Case Study of Two MBCx Projects - Texas A&M University
Transcript of Case Study of Two MBCx Projects - Texas A&M University
Case Study of Two MBCx Projects:Using M&V to Track Energy Performance
David Jump, Ph.D., P.E.Quantum Energy Services & Technologies, Inc.
ICEBO, November 1, 2007
2
Overview
This presentation will discuss:Role of M&V in RCxApplication in two UC Berkeley BuildingsResultsDiscussion & Conclusion
3
Situation• RCx is a means to improve a building’s energy efficiency
OwnersEE Programs
• “RCx Measures”Correct and optimize system operations
• Operational changes• Control system changes
Justification provided by measure cost-effectiveness
• RCx measure recommendations based on savings estimates
4
Situation• RCx measure savings estimates are based on:
Design documentationEquipment specificationsMonitored operational data
• Independent data loggers• Control system trends
Bin models, engineering models, computer simulations, etc.
• Do savings estimates = “real” savings?Model errorsIncomplete or inaccurate dataIncorrect assumptionsEtc.
5
SituationRisks to Owner:
Savings not delivered, no return on investmentNo ability to track actual savingsSavings do not last:
• “Soft” measures that can be and often are defeatedEE Program Risks:
Program’s claimed savings do not stand up to third party reviewSavings lifetimes are shortNegative impact on program realization rates
6
Need for Robust M&V in RCx ProjectsNeeds:• Demonstrate actual, verified energy savings benefits of RCx• Provide a mechanism to determine measure savings
persistence
Opportunities:• Standardization of M&V processes for RCx
California Commissioning Collaborative Project• Provide information tools for operators and owners to
maintain savings• Basis for further energy performance improvements
7
Basic M&V
International Performance Measurement and Verification Protocol (IPMVP) Chapter 3 says:
Energy Savings = Baseyear Energy Use – Post-Retrofit Energy Use ± Adjustments
• Baseline energy use is modeled• Model generates what baseline use would have been
under post-install conditions • ‘Adjusted baseline’ is compared with measured use to
generate savings
8
0
100
200
300
400
500
600
700
Jan-0
5
Jan-0
6
Jan-0
7
Jan-0
8
Jan-0
9
Jan-1
0kW
kWactual kWbaseline
Baseline Period
Post-Installation Period
Quantifying Savings
Verified savings are based on energy measurements before and after improvements
Savings estimates are based on data collected in baseline period
9
IPMVP M&V OptionsRetrofit Isolation Options:• Option A: Allows stipulation of some parameters• Option B: Retrofit isolation – continuous monitoring of parameters
Focus is on systems and equipment – similar to RCx.
Whole Building Options:• Option C: Utility bill analysis• Option D: Calibrated computer simulation
Sometimes used with isolated systems, as applicable• Used when savings distinguishable from variation in use (typ. >15%)
• Option B selected for UC Berkeley Magnifies savings as a proportion of use+ addresses savings persistence, provides tracking toolsTechnique also applied at whole-building level
10
UC Berkeley MBCx Project
• UC Berkeley has significant monitoring resources to devote to this project
Web-based utility information system• Whole building kW and steam meters• Electric and steam trended at 15 minute intervals• Data stored indefinitely
Web-based points mapped from BAS• Chiller kW• BAS points trended at 1 minute intervals• Data stored for 6 months
11
Soda Hall• UC Berkeley’s Computer Science Department (24/7 operation)• 109,000 ft2
• Energy Use Intensity: 174 kBtu/ft2-yr • 2 - 215 ton chillers (lead/lag)• Constant Speed Primary/Variable Speed Secondary Chilled Water
System• Two 2-speed, forced draft, open loop cooling towers• 3 Main VAV AHUs,
AHU1 serves building core, AHUs 3 and 4 serve the perimeter, with hot water reheat
• 11 computer room DX units, water cooled with variable speed pumps• Steam to hot water heat exchanger, 2 variable speed HW pumps
12
Soda Hall RCx Findings• Minimum VAV Box Damper Positions at 50%
Causes excessive reheat in perimeter zonesLittle modulation of fan VFD
• Several AHU VFDs broken or not modulatingReturn to designed VAV operationReturn to scheduled operation
• Re-establish supply air temperature set point reset control in AHU1
• Other measures
• Approximately 483,000 kWh (10%), 2.7M lbs/yr steam (51%)Estimated using DOE2 analysis
• Cost reduction $84,000 (14%), Payback 0.7 years
13
Soda Hall Affected SystemsSystem Equipment Affected
by ECM?Available Points
XMain Electric Meters (2) kWMain Steam Meters (2) lb
XChillers 1 and 2 kWPrimary Chilled Water Pumps P-5, P-6 StatusSecondary Chilled Water Pumps, P-3, P-4 VFD speed
XCooling Towers High/Low StatusCondenser Water Pumps P-7, P-8 Status
XAHU-1, SF-11, EF-12, EF-13 VFD speedAHU-2, SF-14, EF-15 StatusAHU-3, SF-16, SF-17 VFD speedAHU-4, SF-18, SF-19 VFD speedAHU-5, SF-20 Status
Chiller Room 181, SF-2, EF-2 StatusChiller Room 179, SF-3A, SF-3B, EF-1A, EF-1B Status
AC UnitsCondenser Water Pumps P-9, P-10 VFD speedAC-31 through AC-41 Status
XHot Water Pumps P-1, P-2 VFD Speed
Hot Water System
Whole Building
Condenser Water System
Chilled Water System
Air Distribution System
Chiller Room Fans
14
Define the Baseline Period & Collect Data
• 8 months of trended data collected• Baseline period selected to cover widest range of operating
conditions ~ 3 months.
