CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi)...

41
ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTION PHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645 CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY SAN JOSE, CA 95118-3686 TELEPHONE (408) 265-2600 FACSIMILE (408) 979-5631 www.valleywater.org [email protected] Santa Clara Valley Water District Notification of this Addendum is transmitted via email to all current plan holders. This Addendum is posted on the Valley Water website at https://www.valleywater.org/Construction June 21, 2019 ADDENDUM NO. 4 TO CONTRACT DOCUMENTS FOR THE UPPER LLAGAS CREEK FLOOD PROTECTION PROJECT, PHASE 1 Project No. 26174052 Contract No. C0645 Notice is hereby given to Prospective Bidder that the Contract Documents are modified as hereinafter set forth. BID DOCUMENTS BID FORM NO. 1 REPLACE BID FORM NO.1 (Rev. 1) with: BID FORM NO.1 (Rev. 2) - (ATTACHMENT 1) INSTRUCTIONS TO BIDDERS Paragraph 19. BID PROTEST REPLACE Paragraph 19.A. with: “A. Any Bid protest relating to the form or content of the Bid Documents must be submitted in writing to the Engineer as identified in the Special Provisions, Engineer, Article 13.01. The protest must be received before 5 p.m. three (3) business days in advance of the Bid opening. Any Bidder who fails to submit a protest before the Bid opening deadline will be deemed to have waived any protest to the form or content of the Bid Documents.” REPLACE Paragraph 19.B. with: “B. Any Bid protest unrelated to Paragraph 19.A. must be submitted in writing to the Engineer identified in the Special Provisions, Engineer, Article 13.01. The protest must be received before 5 p.m. on the third business day following the Bid opening.” Page 1 of 12

Transcript of CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi)...

Page 1: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTION PHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY

SAN JOSE, CA 95118-3686 TELEPHONE (408) 265-2600

FACSIMILE (408) 979-5631 www.valleywater.org

[email protected]

Santa Clara Valley Water District Notification of this Addendum is transmitted via email to all current plan holders.

This Addendum is posted on the Valley Water website at https://www.valleywater.org/Construction

June 21, 2019

ADDENDUM NO. 4 TO CONTRACT DOCUMENTS FOR THE

UPPER LLAGAS CREEK FLOOD PROTECTION PROJECT, PHASE 1 Project No. 26174052 Contract No. C0645

Notice is hereby given to Prospective Bidder that the Contract Documents are modified as hereinafter set forth.

BID DOCUMENTS

BID FORM NO. 1

REPLACE BID FORM NO.1 (Rev. 1) with:

BID FORM NO.1 (Rev. 2) - (ATTACHMENT 1)

INSTRUCTIONS TO BIDDERS

Paragraph 19. BID PROTEST

REPLACE Paragraph 19.A. with:

“A. Any Bid protest relating to the form or content of the Bid Documents must be submitted in writing to the Engineer as identified in the Special Provisions, Engineer, Article 13.01. The protest must be received before 5 p.m. three (3) business days in advance of the Bid opening. Any Bidder who fails to submit a protest before the Bid opening deadline will be deemed to have waived any protest to the form or content of the Bid Documents.”

REPLACE Paragraph 19.B. with:

“B. Any Bid protest unrelated to Paragraph 19.A. must be submitted in writing to the Engineer identified in the Special Provisions, Engineer, Article 13.01. The protest must be received before 5 p.m. on the third business day following the Bid opening.”

Page 1 of 12

Page 2: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTION PHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

SPECIFICATIONS AND CONTRACT DOCUMENTS

SPECIAL REQUIREMENTS

Section 17. Permits and Regulations

Article 17.03. Noise Monitoring

REPLACE the third to last Sentence of Article 17.03.01.G with:

“G. Noise monitoring shall be performed by Contractor using a Type 1 Sound Level Meter, as specified by the latest ANSI standards, measuring a dynamic range of 40-120 dB. Noise levels shall be A-weighted with a minimum sampling rate of 64 samples per second (Fast). Root Mean Square (RMS) sound pressure levels (SPLs) shall be expressed by the descriptors L (max) and Leq(h). Microphones shall be equipped with windscreens and shall be positioned as designated by the Engineer. Monitoring shall be performed for a duration of at least 60 minutes during each work operation. Additional spot readings shall be taken as directed by the Engineer to assure the noise level during work operations are within the allowable limits. Noise monitoring equipment shall be calibrated before each work shift. Contractor shall use noise monitoring equipment with current calibration. Calibration shall be verified prior to each shift. The noise monitor shall print data to a serial printer, providing immediate on-site results. The Contractor shall keep a copy of all documentation and submit one copy to the Engineer on a daily basis.”

TECHNICAL REQUIREMENTS

Section 22. Preparatory Work

Article 22.07. Non-Native Plant Control

REPLACE Articles 22.07.06.A and 22.7.06.B with:

“A. Initial Himalayan blackberry control shall be field measured per 1/8 acre.

B. Initial Giant Reed control shall be field measured per 1/8 acre.”

REPLACE Articles 22.07.07.A and 22.07.07.B. with:

“A. Full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for performing all Work involved in initial Himalayan blackberry control, including Himalayan blackberry above-grade biomass mowing and legal disposal, and other work as shown on Drawings, as detailed in these Specifications, and as directed by Engineer. Engineer will confirm completion of the initial Himalayan blackberry control. All costs shall be included in the unit price bid item per 1/8 acre for INITIAL HIMALAYAN BLACKBERRY CONTROL, Bid Item No. 22-10.

B. Full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for performing all work involved in initial giant reed control, including above-grade biomass removal and legal disposal, root excavation, and other work as shown on Drawings, as detailed in these Specifications, and as directed by Engineer. Engineer will confirm completion of initial giant reed control. All costs shall be included in the unit price bid per 1/8 acre for INITIAL GIANT REED CONTROL, Bid Item No. 22-11.”

Page 2 of 12

Page 3: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTIONPHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

Section 26. Site Utilities

Article 26.02. Storm Drains

REPLACE Article 26.02.01.07.B with:

“B. Full compensation for furnishing all labor, materials, testing, tools, equipment, inlets, Type 1 or Type 2 outlets, manholes, rock slope protection, protection of existing utilities, dust and erosion control, saw cutting of pavement, excavation, disposal of excess material, concrete collars, connecting to existing pipelines, bedding, backfill, compaction, pipe testing, surface restoration, pavement, striping and other pavement markings, sidewalks, curbs, gutters, valley gutters, CCTV inspection, and incidentals required to install the reinforced concrete pipe as shown on the Drawings and as specified in these Specifications shall be included in the unit price bid each per linear feet for 18-INCH RCP STORM DRAIN - NEW, Bid Item No. 26-4.”

Section 29. Concrete

Article 29.06. Cast-in-Place Concrete

Delete the word “Structural” from Article 29.06.07.A as follows:

“A. Full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all work to supply Structural Concrete (1,500 psi, 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings, as specified by these Specifications will be included in the lump sum bid or unit price bid for the item of work which requires structural concrete, and no additional payment will be made thereof.”

Section 40. Landscape and Revegetation

Article 40.04. Seeding

REPLACE Article 40.04.03.C with:

“C. Hydroseeding – Bid Item No. 40-5”

Section 42. Excavated Materials Management

Article 42.01.02 Materials

REPLACE Article 42.01.02.C with:

“C. Excavated Material for reuse on the Project site shall meet the requirements specified for their intended use and the requirements of this Section 42, Excavated Materials Management.”

Article 42.01.03.J. Hazardous Waste Manifests

ADD Article 42.01.03.J.11 as follows:

“11. The District will be the Generator for all Regulated materials pre-existing on the Project site and will sign the associated waste manifests accordingly. The Contractor will be the Generator for all regulated materials introduced to the Project site by the Contractor or for any unauthorized releases of regulated

Page 3 of 12

Page 4: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTIONPHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

materials occurring as a result of Contractor activities; in such cases, the Contractor will sign the associated waste manifests in accordance with Article 10.11.02. The District shall be responsible for paying the State Superfund fees, the generator’s fees, and other costs of disposal of pre-existing regulated material wastes unless specifically stated otherwise in these Specifications.”

MAP AND CONSTRUCTION PLANS

DRAWINGS

REPLACE Sheet C-112, in Detail 1, Scale 1" = 6' with: Scale 1" = 3’

REPLACE Sheet GC-10, Detail 2, Slide Gate.

DELETE Sheet GS-3, Detail 03000

GENERAL QUESTIONS AND RESPONSES

Question 1. Please clarify bid item 42-2. All of the local landfills are listed as Class III and not Class II Landfills (Newby Island, Kirby Canyon, Zanker Rd). Furthermore, there are two types of landfill options. Cover soil and Direct Burial/Disposal. Please clarify whether this bid item includes both Class II and Class III landfills. Please also clarify if this bid item is for Landfill Cover soil or for landfill direct burial/disposal.

