Carrying Out TEV Study

download Carrying Out TEV Study

of 37

Transcript of Carrying Out TEV Study

  • 7/27/2019 Carrying Out TEV Study

    1/37

    EVALUATION OF PROJECTS-

    TECHNICAL & FINANCIAL ASPECTS

  • 7/27/2019 Carrying Out TEV Study

    2/37

    2

    FEASIBILITY STUDIES

    To implement any project an entrepreneur needs to carry out

    different types of feasibility studies. These feasibility studies

    evaluate all the risks and returns and try to balance them and

    help the entrepreneur to finalize his plans.

  • 7/27/2019 Carrying Out TEV Study

    3/37

    3

    TYPES OF FEASIBILITY STUDIES

    Managerial Feasibility

    Economic Feasibility

    Commercial Feasibility

    Financial Feasibility Technical Feasibility

    Social Feasibility

    Market Feasibility

    Technical and Financial aspects are discussed in detail in the

    following slides.

  • 7/27/2019 Carrying Out TEV Study

    4/37

    4

    TECHNICAL FEASIBILTY

    Under Technical appraisal the necessary facilities required for

    production are analyzed viz.

    Basic infrastructure - Land/Building/Utilities

    Technology/Technical Process

    Machinery/Raw Material/Labour

    Licensing/Registration/Clearances

  • 7/27/2019 Carrying Out TEV Study

    5/37

    5

    An entrepreneur should have the requisite number of

    technically capable people as well as technology required to

    set up and run the plant. The technology should be such thatis can adapt to local conditions.

    Technology transfer from overseas often fails in this

    regard. The conditions in USA and America are quite

    different from India. Most parts of India are hot and dusty.Sophisticated process controls have known to fail.

    Therefore, knowledge and suitability to local conditions is

    very important.

  • 7/27/2019 Carrying Out TEV Study

    6/37

    6

    Technical analysis thus is mainly concernedwith:

    Material inputs and utilities

    Manufacturing processes

    Product mixes Plant capacities

    Locations and sites

    Machinery and equipments

    Structures and civil work

    Project charts

    Lay outs & work schedules

  • 7/27/2019 Carrying Out TEV Study

    7/37

    7

    EVALUATION OF TECHNOLOGICALOPTIONS

    The technology should be

    Proven and tested; preference could be given to the

    technology used by the market leader.

    Up- to date; otherwise, the risk of obsolescence is high.

    Cost effective and par excellence.

  • 7/27/2019 Carrying Out TEV Study

    8/37

    8

    CHOICE OF TECHNOLOGY

    The choice of technology is influenced by many factors

    such as:

    Plant capacity

    Principal Inputs

    Investment outlay and production cost

    Use by other units

    Product mix

    Latest Developments

    Ease of Integration

  • 7/27/2019 Carrying Out TEV Study

    9/37

    9

    PROJECT MANAGEMENT TECHNIQUES

    CPM (Critical Path Method) and PERT (Programme Evaluation

    Review Technique) are project management techniques, which

    have been created out of the need of Western industrial and

    military establishments to plan, schedule and control complex

    projects.

  • 7/27/2019 Carrying Out TEV Study

    10/37

    10

    CPM/PERT

    CPM/PERT can answer the following important questions

    How long will the entire project take to be completed? What are

    the risks involved?

    Which are the critical activities or tasks in the project, whichcould delay the entire project if they were not completed on

    time?

    Is the project on schedule, behind schedule or ahead of

    schedule? If the project has to be finished earlier than planned, what is

    the best way to do this at the least cost?

  • 7/27/2019 Carrying Out TEV Study

    11/37

    11

    FINANCIAL ANALYSIS

    A wide range of criteria are available to judge the worthiness of

    investment projects. They fall into two broad categories:

    Discounting criteria

    1. Net Present value

    2. Benefit cost ratio

    3.Internal rate of return

    Non-discounting criteria

    1. Payback period

    2. Accounting rate of return.

  • 7/27/2019 Carrying Out TEV Study

    12/37

    12

    NET PRESENT VALUE

    The NPV of a project is the sum of the present values of all cash

    flows-positive as well as negative that are expected to occur

    over the life of the project

    NPV = CFt

    t=0 (1+k) t

    where,

    CFt = cash flow at the end of the year tn = life of the project

    r = discount rate

  • 7/27/2019 Carrying Out TEV Study

    13/37

    13

    RULES FOR CONSIDERATION OF PROJECT:

    The proposal for investment will be accepted if the NPV is

    positive, and rejected if the NPV is negative.

