Capital BudgetingCapital Budgeting Capital budgeting (or project/ investment appraisal) is the

process of planning, evaluating and selecting long-term investment decisions that are in line with the goal of investors’ wealth maximization.

Firm’s long-term investment decisions generally include expansion, acquisition, modernization and replacement of long-term assets and research and development projects.

It is used to compare and evaluate alternative projects-• financial and nonfinancial criteria• short and long-term benefits• fit with existing technology• effect on marketing and cost management.

Page 4: Capital Budget FINAL Slide

Capital Budgeting: Scholars’ Capital Budgeting: Scholars’ Points of ViewPoints of View

Project appraisal is a process of investigation and reasoning designed to assist a decision maker to reach an informed and rational choice. (Sugden & Williams)

A capital investment appraisal is a means of ensuring value for money in relation to developing an estate strategy and capital project. A capital investment appraisal is not meant to provide an indication of profit or loss for the institution as a whole, but rather a comparison of costs in relation to those areas of the estate where there is an opportunity or an inclination for change. (Baum T., & Mudambi R.)

Page 5: Capital Budget FINAL Slide

Scope of Capital BudgetingScope of Capital BudgetingCapital Budgeting involves:- Evaluation of investment project proposals that are strategic to business’s overall objectives. Estimation of after-tax incremental operating cash flows for investment projects. Estimation and evaluation of how much cash flows incurred for each of the investment proposals. Selection of an investment proposal that maximizes the return to the investors. Reevaluation of implemented investment projects continually and performing post audits for completed projects.

Page 6: Capital Budget FINAL Slide

Types of Investment Types of Investment DecisionsDecisions

There are typically two types of investment decisions: Selection decisions in terms of obtaining new facilities or

expanding existing facilities. Examples include:

1. Investment in long term assets such as property, plant and equipment.

2. Resource commitments in the form of new product development, market research, refunding of long term debt, introduction of a computer, etc.

Replacement decisions in terms of replacing existing facilities with new facilities. Examples include:

1. Replacing a manual bookkeeping system with a computerized system.

2. Replacing an inefficient lathe with one that is numerically controlled.

Page 7: Capital Budget FINAL Slide

Good Investment DecisionGood Investment Decision

Nature: The exchange of current funds for future benefits The funds are invested in long-term assets The future benefits will occur to the firm over a series of years.

Criteria:We need to ask ourselves the following questions when evaluating capital budgeting decision rules:

Does the decision rule adjust for the time value of money? Does the decision rule adjust for risk? Does the decision rule provide information on whether we are creating value for the firm?

Page 8: Capital Budget FINAL Slide

Capital Budgeting Capital Budgeting ConsiderationsConsiderations

The capital budgeting decision, under any technique, depends in part on a variety of considerations:

The availability of funds The relationships among proposed projects The company’s basic decision-making approach The risk associated with a particular project

Page 9: Capital Budget FINAL Slide

Phases of Capital BudgetingPhases of Capital BudgetingCapital budgeting is a multi-faceted activity. There are several sequential stages in the process.

Page 10: Capital Budget FINAL Slide

Phases of Capital Phases of Capital Budgeting Budgeting contd…contd…

Planning: A firm’s mission and vision is encapsulated in its strategic planning framework. A strategic plan is the grand design of the firm and clearly identifies the business the firm is in and where it intends to position itself in the future. Strategic planning translates the firm’s corporate goal into specific policies and directions, sets priorities, specifies the structural, strategic and tactical areas of business development, and guides the planning process in the pursuit of solid objectives.

Analysis: The focus of this phase of capital budgeting is on gathering, preparing, and summarizing relevant information about various project proposals which are being considered for inclusion in the capital budget.

Page 11: Capital Budget FINAL Slide

Phases of Capital Phases of Capital Budgeting Budgeting contd…contd…

Selection: In the selection phases project worthwhileness is being judged by applying various appraisal criteria. The selection rules associated with these criteria are as follows:

Criterion Accept Reject

Payback period (PBP) PBP< target period PBP> target period

Accounting rate of return (ARR)

ARR>target rate ARR<target rate

Net present value (NPV) NPV>0 NPV<0

Internal rate of return (IRR) IRR>cost of capital IRR<cost of capital

Benefit cost ratio (BCR) BCR>1 BCR<1

Page 12: Capital Budget FINAL Slide

Phases of Capital Phases of Capital Budgeting Budgeting contd…contd…

Financing: Once a project is selected, suitable financing arrangements have to be made. The two broad sources of finance for a project are equity and debt.

Implementation: The implementation phase for an industrial project, consists of several stages:

i.Project and engineering designs,

ii.Negotiations and contracting,

iii.Construction,

iv.Training and

v.Plant commissioning.

Page 13: Capital Budget FINAL Slide

Phases of Capital Phases of Capital Budgeting Budgeting contd…contd…

Review: Performance review should be done periodically to compare actual performance with projected performance. It is useful in the following ways:

i.It throws light on how realistic were the assumptions underlying the project;

ii.It provides a documented log of experience that is highly valuable in future decision making;

iii.It suggests corrective action to be taken in the light of actual performance;

iv.It helps in uncovering judgmental biases;

v.It induces a desired caution among project sponsors.

Page 14: Capital Budget FINAL Slide

Capital Budgeting: Importance & Capital Budgeting: Importance & Limitations Limitations

Importance LimitationsCapital budgeting decisions influence the firm’s growth in the long run.

Poor alignment between strategy and capital budgeting,

They affect the risk of the firm. Deficiencies in analytical techniques-Poorly identified base caseInadequately treated risk Improperly evaluated optionsLack of uniformity in assumptionsSide effects are ignored

They involve commitment of large amount of funds.

No linkage between compensation and financial measures,

They are irreversible, or reversible at substantial loss.

Reverse financial engineering,

They are among the most difficult decisions to make.

Weak integration between capital budgeting and expense budgeting,

Inadequate post-audits.

