Case study of a temporary sports hall

23
Please contact [email protected] or 07966 462460 for more details, thank you Project to install a ‘temporary’ Sports Hall - a case study by Bees Marquees & Structures This particular sports hall available from March 2015! Rental or purchase - 1 careful owner, only 2 years old! Viewings available by appointment; highly competitive deal waiting to be negotiated!

description

This is a summary of a project to design and install a 20m x 35m temporary sports hall for an academy school. This structure is on rental/lease for 2 years but we also offer such structures, almost as large as required, in a variety of designs including timber frame, for sale/purchase. We also installed lighting, heating, changing rooms, reception and transferred the vinyl non slip safety sports floor from a building whilst this hall is in use (during the 2 year construction project to build the new bricks-hall)

Transcript of Case study of a temporary sports hall

Page 1: Case study of a temporary sports hall

Please contact [email protected] or 07966 462460 for more details, thank you

Project to install a ‘temporary’ Sports Hall- a case study by Bees Marquees & Structures

This particular sports hall available from March 2015! Rental or purchase - 1 careful owner, only 2 years old!

Viewings available by appointment;

highly competitive deal waiting to be negotiated!

Page 2: Case study of a temporary sports hall

The need: a school sports hall, built 45 years ago and designed for a 30 year lifespan began to deteriorate. Plans were made to replace it with a new building but whilst planning permission (and funding) was still being considered, the building was deemed no longer safe for use. Our project to provide a temporary sports hall in the meantime was commissioned, with upto 2 years’ usage in mind … although there are similar structures installed elsewhere for 10 times that, so these structures are only as ‘temporary’ if you wish them to be! Many call them ‘permanent temporary’!

Page 3: Case study of a temporary sports hall

Visits to and discussions with the school considered the various possibilities for a site and chose the most suitable & feasible based on a range of factors, also considering the needs of the local community and likely viewpoint of the town planners

Page 4: Case study of a temporary sports hall

A number of designs were considered, including an A-frame roof ‘marquee like’ and a polygon roof structure

A-frame roof,

both structures

Rigid panel walls,

but not insulated

(single layer panel)Rigid panel walls, but

not insulated

(single layer panel)

Page 5: Case study of a temporary sports hall

The chosen design of a 20m x 35m polygon roof structure with thermo roof & insulated walls

Page 6: Case study of a temporary sports hall

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

2'x2'x2'

sunken

concrete

plinth 40cm ø

base plate

on leg

le

gle

gle

gle

g

le

gle

gle

gle

g

le

gle

gle

gle

g

le

gle

gle

gle

g

le

g

le

g

le

g

le

g

le

g

le

g

Grass remains outside of the structure’s footprint & area of plinths

Whole 20m x 35m area under structure (excluding the sunken

concrete plinths to support legs) is filled in with 20 tonnes of

compacted Hoggin, to approx 4" deep

A very brief pictorial summary of the installation process, including some choicesGroundworks: first kill the grass, install sunken concrete plinths to support legs, a DPM and shallow area of hoggin, scree or concrete dust base

Page 7: Case study of a temporary sports hall

The floor above is rolled out

and welded down but the

floor on the left is made

from tiles; it costs more but

could be removed and

installed in your new

building

Doors, partition walls, changing rooms, lighting, heating, dehumidifiers…

Page 8: Case study of a temporary sports hall

Our CAD tool was useful in supporting the funding and planning application stage by letting us show an impression of the project from initial space, through construction to finished item

Page 9: Case study of a temporary sports hall

CAD impression of the outside of the finished sports hall (next 7 pages)

(at this stage the plan was to create in these colours, but in the end they chose white)

Page 10: Case study of a temporary sports hall
Page 11: Case study of a temporary sports hall
Page 12: Case study of a temporary sports hall
Page 13: Case study of a temporary sports hall
Page 14: Case study of a temporary sports hall
Page 15: Case study of a temporary sports hall
Page 16: Case study of a temporary sports hall

Some photos from the installation

Page 17: Case study of a temporary sports hall
Page 18: Case study of a temporary sports hall
Page 19: Case study of a temporary sports hall

The finished item - outside

This particular sports hall available from March 2015! Rental or purchase - 1 careful owner, only 2 years old!

Viewings available by appointment;

highly competitive deal waiting to be negotiated!

Page 20: Case study of a temporary sports hall

This particular sports hall available from March 2015! Rental or purchase - 1 careful owner, only 2 years old!

Viewings available by appointment;

highly competitive deal waiting to be negotiated!

Page 21: Case study of a temporary sports hall

Rough price examples based on the chosen 20m x 35m new sports hall design featured hereTurn-key project based on a min 24 month lease: £140K for Y1 then £7K per month

Or, for an outright purchase:·Same 20m x 35m, as a turn-key project would be £250K (includes installation, groundworks, sub-base floors, specialist floor cover, internal partitioning, heating, lighting, electrics, separate storage rooms)

·Same 20m x 35m sports hall featured here as structure only (no groundworks, no installation/assembly, no content) would be £95K

·The same design but for a 5m longer structure (20m x 40m), as structure only (no groundworks, no installation/assembly, no content) would be £125K

·As above but including installation (not groundworks, floor, content/fixtures etc) £140K·25m x 80m x 4m side height £235K delivered but not installed·40m x 80m x 5m side height £700K including installation for a timber framed design

Storage 10m x 5m x 3m leg

2.5

0

2.5

0

p

o

w

e

r

p

o

i

n

t

p

o

w

e

r

p

o

i

n

t

2.50

2.50

HeatHeat

Gas heater with

ducts & diffuser

Heat Heat

Gas heater with

ducts & diffuser

· 20m span x 35m long x 4m eave height

· POLYGON design Sports Hall

· Thermo PVC (inflated) gables and roof

· Metal sandwich panel insulated/cavity walls

· Timber floor system with non-slip vinyl surface

· 20m internal partition wall (rigid) with gable (soft, single skin)

· 1 set of double doors main entrance centre gable

· 1 sets of double doors to hall opposite entrance

· 2 sets of double doors, each to changing room

· 2 x 5m rigid partition wall forming a changing room (but no plans to roof over

the changing rooms; partition wall is only eave-height)

· 2 sets of double doors long side away from road

· Lighting & Heating

· 2 x multi power points; extension of/drawn from building

2.50 2.50

Funding considerations... outright purchase versus rental/lease, loan/HP, grant, subsidy, Olympic legacy, partnership…Project considerations... Cost of & time for planning permission, land ownership, environmental protection orders, soil survey, whe

Page 22: Case study of a temporary sports hall

A quick roundup of some other sports halls, timber-framed included

Page 23: Case study of a temporary sports hall

Inflated

“Thermo” roof

It’s not just sports halls we install as “permanent temporary” structures; here’s a function / hospitality / conference suite for a hotel

The combination of features give this “marquee” the feel of a built venue; a quiet and very well insulated interior (perfect for conferences) on a firm, sturdy floor… and all installed preserving the protected trees!

Permanent

install electrics

Thick, warm, duvet-

like, acoustic lining

(under the pretty

stuff)

Strong, sub-

base floor, over

foundations

Cavity, thick,

double panel

ISO walls

Thick, double

glazed windows

& doors

Monitored by

quiet air

compressor