Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation...
-
Upload
ella-spencer -
Category
Documents
-
view
217 -
download
4
Transcript of Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation...
![Page 1: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/1.jpg)
Carbon Dioxide Emissions Costs and Electricity Resource Planning
New Mexico Public Regulation Commission
Case No. 06-00448-UT
March 28, 2007
Presented by Anna Sommer and David Schlissel
![Page 2: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/2.jpg)
2 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Background
• There is increasing acknowledgement of climate change from industry and government and that emissions from fossil fired power plants are a major contributor.
• Federal regulation of CO2 emissions is now a question of when, not if.
• Significant reductions will be required.• Imprudent for a utility to evaluate future
resource options without fully considering carbon risks.
![Page 3: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/3.jpg)
3 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Uncertainty in Many Resource Planning Assumptions Example: Natural Gas Prices
EIA Historic Nat Gas Price Forecasts for Electric Utilities
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
1990 1995 2000 2005 2010 2015 2020 2025
NG
Pric
e (Y
2005
$/m
mB
tu)
Actual
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
![Page 4: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/4.jpg)
4 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
How to Make CO2 Costs Not Count In Resource Planning
1. Too uncertain! – assume that CO2 costs will be zero throughout 40-60 year operating lives of proposed generating facilities.
2. Assume CO2 costs only as sensitivity analyses – not in base case studies.
3. Assume only a single CO2 price trajectory, not a range of possible CO2 prices.
4. At best, only a few non-carbon emitting resources are made available for model to select.
5. Avoided costs for energy efficiency don’t reflect the cost of CO2 regulations.
6. Assume CO2 prices do not reflect any increases, over time, of the stringency of regulation.
7. Assume delayed adoption or implementation of CO2 regulations, e.g., not starting until 2015.
8. Focus on decreasing carbon intensity (lbs per MWh) instead of reducing overall CO2 emissions.
9. Assume that new units will be grandfathered.
![Page 5: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/5.jpg)
5 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Current Synapse CO2 Price Forecast
• Developed in the Winter and Spring of 2006.• Based on several factors including analyses of four bills
proposed in Congress prior to 2006 and a proposal from the National Commission on Energy Policy.
Policy proposal Analysis
McCain Lieberman – S. 139 EIA 2003, MIT 2003, Tellus 2003
McCain Lieberman – SA 2028 EIA 2004, MIT 2003, Tellus 2004
Greenhouse Gas Intensity Targets EIA 2005, EIA 2006
Jeffords – S. 150 EPA 2005
Carper 4-P – S. 843 EIA 2003, EPA 2005
![Page 6: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/6.jpg)
6 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Factors that Affect Future Carbon Emissions Policy Costs
• “Base case” emissions forecast
• Complimentary policies
• Policy implementation timeline
• Reduction targets
• Program flexibility
• Technological progress
• Emissions co-benefits
![Page 7: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/7.jpg)
7 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
The Current Synapse CO2 Price Forecast
0
10
20
30
40
50
60
70
2005 2010 2015 2020 2025 2030
Year
2005
$/s
ho
rt t
on
CO
2 Synapse High Case
Synapse Mid Case
Synapse Low Case
Synapse’s Levelized Carbon Price Forecast (2005$/ton)Low Case
Mid Case
High Case
$7.80 $19.10 $30.50
![Page 8: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/8.jpg)
8 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Examples of the Impact of Current Synapse CO2 Price Forecast on Costs of Fossil Supply Options
Proposed Big Stone II Coal-Fired Generating Unit – 600 MW at an average 88% annual capacity factor
• Low Synapse CO2 Price Forecast - 4,856,000 MWh ∙ $7.74/MWh = $37,585,440 per year• Mid Synapse CO2 Price Forecast - 4,856,000 MWh ∙ $19.60/MWh = $95,177,600 per year• High Synapse CO2 Price Forecast - 4,856,000 MWh ∙ $30.39/MWh = $147,573,840 per year
Supercritical PC
Combined Cycle IGCC
Size (MW) 600 600 535CO 2 (lb/MMBtu) 208 110 200
Heat Rate (Btu/KWh) 9,369 7,400 9,612CO 2 Low Price (2005$/ton) 7.8 7.8 7.8
CO 2 Mid Price (2005$/ton) 19.1 19.1 19.1
CO 2 High Price (2005$/ton) 30.5 30.5 30.5
CO 2 Low Cost per MWh $7.60 $3.17 $7.50
CO 2 Mid Cost per MWh $18.61 $7.77 $18.36
CO 2 High Cost per MWh $29.72 $12.41 $29.32
For a new plant online in 2011
![Page 9: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/9.jpg)
9 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Factors that suggest Current Synapse CO2 Price Forecast is too low
• Proposals in Congress have become much more aggressive since early 2006 - would require greater CO2 emissions reductions.