Page 15: Capital Budget FINAL Slide

Project Appraisal CriteriaProject Appraisal Criteria

Project Appraisal Criteria

Discounted Cash Flow Criteria (DCF) Non- discounted Cash Flow Criteria

Net PresentValue (NPV)

Internal Rate

of Return (IRR)

Profitability

Index (PI)

Payback Period

(PB)

DiscountedPayback

Period

AccountingRate ofReturn (ARR)

Page 16: Capital Budget FINAL Slide

Discounted Cash Flow Discounted Cash Flow Criteria (DCF)Criteria (DCF)

It considers what money will be worth in the

future.

Discounting – reduce value of future earnings to

reflect opportunity cost of an investment.

Page 17: Capital Budget FINAL Slide

Net Present Value (NPV)Net Present Value (NPV)

Evaluates if project rate of return is greater than,

equal to, or less than the desired rate of return.

It is the excess of the present value (PV) of cash

inflows generated by the project over the amount of

initial investment (I).

The PV of future cash flows is computed using the

cost of capital or minimum required rate of return

as the discount rate.

Page 18: Capital Budget FINAL Slide

Formulation of NPVFormulation of NPV

General formula for NPV is as follows:

n

0tt

t

)k 1 (

CF NPV

Where, CFt = Expected net cash flow at Period t k = Cost of capital or Discount rate n = Life of the project

Page 19: Capital Budget FINAL Slide

Acceptance Rules of NPVAcceptance Rules of NPV

NPV > 0 Accept (+)

NPV < 0 Reject (-)

NPV = 0 Indifferent ()

A positive NPV means that the project is expected to add value to the firm and will therefore increase the wealth of the owners.

Page 20: Capital Budget FINAL Slide

Calculation of NPV: An Calculation of NPV: An ExampleExample

Assuming, a new project A of which the following cash flows have been estimated: Tk.

•Year 0: CF = -1,65,000•Year 1: CF = 63,120•Year 2: CF = 70,800•Year 3: CF = 91,080

Required rate of return for assets=12%

Whether the investment should be accepted or not?

Page 21: Capital Budget FINAL Slide

Calculation of NPVCalculation of NPV

The calculation of the NPV of Project A will be:

NPV = Tk. -165,000 + 63,120/(1.12) + 70,800/(1.12)2

+ 91,080/(1.12)3

= Tk. -1,65,000 + 56,357 + 56,441 + 64,829

= Tk. 12,627

So, the investment’s NPV is positive and therefore should be accepted according to the acceptance rule of NPV.

Page 22: Capital Budget FINAL Slide

Decision Criteria Test: NPVDecision Criteria Test: NPV Does the NPV rule account for the time value of money? Does the NPV rule account for the risk of the cash flows? Does the NPV rule provide an indication about the

increase in value? Should we consider the NPV rule for our primary

decision rule?

The answer to all of these questions is Yes. Here, the risk of the cash flows is accounted for through

the choice of the discount rate.

Page 23: Capital Budget FINAL Slide

NPV: Benefits & NPV: Benefits & DrawbacksDrawbacks

Benefits Drawbacks Gives the correct financial decision in all cases.

Requires detailed long- term forecasts of incremental cash flow data.

Recognizes time value of money.

Sensitive to discount rates value of money.

Enables comparisons at different interest rates to be considered.

Useful for comparing similar projects with same cost.

Is relatively simple to calculate.

Page 24: Capital Budget FINAL Slide

Internal Rate of Return Internal Rate of Return (IRR)(IRR)

The discount rate which equates the PV of future cash inflows with the initial investment of a project and thus makes its NPV equal to zero.

Using PV tables it is computed by trial- and- error interpolation, which includes: Computation of NPV at the cost of capital (r1). If NPV is positive, then r2 is selected, which is higher than r1. If NPV is negative, then smaller rate r2 is selected rather than r1. The true IRR at which NPV= 0 must be somewhere in between these two rates. Again NPV is calculated using r2 . Interpolation is used for the exact rate.

Page 25: Capital Budget FINAL Slide

Formulation of IRRFormulation of IRRIRR is the value of r in the following equation:

Investment

Where, CFt = Expected net cash flow at Period t

r = Internal Rate of Return (IRR)

n = Life of the project

n

0tt

t

)r 1 (

CF

Page 26: Capital Budget FINAL Slide

Acceptance Rules of IRRAcceptance Rules of IRR

All projects should be accepted whose IRR exceeds the

company’s cost of capital.

IRR> Cost of Capital Accept (+)

IRR< Cost of Capital Reject (-)

For mutually exclusive projects, the projects with the

highest IRR should be chosen.

Page 27: Capital Budget FINAL Slide

Calculation of IRRCalculation of IRRAssuming the previously discussed example for NPV, where NPV>0 at 12% discount rate, we will now find out the IRR (NPV=0) of that project by following the trial- and- error method:

First, let us try 16% as the discount rate. At 16%, the project’s NPV will be:NPV= Tk. -165,000 + 63,120/(1.16) + 70,800/(1.16)2

+ 91,080/(1.16)3 = Tk. 381

Since the project’s NPV is still positive at 16%, a rate higher than 16% should be tried. So, when we try 17% then the project’s NPV will be:NPV= Tk. -165,000 + 63,120/(1.17) + 70,800/(1.17)2

+ 91,080/(1.17)3 = Tk. -2463

The true rate of return should lie between 16% and 17%.

Page 28: Capital Budget FINAL Slide

Calculation of IRRCalculation of IRR contd…contd…

We can find out a close approximation of the rate of return by the

method of linear interpolation as follows:

IRR= 16%+ (17%- 16%) (381/2,844)

= 16%+ 0.13= 16.13%

Since the investment’s IRR is greater than the cost of capital (12%), the investment should be accepted.

