Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation...

16
Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented by Anna Sommer and David Schlissel

Transcript of Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation...

Page 1: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

Carbon Dioxide Emissions Costs and Electricity Resource Planning

New Mexico Public Regulation Commission

Case No. 06-00448-UT

March 28, 2007

Presented by Anna Sommer and David Schlissel

Page 2: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

2 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Background

• There is increasing acknowledgement of climate change from industry and government and that emissions from fossil fired power plants are a major contributor.

• Federal regulation of CO2 emissions is now a question of when, not if.

• Significant reductions will be required.• Imprudent for a utility to evaluate future

resource options without fully considering carbon risks.

Page 3: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

3 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Uncertainty in Many Resource Planning Assumptions Example: Natural Gas Prices

EIA Historic Nat Gas Price Forecasts for Electric Utilities

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

1990 1995 2000 2005 2010 2015 2020 2025

NG

Pric

e (Y

2005

$/m

mB

tu)

Actual

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

Page 4: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

4 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

How to Make CO2 Costs Not Count In Resource Planning

1. Too uncertain! – assume that CO2 costs will be zero throughout 40-60 year operating lives of proposed generating facilities.

2. Assume CO2 costs only as sensitivity analyses – not in base case studies.

3. Assume only a single CO2 price trajectory, not a range of possible CO2 prices.

4. At best, only a few non-carbon emitting resources are made available for model to select.

5. Avoided costs for energy efficiency don’t reflect the cost of CO2 regulations.

6. Assume CO2 prices do not reflect any increases, over time, of the stringency of regulation.

7. Assume delayed adoption or implementation of CO2 regulations, e.g., not starting until 2015.

8. Focus on decreasing carbon intensity (lbs per MWh) instead of reducing overall CO2 emissions.

9. Assume that new units will be grandfathered.

Page 5: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

5 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Current Synapse CO2 Price Forecast

• Developed in the Winter and Spring of 2006.• Based on several factors including analyses of four bills

proposed in Congress prior to 2006 and a proposal from the National Commission on Energy Policy.

Policy proposal Analysis

McCain Lieberman – S. 139 EIA 2003, MIT 2003, Tellus 2003

McCain Lieberman – SA 2028 EIA 2004, MIT 2003, Tellus 2004

Greenhouse Gas Intensity Targets EIA 2005, EIA 2006

Jeffords – S. 150 EPA 2005

Carper 4-P – S. 843 EIA 2003, EPA 2005

Page 6: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

6 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Factors that Affect Future Carbon Emissions Policy Costs

• “Base case” emissions forecast

• Complimentary policies

• Policy implementation timeline

• Reduction targets

• Program flexibility

• Technological progress

• Emissions co-benefits

Page 7: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

7 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

The Current Synapse CO2 Price Forecast

0

10

20

30

40

50

60

70

2005 2010 2015 2020 2025 2030

Year

2005

$/s

ho

rt t

on

CO

2 Synapse High Case

Synapse Mid Case

Synapse Low Case

Synapse’s Levelized Carbon Price Forecast (2005$/ton)Low Case

Mid Case

High Case

$7.80 $19.10 $30.50

Page 8: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

8 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Examples of the Impact of Current Synapse CO2 Price Forecast on Costs of Fossil Supply Options

Proposed Big Stone II Coal-Fired Generating Unit – 600 MW at an average 88% annual capacity factor

• Low Synapse CO2 Price Forecast - 4,856,000 MWh ∙ $7.74/MWh = $37,585,440 per year• Mid Synapse CO2 Price Forecast - 4,856,000 MWh ∙ $19.60/MWh = $95,177,600 per year• High Synapse CO2 Price Forecast - 4,856,000 MWh ∙ $30.39/MWh = $147,573,840 per year

Supercritical PC

Combined Cycle IGCC

Size (MW) 600 600 535CO 2 (lb/MMBtu) 208 110 200

Heat Rate (Btu/KWh) 9,369 7,400 9,612CO 2 Low Price (2005$/ton) 7.8 7.8 7.8

CO 2 Mid Price (2005$/ton) 19.1 19.1 19.1

CO 2 High Price (2005$/ton) 30.5 30.5 30.5

CO 2 Low Cost per MWh $7.60 $3.17 $7.50

CO 2 Mid Cost per MWh $18.61 $7.77 $18.36

CO 2 High Cost per MWh $29.72 $12.41 $29.32

For a new plant online in 2011

Page 9: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

9 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Factors that suggest Current Synapse CO2 Price Forecast is too low

• Proposals in Congress have become much more aggressive since early 2006 - would require greater CO2 emissions reductions.

• Estimates of the CO2 allowance prices at which carbon capture and sequestration technologies would become cost-effective.

• State initiatives create pressure for stringent federal regulation – e.g. California.

Page 10: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

10 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Bills in the 109th Congress

Page 11: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

11 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Bills in 110th Congress are more aggressive than the bills used to develop Synapse CO2 price forecast

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

10,000

11,000

12,000

13,000

1990 1995 2000 2005 2010 2015 2020 2025 2030 2035 2040 2045 2050

Millio

n T

on

nes C

O2e

EIA AEO-2006 Reference CaseBingaman Discussion Draft Cap 2007Bingaman with Safety Valve EmissionsMcCain-Lieberman 2007Olver-Gilchrest 2007Sanders-Boxer 2007Waxman 2006Udall-Petri Cap 2006Udall-Petri with Safety Valve EmissionsKerry-Snowe 2007Kyoto TargetNational Intensity Goal (AEO 2006)550ppm Stabilization 450ppm Stabilization

Source: World Resources Institute

• Most aggressive proposal prior to May 2006 was capping emissions at 1990 levels. Most proposals now are looking at reductions of 60-80 percent below 1990 levels.

Page 12: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

12 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Utility CO2 price forecasts do not reflect current bills being discussed in Congress

• FPL– Bingaman’s 2006 Discussion Draft– Carper 2006 (S.2724)– Feinstein 2006 Draft– McCain-Lieberman 2005

• Duke– Bingaman 2006 Draft

• AEP– Carper 2003 (S.843)– McCain-Lieberman 2003 (S. 139)

• As a result, utility CO2 price forecasts are too low and do not adequately reflect real risks of CO2 regulation.

Page 13: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

13 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

2007 FPL CO2 price forecast

0

10

20

30

40

50

60

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

2026

2027

2028

2029

2030

2006

$/to

n

B - Low

C - Medium

D - High

Synapse Low

Synapse Mid

Synapse High

Comparison of FPL CO2 Forecast to Synapse Forecast

Page 14: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

14 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Duke January 2007 CO2 price forecast

0

10

20

30

40

50

60

20

10

20

11

20

12

20

13

20

14

20

15

20

16

20

17

20

18

20

19

20

20

20

21

20

22

20

23

20

24

20

25

20

26

20

27

20

28

20

29

20

30

20

05

$/t

on

Synapse Low CaseSynapse Mid CaseSynapse High CaseDuke BaseDuke 150%

Page 15: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

15 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

Estimates of the CO2 Prices at which CCS technologies would become cost-effective

• $30/ton – 2007 MIT Study, “The Future of Coal – Options for a Carbon-Constrained World”

• $15-$75/ton CO2 net captured – Intergovernmental Panel on Climate Change, “Carbon Dioxide Capture and Storage”

• $45/ton – Global Energy Technology Strategy Program, “Carbon Dioxide Capture and Geologic Storage

Page 16: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.

16 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.

States also are mandating aggressive reductions in CO2 emissions

Source: December 2006 New Mexico Climate Change Advisory Group Report