• Energy use for each system to be totaled each dayBasis for analysis and reporting
• “Proxy” Variables on EMCS:Constant load equipment: measure operating kW
• Equipment status becomes proxy for kW Variable load equipment: log kW and VFD speed
• VFD speed signal becomes proxy for kW
15
“Proxy” Variable: VFD speed for kW
0
5
10
15
20
25
30
35
0 20 40 60 80 100 120
AHU-1 Fan Speed %
AH
U-1
Fan
kW
Actual Cubic polynomial
16
M&V “Diagnostics”Soda Hall
0
100
200
300
400
500
600
700
800
900
1,000
1/1/20
061/3
/2006
1/5/20
061/7
/2006
1/9/20
061/1
1/200
61/1
3/200
61/1
5/200
61/1
7/200
61/1
9/200
61/2
1/200
61/2
3/200
61/2
5/200
61/2
7/200
61/2
9/200
61/3
1/200
62/2
/2006
2/4/20
062/6
/2006
2/8/20
062/1
0/200
62/1
2/200
62/1
4/200
62/1
6/200
62/1
8/200
62/2
0/200
62/2
2/200
62/2
4/200
62/2
6/200
62/2
8/200
63/2
/2006
3/4/20
063/6
/2006
3/8/20
063/1
0/200
63/1
2/200
63/1
4/200
63/1
6/200
63/1
8/200
63/2
0/200
63/2
2/200
63/2
4/200
63/2
6/200
63/2
8/200
63/3
0/200
6
Date
kWh
0
10
20
30
40
50
60
70
80
Deg
F
AHU 1 Daily kWh AHU 3 Daily kWh AHU 4 Daily kWh OAT Daily Average
AHU 1 supply fan malf. begins here. Same date as economizer fix.
17
M&V DiagnosticsSoda Hall
0
100
200
300
400
500
600
700
800
900
1,000
4/1/20
064/3
/2006
4/5/20
064/7
/2006
4/9/20
064/1
1/200
64/1
3/200
64/1
5/200
64/1
7/200
64/1
9/200
64/2
1/200
64/2
3/200
64/2
5/200
64/2
7/200
64/2
9/200
65/1
/2006
5/3/20
065/5
/2006
5/7/20
065/9
/2006
5/11/2
006
5/13/2
006
5/15/2
006
5/17/2
006
5/19/2
006
5/21/2
006
5/23/2
006
5/25/2
006
5/27/2
006
5/29/2
006
5/31/2
006
6/2/20
066/4
/2006
6/6/20
066/8
/2006
6/10/2
006
6/12/2
006
6/14/2
006
6/16/2
006
6/18/2
006
6/20/2
006
6/22/2
006
6/24/2
006
6/26/2
006
6/28/2
006
6/30/2
006
7/2/20
067/4
/2006
Date
kWh
0
10
20
30
40
50
60
70
80
Deg
F
AHU 1 Daily kWh AHU 3 Daily kWh AHU 4 Daily kWh OAT Daily Average
VAV box implementation begins
VAV box implementation complete
18
Baseline Model: Soda Hall• Total Building Electric Building Steam
• Peak Period Electric HVAC System Electric
19
Soda Hall M&V: HVAC Systems
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
2/9/20
062/1
1/200
62/1
3/200
62/1
5/200
62/1
7/200
62/1
9/200
62/2
1/200
62/2
3/200
62/2
5/200
62/2
7/200
63/1
/2006
3/3/20
063/5
/2006
3/7/20
0610
/31/20
0611
/2/20
0611
/4/20
0611
/6/20
0611
/8/20
0611
/10/20
0611
/12/20
0611
/14/20
0611
/16/20
0611
/18/20
0611
/20/20
0611
/22/20
0611
/24/20
0611
/26/20
0611
/28/20
06
Date
Dai
ly k
Wh
Use
HVAC Daily kWh Usage Baseline Post-Install Model
Date Break
Baseline Model:kWh = 79.9*OAT + 1129RMSE = 136 kWh
Baseline Period Post-Installation Period
Post-Install Model:kWh = 44.1*OAT - 336RMSE = 213 kWh
20
Soda Hall: Estimated vs. Verified Savings