PV required Tk. 1,65,000 PV at lower rate, 16% 1,65,381PV at higher rate, 17% 1,62,537

3812,844

Difference

Page 29: Capital Budget FINAL Slide

NPV Profile for the ProjectNPV Profile for the Project

-20,000

-10,000

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22

Discount Rate

NP

V

IRR = 16.13%

Page 30: Capital Budget FINAL Slide

Decision Criteria Test: IRRDecision Criteria Test: IRR Does the IRR rule account for the time value of money? Does the IRR rule account for the risk of the cash flows? Does the IRR rule provide an indication about the

increase in value? Should we consider the IRR rule for our primary decision

criteria?

The answer to all of these questions is yes, although it is

not always as obvious. We can consider IRR as our primary decision criteria , but

not always as it has some problems that the NPV does not

have.

Page 31: Capital Budget FINAL Slide

IRR: Benefits and IRR: Benefits and DrawbacksDrawbacks

Benefits Drawbacks

Recognizes time value of money. Difficult to compute, as a project may have multiple rates rather than a unique rate of return.

Allows the risk associated with an investment project to be assessed.

Fails to recognize the varying size of investment in competing projects and their respective profitabilities.

Helps measure the worth of an investment.

It may also fail to indicate a correct choice between mutually exclusive projects under certain situations.

Allows the firm to assess whether an investment in the machine, etc. would yield a better return based on internal standards of return.

Allows comparison of projects with different initial outlays.

Page 32: Capital Budget FINAL Slide

NPV vs. IRRNPV vs. IRR NPV and IRR will generally give us the same decision.

Exceptions:

Nonconventional cash flows – cash flow signs change more than once

Mutually exclusive projects• Initial investments are substantially different

(issue of scale)• Timing of cash flows is substantially different

The NPV method has the advantage that the end result of the computations is expressed in amount and not in a percentage.

Page 33: Capital Budget FINAL Slide

NPV vs. IRR NPV vs. IRR contd…contd…

Whenever there is a conflict between NPV and another decision rule, NPV should always be chosen. Because:

Individual projects can be added. It can be used in situations where the required

rate of return varies over the life of the project.

The IRR of individual projects cannot be added or averaged to derive the IRR of a combination of projects.

Page 34: Capital Budget FINAL Slide

IRR and Nonconventional IRR and Nonconventional Cash FlowsCash Flows

When the cash flows change sign more than once, there is more than one IRR. Then problem occurs like, which one should we use to make our decision?

When we solve for IRR we are solving for the root of an equation, and when we cross the x-axis more than once, there will be more than one return that solves the equation.

Another type of nonconventional cash flow involves a “financing” project, where there is a positive cash flow followed by a series of negative cash flows. In this case, our decision rule reverses, and we accept a project if the IRR is less than the cost of capital, since we are borrowing at a lower rate.

Page 35: Capital Budget FINAL Slide

Example : Nonconventional Example : Nonconventional Cash FlowsCash Flows

Assuming an investment will cost Tk. 90,000 initially

and will generate the following cash flows:

Year 1: 132,000

Year 2: 100,000

Year 3: -150,000The required return is 15%.Should we accept or reject the project?

Page 36: Capital Budget FINAL Slide

NPV ProfileNPV Profile

($10,000.00)

($8,000.00)

($6,000.00)

($4,000.00)

($2,000.00)

$0.00

$2,000.00

$4,000.00

0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45 0.5 0.55

Discount Rate

NP

VIRR = 10.11% and 42.66%

We should accept the project if the required return is between 10.11% and 42.66% because none of the two rates of IRR will work satisfactorily. So, simply we will follow NPV, which is positive at a required return of 15%, and should Accept.

Page 37: Capital Budget FINAL Slide

IRR and Mutually IRR and Mutually Exclusive ProjectsExclusive Projects

Mutually exclusive projects• If we choose one, we cannot choose the other.• Example: We can choose to get admitted in either

A&IS or Finance Department, but not both.

Intuitively, we would use the following decision rules: NPV – project with the higher NPV should be

chosen. IRR – project with the higher IRR should be chosen.

Page 38: Capital Budget FINAL Slide

Example With Mutually Example With Mutually Exclusive ProjectsExclusive Projects

Period Project A

Project B

0 -500 -400

1 325 325

2 325 200

IRR 19.43% 22.17%

NPV 64.05 60.74

The required return for both projects is 10%.

Which project should we accept and why?

Page 39: Capital Budget FINAL Slide

NPV ProfilesNPV Profiles

($40.00)

($20.00)

$0.00

$20.00

$40.00

$60.00

$80.00

$100.00

$120.00

$140.00

$160.00

0 0.05 0.1 0.15 0.2 0.25 0.3

Discount Rate

NP

V AB

IRR for A = 19.43%

IRR for B = 22.17%

Crossover Point = 11.8%

If the required return is less than the crossover point of 11.8%, then we should choose A, and B will be chosen in the opposite case. Here, A fulfills the condition and also has higher NPV. So, to maximize wealth and to avoid unreliability of IRR we’ll go for the project with larger NPV, which is project A.

Page 40: Capital Budget FINAL Slide

Modified Internal Rate of Modified Internal Rate of ReturnReturn(MIRR)(MIRR)

To overcome the limitations of IRR, Modified Internal Rate

of Return method (MIRR) can be adopted:

Terminal value of cash inflow

PV of cash outflow = ---------------------------------------

(1 + MIRR)ⁿCalculates the net present value of all cash outflows

using the borrowing rate.Calculates the net future value of all cash inflows using the investing rate.Finds the rate of return that equates these values.

Page 41: Capital Budget FINAL Slide

MIRR: Benefits and MIRR: Benefits and DrawbacksDrawbacks

Benefits Drawbacks

MIRR assumes that project

cash flows are reinvested at the

cost of capital. Hence it

reflects better the profitability

of a project.

For choosing among mutually

exclusive projects of different

size, NPV is a better

alternative in measuring the

contribution of each project to

the value of the firm.

The problem of multiple rates does not exist.

