Cashless Tolling Informational Meeting

24
August 7, 2018 Cashless Tolling Informational Meeting NEWYORK STATE OF OPPORTUNITY.. Thruway Authority

Transcript of Cashless Tolling Informational Meeting

Page 1: Cashless Tolling Informational Meeting

August 7, 2018

Cashless Tolling Informational Meeting

NEWYORK STATE OF OPPORTUNITY..

Thruway Authority

Page 2: Cashless Tolling Informational Meeting

August 7, 2018 2

Agenda• Brief Description of Project • RFQ• Gantry Locations

Exits - 23, 24, 25, 25A, 34A, 36, 39, 45, 46, and 47 Terminus locations –Woodbury, Canaan, Williamsville, Lackawanna, and RipleyExample:Tandem Lots at InterchangesExample:

• Toll in place locations (36 Exits)Work by otherso Design-Builders responsibilityo Exampleo Tandem Lots

• Misc. Worko Exit 35o Exit 16 - Harriman

• Third party Involvement o Kapscho Adestao Utilitieso Work Scopeo Incentives/Disincentives

• Firms Conflicted Out• Questions

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 3: Cashless Tolling Informational Meeting

August 7, 2018 3

RFQ• RFQ scheduled to be released in 2 weeks from today. SOQs shall be required to be returned

approximately 4 weeks after.• Depending on # of respondents, that will determine amount of evaluation time.• Thruway anticipates one month for announcement of Short-List• Typical type of RFQ

o Past performanceo MWBE/DBE goal orientated historyo Work experience o On budget – on time delivery historyo Claim history - explanationo Key personnel o Design-Build organizationo Logistical and geographical presentation of how this work is going to get done*o Map form*o AF Form – Affirmation of subcontractors willing to work as a sub if your team is

declared Best-Value*

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 4: Cashless Tolling Informational Meeting

August 7, 2018 4

MAP

,,,,.

_JNEWV•• RI< I Thruway 2 ~;.~% .. ,,.. Authority

_.,..,,,.. ,... ..

New Yo~k State Thruway Authority All Electronic Cashless Tolling Woodbury Tdl Barrier (MP 45.03) to Ripley Toti Barrier (MP496.00)

Page 5: Cashless Tolling Informational Meeting

August 7, 2018 5

10 Interchanges – 5 Terminus Locations• Gantries shall replace Toll Booths in processing and collecting tolls.• The Gantries will be required to be on the Mainline of the Thruway (Not in the interchange area).• Interchanges include Exits 23, 24, 25, 25A, 34A, 36, 39, 45, 46, 47

Terminus locations include Woodbury, Canaan, Williamsville, Lackawanna and Ripley.• 9 of the 10 Interchanges house Tandem Lots. The Thruway has to capture the point of origin to the

ticketed system and the point of departure.• Work Outline

• Work to be done: (After AET is active)o Toll plaza removalo Signingo Striping o Positive separation of opposing traffico Tandem access modificationo Shrinkage of the Toll area footprinto Barrier/Guiderail outside perimeter o Superelevation adjustments (if necessary)o Other misc. items 4 wvoRK I Thruway

TEOF • oRTUNITY. Authority

Page 6: Cashless Tolling Informational Meeting

August 7, 2018 6

Existing View - Williamsville Toll Plaza

wvoRK I Thruway TE OF •

POFITuN,rv Authority

Page 7: Cashless Tolling Informational Meeting

August 7, 2018 7

Williamsville Toll Plaza

wvoRK I Thruway TE OF •

POFITuN,rv Authority

Page 8: Cashless Tolling Informational Meeting

August 7, 2018 8

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 9: Cashless Tolling Informational Meeting

August 7, 2018 9

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 10: Cashless Tolling Informational Meeting

August 7, 2018 10

Tandem Lots• 9 out of 10 Interchanges have Tandem Lots.• Safety• Tandems will not be entering the Thruway like they once did.• Thruway will be submitting a request for legislation to deal with Tandem access routing to allow

entry back onto Thruway system.o May require modifications to intersections and ramps.o This shall be the Design-Builders responsibility.

• Design-Builder shall be responsible for ensuring safe passage of tandem trucks along proposed legislated routes.

