Case Study of Two MBCx Projects - Texas A&M University

34
Case Study of Two MBCx Projects: Using M&V to Track Energy Performance David Jump, Ph.D., P.E. Quantum Energy Services & Technologies, Inc. ICEBO, November 1, 2007

Transcript of Case Study of Two MBCx Projects - Texas A&M University

Case Study of Two MBCx Projects:Using M&V to Track Energy Performance

David Jump, Ph.D., P.E.Quantum Energy Services & Technologies, Inc.

ICEBO, November 1, 2007

2

Overview

This presentation will discuss:Role of M&V in RCxApplication in two UC Berkeley BuildingsResultsDiscussion & Conclusion

3

Situation• RCx is a means to improve a building’s energy efficiency

OwnersEE Programs

• “RCx Measures”Correct and optimize system operations

• Operational changes• Control system changes

Justification provided by measure cost-effectiveness

• RCx measure recommendations based on savings estimates

4

Situation• RCx measure savings estimates are based on:

Design documentationEquipment specificationsMonitored operational data

• Independent data loggers• Control system trends

Bin models, engineering models, computer simulations, etc.

• Do savings estimates = “real” savings?Model errorsIncomplete or inaccurate dataIncorrect assumptionsEtc.

5

SituationRisks to Owner:

Savings not delivered, no return on investmentNo ability to track actual savingsSavings do not last:

• “Soft” measures that can be and often are defeatedEE Program Risks:

Program’s claimed savings do not stand up to third party reviewSavings lifetimes are shortNegative impact on program realization rates

6

Need for Robust M&V in RCx ProjectsNeeds:• Demonstrate actual, verified energy savings benefits of RCx• Provide a mechanism to determine measure savings

persistence

Opportunities:• Standardization of M&V processes for RCx

California Commissioning Collaborative Project• Provide information tools for operators and owners to

maintain savings• Basis for further energy performance improvements

7

Basic M&V

International Performance Measurement and Verification Protocol (IPMVP) Chapter 3 says:

Energy Savings = Baseyear Energy Use – Post-Retrofit Energy Use ± Adjustments

• Baseline energy use is modeled• Model generates what baseline use would have been

under post-install conditions • ‘Adjusted baseline’ is compared with measured use to

generate savings

8

0

100

200

300

400

500

600

700

Jan-0

5

Jan-0

6

Jan-0

7

Jan-0

8

Jan-0

9

Jan-1

0kW

kWactual kWbaseline

Baseline Period

Post-Installation Period

Quantifying Savings

Verified savings are based on energy measurements before and after improvements

Savings estimates are based on data collected in baseline period

9

IPMVP M&V OptionsRetrofit Isolation Options:• Option A: Allows stipulation of some parameters• Option B: Retrofit isolation – continuous monitoring of parameters

Focus is on systems and equipment – similar to RCx.

Whole Building Options:• Option C: Utility bill analysis• Option D: Calibrated computer simulation

Sometimes used with isolated systems, as applicable• Used when savings distinguishable from variation in use (typ. >15%)

• Option B selected for UC Berkeley Magnifies savings as a proportion of use+ addresses savings persistence, provides tracking toolsTechnique also applied at whole-building level

10

UC Berkeley MBCx Project

• UC Berkeley has significant monitoring resources to devote to this project

Web-based utility information system• Whole building kW and steam meters• Electric and steam trended at 15 minute intervals• Data stored indefinitely

Web-based points mapped from BAS• Chiller kW• BAS points trended at 1 minute intervals• Data stored for 6 months

11

Soda Hall• UC Berkeley’s Computer Science Department (24/7 operation)• 109,000 ft2

• Energy Use Intensity: 174 kBtu/ft2-yr • 2 - 215 ton chillers (lead/lag)• Constant Speed Primary/Variable Speed Secondary Chilled Water

System• Two 2-speed, forced draft, open loop cooling towers• 3 Main VAV AHUs,

AHU1 serves building core, AHUs 3 and 4 serve the perimeter, with hot water reheat

• 11 computer room DX units, water cooled with variable speed pumps• Steam to hot water heat exchanger, 2 variable speed HW pumps

12

Soda Hall RCx Findings• Minimum VAV Box Damper Positions at 50%

Causes excessive reheat in perimeter zonesLittle modulation of fan VFD

• Several AHU VFDs broken or not modulatingReturn to designed VAV operationReturn to scheduled operation

• Re-establish supply air temperature set point reset control in AHU1

• Other measures

• Approximately 483,000 kWh (10%), 2.7M lbs/yr steam (51%)Estimated using DOE2 analysis