Page 42: Capital Budget FINAL Slide

Profitability Index (PI)Profitability Index (PI)

PI is the ratio of the discounted cash inflows, at the

required rate of return, to the initial cash outflow of the

investment.

It is used as a mean of ranking projects in descending

order of attractiveness, especially when resources are

limited.

Also known as benefit- cost ratio.

Page 43: Capital Budget FINAL Slide

Formulation of PIFormulation of PI

The formula for calculating PI is as follows:

PV of cash inflows PV(CFt)

PI= ------------------------- = -------------

Initial cash outlay Co

n CFt

= ------------- // CFo

t=1

(1 + k)t

Page 44: Capital Budget FINAL Slide

Acceptance Rules of PIAcceptance Rules of PI

PI> 1.0 Accept (+)

PI< 1.0 Reject (-)

PI= 1.0 Indifferent ()

Page 45: Capital Budget FINAL Slide

Calculation of PICalculation of PI

The Profitability Index of project A will be:

PI= Tk. 1,77,627// Tk. 1,65,000 = Tk. 0.077

Since this project generates Tk. 0.077 for each Taka invested and its PI< 1, the project should be rejected.

Page 46: Capital Budget FINAL Slide

PI: Benefits and PI: Benefits and DrawbacksDrawbacks

Benefits Drawbacks It can discriminate better between large and small investments and hence is preferable to the NPV criterion.

It provides no means for aggregating several smaller projects into a package that can be compared with a large project.

When the capital budget is limited in the current period, PI may rank projects correctly in the order of decreasingly efficient use of capital.

When cash outflows occur beyond the current period, the PI criterion is unsuitable as a selection criterion.

Recognizes time value of money and easy to compute as well.

Page 47: Capital Budget FINAL Slide

NPV vs. PINPV vs. PI The NPV and PI yield same accept or reject rules, because

PI can be grater than one only when the project’s NPV is

positive. In case of marginal projects, NPV will be zero and PI will

be equal to one. The NPV method should be preferred, except under

capital rationing, because the NPV reflects the net

increase in the firm’s wealth. But a conflict may arise between the methods if a choice

between mutually exclusive projects has to be made. In

this case between projects with same NPV, the one with

lower initial cost or higher PI will be selected.

Page 48: Capital Budget FINAL Slide

Payback periodPayback period

The payback period is the length of time required for a

firm to recover its original investment ,it tells how long

it will take a project to break even.

Calculated by:

Estimating the cash flows, and Subtracting the future cash flows from the initial cost

until the initial investment has been recovered.

Page 49: Capital Budget FINAL Slide

Formulation of Payback Formulation of Payback PeriodPeriod

In case of Uniform Cash Flows, the formula of Payback period is:

Net initial investment

Payback period= ------------------------------------------

Uniform increase in annual future

cash flows

Example: If a project’s initial outlay= Tk. 50,000, annual cash inflow= Tk. 12,500 for 7 years, then:

Tk. 50,000

PB= ------------------= 4 years

Tk. 12,500

Page 50: Capital Budget FINAL Slide

Acceptance Rules of Acceptance Rules of Payback periodPayback period

A project would be accepted if its payback period is less than the maximum or standard payback period set by management.

Shortest payback period gives highest ranking to a project, where lowest ranking is given to a project with highest payback period.

Between two mutually exclusive projects, the project with shorter payback period will be selected.

Generally a payback period of 3 years or less is preferred.

According to some advisors, project with payback period of less than a year should be considered essential.

Page 51: Capital Budget FINAL Slide

Calculation of Payback Calculation of Payback Period: Nonuniform Cash Period: Nonuniform Cash

FlowsFlowsAssuming that, project A will be accepted if it pays back within 2 years (standard payback period). So, whether we will accept or reject the project?Adding up the cash inflows (Tk. 63,120, Tk. 70,800, and Tk. 91,080), we find that in the first 2 years Tk. 1,33,920 of the original outlay of Tk. -1,65,000 is recovered. Third year’s cash inflow is Tk. 91,080 and only Tk. 31,080 of the original outlay remains to be recovered. Now, if the cash inflows occur evenly during the year, the time required to recover Tk. 31,080 will be:(Tk. 31,080/Tk. 91,080) X 12 months= 4 months. Thus, the payback period is 2 years and 4 months.Again, if the cash inflows occur at the end of the year, the payback period will be 3 years.As in both the cases, payback period is more than the standard period of 2 years, the project should be rejected.

Page 52: Capital Budget FINAL Slide

Decision Criteria Test: Payback Decision Criteria Test: Payback PeriodPeriod

Does the payback rule account for the time value of money? Does the payback rule account for the risk of the cash flows? Does the payback rule provide an indication about the increase in value? Should we consider the payback rule for our primary decision rule?

The answer to all of these questions is No.

Page 53: Capital Budget FINAL Slide

Payback Period: Benefits and Payback Period: Benefits and DrawbacksDrawbacks

Benefits Drawbacks Easy to understand. Ignores the time value of

money. Adjusts for uncertainty of later cash flows.

Requires an arbitrary cutoff point.

Biased towards liquidity. Ignores cash flows beyond the cutoff date. Biased against long-term projects, such as research and development, and new projects.

Page 54: Capital Budget FINAL Slide

Discounted Payback PeriodDiscounted Payback Period

Computes the present value of each cash flow and then determine how long it takes to pay back on a discounted basis.

Compares to a specified required period.

Acceptance Rule – The project should be accepted if it pays back on a discounted basis within the specified time.

Page 55: Capital Budget FINAL Slide

Calculation of Discounted Calculation of Discounted Payback Period: An ExamplePayback Period: An Example

Assuming that, we will accept project A if it pays back on a discounted basis in 2 years. Shall we accept or reject the project?