Response 1. For bidding purposes, Bid Item 42-2 quantity shall be assumed to be legally disposed of at a Class II Landfill as direct non-hazardous waste disposal. Bid item 42-2 is not intended to capture additional cost for soil being reused as daily landfill cover. Daily landfill cover is considered a re-use option that is included under bid item 23-1. Receiving landfill screening criteria was provided for informational purposes only in the Soil and Groundwater/Surface Water Management Plan (ex. Newby Island, Kirby Canyon, Zanker Rd.), but it remains the contractor’s decision to determine the legal disposal of soil.

Question 2. How were the volumes determined for Bid Items 42-1, and 42-2? Were these volumes derived from specific areas identified within the project that are already pre-classified? If so, where are these areas? Or are these plug volumes for material that might fall under these classifications after additional soil testing?

Response 2. The volumes for Bid Item 42-1 and Bid Item 42-2 were not derived from identified pre-classified areas. The volume for Bid Item 42-1 (3,300 CY) was selected as a small percentage of overall excavation quantities. The volume for Bid Item 42-2 (6,500 CY) was selected using the assumption of approximately 1% of the excavation volume (650,000 CY).

Question 3. Due to tightening regulations with non-landfill re-use facilities and the reduced metals limits shown within the updated 2019 RWQCB Environmental Screening Limits (ESL’s), only a fraction of this soil may be suitable for reuse at a construction site or reuse facility other than a landfill. As a consequence much of the excess soil may require reuse as Daily cover at a Class II or Class III landfill (Daily cover). As mentioned within the SMP re-use at a Class II or Class III landfill as daily cover soil is included as one of the re-use options. Is bid item 42-2 intended to capture

Page 4 of 12

Page 5: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTIONPHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

the additional cost for soil being reused as Daily cover? If not, how should the contractor price the cost difference of Class II/Class III landfill daily cover from reuse at other locations besides a landfill?

Response 3. For bidding purposes, Bid Item 42-2 quantity shall be assumed to be legally disposed of at a Class II Landfill as direct non-hazardous waste disposal. Bid item 42-2 is not intended to capture additional cost for soil being reused as daily landfill cover. Daily landfill cover is considered a re-use option that is included under bid item 23-1. Bid items 42-1 and 42-2 covers soils that require disposal at regulated waste facilities and do not qualify for other reuse options.

Question 4. We would appreciate your consideration of a Bid Date extension for the Project. Due to the extensive plans and specifications & the complexity of the project, we are requesting that the bid date be extended by at least one week to allow contractors (and our potential subcontractors) to more fully analyze the project. The lack of electronic (CAD) files to assist with our take off efforts has also influenced our request for this extension.

Response 4. The Bid Date has been extended to July 2nd, 2019. See Addendum No.3.

Question 5. Please clarify legend and plan demarcation on Demo and Removal Plans, specifically Non-Native Plant Control – Himalayan Blackberry Control Areas. Plan sheets (see D-28 for example) have two different infill areas shown that are very similar to the Non-Native Blackberry Legend which is the Blackberry and what is marked by the other. Sheet D-28 at 4011+25 shows a clear change side by side of two areas that could be interpreted as Blackberry Control area. Please clarify the difference in these areas and the legend.

Response 5. The question refers to one hatch that looks like an “x” and one hatch that looks like a smaller plus sign (+). Both of these hatches represent the same thing (Non-Native Plant Control - Himalayan Blackberry Control Areas). Within the CAD program one hatch was rotated and scaled differently from the other hatch in the other area. Each D sheet has a legend.

Please note, on sheets from D-20 to D-29 and from D-101 to D-104 the hatch consisting of short diagonal lines represents “Limits of Over Decompaction”. On sheets from D-54 to D-90 the hatch consisting of short diagonal lines represents “Non-Native Plant Control – Giant Reed Control Areas – Inside Planting Area”.

Question 6. P. 23-1 Item 10: We are unable to find any existing box culverts on the plans or in the field. Are there existing box culverts with material removal on the project?

Response 6. Removal of material from existing box culverts is not included in the Project. Structural excavation to remove material in order to construct new box culverts/structures as part of the Project is covered under specification Section 23.10.

Question 7. Reference the provided cross sections and contour grading plans for Silveira Lake, are the finish grades shown to subgrade of topsoil or top of the top soil?

Page 5 of 12

Page 6: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTIONPHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

Response 7. Finish grades shown on the Project Plans includes the placement of topsoil in areas that require topsoil.

Question 8. P. 22-30 Section 22.07.01-B: It seems unreasonable to ask the bidders to survey the entire site to locate Giant Reed and Himalayn Blackberry Control Areas and take on the responsibility of generating a quantity for a lump sum bid item. Please consider paying these items by a measured field quantity.

Response 8. Bid Items 22-10 and 22-11 have been revised from lump sum to field quantity measured per 1/8 acre. Please see the revised BID FORM NO. 1 (REV 2) as ATTACHMENT 1 in this Addendum No. 4, and the revised specifications above.

Question 9. Reference the Soil and Groundwater/Surface Water Management Plan – Table 1 and BI 23-1 Excavation. Our quantity take-off for total excavation including all the items specified (bedload, topsoil, low flow, excavation) is very close to that shown on Table 1, 785,000 CY. It appears that the volume of topsoil excavation has been excluded from the bid item 23-1, 650,000 CY, although the bid item narrative indicates topsoil excavation is paid for in the excavation item.

Response 9. The quantity for Bid Item 23-1 has been revised to 745,000 CY. Please see the revised BID FORM NO.1 (Rev 2) (ATTACHMENT 1). Table 1 in the Soil and Groundwater/Surface Water Management Plan shows 785,000 CY, but that includes the excavation at Lake Silveira. The excavation at Lake Silveira is paid under Bid Item 41-1 Improvements at Lake Silveira (see specification Section 41.01.08.A.1).

Question 10. We respectively request a one (1) week extension to the bid date. It was mentioned at the pre-bid meeting that this is just a dirt job but it is a complicated dirt job in terms of dewatering and disposal, some additional time would be very helpful in getting all the logistics figured out.

Response 10. See Response to Question No. 4.

Question 11. Lake Outlet Structure Section A on Dwg C-110 requires a 3’ x 3’ Gate with reference to Detail 2 on Dwg GC-10. However, the Schedule at the bottom of Detail 2 on Dwg GC-10 indicates the Lake Silveira Outlet Slide Gate is 24”x24”. Please clarify the desired size of this Slide Gate.

Response 11. The 3-ft x 3-ft opening on Dwg C-110 is correct. Modify the schedule at the bottom of Detail 2 on Dwg GC-10 to indicate a 3’x3’ gate as shown on ATTACHMENT 2 of this Addendum No. 4.

Question 12. Please clarify the scope of work required within the “limit of over decompaction” noted in the D- Series drawings. Are these areas currently over-decompacted and require compaction or are these areas required to be decompacted per Planting Area Preparation Spec Section 40.02 (and Bid Item 40-1)?

Response 12. The work required to perform decompaction within the limits of over decompaction shown on the D-sheets is described in Section 40 under Article 40.02.03.B. and paid for under Bid Item 40-1.

Page 6 of 12

Page 7: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTIONPHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

Question 13. (Hexagonal) Construction Note 20 is referenced in the Profile at Station 479+50 (presumably associated with the existing Verizon at this location). Please provide Construction Note 20.

Response 13. The Verizon line shown in the profile at this location (PP-23 station 479+50) does not exist. The line was deleted from the plan window but not the profile window. Delete the reference to the utility and (Hexagonal) Construction Note 20 in the profile window, as shown on ATTACHMENT 3 of this Addendum No. 4.

Question 14. A note on Dwg PP-73 upstream of the Inlet Structure at the Sta 108+00 tributary indicates to “construct 115.5’ of 3 rail wood fence … Fence to located at same location to adjoin existing fence and fence to be provided by others.” Please clarify which element(s) of this fencing scope are provided by others and which are to be performed by Contractor.

Response 14. The Contractor is to provide and install 115.5’ of 3 rail wood fence with barbed wire. The fence will be installed between an existing fence at the edge of the temporary construction easement and a future fence at the edge of the temporary easement. The future fence at the edge of the temporary easement will be provided and installed by others. Please refer to Project Plans sheets PP-72 and C-63.

Question 15. In reference to the Builder’s Risk policy (Paragraph 13.16.01.C of Article 13), please advise if the policy’s term may end at Substantial Completion Milestone 2. (Extending the Builder’s Risk policy term through the 3-year Plant Establishment and Maintenance period will approximately double the cost of the Builder’s Risk policy.)

Response 15. Builder’s Risk policy must extend through completion and acceptance of Milestone 2 by the District’s Board of Directors.

Question 16. At Lake Silveira Dwgs D-102, D-103, D-104 there are hatched areas shown for both “Limits of Over Decompaction” and “Non-Native Plant Control – Himalayan Blackberry Control Areas”. On each of these 3 drawings there is also a third unidentified area hatched with a hatching density between the two aforementioned areas. Please advise what this unidentified hatched area represents

Response 16. The question refers to one hatch that looks like an “x” and one hatch that looks like a smaller plus sign (+). Both of these hatches represent the same thing (Non-Native Plant Control - Himalayan Blackberry Control Areas). Within the CAD program one hatch was rotated and scaled differently from the other hatch in the other area. Each D sheet has a legend.