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 11: Cashless Tolling Informational Meeting

August 7, 2018 11

Int. 24 Proposed Tandem Route I Thruway Authority

Page 12: Cashless Tolling Informational Meeting

August 7, 2018 12

Page 13: Cashless Tolling Informational Meeting

August 7, 2018 13

Page 14: Cashless Tolling Informational Meeting

August 7, 2018 14

Toll in Place (36 Exits)

• Exits – B1, B2,17, 18, 19, 20E, 20W, 21, 21B, 22, 26, 27, 28, 29, 29A, 30, 31, 32, 33, 34, 37, 38, 40, 41, 42, 43, 44, 48, 48A, 49, 56, 57, 57A, 58, 59, and 60.

• All the Equipment/Electronics will be put in place by others (by the end of 2019)through Thruway let contracts.

• Design-Builder will be told in the RFP how many lanes in each direction must be made available.• In some locations there will be criteria for a reversible toll booth lane.• The Design-Builder shall be responsible for all necessary Civil work.

o Signingo Striping o Positive separation of opposing traffic.o Tandem access modification (entry and exit points)o Barrier/Guiderail outside perimeter.o Possible reduction of footprint of Toll Booth areao Other misc. items

o Concrete pavement repairo Asphalt overlayso Treadle repairs or replacement 4 wvoRK I Thruway

TEOF • oRTUNITY. Authority

Page 15: Cashless Tolling Informational Meeting

August 7, 2018 15

Existing View – Exit 56 Toll Plaza

Page 16: Cashless Tolling Informational Meeting

August 7, 2018 16

Proposed View – Exit 56 “In Place” Toll Plaza ~~~oroRK I Thruway ~ aRTUNITY. Authority

Page 17: Cashless Tolling Informational Meeting

August 7, 2018 17

Other Exit Work – Exits 16 and 35

• Exit 16 • Gantry already installed • Kapsch to install equipment• Two lane toll plaza and temporary building to be removed

• Exit 35 • Gantry is included in the Exit 34A and 36 installations• Toll Booth Removal • Reduction of Footprint of Toll Booth Area • Striping• Potential modification to current signage• Tandem Lot access

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 18: Cashless Tolling Informational Meeting

August 7, 2018 18

Exit 35 Interchange

~~,wvoRK I Thruway ~TJR~~NITY. Authority

Page 19: Cashless Tolling Informational Meeting

August 7, 2018 19

KAPSCH (Third Party Involvement) • Work to be performed by Kapsch equipment include: installing electronic sensors on gantry and in-pavement.

Wiring through previously installed conduit communication building to overhead and roadway sensors and up over gantry

• Design-Builder responsible for communication building with foundation, all power, generator, communications and HVAC

• Kapsch will have approximately 6 teams to perform work and will be available to begin installation 4 months after Notice to Proceed. Kapsch will need 30 days for installation and testing. In addition they will need approximately 4 weeks to mobilize per site for shipment of equipment, supplies and staging.

Adesta (Third Party Involvement) • Notification of 2 weeks to splice into the Thruway backbone fiber optic.• Adesta shall require 3 days to do the tie in fiber work.• Adesta shall have x number of work teams available to respond to x locations simultaneously to process the fiber

optic tie ins.• Adesta shall requite 1 week break after completing one location before proceeding to the next location

Utilities

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 20: Cashless Tolling Informational Meeting

August 7, 2018 20

DB Gantry Installation

Kapsch Install Equipment

All Gantries & AET In-Place Installation Complete

Authority 30 Day Testing Go Live

Go Live High Steps

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 21: Cashless Tolling Informational Meeting

August 7, 2018 21

Prior to Cashless Going LiveCashless Tolling in

Place

Cashless Tolling in

Place

Gantry Locations

Gantry Locations

After Cashless Tolling Goes Live

Other Exit Work

Other Exit Work

Work Scope

Background on the basis of what can and can not happen:• Safety• Revenue Security• Congestion (Don’t want to add) 4 wvoRK I Thruway

TEOF • oRTUNITY. Authority

Page 22: Cashless Tolling Informational Meeting

August 7, 2018 22

Brief Discussion on Incentives/Disincentives

• There will be milestone dates• The Thruway would like results better than what will be stated

o Cashless going liveo Toll Plaza removalso Overall completion

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 23: Cashless Tolling Informational Meeting

August 7, 2018 23

Firms Conflicted Out (As of 08/07/2018)• C.V. Associates• SJH Engineering, PC• Popli Architecture and Engineering, L.S., DPC• Shumaker Consulting, Engineering and Land Surveying, PC• WSP• Kapsch• Adesta

4 wvoRK I Thruway TEOF • oRTUNITY. Authority

Page 24: Cashless Tolling Informational Meeting

August 7, 2018 24

Questions?