First we will Compute the PV for each cash flow and determine the payback period using discounted cash flows:

Year 1: 165,000 – 63,120/1.121 = 108,643Year 2: 108,643 – 70,800/1.122 = 52,202Year 3: 52,202 – 91,080/1.123 = -12,627

So, the project pays back in year 3

Since, it doesn’t pay back on a discounted basis within the required 2-year period, we should reject the project.

Page 56: Capital Budget FINAL Slide

Decision Criteria Test: Decision Criteria Test: Discounted Payback PeriodDiscounted Payback Period

Does the discounted payback rule account for the time value of money? Does the discounted payback rule account for the risk of the cash flows? Does the discounted payback rule provide an indication about the increase in value? Should we consider the discounted payback rule for our primary decision rule?

The answer to the first two questions is Yes. The answer to the third question is No because of the arbitrary cut-off date. Since the rule does not indicate whether or not we are creating value for the firm, it should not be the primary decision rule.

Page 57: Capital Budget FINAL Slide

Accounting Rate of Return Accounting Rate of Return (ARR)(ARR)

Looks at the profit generated by the investment compared to the cost of the investment.

This gives the business a percentage figure showing the average rate of return.

Businesses can then compare this figure to how much they would get with alternative investments or the bank.

Also known as ‘Average Rate of Return’, and ‘Return on Investment (ROI)’.

Page 58: Capital Budget FINAL Slide

Formulation of ARRFormulation of ARRARR can be determined by the following equation:

Average incomeARR= ----------------------------------- Average investment

Or, it can be defined in terms of earnings after taxes without an adjustment for interest i.e. EBIT(1-T). Thus: n ∑ EBITt( 1-T) /n t=1

ARR= ------------------------------ (Io+ In)/2Where, EBIT= earnings before interest & taxes, T= tax rate, Io= BV of investment in the beginning, In= BV of investment at the end of n number of years.

Page 59: Capital Budget FINAL Slide

Acceptance Rules of ARRAcceptance Rules of ARR

All those projects are to be accepted whose ARR is higher than the minimum rate established by the management and projects are to be rejected which have ARR less than that preset rate.

Project with highest ARR will be ranked as number one and lower rank would be assigned to the project with lowest ARR.

Page 60: Capital Budget FINAL Slide

Calculation of ARRCalculation of ARRAssuming a 50% tax rate for project A and, a straight- line depreciation method is also assumed to be used here. We also assume that, an average return of 15% from project A is required. Shall we accept or reject the project?

Calculation of ARR

Year 1 Year 2 Year 3 Average

EBDIT 63,120 70,800 91,080 75,000

Depreciation 55,000 55,000 55,000 55,000

EBIT 8,120 15,800 36,080 20,000

Taxes at 50% 4,060 7,900 18,040 10,000

[EBIT(1-T)] 4,060 7,900 18,040 10,000

Book value of investment:

Beginning 1,65,000 1,10,000 55,000

Ending 1,10,000 55,000 -

Average 1,37,500 82,500 27,500 82,500

(Tk.)

Page 61: Capital Budget FINAL Slide

Calculation of ARR Calculation of ARR contd…contd…

10,000So, ARR of project A= ------------ X 100 82,500

= 12.12%

Since, the ARR of the project is lower than the preset rate, the project should be rejected.

Page 62: Capital Budget FINAL Slide

Decision Criteria Test: ARRDecision Criteria Test: ARR Does the AAR rule account for the time value of money? Does the AAR rule account for the risk of the cash flows? Does the AAR rule provide an indication about the

increase in value? Should we consider the AAR rule for our primary

decision rule?

The answer to all of these questions is No. In fact, this rule is even worse than the payback rule in

that it doesn’t even use cash flows for the analysis. Only a few large firms employ the payback and/or ARR

methods exclusively.

Page 63: Capital Budget FINAL Slide

ARR: Benefits and DrawbacksARR: Benefits and Drawbacks

Benefits Drawbacks

Easy to calculate. Not a true rate of return; time value of money is ignored.

Needed information will usually be available.

Uses an arbitrary benchmark cutoff rate.

Based on accounting net income and book values, not cash flows and market values.

Page 64: Capital Budget FINAL Slide

ARR and IRRARR and IRR

The ARR tends to understate the IRR for earlier years and overstate it for later years.

The ARR and the IRR can be the same only if the depreciation schedule is equal to the economic depreciation schedule.

Inflation and creative accounting tend to create a discrepancy between the ARR and the IRR.

Page 65: Capital Budget FINAL Slide

Goal Congruence Issues in Goal Congruence Issues in Capital BudgetingCapital Budgeting

Inconsistency between capital budgeting decision

making and management performance evaluation

persists when a company uses. NPV method for capital budgeting decisions and ARR

method to evaluate performance or ARR for both purposes Inconsistency means managers are tempted to make

capital budgeting decisions on the basis of the method by

which they are being evaluated. This conflict can be reduced by evaluating managers on

a project-by-project basis and by the amount and timing

of forecasted cash flows.

Page 66: Capital Budget FINAL Slide

Assessment of Basic Assessment of Basic Evaluation MethodsEvaluation Methods

Considerations NPV PI IRR Payback

Period

ARR

TheoreticalConsiders all cash flows Yes Yes Yes No ?

Discounts CFs at the opportunity cost of fund Yes Yes No No No

Satisfies the principle of value additivity Yes No No ? ?

From a set of mutually exclusive projects chooses the projects which maximize shareholder wealth Yes No No ? ?

PracticalSimple method Yes Yes Yes Yes Yes

Requires limited information No No No Perhaps Yes

Gives a relative measure No Yes Yes No Yes

Page 67: Capital Budget FINAL Slide

Post Investment AuditPost Investment Audit A post investment audit compares the actual results for a

project to the costs and benefits expected at the time the project was selected.

It provides management with feedback about performance.

It is performed after project has stabilized. Same analysis techniques are used. Identifies areas where results differ from expectation. Evaluates capital budgeting process, particularly original

projections, problems with implementation, and sponsors credibility.

