Capital Beltway CorridorRail Feasibility Study
Chip Badger, Director Public Transportation Division Department of Rail & Public Transportation
April 1, 2004
What This Study Did
• Responded to General Assemblymandate and VDOT’s Beltway MIS
• Identified most feasible transit technology and alignment
• Determined potential ridership• Evaluated potential impacts• Coordinated with previous and on-going
studies in the region and Maryland
The Process
STEP
1
STEP
2
STEP
4
STEP
5
STEP
6
STEP
3
Project Initiation
Short Listing
RefinedAlternatives
Second Evaluation
Preferred Alternative
InitialAlternatives
Three CorridorsBlue Red Green
Placed Technologies in Alignments
10 Technology-Alignment Alternatives
Heavy Rail
Light Rail
Monorail
Bus Rapid Transit
Heavy Rail
Light Rail
Monorail
Heavy Rail
Light Rail
Monorail
BLUE RED GREEN
Five Preferred Alternatives
Heavy Rail
Light RailMonorail
Bus Rapid Transit
Heavy Rail
Light Rail
Monorail
Heavy Rail
Light Rail
Monorail
Blue Red Green
Tier 2 Evaluation
Ridership
Light RailRed
Heavy RailRed
MonorailRed
Light RailBlue
Heavy RailBlue
73,000 62,000 87,000 74,000 69,000
CapitalCosts
($ millions)
$1,208 $2,253 $1,465 $1,499 $2,096
Potentially Affected 350-375 25-50 25-50 125-150 50-75
6,600 6,500 4,000 10,700 11,700Affected Environment
Principal Findings on Ridership
System would:• Attract some new riders to transit• Feed radial routes• Improve service for through riders• Increase load on Orange Line
Principal Findings on Ridership
• Fewer than 15% of riders are purely local• A minority of trips begin or end in
study area• DC is the major trip generator
Possible Transit Alternatives
• Monorail - Red with Heavy Rail extension to Maryland
• Heavy Rail - Red with Braddock Road Station
• LRT Red/Blue combination
Light Rail -Red/Blue
Combination
Findings
• Rapid transit is feasible• Potential for ridership warrants further
study• No fatal flaw environmental impacts• No fatal flaw community impacts • Several alternatives offer potential
Recommendations
• Advance the Capital Beltway Corridor Rail Feasibility Study to the alternatives analysis phase at an appropriate time.
• Before advancing this project perform similar feasibility studies for other transit projects in the Washington region.
Recommendations
• The inter-relationship between land use and transit should be further examined.
• Coordinate highway and transit improvements in the Beltway right-of-way
Capital Beltway CorridorRail Feasibility Study
Chip Badger, Director Public Transportation Division Department of Rail & Public Transportation
April 1, 2004