Please note, on sheets from D-20 to D-29 and from D-101 to D-104 the hatch consisting of short diagonal lines represents “Limits of Over Decompaction”. On sheets from D-54 to D-90 the hatch consisting of short diagonal lines represents “Non-Native Plant Control – Giant Reed Control Areas – Inside Planting Area”.

Question 17. Paragraph 5.07.B indicates imposition of Liquidated Damages shall not preclude the District from taking other action as deemed appropriate to ensure performance of the Contract. Paragraph 6.02.05.A.7.b indicates that the District may withhold payment to cover actual or Liquidated

Page 7 of 12

Page 8: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTIONPHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

Damages if District determines that the Work will not be completed within the Contract Time(s). Please confirm that the Liquidated Damages (as listed in the Special Provisions) are the District’s sole means to recover damages from the Contractor if the Work is not completed within the Contract Time(s).

Response 17. No, the District may also consider actual damages.

Question 18. Paragraph 17.03.01.G indicates to calibrate noise monitoring equipment prior to each shift. Alternatively, please confirm that the noise monitoring equipment’s calibration shall be validated prior to each shift and that if the equipment is no longer properly calibrated it shall then be calibrated.

Response 18. Article 17.03.01.G has been revised. See revised language included in this Addendum No. 4.

Question 19. In reference to Article 10.11, please confirm (1) that Materials generated as a result of the Contractor’s operations do not include Regulated materials pre-existing on the Project site and that (2) District is the Generator for all Regulated materials pre-existing on the Project site.

Response 19. Confirmed.

Question 20. Article 10.11.02.D indicates Contractor shall be responsible for signing the Nonhazardous Waste Manifests and the Hazardous Waste Manifests and for paying the State Superfund fees, the generator’s fees, and other costs of disposal of these wastes unless specifically stated otherwise in these Specfication and that Contractor shall be identified as the owner and generator of the wastes associated with unauthorized releases or discharges. Article 42.01.01.E.1 indicates the District will be the Generator. Please confirm the District will be the Generator for all Regulated materials pre-existing on the Project site and will sign the associated Manifests accordingly.

Response 20. The District will be the Generator for all Regulated materials pre-existing on the Project site and will sign the associated waste manifests accordingly. The Contractor will be the Generator for all regulated materials introduced to the Project site by the Contractor or for any unauthorized releases of regulated materials occurring as a result of Contractor activities; in such cases, the Contractor will sign the associated waste manifests in accordance with Article 10.11.02. The District shall be responsible for paying the State Superfund fees, the generator’s fees, and other costs of disposal of pre-existing regulated material wastes unless specifically stated otherwise in these Specifications.

See new Article 42.01.03.J.11 in this Addendum No. 4.

Question 21. At the Pre-Bid Meeting it was indicated that the Project was targeting an Award of July 9. Article 10.14.07.A indicates Biologist’s qualifications must be favorably reviewed prior to any Work. Article 18.04.02.C indicates the Biologists’ must be approved by CDFW and USFWS and Article 19.01.03.A.1 indicates this will be provided within 60 calendar days. This leaves little to no time to remove the projects’ 1,000+ trees within the permits’ imposed work constraints. Please confirm that any and all Project Delays due to nesting resulting from the inability to

Page 8 of 12

Page 9: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTIONPHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

successfully Clear the Project this year will be addressed as a Compensable Delay.

Response 21. District will submit the Biologist’s qualifications to the regulatory agencies of California Department of Fish and Wildlife and the U.S. Fish and Wildlife Service for approval. Contractors are not required to submit qualifications for the Contractor’s Qualified Biologist until Notice to Proceed, however, the Contractor may choose to submit qualifications earlier than Notice to Proceed.

The Contractor is encouraged to concentrate on tree removal and trimming efforts in the areas where the Contractor intends to begin construction. The Contractor is responsible for Project delays due to nesting. Tree removal is not the only tool available to deter bird nesting; it is in the Contractor’s best interest to use multiple forms of bird deterrents to prevent nesting.

Question 22. Is this project subject to the Buy America or Buy American requirements for steel products?

Response 22. No.

Question 23. When trying to scale the Poppy Jasper Mine Security Enclosure the stated 4’ wide gate scales out to be 8’ wide. Is it possible to have the dimensions for the enclosure given or please confirm the scale 1” = 6’ is correct. I the scale is correct then the gate is mislabeled. Please clarify.

Response 23. The scale should be 1" = 3'. Refer to revision to sheet C-112 in this Addendum and ATTACHMENT 4 of this Addendum No. 4.

Question 24. Item 28-4 the Single Swing Gates it states there is 3 each. We found 5 each of the Single Swing Gates. Please confirm the correct quantity of the Single Swing Gates.

Response 24. The correct quantity of Single Swing Gates is 5. See updated BID FORM NO. 1 (Rev 2) as ATTACHMENT 1 in this Addendum No. 4

Question 25. Item 28-5 the Double swing Gates it states there is 17 each. We found 25 each of the double Swing Gates. Please confirm the correct quantity of the Double Swing Gates.

Response 25. Response to Question 16: The correct quantity of Double Swing Gates is 25. See updated BID FORM 1 (Rev 2) as ATTACHMENT 1 in thisAddendum No. 4

Question 26. Item 28-6 Miscellaneous Fencing is not very clear on how much and the type of fences that are to be modified along the right of way. Is it possible to have a better and clearer amount of footage and type of fence work required along the existing effected fence lines.The information given on the plans make it difficult to evaluate the cost of needed work.

Response 26. The Bidders should anticipate a variety of fencing materials. It is in the Contractor’s best interest to salvage as much of the existing materials as possible. The Contractor is not expected to replace significant portions of the adjacent property owners’ fences, only to adapt their existing fence to

Page 9 of 12

Page 10: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTIONPHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

provide site security for the adjacent property as described in Section 28.11.

Question 27. This is a large project and has a great deal of items of work to price. Is it possible to have the bid date for this project be postponed so that more time is given to prepare our bids.

Response 27. See Response 4 in this Addendum No. 4.

Question 28. Will the contractor be allowed to leave stockpiled non-hazardous material in the provided staging areas up until the project is fully completed 2,095 Calendar days, or is the contractor required to have staging areas returned (Disked and hydroseeded) after 1,000 calendar days?

Response 28. (REVISED RESPONSE, QUESTION 15 ADDENDUM NO. 2) The Contractor Shall be allowed to leave stockpiled material up until the completion of milestone No. 2 (1,000 calendar days). All stockpiled material shall be removed prior to acceptance of Milestone 2 by the District’s Board of Directors. The Contractor’s attention is directed to Temporary Construction Easement Agreements in Appendix B of the Project Specifications for expiration dates of non-District owned staging areas.

Question 29. Please advise where the Patch @ 72” SD Opening Detail 03000 on Dwg GS-3 is to be performed.

Response 29. Detail 03000 is from Phase 2 of the project and not applicable to Phase 1. Delete detail 03000 on sheet GS-3, as shown on ATTACHMENT 5 of this Addendum No. 4.

Question 30. Please confirm that Herbicides test method will not be required as part of soil testing.

Response 30. Tables 5a through 5c in the Soil and Groundwater/Surface Water Management Plan lists typical testing parameters needed to evaluate reuse options. Previous environmental investigation reports for some properties within the Project Area did not identify herbicides as a significant concern, and there are no beneficial reuse criteria established for herbicides for in-channel reuse (Table 2) therefore analyses listed under Table 5a for in-channel beneficial reuse does not include herbicides. Herbicide analysis is listed in Table 5b for off-site reuses. The need to test for herbicides will be determined by the Contractor and depend on requirements of the off-site reuse option selected. There may be circumstances where profiling for waste disposal at a landfill could require testing for herbicides. Those circumstances could include landfill acceptance criteria and/or other reasons that the Contractor identifies herbicides as a potential chemical of concern.

Question 31. We would like to request Upper Llagas get pushed back 3 weeks so we will have the opportunity to bid on both projects.

Response 31. See Response 4 in this Addendum No.4.

Question 32. Table 3 Off-site Reuse Screening Criteria for Excess Material mentions Tier 1 ESLs as applicable to unrestricted reuse of export material. Several other screening levels are provided. Which clean screening level is being used to define the difference between clean and class 2 soil?

Page 10 of 12

Page 11: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ADDENDUM NO. 4 UPPER LLAGAS CREEK FLOOD PROTECTIONPHASE 1: R4, PORTION R5, R7A, AND LAKE SILVEIRA PROJECT, C0645

Response 32. ESLs provide guidance on appropriate reuse options based on protection of human health and the environment and do not correlate directly with waste classification for disposal. In evaluating reuse options, the Contractor needs to understand the basis of individual ESLs to determine appropriate reuse options. The ESLs do not determine waste classification for disposal purposes. Waste soil for disposal follows rules and regulations for hazardous waste (California and federal standards) and acceptance criteria of non-hazardous waste at California Class 2 landfills. Each landfill has its own acceptance criteria according to its own permitting requirements. Typically, Class 2 materials would consist of those that do not qualify for reuse options according to the ESLs but do not exceed hazardous waste thresholds.