• Cost reduction $84,000 (14%), Payback 0.7 years

13

Soda Hall Affected SystemsSystem Equipment Affected

by ECM?Available Points

XMain Electric Meters (2) kWMain Steam Meters (2) lb

XChillers 1 and 2 kWPrimary Chilled Water Pumps P-5, P-6 StatusSecondary Chilled Water Pumps, P-3, P-4 VFD speed

XCooling Towers High/Low StatusCondenser Water Pumps P-7, P-8 Status

XAHU-1, SF-11, EF-12, EF-13 VFD speedAHU-2, SF-14, EF-15 StatusAHU-3, SF-16, SF-17 VFD speedAHU-4, SF-18, SF-19 VFD speedAHU-5, SF-20 Status

Chiller Room 181, SF-2, EF-2 StatusChiller Room 179, SF-3A, SF-3B, EF-1A, EF-1B Status

AC UnitsCondenser Water Pumps P-9, P-10 VFD speedAC-31 through AC-41 Status

XHot Water Pumps P-1, P-2 VFD Speed

Hot Water System

Whole Building

Condenser Water System

Chilled Water System

Air Distribution System

Chiller Room Fans

14

Define the Baseline Period & Collect Data

• 8 months of trended data collected• Baseline period selected to cover widest range of operating

conditions ~ 3 months.

• Energy use for each system to be totaled each dayBasis for analysis and reporting

• “Proxy” Variables on EMCS:Constant load equipment: measure operating kW

• Equipment status becomes proxy for kW Variable load equipment: log kW and VFD speed

• VFD speed signal becomes proxy for kW

15

“Proxy” Variable: VFD speed for kW

0

5

10

15

20

25

30

35

0 20 40 60 80 100 120

AHU-1 Fan Speed %

AH

U-1

Fan

kW

Actual Cubic polynomial

16

M&V “Diagnostics”Soda Hall

0

100

200

300

400

500

600

700

800

900

1,000

1/1/20

061/3

/2006

1/5/20

061/7

/2006

1/9/20

061/1

1/200

61/1

3/200

61/1

5/200

61/1

7/200

61/1

9/200

61/2

1/200

61/2

3/200

61/2

5/200

61/2

7/200

61/2

9/200

61/3

1/200

62/2

/2006

2/4/20

062/6

/2006

2/8/20

062/1

0/200

62/1

2/200

62/1

4/200

62/1

6/200

62/1

8/200

62/2

0/200

62/2

2/200

62/2

4/200

62/2

6/200

62/2

8/200

63/2

/2006

3/4/20

063/6

/2006

3/8/20

063/1

0/200

63/1

2/200

63/1

4/200

63/1

6/200

63/1

8/200

63/2

0/200

63/2

2/200

63/2

4/200

63/2

6/200

63/2

8/200

63/3

0/200

6

Date

kWh

0

10

20

30

40

50

60

70

80

Deg

F

AHU 1 Daily kWh AHU 3 Daily kWh AHU 4 Daily kWh OAT Daily Average

AHU 1 supply fan malf. begins here. Same date as economizer fix.