Page 68: Capital Budget FINAL Slide

Qualitative Techniques of Qualitative Techniques of Project AppraisalProject Appraisal

As well as financial methods firms need to consider:• Corporate image – we may reject an investment

opportunity as it will reflect badly on our business.• Corporate objectives – also have to judge if the

investment is aligned to our corporate objectives• Environmental and ethical reasons – is the investment

environmentally and ethically sound• Industrial relations – what is the impact on the work

force – does it decrease jobs? Some companies also consider intuition, security and

social considerations as important qualitative factors.

Page 69: Capital Budget FINAL Slide

Role of JudgementRole of Judgement The opportunities and constraints of selecting a project, its

evaluation of qualitative and quantitative factors, and the weightage on every bit of pros and cons, cost-benefit analysis, etc., are essential elements of judgement.

Judgement and intuition should definitely be used when a decision of choice has to be made between two or more, closely beneficial projects, or when it involves changing the long-term strategy of the company. For routine matters, liquidity and profits should be preferred over judgement.

It plays a very important role in determining the reliability of figures with the help of qualitative methods as well as other known financial matters affecting the projects.

Capital investment decisions that are strategic in nature require managers to consider a broad range of factors that may be difficult to estimate.

Page 70: Capital Budget FINAL Slide

Strategic Considerations in Strategic Considerations in Capital BudgetingCapital Budgeting

Capital investment decisions that are strategic in nature

require managers to consider a broad range of factors that

may be difficult to estimate. Customer Value and Capital Budgeting NPV can also be used to evaluate the value of customers. The higher the profitability of “customer churn”, the

lower the NPV of the customer. Investment in Research and Development “Real options” of R&D investments increases the NPV of

investment projects.

Page 71: Capital Budget FINAL Slide

Project Cash Flow and Project Cash Flow and Risk AnalysisRisk Analysis

Page 72: Capital Budget FINAL Slide

Risks in Capital BudgetingRisks in Capital Budgeting

Three types of risk are relevant in capital budgeting:

Stand-alone risk

Corporate risk

Market (or beta) risk

Page 73: Capital Budget FINAL Slide

Stand- Alone RiskStand- Alone Risk

The project’s risk if it were the firm’s only asset and

there were no shareholders.

Ignores both firm and shareholder diversification.

Measured by the or CV of NPV, IRR, or MIRR.

Page 74: Capital Budget FINAL Slide

Corporate RiskCorporate Risk Reflects the project’s effect on corporate earnings

stability.

Considers firm’s other assets (diversification within

firm).

Depends on: project’s , and its correlation with returns on firm’s other

assets.

Measured by the project’s corporate beta.

Page 75: Capital Budget FINAL Slide

Market RiskMarket Risk

Reflects the project’s effect on a well-diversified

stock portfolio.

Takes account of stockholders’ other assets.

Depends on project’s s and correlation with the

stock market.

Measured by the project’s market beta.

Page 76: Capital Budget FINAL Slide

Techniques of Risk Techniques of Risk AnalysisAnalysis

Statistical Techniques: To measure and incorporate risk in capital budgeting two important statistical methods are used, which are: expected monetary value, and standard deviation.

Conventional Techniques: Decision- makers in practice may handle risk in conventional ways. Such as: they may use a shorter payback period, or conservative forecasts of cash flows, or discount net cash flows at the risk- adjusted discount rates.

Page 77: Capital Budget FINAL Slide

Capital RationingCapital Rationing It occurs any time there is a budget ceiling, or

constraints, on the amount of funds that can be

invested during a specific period, such as a year.

When capital is rationed over multiple periods; several

alternative methods can be applied to the capital

rationing problem.

If capital is to be rationed for only the current period,

selecting projects by descending order of profitability

index generally leads to a selection of a project mix

that adds most of firm value.

Page 78: Capital Budget FINAL Slide

Sensitivity AnalysisSensitivity Analysis

Shows how changes in a variable such as unit sales

affect NPV or IRR.

Each variable is fixed except one. Change this one

variable to see the effect on NPV or IRR.

Answers “what if” questions, e.g. “What if sales

decline by 30%?”

Page 79: Capital Budget FINAL Slide

Illustration: Sensitivity Illustration: Sensitivity AnalysisAnalysis

Change from __ Resulting NPV (000s)_____ Base Level Unit Sales Salvage k_ 30% $ 10 $78 $105

-20 35 80 97 -10 58 81 89 0 82 82 82+10 105 83 74+20 129 84 67+30 153 85 61

Page 80: Capital Budget FINAL Slide

82

NPV(000s)

Unit Sales

Salvage

k

-30 -20 -10 10 20 30Base Value

Page 81: Capital Budget FINAL Slide

Results of Sensitivity Results of Sensitivity AnalysisAnalysis

Steeper sensitivity lines show greater risk. Small

changes result in large declines in NPV.

Unit sales line is steeper than salvage value or k, so

for this project, should worry most about accuracy

of sales forecast.

Page 82: Capital Budget FINAL Slide

Sensitivity Analysis: Sensitivity Analysis: Benefits & DrawbacksBenefits & Drawbacks

Benefits Drawbacks

Gives some idea of stand- alone risk.

Does not reflect diversification.

Identifies dangerous variables.

Says nothing about the likelihood of change in a variable, i.e. a steep sales line is not a problem if sales won’t fall.

Gives some breakeven information.

Ignores relationships among variables.

Page 83: Capital Budget FINAL Slide

Scenario AnalysisScenario Analysis

Examines several possible situations, usually worst

case, most likely case, and best case.

Provides a range of possible outcomes.

Page 84: Capital Budget FINAL Slide

Illustration: Scenario Illustration: Scenario AnalysisAnalysis

Assuming that, we know with certainty all variables except unit sales, which could range from 900 to 1,600.