Question 33. Regarding Pay Item 42-1 “Removal and Legal Disposal of Hazardous Waste Materials”, given the definition in 42.01.01 E. 2 & 3, this seems to cover both Class1 RCRA and Class 1 Non-RCRA (California Hazardous). These classifications have two different unit prices. Please clarify.

Response 33. Based on preliminary testing, Resource Conservation and Recovery Act (RCRA) waste is not anticipated. The Contractor can assume for bidding purposes that the entire quantity of Bid Item 42-1 can be disposed as Class 1 Non-RCRA waste.

Question 34. How is 3,300 CY of hazardous material established when there are no leachate test ran for all Chromium, Lead and Nickel exceedances over the TCLP and STLC trigger levels?

Response 34. The volume for Bid Item 42-1 was not derived from identified pre- classified areas. The volume was selected using a percentage of the overall excavation volume that could be classified as hazardous for disposal purposes. The Contractor is responsible for performing the necessary testing for waste profiling and disposal.

Question 35. How is 6,500 CY of Non-Hazardous Waste (Class 2) material defined from clean or hazardous soil?

Response 35. The volume for Bid Item 42-2 (6,500 CY) was not derived from identified pre-classified areas. The volume was selected using a percentage of the overall excavation volume that could be classified as non-hazardous Class 2 waste according to California laws and regulations. The Contractor is responsible for performing the necessary testing for waste profiling and disposal.

Question 36. Bid item 22-14 Standing Snag Habitat Feature, I cannot find them on the plans anywhere and there is no quantity, lump sum item. Don’t know what to bid.

Response 36. Bid Item 22-14 Standing Snag Habitat Feature is specified under Article 22.07.03.H Standing Snag Habitat Feature (Girdled Non-Native Trees). The Girdled Non-native Trees are shown on the D-sheets on the Debris and Vegetation Removal Plan.

Question 37. Please reference Spec section 40.02.07 Payment for the Planting Area Prep Section. Note that the specification identifies for the Contractor to provide a unit price for 42,000 square feet of Decompaction. However, Plan Sheet D-104 shows an area designated as the “Limits of

Page 11 of 12

Page 12: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

Decompaction" to be approximately 73,000 sf. ls this area to be included with the Planting Area Prep Bid Item? Or only the 42,000 sf listed in the specifications. Please clarify this item and provide an updated quantity if needed.

Response 37; Bid Item 40-1 Planting Area Preparation (lump sum) includes the labor and equipment to decompact the decompaction areas shown on the drawings. On Sheet D-101 and D-104 there is 84,000 square feet (approx.) of decompaction shown.This 84,000 square feet is included in Bid Item 40-1. During the construction phase, the District may find new areas that need decompaction. These new areas would be added to the Project using the unit price identified in the Schedule of Values for Landscape Related Items. Also, during the construction phase, the District may find that the area currently identified for decompaction does not need decompaction. These areas to be deleted would be subtracted from the project using the unit price identified in the Schedule of Values for Landscape Related Items. The quantity of "42" shown spec section 40.02.07.B is to establish a value for negotiations.

Question 38. Bid Item 34-3, 18" Flap Gate, is for 1 each. However the project plans show 2 flap gates. One on sheet PP-73 and another on PP90. Please update the bid form accordingly.

Response 38.Bid Item 34-3 quantity has been revised from 1 to 2. See revised BID FORM NO. 1 (Rev 2) as ATTACHMENT 1 of this Addendum No. 4

THIS ADDENDUM NO. 4, WHICH CONTAINS 12 PAGES AND 5 ATTACHMENTS, IS ATTACHED TO AND IS A PART OF THE SPECIFICATIONS AND CONTRACT DOCUMENTS FOR THIS PROJECT.

Christopher Hakes, P.E. Deputy Operating Officer Dam Safety and Capital Project Delivery

Enclosures: Attachment No. 1 - BID FORM NO.1 (Rev. 2) Attachment No. 2 - Sheet GC-1 O Attachment No. 3 - Sheet PP-23 Attachment No. 4 - Sheet C-112 Attachment No. 5 - Sheet GS-3

Date: _ _ t�o_lL-'-/1,__1 __ _

ADDENDUM NO. 4 Page 12 of 12

UPPER LLAGAS CREEK FLOOD PROTECTION PHASE 1: R4, PORTION RS, R7A, AND LAKE SILVEIRA PROJECT, C0645

Page 13: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ATTACHMENT 1 BID FORM NO. 1 (Rev 2)

Page 14: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

THIS P

AGE INTENTIO

NALLY LE

FT BLA

NK

Page 15: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

(Rev. 05/04/16)—Ver. 2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 1 of 11

This form must be completed in ink and changes must be initialed.

Honorable Board of Directors Santa Clara Valley Water District (District )

Pursuant to, and in compliance with, the Notice to Bidders and the Contract Documents, relating to the UPPER LLAGAS CREEK FLOOD PROTECTION PROJECT, PHASE 1: REACH 4, PORTION OF REACH 5, REACH 7A, AND LAKE SILVEIRA MITIGATION, the undersigned Bidder having become thoroughly familiar with the terms and conditions of the Contract Documents and with local conditions affecting the performance and costs of the Work and having fully inspected the Work site in all particulars, hereby proposes and agrees to fully perform the Work, including providing any and all labor and materials and performing all Work required to construct and complete said Work within the contract time stated and in accordance with the requirements of the Contract Documents, for the following sum of money.

The undersigned Bidder agrees to complete all the Work within 2,095 calendar days from the first chargeable day of the Contract, as stated in the Notice to Begin Work. The Bidder agrees to enter into a Contract with Santa Clara Valley Water District and provide the required bonds and insurance in accordance with Articles 4.13 and 11.02 of the Standard Provisions. If the Bidder fails to meet these requirements within the time specified in Article 11.02 of the Standard Provisions the Bidder’s security accompanying this Proposal may be forfeited and become the property of the District. No Contract exists until all Contract bonds and insurance documents have been accepted by the District.

TOTAL BID: $ Bidder acknowledges receipt of the following Addenda to the Bid Documents: Addenda are posted online at https://www.valleywater.org/construction.

NO Addenda received

Addenda received as follows:

Addendum No. Date Addendum No. Date Addendum No. Date Addendum No. Date

Failure to acknowledge receipt of an Addendum on the Bid Form is not, in itself, cause for withdrawal or rejection of Bid, if it can be established that Bidder did, in fact, receive such Addendum prior to Bid opening.

The undersigned Bidder has read and understands, and will comply with, each and all of the requirements specified in these Bid Documents.

BIDDER’S COMPANY INFORMATION NAME: ADDRESS: CONTRACTOR’S CALIFORNIA LICENSE NUMBER: DATE OF EXPIRATION: LICENSE CLASSIFICATION(S): PHONE NO.: ( ) FAX NO.: ( ) EMAIL ADDRESS:

SIGNATURE BLOCK (Signature Block must be completed in ink and changes must be initialed.) Bidder’s Signature: Date:

Bidder’s Name and Title (Print):

Page 16: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

(Rev. 05/04/16)—Ver. 2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 2 of 11

This form must be completed in ink and changes must be initialed.

SECTION A — BASE BID

ITEM NO.

N

DESCRIPTION OF ITEM APPROXIMATE

QUANTITY UNIT

UNIT PRICE TOTAL

13-1 Mobilization/Demobilization Lump Sum Lump Sum

13-2 Dispute Resolution/Review Board Lump Sum Lump Sum

13-3 Professionally Facilitated Project Partnering

Lump Sum Lump Sum

14-1 Surveying Lump Sum Lump Sum

15-1 Site Review and Monitoring of Project Limits and Vicinity

Lump Sum Lump Sum

17-1 Noise Monitoring Lump Sum Lump Sum

18-1 Compliance with NPDES General Permit Lump Sum Lump Sum

18-2 Compliance with Regulatory Permits Lump Sum Lump Sum

19-1 Contractor’s Quality Control Lump Sum Lump Sum

22-1 Clearing and Grubbing Lump Sum Lump Sum

$50,000 $50,000

$50,000 $50,000

Page 17: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 3 of 11

(Rev. 05/14/16)—Ver.2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

ITEM NO.

