Case Study on Project Planning for faster construction of ...
Transcript of Case Study on Project Planning for faster construction of ...
Case Study on Project Planning for faster construction of new BG rail line between Kawar &
Maheshmunda stations of E. C. Railway
By
Sitesh Kumar SinghChief Engineer (Construction)/Patna
&
Ashutosh ChourasiaDy. Chief Engineer (Construction)/Dhanbad
East Central RailwayConstruction Department
Brief History
Koderma-Giridih project was sanctioned in 2003 with 102 Route kms.
Due to presence of Coal bed below proposed alignment of project, it was changed from Kawar to Maheshmunda instead of Giridih.
For completion of the project, there was need for faster construction of work from Kawar (Km 94.5) to Maheshmunda (Km 111).
The new alignment was mainly passing through residential and hilly area.
2
Challenges in construction of new lines in hilly terrains
4
No approach roads
Rough weather
Height of work space
Law & order problems
Availability of skilled manpower
Poisonous snakes/insects/bees
Availability of good contractors
Objective & Motivation
5
Ensure quality
• Well defined QAP
• Fabrication at site
• Modern testing lab
Economy & safety
• 50:50 cost sharing
• National project
Speedy construction
• Finalization of tender, drawings etc
• Earth Moving Equipment
• Launching by road crane
Challenges
Ensure QUALITY construction for bridges with reasonably FAST
pace and overcome unforeseen PROBLEMS in the field
Positive contributionProblems faced
Analysis
Remedial measures
Scope of workS. No. Description Quantity
1 Earth cutting 5 lakh cum
2 Rock cutting 1 lakh cum
3 Earth filling 13 lakh cum
4 Blanketing 1 lakh cum
5 Minor bridges 21 nos
6 Major bridges 2 nos
7 Road over bridges 4 nos
8 Road under bridges 10 nos
9 Station buildings
with yards
5 nos
10 Signalling works Involved
11 Electrical works Invoved
6
Note: Aerial video of complete section taken by drone is available at: https://www.youtube.com/watch?v=SZjVsfh2Rt8&t=74s
Major achievements
Full scope of work completed from May’17 to Feb’18 with total contractual expenditure of 150 Crores.
Engine trial was successfully done in March’18.
Commissioner of Railway Safety’s mandatory inspection done in July’18 and authorization for running of trains at 100 kmph (maximum permissible speed) was accorded.
7
Methodology adopted for Execution
• Timely processing of tender with required eligibility criteria
• Timely preparations of L-section, all GADs, designs,drawings
• Suitable selection of location of concrete batching plant &camp office
• Use of Modern facilities in camp office
Organizational Set Up
Railway’s organization
• As work was in progress, 24x7 hrs manning of site was essential, therefore
two SSE/Con/Works/Giridih was posted at Giridih with one Assistant Engineer
& Dy.Chief engineer at Dhanbad under Chief Engineer at headquarter/Patna.
Contractor’s organization
• To maintain the highest level of quality, the contractor’s organization was set
up with 1 Project Director, 3 Project Managers, 1 HR deptt., 2 Accountants, 2
Mechanical Engineers, 1 Store Incharge, 2 Sr. Engineers (Earthwork), Material
Engineer, Sr. Structure Engineer, 1 Lab Technician, Mechanical Foreman, 2
Mechanical Supervisors, 4 Sr. Mechanics, 6 Mechanical helpers, Welders, Lab
helpers, Safety & Security personnel etc.
Concrete Batching Plant
• To ensure timely completion of such a huge concrete work 20m3/hrscapacity batching plant was set up with storage capacity of 25000cement bags.
Use of Advanced Earth Moving Equipment
• For faster progress of earthwork, following advance earthmovingequipment were deployed: 8 nos of Poclains, 2 nos of Graders, 20 nos ofHyvas, 2 nos of Vibro rollers, 2 nos of Dozers, Wagon & Tractor drills etc.
• Use of concrete boom placer
Sequencing of Activities
• Construction of wing walls of bridges takes more time andgenerally done only after deck/top slab construction. In thisproject, wing walls of bridge have been done afterfoundation raft of bridge and it has saved lot of time tofinally get through the bridge for track linking work with drystone backing, backfilling and other activities.
• Sequencing of activities have been planned in a manner sothat through patch is made available for track linking workand just after completion of bridge, track has been laid.
Weekly Meeting with Deputy Commissioners & other state officials
• As work had been immediately started after land acquisition, therewere regular issues like crop compensation, less compensation toland owners etc. which was creating difficulties in work progress andagency was already mobilized as per requirement.
• All issues were sorted out on day to day basis with regularcoordination with state officials and weekly meeting was done withDeputy Commissioner, Giridih to resolve major issue (if any). Eventimely messages to Deputy Commissioner, Giridih has resolved manypetty issues.
• Therefore, regular liasoning with Deputy Commissioner, Giridih &Superintendent of Police, Giridih for law & order related issueshelped in smooth progress of works.
Problems faced and remedial measures
S. No.
Problems faced Remedial measures
1 No approach road New temporary roads were built
2 Rough weather Weather pattern studied & activities planned accordingly
3 Height of work space Local labourers were trained
4 Frequent law & order problems Dedicated Police camps were provided
5 Delay in supply of detonators Alternate sources were arranged
6 Non availability of good contractor locally
Eligibility criteria in Contract provisions need to cater to this aspect
7 Poisonous insects, snakes and bees
Special chemicals arranged alongwith first aid
8 Local festivals Some outside labourers were kept in camps
9 Release of sudden water from Dam intermittently
Regular liasoning with Dam authorities
20
Conclusions
21
Timely processing of tender (including all works) with suitable eligibility criteria is very important
Finalization of L-section, GADs, design etc. before award of tender is a critical item for timely completion of the project
Use of advance construction equipment like heavy earthmoving machines, Concrete batching plant with Ready Mix concrete, Concrete Boom placer are very helpful for expeditious work
Conclusions contd..
22
Suitable selection of camp office and concrete batching plant with ready mix concrete is key factor to monitor the concrete quality as per the requirement
For long lead works, locally available manpower may be trained to carry out skilled jobs.
At militant infested work sites, it is better to arrange police camps in advance for smooth progress of work.
Special chemicals under skilled supervision can be used to tackle problems of poisonous snakes/insects/bees.
Conclusions contd..
23
Adequate organizational set up of client as per as contractor is key to monitor day to day work as well quality
Regular liasoning with district administration is very helpful to resolve day to day issues