Whole Building HVAC SystemkWh 483,008 216,716 462,472kW - 22 50Lbs. Steam 2,713,650 854,407* based on eQUEST model** based on baseline and post-installation measurements and TMY OAT data
Verified Savings**Source Estimated
Savings*
21
Tan Hall• UC Berkeley’s Chemistry and Chemical Engineering
Departments• 7 above-grade, 2 below-grade levels• 106,000 ft2
• 100% outside air through 4 VFD-controlled 100 HP supply fans
• Steam heating and CHW cooling coils in AHU• Separate exhaust system on roof: 4 VFD-controlled 60 HP
exhaust fans• 1 475-ton chiller, constant speed primary loop• Constant speed CW loop – Tower shared among buildings• Steam-to HW HX system, circulated to perimeter zone boxes
22
Tan Hall RCx Findings
• Chilled water and condenser water pumps operating in parallel instead of lead/lag
Balancing vales on each were closed downShut off one pump, rebalance flow and operate in lead/lag mode as intended
• Chiller outside air lockout temperature sequence not functioningOAT set point also too highCorrect operation and lower set point 2 °F
• Leaky steam valve in AHU – caused simultaneous heating and cooling
• Savings: 654,000 kWh (14%), 90 kW, 10.5 M lbs steam (62%)Estimated using bin analysis
• Cost reduction $154,000 (19%), Payback 0.02 years
23
Tan Hall Affected SystemsSystem Equipment Affected by
ECM?Available
PointsX
Main 480/277 Electric Meter kWMain 220/110 Electric Meter kWMain Steam Meter lbs/hr
XChiller (VS) kWPrimary Chilled Water Pumps CHWP-1, CHWP-2 (CS) Status
XCondenser Water Pumps CDWP-1, CDWP-2 (CS) StatusCooling Tower (CS, 2-speed) Not Avail.
AHU-3 XAHU-3 Supply Fans SF-1, SF-2, SF-3, SF-4 (CS) S/S & SpeedAHU-3 Exhaust Fans EF-1, EF-2, EF-3, EF-4 (CS) S/S & SpeedTerminal Boxes and Fume Hoods associated with AHU-3 NA
AHU-1AHU-1 Chemical Storage AH-1, SE-1 Status
AHU-2AHU-2 Chemical Storage AH-2, SE-2 Status
XHeat Exchanger HWC-1Hot Water Pumps HHWP-1, HHWP-2 Status
Lighting Circuits NAPlug Loads
Plug Load Circuits NA
Domestic Water Pumps NA
Whole Building
Chilled Water System
Condenser Water System
Heating Water System
Lighting System
Domestic Water
24
Tan Hall Diagnostics
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
1/1/20
061/3
/2006
1/5/20
061/7
/2006
1/9/20
061/1
1/200
61/1
3/200
61/1
5/200
61/1
7/200
61/1
9/200
61/2
1/200
61/2
3/200
61/2
5/200
61/2
7/200
61/2
9/200
61/3
1/200
62/2
/2006
2/4/20
062/6
/2006
2/8/20
062/1
0/200
62/1
2/200
62/1
4/200
62/1
6/200
62/1
8/200
62/2
0/200
62/2
2/200
62/2
4/200
62/2
6/200
62/2
8/200
63/2
/2006
3/4/20
063/6
/2006
3/8/20
063/1
0/200
63/1
2/200
63/1
4/200
63/1
6/200
63/1
8/200
63/2
0/200
63/2
2/200
63/2
4/200
63/2
6/200
63/2
8/200
63/3
0/200
6
Date
Dai
ly k
Wh
0
10
20
30
40
50
60
70
80
Deg
. F
AHU-3 Supply Fans Avg. Daily Temp.
25
Tan Hall Diagnostics – cont.