N

DESCRIPTION OF ITEM APPROXIMATE

QUANTITY UNIT

UNIT PRICE TOTAL

22-2 Demolition Lump Sum Lump Sum

22-6 Remediation Sites Lump Sum Lump Sum

22-7 Monitoring Well Destruction 1

Each

22-9 Control of Water Lump Sum Lump Sum

22-10 Initial Himalayan Blackberry Control 94

1/8 Acre

22-11 Initial Giant Reed Control 2

1/8 Acre

22-12 Initial Yellowflag Iris Control Lump Sum Lump Sum

22-13 Non-Native Noxious and Invasive Plant Control Event

8 Each Event

22-14 Standing Snag Habitat Feature Lump Sum Lump Sum

22-15

Himalayan Blackberry Follow-up Herbicide Event 8

Each Event

Page 18: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 4 of 11

(Rev. 05/14/16)—Ver.2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

ITEM NO.

N

DESCRIPTION OF ITEM APPROXIMATE

QUANTITY UNIT

UNIT PRICE TOTAL

22-16 Giant Reed Follow-up Herbicide Event 8

Each Event

23-1 Excavation 745,000

Cubic Yards

23-2 Fill at Lake Silveira 110,000

Cubic Yards

23-3a Bedload Material Storage 3,500

Cubic Yards

23-3b Bedload Material Placement 2,200 Cubic Yards

23-4 Topsoil 111,000

Cubic Yards

25-1 Bike Trail Pavement 20

Cubic Yards

25-2 Driveway 2 Each

25-4 Maintenance Roads 15,000

Cubic Yards

25-5 Access Ramps 16

Each

Page 19: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 5 of 11

(Rev. 05/14/16)—Ver.2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

ITEM NO.

N

DESCRIPTION OF ITEM APPROXIMATE

QUANTITY UNIT

UNIT PRICE TOTAL

26-4 18-inch RCP Storm Drain - New140

Linear Feet

26-8 36-inch RCP Storm Drain – Modification1

Each

26-10 18-inch RCP Storm Drain Modification1

Each

26-15 Type 3 Outlet at Station 485+10 Lump Sum Lump Sum

27-1 Traffic Control Lump Sum Lump Sum

28-1 Uncoated Chain Link Fence (Type A1) 4,600

Linear Foot

28-2 Black Vinyl Coated Chain Link Fence (Type A2)

45,000 Linear Foot

28-3 Orange Fence (Exclusion Fence) 108,000

Linear Foot

28-4 Chain Link Gates – Single Swing Gate 5

Each

28-5 Chain Link Gates – Double Swing Gate 25

Each

Page 20: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 6 of 11

(Rev. 05/14/16)—Ver.2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

ITEM NO.

N

DESCRIPTION OF ITEM APPROXIMATE

QUANTITY UNIT

UNIT PRICE TOTAL

28-6 Miscellaneous Fencing Lump Sum Lump Sum

28-7 Poppy Jasper Mine Security Enclosure Lump Sum Lump Sum

30-1 Rock Slope Protection 5,300 Ton

30-2 Type 1 Grade Control Structures 13

Each

30-7 Chute and Pool Feature on Llagas Creek (Sta. 239+00 C-Line-1)

Lump Sum Lump Sum

30-8Chute and Pool Feature on Llagas

Creek Near Lake Silveira (Sta. 4005+00 C-Line-4)

Lump Sum Lump Sum

30-9 Instream Complexity Structure – Log-Rootwad Structure

163 Each

30-10Instream Complexity Structure –

Combination Log-Rootwad Boulder Structure

1 Each

30-11 Instream Complexity Structure – Stream Boulder

40 Each

30-12 Instream Complexity Structure – Triangular Boulder Cluster

39 Each

Page 21: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 7 of 11

(Rev. 05/14/16)—Ver.2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

ITEM NO.

N

DESCRIPTION OF ITEM APPROXIMATE

QUANTITY UNIT

UNIT PRICE TOTAL

30-13 Instream Complexity Structure – Wing Deflector

2 Each

30-14 Instream Complexity Structure – Coarse Woody Habitat

14 Each

30-16 Instream Complexity Structure – Spider Structure

1 Each

30-17 Erosion Control Blanket 3,200

Square Yard

34-3 18-inch Flap Gate2

Each

40-1 Planting Area Preparation Lump Sum Lump Sum

40-2 Single-Log Installation 32

Each

40-3 Five-Log Pile Installation 43

Each

40-4 Broadcast Seeding 7

Acres

40-5 Hydroseeding 75

Acres

Page 22: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 8 of 11

(Rev. 05/14/16)—Ver.2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

ITEM NO.

N

DESCRIPTION OF ITEM APPROXIMATE

QUANTITY UNIT

UNIT PRICE TOTAL

40-9 Irrigation Standpipe System Lump Sum Lump Sum

40-10 Irrigation Automated System Lump Sum Lump Sum

40-11 Irrigation Sleeve 1,000

Linear Foot

40-12 Planting Lump Sum Lump Sum

40-19 Establishment Maintenance 36

Month

41-1 Improvements at Lake Silveira Lump Sum Lump Sum

41-2 Improvements at Watsonville Road Lump Sum Lump Sum

41-3 Improvements at Middle Avenue Lump Sum Lump Sum

41.4 Improvements at Monterey Road Lump Sum Lump Sum

41-5 Improvements at Masten Avenue Lump Sum Lump Sum

Page 23: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 9 of 11

(Rev. 05/14/16)—Ver. 2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

ITEM NO.

N

DESCRIPTION OF ITEM APPROXIMATE

QUANTITY UNIT

UNIT PRICE TOTAL

41-6 Improvements at Rucker Avenue Lump Sum Lump Sum

41-7 Improvements at Buena Vista Avenue Lump Sum Lump Sum

41-29 Culvert at Drainage E (Station 183+75) Lump Sum Lump Sum

41-30 Culvert at Drainage F (Station 113+50) Lump Sum Lump Sum

41-31 Culvert at Rucker Creek (Station 108+00)

Lump Sum Lump Sum

41-32 Culvert at Church Creek (Station 707+00)

Lump Sum Lump Sum

42-1 Removal and Legal Disposal of Hazardous Waste Materials

3,300 Cubic Yard

42-2 Removal and Legal Disposal of Non-Hazardous Waste (Class II) Material

6,500 Cubic Yard

42-3 Excavated Materials Management Lump Sum Lump Sum

TOTAL BASE BID SECTION A: SUBTOTAL

Page 24: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

BID FORM NO. 1 (Rev.2) Proposal Form and Bid Items

Page 10 of 11

(Rev. 05/14/16)—Ver.2 Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

SECTION B — SUPPLEMENTAL CONTRACT ITEMS

ITEM NO. DESCRIPTION OF ITEM

APPROXIMATE QUANTITY

UNIT

UNIT PRICE TOTAL

SECTION B: SUPPLEMENTAL CONTRACT ITEMS These Bid Items may or may not be required. They may be deleted entirely or in part

at the sole discretion of the District. See Section 20.01.03 of these Specificatons

22-8 Water Well Destruction 1 Each

23-3c Imported Bedload Material 2,000 Ton

30-5 Grade Transition Structure at East Little Llagas Creek (Sta. 709+00 C-Line-2)

Lump Sum Lump Sum

40-6 Hydroseed Irrigation 1 Event

40-7 Broadcast Re-Seeding 9

1/8 Acre

40-8 Hydroseed Re-Seeding 14

Acre

40-13 Foliage Protection Cage Installation 100

Each

40-14 Root Protection Cage 100

Each

Page 25: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

BID FORM NO. 1 (Rev.2)Proposal Form and Bid Items

Page 3 of 3

This form must be completed in ink and changes must be initialed.

SECTION B — SUPPLEMENTAL CONTRACT ITEMS

Upper Llagas Phase 1: R 4, R 5, R 7A and Lake Silveira

(Rev. 05/04/16)—Ver.2

ITEM NO.

DESCRIPTION OF ITEM

APPROXIMATE QUANTITY

UNIT

UNIT PRICE

TOTAL

40-15 Supplemental Plug Container Plants

100

Each

40-16Supplemental Giant Reed Follow-up

Herbicide Control Event

2

Event

40-17Supplemental Himalayan Blackberry

Follow-up Herbicide Control Event

3

Event

40-18 Giant Reed Biomass Removal

1

Thousand Square Feet

40-20 Cutting Installation 100

Each

TOTAL SUPPLEMENTAL BID SECTION B SUBTOTAL:

TOTAL BID (SECTION A SUBTOTAL + SECTION B SUBTOTAL)

Total Bid (Section A Subtotal + Section B Subtotal ) will be used to determine the lowest bid.

Page 26: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

THIS P

AGE INTENTIO

NALLY LE

FT BLA

NK

Page 27: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ATTACHMENT 2 Sheet GC-10

Page 28: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

THIS P

AGE INTENTIO

NALLY LE

FT BLA

NK

Page 29: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

SOLI

CIT

ATIO

N N

O.:

FILE

NAM

E:

DR

AWN

BY:

CH

ECKE

D B

Y:

DES

IGN

ED B

Y:

DES

CR

IPTI

ON

1

D

2 3

C

4 5

A

B

MAR

KAP

PR

DAT

E:

FILE

NU

MBE

R:

SIZE

:D

ATE

CO

NTR

ACT

NO

.:

SHEET NUMBER

PAGE OF

®US Army Corpsof Engineers

22 x

34

April

201

9

FLO

OD

PR

OTE

CTI

ON

PR

OJE

CT

UPP

ER L

LAG

AS C

REE

KSA

NTA

CLA

RA

CO

UN

TY

C

ALIF

OR

NIA

0027

-009

-GC

1-G

C16

-PH

ASE

1.D

WG

RMC PROJ MNGRC27169

C46659

423

RMC PRINCIPAL

SUBMITTED:

GLENN HERMANSON

APPROVED:RMC TECH MNGR

SCVW

D P

RO

JEC

T N

O.