17

M&V DiagnosticsSoda Hall

0

100

200

300

400

500

600

700

800

900

1,000

4/1/20

064/3

/2006

4/5/20

064/7

/2006

4/9/20

064/1

1/200

64/1

3/200

64/1

5/200

64/1

7/200

64/1

9/200

64/2

1/200

64/2

3/200

64/2

5/200

64/2

7/200

64/2

9/200

65/1

/2006

5/3/20

065/5

/2006

5/7/20

065/9

/2006

5/11/2

006

5/13/2

006

5/15/2

006

5/17/2

006

5/19/2

006

5/21/2

006

5/23/2

006

5/25/2

006

5/27/2

006

5/29/2

006

5/31/2

006

6/2/20

066/4

/2006

6/6/20

066/8

/2006

6/10/2

006

6/12/2

006

6/14/2

006

6/16/2

006

6/18/2

006

6/20/2

006

6/22/2

006

6/24/2

006

6/26/2

006

6/28/2

006

6/30/2

006

7/2/20

067/4

/2006

Date

kWh

0

10

20

30

40

50

60

70

80

Deg

F

AHU 1 Daily kWh AHU 3 Daily kWh AHU 4 Daily kWh OAT Daily Average

VAV box implementation begins

VAV box implementation complete

18

Baseline Model: Soda Hall• Total Building Electric Building Steam

• Peak Period Electric HVAC System Electric

19

Soda Hall M&V: HVAC Systems

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

2/9/20

062/1

1/200

62/1

3/200

62/1

5/200

62/1

7/200

62/1

9/200

62/2

1/200

62/2

3/200

62/2

5/200

62/2

7/200

63/1

/2006

3/3/20

063/5

/2006

3/7/20

0610

/31/20

0611

/2/20

0611

/4/20

0611

/6/20

0611

/8/20

0611

/10/20

0611

/12/20

0611

/14/20

0611

/16/20

0611

/18/20

0611

/20/20

0611

/22/20

0611

/24/20

0611

/26/20

0611

/28/20

06

Date

Dai

ly k

Wh

Use

HVAC Daily kWh Usage Baseline Post-Install Model

Date Break

Baseline Model:kWh = 79.9*OAT + 1129RMSE = 136 kWh

Baseline Period Post-Installation Period

Post-Install Model:kWh = 44.1*OAT - 336RMSE = 213 kWh

20

Soda Hall: Estimated vs. Verified Savings

Whole Building HVAC SystemkWh 483,008 216,716 462,472kW - 22 50Lbs. Steam 2,713,650 854,407* based on eQUEST model** based on baseline and post-installation measurements and TMY OAT data

Verified Savings**Source Estimated

Savings*

21

Tan Hall• UC Berkeley’s Chemistry and Chemical Engineering

Departments• 7 above-grade, 2 below-grade levels• 106,000 ft2

• 100% outside air through 4 VFD-controlled 100 HP supply fans

• Steam heating and CHW cooling coils in AHU• Separate exhaust system on roof: 4 VFD-controlled 60 HP

exhaust fans• 1 475-ton chiller, constant speed primary loop• Constant speed CW loop – Tower shared among buildings• Steam-to HW HX system, circulated to perimeter zone boxes

22

Tan Hall RCx Findings

• Chilled water and condenser water pumps operating in parallel instead of lead/lag

Balancing vales on each were closed downShut off one pump, rebalance flow and operate in lead/lag mode as intended

• Chiller outside air lockout temperature sequence not functioningOAT set point also too highCorrect operation and lower set point 2 °F

• Leaky steam valve in AHU – caused simultaneous heating and cooling

• Savings: 654,000 kWh (14%), 90 kW, 10.5 M lbs steam (62%)Estimated using bin analysis

• Cost reduction $154,000 (19%), Payback 0.02 years

23

Tan Hall Affected SystemsSystem Equipment Affected by

ECM?Available

PointsX

Main 480/277 Electric Meter kWMain 220/110 Electric Meter kWMain Steam Meter lbs/hr

XChiller (VS) kWPrimary Chilled Water Pumps CHWP-1, CHWP-2 (CS) Status

XCondenser Water Pumps CDWP-1, CDWP-2 (CS) StatusCooling Tower (CS, 2-speed) Not Avail.

AHU-3 XAHU-3 Supply Fans SF-1, SF-2, SF-3, SF-4 (CS) S/S & SpeedAHU-3 Exhaust Fans EF-1, EF-2, EF-3, EF-4 (CS) S/S & SpeedTerminal Boxes and Fume Hoods associated with AHU-3 NA

AHU-1AHU-1 Chemical Storage AH-1, SE-1 Status

AHU-2AHU-2 Chemical Storage AH-2, SE-2 Status

XHeat Exchanger HWC-1Hot Water Pumps HHWP-1, HHWP-2 Status

Lighting Circuits NAPlug Loads

Plug Load Circuits NA

Domestic Water Pumps NA

Whole Building

Chilled Water System

Condenser Water System

Heating Water System

Lighting System

Domestic Water

24

Tan Hall Diagnostics

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

1/1/20

061/3

/2006

1/5/20

061/7

/2006

1/9/20

061/1

1/200

61/1

3/200

61/1

5/200

61/1

7/200

61/1

9/200

61/2

1/200

61/2

3/200

61/2

5/200

61/2

7/200

61/2

9/200

61/3

1/200

62/2

/2006

2/4/20

062/6

/2006

2/8/20

062/1

0/200

62/1

2/200

62/1

4/200

62/1

6/200

62/1

8/200

62/2

0/200

62/2

2/200

62/2

4/200

62/2

6/200

62/2

8/200

63/2

/2006

3/4/20

063/6

/2006

3/8/20

063/1

0/200

63/1

2/200

63/1

4/200

63/1

6/200

63/1

8/200

63/2

0/200

63/2

2/200

63/2

4/200

63/2

6/200

63/2

8/200

63/3

0/200

6

Date

Dai

ly k

Wh

0

10

20

30

40

50

60

70

80

Deg

. F

AHU-3 Supply Fans Avg. Daily Temp.

25

Tan Hall Diagnostics – cont.