ScenarioScenario Probability Probability NPV(000)NPV(000) Worst 0.25 $ 15 Base 0.50 82 Best 0.25 148

E(NPV) = $ 82 (NPV) = 47

CV(NPV) = s(NPV)/E(NPV) = 0.57

Page 85: Capital Budget FINAL Slide

Simulation AnalysisSimulation Analysis A computerized version of scenario analysis which

uses continuous probability distributions.

Computer selects values for each variable based on

given probability distributions.

NPV and IRR are calculated.

Process is repeated many times (1,000 or more).

End result: Probability distribution of NPV and IRR

based on sample of simulated values.

Generally shown graphically.

Page 86: Capital Budget FINAL Slide

Monte Carlo SimulationMonte Carlo Simulation Monte Carlo simulation of capital budgeting projects

is often viewed as a step beyond either sensitivity

analysis or scenario analysis.

Interactions between the variables are explicitly

specified in Monte Carlo simulation; so, at least

theoretically, this methodology provides a more

complete analysis.

While the pharmaceutical industry has pioneered

applications of this methodology, its use in other

industries is far from widespread.

Page 87: Capital Budget FINAL Slide

Computation Steps: Computation Steps: Monte Carlo SimulationMonte Carlo Simulation

Step 1: Specify the Basic Model

Step 2: Specify a Distribution for Each Variable in the

Model

Step 3: The Computer Draws One Outcome

Step 4: Repeat the Procedure

Step 5: Calculate NPV

Page 88: Capital Budget FINAL Slide

When we talk about a project we have to keep full attention on the cash flows of that project . It is the most critical step. Because the cost and revenue forecasting of a large complex project often shows a big forecasting error. Suitable example may be Padma bridge.

Before making cash flow analysis, we should keep in mind some relevant Issues.

Interest Payment:Interest Payment:Common mistakes made by many students and financial analysts is that they subtracts interest payment in estimating project cash flows .the cost of the debt is already embedded in the WACC(weighted average cost of capital).so subtracting interest payment from the project cash flow would amount to double counting interest costs.

Relevant Issues in Capital BudgetingRelevant Issues in Capital Budgeting

Page 89: Capital Budget FINAL Slide

Relevant Issues in Capital Relevant Issues in Capital BudgetingBudgeting

Contd…Contd…Sunk Cost:Sunk Cost:We focus on the cash flow if and only if we accept the project this cash flows are called incremental cash flows. For example assuming, standard chartered has considered whether to establish a branch in Sylhet and for site analysis they hired a consulting firm. For this task they paid tk. 2,00,000 and undoubtedly it is a sunk cost for that firm. Because we know a sunk cost is an outlay that has already occurred & it is not affected by the decision under condition.so Either the project accepted or rejected, should this cost be taken into consideration in project cash flow analysis ?

The answer is no. because sunk cost does not fall under incremental cash flow.

Opportunity cost:Opportunity cost:Agrani bank owns a piece of land in Konabari, Gazipur, which is suitable for a branch location, now in project cash flow analysis should the cost of the land be disregarded in cash flow estimation in the argue that no additional cash outlay be required? The answer is no because there is an opportunity cost. If this land have a market value tk.1,50,000, then that value should be charged against the project.

Page 90: Capital Budget FINAL Slide

Relevant Issues in Capital Relevant Issues in Capital BudgetingBudgeting

Contd…Contd… Externalities: Externalities: Another potential problem involves the effects of a project on the other parts on the firm. which is called externalities.• A suitable example would be Mina bazar. suppose Mina bazar opened its new branch in dhanmondi-5.Now many of its customers who previously purchased their daily necessities from mohammadpur branch, will come to this new branch. Thus net income provided by this customers should not be treated as incremental cash flows in the capital budgeting decision.

Cannibalization: Cannibalization: Another problem in project cash flow estimation is cannibalization. When a new product takes away sales from existing product , then we call this situation as Cannibalization. A suitable example may clear this concept-• Nautica international inc. is a American company that sales sport wares. Nautica sales its products to the traditional retailers. These retailers adds a mark up &they further sales this commodities to the consumers.• Now if Nautica open a new own online store , then it could potentially increase its profit margin by huge amount.

Page 91: Capital Budget FINAL Slide

Relevant Issues in Capital Relevant Issues in Capital BudgetingBudgeting

Contd…Contd…• But internet sales would most probably cannibalize its existing sales. that is the new project will decrease its existing sales stream. Even worse , dealers/ retailers might react adversely by moving their product line to another brands.

Inflation Adjustment:Inflation Adjustment:inflation is a fact of life in Bangladesh. Recently it has been touched two digit. In the absence of inflation the real rate (rr) would be equal to nominal rate. Moreover , the real & nominal expected cash flow RCFt & NCFt would also be equal .But when the expected rate of inflation is positive then all of the projects cash flow including depreciation related items also should be rise at the rate i. in this case the nominal net cash flow NCFt will increase at the rate of i percent, result will be ,

NCFt =RCFt (1+i)^tThus the cost of capital which is used as the discount rate calculation formula will be: (1+rn) = (1+rr) X (1+i)

Page 92: Capital Budget FINAL Slide

Relevant Issues in Capital Relevant Issues in Capital BudgetingBudgeting

Contd…Contd…Tax & Depreciation Effect: • Tax have a major effect on cash flows. In many cases tax effect will make or break a project. therefore it is critical that taxes should be dealt with correctly.• Depreciation on assets should be considered in cash flow estimation. Because accountants do not subtract the purchase price of fixed assets when calculating net income ,they do subtract a charge each year for depreciation. depreciation shelters income from taxation. Depreciation must be added to NOPAT in following estimating a projects cash flow-

FCF =EBIT(1-t)+ depreciation- gross fixed asset expenditure- ∆ in net operating working capital

• The main effect of depreciation is-higher depreciation expense results in lower taxes in the early years that shows a higher net present value in cash flow analysis.