2617

4052

LYNDEL MELTON

C06

45SM

GC-10

PHAS

E 1

AND

PH

ASE

2C

IVIL

DET

AILS

5

G. H

erm

anso

n

J. M

ay

R. B

iche

tte

205

UPL

_UL_

GC

_502

7_62

296

ghermanson
Line
ghermanson
Line
ghermanson
Line
ghermanson
Line
ghermanson
Line
ghermanson
Callout
C-110
ghermanson
Callout
36"
ghermanson
Callout
43.2"
ghermanson
Callout
36"
ghermanson
Callout
25.2"
Page 30: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

 

 

Page 31: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ATTACHMENT 3 Sheet PP-23

Page 32: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

THIS P

AGE INTENTIO

NALLY LE

FT BLA

NK

Page 33: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

PP-23

PH

AS

E 1

PL

AN

A

ND

P

RO

FIL

E

ST

A 4

73

+0

0 T

O 4

81

+0

0

99

SO

LIC

IT

AT

IO

N N

O.:

FILE

N

AM

E:

DR

AW

N B

Y:

CH

EC

KE

D B

Y:

DE

SIG

NE

D B

Y:

DE

SC

RIP

TIO

N

1

D

2 3

C

4 5

A

B

MA

RK

AP

PR

DA

TE

:

FILE

N

UM

BE

R:

SIZ

E:

DA

TE

CO

NT

RA

CT

N

O.:

SHEET NUMBER

PAGE OF

®

US Army Corps

of Engineers

22 x 34

April 2019

FLO

OD

P

RO

TE

CT

IO

N P

RO

JE

CT

UP

PE

R LLA

GA

S C

RE

EK

SA

NT

A C

LA

RA

C

OU

NT

Y C

ALIF

OR

NIA

RE

AC

H 7A

P

LA

N-P

RO

.D

WG

RMC PROJ MNGRC27169

C46659

423

SM

RMC PRINCIPAL

SUBMITTED:

GLENN HERMANSON

APPROVED:

RMC TECH MNGR

SC

VW

D P

RO

JE

CT

N

O.