• Estimates of the CO2 allowance prices at which carbon capture and sequestration technologies would become cost-effective.
• State initiatives create pressure for stringent federal regulation – e.g. California.
![Page 10: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/10.jpg)
10 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Bills in the 109th Congress
![Page 11: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/11.jpg)
11 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Bills in 110th Congress are more aggressive than the bills used to develop Synapse CO2 price forecast
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
11,000
12,000
13,000
1990 1995 2000 2005 2010 2015 2020 2025 2030 2035 2040 2045 2050
Millio
n T
on
nes C
O2e
EIA AEO-2006 Reference CaseBingaman Discussion Draft Cap 2007Bingaman with Safety Valve EmissionsMcCain-Lieberman 2007Olver-Gilchrest 2007Sanders-Boxer 2007Waxman 2006Udall-Petri Cap 2006Udall-Petri with Safety Valve EmissionsKerry-Snowe 2007Kyoto TargetNational Intensity Goal (AEO 2006)550ppm Stabilization 450ppm Stabilization
Source: World Resources Institute
• Most aggressive proposal prior to May 2006 was capping emissions at 1990 levels. Most proposals now are looking at reductions of 60-80 percent below 1990 levels.
![Page 12: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/12.jpg)
12 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Utility CO2 price forecasts do not reflect current bills being discussed in Congress
• FPL– Bingaman’s 2006 Discussion Draft– Carper 2006 (S.2724)– Feinstein 2006 Draft– McCain-Lieberman 2005
• Duke– Bingaman 2006 Draft
• AEP– Carper 2003 (S.843)– McCain-Lieberman 2003 (S. 139)
• As a result, utility CO2 price forecasts are too low and do not adequately reflect real risks of CO2 regulation.
![Page 13: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/13.jpg)
13 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
2007 FPL CO2 price forecast
0
10
20
30
40
50
60
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2006
$/to
n
B - Low
C - Medium
D - High
Synapse Low
Synapse Mid
Synapse High
Comparison of FPL CO2 Forecast to Synapse Forecast
![Page 14: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/14.jpg)
14 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Duke January 2007 CO2 price forecast
0
10
20
30
40
50
60
20
10
20
11
20
12
20
13
20
14
20
15
20
16
20
17
20
18
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
20
05
$/t
on
Synapse Low CaseSynapse Mid CaseSynapse High CaseDuke BaseDuke 150%
![Page 15: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/15.jpg)
15 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
Estimates of the CO2 Prices at which CCS technologies would become cost-effective
• $30/ton – 2007 MIT Study, “The Future of Coal – Options for a Carbon-Constrained World”
• $15-$75/ton CO2 net captured – Intergovernmental Panel on Climate Change, “Carbon Dioxide Capture and Storage”
• $45/ton – Global Energy Technology Strategy Program, “Carbon Dioxide Capture and Geologic Storage
![Page 16: Carbon Dioxide Emissions Costs and Electricity Resource Planning New Mexico Public Regulation Commission Case No. 06-00448-UT March 28, 2007 Presented.](https://reader037.fdocuments.net/reader037/viewer/2022110116/55150634550346a87d8b45dc/html5/thumbnails/16.jpg)
16 www.synapse-energy.com | ©2006 Synapse Energy Economics Inc. All rights reserved.
States also are mandating aggressive reductions in CO2 emissions
Source: December 2006 New Mexico Climate Change Advisory Group Report