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4/1/20
064/3
/2006
4/5/20
064/7
/2006
4/9/20
064/1
1/200
64/1
3/200
64/1
5/200
64/1
7/200
64/1
9/200
64/2
1/200
64/2
3/200
64/2
5/200
64/2
7/200
64/2
9/200
65/1
/2006
5/3/20
065/5
/2006
5/7/20
065/9
/2006
5/11/2
006
5/13/2
006
5/15/2
006
5/17/2
006
5/19/2
006
5/21/2
006
5/23/2
006
5/25/2
006
5/27/2
006
5/29/2
006
5/31/2
006
6/2/20
066/4
/2006
6/6/20
066/8
/2006
6/10/2
006
6/12/2
006
6/14/2
006
6/16/2
006
6/18/2
006
6/20/2
006
6/22/2
006
6/24/2
006
6/26/2
006
Date
Dai
ly k
Wh
0
10
20
30
40
50
60
70
80
Deg
. F
AHU-3 Supply Fans Avg. Daily Temp.
Measures Implemented
SF-1 Fails. The other fans ramp up to meet setpoint.
SF-1 repaired. Fans return to normal operation.
Prefilters and bags changed.
26
M&V Models: Tan Hall
Whole Building Electric Whole Building Steam
Peak Period Electric Chilled Water System Electric
27
Tan Hall M&V: Whole-Building Electric
0
5,000
10,000
15,000
20,000
25,000
6/1/2006 6/3/2006 6/5/2006 6/7/2006 6/9/2006 6/11/2006 6/13/2006 6/15/2006 6/17/2006 6/19/2006 6/21/2006 6/23/2006 6/25/2006
Date
Dai
ly k
Wh
0
10
20
30
40
50
60
70
80
Deg
. F
Total Building Daily kWh Average Daily Outside Air Temperature Baseline New Baseline
Baseline ModelR2 = 0.75RMSE = 581 kWh
New BaselineR2 = 0.88RMSE = 438 kWh
28
Tan Hall M&V: Whole-Building Steam
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
6/1/2006 6/3/2006 6/5/2006 6/7/2006 6/9/2006 6/11/2006 6/13/2006 6/15/2006 6/17/2006 6/19/2006 6/21/2006 6/23/2006 6/25/2006
Date
Dai
ly S
team
lbs
0
10
20
30
40
50
60
70
80
Deg
. F
Steam Baseline New Baseline Average Daily Outside Air Temperature
New Baseline
Baseline Model
29
Tan Hall M&V: Chilled Water System
0
1,000
2,000
3,000
4,000
5,000
6,000
6/1/2006 6/3/2006 6/5/2006 6/7/2006 6/9/2006 6/11/2006 6/13/2006 6/15/2006 6/17/2006 6/19/2006 6/21/2006 6/23/2006 6/25/2006
Date
Dai
ly k
Wh
0
10
20
30
40
50
60
70
80
Deg
. F
Chilled Water System Average Daily Outside Air Temperature Baseline New Baseline
New BaselineR2 = 0.95RMSE = 251 kWh
Baseline ModelR2 = 0.87RMSE = 486 kWh
30
Tan Hall: Estimated vs. Verified Savings
Whole Building CHW SystemkWh 653,575 663,184 686,519kW 91 69Lbs. Steam 10,543,991 5,995,232* based on engineering calculations** based on baseline and post-installation measurements and TMY OAT data
Verified Savings**Source Estimated
Savings*
31
Costs
Soda Hall 4,442$ 62,160$ 51,087$ 117,689$ Tan Hall 22,573$ 53,000$ 15,300$ 90,873$
Building Metering Costs
MBCx Agent Costs
In-House Costs Total
• Including all costs, project remains cost-effective:Soda Hall: 1.7 year paybackTan Hall: 0.7 year payback
• Added costs of metering hardware and software did not overburden project’s costs
• In private sector – metering costs lowerExisting electric metersSophisticated BAS systemsMBCx approach should be viable
32
Discussion
• Consider new approach:Focus project resources on verified savings instead of estimated savings approach
• More rigorous savings analysis, more reliable results
• Install all low-cost measures • Estimate savings for only higher cost measures• Leave in place capability to track & tally savings• Diagnostic benefits of approach• Addresses savings persistence
• BarrierLack of understanding of M&VM&V training required
33
Conclusion• Soda & Tan Hall projects showed technique to integrate M&V
into RCx• Technique as tools:
Diagnostic capability, Verify savings, track energy use
• Other benefitsPersistence of RCx savingsLess uncertainty in savings Establish new baselines for next project
34
Related WorkM&V Guidelines:• Energy Valuation Organization’s International Performance
Measurement and Verification Protocol (IPMVP)New 2007 release available now at: www.evo-world.org
• ASHRAE Guideline 14: www.ashrae.org
• California Commissioning Collaborative: Verification of Savings Project
Review current M&V methods within RCx projectsRecommend best practices for M&V in RCxDisseminate results