    If the NPV is zero then the project is in an indifferent position.

    If a choice has to be made between two projects, the projectwith higher NPV will be accepted for investment.

  • 7/27/2019 Carrying Out TEV Study

    14/37

    14

    BENEFITS:

    It considers the total benefit of an investment proposal over itslifetime.

    Changes in the discount rate are easily reflected in the

    evaluation process.

    The most significant benefit of NPV is that it considers thetime value of money in calculations

    NPV allows easy comparisons of returns from differentprojects, which enables rational resource allocation decisions tobe made

  • 7/27/2019 Carrying Out TEV Study

    15/37

    15

    DRAWBACKS

    NPV cannot differentiate between a project with higher cashflows and a project with lesser cash flows in the early years

    It does not provide the same base for comparison between twoprojects, with different lives of cash outflow

    It is an absolute measure, and does not consider initial cashoutlays. Hence, it may not provide dependable results.

  • 7/27/2019 Carrying Out TEV Study

    16/37

    16

    BENEFIT COST RATIO:

    BCR = PVB/I

    Where PVB = Present value of benefits

    I = Initial Investment

  • 7/27/2019 Carrying Out TEV Study

    17/37

    17

    RULES FOR CONSIDERATION OF PROJECT

    If BCR =1, the decision will be indifferent

    If BCR > 1, The Investment decision can be accepted

    If BCR < 1, The Investment decision should be rejected

  • 7/27/2019 Carrying Out TEV Study

    18/37

    18

    BENEFITS

    As this measures NPV Per rupee of outlay, it can discriminate

    large and small investments and hence is preferable to NPV

    method.

  • 7/27/2019 Carrying Out TEV Study

    19/37

    19

    DRAWBACKS

    Under unconstrained conditions, this method will accept and

    reject the same projects as NPV.

    It provides no means for aggregating several projects into a

    package that can be compared with a large project. When cash outflows occur beyond the current period, the

    Benefit- Cost

  • 7/27/2019 Carrying Out TEV Study

    20/37

    20

    INTERNAL RATE OF RETURN (IRR)

    IRR of a project is the discountrate which makes its NPV = 0.

    In the NPV calculation we assume that the discount rate is known

    and determine the NPV.

    In IRR Calculation we set the NPV= 0 and determine the discountrate that satisfies this condition

  • 7/27/2019 Carrying Out TEV Study

    21/37

    21

    RULES FOR CONSIDERATION OF PROJECT

    If IRR > 1 accept the investment decision

    If IRR < 1, reject the investment decision

    BENEFITS

    IRR is closely related to NPV.

    This method is easy to understand and interpret.

  • 7/27/2019 Carrying Out TEV Study

    22/37

    22

    DRAWBACKS

    This method may lead to multiple rates of return

    This method may result into incorrect decisions in comparing

    mutually exclusive projects

  • 7/27/2019 Carrying Out TEV Study

    23/37

    23

    MODIFIED INTERNAL RATE OF RETURN

    To overcome this limitation, MIRR (MODIFIED INTERNAL

    RATE OF RETURN) METHOD CAN BE ADOPTED:

    Here,

    PV OF CASH OUTFLOW= Terminal value of cash inflow

    ________________________

    (1 + MIRR)

  • 7/27/2019 Carrying Out TEV Study

    24/37

    24

    BENEFITS / DRAWBACKS

    BENEFITS

    MIRR assumes that project cash flows are reinvested at thecost of capital. Hence it reflects better the profitability of a

    project The problem of multiple rates does not existDRAWBACKS

    For choosing among mutually exclusive projects of different

    size, NPV is a better alternative in measuring the contribution

    of each project to the value of the firm.