26174052

LYNDEL MELTON

C0645

SA

T, M

ER

LJK

, M

ER

CD

A

(408) 246-4848SANTA CLARA, CA 95050

1171 HOMESTEAD ROAD, STE 255CONSULTING CIVIL ENGINEERS

Schaaf Wheeler

UP

L_U

L_P

P_5027_62190

AutoCAD SHX Text
x
AutoCAD SHX Text
321.5
AutoCAD SHX Text
x
AutoCAD SHX Text
321.7
AutoCAD SHX Text
x
AutoCAD SHX Text
321.7
AutoCAD SHX Text
x
AutoCAD SHX Text
321.4
AutoCAD SHX Text
x
AutoCAD SHX Text
321.2
AutoCAD SHX Text
x
AutoCAD SHX Text
321.4
AutoCAD SHX Text
x
AutoCAD SHX Text
321.4
AutoCAD SHX Text
x
AutoCAD SHX Text
322.4
AutoCAD SHX Text
x
AutoCAD SHX Text
321.7
AutoCAD SHX Text
x
AutoCAD SHX Text
321.8
AutoCAD SHX Text
x
AutoCAD SHX Text
321.6
AutoCAD SHX Text
x
AutoCAD SHX Text
320.9
AutoCAD SHX Text
x
AutoCAD SHX Text
320.8
AutoCAD SHX Text
x
AutoCAD SHX Text
320.9
AutoCAD SHX Text
x
AutoCAD SHX Text
320.6
AutoCAD SHX Text
x
AutoCAD SHX Text
321.5
AutoCAD SHX Text
321.6
AutoCAD SHX Text
x
AutoCAD SHX Text
321.6
AutoCAD SHX Text
x
AutoCAD SHX Text
321.9
AutoCAD SHX Text
x
AutoCAD SHX Text
322.1
AutoCAD SHX Text
x
AutoCAD SHX Text
321.3
AutoCAD SHX Text
x
AutoCAD SHX Text
321.6
AutoCAD SHX Text
x
AutoCAD SHX Text
320.8
AutoCAD SHX Text
x
AutoCAD SHX Text
321.3
AutoCAD SHX Text
x
AutoCAD SHX Text
321.2
AutoCAD SHX Text
x
AutoCAD SHX Text
321.7
AutoCAD SHX Text
x
AutoCAD SHX Text
322.3
AutoCAD SHX Text
x
AutoCAD SHX Text
322.5
AutoCAD SHX Text
322.2
AutoCAD SHX Text
x
AutoCAD SHX Text
320.8
AutoCAD SHX Text
x
AutoCAD SHX Text
320.6
AutoCAD SHX Text
x
AutoCAD SHX Text
320.8
AutoCAD SHX Text
x
AutoCAD SHX Text
320.7
AutoCAD SHX Text
x
AutoCAD SHX Text
320.5
AutoCAD SHX Text
x
AutoCAD SHX Text
320.5
AutoCAD SHX Text
x
AutoCAD SHX Text
320.8
AutoCAD SHX Text
x
AutoCAD SHX Text
320.3
AutoCAD SHX Text
x
AutoCAD SHX Text
320.6
AutoCAD SHX Text
x
AutoCAD SHX Text
320.6
AutoCAD SHX Text
x
AutoCAD SHX Text
320.3
AutoCAD SHX Text
x
AutoCAD SHX Text
320.5
AutoCAD SHX Text
x
AutoCAD SHX Text
320.7
AutoCAD SHX Text
x
AutoCAD SHX Text
320.7
AutoCAD SHX Text
x
AutoCAD SHX Text
321.1
AutoCAD SHX Text
x
AutoCAD SHX Text
321.2
AutoCAD SHX Text
x
AutoCAD SHX Text
321.1
AutoCAD SHX Text
x
AutoCAD SHX Text
321.4
AutoCAD SHX Text
x
AutoCAD SHX Text
321.5
AutoCAD SHX Text
x
AutoCAD SHX Text
320.9
AutoCAD SHX Text
x
AutoCAD SHX Text
320.9
AutoCAD SHX Text
x
AutoCAD SHX Text
320.4
AutoCAD SHX Text
x
AutoCAD SHX Text
320.3
AutoCAD SHX Text
x
AutoCAD SHX Text
320.2
AutoCAD SHX Text
x
AutoCAD SHX Text
320.1
AutoCAD SHX Text
x
AutoCAD SHX Text
320.9
AutoCAD SHX Text
x
AutoCAD SHX Text
320.7
AutoCAD SHX Text
x
AutoCAD SHX Text
320.9
AutoCAD SHX Text
x
AutoCAD SHX Text
320.6
AutoCAD SHX Text
320
AutoCAD SHX Text
325
AutoCAD SHX Text
320
AutoCAD SHX Text
Grass
AutoCAD SHX Text
Piles
AutoCAD SHX Text
Dirt
AutoCAD SHX Text
Dirt
AutoCAD SHX Text
Dirt
AutoCAD SHX Text
Dirt
AutoCAD SHX Text
Dirt
AutoCAD SHX Text
Dirt
AutoCAD SHX Text
Dirt
AutoCAD SHX Text
x
AutoCAD SHX Text
321.6
AutoCAD SHX Text
x
AutoCAD SHX Text
321.5
AutoCAD SHX Text
x
AutoCAD SHX Text
321.4
AutoCAD SHX Text
x
AutoCAD SHX Text
321.1
AutoCAD SHX Text
x
AutoCAD SHX Text
320.6
AutoCAD SHX Text
x
AutoCAD SHX Text
320.6
AutoCAD SHX Text
x
AutoCAD SHX Text
320.8
AutoCAD SHX Text
x
AutoCAD SHX Text
320.4
AutoCAD SHX Text
x
AutoCAD SHX Text
320.5
AutoCAD SHX Text
x
AutoCAD SHX Text
320.2
AutoCAD SHX Text
x
AutoCAD SHX Text
319.8
AutoCAD SHX Text
x
AutoCAD SHX Text
319.7
AutoCAD SHX Text
x
AutoCAD SHX Text
320.4
AutoCAD SHX Text
x
AutoCAD SHX Text
321.1
AutoCAD SHX Text
x
AutoCAD SHX Text
321.4
AutoCAD SHX Text
x
AutoCAD SHX Text
321.2
AutoCAD SHX Text
x
AutoCAD SHX Text
321.3
AutoCAD SHX Text
320
AutoCAD SHX Text
Dirt
AutoCAD SHX Text
480+00
AutoCAD SHX Text
481+00
AutoCAD SHX Text
478+00
AutoCAD SHX Text
479+00
AutoCAD SHX Text
475+00
AutoCAD SHX Text
477+00
AutoCAD SHX Text
476+00
AutoCAD SHX Text
474+00
AutoCAD SHX Text
473+00
AutoCAD SHX Text
MATCHLINE
AutoCAD SHX Text
MATCHLINE
AutoCAD SHX Text
315
AutoCAD SHX Text
315
AutoCAD SHX Text
310
AutoCAD SHX Text
320
AutoCAD SHX Text
305
AutoCAD SHX Text
320
AutoCAD SHX Text
305
AutoCAD SHX Text
310
AutoCAD SHX Text
2+00
AutoCAD SHX Text
3+00
AutoCAD SHX Text
4+00
AutoCAD SHX Text
8+00
AutoCAD SHX Text
7+00
AutoCAD SHX Text
10+00
AutoCAD SHX Text
6+00
AutoCAD SHX Text
9+00
AutoCAD SHX Text
2+00
AutoCAD SHX Text
3+00
AutoCAD SHX Text
4+00
AutoCAD SHX Text
5+00
AutoCAD SHX Text
6+00
AutoCAD SHX Text
8+00
AutoCAD SHX Text
7+00
AutoCAD SHX Text
10+00
AutoCAD SHX Text
9+00
AutoCAD SHX Text
5+00
AutoCAD SHX Text
LLAGAS CREEK DIVERSION
AutoCAD SHX Text
1% POST-PROJECT FLOOD WATER SURFACE
AutoCAD SHX Text
FLOWLINE OF BANKFULL CHANNEL
AutoCAD SHX Text
7A-RB2 LINE
AutoCAD SHX Text
7A-LB2 LINE
AutoCAD SHX Text
TCX-6
AutoCAD SHX Text
E
AutoCAD SHX Text
APPROXIMATE EXISTING GROUND AT C-LINE-1
AutoCAD SHX Text
(E) VERIZON DEPTH UNKNOWN
AutoCAD SHX Text
S=0.0020
AutoCAD SHX Text
SCALE IN FEET
AutoCAD SHX Text
0
AutoCAD SHX Text
40
AutoCAD SHX Text
80
AutoCAD SHX Text
120
AutoCAD SHX Text
SCALE: 1"=40'
AutoCAD SHX Text
%%UPLAN
AutoCAD SHX Text
HORIZ: 1"=40' VERT: 1"=4'
AutoCAD SHX Text
%%UPROFILE
AutoCAD SHX Text
295
AutoCAD SHX Text
300
AutoCAD SHX Text
305
AutoCAD SHX Text
310
AutoCAD SHX Text
315
AutoCAD SHX Text
320
AutoCAD SHX Text
325
AutoCAD SHX Text
330
AutoCAD SHX Text
295
AutoCAD SHX Text
300
AutoCAD SHX Text
305
AutoCAD SHX Text
310
AutoCAD SHX Text
315
AutoCAD SHX Text
320
AutoCAD SHX Text
325
AutoCAD SHX Text
330
AutoCAD SHX Text
FOR CONTINUATION SEE PREVIOUS SHEET
AutoCAD SHX Text
FOR CONTINUATION SEE NEXT SHEET
AutoCAD SHX Text
3
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
481+00
AutoCAD SHX Text
480+00
AutoCAD SHX Text
479+00
AutoCAD SHX Text
478+00
AutoCAD SHX Text
477+00
AutoCAD SHX Text
476+00
AutoCAD SHX Text
475+00
AutoCAD SHX Text
474+00
AutoCAD SHX Text
473+00
AutoCAD SHX Text
MATCHLINE STATION 481+00 - FOR CONTINUATION SEE DRAWING PP-22
AutoCAD SHX Text
MATCHLINE STATION 473+00 - FOR CONTINUATION SEE DRAWING PP-24
AutoCAD SHX Text
CONSTRUCTION NOTES: MAINTENANCE ROAD (18' WIDE UON). SEE RP SHEETS FOR TYPE AND PROFILE. RAMP (18' WIDE UON). SEE DETAIL 2 ON SHEET GC-3. DRAINAGE SWALE. SEE DETAIL 4 ON SHEET GC-3. FENCE. SEE DETAIL 1 ON SHEET GC-4 CORRESPONDING TO TYPE CALL-OUT ON PP SHEET.
AutoCAD SHX Text
3
AutoCAD SHX Text
1
AutoCAD SHX Text
C-LINE-1
AutoCAD SHX Text
TOP OF BANK
AutoCAD SHX Text
TOP OF BANK
AutoCAD SHX Text
R7A-RAMP3
AutoCAD SHX Text
28
AutoCAD SHX Text
20
AutoCAD SHX Text
FOR INFORMATION ON 7A-LB2 SEE RP SHEETS
AutoCAD SHX Text
FOR INFORMATION ON 7A-RB2 SEE RP SHEETS
AutoCAD SHX Text
28
AutoCAD SHX Text
TYPE A L = 800'±THIS SHEET
AutoCAD SHX Text
28
AutoCAD SHX Text
TYPE A L = 800'±THIS SHEET
AutoCAD SHX Text
7
AutoCAD SHX Text
7
AutoCAD SHX Text
NOTES: 1. SEE DEMOLITION PLAN SHEETS FOR DEMOLITION INFORMATION. SEE DEMOLITION PLAN SHEETS FOR DEMOLITION INFORMATION. SEE CROSS SECTION SHEETS FOR CHANNEL CROSS SECTIONS. SEE INSTREAM COMPLEXITY SHEETS FOR INFORMATION ON INSTREAM COMPLEXITIES. SEE LANDSCAPING SHEETS FOR PLANTING AND IRRIGATION INFORMATION. SEE ROAD PROFILE SHEETS FOR MAINTENANCE ACCESS ROAD INFORMATION. 2. OFFSET DISTANCES ARE MEASURED FROM THE CONSTRUCTION OFFSET DISTANCES ARE MEASURED FROM THE CONSTRUCTION CONTROL LINE OF THE CHANNEL UNLESS NOTED OTHERWISE. SEE SURVEY LAYOUT DRAWINGS FOR CONTROL LINE LAYOUT. 3. EXISTING UTILITY LOCATIONS SHOWN ON PLANS ARE EXISTING UTILITY LOCATIONS SHOWN ON PLANS ARE APPROXIMATE. CONTRACTOR SHALL LOCATE EXISTING UNDERGROUND AND OVERHEAD UTILITY LINES AND POLES PRIOR TO CONSTRUCTION. CONTRACTOR TO COORDINATE WITH UTILITY COMPANIES SO THAT CONSTRUCTION ACTIVITIES DO NOT CONFLICT WITH EXISTING UTILITIES. 4. CONTRACTOR'S ATTENTION IS DIRECTED TO ARTICLE 15 OF THE CONTRACTOR'S ATTENTION IS DIRECTED TO ARTICLE 15 OF THE SPECIFICATIONS REGARDING UTILITIES. 5. AREAS WITHIN THE CWL SHALL BE GRADED SUCH THAT RUNOFF AREAS WITHIN THE CWL SHALL BE GRADED SUCH THAT RUNOFF DRAINS INTO THE CHANNEL UNLESS NOTED OTHERWISE. 6. SEE SHEET G-9 FOR CHANNEL AND ROAD NOMENCLATURE SEE SHEET G-9 FOR CHANNEL AND ROAD NOMENCLATURE DEFINITION. 7. SEE IRRIGATION AND PLANTING SHEETS FOR DECOMPACTION SEE IRRIGATION AND PLANTING SHEETS FOR DECOMPACTION AREAS.
ghermanson
PolyLine
ghermanson
PolyLine
ghermanson
PolyLine
Page 34: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

 

 

Page 35: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ATTACHMENT 4 Sheet C-112

Page 36: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

THIS P

AGE INTENTIO

NALLY LE

FT BLA

NK

Page 37: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

X

3

4

0

3

3

9

3

3

8

3

4

1

3

4

2

3

4

3

3

3

6

3

3

5

3

3

6

3

3

7

3

3

8

3

3

9

3

4

0

3

4

1

651

652

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

S

F

3

4

1

3

4

2

3

4

3

3

4

4

3

4

5

3

3

6

3

3

7

3

3

8

3

3

9

3

4

0

3

4

1

3

4

2

3

4

3

SO

LIC

IT

AT

IO

N N

O.:

FILE

N

AM

E:

DR

AW

N B

Y:

CH

EC

KE

D B

Y:

DE

SIG

NE

D B

Y:

DE

SC

RIP

TIO

N

1

D

2 3

C

4 5

A

B

MA

RK

AP

PR

DA

TE

:

FILE

N

UM

BE

R:

SIZ

E:

DA

TE

CO

NT

RA

CT

N

O.:

SHEET NUMBER

PAGE OF

®

US Army Corps

of Engineers

22

x 3

4

Ap

ril 2

01

9

FL

OO

D P

RO

TE

CT

IO

N P

RO

JE

CT

UP

PE

R L

LA

GA

S C

RE

EK

SA

NT

A C

LA

RA

C

OU

NT

Y C

AL

IF

OR

NIA

PO

PP

Y JA

SP

ER

.D

WG

RMC PROJ MNGRC27169

423

SM

RMC PRINCIPAL

SUBMITTED:

APPROVED:

SC

VW

D P

RO

JE

CT

N

O.

