Capital Improvement Program

City of Warren, Ohio

April 2012

Page 2: Capital Improvement Program City of Warren, Ohio April 2012.

Parkman Road Improvements

Phase 1 (2008) - $2 million Phase 2 (2011) - $1 million Phase 3 (2014) - $3 million Parkman Road Bridge (2012) - $4.6 million Collective Cost = Over $10 million

Page 3: Capital Improvement Program City of Warren, Ohio April 2012.

Parkman Road Improvements – Phase 1

Constructed 2008 – 2009 West Market Street to west of Linda Drive NW $2 Million 100% funded through ODOT and FHWA

Page 4: Capital Improvement Program City of Warren, Ohio April 2012.

Parkman Road Improvements – Phase 2

Constructed in 2011 Southern Blvd. north to City Limits $1 Million 100% funded through ODOT and FHWA

Page 5: Capital Improvement Program City of Warren, Ohio April 2012.

Parkman Road Improvements – Phase 3

Scheduled for 2014 Linda Drive to Southern Blvd. New 5 lane roadway with left turn lanes between

Southern Blvd. & Coit Ave. NW to eliminate left turn accidents.

$3 Million 80% funded through ODOT and FHWA

Page 6: Capital Improvement Program City of Warren, Ohio April 2012.

Parkman Road Bridge Project

Is currently under construction – 2012 Bridge Replacement Left turn lanes at Tod Ave. & Lovers Lane $4.6 million Traditional ODOT Project Local Share is $28,000 (1/2% of total cost)

Page 7: Capital Improvement Program City of Warren, Ohio April 2012.

Warren Boulevard Bridge Project

This year - 2012 US 422 Bridge Replacement Over railroad between Logan and Chestnut $2 million Traditional ODOT Project 100% funded through ODOT and FHWA

Page 8: Capital Improvement Program City of Warren, Ohio April 2012.

Between 2003 and 2009 there were 25 accidents on Lovers Lane.

21 of the 25 accidents were single car failure-to-control accidents.

Lovers Lane Reconstruction

Page 9: Capital Improvement Program City of Warren, Ohio April 2012.

Lovers Lane – Phase 1

Reconstructed a vertical curve by cutting existing hill near the Warren Twp. Cemetery

Page 10: Capital Improvement Program City of Warren, Ohio April 2012.

Lovers Lane – Phase 1

Visibility and safety was improved by paint striping, guardrail, signage and clearing vegetation.

Page 11: Capital Improvement Program City of Warren, Ohio April 2012.

Lovers Lane Reconstruction – Ph 1

Resurfaced from West Market Street to Williamsburg Street.

Also resurfaced and striped portions of: Southern Blvd. Paige Ave. Perkinswood Blvd.

2011 - Phase 1 - $400,000 – Issue 2

Page 12: Capital Improvement Program City of Warren, Ohio April 2012.

Lovers Lane Reconstruction – Ph 2

An 800 foot section near Starlite Drive will be reconstructed to new grade.

New guardrail, signage, paint striping, and clearing of vegetation along the roadway.

Page 13: Capital Improvement Program City of Warren, Ohio April 2012.

Lovers Lane Reconstruction – Ph 2

Resurfacing from Williamsburg Street to Parkman Rd.

Also resurfacing portions of: Southern Blvd. Perkinswood Blvd. Atlantic St. Laird Ave. Berkshire Dr. Harvard Dr.

2012 - Phase 2 - $900,000 – Issue 2

Page 14: Capital Improvement Program City of Warren, Ohio April 2012.

CBD Road Projects: TRU- Park Ave.

Will be constructed this summer (2012) Fulton Street to the northern city limits. Cost is $650,000 ODOT/FHWA and Issue 2 Funding (100%).

Page 15: Capital Improvement Program City of Warren, Ohio April 2012.

CBD Road Projects Continued:

1. South Street & Summit Street Resurfacing 2011 (Traditional ODOT) Cost $1 million

2. TRU - High Street Resurfacing Project 2010 Cost - $365,000

3. TRU – 45 (Mahoning Ave.) Reconstruction 2010 Cost - $475,000

4. TRU - East Market St. Reconstruction 2008 – 2009 Cost - $1.8 million

Page 16: Capital Improvement Program City of Warren, Ohio April 2012.

Upcoming Federal Projects

2013 - Niles Road - $550,000 2014 - Pine Avenue - $900,00 2015 - Palmyra Road, Highland Ave.

& Main Ave. - $2 million 2016 - West Market St. - $2.5 million Collective Cost = $6 million

Page 17: Capital Improvement Program City of Warren, Ohio April 2012.

Requesting Federal & State Funds:

Youngstown Road Reconstruction Laird Ave. to Ridge Road $4 million

Youngstown Road Resurfacing Ridge Road to North Road $1 million

Page 18: Capital Improvement Program City of Warren, Ohio April 2012.

Decorative Crosswalks (2009 & 2010) Mahoning Avenue Lighting (2010) Warren Boulevard Trees (2011) Community Signs (Future Project)

Gateway Improvements

Page 19: Capital Improvement Program City of Warren, Ohio April 2012.

City Sign Ordinance

The City of Warren is presently reviewing its sign ordinance and discussing adoption of new regulations.

Page 20: Capital Improvement Program City of Warren, Ohio April 2012.

Greenway Bike Trail Phase 1 (2011) -

$1.2 million Phase 2 (2012) -

$1.4 million

Page 21: Capital Improvement Program City of Warren, Ohio April 2012.

Trails through Bullhead Park (Footbridge) Stone retaining wall repair at Packard Park Trails along river at Burbank Park Trails through the Lovers Lane parklands Overlook at the Mahoningside Property FHWA – $1.1 million – 2012 or 2013

Riverwalk Project

Page 22: Capital Improvement Program City of Warren, Ohio April 2012.

Capital Improvement Program

The opportunity to present the City of Warren’s Capital Improvement Program is greatly appreciated.

We look forward to implementing the plan and serving the citizens of the community.

Thank you.