Activity ID Activity Name Original Duration Start Finish Jammu-Udhampu Jammu-Udhampur Road Project (Jammu Sec... 256 06-Oct-12 07-Sep-13 J.SS5.V7A.RS.S1.10 Casting of Post Tension Girder 45 06-Oct-12 19-Nov-12 J.SS6.B6.LS.S1.010 Casting of Post Tension Girder 45 09-Dec-12 22-Jan-13 J.SS6.B3.LS.S1.010 Casting of Post Tension Girder 45 12-Dec-12 25-Jan-13 J.SS4.B10.LS.S1.010 Casting of Post Tension Girder 45 20-Dec-12 12-Feb-13 J.SS6.B6.LS.S2.010 Casting of Post Tension Girder 45 22-Feb-13 07-Apr-13 J.SS6.B4.LS.S1.010 Casting of Post Tension Girder 45 25-Feb-13 10-Apr-13 J.SS5.V7A.LS.S1.10 Casting of Post Tension Girder 45 20-Mar-13 03-May-13 J.SS4.B9.RS.S1.010 Casting of Post Tension Girder 45 08-May-13* 21-Jun-13 J.SS4.B9.LS.S1.010 Casting of Post Tension Girder 45 11-May-13* 24-Jun-13 J.SS4.B9.RS.S6.010 Casting of Post Tension Girder 45 22-Jul-13 04-Sep-13 J.SS4.B9.LS.S6.010 Casting of Post Tension Girder 45 25-Jul-13 07-Sep-13 Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 2013 2014 06-Oct-12 07-Sep-13 Casting of Post Tension Girder Casting of Post Tension Girder Casting of Post Tension Girder Casting of Post Tension Girder Casting of Post Tension Girder Casting of Post Tension Girder Casting of Post Tension Girder Casting of Post Tension Girder Casting of Post Tension Girder Casting of Post Tension Girder Casting of Post Tension Girder Jammu-Udhampur Road Project (Jammu Section) 16-Oct-12 1 of 1 Actual Work Remaining Work Critical Remaining Work Milestone Summary PROJECT: JAMMU UDHAMPUR ROAD PROJECT (JAMMU SECTION) CONCESSIONAIRE: SP JAMMU UDHAMPUR HIGHWAYS (P) LTD EPC CONTRACTOR: AFCONS INFRASTRUCTURE LTD Date Revision Checked Approved 16-Aug-12 R4 26-Mar-12 Addendum-R3 16-Mar-12 R3 13-Feb-12 R2 26-Dec-11 R1 19-Oct-11 R0

description

Girder Programme

Transcript of Cast Insitu Girder Programme

Page 1: Cast Insitu Girder Programme

Activity ID Activity Name OriginalDuration

Start Finish

Jammu-Udhampur Road Project (Jammu Section)Jammu-Udhampur Road Project (Jammu Sec... 256 06-Oct-12 07-Sep-13

J.SS5.V7A.RS.S1.10 Casting of Post Tension Girder 45 06-Oct-12 19-Nov-12

J.SS6.B6.LS.S1.010 Casting of Post Tension Girder 45 09-Dec-12 22-Jan-13

J.SS6.B3.LS.S1.010 Casting of Post Tension Girder 45 12-Dec-12 25-Jan-13

J.SS4.B10.LS.S1.010 Casting of Post Tension Girder 45 20-Dec-12 12-Feb-13

J.SS6.B6.LS.S2.010 Casting of Post Tension Girder 45 22-Feb-13 07-Apr-13

J.SS6.B4.LS.S1.010 Casting of Post Tension Girder 45 25-Feb-13 10-Apr-13

J.SS5.V7A.LS.S1.10 Casting of Post Tension Girder 45 20-Mar-13 03-May-13

J.SS4.B9.RS.S1.010 Casting of Post Tension Girder 45 08-May-13* 21-Jun-13

J.SS4.B9.LS.S1.010 Casting of Post Tension Girder 45 11-May-13* 24-Jun-13

J.SS4.B9.RS.S6.010 Casting of Post Tension Girder 45 22-Jul-13 04-Sep-13

J.SS4.B9.LS.S6.010 Casting of Post Tension Girder 45 25-Jul-13 07-Sep-13

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2013 2014

06-Oct-12 07-Sep-13

Casting of Post Tension Girder

Casting of Post Tension Girder

Casting of Post Tension Girder

Casting of Post Tension Girder

Casting of Post Tension Girder

Casting of Post Tension Girder

Casting of Post Tension Girder

Casting of Post Tension Girder

Casting of Post Tension Girder

Casting of Post Tension Girder

Casting of Post Tension Girder

Jammu-Udhampur Road Project (Jammu Section) 16-Oct-12 1 of 1

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary

PROJECT:

JAMMU UDHAMPUR ROAD PROJECT

(JAMMU SECTION)

CONCESSIONAIRE:

SP JAMMU UDHAMPUR HIGHWAYS (P) LTD

EPC CONTRACTOR:

AFCONS INFRASTRUCTURE LTD

Date Revision Checked Approved

16-Aug-12 R4

26-Mar-12 Addendum-R3

16-Mar-12 R3

13-Feb-12 R2

26-Dec-11 R1

19-Oct-11 R0