26

17

40

52

LYNDEL MELTON

C0

64

5

UP

L_

UL

_C

_5

02

7_

62

33

0

C-112

PO

PP

Y JA

SP

ER

M

IN

E

SE

CU

RIT

Y E

NC

LO

SU

RE

P

LA

N

N. P

HA

M

N. P

HA

M

S. F

ER

RA

NT

I

239

N

AutoCAD SHX Text
N 1859096.6837 E 6235007.0221
AutoCAD SHX Text
N 1859088.8107 E 6235008.4420
AutoCAD SHX Text
N 1859084.0780 E 6235039.3585
AutoCAD SHX Text
N 1859087.7083 E 6235054.9393
AutoCAD SHX Text
N 1859100.1573 E 6235071.3589
AutoCAD SHX Text
N 1859108.0303 E 6235069.9391
AutoCAD SHX Text
N 1859082.1171 E 6235019.1247
AutoCAD SHX Text
N 1859078.9897 E 6235039.5546
AutoCAD SHX Text
N 1859083.0805 E 6235057.1113
AutoCAD SHX Text
N 1859098.0262 E 6235076.8239
AutoCAD SHX Text
N 1859104.8748 E 6235075.5888
AutoCAD SHX Text
REMOVE EXIST CHAINLINK FENCE
AutoCAD SHX Text
INSTALL PERIMETER SECURITY FENCE, PRODUCT BY AMERISTAR FENCE, MODEL IMPASSE II, OR APPROVED EQUAL. SEE DETAIL 2 SHEET GC-4
AutoCAD SHX Text
PROPOSED CWL
AutoCAD SHX Text
PROPOSED CWL
AutoCAD SHX Text
INSTALL 4' SWING GATE, PRODUCT BY AMERISTAR FENCE, MODEL IMPASSE II, OR APPROVED EQUAL. SEE DETAIL 3 SHEET GC-4
AutoCAD SHX Text
EXIST CWL
AutoCAD SHX Text
EXIST CWL
AutoCAD SHX Text
TW ELEV = 335.00
AutoCAD SHX Text
TW ELEV = 338.00
AutoCAD SHX Text
TW ELEV = 342.00
AutoCAD SHX Text
TW ELEV = 342.00
AutoCAD SHX Text
TW ELEV = 342.00
AutoCAD SHX Text
TW ELEV = 340.00
AutoCAD SHX Text
GC-4
AutoCAD SHX Text
D
AutoCAD SHX Text
GC-4
AutoCAD SHX Text
D
AutoCAD SHX Text
GC-4
AutoCAD SHX Text
C
AutoCAD SHX Text
GC-4
AutoCAD SHX Text
C
AutoCAD SHX Text
APN 779-06-002
AutoCAD SHX Text
APN 779-06-030
AutoCAD SHX Text
18" X 18" FENCE POST FOUNDATION, TYP. SEE FENCE DETAIL 2 AND SECTION C, SHEET GC-4
AutoCAD SHX Text
CONCRETE SLAB, TYP. SEE FENCE DETAIL 2 AND SECTION D, SHEET GC-4
AutoCAD SHX Text
12" EXPANSION JOINT FILLER, TYP.
AutoCAD SHX Text
SEE NOTE 4
AutoCAD SHX Text
TW ELEV = 337.00
AutoCAD SHX Text
TW ELEV = 337.00
AutoCAD SHX Text
TW ELEV = 336.00
AutoCAD SHX Text
TW ELEV = 336.00
AutoCAD SHX Text
TW ELEV = 335.00
AutoCAD SHX Text
TW ELEV = 342.00
AutoCAD SHX Text
CONTOUR GRADING AS REQUIRED
AutoCAD SHX Text
CONTOUR GRADING AS REQUIRED
AutoCAD SHX Text
A
AutoCAD SHX Text
I
AutoCAD SHX Text
N
AutoCAD SHX Text
R
AutoCAD SHX Text
O
AutoCAD SHX Text
F
AutoCAD SHX Text
I
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
C
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
A
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
E
AutoCAD SHX Text
N
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
N
AutoCAD SHX Text
E
AutoCAD SHX Text
L
AutoCAD SHX Text
A
AutoCAD SHX Text
N
AutoCAD SHX Text
O
AutoCAD SHX Text
I
AutoCAD SHX Text
S
AutoCAD SHX Text
S
AutoCAD SHX Text
E
AutoCAD SHX Text
F
AutoCAD SHX Text
O
AutoCAD SHX Text
R
AutoCAD SHX Text
P
AutoCAD SHX Text
D
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
E
AutoCAD SHX Text
T
AutoCAD SHX Text
S
AutoCAD SHX Text
I
AutoCAD SHX Text
G
AutoCAD SHX Text
E
AutoCAD SHX Text
R
AutoCAD SHX Text
Exp.
AutoCAD SHX Text
No.
AutoCAD SHX Text
3/31/20
AutoCAD SHX Text
C81902
AutoCAD SHX Text
NGOC H. PHAM
AutoCAD SHX Text
CIVIL
AutoCAD SHX Text
LEGEND:
AutoCAD SHX Text
651, 6" DIAMETER BLACK OAK
AutoCAD SHX Text
652, 10" DIAMETER ALMOND
AutoCAD SHX Text
X
AutoCAD SHX Text
POPPY JASPER OUTCROP
AutoCAD SHX Text
NOTES: 1. THE CONTRACTOR SHALL VERIFY ALL CONTROLLING FIELD DIMENSIONS BEFORE THE CONTRACTOR SHALL VERIFY ALL CONTROLLING FIELD DIMENSIONS BEFORE ORDERING OR FABRICATING ANY MATERIAL. 2. FENCE SHALL CONFORM TO HORIZONTAL AND VERTICAL ALIGNMENT. FENCE SHALL CONFORM TO HORIZONTAL AND VERTICAL ALIGNMENT. 3. THE CONTRACTOR TO PERFORM SITE GRADING AS REQUIRED TO FACILITATE THE CONTRACTOR TO PERFORM SITE GRADING AS REQUIRED TO FACILITATE CONSTRUCTION OF THE ENCLOSURE IN ACCORDANCE WITH THE SPECIFICATIONS AND AS DIRECTED BY THE ENGINEER. 4. THE CONTRACTOR TO MODIFY DEPTH OF CONCRETE FOOTING/SLAB AS NEEDED THE CONTRACTOR TO MODIFY DEPTH OF CONCRETE FOOTING/SLAB AS NEEDED TO AVOID IMPACTING THE EXIST TREE ROOTS THAT GREATER THAN OR EQUAL 6" DIAMETER. THE CONTRACTOR SHALL NOTIFY THE ENGINEER BEFORE MODIFYING DEPTH OF THE FOOTING. 5. WHEN FENCING IS ON SLOPE, THE FENCE PANEL SHALL BE DESIGNED & WHEN FENCING IS ON SLOPE, THE FENCE PANEL SHALL BE DESIGNED & FABRICATED TO BE PLACED PARALLEL TO SLOPE. 6. LONGITUDINAL REINFORCEMENT TO STOP AT ALL EXPANSION JOINTS. LONGITUDINAL REINFORCEMENT TO STOP AT ALL EXPANSION JOINTS. 7. PROVIDE " EXPANSION JOINTS FILLERS BETWEEN THE CONCRETE FOOTING AND PROVIDE " EXPANSION JOINTS FILLERS BETWEEN THE CONCRETE FOOTING AND 12" EXPANSION JOINTS FILLERS BETWEEN THE CONCRETE FOOTING AND THE FENCE POST FOUNDATION.
AutoCAD SHX Text
DETAIL
AutoCAD SHX Text
SCALE: 1" = 3'
AutoCAD SHX Text
PLAN - POPPY JASPER MINE SECURITY ENCLOSURE
AutoCAD SHX Text
PP-28
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
1
AutoCAD SHX Text
ADDENDUM #4
AutoCAD SHX Text
6/18/19
Page 38: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

 

 

Page 39: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

ATTACHMENT 5 Sheet GS-3

Page 40: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,

THIS P

AGE INTENTIO

NALLY LE

FT BLA

NK

Page 41: CAPITAL PROGRAM SERVICES 5750 ALMADEN EXPRESSWAY … Addendum No. … · 3,000 psi and 4,000 psi) per this Article to construct reinforced concrete structures as shown on the Drawings,
ghermanson
Line
ghermanson
Line
ghermanson
Text Box
NOT IN CONTRACT