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4/1/20

064/3

/2006

4/5/20

064/7

/2006

4/9/20

064/1

1/200

64/1

3/200

64/1

5/200

64/1

7/200

64/1

9/200

64/2

1/200

64/2

3/200

64/2

5/200

64/2

7/200

64/2

9/200

65/1

/2006

5/3/20

065/5

/2006

5/7/20

065/9

/2006

5/11/2

006

5/13/2

006

5/15/2

006

5/17/2

006

5/19/2

006

5/21/2

006

5/23/2

006

5/25/2

006

5/27/2

006

5/29/2

006

5/31/2

006

6/2/20

066/4

/2006

6/6/20

066/8

/2006

6/10/2

006

6/12/2

006

6/14/2

006

6/16/2

006

6/18/2

006

6/20/2

006

6/22/2

006

6/24/2

006

6/26/2

006

Date

Dai

ly k

Wh

0

10

20

30

40

50

60

70

80

Deg

. F

AHU-3 Supply Fans Avg. Daily Temp.

Measures Implemented

SF-1 Fails. The other fans ramp up to meet setpoint.

SF-1 repaired. Fans return to normal operation.

Prefilters and bags changed.

26

M&V Models: Tan Hall

Whole Building Electric Whole Building Steam

Peak Period Electric Chilled Water System Electric

27

Tan Hall M&V: Whole-Building Electric

0

5,000

10,000

15,000

20,000

25,000

6/1/2006 6/3/2006 6/5/2006 6/7/2006 6/9/2006 6/11/2006 6/13/2006 6/15/2006 6/17/2006 6/19/2006 6/21/2006 6/23/2006 6/25/2006

Date

Dai

ly k

Wh

0

10

20

30

40

50

60

70

80

Deg

. F

Total Building Daily kWh Average Daily Outside Air Temperature Baseline New Baseline

Baseline ModelR2 = 0.75RMSE = 581 kWh

New BaselineR2 = 0.88RMSE = 438 kWh

28

Tan Hall M&V: Whole-Building Steam

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

6/1/2006 6/3/2006 6/5/2006 6/7/2006 6/9/2006 6/11/2006 6/13/2006 6/15/2006 6/17/2006 6/19/2006 6/21/2006 6/23/2006 6/25/2006

Date

Dai

ly S

team

lbs

0

10

20

30

40

50

60

70

80

Deg

. F

Steam Baseline New Baseline Average Daily Outside Air Temperature

New Baseline

Baseline Model

29

Tan Hall M&V: Chilled Water System

0

1,000

2,000

3,000

4,000

5,000

6,000

6/1/2006 6/3/2006 6/5/2006 6/7/2006 6/9/2006 6/11/2006 6/13/2006 6/15/2006 6/17/2006 6/19/2006 6/21/2006 6/23/2006 6/25/2006

Date

Dai

ly k

Wh

0

10

20

30

40

50

60

70

80

Deg

. F

Chilled Water System Average Daily Outside Air Temperature Baseline New Baseline

New BaselineR2 = 0.95RMSE = 251 kWh

Baseline ModelR2 = 0.87RMSE = 486 kWh

30

Tan Hall: Estimated vs. Verified Savings

Whole Building CHW SystemkWh 653,575 663,184 686,519kW 91 69Lbs. Steam 10,543,991 5,995,232* based on engineering calculations** based on baseline and post-installation measurements and TMY OAT data

Verified Savings**Source Estimated

Savings*

31

Costs

Soda Hall 4,442$ 62,160$ 51,087$ 117,689$ Tan Hall 22,573$ 53,000$ 15,300$ 90,873$

Building Metering Costs

MBCx Agent Costs

In-House Costs Total

• Including all costs, project remains cost-effective:Soda Hall: 1.7 year paybackTan Hall: 0.7 year payback

• Added costs of metering hardware and software did not overburden project’s costs

• In private sector – metering costs lowerExisting electric metersSophisticated BAS systemsMBCx approach should be viable

32

Discussion

• Consider new approach:Focus project resources on verified savings instead of estimated savings approach

• More rigorous savings analysis, more reliable results

• Install all low-cost measures • Estimate savings for only higher cost measures• Leave in place capability to track & tally savings• Diagnostic benefits of approach• Addresses savings persistence

• BarrierLack of understanding of M&VM&V training required

33

Conclusion• Soda & Tan Hall projects showed technique to integrate M&V

into RCx• Technique as tools:

Diagnostic capability, Verify savings, track energy use

• Other benefitsPersistence of RCx savingsLess uncertainty in savings Establish new baselines for next project

34

Related WorkM&V Guidelines:• Energy Valuation Organization’s International Performance

Measurement and Verification Protocol (IPMVP)New 2007 release available now at: www.evo-world.org

• ASHRAE Guideline 14: www.ashrae.org

• California Commissioning Collaborative: Verification of Savings Project

Review current M&V methods within RCx projectsRecommend best practices for M&V in RCxDisseminate results