Page 93: Capital Budget FINAL Slide

Tax Effect in BangladeshTax Effect in BangladeshIn Bangladesh taxation system is not so critical as the MACRS of USA. There are a lot of exemption & incentives to encourage investment .Some of them are

• Industry engaged in agro-processing, ship building, diamond cutting. Physical Sea or river port, container terminals, container freight station, LNG terminal and transmission line, CNG terminal and transmission line, flyover, mono rail, underground rail, large water. Tourism Industry Eligible for Tax holiday.

• Income derived from any Small and Medium Enterprise (SME) engaged in production of any goods and having an annual turnover of not more than taka twenty four lakh is exempt from tax. 

• Accelerated depreciation: Accelerated depreciation on cost of machinery is admissible for new industrial undertaking in the first year of commercial production 50%, in the second year 30% and in the third year 20%. 

• Industry set up in EPZ is exempt from tax for a period of 10 years from the date of commencement of commercial production. 

• Avoidance of Double Taxation Agreement : There are agreements on avoidance of double taxation between Bangladesh and 28 countries.

Page 94: Capital Budget FINAL Slide

A Popular SurveyA Popular SurveyAuthor –JOHN GRAHAM,Associate Professor of Finance at Duke University’s Fuqua School of Business. & CAMPBELL HARVEY , J. Paul Sticht Professor of Finance at Duke University’s Fuqua School of Business.

This survey conducted in 1998 published in 2001 in the ‘journal of financial economics’ & it won the best best JFE paper in 2001. The 3- page long survey was conducted on all of the Fortune-500 company CFOs .

It represented a wide verity of companies , ranging from small(26% has sales less then $100 million) to very large(42% had sales at least $1 billion.) 40% of them was manufacturing firm,15% was financial ,11% retailers & 9% high tech firms. they also asked a number of questions to the CEOs because they are the ultimate decision.

Page 95: Capital Budget FINAL Slide

Findings of the Research by Findings of the Research by Graham & CampbellGraham & Campbell

NPV has been the dominant method taught in business schools, but past surveys have suggested that IRR was for long the primary corporate criterion for evaluating investment projects. For example, a 1977 survey of 103 large companies reported that fewer than 10% of the firms relied on NPV as their primary method, while over 50% said they relied mainly on IRR. Although the two measures are similar in several respects, the critical difference is that IRR is a ratio while NPV is a dollar measure of value added. The main problem with using the former is that, in some cases, managers intent on maximizing IRR may actually reduce value by rejecting positive- NPV projects.

Page 96: Capital Budget FINAL Slide

Findings of the Research by Findings of the Research by Graham & CampbellGraham & Campbell

Page 97: Capital Budget FINAL Slide

Findings of the Research by Findings of the Research by Graham & CampbellGraham & Campbell

As shown in Figure 1, most respondents cited net present value and internal rate of return as their most frequently used capital budgeting techniques; 74.9% of CFOs always or almost always used NPV and 75.7% always or almost always used IRR. However, large companies were significantly more likely to use NPV than were small firms. Highly leveraged firms were significantly more likely to use NPV and IRR than firms with low debt ratios. And as in the case of highly leveraged companies, companies that pay dividends ,were also significantly more likely to use NPV and IRR than firms that do not pay dividends, regardless of firm size.

Page 98: Capital Budget FINAL Slide

Findings of the Research by Findings of the Research by Graham & CampbellGraham & Campbell

Highly levered firms were also more likely to use sensitivity and simulation analysis, in part to assess (and limit to acceptable levels) the probability of financial distress. Utilities, too, perhaps because of regulatory requirements, were also more likely to use IRR and NPV and to perform sensitivity and simulation analyses. It also found that companies whose CEOs had MBAs were more likely to use NPV than firms whose CEOs did not. also found that, among small firms, older CEOs with long tenures and without MBAs were more likely to use the payback criterion. The simplicity of the method, combined in some cases with top management’s lack of familiarity with more sophisticated techniques. Public companies were significantly more likely to use NPV and IRR than were private corporations. Other than NPV and IRR (and the hurdle rate), the payback period was the most frequently used capital budgeting technique (56.7% always or almost always used it).

Page 99: Capital Budget FINAL Slide

Findings of the Research by Findings of the Research by Graham & CampbellGraham & Campbell

Finally the other capital budgeting techniques were used less frequently. For example, only about 20% of the companies said they used accounting rate of return; 14% always or almost always used value at risk or some other form of simulation, 12% used a profitability index, and 11% used adjusted present value (APV).

Somewhat surprisingly, more than one-fourth of the companies claimed to be using real options (RO) evaluation techniques In comparison, it is also surprising that only 11% of firms used APV since the method is fairly easy to use while at the same time flexible enough to handle a wide variety of project evaluation situations.

Page 100: Capital Budget FINAL Slide

SummarySummaryIn this chapter we have discussed about the following issues:Capital budgeting or project appraisal is the process of selecting investment projects whose returns or cash flows are expected to extend beyond one year.Project appraisal techniques aim to assess the financial feasibility of investment options and based on a number of assumptions.NPV, IRR and PI are the discounted cash flow criteria and PB, Discounted PB and ARR are the non discounted criteria for appraising the worth of an investment project.Payback method looks at how long it will take to pay back the cost of the initial investment.

Page 101: Capital Budget FINAL Slide

Summary Summary contd…contd…

Average rate of return looks at the percentage rate of return on the investment.Discounted cash flow (NPV) looks at the present values of any future revenues from the investment.For small sized projects payback method & ARR are preferred to be used. Capital rationing occurs when a company chooses not to fund all positive NPV projects.NPV method is the most superior investment criterion as it always consistent with the wealth maximization principle. But for larger projects IRR appears to be the most commonly used method as the end result of the computations is expressed in percentage.

Page 102: Capital Budget FINAL Slide

GroupGroup : Ever ShinersEver Shiners

Name of Members ID No.Md Delowar Hossain 13055Touhidul Islam 13062Ashraful Islam 13089Kazi Tasnim Afroz 13132Fahmida Sharmin13149