  • 7/27/2019 Carrying Out TEV Study

    25/37

    25

    PAY BACK METHOD

    This method is the length of time required to recover the initial

    cash outlay on the project.

    RULES FOR CONSIDERATION OF PROJECTThe shorter the pay back period, the project will be more

    desirable for consideration

  • 7/27/2019 Carrying Out TEV Study

    26/37

    26

    BENEFITS/DRAWBACKS

    BENEFITS

    It is simple in concept and application

    It is a rough and ready method for dealing with risk

    DRAWBACKS

    It does not consider the time value of money

    It ignores cash flows beyond the payback period

    It is a measure of capital recovery and not profitability

  • 7/27/2019 Carrying Out TEV Study

    27/37

    27

    To overcome this limitation, the discounted Payback period is

    considered.

    Here, the cash flows are first converted into their present

    values (by applying suitable discounting factors) and then added

    to ascertain the period of time required to recover the initial

    outlay of the project.

  • 7/27/2019 Carrying Out TEV Study

    28/37

  • 7/27/2019 Carrying Out TEV Study

    29/37

    29

    BENEFITS / DRAWBACKS

    BENEFITS

    It is simple to calculate

    It is based on information that is easily available

    It considers benefits over entire life of the project

    DRAWBACKS

    It is based on accounting profit and not cash flow

    It does not take into account Time value of money.

    It is internally inconsistent

  • 7/27/2019 Carrying Out TEV Study

    30/37

    30

    CONCLUSION

    To conclude,

    For small sized projects, it is best to use Pay back and ARR

    method and for larger projects, IRR method is suitable.

  • 7/27/2019 Carrying Out TEV Study

    31/37

    31

    WHY DO SOME PROJECTS FAIL?

    Most projects suffer from one or more of the followingproblems:

    Customers are not satisfied with the deliverables.

    Deadlines are missed.

    Budgets are chronically overrun. Team members are disgruntled.

    Many projects never end.

    The team members are not committed to the project

  • 7/27/2019 Carrying Out TEV Study

    32/37

    32

    STEPS TO CREATING MORE SUCCESSFUL

    PROJECTS

    The three key steps to creating more successful projects

    are:

    Have a process template and keep improving upon it.

    Adapt a team based and participative approach.

    Use project management methods.

  • 7/27/2019 Carrying Out TEV Study

    33/37

    33

    STEP 1:

    A project exists to produce a unique product, service, process,

    or plan. Since each product is unique, each set of steps to create

    the product should be unique. Hence, rather than starting from

    the scratch on each project and making up a set of steps, mostprojects can work off a process template that serves as a

    starting point for how to create the deliverable.

  • 7/27/2019 Carrying Out TEV Study

    34/37

    34

    For example, for a project such as software development, the

    organisation probably has a software development process that

    project teams use when creating a new or improved software

    program. This process template defines a generic set of stepsto follow that will get one from concept to design to coding to

    testing.

  • 7/27/2019 Carrying Out TEV Study

    35/37

    35

    STEP 2

    Project success depends on the project team. The new project

    management approach is team-based and participative. The

    project leader acts as a facilitator to the team and as a guide

    through the project management process. The team creates theproject plan, monitors and controls the project and assesses

    what went well and what should be improved for the next

    project.

  • 7/27/2019 Carrying Out TEV Study

    36/37

    36

    This new approach to project management means project

    managers must learn new skills: conflict resolution, active

    listening, team participation, and team decision making-skills.

    The participative approach to managing a project is a critical

    factor in creating better project results.

  • 7/27/2019 Carrying Out TEV Study

    37/37

    37

    STEP 3

    Project results are improved when a project management methodology is

    used. Project management methodology is a set of tools and techniques

    that help project team to:

    Produce deliverables that will satisfy the client.

    Get the project done on time.

    Prevent constantly changing project requirements.

    Get the project done within budget.

    Make sure the project doesnt drag on forever.

    Ensure that all stakeholders have a voice in the process.

    Make the project a more satisfying experience for team members.