfactory, actual or practice approaches to the applicable CAT II or III minima

• Unsatisfactory approaches by aircraft/airfield

• Detect any decrease in the level of safety

Air Operator ApprovalContinuos Monitoring

Page 58: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

• Training purposes or data gathering

• CAT I beam - to be checked

• Terrain profile to be checked

• Generally accepted without activation of low visibility procedures

• Crew authorisation to be required

• Crew procedures established

• Vigilant for ILS disturbances

Air Operator ApprovalAutoland in > CAT I

Page 59: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Aircraft requirements Airfield requirements

CAT II/III cert ification CAT II/III facilities

Operator’s duties

Crew training

Flight Procedures

Maintenance programme

Airf ield operating minima

FILE

Simulator training

Operational demonstration

Approval

In-line operation Monitoring

Approval Process

Page 60: CAT II/III Workshop Flight Operations View CAT II/III Flight Operations View General Concepts ICAO/JAA/FAA Approval Process –Aircraft Requirements –Aerodrome.

Questions/Comments